TABLE OF CONTENTS
1.2 Environmental Impact Assessment
Study
1.3 Purpose of this Executive Summary
2.1 Appreciation of Existing
Environment
2.3 Development Opportunities for
Project Development
2.4 Development Constraints for
Project Development
2.5 General Description of the
Project
2.6 Recommended Outline Development
Plan (RODP)
2.9 Development Programme for the
Project
3. Key Findings of the
Environmental Impact Assessment
3.5 Sewerage and Sewage Treatment
Implications
3.6 Waste Management Implications
3.8 Ecological Impact (Terrestrial and
Marine)
3.10 Landscape and Visual Impacts
3.11 Impact on Cultural Heritage
3.14 Impact from Electric and Magnetic Fields
4. Environmental
Monitoring and Audit
5. Summary of
Environmental Outcomes
List
of Tables
Table 2.1 Needs for Public Facilities in
PODP Stage
Table 2.2 Planning Requirements for Public
Facilities in PODP Stage
Table 2.3
Land Use Budget
of the RODP for Tseung Kwan O Area 137
Table 2.4 Land Use Budget of the RODP for
the land to be created off Tseung Kwan O Area 132
Table 2.5 Schedule 2 Designated Projects in the Project
Table 5.1 Summary of Key Environmental
Problems Avoided and Sensitive Areas Protected
Table 6.1 Summary of Environmental Impacts
List of Figures
Project Location Plan |
|
RODP for Tseung Kwan O
Area 137 |
|
RODP for the land to
be created off Tseung Kwan O Area 132 |
|
Location of Designated
Projects (Sheet 1 of 2) |
|
Location of Designated
Projects (Sheet 2 of 2) |
Table
2.1 Needs for Public Facilities in PODP Stage
Public Facility |
Need of the facilities/
site selection consideration |
Marine Frontage
Requirement |
PFTF |
Public
fill generated in the territory east is currently received and stockpiled at
the TKO 137 temporary fill bank pending transfer to appropriate projects for
reuse. With the plan to develop TKO 137, and while the upcoming
reclamation projects in Hong Kong would reduce significantly the need for
stockpiling public fill, there is still a need to retain a smaller-scale
facility to receive and transfer public fill generated in the territory east
(including TKO), at a location with marine frontage. |
Marine
frontage is required for transferring public fill received to appropriate
projects through marine transport. |
CBP |
The temporary
CBP at TKO 137 is planned to be decommissioned by 2029. A permanent
site for re-provisioning the CBP in the vicinity is required to serve
construction sites in East Kowloon and New Territories East (including TKO),
as freshly mixed concrete must be delivered within a reasonably short time to
construction sites to maintain the quality of concrete. |
To
facilitate the operation of the CBP, a waterfront site to allow
transportation of raw materials by sea for concrete production could avoid
increasing loading on road traffic. |
EFs,
comprising power receiving and conversion facilities, are important strategic
infrastructure for enhancing Hong Kong’s capability to import zero-carbon
energy through regional cooperation and meeting the decarbonisation target of
reducing Hong Kong’s carbon emissions by 50% before 2035 as compared to the
2005 level, with a view to achieving carbon neutrality before 2050. TKO 132 is
considered as the optimal location as it is situated near the potential
connection points at TKO and Island East of the two power companies’ existing
power grids, and their power systems can be interconnected through submarine
cables with a shorter distance. |
Marine
frontage is necessary for the landing of submarine cables. |
|
CWHF |
There is a
need to set up a CWHF to receive, handle and bulk transfer construction waste
primarily generated from the territory east (including TKO) to the other
waste handling facilities (e.g. landfill) upon the closure of SENTX prior to population intake at TKO 137. |
Bulk
transfer of mixed construction waste to other waste handling facilities would
require marine frontage. |
RTS |
There is
currently no dedicated RTS in the territory east area (including TKO).
Temporary arrangement is put in place to transfer municipal solid waste (MSW)
generated in this area to RTSs in Island East, West Kowloon and Shatin for
handling. As these three RTSs have reached their capacity limits, there
is a need to set up a RTS for serving existing and future developments in the
territory east area (including TKO). |
Marine
frontage is necessary as MSW would be compacted and containerised in
purposely built containers for onward shipment to waste management facilities
via marine traffic. |
MRCP |
As the Cha
Kwo Ling site is to be developed into part of a waterfront promenade, the
MRCP thereat is proposed to be reprovisioned at a location in the territory
east to serve the eastern waters. Proximity to the RTS also allows
operational synergy. |
Marine
frontage is necessary for unloading collected refuse from the vessels. |
Infrastructure Constraints
Limited Development Area in TKO 137
Tathong Channel Traffic Separation Scheme (Tathong Channel
TSS)
Avoidance and Minimisation of Industrial and Residential
Interface Problems
Consideration of Permitted Burial Ground during planning
Environmental Constraints
Existing Ecological, Natural and Landscape Features
Declared Monument/ Site of Archaeological Interest
Infrastructure Constraints
Existing Government Land Licences
Junk Bay Chinese Permanent Cemetery (JBCPC)
Junk Bay Dangerous Goods Anchorage (JBDGA)
Diagram 2.1– Location of JBDGA[4]
Requirements for Public Facilities
Table
2.2 Planning Requirements for Public
Facilities in PODP Stage
Public Facilities |
Required Footprint |
Maximum Building Height |
Minimum Marine Frontage Required |
EFs |
5.9 ha |
60 m |
200 m for sloping seawall for cable landing |
RTS |
3.0 ha |
40 m (50 m for on-shore crane) |
170 m |
CWHF |
4.5 ha |
20 m |
180 m |
PFTF |
4.0 ha |
25 m |
230 m |
CBP |
0.6 ha |
28 m |
80 m |
MRCP |
0.18 ha |
14 m |
30 m |
Environmental Constraints
Existing Ecological, Natural and Landscape Features
Graded Historic Buildings
·
Residential sites for high density public and private
residential developments. About 50,000 new flats will be provided to
accommodate about 135,000 persons upon full development.
·
A wide variety of G/IC
facilities such as schools, police station, fire station, Government
Complex etc. serving the needs of the local residents and/or a
wider district, region or the territory.
·
A variety of infrastructural
facilities such as an Effluent Polishing Plant (EPP), a fresh water service
reservoir (FWSR), a salt water service reservoir (SWSR), electricity
substations (ESSs), Public Transport Interchanges (PTIs) and a SPS serving the
needs of the local residents and/or a wider district, region or the
territory.
·
Open space including outdoor open-air public
space for active and/or passive recreational uses serving the needs of both
the local residents, workers, as well as the general public.
·
Amenity strips enhancing the amenity and serving
as visual buffers between existing villages and new developments.
·
Eight Local
Distributor Roads (Dual 2-lane / Single 2-lane Standard)
·
A single-2-lane
carriageway road connecting carriageway bridges for motor vehicles in the
form of marine viaduct to/from TKO 132
Table 2.3
Land Use Budget of the RODP for Tseung Kwan O
Area 137
Approx. Area (ha) (% of total) |
|
Residential -
Public -
Private |
51.9 (50.8%) 25.9 26.0 |
Government, Institution and
Community Facilities -
Primary Schools -
Secondary Schools -
Sports Centre and Government Reserve -
Divisional Police Station -
Sub-divisional Fire Station cum Ambulance Depot -
Government Complex (includes Swimming Pool Complex, Sports Centre,
Public Market, Community Hall, Health Centre, Recycling Store, Refuse
Collection Point) |
7.3 (7.2%) 2.0 1.6 0.8 0.4 0.5 2.0 |
Open Space |
18.8 (18.4%) |
Other Specified Uses – -
Effluent Polishing Plant -
Green Fuel Station -
Electricity Substation -
Fresh Water Service Reservoir / Salt Water Service Reservoir |
6.9
(6.8%) 4.5 0.4 1.0 1.0 |
Roads |
17.2 (16.9%) |
TOTAL (about) |
102.2
(round to 103) (100%) |
Remarks: The above Land Use
Budget is based on the RODP version dated 2024.07.10. Due to rounding, the
figures presented may not add up precisely to the totals provided and
percentages may not precisely reflect the absolute figures.
