1.5 Purpose of this Executive Summary
2.3 Scenarios "With" and "Without"
the Project
2.4 Consideration of Alternative Options
2.6 Tentative Implementation Programme
3 Summary of Environmental Impact Assessment
3.4 Waste Management Implications
3.7 Ecology (Terrestrial and Marine)
4 Environmental
Monitoring and Audit
Figures
Figure 1.1 Location
of Project and Interfacing Projects
1.1.1.1 The objective of Route 11 (Section between Yuen Long and North Lantau) (hereinafter named as the Project) is to enhance the connectivity between the Northwest New Territories (NWNT) and North Lantau to meet the future traffic demands generated by the future developments in both regions and also the increasing cross-boundary activities. Route 11 will be a strategic highway to support the proposed developments in the NWNT. It will also provide the third vehicular access to Lantau in addition to the existing Lantau Link (LL) and the Tuen Mun-Chek Lap Kok Link (TM-CLKL).
1.1.1.2 In September 2021, Highways Department (HyD) commissioned Arup to carry out Agreement No. CE 13/2021 (HY) Route 11 (Section between Yuen Long and North Lantau) - Investigation to examine and review the Preferred Alignment for the Project, formulate a Recommended Alignment developed under the feasibility study for the Project, and work out the preliminary design details of the Recommended Alignment of Route 11 and the associated works.
1.2.1.1 The Project will have a total length of approximately 12km, covering areas in Lam Tei, So Kwun Wat, Tai Lam, Tsing Lung Tau and North Lantau. The alignment of the Project is shown in Figure 1.1.
1.2.1.2
The Project has a similar
mainline layout of the Public Works Programme Item No 519TH “Route 10 – North
Lantau to Yuen Long Highway (YLH)” (Ex-Route 10). The feasibility study as well as the
investigation and preliminary design of Ex-Route 10 were completed in 1998 and
2002 respectively. Detailed design for
Ex-Route 10 was commenced in 2000 but had not been completed in view of the
proposed implementation of the Tuen Mun – Chek Lap Kok Link (TM-CLKL) and Tuen
Mun Western Bypass (now is replaced by the proposed Tuen Mun Bypass (TMB)),
with Route 10 as a future option after review of the traffic and transport
infrastructure in the Northwest New Territories (NWNT) and Lantau in 2002. As the above studies were carried out some 20
years ago, much information had become outdated, and the technical feasibility
of the Project needs to be assessed again.
1.2.1.3
HyD commissioned a Feasibility
Study (FS) of the Project in May 2018 in order to take account of the latest
planning and development parameters. The
FS has established the technical feasibility of the Project, examined and
evaluated possible alignment options and determined the Preferred Alignment for
the Project.
1.2.1.4 Subsequently, HyD commissioned an Investigation consultancy of the Project in September 2021, to examine and review the Preferred Alignment for the Project, formulate a Recommended Alignment for the Project, and work out the preliminary design details of the Recommended Alignment of the Project and the associated works. The scope of the consultancy also includes the preparation of the Environmental Impact Assessment (EIA) for the Project under the Environmental Impact Assessment Ordinance (EIAO).
1.3.1.1 Figure 1.1 shows the latest alignment and locations of the following key elements.
a) construction
of Lam Tei Quarry Interchange, which comprises slip roads and viaducts,
connecting the proposed Lam Tei Tunnel to Kong Sham Western Highway, Yuen Long
Highway and the proposed TMB (under separate project);
b) construction
of Lam Tei Tunnel, which is an approximately 4.2 km
long dual 3-lane carriageway tunnel, connecting the proposed Lam Tei Quarry
Interchange and So Kwun Wat Interchange;
c) construction
of So Kwun Wat Interchange, which comprises slip roads and viaducts, connecting
the proposed Lam Tei Tunnel, So Kwun Wat Link Road and Tai Lam Chung Tunnel
(North Section);
d) construction
of So Kwun Wat Link Road, which comprises an approximately 2.0 km long dual
2-lane carriageway tunnel and associated slip roads and viaducts, connecting to
Tuen Mun Road (TMR), So Kwun Wat Road, and the proposed So Kwun Wat
Interchange;
e) construction
of Tai Lam Chung Tunnel (North Section) which is an approximately 0.4km long
dual 4-lane carriageway tunnel, a viaduct crossing Tai Lam Chung River, and Tai
Lam Chung Tunnel (South Section) which is another tunnel to the east of Tai Lam
Chung River and an approximately 1.7km long dual 4-lane carriageway tunnel,
connecting the proposed So Kwun Wat Interchange and Tsing Lung Tau Interchange;
f) construction
of Tsing Lung Tau Interchange, which comprises slip roads, viaducts and tunnel,
connecting the proposed Tai Lam Chung Tunnel (South Section) and Tsing Lung
Bridge to TMR;
g) construction
of Tsing Lung Bridge, which is an approximately 1.9 km long dual 4-lane
carriageway suspension bridge, crossing over the Ha Pang Fairway and connecting
the proposed Tsing Lung Tau Interchange and North Lantau Interchange, with
reclamation of approximately 2.2 ha for construction of bridge tower at Tsing Lung Tau;
h) construction
of North Lantau Interchange, which comprises slip roads, viaducts and tunnels,
connecting Tsing Lung Bridge to North Lantau Highway, LL, the proposed Road P1 (under
separate project), the proposed Tsing Yi-Lantau Link (under separate project)
and the proposed Hong Kong Island West-Northeast Lantau (HKIW-NEL) Link (under
separate project);
i) re-alignment
of an approximately 1.4 km long section of TMR at Tsing Lung Tau;
j) modification
/ realigning of the existing interchanges / roundabouts / roads, where
appropriate (e.g. widening of an approximately 0.4 km
long Tai Lam Chung Road);
k) reprovision
/ modification of existing bridges, underpasses, footbridges, access roads,
crossings affected;
l) construction
of associated administration buildings, ventilation buildings;
m) construction
of temporary explosive magazines in Lam Tei Quarry, Siu Lam and Pillar Point;
and
n) associated
geotechnical works, ground investigation (GI) works, drainage works, natural
terrain hazard mitigation works, sewerage works, traffic aids, directional
signs, street lightings, Traffic Control and Surveillance System, Electrical
and Mechanical (E&M) works, environmental mitigation measures, landscaping
works, Vessel Impact Protection System, dehumidification systems for cables and decks, and services systems
for inspection, maintenance, structural health monitoring and management of the
suspension bridge.
1.3.1.2 The EIA report has included locations of the temporary work sites, works areas, construction haul roads and barging facilities of the Project for supporting the construction of the Project based on the latest information at the time of writing.
1.4.1.1 After the submission of Project Profile (No. PP-637/2022), pursuant to Section 5(7)(a) of the EIA Ordinance, the Director of Environmental Protection issued an EIA Study Brief (No.: ESB-352/2022 dated 25 February 2022) for the EIA study. This EIA study focuses on assessing the potential impacts associated with the construction and operation of the Project in accordance with the requirements of EIA Study Brief and the Technical Memorandum on Environmental Impact Assessment Process.
1.5 Purpose of this Executive Summary
1.5.1.1 This Executive Summary (ES) highlights the key information and findings of the EIA Study of Route 11 (Section between Yuen Long and North Lantau).
2.1.1.1
The objective of the Project
is to enhance the connectivity between NWNT and North Lantau to meet the future
traffic demands generated by the future developments in both regions and also
the increasing cross boundary activities.
The Project will be a strategic highway to support the proposed
developments in the NWNT.
2.2.1.1
According to the traffic
impact assessment, in the absence of the Project, TMR (Siu Lam Section and Sham
Tseng Section), Tai Lam Tunnel, Ting Kau Bridge, and LL will be over capacity
during morning peak hours in 2036.
2.2.1.2 The Project will offer an alternative route connecting the NWNT and the urban areas. It is anticipated that traffic conditions of TMR (Siu Lam Section and Sham Tseng Section), Tai Lam Tunnel, Ting Kau Bridge and LL during morning peak hours in 2036 will be significantly improved after commissioning of the Project and the associated major roads, resulting in reduced travel time between NWNT and urban areas.
2.2.1.3 In addition, the Project will provide an alternative commuting route with the proposed TYLL. This will enhance the resilience of the NWNT traffic network to traffic incidents and emergencies on major roads. By having multiple access points and connections to major roads in NWNT, the Project and TYLL can serve as a dependable route for diverting traffic towards urban areas during such situations. Furthermore, the Project and TYLL will serve as a strategic route linking NWNT and the urban areas to Lantau, enhancing the resilience to the road network connecting to the airport.
2.3 Scenarios "With" and "Without" the Project
2.3.1 Consideration of “Without” Project Scenario
2.3.1.1
Without the implementation of
the Project, much of the traffic from various new and existing developments in
NWNT commuting to Tsuen Wan, West Kowloon and Hong Kong Island, etc. would need
to use the existing TMR, or Tai Lam Tunnel with Ting Kau Bridge. According to the traffic impact assessment,
TMR, Tai Lam Tunnel, and Ting Kau Bridge, would not have sufficient capacity to
handle the future traffic demand. Hence,
it is anticipated that these major roads would experience congestion during
peak hours, which would lead to higher vehicular traffic emissions as the
traffic speed decreases during traffic congestion. Moreover, as it was anticipated that the
traffic volume during non-peak hours would increase, potential adverse impacts
on air quality and noise to the neighbouring sensitive receivers would also be
more significant.
2.3.2 Consideration of “With” Project Scenario
2.3.2.1 With the implementation of the Project, the traffic from various new and existing developments in NWNT commuting to Tsuen Wan, West Kowloon and Hong Kong Island, etc. could use the Route 11 as an alternative route to reach Tsing Lung Tau and North Lantau swiftly instead of relying on TMR or Tai Lam Tunnel with Ting Kau Bridge. From there, the traffic can take suitable routes to reach Tsuen Wan, West Kowloon and Hong Kong Island as needed. As a result, traffic conditions on TMR, Tai Lam Tunnel, Ting Kau Bridge and LL would be relieved, and the associated environmental impacts along this main traffic corridor would also be improved. In addition, the Project has proactively avoided any aboveground works within Tai Lam Country Park (TLCP) to minimize environmental impacts.
2.3.2.2
By adopting underground tunnel
form for all sections within TLCP, no habitat within TLCP will be lost or
fragmented and no direct impact will be exerted on flora and fauna within TLCP,
including those of conservation importance. Indirect impacts due to the
construction activities are also mitigated by proper planning of construction
works and other mitigation measures.
2.4 Consideration of Alternative Options
2.4.1.1 Due considerations have been given in formulating options to address the environmental challenges in the Project. The hierarchy of “Avoidance, Minimization and Mitigation” has been fully adopted in the process to protect the environment as much as practicable.
2.4.2 Avoidance of Above-ground Works within TLCP and other Recognized Sites of Conservation Importance
2.4.2.1 In particular, while the alignment would be unavoidably located in TLCP for the direct connection between Lam Tei, So Kwun Wat and Tsing Lung Tau, tunnel option (i.e. Lam Tei Tunnel, So Kwun Wat Link Road and Tai Lam Chung Tunnel (South Section)) has been adopted within TLCP to avoid any aboveground works and thus no direct impact to TLCP.
2.4.2.2 The Project has also sought to avoid direct impact on recognized sites of conservation importance (i.e. “Conservation Area”, Siu Lang Shui Site of Special Scientific Interest), important habitats (i.e. Siu Lang Shui Butterfly Habitat, Ma Wan Egretry, Day Roost and Night Roost, and Fung Shui Woodlands) and, roosting ground (i.e. bat roosts inside Tai Lam Chung (TLC) Catchwater Tunnel Nos. 5, 6 and 8) as far as possible.
2.4.3 Formulation of Alignment Options
2.4.3.1 During formulation of the alignment options, due consideration has been made to site constraints, such as site of archaeological interest, permitted burial grounds, and planned and existing residential developments. Therefore, most portions of main alignment are in form of viaducts/ elevated roads, which aim to reduce land impacts and provide more separation from the sensitive receivers.
2.4.3.2 Full tunnel option between Lam Tei and North Lantau was explored, but it is not considered viable due to:
· Need for connectivity of the Project at particular locations such as Tsing Lung Tau and So Kwun Wat;
· Significant variation of terrain, including hilly areas and across marine sea; and
· Significant reclamation required to connect the tunnel to the existing roads at North Lantau at a favourable gradient to LL and North Lantau Highway.
2.4.3.3 The full tunnel running from +40mPD at Lam Tei to below Ha Pang Fairway (deepest seabed level at -35mPD) and then climbing up to +60mPD at North Lantau require drastic change in road levels along the alignment. It also requires either steep or long tunnel deep below ground to connect to at-grade roads at the proposed interchanges. It is not favourable from highway design and traffic operation points of view.
2.4.3.4 On the above basis, other alignment options comprising sections of tunnels, viaducts, at-grade roads and suspension bridge have been considered for the Project. In consideration of the alignment options, the whole Project is sub-divided for 3 sections:
· Northern Section (Tuen Mun to So Kwun Wat);
· Central Section (So Kwun Wat to Tai Lam Chung); and
· Southern Section (Tai Lam Chung to North Lantau).
2.4.3.5 The details of the alignment options (including benefits and dis-benefits) are given in Section 2 of the EIA report. Key elements are highlighted in below paragraphs.
2.4.4 Northern Section (Tuen Mun to So Kwun Wat)
2.4.4.1 Three alignment options for the northern section (namely Option FS(LT), Option LT1 and Option LT2) have been considered. Option LT2 is selected as the recommended option. Option LT2 has more compacted layout developed for Lam Tei Quarry Interchange to achieve a reduced footprint, with the northern tunnel portal of Lam Tei Tunnel located outside TLCP. It provides connection with the proposed TMB.
2.4.4.2 Option FS(LT) cannot accommodate the interfacing projects that were not proposed when developing the alignment in the feasibility study stage, and has larger encroachment on Fuk Hang Tsuen and Permitted Burial Ground No. BURG22. Option LT1 will be in conflict with the proposed underground quarry, and limit the future land use of Lam Tei Quarry.
2.4.5 Central Section (So Kwun Wat to Tai Lam Chung)
2.4.5.1 Five alignment options for the central section (namely Option FS(SL), Option SL1, Option SL2, Option SL3 and Option SL4) have been considered. Option SL1 is selected as the recommended option. Option SL1 will have comparatively longer tunnel length. However, most of the constraints and impacts can be avoided under this option, including TLCP, MacLehose Trail, Fung Shui Woodlands, So Kwun Wat Tsuen, So Kwun Wat San Tsuen, other residential premises at Tuen Mun East, So Kwun Wat (east part) SAI and the Permitted Burial Ground No. BURG19.
2.4.5.3 Other options (i.e. Option SL2, Option SL3 and Option SL4) attempted to avoid the constraints encountered by Option FS(SL). However, they will be located close to various residential premises, leading to more significant environmental impacts.
2.4.6 Southern Section (Tai Lam Chung to North Lantau)
2.4.6.1 Eight alignment options for the southern section (namely Option FS, Option A1, Option A2, Option B1, Option B2, Option C1, Option C2 and Option D) have been considered. Option A1 is selected as the recommended option. It will provide direct traffic routing between Tai Lam Chung and North Lantau. Option A1 will avoid reclamation for tower of Tsing Lung Bridge at North Lantau side. It will reduce slope cutting at Ng Kwu Leng, and is compatible with Kap Shui Mun Bridge lower deck entry, MTR substation and other concurrent projects (e.g. TYLL and HKIW-NEL Link). It will also avoid aboveground works within TLCP. As Option A1 at Tai Lam and Tsing Lung Tau is mainly in form of tunnel section, it will minimize potential environmental impacts to residential premises at Tai Lam Chung area.
2.4.6.2 Option FS requires reclamation at both Tsing Lung Tau and North Lantau sides and also extensive slope cutting at Ng Kwu Leng. Its southern portal and its associated earthwork of Tai Lam Chung Tunnel will likely be encroached on TLCP It is not compatible with Kap Shui Mun Bridge lower deck entry, MTR substation and other concurrent projects (e.g. TYLL and HKIW-NEL Link).
2.4.6.3 Option A2, Option C1 and Option C2 are with larger separation from with the TLC Catchwater Tunnel No. 6 to minimize the impact to the catchwater tunnel and the bat habitats. However, they will be either too steep for trunk road with engineering design constraint, or encroaching upon Tai Lam Chung Tsuen or CSD’s Tai Lam Correctional Institution.
2.4.6.4 Option B1 and B2 will require substantial slope cutting along northern hillside of TMR, leading to significant natural terrain hazard risks. Lane closure will be required during construction leading to major impact to busy traffic along TMR. It will likely be encroached on TLCP at the eastern end of connection with Tuen Mun Road. As the route between Tai Lam Chung and Tsing Lung Tau will be longer and less direct, it will lead to longer travel times and potential environmental impacts to residential premises at Tai Lam Chung area.
2.4.6.5 The highway design with subsea tunnel of Option D in terms of road gradients and connection is considered unfavourable, and longer travel times will be required for the longer and steeper ramps. Substantial reclamations will be required to connect the tunnel to the roads at North Lantau at a favourable gradient. Considerable amount of dredged materials will also be generated from tunnel construction. If immersed tube tunnel construction method is adopted, marine navigation will be seriously affected, and water quality impact is also anticipated.