Table 2.4 Land Use Budget of the RODP for the
land to be created off Tseung Kwan O Area 132
Land Use |
Approx. Area (ha) (%
of total) |
(A) EFs |
5.6 (28.3%) |
(B) RTS |
3.0 (15.3%) |
(C) CWHF |
4.5 (22.7%) |
(D) PFTF |
4.0 (20.2%) |
(E) CBP |
0.6 (3.0%) |
(F)
Others* |
2.0 (10.1%) |
Total (about) |
19.8 (round to 20) (100%) |
·
1: An urban development
or redevelopment project covering an area of more than 50 ha.
Table 2.5 Schedule 2 Designated Projects in the Project
Ref. No. |
Schedule 2 Designated Project |
Work Component /Reference in RODP |
|
DP1 |
A.8 |
A carriageway bridge for motor vehicles, or a railway bridge, the
length between abutments for which is more than 100 m, with bridge piers over
the sea supporting the bridge |
A carriageway bridge in form of viaduct structure for motor vehicles
with a minimum length of about 700 m between abutments and supported by piers
over the sea, will be constructed near TKO-LTT to provide a direct and
convenient connection to the proposed facilities at TKO 132. |
DP2 |
C.1 |
Reclamation works (including associated dredging works) more than 5 ha
in size |
Around 20 ha of land will be formed by reclamation at TKO 137. |
C.2 |
Reclamation works (including associated dredging works) that are of
more than 1 ha in size, and a boundary of which is (c) less than 100 m from
the nearest boundary of an existing residential area |
Project boundary of the reclamation works (around 19 ha) at TKO 132 is
around 30 m from the nearest boundary of On Luen Village (location of
existing government land licences). |
|
DP3 |
F.1 |
Sewage treatment works with an installed capacity of more than 15,000
m3 per day |
Construction and operation of an EPP with an installed capacity of
approx. 54,000 m3 per day at TKO 137. The EPP is around 100 m from the planned
residential area and around 60 m from the planned educational institution at
TKO 137. |
F.2 |
Sewage treatment works (a) with an installed capacity of more than
5,000 m3 per day; and (b) a boundary of which is less than 200m
from the nearest boundary of an existing or planned (i) residential area and
(iii) educational institution |
||
DP4 |
G.2 |
A refuse transfer station |
Construction and operation of a RTS at formed land off TKO 132 |
DP5 |
G.5 |
A facility for the treatment of construction waste (a) with a designed
capacity of more than 500 tonnes per day; and (b) a boundary of which is less
than 200 m from the nearest boundary of an existing or planned (i)
residential area |
Construction and operation of a Construction Waste Handling Facility
with handling capacity of around 3,000 tonnes per day at formed land off TKO
132. |
DP6 |
H.1 |
A 400kV electricity substation and transmission line |
Construction and operation of Electricity Facilities (EFs) at formed
land off TKO 132. EFs are planned to
house equipment up to 400kV. |
Note:
1
Application of
Environmental Permit (EP) will be supported by this EIA Study.
2 Application of EP will be supported by a separate Schedule 2 EIA Study
or separate Direct Application of EP to
be conducted by the
respective project proponent.
3 There
is no design information for EFs provided from the operator at the time of
assessment. The assumption of a 400 kV electricity substation, a Schedule
2 DP under EIAO, is considered in this EIA study.
Table 2.6 Summary of
Non-Designated Projects
Non-Designated
Project |
Sub-Element |
TKO 132 |
|
Other
Specified Uses (OU) |
Public Fill
Transfer Facility (OU(PFTF)) |
Concrete
Batching Plant (OU(CBP)) |
|
Sewage
Pumping Station (OU(SPS)) |
|
Amenity (A) |
Roadside
amenity |
Roads |
Local roads |
TKO 137 |
|
Residential
Development |
Public Housing
Site (RSc) |
Private
Housing - Zone 1 (R1) |
|
Private
Housing - Zone 2 (R2) |
|
Public
Transport Interchange |
|
Social
Welfare Facilities |
|
Government,
Institutional or Community (G/IC) |
Divisional
Police Station |
Sub-divisional
Fire Station cum Ambulance Depot |
|
Sports
centre and Government Reserve |
|
Government
Complex (includes Swimming Pool Complex, Sports Centre, Public Market,
Community Hall, Health Centre, Recycling Store, Refuse Collection Point) |
|
Education
(E) |
Schools |
Open Space
(O) |
Recreational
Facilities and Landscaping |
Other
Specified Uses (OU) |
Electrical
Substation (OU(ESS)) |
Green Fuel
Station (OU(GFS)) |
|
Salt Water
Service Reservoir (OU(SWSR)) |
|
Fresh Water
Service Reservoir (OU(FWSR)) |
|
Roads |
Local roads |
(a)
Should the change(s)
involve a DP item under Schedule 2 of the EIAO, the requirements under the EIAO
will be complied with; and
(b)
Should the change(s)
not involve any DP items under Schedule 2 of the EIAO, prevailing planning
mechanisms and standards will be followed and relevant EIA findings will be
conformed to.
Direct Benefits
Environmental Benefit and Initiatives
2.8.1.4
Reduce heavy
vehicles at Wan Po Road –Currently, vast majority of the existing traffic on Wan Po Road south
of LOHAS Park is generated by TKOFB. The heavy vehicles, such as diesel fuel
dump trucks, are driving through the existing road network of TKO New Town to
TKOFB which could cause disturbance to local residents. With TKOFB converting
into a housing development, the traffic on Wan Po Road is expected to shift
predominantly to electric and petroleum vehicles, which emit fewer pollutants.
By locating the PFTF at TKO 132, those heavy vehicles generated could be
diverted away from TKO New Town and access to Kowloon directly via Tseung
Lam Highway. This would
minimise any possible nuisance to local residents.
·
Comprehensive
pedestrian network –
Comprehensive pedestrian network of TKO 137 connects residential and employment
nodes to provide continuous walkways for pedestrians. It could promote walking
from homes to workplaces, retail and services for various purposes.
·
Open space network /
green linkages – A
series of open space corridors branching off the main comprehensive pedestrian
network, including the open spaces along drainage channel and linear parks
along major road. They shall provide additional pedestrian connections to the
surrounding residential communities and employment areas, and further to the
green and natural areas.
·
Robust cycling
network – TKO 137
provides a robust cycling network which link effectively to the existing and
planned cycling tracks within and outside TKO 137. The proposed cycling
network would connect to the existing tracks from Wan Po Road to create a
continuous cycling environment that extends to other destinations beyond the
TKO 137. Routes within TKO 137 would be provided parallel to the major roadways
to serve commuting needs, as well as to provide some other routes within the
proposed open space areas for leisure.
Promoting Biodiversity
Initial Phase Development
·
Phase 1 Reclamation
including associate seawall works, site formation, box culvert and seawall
outfall works for the middle portion along the southwest shoreline and the existing barging basin at the north of TKO 137.
·
Site development works
for two “Public Housing” (“PU”) sites at north of the Project area, including
associated local roads and the interchange/junction works connecting with Wan
Po Road, pedestrian connectivity, drainage, waterworks, sewerage (including
construction of advance SPS), utilities, electrical and mechanical, M, paving,
road marking and street furniture works to support the first population intake.
·
Reclamation, seawall
construction, slope-cutting, site formation, box culvert(s) and seawall
outfall(s) to form about 20 ha for the proposed development.
·
Construct of marine
viaducts and road network to connect the land to be created off TKO 132 to
existing Tseung Lam Highway.
·
Other engineering
infrastructure works including roads, interchange/junction, pedestrian
connectivity, drainage, sewerage including construction of SPS, waterworks,
landscape to support the development
Main Phase Development
·
Phase 2 Reclamation
including associated seawall works, site formation, box culvert(s) and seawall
outfall(s) for the southern portion along the southwest shoreline.
·
Site development works
for four “Public Housing” (“RSc”) sites at east of the Project area.
·
Site development works
for one ‘Private Housing” (“R1”) site at northwest of the Project area.
·
Site development works
for “Government, Institution or Community” (“G”) sties.
·
Site development works
for “Education” (“E”) sites.
·
Site development works
for “Other Specified Uses” (“OU”) sites for key infrastructures, including EPP,
FWSR and SWSR.
·
Associated local roads,
interchange/junction, pedestrian connectivity, drainage,
waterworks, sewerage, UU, E&M, paving, road marking and street furniture
works.
Remaining Phase Development
2.9.1.9
Remaining Phase
Development is the last phase of the development for TKO 137, mainly including
development works at the land area that was occupied by HyD/RDO for
TKLSE construction at initial phase (subject to HyD/RDO’s later formulation of the railway construction
works), as well as any remaining infrastructure and interfacing works from the
last development phase. The development works in this phase is to
support the targeted population intake in Year 2038 and the targeted mass
population intake in Year 2041 respectively at TKO 137.
2.9.1.10
The major development works in this development phase will include:
·
Site development works
for two ‘Private Housing” (“R1”) sites and two ‘Private Housing” (“R2”) sites
at west of the Project area.
·
Associated local roads,
interchange/junction, pedestrian connectivity, drainage,
waterworks, sewerage, UU, E&M, paving, road marking and street furniture.
·
Interfacing works from
the last development phase.
·
Air Quality Impact
·
Noise Impact
·
Water Quality Impact
·
Sewerage and Sewage
Treatment Implications
·
Waste Management
Implications
·
Land Contamination
·
Ecological Impact
·
Fisheries Impact
·
Landscape and Visual
Impact
·
Cultural Heritage
Impact
·
Hazard to Life
·
Landfill Gas Hazard
·
Electric and Magnetic
Fields
Construction Phase
Operation Phase
Construction Phase
Operational phase
Construction Phase
Operation Phase
Construction Phase
Operation phase
Table 5.1
Summary of Key Environmental Problems Avoided and
Sensitive Areas Protected
Design Approaches |
Environmental Problems Avoided and Environmental Options |
Avoidance
of encroachment into CWBCP |
· The proposed
natural terrain mitigation works (i.e. flexible barrier) has been re-located
to be within the EPP site to avoid any works encroaching into CWBCP |
Preservation
of natural shoreline |
· Reclamation
extent of TKO 132 has been optimised to minimise the impact to the natural shoreline.
Approximately 1 km of natural shoreline can be maintained |
Minimise
direct impact to hard and black corals colonies and coral recipient site at western
Junk Bay |
· Reclamation
extent of TKO 132 has been optimised to avoid encroachment into the coral recipient
sites at Junk Bay and minimise direct impact to hard and black corals
colonies and coral recipient site at western Junk Bay |
Minimise
direct impact to subtidal habitats and associated coral colonies in Western Junk
Bay |
· Reclamation
extent of TKO 132 has been optimised to minimise direct impact to subtidal habitats
and associated coral colonies in Western Junk Bay |
Avoidance
of encroachment on the existing government land licences at On Luen Village |
· Site formation
at TKO 132 has been designed to avoid encroachment into the existing
government land licences at On Luen Village. |
Avoidance
of direct impacts on natural water course |
· Pier locations
of the marine viaduct has been designed to avoid direct impact on the natural
watercourse near TKO 132. |
Minimise
impact to the terrestrial ecology at Devil’s Peak |
· The natural
terrain mitigation works have been optimised to ensure that the works area is
limited to the toe of Devil’s Peak as far as possible in order to minimise
the terrestrial ecology impact. |
Minimise
potential odour impact |
· The EPP
emission points are designed to be located away from the sensitive receivers
to minimise the potential odour impact |
Providing
sustainable transport infrastructure to promote low-carbon living |
· Pedestrian-friendly
environment and robust cycling network are proposed to promote walkability and
cycling for low-carbon living |
Appropriate Planning of Building
Configuration and Setback, and application of acoustic windows and/or
enhanced acoustic balcony |
· With appropriate planning on
building configuration and setback from roads, potential road traffic noise
impact on future noise sensitive uses within the development would be
minimised. The potential noise impacts could be alleviated by the use
of low-noise road surfacing, acoustic windows and / enhanced acoustic
balcony, blank wall, fixed window, architectural fin, etc., thereby avoiding
the use of roadside noise barriers or enclosures. Without roadside
noise barriers or enclosures, the associated visual impacts and bird
collisions would also be avoided / minimised. |
Create buffer distance between TKOIP and
sensitive receivers/uses in TKO 137 |
· To minimise the impact from the
TKOIP to the sensitive receivers/uses in TKO 137, G/IC and open spaces have
been positioned between TKOIP and residential sites to sufficient buffer
distance |
Adoption of Non-dredged Reclamation |
· Non-dredged reclamation with
in-situ ground treatment methods (including marine-based deep cement mixing
and land-based jet grouting) would be adopted to minimise the associated
water quality impacts, the waste management implications from sediment disposal
and the secondary environmental impacts from induced marine traffic. |
Adoption of Environmentally Friendly
Construction Method |
· The precast method would be
adopted for the construction of the proposed marine viaduct to reduce the
overall C&D materials to be generated on-site, shorten construction
duration and minimise on-site environmental impacts (e.g. dust and
noise) on nearby sensitive receivers. |
Table 6.1
Summary of Environmental Impacts
Impact Prediction Results (Without Mitigation) |
Key Relevant Standards/Criteria |
Extents of Exceedance Predicted (Without Mitigation) |
Impact Avoidance Measures / Mitigation Measures |
Residual Impacts (After Implementation of
Mitigation Measures) |
|
Air Quality Impact |
|||||
Construction
Impact |
|||||
·
Representative existing residential, commercial
developments and government uses within 500 m from the boundary of the
Project site |
The potential sources of air quality impact associated with the
construction works would include site formation, excavation, backfilling,
stockpiling, material handling, spoil removal, vehicle movement and wind
erosion, as well as construction activities of other concurrent projects
within 500 m assessment area. |
·
Annexes 4 and 12 of the EIAO-TM ·
Prevailing Air Quality Objectives (AQO) RSP o 24-hr average conc.: 100 μg/m3 (Number of exceedances
allowed: 9) o Annual average conc.: 50 μg/m3 FSP o 24-hr average conc.: 50 μg/m3 (Number of exceedances
allowed: 18) o Annual average conc.: 25 μg/m3 ·
Proposed Air Quality Objectives (AQO) RSP o 24-hr average conc.: 75 μg/m3 (Number of exceedances
allowed: 9) o Annual average conc.: 30 μg/m3 FSP o 24-hr average conc.: 37.5 μg/m3 (Number of exceedances
allowed: 18) o Annual average conc.: 15 μg/m3 |
·
N/A |
Regular watering on construction work areas, exposed surface and paved
haul roads to dust suppression. Dust suppression measures stipulated in Air Pollution Control
(Construction Dust) Regulation and good site practices listed below should be
carried out to further minimise construction dust impact. ·
Use of regular watering to reduce dust emissions
from exposed site surfaces and unpaved roads, particularly during dry
weather. ·
Use of frequent watering for particularly dusty
construction areas and areas close to ASRs. ·
Side enclosure and covering of any aggregate or
dusty material storage piles to reduce emissions. Where this is not
practicable owing to frequent usage, watering shall be applied to aggregate
fines. ·
For the work sites close to the ASR with a
separation distance less than 5m, provide hoardings of not less than 5m high
from ground level along the project boundary; for the work sites close to the
ASRs with a separation distance less than 10 m, provide hoardings of not less
than 3.5 m high from ground level along the project boundary; for the other
work sites, provide hoarding not less than 2.4m high from ground level along
project boundary except for site entrance or exit. ·
Avoid position of material stockpiling areas, major
haul roads and dusty works within the construction site close to concerned
ASRs. ·
Avoid unnecessary exposed earth. ·
Locate all the dusty activities away from any nearby
ASRs as far as practicable. ·
Open stockpiles shall be avoided or covered.