2.4.6.6 The key design considerations to tackle all the environmental challenges are summarised in Table 2.1.
Table
2.1 Key
design considerations and the associated environmental benefits
Design Approach |
Key Design Considerations |
Associated Environmental Benefits |
Avoidance of aboveground works within TLCP and
water gathering grounds |
·
Adopt suitable tunnel alignments for the sections
across TLCP, such that no aboveground works within TLCP are required ·
Adopt suitable engineering design during
drill-and-blast tunnelling to avoid adverse impacts on the water gathering
ground |
·
Avoided direct habitat loss and disturbance
within TLCP |
Avoidance of direct impact on butterfly
overwintering ground at Siu Lang Shui |
·
Maintain a sufficient separation distance from
the butterfly overwintering ground at Siu Lang Shui from the proposed
explosive magazine site at Pillar Point ·
Minimize large scale of engineering works (e.g.
site formation works) by selecting the proposed explosive magazine site at
Pillar Point, which was substantially formed by previous projects |
·
Avoided direct impacts on the butterfly
overwintering ground ·
Minimised habitat loss through proper site
selection |
Avoidance of direct impacts to eastern patch of Ching Uk Tsuen Fung Shui Woodland (Fung
Shui Woodland at So Kwun Wat) |
·
Elevate the vertical alignment near the eastern
patch of Ching Uk Tsuen Fung Shui Woodland (CUTFSW) at So Kwun Wat to
increase the headroom clearance as much as technically feasible ·
Adjust the horizontal alignment to avoid
overlapping with the Fung Shui Woodland as much as practicable ·
Avoid columns and associated works areas within
the Fung Shui Woodland ·
Separate the northbound and southbound viaduct
structures to provide a 7m separation between the viaduct structures, which
would allow a longer duration of direct sunlight to the Fung Shui Woodland
underneath |
·
Avoided direct impacts on the Fung Shui Woodland ·
Minimised disturbance to the Fung Shui Woodland |
Minimization of
disturbance to bat roosting
habitats |
·
Increase separation distances of the tunnel
alignment from WSD catchwater tunnels with bat habitats ·
Adjust tunnel construction methodology (i.e.
review explosive charge weight of drill-and-blast method and explore
alternative tunnelling methods) in close vicinity of WSD tunnels with bat
habitats |
·
Avoided direct impacts on bat roosts in WSD
tunnels ·
Minimised disturbance to bat roosts in WSD
tunnels |
Avoidance of direct impacts on Sites of
Archaeological Interest (SAI), Graded Buildings and Potential Marine
Archaeology |
·
Avoid encroachment on SAI and graded buildings ·
Adopt a viaduct alignment for the section running
across So Kwun Wat Perowne Barrick SAI and avoid temporary works areas within
the SAI ·
Avoid all the anomalies by allowing sufficient
setback distance (around 50m) for marine ground investigation |
·
Avoided direct impact on SAI and graded buildings ·
Avoided direct impact on anomalies with unknown
marine archaeological potential |
Avoidance of reclamation at To Kau Wan in North
Lantau |
·
Remove the original scheme of reclamation at To
Kau Wan in North Lantau through optimization of Project alignment and
engineering design |
·
Avoided seabed loss at North Lantau, and the
associated water quality impacts during the construction stage |
Minimization of reclamation and dredging extents
for the reclamation in Tsing Lung Tau |
·
Optimise the extents of reclamation and dredging
for the reclamation in Tsing Lung Tau |
·
Minimised construction phase water quality
impacts at Tsing Lung Tau ·
Minimised the amount of sediment to be dredged
and disposed ·
Minimised the numbers of corals to be directly
affected |
Confinement of filling works within seawall for
the reclamation in Tsing Lung Tau |
·
Commence filling works upon the full completion
of the perimeter seawall for the reclamation in Tsing Lung Tau |
·
Minimised the possibility of fill materials and
fine suspended solids from being discharged into the open sea in an
unacceptable manner |
Minimization of slope cutting |
·
Minimise slope cutting through refinement of
alignment of the Project |
·
Minimised disruption and impacts to the landscape
resources and characters ·
Minimised the number of trees to be impacted ·
Minimised the loss of habitats, especially those
of relatively higher ecological value, such as mixed woodland ·
Minimised the amount of excavation spoil and
construction waste generated |
2.4.7 Recommended Alignment for the Project
2.4.7.1
The
recommended alignment option (as presented in Figure 1.1) is summarised in Table 2.2.
Table
2.2 Summary of
Recommended Alignment Option for the Project
Sections |
Recommended
Alignment Option |
Northern
Section (Tuen Mun to So Kwun Wat) |
LT2 |
Central Section (So Kwun Wat to Tai Lam Chung) |
SL1 |
Southern Section (Tai Lam Chung to North
Lantau) |
A1 |
2.5.1 Construction Methodology for Tunnels
2.5.1.1 The primary method of construction for the Route 11 tunnels and cuttings is expected to be by drill and blast method which utilises controlled blasting to excavate hard rock. Compared with mechanical breaking of the rock by hydraulic excavator, the drill and blast method can significantly shorten the period for the tunnel excavation. The shortened construction period is not only financially beneficial for the construction of Route 11 tunnels but also minimize disturbance to the interfacing WSD catchwater tunnels through reducing the duration of exposure to vibration at the WSD tunnel. Alternative methods using tunnel boring machine (TBM) and non-explosive chemical expansion agent have also been considered for construction of the tunnels. However, TBMs of the size required for dual 3-lane or dual 4-lane tunnels for hard rock ground condition are not currently available on the market and non-explosive chemical expansion agent is not effective in hard rock excavation.
2.5.2 Construction Methodology for Reclamation
2.5.2.1
It
is intended to avoid dredging as far as possible for reclamation. However,
based on the latest GI result, marine deposit found locally at the proposed
reclamation area is roughly 3m to 4m deep. Owing to its shallowness of marine
deposit, un-dredged method like deep cement mixing technique and construction
of stone column are not effective in strengthening the seabed for seawall
construction.
2.5.2.2
A
mud pit is proposed at the centre of the proposed reclamation area to receive
the dredged marine deposit. The fully dredged trench will then be formed and
filled with sand and/or rockfill for construction of seawall. Armour stones
will be placed on the sloping seawall surface as protection to the seawall.
2.5.3 Construction Methodology for Tsing Lung Bridge
2.5.3.1 Construction of Tsing Lung Bridge involve construction of foundations and anchorages. All foundation and substructures of Tsing Lung Bridge and approach viaducts are located on land or reclaimed area. No marine works is required in addition to the reclamation works. Foundations and substructures will be cast-in-situ with erection of falsework and formwork and rebar fixing. Bridge towers can be made of concrete or steel. Concrete towers will be cast-in-situ with either slip forms or jump forms while steel towers will be segmental pre-fabricated off-site and erected on-site.
2.5.3.2 Upon completion of towers and anchorages, cables will be threaded and installed, followed by installation of suspenders and bridge deck segment erection. The bridge deck will be prefabricated off-site and transported to the site by barge for lifting and installation. Appropriate temporary arrangements for marine navigation will be implemented during installation of the deck segments.
2.5.4 Construction Methodology for Viaducts
2.5.4.1 Generally, precast concrete segmental viaduct construction method would be adopted as far as possible to minimise in-situ concreting works on-site. Under this method, the decks will be formed from precast concrete segments which will be manufactured at the casting yard off-site and stitched together at their final positions on-site. This method will minimise the quantities of construction and demolition (C&D) materials, and also minimise the extent and duration of construction activities required on-site.
2.5.4.2 On the other hand, consideration is also given to the site constraints in terms of accessibility for delivery of the precast deck segments. Where space is limited for access, cast-in-situ using formwork and falsework would be adopted as an alternative option.
2.5.5 Construction Methodology for Rock Cuttings
2.5.5.1 Open blasting is intended for large rock cuttings at Lam Tei Quarry, Tsing Lung Tau and North Lantau in view of cost and time benefits to the Project. The selected locations for open blasting are predominately in low population density areas. Additional blasting screens, blast cages and blast mats will be provided alongside a well-designed surface blast design to control the effects of flyrock.
2.5.6 Construction Methodology for Buildings
2.5.6.1 The administration buildings and ventilation buildings will be typically designed as reinforced concrete structure and constructed by cast-in-situ method using formwork and falsework. Subject to the ground conditions, bored piles or raft footing foundation is envisaged. No percussive piling is envisaged. As the ventilation requirement and schedule of areas of each building is different, there is no economy of scale adopting modular construction.
2.5.7 Construction Methodology for Other Project Elements
2.5.7.1 The Project also consists of construction of other temporary structures including temporary explosive magazines. The details of the construction methodologies are given in Section 2 of the EIA report.
2.6 Tentative Implementation Programme
2.6.1.1
The construction phase of
the Project, including reclamation works, site formation for Tsing Lung Bridge
anchorages, tunnelling, roads and viaducts construction, road realignment of
TMR, ventilation buildings and administration buildings construction, and Tsing
Lung Bridge construction, will be tentatively commenced in 2026 Q1 and
completed in 2033 Q4. The tentative phasing of
major construction works is outlined in Table
2.3.
2.6.1.2 Sequence of works will be further reviewed during detailed design stage and construction stage. Liaison with nearby concurrent projects (e.g. TMB, TYLL, Road P1, Underground Quarrying at Lam Tei, etc.) will be conducted to minimize potential cumulative environmental impacts.
Table 2.3 Summary of
the Key Construction Works for the Project
Description |
Tentative Construction Programme |
Reclamation at Tsing Lung Tau |
Q1 2026 to Q1 2028 |
Site
formation for anchorages of Tsing Lung Bridge |
Q1 2026 to Q1 2028 |
Construction
of explosive magazines |
Q1 2026 to Q1 2028 |
Construction
of tunnels, viaducts and interchanges |
Q1 2028 to Q4 2033 |
Road
realignment of Tuen Mun Road |
Q1 2028 to Q4 2033 |
Construction
of Tsing Lung Bridge |
Q1 2028 to Q4 2033 |
Construction
of ventilation buildings and
administration buildings |
Q1 2031
to Q4 2033 |
2.7.1.1 Various cumulative impacts for different key concurrent projects have been identified. Detailed justification on consideration of various cumulative environmental impacts from individual concurrent project has been included and addressed in the corresponding assessment sections of this EIA report.
3
Summary of Environmental Impact Assessment
3.1.1.1 Potential construction dust impact would be generated from site clearance, soil excavation, backfilling, reclamation, construction of tunnels, blasting, barging facilities, proposed concrete batching facilities and construction vessels, etc. during construction phase of the Project. A comprehensive review has been conducted on the monitoring data for similar infrastructure projects and the construction dust impact assessment indicates that given the implementation of good site practices and mitigation measures, such as regular watering, implementation of vehicle washing facilities at the construction site exits, tunnel blasting in a fully enclosed environment, and open blasting with blast screens, cages or mats, etc., adverse air quality impact during construction phase is not anticipated. Nevertheless, continuous dust monitoring is also proposed at representative locations (i.e. the closest air sensitive receivers (ASRs) in all directions) to ensure that there is no adverse dust impact on the nearby ASRs.
3.1.2.1 Cumulative air quality impact during operational phase arising from the operation of the Project, concurrent projects and other emission sources such as vehicular emission from open roads, emission from public transport interchanges and heavy goods vehicle / coach parkings, industrial emissions and marine emission within 500m study area has been assessed for the operation phase of the Project at the worst Year 2033 for Respirable Suspended Particulates (RSP) and Fine Suspended Particulates (FSP), and Year 2048 for Nitrogen Oxides (NOx) with respect to vehicular emissions, which has the highest vehicular emission burden within 15 years after commencement of the Project for RSP/FSP and NOx respectively. The results concluded that the predicted cumulative Nitrogen Dioxide (NO2), RSP and FSP concentration at all Air Sensitive Receivers (ASRs) would comply with Air Quality Objectives (AQOs). The planned air sensitive uses within the operation area of the TMB shall be properly designed such that any openings, openable windows, and/or fresh air intakes will be located and avoided from the predicted exceedance zone at 1.5mAG. Further review of the layout and design of operation area will be conducted in detailed design stage to ensure compliance of the AQOs. No adverse air quality impact is anticipated arising from the operation of the Project.
3.1.2.2 Moreover, during the subsequent design stage and the operational stage, the ventilation engineer should conduct reviews on the ventilation scheme covering different periods of a day, taking into account the contemporary circumstance such as latest traffic forecast, traffic composition, update on the ambient air quality, etc., and then review and update the air quality assessment as necessary to demonstrate full compliance of the AQOs. These reviews would allow the designer and operator to optimize the operation of the ventilation system without compromising the compliance of AQOs.
3.2.1 Construction Noise Impact
3.2.1.1 Potential construction noise impact would be generated from the use of PME during construction phase of the Project. A review has been conducted on the construction methodology, and it is considered that given the implementation of good site practices and mitigation measures, such as quieter plant/methods (e.g. non-percussive construction methods, silent press-in piler, etc.), silencer, movable noise barrier, noise enclosure / barrier, etc., adverse construction noise impact during construction phase is not anticipated.
3.2.1.2 A Construction Noise Management Plan (CNMP) shall be submitted which will contain a quantitative construction noise impact assessment, the adopted quieter construction method and equipment, noise mitigation measures and the construction noise impact monitoring and audit programme once available and in any case before the tender and commencement of the project construction, and if there is any change to the construction noise mitigation measures recommended in the CNMP, an updated CNMP shall be submitted one month before the implementation of such change.
3.2.2 Road Traffic Noise Impact
3.2.2.1 Quantitative road traffic noise impact assessment has been conducted for planned, existing and committed noise sensitive uses. Without the implementation of mitigation measures, exceedance of noise criteria as stipulated in EIAO-TM is anticipated.
3.2.2.2 The predicted road traffic noise impact would comply with respective noise criteria at all noise sensitive receivers with the proposed traffic noise mitigation measures in place. Noise mitigation measures at Lam Tei, So Kwun Wat and Tsing Lung Tau, including 1) low noise road surfacing on applicable road sections; and 2) noise barriers as well as semi-enclosure along suitable road sections, as well as 3) at-receiving end measures as agreed with relevant project proponents, will be implemented.
3.2.3 Fixed Noise Sources Impact
3.2.3.1 Potential fixed noise source impact would be generated from the ventilation shaft of ventilation buildings and mechanical ventilation system of the administration buildings. A review has been conducted on the design of these fixed noise sources and it is considered that given the implementation of good design and mitigation measures, such as quieter plant, acoustic louvres, silencer, barriers, enclosures, etc., adverse fixed noise source impact during operational phase is not anticipated.
3.2.3.2 A Fixed Noise Source Management Plan (FNMP) shall be submitted which will contain the quantitative fixed noise sources impact assessment, noise mitigation measures, and fixed noise sources impact monitoring and audit programme, with reference to the updated and identified inventories once available and in any case before the commencement of construction of the Project. If there is any change to the specifications of the planned fixed noise sources, layout design, operation modes, mitigation measures, or any other factors that would have implications on the fixed noise sources impact as concluded in the FNMP, an updated FNMP shall be submitted to the EPD no later than one month before the implementation of any such change.
3.3.1.1 The key water quality impact associated with the Project which could impact the nearby waterbodies and water sensitive receivers are mainly associated with the land-based construction phase of the Project, which includes general construction activities, construction site run-off, tunnelling and underground works, buildings construction, sewage due to construction workforce, construction works in close proximity of inland water, groundwater from contaminated areas and contaminated site run-off, diversion of watercourse and the accidental spillage of chemicals. With the mitigation measures such as Best Management Practices (BMPs) and water control strategies during tunnelling and underground works, adverse impacts are not anticipated during construction phase.
3.3.1.2 A small reclamation at Tsing Lung Tau (i.e. a land area of about 2.2ha) is required for the Project. The marine-based construction works that would induce potential water quality impact include reclamation works, construction of mud pit and other marine works. A quantitative water quality assessment has been conducted. Results indicate that adverse water quality impact is not anticipated during the reclamation works. Nevertheless, deployment of single layer of silt curtain is proposed as enhancement measures. Good site practices are also proposed to minimize the potential water quality impact due to marine works. Hence, adverse impacts are not anticipated during the construction phase of the Project.
3.3.2.1 During the operational phase of the Project, the major sources of potential adverse water quality impact include road and tunnel runoff discharged from paved roads and developments proposed under the Project, the sewage generated by the proposed administration buildings, wastewater generated from washing and maintenance operations, and the change in hydrodynamic regime due to the reclamation. However, with proper implementation of recommended mitigation measures and minimization of reclamation extent, adverse water quality impacts are not anticipated during the operational phase of the Project.
3.4 Waste Management Implications
3.4.1.1 Potential waste management implications from the generation of waste during the construction phase have been evaluated. The main types of waste would be generated include C&D materials, land-based marine sediment, chemical waste, general refuse and floating refuse. It has been estimated that 9,298,300 m3 of inert C&D materials, 64,060 m3 of non-inert C&D materials, 31,000 m3 of marine sediment, a few hundred litres per month of chemical waste, 4,705 tons of general refuse, as well as 1.5 m3 per year of floating refuse would be generated.
3.4.1.2 In order to reduce the number of surplus materials to be disposed of, strategic mitigation measures such as the opportunity for on-site sorting, reusing C&D materials, etc. are devised. With the proper implementation of the recommended migration measures such as good site practices, waste reduction through good management and control, proper storage, collection and transportation of waste, all dump trucks and vessel engaged on site for delivery of inert C&D materials from the site to Public Fill Reception Facilities (PFRFs) equipped with Global Positioning System (GPS) or equivalent system, preparation of a Construction and Demolition Management Plan (C&DMMP), etc., adverse environmental impacts from waste management during construction phase are not anticipated.
3.4.2.1 Potential waste management implications from the generation of waste during the operational phase have been evaluated. The main types of waste that would be generated include general refuse from the employees within mainly the administration buildings and partly from the tunnel ventilation buildings, chemical waste from administration buildings, ventilation buildings as well as maintenance of the tunnel, and floating refuse trapped/accumulated by the proposed artificial seawall for the reclamation at Tsing Lung Tau.
3.4.2.2
With the implementation of
recommended mitigation measures for the handling, transportation and disposal
of the identified waste such as employment of a reputable waste collector to
remove municipal solid waste regularly, reduction of generation of chemical
wastes, following the Code of Practice on the Packaging, Labelling and Storage
of Chemical Wastes, regular inspection and monitoring of floating refuse by
Marine Department’s appointed contractor, adverse environmental impacts form
waste management during operational phase are not anticipated.
3.5.1.1 Potential contaminative land uses within the assessment area and their potential impacts to future use have been examined. 15 potentially contaminated sites were identified. Due to actual site conditions, environmental site investigation (SI) could not be conducted during the EIA stage. In addition, as some of the sites are still in operation, it is considered not practicable to carry out the SI at this stage as the on-going activities would make the assessment result obsolete.
3.5.1.2 In view of this, further site visits at these 15 potentially contaminated sites are proposed when access is available in order to identify the need for SI for any additional hot spots as a result of the on-going activities.
3.5.1.3 In addition, re-appraisal would be required for the whole Project Areas to address any change in land use that may give rise to potential land contamination issues.
3.5.1.4 Findings of the re-appraisal will be presented in a supplementary Contamination Assessment Plan (CAP). Upon approval of the supplementary CAP and completion of the SI works, a Contamination Assessment Report (CAR) would be prepared to present findings of the SI works. If contamination has been identified, a Remediation Action Plan (RAP) would be prepared to recommend specific remediation measures. Upon completion of the remediation works, if any, a Remediation Report (RR) would also be prepared to demonstrate that the clean-up is adequate. The CAR, RAP and RR would be submitted to EPD for approval prior to commencement of any construction /development works.
3.6.1.1 The Project is located within the 1km consultation zone of the Tai Lam Chung No.2 Chlorination Station, which is currently a Potentially Hazardous Installation (PHI). According to the latest information available, it will be delisted prior to the commencement of the construction works of the Project and will no longer be classified as a PHI. Therefore, the hazard assessment for it is no longer required as there would not be any hazard-to-life concerns.
3.6.1.2 Drill-and-blast works are required for the tunnel construction and open blasting works are required for some of the slope works. According to the latest design, overnight storage of explosives on site is required. Three temporary explosive magazines at Lam Tei, Siu Lam and Pillar Point have been proposed, which would be share-used with TMB.
3.6.1.3 A quantitative risk assessment (QRA) has been conducted for the transportation, overnight storage and use of explosives. The QRA has also considered other concurrent projects (e.g. TMB) for the cumulative impacts. The assessment results show that the societal risk for the overnight storage and transport of explosives as well as the use of explosives lie within the “ALARP” region. For individual risk, compliance is anticipated. A detailed ALARP assessment has been conducted. Mitigation measures and best practices, such as provision of dedicated training programme and implementation of emergency response and training, have been recommended to minimize the risk even further.
3.6.1.4 Subject to the liaison of the three concurrent projects R11, Tuen Mun Bypass (TMB) and Lam Tei Underground Quarrying (LTUQ), a Hazard Management Plan would be formulated with a view to aligning the understanding of the risk of the three projects so that all the working populations at Lam Tei Quarry area, which includes the workforce induced under the construction and operational stage of three projects, could be considered as on-site populations in the quantitative risk assessment for all the three projects. The measures stipulated in the Hazard Management Plan may include, but not limited to, the adjustment of the blasting schedules of the three projects to minimize the potential cumulative impact, provision of common trainings and drills to the workforce of all the three projects, etc. The Hazard Management Plan, which would be agreed among the three projects, would be submitted to EPD for agreement prior to the tender invitation of construction phases of R11, TMB and LTUQ, whichever is earlier.
3.6.2.1 The Project does not fall into consultation zone of any PHIs. Besides, the operation of the Project does not involve any use of explosives, hence, potential risk during operational phase is not envisaged.
3.7 Ecology (Terrestrial and Marine)
3.7.1 Findings from Surveys and Literature
3.7.1.1 Ecological assessment has been conducted in accordance with Section 3.4.10 and Appendix H of the EIA Study Brief No. ESB 352/2022. The ecological baseline has been established based on literature review and results of the core field surveys of nine months between May 2022 and January 2023 with supplementary surveys completed in May 2023, covering both wet and dry seasons.
3.7.1.2 Recognized sites of conservation importance falling within or in the vicinity of the assessment area include Tai Lam Country Park (TLCP), Siu Lang Shui Site of Special Scientific Interest (SSSI), and “Conservation Area” under OZP. Important habitats within or in the vicinity of the assessment area include Fung Shui Woodlands in So Kwun Wat, catchwater tunnels with roosting bats in Tai Lam Chung, Siu Lang Shui Butterfly Habitat, Ma Wan Egretry, Day Roost and Night Roost, and marine habitat for Chinese White Dolphin. Twelve types of habitats were identified within the assessment area, namely agricultural land, backshore, channel, developed area, fung shui woodland, intertidal habitat (including seawall and natural coastline), mixed woodland, plantation, reservoir, sea, shrubland/grassland and watercourse. Dominant habitat types within the assessment area are shrubland/grassland, followed by developed area, sea and mixed woodland. The number and abundance of species of conservation importance recorded within the aboveground works areas or marine works areas were limited.
3.7.2 Avoidance and Minimization
3.7.2.1 Key ecological issues of the Project include potential impacts to TLCP, catchwater tunnels with roosting bats in Tai Lam Chung, Fung Shui Woodlands (FSWs) in So Kwun Wat and mixed woodland. Nevertheless, due consideration on impact avoidance and impact minimization have been taken in the Project.
3.7.2.2 The Project has minimized the overall habitat loss and completely avoided direct impact on TLCP and all other recognized sites of conservation importance by adopting tunnel form for significant proportion of the alignment (i.e. Lam Tei Tunnel, So Kwun Wat Link Road and Tai Lam Chung Tunnel), including all sections through TLCP, and careful site selection for aboveground works areas. The Project has thus avoided direct habitat loss from any recognized sites of conservation importance including TLCP. Besides all sections of alignment within TLCP, there are also some further tunnel sections outside TLCP, and the overall loss of natural habitats are further minimized.
3.7.2.3 Direct loss of important terrestrial habitats will also be avoided. By refining the alignment, in addition to reducing the extent of cut slope in So Kwun Wat and thus the associated habitat loss, overlapping of the alignment with FSW habitat has also been minimized to 0.25ha. The design of the concerned overlapping section has also been further considered to adopt viaduct form instead of at-grade road form, to span over the FSW. The piers for this section of viaduct would avoid the FSW, with increased gradient of viaduct to allow more headroom and a 7-metre gap between the north-southbound lanes, direct encroachment onto the FSW will therefore be avoided and shading impact is also minimized. Besides, Siu Lang Shui Butterfly Habitat, as well as Ma Wan Egretry, Day Roost and Night Roost will also be avoided.
3.7.2.4 For temporary habitat loss during construction, the temporary works areas, barging points and magazine sites are dominated by existing developed areas. The haul roads would follow the main alignment of the Project as far as possible, so as to maximize the overlapping with aboveground works areas and minimize the additional temporary habitat loss.
3.7.2.5 The alignment has also avoided overlapping with most of the catchwater tunnels with roosting bats in Tai Lam Chung. The only exception is TLC Catchwater Tunnel No. 6 in which the proposed Tai Lam Chung Tunnel (South Section) would pass underneath due to site constraints and technical requirements. While there will be no direct impact, indirect impact would still be reduced by optimizing the vertical separation distance between TLC Catchwater Tunnel No. 6 and the proposed Tai Lam Chung Tunnel (South Section). The horizontal separation between Lam Tei Tunnel and So Kwun Wat Link Road with TLC Catchwater Tunnel No. 8 has also been maximized as far as practicable to minimize ground-borne vibration impact to roosting bats.
3.7.2.6 Fragmentation of habitats has also been minimized by adopting tunnel and viaduct design at the aboveground sections. In addition, the aboveground works areas for the main alignment in Lam Tei, So Kwun Wat, Tai Lam, Siu Lam, Tsing Lung Tau and Ng Kwu Leng are located at the edge of natural habitats, such that the resulting habitat fragmentation is minimized to the best practicable extent.
3.7.2.7 Furthermore, reclamation in North Lantau has been avoided and the reclamation area in Tsing Lung Tau has also reduced to 2.2ha.
3.7.3.1 Potential direct ecological impacts arising from the Project during the construction phase include permanent and temporary habitat loss, as well as impact on flora (including Incense Tree, Small Persimmon, Luofushan Joint-fir, Ixonanthes and Pitcher Plant) and fauna species of conservation importance of relatively low mobility (including Hong Kong Cascade Frog) identified within the aboveground works areas. A conservative approach has been adopted for the estimation of direct habitat loss, assuming that all areas covered by viaduct on plan as part of the permanent habitat loss and areas within 5m distance on plan from the aboveground Project footprint as additional works areas forming part of the temporary habitat loss, but both will be subject to actual needs during construction and are expected to be smaller than the estimated areas. The majority of watercourses falling within the aboveground works areas would also be preserved onsite even construction activities are conducted nearby, except at four locations where direct impact is expected and provision of green channel diversion is needed where practicable. With the implementation of mitigation measures, no adverse impact is anticipated.
3.7.3.2 Most terrestrial habitats to be lost (e.g. backshore, channel, developed area, plantation, and shrubland/grassland) are of low ecological value. No specific ecological mitigation measure will be required for the permanent or temporary loss of habitats of low ecological value.
3.7.3.3
For the
rest of habitats mentioned above, the potential impact of loss of mixed
woodland of low to medium value is considered as moderate. Permanent loss of about 17.54ha
of mixed woodland would be mitigated by off-site compensatory woodland planting
at Tuen Mun West, since on-site compensation is not feasible due to limited
Project area available for tree planting.
For the temporary loss of about 6.54ha of mixed woodland, on-site
reinstatement planting will be provided after construction as far as
practicable. Should reinstatement
at temporary works areas be found not feasible, the loss may also be
compensated together as part of the off-site compensation woodland.
3.7.3.4 By optimizing the design of viaduct as mentioned in Table 2.1, FSW habitat beneath the viaduct has been preserved, but felling of 8 trees of Ixonanthes reticulata located in the eastern patch of Ching Uk Tsuen (CUT) FSW will be unavoidable. Owing to their size and their locations on slopes, which may not be accessible by mechanical equipment, transplantation is considered not feasible. Compensation of these 8 nos. of I. reticulata will be provided within or in the vicinity of CUTFSW as far as practicable.
3.7.3.5 Direct impact on watercourses in So Kwun Wat and Siu Lam, all of which fall outside TLCP, is expected during the construction phase, including a ditch and four watercourse sections, which are of low and low to medium ecological value respectively. Direct impact will be mitigated by diversion of the sections of watercourses to be directly impacted and provision of green channel design, together with translocation of aquatic and/or water-dependent species of conservation importance, should any be recorded during the detailed survey on aquatic and/or water-dependent species of conservation importance to be carried out.
3.7.3.6 Bird, butterfly, odonate and reptile species of conservation importance of relatively higher mobility and recorded within the aboveground works areas of the Project are unlikely to be directly impacted. Besides, during the construction phase, mammal and herpetofauna species, including those of conservation importance, will be prevented from entering the aboveground works areas with site formation by the erection of construction hoardings around their boundaries.
3.7.3.7 To mitigate the remaining potential direct ecological impacts on flora and fauna species of conservation importance within the aboveground works areas falling outside TLCP, detailed vegetation survey followed by preservation, transplantation and/or compensatory planting of flora species of conservation importance, and detailed survey and translocation of aquatic and/or water-dependent fauna species of conservation importance at watercourse sections to be affected will be carried out.
3.7.3.8 The anticipated direct ecological impact will be mitigated to minor level. Monitoring of the establishment of the compensatory woodland, implementation of transplantation and monitoring of the flora species of conservation importance and translocation and monitoring of aquatic and water-dependent fauna species will be conducted where applicable.
3.7.3.9 Potential indirect impacts during the construction phase have been assessed, including habitat fragmentation, construction disturbance (the impact of ground-borne vibration on the roosting bats inside catchwater tunnels is to be addressed separately in Section 3.7.3.10), light glare impact, water quality impact and potential groundwater drawdown along the tunnel alignments, potential indirect impact on recognized sites of conservation importance, important habitats, roosting grounds and species of conservation importance. These impacts are either minor or insignificant in nature or level and do not require specific ecological mitigation measure to be implemented to mitigate their effect. Nevertheless, good site practices will be implemented to further minimize the impacts and monitoring on effectiveness of mitigation measures for potential groundwater drawdown will be carried out.
3.7.3.10 For the other potential indirect ground-borne vibration impact on TLC Catchwater Tunnel Nos. 1, 5, 6, 7 and 8 with roosting bats, the Project has considered to maximize the separation distance between the concerned catchwater tunnels and tunnels to be constructed by the Project to the best practicable extent. The impact of ground-borne vibration arising from tunnelling works of Lam Tei Tunnel, So Kwun Wat Link Road and Tai Lam Chung Tunnel (South Section) on the catchwater tunnels with roosting bats within the assessment area is anticipated to be minor (TLC Catchwater Tunnel No. 5), minor to moderate (TLC Catchwater Tunnel Nos. 6 and 8) or insignificant (TLC Catchwater Tunnel Nos. 1 and 7) in the absence of mitigation. To mitigate the impact of ground-borne vibration on these roosting bats, controlled blasting with the charge weight adjusted with the works fronts of tunnelling will be implemented. Through reviewing relevant and publicly available literature, ground-borne vibration levels are recommended for planning of blasting works for tunnelling, including “Alert Level”, “Action Level” and “Limit Level”. Regular adaptive review on the “Alert Level”, “Action Level” and “Limit Level” based on the monitoring data, including ground-borne vibration and bat monitoring data to be collected for TLC Catchwater Tunnel Nos. 6 and 8 during pre-blasting and blasting phases, and the latest studies available will be conducted throughout the course of tunnelling works. Should TLC Catchwater Tunnel No. 5 be found to be occupied by roosting bats during the pre-blasting and blasting phases, the monitoring results related to TLC Catchwater Tunnel No. 5 should also be taken into account when reviewing the Alert, Action and Limit Levels. A monitoring programme on TLC Catchwater Tunnel Nos. 1, 5, 6, 7 and 8 covering pre-blasting baseline condition, the full course of blasting works, post-blasting, and operational phase, will be conducted. Ground-borne vibration monitoring and bat monitoring surveys comprising acoustics survey, emergence survey, and bat roost survey covering overwintering season, breeding season and time gap between overwintering and breeding season, will be conducted for TLC Catchwater Tunnel Nos. 1, 5, 6, 7 and 8 for at least 9 months prior to any blasting to establish the pre-construction baseline, and during the whole blasting programme within construction phase, and also for at least 9 months after all blasting works are completed. Moreover, within the first year of the operational phase, both ground-borne vibration and bat roost monitoring will be conducted for TLC Catchwater Tunnel Nos. 1, 5, 6, 7 and 8 for at least 9 months. With the adoption of bat-relevant mitigation measures, it is anticipated that the ground-borne vibration impact on roosting bats will be mitigated to an acceptable level.
3.7.3.11 There will be potential direct marine ecological impacts arising from the proposed 2.2ha reclamation site at Tsing Lung Tau for Tsing Lung Bridge during the construction phase include permanent (about 4.1 ha) and temporary (about 13 ha) loss of seabed and the marine waters above, and associated direct impact on species of conservation importance (including very low density of amphioxus Branchiostoma belcheri, and less than 1% coverage of hard coral, namely Oulastrea crispata and ahermatypic cup coral Balanophyllia sp. and gorgonian Guaiagorgia sp). identified within the reclamation site.
3.7.3.12 No specific marine ecological mitigation will be required for the permanent or temporary loss of seabed, man-made seawall or natural coastline with relatively low ecological value. Most of the species recorded throughout the benthic and subtidal surveys are considered common and widespread in Hong Kong, the permanent loss of 4.1 ha sea habitat and temporary loss of about 13 ha sea habitat caused by the current Project is considered minor.
3.7.3.13 As a precautionary measure, prior to the start of marine construction works, a detailed reconnaissance dive survey along the man-made seawall and semi-natural coastline within the reclamation site was recommended to inspect if there are any additional colonies of hard and/or soft coral species. Should significant colonises are identified, the effectiveness and feasibility of coral translocation will be assessed. A detailed translocation proposal will be prepared if coral translocation is confirmed necessary.
3.7.3.14 As an enhancement measure, seawall enhancement design will be considered during the design stage of the reclamation site at Tsing Lung Tau for Tsing Lung Bridge. Possible ecological features should be considered to enhance the recruitment and colonization of the intertidal and subtidal fauna.
3.7.3.15 Potential indirect marine ecological impacts during the construction phase include impacts on marine water quality and disturbance due to increased marine traffic of works vessels. These indirect marine ecological impacts are either minor or insignificant and do not require specific ecological mitigation measure.