Where possible, prevent placing dusty material storage piles near ASRs. ·
Tarpaulin covering of all dusty vehicle loads
transported to, from and between site locations. ·
Establishment and use of vehicle wheel and body
washing facilities at the exit points of the site. ·
Where possible, routing of vehicles and positioning
of construction plant should be at the maximum possible distance from ASRs. Imposition
of speed controls for vehicles on site haul roads. ·
Instigation of an environmental monitoring and
auditing program to monitor the construction process in order to enforce
controls and modify method of work if dusty conditions arise. |
·
No residual impacts anticipated |
Operation Impact |
|||||
·
Existing and planned residential, commercial
developments and government uses within 500m from the boundary of the Project
site |
Air
Quality Impact NO2 ·
19th highest 1-hr average conc.: 66 – 175
μg/m3 ·
10th highest 24-hr average conc: 25 – 92
μg/m3 ·
Annual average conc.: 12 – 36 μg/m3 SO2 ·
4th highest 10-min average conc: 22 –47
μg/m3 ·
4th highest 24-hr average: 7 – 9
μg/m3 RSP ·
10th highest 24-hr average conc: 49 – 56
μg/m3 ·
Annual average: 19 – 22 μg/m3 FSP ·
19th highest 24-hr average conc: 28 – 33
μg/m3 ·
Annual average: 11 – 13 μg/m3 CO ·
Highest 1-hr average conc: 510 – 648 μg/m3 ·
Highest 8-hr average: 478 – 576 μg/m3 ·
Highest 24-hr average: 444 – 474 μg/m3 Methane ·
Highest 1-hr average conc: 4468 – 4485 μg/m3 HCl ·
Highest 1-hr average conc: 1.04 – 2.19 μg/m3 ·
Annual average: 1.00 – 1.10 μg/m3 HF ·
Highest 1-hr average conc: 0.00 – 0.12 μg/m3 ·
Annual average: 0.00 – 0.01 μg/m3 Formaldehyde ·
Highest 30-min average conc: 3.35 – 4.96 μg/m3 ·
Annual average: 1.51 – 1.65 μg/m3 Vinyl Chloride ·
Highest 1-hr average conc: 0.40 – 0.40 μg/m3 ·
Annual average: 0.33 – 0.33 μg/m3 Benzene ·
Highest 1-hr average conc: 2.0 – 2.0 μg/m3 ·
Highest 8-hr average conc: 2.0 – 2.0 μg/m3 ·
Annual average: 1.1 – 1.1 μg/m3 Acetaldehyde ·
Highest 1-hr average conc: 6.75 – 12.47 μg/m3 ·
Highest 8-hr average conc: 6.63 – 8.10 μg/m3 ·
Annual average: 1.32 – 1.36 μg/m3 |
·
Prevailing AQO NO2 o 1-hr average conc.: 200 μg/m3 (Number of exceedances
allowed: 18) o Annual average conc.: 40 μg/m3 SO2 o 10-min average conc.: 500 μg/m3 (Number of exceedances
allowed: 3) o 24-hr average conc.: 50 μg/m3 (Number of exceedances
allowed: 3) RSP o 24-hr average conc.: 100 μg/m3 (Number of exceedances
allowed: 9) o Annual average conc.: 50 μg/m3 FSP o 24-hr average conc.: 50 μg/m3 (Number of exceedances
allowed: 18) o Annual average conc.: 25 μg/m3 CO o 1-hr average conc.: 30000 μg/m3 (Number of exceedances
allowed: 0) o 8-hr average conc.: 10000 μg/m3 (Number of exceedances
allowed: 0) ·
Proposed AQO NO2 o 1-hr average conc.: 200 μg/m3 (Number of exceedances
allowed: 18) o 24-hr average conc.: 120 μg/m3 (Number of exceedances
allowed: 9) o Annual average conc.: 40 μg/m3 SO2 o 10-min average conc.: 500 μg/m3 (Number of exceedances
allowed: 3) o 24-hr average conc.: 40 μg/m3 (Number of exceedances
allowed: 3) RSP o 24-hr average conc.: 75 μg/m3 (Number of exceedances
allowed: 9) o Annual average conc.: 30 μg/m3 FSP o 24-hr average conc.: 37.5 μg/m3 (Number of exceedances
allowed: 18) o Annual average conc.: 15 μg/m3 CO o 1-hr average conc.: 30000 μg/m3 (Number of exceedances
allowed: 0) o 8-hr average conc.: 10000 μg/m3 (Number of exceedances
allowed: 0) o 24-hr average conc.: 4000 μg/m3 (Number of exceedances
allowed: 0) ·
Non-AQO Methane o 1-hr average conc.: 600,000 μg/m3 (Number of
exceedances allowed: 0) HCl o 1-hr average conc.: 2100 μg/m3 (Number of exceedances
allowed: 0) o Annual average conc.: 20 μg/m3 HF o 1-hr average conc.: 240 μg/m3 (Number of exceedances
allowed: 0) o Annual average conc.: 14 μg/m3 Formaldehyde o 30-min average conc.: 100 μg/m3 (Number of exceedances
allowed: 0) o Annual average conc.: 9 μg/m3 Vinyl
Chloride o 1-hr average conc.: 180000 μg/m3 (Number of
exceedances allowed: 0) o Annual average conc.: 100 μg/m3 Benzene o 1-hr average conc.: 27 μg/m3 (Number of exceedances
allowed: 0) o 8-hr average conc.: 3 μg/m3 (Number of exceedances
allowed: 0) o Annual average conc.: 3 μg/m3 Acetaldehyde o 1-hr average conc.: 470 μg/m3 (Number of exceedances
allowed: 0) o 8-hr average conc.: 300 μg/m3 (Number of exceedances
allowed: 0) o Annual average conc.: 9 μg/m3 |
NO2,
SO2, RSP, FSP and CO ·
No exceedance was predicted Methane, HCl, HF, Formaldehyde, Vinyl Chloride, Benzene and
Acetaldehyde ·
No exceedance was predicted |
·
No mitigation measure is required. ·
Specific site
considerations are recommended to be implemented in order to avoid any
potential air quality impact. Air
sensitive at Site G3 (P05) use should locate at 5mAG or above. Long-term air
sensitive use at Site O5 which is a proposed open space should be avoided.