3.7.4.1 With good site practice guidelines, ecological impacts due to noise disturbance, ground-borne vibration disturbance from traffic, light glare, habitat fragmentation, impact on flight-lines and foraging habitats of ardeids (insignificant routing towards the direction of Tsing Lung Bridge), potential roadkill and bird collision, water quality impact, shading effect on part of the eastern patch of Ching Uk Tsuen Fung Shui Woodland and impact on recognized sites of conservation importance, important habitats, roosting ground and species of conservation importance during the operational phase are all considered minor or insignificant in nature and magnitude. No specific ecological mitigation measure but good practices for these ecological impacts during the operational phase is considered necessary.
3.8.1 Findings from Surveys and Literature
3.8.1.1
The
assessment area for the Fisheries Impact Assessment followed the assessment
area for water quality impact assessment and included any other areas likely to
be impacted by the Project. Special attention has been given to potential loss
or disturbance of fishing grounds, fisheries resources, habitats and other
fisheries sensitive receivers.
3.8.1.2
Information
from literatures and the field surveys has been incorporated, which provided
sufficient information on fisheries resources and operation in the assessment
area. The overall fisheries production and fishing operation in the vicinity of
the proposed development is regarded as low to moderate
and moderate, respectively.
Sensitive receivers, including Ma Wan Fish Culture Zone, spawning ground of
commercial fisheries resources in northern Lantau waters and artificial reefs
in the Brothers Marine Park have been identified. These fisheries
sensitive receivers are located away from the proposed alignment. The potential
impacts arising from the construction and operation activities of this Project
to these sensitive receivers have been evaluated.
3.8.2.1
There will be
direct fisheries impacts arising from the proposed reclamation site at Tsing
Lung Tau for Tsing Lung Bridge of the Project during the construction phase,
including permanent loss of about 4.1 ha fisheries habitats and fishing ground
due to 2.2ha of reclamation area and 1.9ha of seawall construction, and
temporary loss of about 13ha fishing ground due to marine works areas. Considering
the small extent of the area to be affected during the construction phase which
is of low to moderate fisheries production and moderate level of fishing
operation, impacts are considered to be of minor significance and unacceptable
impacts on fisheries resources, habitats and fishing activities are not
expected.
3.8.2.2
Potential indirect fisheries impacts
arising during the construction phase include deterioration of water quality
caused by marine works, increased marine traffic and underwater noise are evaluated
and all considered negligible in nature. Deployment of silt curtain and good
site practices will be implemented to further avoid/reduce potential impacts on
water quality. These measures are expected to control and reduce potential
impacts to fisheries as well, and no other fisheries-specific mitigation
measures are thus required during construction of the Project.
3.8.3.1
During the
operational phase, the proposed reclamation site at Tsing Lung Tau for Tsing
Lung Bridge of the Project will arise direct fisheries impacts, including
permanent loss of about 4.1ha of fisheries habitats and fishing ground due to
2.2ha of reclamation area and 1.9ha of seawall construction. Other indirect
impact to fisheries, such as the change of hydrodynamic and marine water
quality are evaluated and considered negligible in nature. No
fisheries-specific mitigation measures are required during operation of the
Project.
3.9.1 Landscape and Visual Baseline
3.9.1.1 The Landscape Resources (LRs) and Landscape Character Areas (LCAs) of the Project were identified and assessed. Within the assessment area, there are a total of 23 LRs and 15 LCAs.
3.9.1.2 A total of 57 Visually Sensitive Receivers (VSRs) within the Visual Envelop (VE) of the Project were identified and assessed.
3.9.1.3 It is estimated there are total approximate 25,720 nos. of existing trees within the 100m landscape impact assessment area.
3.9.1.4 There is no Registered Old Valuable Trees (OVT) within the 100m landscape impact assessment area.
3.9.1.5 There are approximate 63 nos. Ixonanthes reticulata (TPI) (size range: 5 to 22m height, 100 to 570mm DBH and, 2 to 12m crown) are identified within and near the works area within LR-SK1 (Secondary Woodlands in So Kwun Wat) and LR-SK11 (Developed Areas in So Kwun Wat), as well as 2 nos. of mature Ficus spp. with DBH of over 1m at other locations are recorded within the 100m landscape assessment area.
3.9.1.6 Saplings of Aquilaria sinensis, a species of conservation interest, are identified in LR-LT1 Secondary Woodlands in Lam Tei and LR-TL1 Secondary Woodlands in Tsing Lung Tau, and will not be affected.
3.9.1.7 8 nos. likely planted saplings of Aquilaria sinensis, a species of conservation interest, are identified in LR-SK12 Carriageway and roadside planter in So Kwun Wat will be affected by the road widening works and the construction of So Kwun Wat Link Road.
3.9.2 Landscape and Visual Impact Summary
3.9.2.1 An estimated approximate 5,077 nos. of affected trees in tree groups, together with 8 nos. of Tree of Particular Interest (TPI), namely Ixonanthes reticulata in Fung Shui Woodland near So Kwun Wat would be affected due to excessive tree topping, and proposed to be felled due to low “Suitability for Transplanting” based on preliminary assessment at this stage.
3.9.2.2 During the operational phase in Year 10, there will be Moderate adverse residual impacts in Year 10 for LR-SK1 Secondary Woodlands in So Kwun Wat, LR-NL4 Shrublands in North Lantau and LCA-NL9 Ng Kwu Leng Peninsular Landscape.
3.9.2.3 During the operational phase, there will be Slight adverse residual impacts in Year 10 for LR-LT1 Secondary Woodlands in Lam Tei, LR-LT2 Plantations in Lam Tei, LR-SK2 Plantations in So Kwun Wat, LR-SK4 Shrubland in So Kwun Wat, LR-TL2 Plantations / Mixed Woodlands in Tsing Lung Tau, LR-NL2 Plantations in North Lantau, LCA-LT3 Lam Tei Rural Landscape, LCA-SK4 Tai Lam Country Park Upland Landscape, LCA-SK6 Siu Lam and Tai Lam Chung Foothill Landscape, and LCA-SK7 Tai Lam Chung River Valley Landscape.
3.9.2.4 The remaining LRs would be subject to an Insubstantial residual impact during Year 10 of the operational phase.
3.9.2.5 An estimated approx. 100 nos. of affected trees, mostly roadside amenity tree plantings, are considered suitable for transplanting.
3.9.2.6 The exact quantity, tree condition, proposed recommendations as well as future receptor locations of these trees shall be further reviewed in the formal Tree Preservation and Removal Proposal (TPRP) to be prepared and submitted in the detailed design stage. To achieve a compensatory ratio of not less than 1:1 in terms of number of trees to be felled, at least 5,085 nos. (5,077 nos. common trees + 8 nos. TPI) of compensatory trees are required. Under the proposed scheme for the Project, opportunities for tree compensation within the Project boundary has been fully explored and incorporated in the proposed mitigation measures as much as practicable. It is estimated that approximate 1,300 nos. compensatory tree planting in heavy standard size is proposed at roadside flat areas mainly near the tunnel portal areas, administration areas in Lam Tei Quarry and North Lantau and road verge areas. Further, it is estimated that approximate 700 nos. light standard trees will be proposed along at-grade wall planters, subject to the gradient of the proposed new slopes. All proposed species shall be commonly used in roadside environment and be native for areas adjoining woodland area where appropriate, so as to enhance the surrounding landscape and ecological value. The native seedlings/whip trees for off-site woodland compensation at Tuen Mun West will be tentatively planted at an initial spacing of 1,500 mm in staggered pattern on planting area with gradient less than 35 degree, followed by thinning during the establishment period to decrease the potential competition between trees. It is anticipated that total area of ~24.4ha will be proposed for not less than approximate 3,085 nos. compensatory whip tree planting.
3.9.2.7 Compensatory planting proposals in the form of trees as well as other planting opportunities (e.g. slope greening, vertical greening, etc.) shall be prepared as part of the formal TPRP in the detailed design stage for relevant government departments’ agreement.
3.9.2.8 The residual visual impacts in Year 10 of the operational phase include Moderate adverse impacts for VSR-LT2 Residents of Fu Tai Estate, VSR-LT3 Residents of Lo Fu Hang, VSR-LT6 Residents of The Sherwood, VSR-LT8 Residents of Tsoi Yuen Tsuen, VSR-LT11 Future Residents of Potential Residential Development at Brownfield Clusters in Lam Tei North and Nai Wai, VSR-SK1 Trail Walkers on MacLehose Trail Section 10 (West), VSR-SK3 Residents of The Bloomsway, VSR-SK4 Students and Staff at Harrow International School Hong Kong, VSR-SK6 Residents of Aegean Coast, VSR-LT5 Residents of Fuk Hang Tsuen, VSR-SK8 Vehicle Travellers and Pedestrians on So Kwun Wat Tsuen Road, VSR-SK9 Trail Walkers on MacLehose Trail Section 10 (East), VSR-SK10 Residents of So Kwun Wat Tsuen, VSR-SK11 Residents of So Kwun Wat San Tsuen, VSR-SK12 Visitors to Glorious Praise Fellowship (Hong Kong) Treatment Centre, VSR-SK13 Vehicle Travellers on Siu Lam Road, VSR-SK15 Residents of Palatial Coast, VSR-SK16 Residents of Siu Lam, VSR-SK21 Trail Walkers and Cyclists on Tai Lam Chung Reservoir Main Dam, VSR-SK22 Pedestrians on Footbridge over Tai Lam Chung River, VSR-SK24 Trail Walkers on Summit of Hill 141, VSR-SK29 Residents of Tai Lam Chung Tsuen, VSR-TL3 Residents of Hong Kong Garden, Vista Cove and L'Aquatique, VSR-NL2 Trail Walkers on Summit of Fa Peng Teng, and VSR-NL8 Residents of Park Island.
3.9.2.9
The residual visual impacts in
Year 10 of the operational phase include Slight
adverse impacts for VSR-LT1 Residents of Parkland Villas, VSR-LT4 Vehicle
Travellers on Yuen Long Highway (Eastbound), VSR-LT7 Vehicle Travellers on Kong
Sham Western Highway (Southbound), VSR-LT9 Vehicle Travellers on Yuen Long
Highway (Westbound), VSR-SK2 Vehicle Travellers on Tuen Mun Road, VSR-SK5
Residents of Hong Kong Gold Coast, VSR-SK7 Residents of Avignon, VSR-SK14 Trail
Walkers on Tai Lam Chung Reservoir Subsidiary Dam at Siu Lam Road, VSR-SK26
Vehicle Travellers on Castle Peak Road – So Kwun Wat, VSR-SK27 Students and
Staff at PLK Women's Welfare Club Western District Fung Lee Pui Yiu Primary
School and S.T.F.A. Lee Kam Primary School, VSR-SK23 Vehicle Travellers and
Pedestrians on Castle Peak Road – Tai Lam, VSR-SK25 Trail Walkers at South of
To Hang Tung, VSR-SK30 Students and Staff at Hong Kong Customs College,
VSR-SK31 Staff and Visitors at Tai Lam Correctional Institution, VSR-TL1
Vehicle Travellers on Tuen Mun Road (Westbound), VSR-TL2 Residents of Bellagio
and Ocean Pointe, VSR-TL4 Vehicle Travellers and Pedestrians on Castle Peak
Road – Tsing Lung Tau (Eastbound), VSR-TL5 Vehicle Travellers on Tuen Mun Road
(Eastbound), VSR-TL11 Pedestrians on Footbridge across Castle Peak Road – Tsing
Lung Tau, VSR-TL12 Travellers in Tsing Lung Tau Ferry Pier, VSR-TL13 Travellers
in Sham Tseng Public Pier, VSR-TL14 Residents of Sea Crest Villa Phase 4,
VSR-NL1 Vehicle Travellers on North Lantau Highway (Westbound), VSR-NL3 Vehicle
Travellers at Lantau Link Toll Plaza, VSR-NL4 Travellers in Ma Wan Public Pier,
VSR-NL5 Vehicular Travellers on Kap Shui Mun Bridge, VSR-NL6 Visitors at Sunny
Bay Promenade, VSR-NL7 Maritime Travellers in Ha Pang Fairway and VSR-NL9
Future Users at Planned Sunny Bay Reclamation Area.
3.9.2.10 The remaining VSR will be subject to an Insubstantial residual impact in Year 10 of the operational phase, namely, VSR-LT10 Trail Walkers on Fu Tei Country Trail and Lam Tei Irrigation Reservoir, VSR-SK28 Students and Staff at Chu Hai College of Higher Education and VSR-NL10 Future Vehicle Travellers on Planned Road P1.
3.9.2.11 Overall, it is considered that the residual landscape and visual impacts of the proposed development are acceptable with mitigation during the construction and operational phases.
3.10.1 Terrestrial Archaeology
3.10.1.1 An archaeological impact assessment has been conducted for the Project. No site of archaeological interest would be affected by the Project and associated works. An area of archaeological potential was identified at the east of Area A at the lower slopes to the north of Lam Tei Quarry within the works area. Due to restrictions in access, no archaeological field survey could be undertaken at this stage and it is recommended that the survey to be undertaken when access is available but before the site formation and construction phases.
3.10.1.2 Furthermore, if antiquities or supposed antiquities are identified during the construction works, the works should be suspended, and the project proponent should notify AMO immediately for discussion of appropriate mitigation measures to be agreed with AMO before implementation by the project proponent to the satisfaction of AMO.
3.10.1.3 An archaeological field survey will be conducted at east of Area A at the lower slopes to the north of Lam Tei Quarry within the works area when access is available before the site formation and construction phase. Subject to the result(s) of the survey, mitigation measures, if necessary, will be proposed for AMO’s agreement before implementing to the satisfaction of AMO.
3.10.1.4 Terrestrial archaeological impact is not anticipated during operational phase.
3.10.2.1 The literature review conducted for the built heritage impact assessment has also collated relevant information on Declared Monuments and Graded Historic Buildings. A field survey was also conducted for built heritage to identify all built heritage resources within 300m from the boundary of the Project area. Results indicate there is a Grade 3 Former Perowne Barracks, Gurkha Temple located at around 11m from the earthworks associated with road works.
3.10.2.2 Other resources including shrines, former stone quarry site, Fung Shui Woodland and other concerned buildings were also identified. Furthermore, if buildings / structures both at-grade and underground with potential heritage value that would likely be affected by the development are identified during the construction works, the works should be suspended, and the project proponent should notify AMO immediately for discussion of appropriate mitigation measures to be agreed with AMO before implementation by the project proponent to the satisfaction of AMO.
3.10.2.3 The earthworks associated with road works have the potential to directly/indirectly impact on Former Perowne Barracks, Gurka Temple nearby. Mitigation measures before, during and after the construction phase will be required including a condition survey before and after the construction phase, ongoing vibration and building movement monitoring, and any other monitoring identified in the condition survey and a buffer zone to physical separate the heritage site from the works. Special attention should be paid to avoid adverse physical impact arising from the construction of the Project. Design proposal, method of works and choice of machinery will be selected to minimize adverse impacts to the heritage site. Foundation information of the historic structure shall be verified on site if needed, sufficient lateral support should be provided, and de-watering (if required) should be carried out with great cautions to control ground movement and change of ground water regime at the heritage site. Therefore, adverse impact on built heritage is not anticipated during operational phase.
3.10.2.4 Impact on built heritage is not anticipated during operational phase.
3.10.3.1 A Marine Archaeological Investigation (MAI) has been conducted for the proposed reclamation of the Project. The baseline conditions have been established by first reviewing historical information. A MAI was previously conducted under “Route 10 – North Lantau to Tsing Lung Tau Section” project, which concluded that there was no marine archaeological resource within the respective study area, which partially overlapped with the Study Area of the Project.
3.10.3.2 It should however be noted that the Study Area for marine archaeology is located along the Ha Pang Fairway which is heavily utilized by marine vessels such as ocean-going vessels. As advised by Marine Department, it is highly not recommended to conduct the diving works within the inshore traffic zone and the fairway from the marine navigational safety point of view. Fencing off the diving area is required to secure diver’s safety, which would unavoidably affect the operation of the fairway. As such, a marine traffic impact assessment would be required to be conducted to minimize the potential marine traffic impact, especially on the ocean-going vessels in relatively close proximity or even with potential interface. In addition, a contractor would be required to be engaged to fence off the fairway. All of the above would have significant time implication and thus considered not feasible to be carried out in the EIA stage, and better to be implemented during the detailed design stage.
3.10.3.3 It should be emphasized that according to the geophysical survey data, there is no shipwreck within the 300m assessment area. The anomalies identified from the geophysical survey are also relatively small in size.
3.10.3.4 In case any of the anomalies with marine archaeological value is confirmed during the marine diver survey of MAI during detailed design stage, the project proponent should inform AMO immediately for discussion of appropriate mitigation measures to be agreed by AMO before implementation by the project proponent to the satisfaction of AMO. Moreover, with reference to the previous MAI, no marine archaeological resource was identified within the proposed reclamation area of the Project. Thus, it is considered unlikely to affect the design of the Project.
3.10.3.5 After considering all relevant literatures, all the previous MAI, latest geophysical survey, consideration of marine safety and time implication, it is recommended to conduct the marine diver survey during detailed design stage when fencing off of the diving area can be safely implemented. Nevertheless, all the diver survey shall be conducted prior to reclamation works.
3.10.3.6 For marine ground investigation (GI), which would be required prior to the reclamation works or the diver survey, it is recommended that the marine GI works shall be arranged to avoid all the anomalies identified by the geophysical survey conducted, by allowing sufficient setback distance (around 50m) from the anomalies. In case of discovery of any antiquities or supposed antiquities in the course of marine GI works, the project proponent is required to inform AMO immediately for discussion of appropriate mitigation measures to be agreed by AMO before implementation by the project proponent to the satisfaction of AMO. Besides, any GI at the anomalies is required to be conducted after confirming their nature by MAI and seeking agreement with AMO.
3.10.3.7 Marine archaeological impact is not anticipated during operational phase.
4.1.1.1 An Environmental Monitoring and Audit (EM&A) programme has been formulated for Project which is a DP listed under Schedule 2 of the EIAO, with details presented in the separate EM&A Manual. Key aspects which require monitoring include air quality (i.e. construction dust), noise (i.e. construction noise and road traffic noise), water quality and ecology (i.e. impacts on bat roosts).
4.1.1.2 The EM&A programme will provide management actions to check the effectiveness of the recommended mitigation measures and compliance with relevant statutory criteria, thereby ensuring the environmental acceptability of the construction and operation of the Project.
5.1.1.1 The Project will be a strategic highway, consists of at-grade roads, viaducts, tunnels and suspension bridge, to support the proposed developments in the NWNT, and provide the third vehicular access to Lantau in addition to the existing Tsing Ma and Kap Shui Min Bridges and the TM-CLKL. It will cover areas in Lam Tei, So Kwun Wat, Tai Lam, Tsing Lung Tau and North Lantau.
5.1.1.2 An EIA Report has been prepared to fulfil the requirements as specified in the EIA Study Brief (No.: ESB-352/2022) and the EIAO-TM. All the latest design information has been incorporated into the EIA process. The aspects that have been considered in this EIA Report include:
· Project Description and Consideration of Alternatives;
· Air Quality Impact;
· Noise Impact;
· Water Quality Impact;
· Waste Management Implications;
· Land Contamination;
· Hazard to Life;
· Ecological Impact (Terrestrial and Marine);
· Fisheries Impact;
· Landscape and Visual Impact;
· Impact on Cultural Heritage; and
· EM&A Requirements.
5.1.1.3 The summary of the environmental impacts arising from the Project is presented in Table 5.1.
5.1.1.4 Overall, the EIA Report has predicted that the Project would be environmentally acceptable and individual impacts are minimized with the implementation of the proposed mitigation measures for construction and operational phases. An EM&A programme has been recommended to check the effectiveness of recommended mitigation measures.
Table 5.1 Summary of
environmental impacts
Sensitive Receivers / Assessment
Points |
Impact Prediction Results |
Key Relevant Standards/Criteria |
Extents of Exceedance (Without
Mitigation) |
Impact Avoidance Measures/ Mitigation Measures |
Residual Impacts (After Implementation
of Mitigation Measures) |
Air Quality Impact |
|||||
Construction Phase |
|||||
Existing
and planned ASRs |
·
Adverse construction dust impact is not anticipated
with proper implementation of good control measures and environmental
monitoring and audit |
·
AQO ·
EIAO-TM Annex 4 o 24-hour average RSP
concentration: 100 μg/m3 (Number of exceedance allowed: 9) o Annual average
RSP concentration: 50 μg/m3 o 24-hour average
FSP concentration: 50 μg/m3 (Number of exceedance allowed:
18) o Annual average
FSP concentration: 25 μg/m3 |
·
Not applicable |
·
Close liaison between the contractors of other concurrent
projects and
the Project would be maintained to minimise dusty activities to be conducted
concurrently as far as practicable Good control measures are
recommended: ·
Watering once per hour on the exposed
construction areas with dust emission and paved haul roads to reduce dust
emission; ·
Dust suppression measures stipulated in the Air
Pollution Control (Construction Dust) Regulation and good sites practices
would be carried out to further minimise construction dust impact; ·
Follow the requirements stipulated in the Best
Practicable Means for Cement Works (Concrete Batching Plant) BPM 3/2 (16) to
minimise the fugitive emissions arising from the operation of concrete
batching plant; ·
Emission control measures for barging facilities,
such as provision of enclosed system with 3-side screen with top cover and
provision of water spraying system, regular water and covering spoils by
tarpaulin; and ·
The engine of the barge shall be switched-off
during berthing as far as practicable. Provision of on-shore power supply
shall also be considered wherever possible to minimize air quality impact
from the marine vessels, with consideration of actual site constraints or
circumstances to be further reviewed during detailed design stage. |
·
No adverse residual impacts anticipated |
Operational Phase |
|||||
Existing
and planned ASRs |
·
19th highest 1-hr average
concentration: 88 – 166 μg/m3 ·
Annual average concentration: 17 – 39μg/m3 RSP ·
10th highest 24-hour average RSP concentration:
64 – 73μg/m3 ·
Annual average RSP concentration: 26 –
29μg/m3 FSP ·
19th highest 24-hour average FSP concentration:
35 – 41μg/m3 ·
Annual average FSP concentration: 15 –
16μg/m3 |
·
AQO ·
EIAO-TM Annex 4 o 1-hour average
NO2 concentration: 200 μg/m3 (Number of exceedance
allowed: 18) o Annual average
NO2 concentration: 40 μg/m3 o 24-hour average RSP
concentration: 100 μg/m3 (Number of exceedance allowed: 9) o Annual average
RSP concentration: 50 μg/m3 o 24-hour
average FSP concentration: 50 μg/m3 (Number of exceedance
allowed: 18) o Annual average
FSP concentration: 25 μg/m3 |
·
No exceedance is anticipated |
·
No mitigation measure is required; ·
During the subsequent design stage
and the operational stage, the ventilation engineer should conduct adaptive
reviews on the ventilation scheme covering different periods of a day, taking
into account the contemporary circumstance such as latest traffic forecast,
traffic composition, update on the ambient air quality etc., and then review
and update the air quality assessment as necessary to demonstrate full
compliance of the AQOs. These adaptive reviews would allow the designer
and operator to optimize the operation of the ventilation system without
compromising the compliance of AQOs; and ·
The planned air sensitive uses within the
operation area of the TMB shall be properly designed such that any openings,
openable windows, and/or fresh air intakes will be located and avoided from
the predicted exceedance zone at 1.5mAG. Further review of the layout and
design of operation area will be conducted in detailed design Stage to ensure
compliance of the AQOs. |
·
No adverse residual impacts anticipated |
Noise |
|||||
Construction Phase |
|||||
Existing and
planned NSRs |
·
Adverse construction noise impact is not
anticipated with proper implementation of good control measures and
environmental monitoring and audit ·
The future Contractor will also be required to
prepare a Construction Noise Management Plan (CNMP) |
·
EIAO-TM
Annex 5 and Annex 13 for non-restricted hours for domestic premises: o Leq (30mins) 75 dB(A) for
all domestic premises, temporary housing accommodation, hostel, convalescent
homes and homes for the aged o Leq (30mins) 70 dB(A) for
places of public worship, courts of law, hospitals, medical clinics and
educational institution (including kindergartens and nurseries) (65 dB(A)
during examination period |
·
Not applicable |
Good control measures are recommended
to minimize the construction noise impact as far as practical: ·
Good site practices to limit noise emissions at
the source; ·
Use of quality powered mechanical equipments
(QPMEs) and quieter construction methods; ·
Use of temporary noise barriers and enclosures to
screen noise from relatively static PME; and ·
Alternative use of plant items within one
worksite, wherever practicable. |
·
No adverse residual impacts anticipated |
Operational Phase (Road Traffic Noise) |
|||||
Existing and planned NSRs |
·
Predicted overall noise levels: 40 – 82dB(A) ·
Predicted road traffic noise levels of the
project roads: ≤40 – 79dB(A) ·
Maximum contribution from Project roads (When the
overall level exceeds respective criterion): 6.6dB(A) |
EIAO-TM Annex 5 and Annex 13: o L10 (1hour) 70dB(A) for
all domestic premises, temporary housing accommodation, hostel, convalescent
homes and homes for the aged o L10 (1hour) 65dB(A) for
places of public worship, courts of law and educational institution o L10 (1hour) 55dB(A) for
medical and clinics |
·
Exceed EIAO-TM criterion by up to 12 dB(A) |
·
Provision of highly modified friction course
(HMFC) as standard surfacing material on the high speed road sections of new
road projects with design speed of 80km/hr or above and expressway; ·
Provision of 6mm polymer modified stone mastic
asphalt (PMSMA6) as low noise surfacing material for other roads without
standard surfacing material on suitable Project Road sections; ·
Provision of noise mitigation measures: o
Lam Tei: Vertical Barrier (VB) and Cantilever Barrier (CB) along slip roads
connecting KSWH / YLH; o
So Kwun Wat: CB near So Kwun Wat Link Road western portal; and o
Tsing Lung Tau: VB, CB and semi-enclosure along realigned TMR. ·
For planned developments,
necessary receiving-end mitigation measures will be proposed by the
respective project proponent in addition to the proposed at-source mitigation
measures. |
·
No adverse residual impacts anticipated |
Operational Phase (Fixed Noise) |
|||||
Existing and planned NSRs |
·
Adverse fixed noise impact is not anticipated
with good design and control measures, and environmental monitoring and audit ·
The future Contractor will also be required to
prepare a Fixed Noise Management Plan (FNMP) |
·
EIAO-TM
Annex 5 and Annex 13, and IND-TM ·
Appropriate ANLs and ANLs-5 as shown in Table 2 of
IND-TM or the prevailing background noise level |
·
Not applicable |
·
Proper selection of quieter equipment and
installation of silencer, barrier or enclosure; ·
Orientating louvres away from adjacent NSRs,
preferably onto main roads which are less noise sensitive; and ·
Selection of façade for ventilation shafts with
adequate sound insulation properties. |
·
No adverse residual impacts anticipated |
Water Quality |
|||||
Construction Phase |
|||||
Water Sensitive Receivers |
Water
quality in WSRs would be deteriorated by land-based construction with the
following pollution sources: ·
Construction run-off and general construction
activities; ·
Tunnelling and underground works; ·
Construction for ventilation buildings and
administration buildings; ·
Sewage due to construction workforce; ·
Construction works in close proximity of inland
water; ·
Removal or diversion of Watercourses ·
Groundwater from contaminated areas and
contaminated site run-off; ·
Operation of barging point; and ·
Accidental spillage of chemicals. Water
quality in WSRs would be affected by marine-based construction with the
following pollution sources: ·
Reclamation at Tsing Lung Tau; ·
Seawall construction; ·
Stone column installation; and ·
Marine traffic. Quantitative water quality assessment
results showed no adverse impact to water quality during reclamation works. |
·
EIAO-TM Annex 6 and Annex 14 ·
WPCO (Cap. 358) ·
TM-DSS ·
ProPECC PN 1/94 ·
WSD’s Water Quality
Criteria for Sea Water Intakes |
·
Not applicable |
·
Good site practices in accordance with ProPECC
PN1/94 when handling the site sun-off from general site operation; ·
Suitable water control strategies (e.g. probing
ahead and pre-grouting) during tunnel works; ·
Temporary dewatering to minimize impacts on
groundwater table during the works; ·
Providing temporary sanitary facilities and
posting notices about treating discharge at conspicuous locations for the
workforce; ·
Comply with the Conditions for Working within
Water Gathering Grounds; ·
Good site practices in accordance with ETWB
TC(Works) No. 5/2005 “Protection of natural streams/rivers from adverse
impacts arising from construction works” for removal or diversion of
watercourses; ·
Proper handling of contaminated groundwater and
site run-off; ·
Proper good site practice to prevent water
quality impact during transportation of spoil when using the barging point; ·
Proper storage of the chemicals used during
construction; ·
Filling works to be conducted within the
completed leading seawall; ·
Mud pit to be completely sealed to prevent any
leakage of backfilled sediments to the surrounding marine waters; and ·
Deployment of single layer silt curtain as
enhancement measures. |
·
No adverse residual impacts anticipated |
Operational Phase |
|||||
Water Sensitive Receivers |
Water
quality in WSRs would be affected by the following operational activities: ·
Surface run-off from paved areas of the Project; ·
Sewage effluent from the proposed buildings; ·
Drainage of road surface and tunnel runoff; and ·
Wastewater generated from washing and maintenance
operation. Quantitative water quality assessment
results showed no adverse impact to water quality during operational phase. |
·
EIAO-TM Annex 6 and
Annex 14 ·
WPCO (Cap. 358) · TM-DSS ·
ProPECC PN 5/93 |
·
Not applicable |
·
Provision of mitigation measures including 1)
standard oil interceptors before discharge to public stormwater drainage
system and 2) silt trap for the surface runoff at the stormwater drainage
system as necessary; ·
Connection to existing sewerage networks for
sewage effluent from proposed buildings; ·
Collecting and treating wastewater generated by
washing and maintenance activities of ventilation systems via an active
carbon filter before being discharged to stormwater drainage system; and ·
Proper collection and disposal of spent
lubrication oil by Licensed Chemical Contractor. |
·
No adverse residual impacts anticipated |
Waste Management Implication |
|||||
Construction Phase |
|||||
The waste transportation
routes and the waste disposal site, as well as the waste disposal outlet |
·
It is estimated that 1,596,600m3 of
soft inert C&D material would be generated and reused on-site as far as
practicable or delivered to Tuen Mun Area 38 Fill Bank for reuse in other
projects; ·
It is estimated
that 7,701,700m3 of hard inert C&D material would be reused
on-site as much as practicable and the surplus would be delivered to Tuen Mun
Area 38 Fill Bank for reuse in other projects; ·
It is estimated
that 64,060m3 of non-inert C&D materials would be generated
and be disposed of at WENT Landfill; ·
It is estimated
that 31,000m3 of marine sediment would be generated. Reuse of
sediment on site would be explored and marine disposal would only be
considered as last resort; ·
It is estimated
that 4,705tonnes of general refuse would be generated and be recycled for
recyclables or disposed of at WENT Landfill; ·
A few hundred
litres of chemical wastes would be generated per month. It would be collected
and disposed of by licensed collector at CWTC; and ·
Floating refuse
of approximately 1.5m3 per year would be trapped within the
Project Area. |
· EIAO-TM Annex 7 and Annex 15 · WDO (Cap. 354) · Land (Miscellaneous Provisions) Ordinance
(Cap. 28) · Public Health and Municipal Services
Ordinance (Cap. 132) – Public Cleansing and Prevention of Nuisances
Regulations · DASO (Cap. 466) · DEVB TCW No. 06/2010 · ETWB TC(W) No. 34/2002 ·
WBTC No. 12/2000 Fill Management |
·
Not applicable |
·
Waste reduction should be considered at the
planning and design phase, as well as by ensuring the implementation of good
site practices; ·
Carry out on-site sorting to retrieve recyclable
materials as much as possible; ·
Inert construction waste shall not be in liquid
form such that it can be contained and delivered by water-tight
containers. Inert C&D materials in
liquid form shall be solidified before delivering to the public fill
reception facilities; ·
A trip-ticket system shall be implemented and GPS
or equivalent system shall be installed in dump trucks and vessels for
delivery of inert C&D materials or marine sediment from the site to
disposal locations to avoid illegal dumping and landfilling; ·
If chemical wastes are produced at the
construction site, the contractors should register with EPD as chemical waste
producers. Chemical wastes should be stored in appropriate containers and
collected by a licensed chemical waste collector; ·
General refuse should be stored in enclosed bins
separately from construction and chemical wastes. Recycling bins should also
be placed to encourage recycling. Preferably enclosed and covered areas
should be provided for general refuse collection and routine cleaning for
these areas should also be implemented to keep areas clean. A reputable waste
collector should be employed to remove general refuse on a daily basis; ·
Good management practices for handling and
disposal of marine sediments at dedicated marine disposal sites; and ·
Regular inspection and monitoring of floating
refuse will be conducted by contractor at biweekly interval. Waste collection
by the contractor will be arranged at biweekly interval. |
·
No adverse residual impact anticipated |
Operational Phase |
|||||
The waste
transportation routes and the waste disposal site, as well as the waste
disposal outlet |
·
It is estimated that approximately 260kg of
general refuse would be generated per day; ·
It is estimated that maximum of a few hundred
litres of chemical waste would be generated per month; and ·
An estimation of 1.5m3 of floating
refuse will be accumulated and collected by the contractor. |
· Waste Disposal Ordinance (Cap. 354) ·
DEVB TCW No. 06/2010 |
·
Not applicable |
·
Reputable waste collector should be employed to
remove municipal solid waste regularly; ·
Recycling companies should be arranged to collect
the recycled waste as required; ·
Requirements given in the Code of Practice on
Packaging, Labelling and Storage of Chemical Wastes should be followed; ·
A trip-ticket system should be operated to
monitor all movements of chemical wastes, which would be collected by a
licensed collector to a licensed facility; ·
Chemical waste should be recycled as far as
possible; and ·
Regular inspection and monitoring of floating
refuse will be conducted by MD’s contractor, and waste collection and
disposal will be arranged as required. |
·
No adverse residual impact anticipated |
Land Contamination |
|||||
Construction
workers and future users within the Project |
·
15 potentially contaminated sites have
been identified. When site access is available, environmental site
investigation (SI) will be carried out to determine the extent of the
contamination, if any. |
·
EIAO-TM Section 3 (Potential Contaminated Land
Issues) of Annex 19 “Guidelines for Assessment of Impact on Sites of Cultural
Heritage and Other Impacts” ·
Guidance Note for Contaminated Land Assessment
and Remediation ·
Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management ·
Practice Guide for
Investigation and Remediation of Contaminated Land |
·
The extent of the contamination of 15 potentially
contaminated sites if any, will be determined when site access is available
and SI works will be carried out. |
·
Supplementary CAP will be submitted to EPD for
endorsement before the commencement of environmental SI; ·
Following the completion of SI and lab testing
works, a CAR would be prepared to present the findings of the SI and evaluate
the level and extent of potential contamination; ·
If potential contamination is identified and
remediation actions are required, a RAP will be prepared for submission to
EPD; and ·
A Remediation Report (RR) would also be prepared
to demonstrate that the clean-up works are adequate. |
·
No adverse residual impact anticipated |
Hazard to Life |
|||||
Construction Phase |
|||||
Population
in the vicinity of the Project |
·
The societal risk for use of explosives,
overnight storage of explosives and transport of explosives are within the
“ALARP” region; ·
The individual risk complies with the criterion
of Annex 4 of the EIAO-TM; ·
The overall societal risk lies within the “ALARP” region; and ·
Tai Lam Chung No.2 Chlorination Station will be
delisted from Potentially Hazardous Installations Register by the time when
the construction works commence and thus risk during the construction phase
is not anticipated. |
· Annex 4 of the EIAO-TM · Practice Note for Authorized Persons and
Registered Structural Engineers – Control of Blasting (APP-72) · Guidance Note No. GN 8 How to Apply for a Mode A Store
Licence for Storage of S1DG (Blasting Explosives) · Guidance Note No. GN 2 Approval of an Explosives Delivery
Vehicle ·
Guidance Note No.