Air sensitive use within the exceedance zones in the proposed RTS, PFTF and
CWHF of TKO 132 should be avoided |
·
No residual impacts anticipated |
• Existing and planned residential, commercial developments and
government uses within 500m from the boundary of the Project site |
Odour Impact 5-second average odour concentration: 0.12 – 2.20
OU/m3 |
· Annex 4 of EIAO-TM · 5 odour units based on an averaging time of 5 seconds |
Odour ·
No exceedance was predicted |
· No mitigation measure is required. |
·
No residual impacts anticipated |
Noise Impact |
|||||
Construction
Airborne Noise Impact |
|||||
·
Representative existing residential uses, planned
residential developments, and planned educational institutions within 300m
from the boundary of the Project Site |
·
Potential adverse construction noise impact due to
construction works within the project boundary |
·
Annexes 5 and 13 of the EIAO-TM ·
Leq(30 min) 75dB(A) at 1m from the façade
of residential dwellings ·
Leq(30 min) 70dB(A) at 1m from the façade
of Educational Institutions and 65 dB(A) during examinations ·
Professional Persons Environmental Consultative
Committee Practice Notes (ProPECC PN1/24) |
·
N/A |
·
Use of Quieter Construction Methods and Quality
Powered Mechanical Equipment such as use of press-in method for sheet piling;
large diameter bored piling to replace percussive piling; use of hydraulic
splitter / hydraulic crusher / bursting system / quieter type saw / chemical
expansion agent for demolition, concrete breaking, site formation, filling
and slope cutting works and removal activities; use of fully enclosed
conveyor for material handling; use of mini-breaker for small boulder removal
and infrastructural works; pipe jacking using tunnel boring machine for large
diameter pipe laying; use of quiet type saw, robot-type hydraulic crusher or
handheld concrete crusher for building works; use of pre-casting and
prefabrication technology for building superstructure works; and use of
self-compacting concrete or rubber head poker vibrator ·
Use of Noise Barrier and Noise Enclosure ·
Careful Scheduling of Construction Activities ·
Good site practices - Only well-maintained plant should be operated on site and plant should
be serviced regularly. - Silencers or mufflers on construction plant should be utilised and
should be properly maintained. - Mobile plant should be sited as far away from sensitive uses as
possible. - Machines and plant that may be in intermittent use should be shut down
between works periods or should be throttled down to a minimum. - Plant known to emit noise strongly in one direction should, where
possible, be orientated so that noise is directed away from the nearby
sensitive uses. - Material stockpiles and other structures should be effectively
utilised to screen noise from on-site construction activities. ·
Submission of Construction Noise Management Plans
(CNMPs) to EPD for agreement before tender invitation and before construction
works commencement |
·
No residual impacts anticipated |
Operation
Phase Impact |
|||||
·
Representative existing residential uses, place of
public worship, planned residential developments and planned educational
institutions within 300 m from the boundary of the Project Site |
Fixed
Noise ·
Adverse fixed noise impact is not anticipated due to
proposed fixed noise sources with good design and mitigation measures, and
environmental monitoring and audit ·
Potential noise impact due to existing fixed noise
source (SNG Plant) |
Fixed
Noise ·
Annexes 5 and 13 of the EIAO-TM ·
Appropriate ANL -5 dB(A) as shown in Table 2 of
IND-TM or the prevailing background noise level for planned/proposed fixed
noise sources ·
Appropriate ANL as shown in Table 2 of IND-TM for
cumulative fixed noise impact from planned and existing noise sources ·
EIAO-GN 16/2023 ·
HKPSG |
Fixed
Noise ·
N/A |
Fixed
Noise ·
Mitigation measure required at existing SNG Plant to
alleviate any potential fixed noise impact. ·
For proposed fixed noise sources, use of quiet
plant, enclosing plant inside buildings with opening facing away from
existing/proposed/planned NSRs, install acoustic silencers, noise barrier to
ensure the noise compliance of the fixed noise source. Noise commissioning
test for fixed noise sources will be carried out by relevant government
departments/ future operators before operation of fixed noise sources. ·
For various DP fixed noise sources, Fixed Noise
Management Plan (FNMP) should be submitted to EPD by each of the proponent of
the proposed/planned fixed noise sources ·
For non-DPs fixed noise sources within the Project
area and existing noise sources within the assessment area affecting the
proposed/planned NSRs under this Project, quantitative fixed noise impact
assessment should be carried out via various planning/funding/land lease
mechanism. |
·
No residual impacts anticipated. |
Rail
Noise ·
No adverse impact anticipated |
Rail
Noise ·
Annexes 5 and 13 of the EIAO-TM |
Rail
Noise N/A |
Rail
Noise ·
Floating slab trackform, and high attenuation
baseplate etc., subject to findings of a separate EIA |
·
No residual impacts anticipated. |
|
Road
Traffic Noise ·
Predicted overall noise levels: up to 73 dB(A) ·
Predicted road traffic noise levels of the Project
roads: up to 73 dB(A) |
Road
Traffic Noise ·
Annexes 5 and 13 of the EIAO-TM ·
EIAO-GN 12/2023 ·
L10(1 hour) 70dB(A) at 1m from the façade
of residential dwellings / noise sensitive temporary structures ·
L10(1 hour) 65dB(A) at 1m from the façade
of educational institute |
Road
Traffic Noise ·
Exceedance of the noise criteria by up to 2 dB(A)
for planned residential uses and up to 8 dB(A) for planned schools |
Road
Traffic Noise ·
Provision of low noise road surfacing (LNRS) on
Local Roads L1 and L8. ·
Provision of at-receiver mitigation measures such as
acoustic window for residential uses ·
Provision of noise insulation with suitable window
type and air-conditioning for schools. |
Road
Traffic Noise ·
No residual impacts anticipated. |
|
Marine
Traffic Noise ·
Predicted cumulative peak marine traffic hour Leq(1-hr)
of 49 to 63 dB(A) ·
Predicted peak marine traffic hour Leq(1-hr)
of 40 to 58 dB(A) due to Project-related vessels |
Marine
Traffic Noise ·
Measured Prevailing noise level (Leq(1-hr))
during peak marine traffic hour (ranged from 54 to 64 dB(A)) |
Marine
Traffic Noise ·
No exceedance predicted |
Marine
Traffic Noise ·
No mitigation measure required |
Marine
Traffic Noise ·
No residual impacts anticipated. |
|
Water Quality Impact |
|||||
Construction
Impact |
|||||
·
Seawater intakes, secondary contact recreation
subzone, ecological and fisheries sensitive receivers such as coral
communities and fish culture zones |
·
Full compliances with water quality assessment
criteria were predicted except for suspended solids (up to 15.8 mg/L) and
sedimentation rates (up to 650g/m2/day) |
· EIAO-TM
Annexes 6 and 14 · Water
Quality Objectives (WQOs) stipulated under Water Pollution Control Ordinance
(WPCO) · Technical
Memorandum Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS) · Water
Supplies Department (WSD) Water Quality Criteria for Flushing Water Intakes · Raw water quality design basis values for the first stage of TKO
desalination plant |
·
Exceedance of the assessment criteria for suspended
solids elevations by up to 12 mg/L for coral communities near TKO 132 ·
Exceedance of the sedimentation criteria by up to
550 g/m2/day for coral communities near TKO 132 |
· Deployment
of silt curtains around marine construction works · Mitigation
measures and good site practices in ProPECC PN 2/23 · Precautionary
measures in ETWB Technical Circular (Works) No. 5/2005 · Waste
Disposal (Chemical Waste) (General) Regulation · Provision
of interim treatment facilities, such as chemical toilets, for construction
workforce · Use of
non-dredged reclamation method · Carrying
out underwater filling behind leading seawall · Control
of production rates for reclamation / sediment removal works |
·
No residual water quality impact |
Operation
Impact |
|||||
·
Seawater intakes, secondary contact recreation
subzone, ecological and fisheries sensitive receivers such as coral
communities and fish culture zones |
·
Full compliances with water quality assessment
criteria were predicted at all representative WSRs except for 10 WSRs where
the predicted TIN level exceeded the WQO and 1 WSR where the predicted E.
coli level exceeded the WQO. |
· EIAO-TM
Annexes 6 and 14 · WQOs
stipulated under WPCO · TM-DSS · WSD
Water Quality Criteria for Flushing Water Intakes · Raw water quality design basis values for the first stage of TKO
desalination plant |
·
For the 10 WSRs with WQO exceedances for TIN
(including bathing beaches, coral sites, Shek O headland SSSI, important
spawning/nursery ground of commercial fisheries resources), there is no
noticeable difference in the predicted TIN levels between all the modelling
scenarios (i.e., with or without the Project). These exceedances are not
caused by this Project. ·
For the 1 WSR with WQO exceedance for E.coli (Po
Toi O FCZ), there is no noticeable difference in the predicted E.coli
levels between all the modelling scenarios (i.e., with or without
the Project). These exceedances are not caused by this Project. |
· Precautionary
design measures to prevent emergency discharges from EPP and SPS · Emergency
Contingency Plan to deal with power / treatment failure at EPP and SPS · Design
measures and practices in ProPECC PN 1/23 · Develop
and implement Environmental Management Plan for Public Facilities at TKO 132 · Best management practices for storm water management · DSD's “Sewerage Manual (Part 2) Pumping Stations and Rising Mains” |
·
No residual water quality impact |
Sewerage and Sewage Treatment Implications |
|||||
·
Existing and planned sewerage system, sewage
treatment and disposal facilities |
·
Increase in sewage discharge arising from the
population and potential waterborne pollution |
• DSD’s Sewerage Manual, Drainage Record Plan and standard drawings; • EPD’s Guidelines for Estimating Sewage Flows for Sewage Infrastructure
Planning (GESF) Version 1.0; and • Annex 14 of the EIAO-TM |
·
N/A |
· Precautionary
design measures to prevent emergency discharges from EPP and SPS · Emergency
Contingency Plan to deal with power / treatment failure at EPP and SPS |
·
N/A |
Waste Management Implications |
|||||
Construction
Impact |
|||||
·
N/A |
·
Around 123,500 m3 of non-inert C&D
materials and 5,164,970 m3 of inert C&D materials will be
generated from reclamation, site clearance, site formation works,
construction of viaducts, buildings and infrastructures. ·
Chemical wastes will be generated from plant
operation and maintenance of mechanical equipment, at a few hundred litres
per month. ·
Around 2,535 kg per day and 585 kg per day of
general refuse will be generated from construction works and site- based
staff and workers at TKO 137 and TKO 132 respectively. ·
Approximately 9,951m3 of sediment from
TKO 137 and 184,601 m3 of sediment from TKO 132 will be disposed
of at the marine disposal areas. ·
Around 6.8 m3 per year at TKO 137 and 4.4
m3 per year at TKO 132 of floating refuse will be generated from construction
activities at / near the sea and accumulation along seawall. |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Chemical Waste) (General) Regulation
(Cap. 354C) ·
Waste Disposal (Charges for Disposal of Construction
Waste) Regulation (Cap. 354N) ·
Land (Miscellaneous Provisions) Ordinance (Cap. 28) ·
Public Health and Municipal Services Ordinance (Cap.