GN 3 Application and Handling of a Conveyance Permit |
·
Not applicable |
·
The truck should be designed and improved to
reduce the amount of combustibles in the cabin. The fuel carried in the fuel
tank should also be minimized to reduce the duration of any fire; ·
The accident frequency of the explosive truck
should be minimized through the implementation of a defensive driving
attitude and a dedicated training programme for both driver and his attendants
which includes regular briefing sessions. Moreover, drivers should be
selected based on good safety record and provided with regular medical
checks; ·
The required quantity of explosives should only
be transported for a particular blast to avoid any unused explosives send
back to the magazine; ·
The contractor should combine the explosive
deliveries for a given work area as far as practicable; ·
A minimum headway between two consecutive truck
convoys of 10 minutes should be maintained whenever practicable; ·
To reduce the explosive truck fire involvement
frequency, a better emergency response and training should be implemented to
ensure adequate fire extinguishers are used and attempt is made to evacuate
the area of the incident or securing the explosive load if possible. All
explosive vehicles should also be equipped with bigger capacity aqueous film
forming forma (AFFF)-type extinguishers; ·
Each blasting activities including storage and
transport of explosives should be supervised and adutied by competent site
staff to ensure strict compliance with the blasting permit condition; ·
Security plan should address different alert
security level to reduce opportunity for arson or deliberate initiation of
explosives; ·
Follow good practices listed in Practice Note for
Authorized Persons and Registered Structural Engineers – Control of Blasting
(APP-72), “Guidance Note No. GN 8 How to Apply for a Mode A Licence for
Storage of Schedule 1 Dangerous Goods (Blasting Explosives)”, “Guidance Note
No. GN 2 Approval of an Explosives Delivery Vehicle” and “Guidance Note No.
GN 3 Application and Handling of a Conveyance Permit”; and ·
Formulate a Hazard Management Plan with a view to
aligning the understanding of the risk of the three projects (i.e. Route 11
(R11), Tuen Mun Bypass (TMB) and Lam Tei Underground Quarrying (LTUQ)) so
that all the working populations at Lam Tei Quarry area, which includes the
workforce induced under the construction and operational stage of three
projects, could be considered as on-site populations in the QRA for all the
three projects. The measures
stipulated in the Hazard Management Plan may include, but not limited to, the
adjustment of the blasting schedules of the three projects to minimize the
potential cumulative impact, provision of common trainings and drills to the
workforce of all the three projects, etc. The Hazard Management Plan, which
would be agreed among the three projects, would be submitted to EPD for
agreement prior to the tender invitation of construction phases of R11, TMB
and LTUQ, whichever is earlier. |
·
No adverse
residual impact anticipated |
Operational Phase |
|||||
Population
in the vicinity of the Project |
·
No potential risk identified since it does not
involve any use of explosives ·
Tai Lam Chung No.2 Chlorination Station will be
delisted from Potentially Hazardous Installations Register by the time when
the construction works commence and thus risk during the operational phase is
not anticipated |
·
Annex 4 of the EIAO-TM |
·
Not applicable |
·
No mitigation
measure is required |
·
Not applicable |
Ecology |
|||||
Construction Phase |
|||||
Ecological
resources likely to be impacted by the Project |
·
Habitat loss; o
Permanent loss of 0.16ha of backshore, 257m of
channel, 24.60ha of developed area, 17.54ha of mixed woodland, 91m of natural
coastline, 13.93ha of plantation, 4.1ha of seabed, 122m of seawall, 16.47ha
of shrubland/grassland and 164m of watercourse; and o
Temporary loss of 0.09ha of
backshore, 90m of channel, 16.85ha of developed area, 6.54ha of mixed
woodland, 298m of natural coastline 5.88ha of plantation, 13ha of sea, 49m of
seawall and 5.72ha of shrubland/grassland. ·
Harm/Mortality to species of
conservation importance/wildlife o
Potential direct impact on five flora species of
conservation importance (including Aquilaria sinensis, Diospyros
vaccinioides, Gnetum luofuense, Ixonanthes reticulata and Nepenthes
mirabilis) recorded within the aboveground works area; and o
Potential direct impact on one fauna species of
conservation importance of relatively low mobility (Hong Kong Cascade Frog). ·
Impact resulting from terrestrial and marine
habitat fragmentation; ·
Disturbance (e.g. dust, ground-borne vibration,
light glare, noise and marine traffic of works vessels) to habitats, wildlife
(including species of conservation importance), roosting grounds (especially
bat roosts inside Tai Lam Chung Catchwater Tunnel Nos. 1, 5, 6, 7 and 8) ·
Ground-borne vibration impact on roosting bats
inside Tai Lam Chung Catchwater Tunnel Nos. 1, 5, 6, 7 and 8; ·
Light glare impact; ·
Impact on quality of terrestrial waterbodies
(e.g. surface runoff) and wildlife therein and in the vicinity; ·
Groundwater infiltration/drawdown impact; ·
Impact on recognized sites of conservation
importance o
Tai Lam Country Park o
“Conservation Area” o
Siu Lang Shui Site of Special Scientific Interest ·
Impact on important habitats (i.e. Siu Lang Shui
Butterfly Habitat and Ma Wan Egretry, Day Roost and Night Roost); ·
Impact on terrestrial species of conservation
importance, other than bats inside catchwater tunnels, and marine species of
conservation importance; ·
Impact on habitats o
Agricultural land; o
Artificial shore; o
Channels other than WSD’s catchwater tunnels; o
Tai Lam Chung Catchwater Tunnel Nos. 1, 5, 6, 7
and 8; o
Developed area; o
Fung shui woodland (i.e. Li UK, Tin Hau Temple
and Ching Uk Tsuen Fung Shui Woodlands) o
Intertidal habitat (Natural coastline and
seawall) o
Mixed woodland o
Plantation; o
Reservoir; o
Sea; o
Shrubland/Grassland; and o
Watercourse (e.g. ditch and the downstream
sections of W4, W22, W23 and W24 outside TLCP). ·
Indirect marine water quality impact ·
Disturbance due to marine traffic works vessels |
·
Annex 8 and 16 of
EIAO-TM |
·
Not applicable |
·
Locate all aboveground works areas outside
recognized sites of conservation importance (such as TLCP, “Conservation
Area” and Siu Lang Shui Site of Special Scientific Interest), important
habitats (Fung Shui Woodlands in So Kwun Wat, Siu Lang Shui Butterfly Habitat
and Ma Wan Egretry, Day Roost and Night Roost) and roosting grounds (Tai Lam
Chung Catchwater Tunnel Nos. 1, 5, 6, 7 and 8) to avoid direct impact on
them; ·
Avoid reclamation in North Lantau; ·
Adopt tunnelling design if practicable (e.g.
within Tai Lam Country Park), refinement/shifting the alignment to minimize
mixed woodland loss and slope cutting, maximization of haul road extent
overlapping with the main alignment and minimize reclamation footprint in
Tsing Lung Tau to minimize habitat loss; ·
Select habitat edges as aboveground works areas,
maximize the proportion and extent of the tunnel sections and adopt
considerable length of viaduct section of the main alignment of the Project
to minimize habitat fragmentation; ·
Raise the gradient of and elevate the viaduct
above the eastern patch of Ching Uk Tsuen Fung Shui Woodland to minimize
direct injury/mortality to species of conservation importance (i.e. Ixonanthes
reticulata); ·
Provide a 7-metre gap between the viaduct above
the eastern patch of Ching Uk Tsuen Fung Shui Woodland to minimize shading
impact on it; ·
Direct artificial lighting towards areas with
necessity of lighting only and away from natural habitats at and immediately
outside TLCP to minimize glare impact; ·
Adopt the mitigation measures listed in Section 5
of EIA report to minimize water quality impacts; ·
Adopt good site practice (e.g. confine works
within construction site boundary) to minimize indirect disturbance; ·
Adopt mitigation measures listed in Section 5 of
EIA report to minimize groundwater infiltration and site runoff; ·
Maximize distance between the tunnelling works
and the bat roosting grounds; ·
Control charge weight and continuous monitoring
on ground-borne vibration at Tai Lam Chung Catchwater Tunnel Nos. 1, 5, 6, 7
and 8 and conduct ecological monitoring on the bat roost usage and bats to
minimize disturbance to roosting bats; ·
Conduct continuous adaptive review on the
alert, action and limit levels of ground-borne
vibration based on the ground-borne vibration and bat roost monitoring
results to be collected during the pre-blasting and blasting phases; ·
Suspend blasting works and adopt remedial action
including the use of alternative tunnelling method; ·
Divert potentially impacted section of
watercourses falling within the aboveground works area and adopt green
channel design where applicable; ·
Conduct compensatory woodland planting to
mitigate the area of mixed woodland to be permanently lost and temporarily
lost, the feasibility of reinstatement of the latter should be confirmed
during the detailed design phase in advance; ·
Conduct pre-construction detailed vegetation
survey, submit a detailed transplantation plan for the flora species of
conservation importance anticipated to be directly impacted, including but
not limited to Aquilaria sinensis, Diospyros
vaccinioides, Gnetum luofuense, Ixonanthes reticulata and
Nepenthes mirabilis, at detailed design stage and conduct
preservation/transplantation of plant of species of conservation importance
if feasible; ·
Conduct pre-construction survey of aquatic and
water-dependent fauna species of conservation importance at one ditch and
section of watercourses to be directly impacted (e.g. W4, W22, W23 and W24),
including but not limited to Hong Kong Cascade Frog, and submit translocation
plan and conduct translocation of aquatic and water-dependent fauna species
of conservation importance where necessary; ·
Conduct detailed reconnaissance dive survey to
inspect if there are any additional colonies of hard and/or soft coral
species, assess the effectiveness and feasibility of coral translocation if
there are significant colonies, and prepare translocation plan if confirmed
translocation is necessary; ·
Enhance the seawall with ecological features to
increase the overall ecological value, integrity and complexity; and ·
Monitoring of the
effectiveness of the mitigation measures on groundwater infiltration. |
·
No adverse
residual impact is anticipated |
Operational Phase |
|||||
Ecological resources likely to be
impacted by the Project |
·
Disturbance (noise, ground-borne
vibration and light glare) impact; ·
Terrestrial and marine habitat
fragmentation impact; ·
Light glare impact; ·
Barrier effect to the flight-lines of and loss of
foraging habitats of ardeids; ·
Roadkill and bird collision impacts; ·
Adverse water quality impact on terrestrial and
marine habitats; ·
Shading effect on the eastern patch of Ching Uk
Tsuen Fung Shui Woodland; ·
Air-borne noise and ground-borne vibration caused
by moving vehicles; ·
Impact on recognized sites of conservation
importance, important habitats, roosting grounds and terrestrial species of
conservation importance other than cave-dwelling bats inside catchwater
tunnels: o
Tai Lam Country Park; o
“Conservation Area”; o
Fung shui wood in So Kwun Wat; o
Siu Lang Shui Butterfly Habitat; o
Ma Wan Egretry, Day Roost and Night Roost; o
Terrestrial species of conservation importance
other than cave-dwelling bats inside catchwater tunnels; and o
Marine species of conservation importance (i.e.,
corals) ·
Impact on marine hydrological regime; ·
Spillage of chemicals/pollutants; and ·
Impact due to increased marine traffic. |
·
Annex 8 and 16 of
EIAO-TM |
·
Not applicable |
·
Upon all blasting works are completed,
ground-borne vibration monitoring, acoustics survey, emergence survey, and
bat roost survey will be conducted at Tai Lam Chung Catchwater Tunnel Nos. 1,
5, 6, 7 and 8 for at least 9 months, following the same method and frequency
as the baseline monitoring. In addition, within one year from the
commencement of the operational phase, monitoring on ground-borne vibration
and roosting bats will be conducted for TLC Catchwater Tunnel Nos. 1, 5, 6, 7
and 8 for at least 9 months, covering overwintering, breeding season and time
gap between overwintering and breeding season of bats; ·
Direct artificial lighting towards areas with
necessity of lighting only and away from natural habitats to minimize light
glare impact; ·
Adopt mitigation measures in Section 5 of EIA
report to mitigate water quality impact; ·
Monitoring of compensatory woodland; ·
Monitoring of flora species of conservation
importance to be preserved, transplanted and/or compensated, if
transplantation and/or compensatory planting is/are confirmed necessary; ·
Monitoring of aquatic and/or water-dependent
fauna species of conservation importance (e.g. Hong Kong Cascade Frog) to be
translocated, if translocation is necessary; ·
Adopt tinted materials and superimposing dark
patterns or strips on noise barriers to minimize risk of potential bird
collision with noise barriers; and ·
Monitoring of the
effectiveness of the mitigation measures on groundwater infiltration |
·
No adverse
residual impact is anticipated. |
Fisheries |
|||||
Construction Phase |
|||||
Fisheries
resources and habitats likely to be impacted by the Project |
·
Permanent loss of 4.1ha of fishing ground due to
reclamation and temporary loss of 13ha fishing ground; ·
Indirect impact
on marine works required for the reclamation of landing area for Tsing Lung
Tau including dredging and filling activities; and ·
Indirect impacts
on underwater noise. |
·
EIAO-TM Annex 9 and
Annex 17 |
·
Not applicable |
·
Follow mitigation measures, good practices and
guidelines to minimise water quality impacts. |
·
No adverse
residual impact anticipated |
Operational Phase |
|||||
Fisheries
resources and habitats likely to be impacted by the Project |
·
Permanent
loss of 4.1ha fishing ground due to 2.2ha reclamation; and ·
No adverse fisheries impact on change of
hydrodynamics and deterioration of water quality induced by the reclamation
site for Tsing Lung Tau for Tsing Lung Bridge is identified |
·
EIAO-TM Annex 9 and Annex 17 |
·
Not applicable |
·
No specific mitigation
measure is required |
·
Not applicable |
Landscape and Visual
Impact |
|||||
Construction Phase |
|||||
Existing
Trees, Landscape Resources (LRs) and Landscape Character Areas (LCAs) and
Visually Sensitive Receivers (VSRs) |
·
Sources of impact include construction works,
temporary works and night-time lighting; ·
Around 5,085 of existing trees within the 100m
landscape assessment area will be felled; ·
Substantial adverse impacts on LRs including
LR-LT1 Secondary Woodlands in Lam Tei, LR-SK1 Secondary Woodlands in So Kwun
Wat, LR-SK2 Plantations in So Kwun Wat, LR-SK4 Shrublands in So Kwun Wat,
LR-NL4 Shrublands in North Lantau; ·
Moderate adverse impacts on LRs including LR-LT2
Plantations in Lam Tei, LR-LT11 Developed Areas in Lam Tei, LR-TL2
Plantations / Mixed Woodlands in Tsing Lung Tau, LR- TL11 Developed Areas in
Tsing Lung Tau, LR-TL12 Carriageway and Roadside planter at Tsing Lung Tau,
LR-NL1 Secondary Woodlands in North Lantau, LR-NL2 Plantations in North
Lantau, LR-NL10 Seawater Body and Shorelines at Ha Pang Fairway, LR-NL11
Developed Areas in North Lantau, LR-NL12 Carriageway and Roadside Planter in
North Lantau; ·
Slight adverse impacts on LRs including LR-SK11
Developed Areas in So Kwun Wat,
LR-SK12 Carriageway and Roadside Planter in So Kwun Wat; ·
Insubstantial adverse impacts on LRs including
LR-LT7 Watercourses in Lam Tei, LR-SK7 Watercourses in So Kwun Wat, LR-TL1
Secondary Woodlands in Tsing Lung Tau, LR-TL4 Shrublands in Tsing Lung Tau,
LR-TL7 Watercourses in Tsing Lung Tau, LR-NL7 Watercourses in North Lantau; ·
Substantial adverse impacts on LCAs including
LCA-SK4 Tai Lam Country Park Upland Landscape, LCA-SK6 Siu Lam and Tai Lam
Chung Foothill Landscape, LCA-NL9 Ng Kwu Leng Peninsular Landscape; ·
Moderate adverse impacts on LCAs including
LCA-LT1 Lam Tei Rural Fringe Landscape, LCA-LT3 Lam Tei Rural Landscape,
LCA-SK3 So Kwun Wat Village Landscape, LCA-SK5 Tuen Mun Road Urban Corridor
Landscape, LCA-SK7 Tai Lam Chung River Valley Landscape, LCA-TL5 Tsing Lung
Tau Urban Landscape, LCA-NL8 Ha Pang Fairway Maritime Landscape, LCA-NL10
North Lantau Highway Corridor Landscape; ·
Slight adverse impacts on LCAs including LCA-LT2
Lam Tei Upland Fringe Landscape; ·
Insubstantial adverse impacts on LCAs including
LCA-LT4 Lam Tei Upland Landscape, LCA-TL6 To Hang Tung Foothill Landscape, LCA-NL4
North Lantau Fa Peng Teng Upland Landscape; ·
Substantial adverse impacts on VSRs including
Residents of VSR-LT3 Lo Fu Hang, VSR-LT5 Residents of Fuk Hang Tsuen, VSR-LT6
Residents of The Sherwood, VSR-LT8 Residents of Tsoi Yuen Tsuen, VSR-LT11
Future Residents of Potential Residential Development at Brownfield Clusters
in Lam Tei North and Nai Wai, VSR-SK1 Trail Walkers on MacLehose Trail
Section 10 (West), VSR-SK3 Residents of The Bloomsway, VSR-SK4 Students and
Staff at Harrow International School Hong Kong, VSR-SK6 Residents of Aegean
Coast, VSR-SK9 Trail Walkers on MacLehose Trail Section 10 (East), VSR-SK10
Residents of So Kwun Wat Tsuen, VSR-SK11 Residents of So Kwun Wat San Tsuen,
VSR-SK12 Visitors to Glorious Praise Fellowship (Hong Kong) Treatment Centre,
VSR-SK14 Trail Walkers on Tai Lam Chung Reservoir Subsidiary Dam at Siu Lam
Road, VSR-SK15 Residents of Palatial Coast, VSR-SK16 Residents of Siu Lam,
VSR-SK21 Trail Walkers and Cyclists on Tai Lam Chung Reservoir Main Dam, VSR-SK22
Pedestrians on Footbridge over Tai Lam Chung River, VSR-SK24 Trail Walkers on
Summit of Hill 141, VSR-SK29 Residents of Tai Lam Chung Tsuen, VSR-TL3
Residents of Hong Kong Garden, Vista
Cove and L'Aquatique; ·
Moderate or Substantial adverse impacts on VSRs
including VSR-LT1 Residents of Parkland Villas, VSR-LT2 Residents of Fu Tai
Estate, VSR-SK5 Residents of Hong Kong Gold Coast; ·
Moderate adverse impacts on VSRs including VSR-LT7 Vehicle
Travellers on Kong Sham Western Highway (Southbound), VSR-SK7 Residents of
Avignon, VSR-SK27 Students and Staff at PLK Women's Welfare Club Western
District Fung Lee Pui Yiu Primary School and S.T.F.A. Lee Kam Primary School,
VSR-SK8 Vehicle Travellers and Pedestrians on So Kwun Wat Tsuen Road,
VSR-SK13 Vehicle Travellers on Siu Lam Road, VSR-SK23 Vehicle Travellers and
Pedestrians on Castle Peak Road – Tai Lam, VSR-SK25 Trail Walkers at South of
To Hang Tung, VSR-SK30 Students and Staff at Hong Kong Customs College,
VSR-SK31 Staff and Visitors at Tai Lam Correctional Institution, VSR-TL2 Residents of Bellagio and Ocean Pointe, VSR-TL4
Vehicle Travellers and Pedestrians on Castle Peak Road – Tsing Lung Tau
(Eastbound), VSR-TL5 Vehicle Travellers on Tuen Mun Road (Eastbound),
VSR-TL11 Pedestrians on Footbridge across Castle Peak Road – Tsing Lung Tau,
VSR-TL12 Travellers in Tsing Lung Tau Ferry Pier, VSR-TL13 Travellers in Sham
Tseng Public Pier, VSR-TL14 Residents of Sea Crest Villa Phase 4, VSR-NL1 Vehicle Travellers on North Lantau Highway
(Westbound), VSR-NL2 Trail Walkers on
Summit of Fa Peng Teng, VSR-NL3 Vehicle Travellers at Lantau Link Toll Plaza,
VSR-NL4 Travellers in Ma Wan Public Pier, VSR-NL5 Vehicular Travellers on Kap
Shui Mun Bridge, VSR-NL6 Visitors at Sunny Bay Promenade, VSR-NL7 Maritime
Travellers in Ha Pang Fairway, VSR-NL8 Residents of
Park Island, VSR-NL9 Future Users at Planned Sunny Bay
Reclamation Area; ·
Slight or Moderate adverse impacts on VSRs
including
VSR-LT4 Vehicle
Travellers on Yuen Long Highway (Eastbound), VSR-LT9 Vehicle Travellers on
Yuen Long Highway (Westbound); ·
Slight adverse impacts on VSRs including VSR-SK2 Vehicle
Travellers on Tuen Mun Road, VSR-SK26 Vehicle Travellers on Castle Peak Road
– So Kwun Wat, VSR-SK28 Students and Staff at Chu Hai College of Higher
Education, VSR-TL1 Vehicle Travellers on Tuen Mun Road (Westbound), VSR-NL10
Future Vehicle Travellers on Planned Road P1; and ·
Insubstantial adverse impacts on VSRs including VSR-LT10 Trail
Walkers on Fu Tei Country Trail and Lam Tei Irrigation Reservoir . |
·
TM-EIAO Annexes 3, 10, 11, 18, 20 and 21 ·
EIAO (Cap. 499. S16) and EIAO-TM Annexes 3, 10,
11, 18, 20 and 21 ·
EIAO Guidance Note 8/2010 Preparation of
Landscape and Visual Impact Assessment ·
HKPSG Chapters 4, 10 and 11 ·
Protection of Endangered Species of Animals and
Plants Ordinance (Cap.586) ·
Town Planning Ordinance and Town Planning
(Amendment) Ordinance (Cap. 131) ·
Country Parks Ordinance (Cap. 208) ·
The Forests and Countryside Ordinance (Cap. 96) –
Prohibiting the Felling, Cutting, Burning or Destruction of Tress, Growing
Plants and Forests on Government Land ·
ETWB TC(W) No. 5/2020 –
Registration and Preservation of Old and Valuable Trees |
·
Not applicable |
·
Tree preservation; ·
Tree transplanting; ·
Works Area and Temporary Works Areas; ·
Advance Implementation of Mitigation Planting; ·
Decorative Screen Hoarding; ·
Compensatory planting proposal should have the
basic primary objective of planting compensatory trees in a ratio not less
than 1:1 in terms of quantity as far as practicable; ·
Landscape reinstatement; ·
Lighting control; ·
Erection of screen hoarding; and ·
Optimisation of construction areas. |
·
Residual impacts are considered acceptable; ·
Substantial adverse impacts on LRs including
LR-NL4 Shrublands in North Lantau; ·
Moderate adverse impacts on LRs including LR-LT1
Secondary Woodlands in Lam Tei, LR-LT2 Plantations in Lam Tei, LR-SK1
Secondary Woodlands in So Kwun Wat, LR-SK2 Plantations in So Kwun Wat, LR-SK4
Shrublands in So Kwun Wat, LR-TL2
Plantations / Mixed Woodlands in Tsing Lung Tau, LR-TL12 Carriageway
and roadside planter in Tsing Lung Tau, LR-NL2 Plantations in North Lantau,
LR-NL12 Carriageway and roadside planter in North Lantau; ·
Slight adverse impacts on LRs including LR-LT11
Developed Areas in Lam Tei, LR-SK11 Developed Areas in So Kwun Wat, LR-SK12
Carriageway and roadside planter in So Kwun Wat, LR-TL11 Developed Areas in
Tsing Lung Tau, LR-NL1 Secondary Woodlands in North Lantau, LR-NL10 Seawater
Body and Shorelines at Ha Pang Fairway, LR-NL11 Developed Areas in North
Lantau; ·
Insubstantial adverse impacts on LRs including
LR-LT7 Watercourses in Lam Tei, LR-SK7 Watercourses in So Kwun Wat, LR-TL1
Secondary Woodlands in Tsing Lung Tau, LR-TL4 Shrublands in Tsing Lung Tau,
LR-TL7 Watercourses in Tsing Lung Tau, LR-NL7 Watercourses in North Lantau; ·
Substantial adverse impacts on LRs including
LR-NL4 Shrublands in North Lantau; ·
Moderate adverse impacts on LCAs including
LCA-LT3 Lam Tei Rural Landscape, LCA-SK4 Tai Lam Country Park Upland
Landscape, LCA-SK6 Siu Lam and Tai Lam Chung Foothill Landscape, LCA-SK7 Tai
Lam Chung River Valley Landscape; ·
Slight adverse impacts on LCAs including LCA-LT1
Lam Tei Rural Fringe Landscape, LCA-LT2 Lam Tei Upland Fringe Landscape,
LCA-SK3 So Kwun Wat Village Landscape, LCA-SK5 Tuen Mun Road Urban Corridor
Landscape, LCA-TL5 Tsing Lung Tau Urban Landscape, LCA-NL8 Ha Pang Fairway
Maritime Landscape, LCA-NL10 North Lantau Highway Corridor Landscape; ·
Substantial adverse impacts for LCAs including
LCA-NL9
Ng Kwu Leng
Peninsular Landscape; ·
Insubstantial adverse impacts on LCAs including
LCA-LT4 Lam Tei Upland Landscape, LCA-TL6 To Hang Tung Foothill Landscape,
LCA-NL4 North Lantau Fa Peng Teng Upland Landscape; ·
Substantial adverse impacts for VSR-LT1 Residents
of Parkland Villas, VSR-LT2 Residents of Fu Tai Estate, VSR-LT3 Residents of
Lo Fu Hang, VSR-LT6 Residents of The Sherwood, VSR-LT5 Residents of Fuk Hang
Tsuen , VSR-LT8 Residents of Tsoi Yuen Tsuen, VSR-SK9 Trail Walkers on
MacLehose Trail Section 10 (East), VSR-SK10 Residents of So Kwun Wat Tsuen,
VSR-SK11 Residents of So Kwun Wat San Tsuen, VSR-SK15 Residents of Palatial
Coast, VSR-SK16 Residents of Siu Lam, VSR-SK21 Trail Walkers and Cyclists on
Tai Lam Chung Reservoir Main Dam, VSR-SK22 Pedestrians on Footbridge over Tai
Lam Chung River, VSR-TL3 Residents of Hong Kong Garden, and Vista Cove and
L'Aquatique; ·
Moderate adverse impacts on VSRs including
VSR-LT7 Vehicle Travellers on Kong Sham Western Highway (Southbound), VSR-LT9
Vehicle Travellers on Yuen Long Highway (Westbound), VSR-LT11 Future
Residents of Potential Residential Development at Brownfield Clusters in Lam
Tei North and Nai Wai, VSR-SK1 Trail Walkers on MacLehose Trail Section 10 (West),
VSR-SK3 Residents of The Bloomsway, VSR-SK4 Students and Staff at Harrow
International School Hong Kong, VSR-SK5 Residents of Hong Kong Gold Coast,
VSR-SK6 Residents of Aegean Coast, VSR-SK7 Residents of Avignon, VSR-SK8
Vehicle Travellers and Pedestrians on So Kwun Wat Tsuen Road, VSR-SK12
Visitors to Glorious Praise Fellowship (Hong Kong) Treatment Centre, VSR-SK13
Vehicle Travellers on Siu Lam Road, VSR-SK14 Trail Walkers on Tai Lam Chung
Reservoir Subsidiary Dam at Siu Lam Road, VSR-SK23 Vehicle Travellers and
Pedestrians on Castle Peak Road – Tai Lam, VSR-SK24 Trail Walkers on Summit
of Hill 141, VSR-SK25 Trail Walkers at South of To Hang Tung, VSR-SK29
Residents of Tai Lam Chung Tsuen, VSR-SK30 Students and Staff at Hong Kong
Customs College, VSR-SK31 Staff and Visitors at Tai Lam Correctional
Institution, VSR-TL2 Residents of Bellagio and Ocean Pointe, VSR-TL4 Vehicle
Travellers and Pedestrians on Castle Peak Road – Tsing Lung Tau (Eastbound),
VSR-TL5 Vehicle Travellers on Tuen Mun Road (Eastbound), VSR-TL13 Travellers
in Sham Tseng Public Pier, VSR-TL14 Residents of Sea Crest Villa Phase 4,
VSR-NL1 Vehicle Travellers on North Lantau Highway (Westbound), VSR-NL2 Trail
Walkers on Summit of Fa Peng Teng, VSR-NL3 Vehicle Travellers at Lantau Link
Toll Plaza, VSR-NL5 Vehicular Travellers on Kap Shui Mun Bridge, VSR-NL6
Visitors at Sunny Bay Promenade, VSR-NL7 maritime
travellers in Ha Pang Fairway , VSR-NL8 Residents of Park Island,
VSR-NL9 Future Users at Planned Sunny Bay Reclamation Area; ·
Slight adverse impacts on VSRs including VSR-LT4 Vehicle
Travellers on Yuen Long Highway (Eastbound), VSR-SK2 Vehicle
Travellers on Tuen Mun Road, VSR-SK26 Vehicle
Travellers on Castle Peak Road – So Kwun Wat, VSR-SK27 Students and
Staff at PLK Women's Welfare Club Western District Fung Lee Pui Yiu Primary
School and S.T.F.A. Lee Kam Primary School, VSR-SK28 Students and
Staff at Chu Hai College of Higher Education, VSR-TL1 Vehicle
Travellers on Tuen Mun Road (Westbound), VSR-TL11 Pedestrians on
Footbridge across Castle Peak Road – Tsing Lung Tau, VSR-TL12 Travellers in
Tsing Lung Tau Ferry Pier, VSR-NL4 Travellers in Ma Wan Public Pier, VSR-NL10 Future Vehicle
Travellers on Planned Road P1, and ·
Insubstantial adverse impacts on VSRs including VSR-LT10 Trail
Walkers on Fu Tei Country Trail and Lam Tei Irrigation Reservoir. |
Operational Phase |
|||||
Existing
Trees, Landscape Resources (LRs) and Landscape Character Areas (LCAs) and
Visually Sensitive Receivers (VSRs) |
·
Substantial adverse impacts on LRs including
LR-LT1 Secondary Woodlands in Lam Tei, LR-SK1 Secondary Woodlands in So Kwun
Wat, LR-SK2 Plantations in So Kwun Wat, LR-SK4 Shrublands in So Kwun Wat,
LR-NL4 Shrublands in North Lantau; ·
Moderate adverse impacts on LRs including LR-LT2
Plantations in Lam Tei, LR-LT11 Developed Areas in Lam Tei, LR-TL2
Plantations / Mixed Woodlands in Tsing Lung Tau, LR-TL11 Developed Areas in
Tsing Lung Tau, LR-TL12 Carriageway and roadside planter in Tsing Lung Tau,
LR-NL1 Secondary Woodlands in North Lantau, LR-NL2 Plantations in North
Lantau, LR-NL10 Seawater Body
and Shorelines at Ha Pang Fairway, LR-NL11 Developed Areas in North Lantau,
LR-NL12 Carriageway and roadside planter in North Lantau; ·
Slight adverse impacts on LRs including LR-SK11
Developed Areas in So Kwun Wat, LR-SK12 Carriageway and roadside planter in
So Kwun Wat; ·
Insubstantial adverse impacts on LRs including
LR-LT7 Watercourses in Lam Tei, LR-SK7 Watercourses in So Kwun Wat, LR-TL1
Secondary Woodlands in Tsing Lung Tau, LR-TL4 Shrublands in Tsing Lung Tau,
LR-TL7 Watercourses in Tsing Lung Tau, LR-NL7 Watercourses in North Lantau; ·
Substantial adverse impacts on LCAs including
LCA-SK4 Tai Lam Country Park Upland Landscape, LCA-SK6 Siu Lam and Tai Lam
Chung Foothill Landscape, LCA-NL9 Ng Kwu Leng Peninsular Landscape; ·
Moderate adverse impacts on LCAs including
LCA-LT1 Lam Tei Rural Fringe Landscape, LCA-LT3 Lam Tei Rural Landscape,
LCA-SK3 So Kwun Wat Village Landscape, LCA-SK5 Tuen Mun Road Urban Corridor
Landscape, LCA-SK7 Tai Lam Chung River Valley Landscape, LCA-TL5 Tsing Lung
Tau Urban Landscape, LCA-NL8 Ha Pang Fairway Maritime Landscape, LCA-NL10 North
Lantau Highway Corridor Landscape; ·
Slight adverse impacts on LCAs including LCA-LT2
Lam Tei Upland Fringe landscape ; ·
Insubstantial adverse impacts on LCAs including
LCA-LT4 Lam Tei Upland Landscape, LCA-TL6 To Hang Tung Foothill Landscape,
LCA-NL4 North Lantau Fa Peng Teng Upland Landscape; ·
Substantial adverse impacts on VSRs including Residents of
VSR-LT3 Lo Fu Hang, VSR-LT5 Residents of Fuk Hang Tsuen, VSR-LT6 Residents of
The Sherwood, VSR-LT8 Residents of Tsoi Yuen Tsuen, VSR-SK1 Trail Walkers on
MacLehose Trail Section 10 (West), VSR-SK9 Trail Walkers on
MacLehose Trail Section 10 (East), VSR-SK11 Residents of So
Kwun Wat San Tsuen, VSR-SK15 Residents of Palatial Coast, VSR-SK16 Residents
of Siu Lam, VSR-SK21 Trail Walkers and Cyclists on Tai Lam Chung Reservoir
Main Dam, VSR-SK22 Pedestrians on Footbridge over Tai Lam Chung River,
VSR-TL3 Residents of Hong Kong Garden, Vista Cove and L'Aquatique; ·
Moderate or Substantial adverse impacts on VSRs
including VSR-LT1 Residents of Parkland Villas, VSR-LT2 Residents of Fu Tai
Estate, VSR-LT11 Future Residents of Potential Residential Development at
Brownfield Clusters in Lam Tei North and Nai Wai, VSR-SK3 Residents of The
Bloomsway, VSR-SK4 Students and Staff at Harrow International School Hong
Kong, VSR-SK6 Residents of Aegean Coast, VSR-SK10 Residents of So Kwun Wat
Tsuen; ·
Moderate adverse impacts on VSRs including VSR-LT7 Vehicle
Travellers on Kong Sham Western Highway (Southbound), VSR-SK8 Vehicle