132BK) – Public Cleansing and Prevention of Nuisances Regulation ·
Dumping at Sea Ordinance (DASO) (Cap.466) ·
Project Administration Handbook for Civil
Engineering Works (PAH) |
·
N/A |
·
Implementation of good site practices, waste
reduction measures and proper storage, collection and transport of waste ·
Careful design, planning and good site management to
reduce generation of C&D materials ·
Monitoring of disposal of C&D waste with
trip-ticket system and installing CCTV on site |
·
No residual impact anticipated |
Operation
Impact |
|||||
·
N/A |
·
Around 350 tonnes per day of municipal solid waste
will be generated from TKO 137 and TKO 132 ·
Small quantity of chemical wastes in the order of a
few cubic metres per month will be generated from maintenance and service
activities and laboratories in education institutions at TKO 137. ·
Around 40 tonnes per day of concrete waste and
sludge will be generated from operation of the concrete batching plant and
construction waste handling facility at TKO 132 ·
About 27 m3/day of sewage sludge and 26 m3/day
of screening and grits will be generated from TKO 137 EPP and TKO 132 SPS. ·
Around 6.8 m3 per year at TKO 137 and 4.4
m3 per year at TKO 132 of floating refuse will be generated from
accumulation along seawall. |
·
Annexes 7 and 15 of the EIAO-TM ·
Waste Disposal Ordinance (Cap. 354) ·
Waste Disposal (Chemical Waste) (General) Regulation
(Cap. 354C) ·
Public Health and Municipal Services Ordinance (Cap.
132BK) – Public Cleansing and Prevention of Nuisances Regulation |
·
N/A |
·
Implementation of waste reduction measures and
proper storage, collection and transport of waste |
·
No residual impact anticipated |
Land Contamination |
|||||
·
Onsite construction workers and future occupants |
·
A total of 2 areas with potential land contamination
concerns (i.e. an oil stain at the skips storage and skip lorries parking
area (Site S1) and the future concrete batching plant and transformer room
(Site S2)) were identified at TKO 137 within the Project area. |
·
Annex 19 of the EIAO-TM ·
Guidance Note for Contaminated Land Assessment and
Remediation (EPD, April 2023) ·
Practice Guide for Investigation and Remediation of
Contaminated Land (EPD, April 2023) ·
Guidance Manual for Use of Risk-based Remediation
Goals for Contaminated Land Management (EPD, April 2023) |
·
N/A |
·
A sampling and testing programme, targeting the
hotspot identified within Site S1 had been proposed. ·
Further site appraisal should be carried out for the
two concerned sites when site operation has ceased / after site handover in
order to assess the latest site conditions / to identify the presence of any
potential land contamination sources, and to address any new contamination
issues caused by any changes in site operation and/or land use within the two
concerned sites. Any necessary site investigation SI works and
remediation action are recommended to be carried out after the site operation
has ceased / decommissioning of the facility but prior to the commencement of
construction works at the concerned sites / areas. ·
The further works including further site appraisal,
associated SI works, any necessary remediation works and submission of CAP,
CAR / RAP / RR would follow the relevant Guidance Manual, Guidance Note and
Practice Guide. |
·
No residual impact anticipated. |
Landfill Gas Hazard |
|||||
Construction
Impact |
|||||
·
Onsite construction workers |
·
Quantitative landfill gas hazard is conservatively
assessed as “Medium” or “Low” risk for construction phase based on the
source, pathway and target risk categories for the proposed development
located within the Consultation Zone for the SENT and SENTX. |
·
Annex 7 & 19 of the EIAO-TM ·
Landfill Gas Hazard Assessment Guidance Note |
·
N/A |
·
Safety requirements stated in Chapter 8 - Hazards
Arising During Construction of the Landfill Gas Hazard Assessment Guidance
Note should be implemented properly during construction phase. |
·
No residual impact anticipated. |
Operation
Impact |
|||||
·
Future occupants |
·
Quantitative landfill gas hazard is conservatively
assessed as “High”, “Medium” or “Low”, for operation phase based on the
source, pathway and target risk categories for the proposed development
located within the Consultation Zone for the SENT and SENTX. |
·
Annex 7 & 19 of the EIAO-TM ·
Landfill Gas Hazard Assessment Guidance Note |
·
N/A |
·
“Passive” and “Active” control measures should
be considered for developments categorised as “Medium” or “High” Risk
respectively. ·
For developments of which the landfill gas risk is
categorised as “Low”, some precautionary measures may be required to ensure
that the planned development is safe, however the measures which depend on
the actual design of indoor facilities if any (such as toilets). |
·
No residual impact anticipated. |
Ecological Impact (Terrestrial and Marine) |
|||||
Construction
Impact |
|||||
·
Recognised sites of conservation importance and
other ecologically sensitive sites ·
Terrestrial and marine habitats ·
Wildlife (including flora and fauna species of
conservation importance) |
·
Major permanent loss of sea area (subtidal hard
substrata habitat) ·
Permanent and temporary loss of natural habitats
including terrestrial habitat (mixed woodland, shrubland, shrubby
grassland/grassland), intertidal habitat (rocky shore and soft shore), and
sea area (subtidal soft substrata habitats) ·
Direct impact on floral species of conservation
importance and hard and black coral communities ·
Potential direct injury / mortality of wildlife
species ·
Indirect disturbance impact (e.g. air quality,
noise, light pollution, water quality, traffic and visual) on natural
habitats and associated wildlife in the vicinity |
·
Annexes 8 and 16 of the EIAO-TM ·
EIAO Guidance Notes Nos. 3/2010, 6/2010, 7/2023 and
10/2023 |
·
N/A |
·
Avoided loss of site of conservation importance and
other ecologically sensitive sites ·
Avoided direct impact on nesting Black Kite and
potential movement corridor of Philippine Neon Goby, as well as the stream
(i.e. S2) which the Goby was previously recorded. ·
Minimisation of adverse impact to recognised site of
conservation importance and natural habitats ·
Minimisation on the direct loss of terrestrial and
marine natural habitats and associated wildlife through careful design of the
Project layout ·
Translocation of affected coral colonies with high
ecological value ·
Protection / transplantation of floral species of
conservation importance ·
Minimisation of direct mortality of wildlife ·
Pre-construction survey to identify the presence of
faunal species of conservation importance within the Project area, esp.