Travellers and Pedestrians on So Kwun Wat Tsuen Road, VSR-SK12 Visitors to
Glorious Praise Fellowship (Hong Kong) Treatment Centre, VSR-SK14 Trail
Walkers on Tai Lam Chung Reservoir Subsidiary Dam at Siu Lam Road, VSR-SK23
Vehicle Travellers and Pedestrians on Castle Peak Road – Tai Lam, VSR-SK24
Trail Walkers on Summit of Hill 141, VSR-SK25 Trail Walkers at South of To
Hang Tung, VSR-SK29 Residents of Tai Lam Chung Tsuen, VSR-SK30 Students and
Staff at Hong Kong Customs College, VSR-SK31 Staff and Visitors at Tai Lam
Correctional Institution, VSR-TL2 Residents of Bellagio and Ocean Pointe, VSR-TL4
Vehicle Travellers and Pedestrians on Castle Peak Road – Tsing Lung Tau
(Eastbound), VSR-TL5 Vehicle Travellers on Tuen Mun Road (Eastbound),
VSR-TL11 Pedestrians on Footbridge across Castle Peak Road – Tsing Lung Tau, VSR-TL12
Travellers in Tsing Lung Tau Ferry Pier, VSR-TL13 Travellers in Sham Tseng
Public Pier, VSR-TL14 Residents of Sea Crest Villa Phase 4, VSR-NL1 Vehicle
Travellers on North Lantau Highway (Westbound), VSR-NL2 Trail Walkers on
Summit of Fa Peng Teng, VSR-NL3 Vehicle Travellers at Lantau Link Toll Plaza,
VSR-NL4 Travellers in Ma Wan Public Pier, VSR-NL5 Vehicular Travellers on Kap
Shui Mun Bridge, VSR-NL6 Visitors at Sunny Bay Promenade, VSR-NL7 Maritime
Travellers in Ha Pang Fairway, VSR-NL8 Residents of
Park Island, VSR-NL9 Future Users at
Planned Sunny Bay Reclamation Area; ·
Slight or Moderate adverse impacts on VSRs
including
VSR-SK5
Residents of Hong Kong Gold Coast, VSR-SK13 Vehicle Travellers on Siu Lam
Road; ·
Slight adverse impacts on VSRs including VSR-SK2 Vehicle
Travellers on Tuen Mun Road, VSR-SK7 Residents of Avignon, VSR-SK26 Vehicle
Travellers on Castle Peak Road – So Kwun Wat, VSR-SK27 Students and Staff at
PLK Women's Welfare Club Western District Fung Lee Pui Yiu Primary School and
S.T.F.A. Lee Kam Primary School, VSR-SK28 Students and Staff at Chu Hai
College of Higher Education, VSR-TL1 Vehicle Travellers on Tuen Mun Road
(Westbound), VSR-NL10 Future Vehicle Travellers on Planned Road P1; ·
Insubstantial or Slight adverse impacts on VSRs
including
VSR-LT4 Vehicle
Travellers on Yuen Long Highway (Eastbound), VSR-LT9 Vehicle Travellers on
Yuen Long Highway (Westbound); and ·
Insubstantial adverse impacts on VSRs including VSR-LT10 Trail
Walkers on Fu Tei Country Trail and Lam Tei Irrigation Reservoir. |
·
TM-EIAO Annexes 3, 10, 11, 18, 20 and 21 ·
EIAO Guidance Note 8/2010 Preparation of
Landscape and Visual Impact Assessment ·
HKPSG Chapters 4 and 10 ·
Protection of Endangered Species of Animals and
Plants Ordinance (Cap.586) ·
ETWB TC(W) No. 29/2004 – Registration of Old and
Valuable Trees, and Guidelines for their Preservation ·
Land Administration
Office, Lands Department Practice Note Nos. 7/2007 and 7/2007A Tree
Preservation and Tree Removal Application for Building Development in Private
Projects |
·
Not applicable |
·
Integrated
Design Approach; ·
Roadside Buffer
Planting / Roadside Planting; ·
Compensatory
Planting Proposals; ·
Post-Planting
Monitoring; ·
Greening Works
on Slopes and Associated Structures; ·
Design of Tunnel
Portals and Landscape Treatment; ·
Design of an
Elegant Bridge Structure and Approach Road; ·
Provision of
Visually Pleasing Aesthetic Treatment of Noise Mitigation Measures; and ·
Provision of
Green Roof. |
·
Residual impacts are considered acceptable; ·
Moderate adverse impacts on LRs LR-SK1 including
Secondary Woodlands in So Kwun Wat, LR-NL4
Shrublands in North Lantau; and ·
Slight adverse impacts on LRs including LR-LT1
Secondary Woodlands in Lam Tei, LR-LT2 Plantations in Lam Tei, LR-SK2
Plantations in So Kwun Wat, LR-SK4 Shrublands in So Kwun Wat, LR-TL2
Plantations / Mixed Woodlands in Tsing Lung Tau, LR-NL2 Plantations in North
Lantau; ·
Insubstantial adverse impacts on LRs including Watercourses in
LR-LT7 Lam Tei, LR-LT11 Developed Areas in Lam Tei, LR-SK7 Watercourses in So
Kwun Wat, LR-SK11 Developed Areas in So Kwun Wat, LR-SK12 Carriageway and
roadside planter in So Kwun Wat, LR-TL1 Secondary Woodlands in Tsing Lung
Tau, LR-TL4 Shrublands in Tsing Lung Tau, LR-TL7 Watercourses in Tsing Lung
Tau, LR-TL11 Developed Areas in Tsing Lung Tau, LR-TL12 Carriageway and
roadside planter in Tsing Lung Tau, LR-NL1 Secondary Woodlands in North
Lantau, LR-NL7 Watercourses in North Lantau, LR-NL10 Seawater Body and
Shorelines at Ha Pang Fairway, LR-NL11 Developed Areas in North Lantau,
LR-NL12 Carriageway and roadside planter in North Lantau; ·
Moderate adverse impacts on LCAs including
LCA-NL9 Ng Kwu Leng Peninsular Landscape; ·
Slight adverse impacts on LCAs including
LCA-LT3 Lam Tei Rural Landscape,
LCA-SK4 Tai Lam Country Park Upland Landscape, LCA-SK6 Siu Lam and Tai Lam
Chung Foothill Landscape, LCA-SK7 Tai Lam Chung River Valley Landscape; ·
Insubstantial adverse impacts on LCAs including LCA-LT1 Lam Tei
Rural Fringe Landscape, LCA-LT2 Lam Tei Upland Fringe Landscape, LCA-LT4 Lam
Tei Upland Landscape, LCA-SK3 So Kwun Wat Village Landscape, LCA-SK5 Tuen Mun
Road Urban Corridor Landscape, LCA-TL5 Tsing Lung Tau Urban Landscape,
LCA-TL6 To Hang Tung Foothill Landscape, LCA-NL4 North Lantau Fa Peng Teng
Upland Landscape, LCA-NL8 Ha Pang Fairway Maritime Landscape, LCA-NL10 North
Lantau Highway Corridor Landscape; ·
Moderate adverse impacts for VSR-LT2 Residents
of Fu Tai Estate, VSR-LT3 Residents of Lo Fu Hang, VSR-LT6 Residents of The
Sherwood, VSR-LT8 Residents of Tsoi Yuen Tsuen, VSR-LT11 Future Residents of
Potential Residential Development at Brownfield Clusters in Lam Tei North and
Nai Wai, VSR-SK1 Trail Walkers on MacLehose Trail Section 10 (West), VSR-SK3
Residents of The Bloomsway, VSR-SK4 Students and Staff at Harrow
International School Hong Kong, VSR-SK6 Residents of Aegean Coast, VSR-LT5
Residents of Fuk Hang Tsuen, VSR-SK8 Vehicle Travellers and Pedestrians on So
Kwun Wat Tsuen Road, VSR-SK9 Trail Walkers on MacLehose Trail Section 10
(East), VSR-SK10 Residents of So Kwun Wat Tsuen, VSR-SK11 Residents of So
Kwun Wat San Tsuen, VSR-SK12 Visitors to Glorious Praise Fellowship (Hong
Kong) Treatment Centre, VSR-SK13 Vehicle Travellers on Siu Lam Road, VSR-SK15
Residents of Palatial Coast, VSR-SK16 Residents of Siu Lam, VSR-SK21 Trail
Walkers and Cyclists on Tai Lam Chung Reservoir Main Dam, VSR-SK22
Pedestrians on Footbridge over Tai Lam Chung River, VSR-SK24 Trail Walkers on
Summit of Hill 141, VSR-SK29 Residents of Tai Lam Chung Tsuen, VSR-TL3
Residents of Hong Kong Garden, Vista Cove and L'Aquatique, VSR-NL2 Trail
Walkers on Summit of Fa Peng Teng; ·
Slight adverse impacts
for VSR-LT1 Residents of Parkland Villas, VSR-LT4 Vehicle Travellers on Yuen
Long Highway (Eastbound), VSR-LT7 Vehicle Travellers on Kong Sham Western
Highway (Southbound), VSR-LT9 Vehicle Travellers on Yuen Long Highway
(Westbound), VSR-SK2 Vehicle Travellers on Tuen Mun Road, VSR-SK5 Residents
of Hong Kong Gold Coast, VSR-SK7 Residents of Avignon, VSR-SK14 Trail Walkers
on Tai Lam Chung Reservoir Subsidiary Dam at Siu Lam Road, VSR-SK26 Vehicle
Travellers on Castle Peak Road – So Kwun Wat, VSR-SK27 Students and Staff at
PLK Women's Welfare Club Western District Fung Lee Pui Yiu Primary School and
S.T.F.A. Lee Kam Primary School, VSR-SK23 Vehicle Travellers and Pedestrians
on Castle Peak Road – Tai Lam, VSR-SK25 Trail Walkers at South of To Hang
Tung, VSR-SK30 Students and Staff at Hong Kong Customs College, VSR-SK31
Staff and Visitors at Tai Lam Correctional Institution, VSR-TL1 Vehicle
Travellers on Tuen Mun Road (Westbound), VSR-TL2 Residents of Bellagio and
Ocean Pointe, VSR-TL4 Vehicle Travellers and Pedestrians on Castle Peak Road
– Tsing Lung Tau (Eastbound), VSR-TL5 Vehicle Travellers on Tuen Mun Road
(Eastbound), VSR-TL11 Pedestrians on Footbridge across Castle Peak Road –
Tsing Lung Tau, VSR-TL12 Travellers in Tsing Lung Tau Ferry Pier, VSR-TL13
Travellers in Sham Tseng Public Pier, VSR-TL14 Residents of Sea Crest Villa
Phase 4, VSR-NL1 Vehicle Travellers on North Lantau Highway (Westbound),
VSR-NL3 Vehicle Travellers at Lantau Link Toll Plaza, VSR-NL4 Travellers in
Ma Wan Public Pier, VSR-NL5 Vehicular Travellers on Kap Shui Mun Bridge,
VSR-NL6 Visitors at Sunny Bay Promenade, VSR-NL7 Maritime Travellers in Ha
Pang Fairway, VSR-NL8 Residents of
Park Island, VSR-NL9 Future Users at Planned Sunny Bay Reclamation Area; and ·
Insubstantial residual impact
in Year 10 of the operational phase, namely, VSR-LT10 Trail Walkers on Fu Tei
Country Trail and Lam Tei Irrigation Reservoir, VSR-SK28 Students and Staff
at Chu Hai College of Higher Education, VSR-NL10 Future Vehicle Travellers on
Planned Road P1. |
Cultural Heritage |
|||||
Construction Phase |
|||||
Terrestrial
archaeology |
·
No adverse
impact on the sites of archaeological interest identified within or near the
Project; and ·
An area of
archaeological potential at the east of Area A at the lower slopes to the
north of Lam Tei Quarry within the works area would require further
archaeological investigation to verify the presence of any archaeological
remains. |
·
Antiquities and Monuments Ordinance (Cap. 53) ·
EIAO including EIAO-TM ·
Guidelines for Cultural
Heritage Impact Assessment |
·
Not applicable |
·
Testing including field scan, auger tests and
test pit excavation within the non-tested area of archaeological potential is
recommended to be conducted by an
archaeologist who obtains a licence under the Antiquities and Monuments
Ordinance (Cap. 53); and ·
AMO should be informed immediately in case of
discovery of antiquities or supposed antiquities in the course of the project
works for discussion of appropriate mitigation measures to be agreed by AMO
before implementation by the project proponent to the satisfaction of AMO. |
·
No adverse residual impact anticipated |
Built
heritage |
·
There is no
Declared Monuments, Proposed Monuments, Graded Historic Buildings and
Government Historic Sites. Former Perowne Barracks, Gurkha Temple, a grade 3
structure will require mitigation during the construction phase as it is in
close proximity of earthworks (around 11m). |
·
Antiquities and Monuments Ordinance (Cap. 53) ·
EIAO including EIAO-TM ·
Guidelines for Cultural Heritage Impact
Assessment ·
AMO Proposed Vibration Limits ·
Proposed Grading and
Graded Historic Buildings Classification |
·
Not applicable |
·
A condition survey be undertaken by qualified
building surveyor or engineer prior and after the construction phase. The
relevant works drawings and proposal shall be submitted to AMO for
consideration; ·
The Condition Survey Report for the graded
historic building shall be submitted to AMO for comment before commencement
and after construction activities. The
locations of proposed monitoring points in the building should avoid damaging
the historic fabric and agreed by the owner and Antiquities and Monuments
Office (AMO). The contractor should implement the approved monitoring and
precautionary measures; ·
Any vibration and building movement induced from
the construction works should be strictly monitored to ensure no disturbance
and physical damages made to the heritage site during the course of works.
Monitoring proposal for the heritage sites, including checkpoint locations,
installation details, response actions for each of the Alert/ Alarm/ Action
(3As) levels and frequency of monitoring should be submitted for AMO's
consideration. The recommended 3As levels for Grade 3 heritage site are
specified in the EM&A Manual; ·
A buffer zone should be provided to separate the
Former Perowne Barracks, Gurkha Temple building from the construction works.
The buffer zone should be clearly marked out by temporary fencing. The buffer
zone should be made at least 5m from the proposed works or if this is not
possible as large as the site restrictions allow; ·
Special attention should be paid to the heritage
site to avoid adverse physical impact arising from the construction of the
Project. Design proposal, method of works and choice of machinery will be
targeted to minimize adverse impacts to the heritage site; ·
Foundation information of the historic structure
shall be verified on site if needed, sufficient lateral support should be
provided and de-watering (if required) should be carried out with great
cautions to control ground movement and change of ground water regime at the
heritage site; and ·
AMO should be informed immediately in case of
discovery of buildings
/ structures both at-grade and underground with potential heritage value that
would likely be affected by the development in the course of the project works
for discussion of appropriate mitigation measures to be agreed by AMO before
implementation by the project proponent to the satisfaction of AMO. |
·
No adverse residual impact anticipated |
Marine
archaeology |
·
19 anomalies were
identified from geophysical surveys; ·
In addition,
due to shallow water depth along the coast, geophysical survey could not be
conducted in this area. Therefore, it is proposed to dive every 50m along
this area (i.e. 35 dive targets); and ·
After consulting with
Marine Department, it is recommended to conduct the marine diver survey when
fencing off of the diving area could be safely implemented but prior to any
reclamation works, i.e. during the detailed design stage. |
·
Antiquities and Monuments Ordinance (Cap. 53) ·
EIAO including EIAO-TM ·
Guidelines for Cultural
Heritage Impact Assessment |
·
Not applicable |
·
Marine diver survey shall be conducted during the
detailed design stage when fencing off can be implemented but prior to any
reclamation works; ·
Should there be any marine archaeological
resources identified during the marine ground investigation works and MAI, proper mitigation measures
including but not limited to rescue excavation shall be proposed for
agreement with AMO before the commencement of reclamation works; ·
If the marine ground investigation works is
required prior to the diver survey, it shall be arranged to avoid all the anomalies identified by geophysical
survey conducted, by allowing sufficient setback distance (around 50m) from
the anomalies; ·
Any marine GI works at the anomalies is required
to be conducted after confirming their nature by MAI and seeking agreement
with AMO; and ·
In case antiquities or supposed antiquities are
identified during the construction works, the works should be suspended, and
the project proponent should notify AMO immediately for discussion of
appropriate mitigation measures to be agreed by AMO before implementation by
the project proponent to the satisfaction of AMO. |
·
No adverse residual impact anticipated |
Operational Phase |
|||||
Terrestrial
archaeology, built heritage and marine archaeology |
·
Adverse impact
to terrestrial archaeology, built heritage and marine archaeology is not
anticipated. |
·
Antiquities and Monuments Ordinance (Cap. 53) ·
EIAO including EIAO-TM; ·
Guidelines for Cultural
Heritage Impact Assessment ·
HKPSG ·
Proposed Grading and
Graded Historic Buildings Classification |
·
Not applicable |
·
No mitigation measure is required |
·
No adverse residual impact anticipated |