breeding site and low mobility species ·
Good site practices with mitigation measures for
noise, dust, light and glare and water quality (esp. marine water) impacts |
·
No unacceptable residual impact anticipated |
Operation
Impact |
|||||
·
Recognised Sites of Conservation Importance and
Other Ecologically Sensitive Sites ·
Terrestrial and Marine Habitats ·
Wildlife (including flora and fauna species of
conservation importance) |
·
Temporary loss of subtidal soft substrata due to
maintenance sediment removal in TKO 132 ·
Indirect disturbance impact (e.g. air quality,
noise, light pollution, water quality, traffic and visual) on natural
habitats and associated wildlife in the vicinity ·
Changes in hydrodynamic properties and water quality
pattern |
·
Same as construction phase |
·
N/A |
·
Minimisation of direct impact on hard coral
communities through careful consideration on the extend of maintenance
sediment removal (i.e. conduct only in area with water depth >8m) ·
Adoption of planning design subject to its
feasibility (e.g. vegetation buffer) to minimise potential injury / mortality
of wildlife ·
Good site practices with mitigation measures for
noise, dust, light and glare and water quality (esp. marine water) impacts ·
Enhancement measures including eco-shoreline /
ecological enhanced seawall to provide additional hard substrata for the
recolonisation of intertidal fauna and corals ·
Greening opportunity on buildings such as green
façades and green roofs |
·
No unacceptable residual impact anticipated |
Fisheries Impact |
|||||
·
Fish Culture Zones in Tung Lung Chau and Po Toi O,
spawning grounds of commercial fisheries resources at eastern waters, nursery
area of commercial fisheries resources at Port Shelter, Artificial Reefs at
Outer Port Shelter |
·
Direct loss of fishing ground and fisheries habitat ·
Changes in water quality ·
Change in hydrodynamics ·
Underwater sound |
·
EIAO-TM Annexes 9 & 17 ·
Water Pollution Control Ordinance (Cap. 358) |
·
N/A |
·
Mitigation measures and good site practices as
proposed in Water Quality section would further minimise fisheries impacts. |
·
No residual impact anticipated |
Cultural Heritage Impact |
|||||
Construction
Impact |
|||||
·
Built heritage and other identified items |
·
No adverse impact on built heritages and other
identified items would be anticipated. |
·
EIAO-TM Annexes 10
and 19 |
·
N/A |
·
No mitigation measures would be required. |
·
No residual impact
anticipated |
·
Terrestrial archaeological heritage |
· No direct impact on terrestrial archaeological heritage is anticipated
except the areas
on Fat Tau Chau within the Project boundary of TKO137 on which there would
possibly be potential impact during the construction phase. ·
Indirect impacts of ground-borne vibration, tilting
and ground settlement are anticipated on Fat Tau Chau House Ruin SAI (SAI185) |
·
EIAO-TM Annexes 10
and 19 ·
Antiquities and
Monuments Ordinance (A&MO) (Cap.53) |
·
N/A |
Monitoring
of vibration, settlement and tilting · A condition and structural
survey, as well as a baseline vibration review shall be conducted for
construction works located in close proximity to the Fat Tau Chau House Ruin
SAI (SAI185). · Condition and structural survey
should be carried out for Fat Tau Chau House Ruin SAI (SAI185) both before
and after all construction works to inspect its physical condition and
structural integrity. The pre- and post- condition survey reports should
be submitted for AMO’s record. · Based on the pre-construction
condition and structural survey results and construction details, the
baseline vibration review before the construction phase shall evaluate if
monitoring of ground-borne vibration, tilting and ground settlement is
required for Fat Tau Chau House Ruin SAI during the construction phase.
The baseline vibration review should be submitted to AMO for comment
and agreement before implementation. · Any vibration and building
movement induced from the construction works should be strictly monitored to
ensure no disturbance and physical damages made to the heritage sites during
the course of works. If monitoring of ground-borne vibration is
required, a monitoring proposal, including vibration limit, type of
monitoring, checkpoint locations, installation details and frequency of
monitoring should be submitted by contractor to AMO for agreement before
commencement of the works. Prior agreement and consent should be sought
from the owner(s), stakeholder(s) and relevant Government department(s) for
the installation of monitoring points on the archaeological heritage before
commencement of the works. · Should the monitoring data be
approaching to the vibration limit, the contractor shall propose measures to
mitigate movement situation at the heritage site for consideration by AMO and
implement on site, with examples, not limited to, increasing monitoring
frequency, additional condition surveys, amendment / review of design of the
construction, etc., so that the concerned archaeological heritage would be
protected and preserved. · AMO should be informed
immediately should irregularities be observed. Dust Suppression · Due to the close proximity of
the Fat Tau Chau House Ruin SAI (SAI185) to the Project Boundary, dust from
the works area might have potential impact. Air Pollution Control
(Construction Dust) Regulation shall be followed. · Dust suppression measures and
good site practice should be observed by the project proponent during the
construction phase in order to avoid dust accumulation on Fat Tau Chau House
Ruin SAI (SAI185). Buffer Zone · A buffer zone should be
reserved during the construction phase of the Project to safeguard Fat Tau
Chau House Ruin SAI (SAI185). · The buffer zone should be
established in the form of physical barrier to separate the works area from
the concerned structures. · No works shall be allowed
within the buffer zone. No workers or any construction related
equipment and materials should trespass the buffer zone to avoid direct
contact with Fat Tau Chau House Ruin SAI (SAI185). · It is suggested that the buffer
zone should be of 10m from the concerned SAI or as practical as
possible. Considering the challenging terrain of the environment
nearby, implementation details shall be proposed by the contractor and agreed
with AMO prior to commencement of the proposed works. Archaeological Impact
Assessment at the detailed design phase · To ensure no archaeological
resources related to the Customs Station or other facilities on Fat Tau Chau
would be affected by the Project, an Archaeological Impact Assessment should
be undertaken during the detailed design phase when the details of the proposed
works on Fat Tau Chau are available. This Archaeological Impact
Assessment at the detailed design phase shall assess the archaeological
potential concerning the existence of remains or features in relations to the
Customs Stations or other facilities within the Project boundary of TKO 137
on Fat Tau Chau, particularly in areas that would be affected by the proposed
works. Based on the details and extent of proposed works to be carried
out on Fat Tau Chau, the Archaeological Impact Assessment at the detailed
design phase would propose appropriate measures if any impact on
archaeological heritage is identified, for consideration and agreement by
AMO. The Archaeological Impact Assessment at the detailed design phase
shall be conducted by an archaeologist. It shall incorporate desktop
information, site inspection results and recommendation of appropriate
mitigation measures if necessary, namely change of work design, preservation
of archaeological heritage in-situ, preservation by relocation,
archaeological survey cum excavation or rescue excavation, archaeological
watching brief or preservation by record subject to the level of potential
impacts to be confirmed in the Archaeological Impact Assessment upon availability
of the details and extent of the proposed works to be carried out on Fat Tau
Chau, as necessary for consideration and agreement by AMO. This
Archaeological Impact Assessment at the detailed design phase should be
conducted by the project proponent. In the light of the above
considerations, no adverse impact would be anticipated with mitigation
measures agreed by AMO and implemented to the satisfaction of AMO to ensure
preservation of the archaeological heritage within the Project boundary of
TKO 137 on Fat Tau Chau. Precautionary
Measure · If antiquities or supposed
antiquities under the Antiquities and Monuments Ordinance (Cap. 53) are
discovered during the construction works within the Project boundary of TKO
137 and TKO 132, the project proponent is required to inform AMO immediately
for discussion of appropriate mitigation measures to be agreed by AMO before
implementation by the project proponent to the satisfaction of AMO. |
·
No residual impact
anticipated |
·
Marine archaeological heritage |
·
No impact on marine archaeology is anticipated from
this project. |
·
EIAO-TM Annexes 10
and 19 ·
Guidelines for
Marine Archaeological Investigation |
·
N/A |
·
As a precautionary
measure, it is recommended to designate the locations with data gaps and the
uninvestigated anomaly as archaeological exclusion zones during the marine
works of the Project to ensure no impact on the seabed from anchoring of work vessels during
the marine works of the Project in these locations. |
·
No residual impact anticipated. |
Operation
Impact |
|||||
·
Built heritage and other identified items |
·
No adverse impact would be anticipated on built
heritages and other identified items during the operational phase. |
·
EIAO-TM Annexes 10 and 19 |
·
N/A |
·
No mitigation measure would be required. |
·
No residual impact anticipated. |
·
Terrestrial archaeological heritage |
·
No adverse impact would be anticipated on
terrestrial archaeology during the operational phase. |
·
EIAO-TM Annexes 10 and 19 |
·
N/A |
·
No mitigation measure would be required. |
·
No residual impact anticipated. |
·
Marine archaeological heritage |
·
No impact on marine archaeology is anticipated from
this project. |
·
EIAO-TM Annexes 10
and 19 ·
Guidelines for
Marine Archaeological Investigation |
·
N/A |
·
No mitigation measure would be required. |
·
No residual impact anticipated. |
Landscape and Visual Impacts |
|||||
Construction
Impact |
|||||
·
Landscape Resources (LRs) |
·
Negligible impact on hillside vegetation along
Eastern Boundary of TKO 137 (LR5), SENT Landfill (LR7), vegetation on
modified slope and amenity planting (LR10) and vegetation in developed area (LR14) ·
Slight impact on the vegetation along drainage
channel (LR4), roadside planting (LR8) and orchard/ vegetation near rural
settlement (LR12) ·
Moderate impact on the vegetation within TKO 137
(LR1), hillside vegetation at Devil’s Peak (LR2), shrubland at Tit Cham Chau
and Fat Tong Chau (LR3), portion of coastal water (LR6), rocky shore
along western coastline of Junk Bay (LR9), hillside vegetation at Chiu Keng
Wan Shan (LR11) and sandy shore along western coastline of Junk Bay (LR13) |
·
Annexes 10 and 18 of the EIAO – TM ·
EIAO – GN 8/2023 |
·
NA |
·
Tree Preservation and Transplantation ·
Preservation of Natural Coastline ·
Erection of Decorative Screen Hoarding ·
Management of Construction Activities and Facilities
·
Reinstatement of the affected landscaped area |
·
Negligible residual impact on LR5, LR7, LR10
and LR14 ·
Slight residual impact on LR4, LR8 and LR12 ·
Moderate residual impact on LR1, LR2, LR3, LR6, LR9,
LR11 and LR13 |
·
Landscape Character Areas (LCAs) |
·
Negligible impact on SENT Landfill and Ongoing Major
Development Landscape (LCA6), TKO Industrial Urban Landscape (LCA7), Junk Bay
Cemetery Landscape (LCA10), Tiu Keng Leng Urban Residential Landscape (LCA11) ·
Slight impact on Fat Tong O Industrial Urban
Landscape (LCA8), TKO Transportation Corridor Landscape (LCA9) ·
Moderate impact on Fat Tong O Reclamation Landscape
(LCA1), Fat Tong Chau and Tin Ha Au Upland and Hillside Landscape (LCA2),
Chiu King Wan Upland and Hillside Landscape (LCA3), Tathong Channel and Joss
House Bay Inshore Water Landscape (LCA4), Junk Bay Bay Landscape (LCA5) |
·
Annexes 10 and 18 of the EIAO – TM ·
EIAO – GN 8/2023 |
·
NA |
·
Tree Preservation and Transplantation ·
Preservation of Natural Coastline ·
Erection of Decorative Screen Hoarding ·
Management of Construction Activities and Facilities
·
Reinstatement of the affected landscaped area |
·
Negligible residual impact on LCA6, LCA7, LCA10 and
LCA11 ·
Slight residual impact LCA8 and LCA9 ·
Moderate residual impact LCA1, LCA2, LCA3, LCA4 and
LCA5 |
Operation
Impact |
|||||
·
Landscape Resources (LRs) |
·
Negligible impact on hillside vegetation along
Eastern Boundary (LR5) of TKO 137, SENT Landfill (LR7), vegetation on
modified slope and amenity planting (LR10),
vegetation in developed area (LR14) ·
Slight impact on vegetation along drainage channel
(LR4), roadside planting (LR8), orchard/ vegetation near rural settlement
(LR12) ·
Moderate impact on the vegetation within TKO 137
(LR1), hillside vegetation at Devil’s Peak (LR2), shrubland at Tit Cham Chau
and Fat Tong Chau (LR3), coastal water (LR6), rocky shore along western
coastline of Junk Bay (LR9), hillside vegetation at Chiu Keng Wan Shan
(LR11), sandy shore along western coastline of Junk Bay (LR13) |
·
Annexes 10 and 18 of the EIAO – TM ·
EIAO – GN 8/2023 |
·
Aesthetically pleasing design of Aboveground
Structures ·
Buffer Screen Planting ·
Roof Greening ·
Roadside Greening ·
Open Space provision ·
Compensatory Tree Planting ·
Landscape Treatments on Slope or Retaining Structure ·
Shoreline Treatment |
Upon Day 1 of operation: ·
Negligible residual impact on LR5, LR7, LR10 and
LR14 ·
Slight residual impact on LR1, LR2, LR3, LR4, LR8,
LR11 and LR12 ·
Moderate residual impact on LR6, LR9 and LR13 Upon
Year 10 of operation ·
Negligible residual impact on LR1, LR2, LR3, LR4,
LR5, LR7, LR8, LR10, LR11, LR12 and LR14 ·
Slight residual impact on LR9 and LR13 ·
Moderate residual impact on LR6 |
|
·
Landscape Character Areas (LCAs) |
·
Negligible impact on SENT Landfill and Ongoing Major
Development Landscape (LCA6), TKO Industrial Urban Landscape (LCA7), Junk Bay
Cemetery Landscape (LCA10), Tiu Keng Leng Urban Residential Landscape (LCA11) ·
Slight impact Fat Tong O Industrial Urban Landscape
(LCA8), TKO Transportation Corridor Landscape (LCA9) ·
Moderate to substantial impact on Fat Tong O
Reclamation Landscape (LCA1), Fat Tong Chau and Tin Ha Au Upland and Hillside
Landscape (LCA2), Chiu King Wan Upland and Hillside Landscape (LCA3), Tathong
Channel and Joss House Bay Inshore Water Landscape (LCA4), Junk Bay Bay
Landscape (LCA5) |
·
Annexes 10 and 18 of the EIAO – TM ·
EIAO – GN 8/2023 |
·
Aesthetically pleasing design of Aboveground
Structures ·
Buffer Screen Planting ·
Roof Greening ·
Roadside Greening ·
Open Space provision ·
Compensatory Tree Planting ·
Landscape Treatments on Slope or Retaining Structure ·
Shoreline Treatment |
Upon Day 1 of operation: ·
Negligible residual impact on LCA6, LCA7, LCA10 and
LCA11 ·
Slight residual impact LCA1, LCA2, LCA3, LCA8 and
LCA9 ·
Moderate residual impact on LCA4 and LCA5 Upon Year 10 of operation: ·
Negligible residual impact on LCA1, LCA2, LCA3,
LCA6, LCA7, LCA8, LCA9, LCA10 and LCA11 ·
Moderate residual impact LCA4 and LCA5 |
|
·
Key Public Viewpoint (VPs) |
·
Slight impact on view from Waterfront of LOHAS Park
(VP3), view from TKO InnoPark (VP6) and view from Tseung Lam Highway Garden
(VP12) ·
Moderate impact on view from view from dragon’s Back
Trail (VP1), Siu Sai Wan Promenade (VP2), view from TKO Waterfront Park
(VP4), view from LOHAS Park (VP5), view from Tung Lung Chau Lookout (VP9) and
view from the Heng Fa Chuen Promenade (VP11) ·
Substantial impact on view from lookout of the
Devil’s Peak (VP7), view from Tin Ha Shan (VP8), view from the traveller
along the ferry route along the Tathong Channel (VP10) |
·
Annexes 10 and 18 of the EIAO – TM ·
EIAO – GN 8/2023 |
·
Aesthetically pleasing design of Aboveground
Structures ·
Buffer Screen Planting ·
Roof Greening ·
Roadside Greening ·
Open Space provision ·
Compensatory Tree Planting ·
Landscape Treatments on Slope or Retaining Structure ·
Shoreline Treatment |
Upon Day 1 of operation: ·
Sight residual impact on VP1, VP3, VP4, VP5, VP6 and
VP12 ·
Moderate residual impact on VP2, VP9 and VP11 ·
Substantial residual impact on VP7, VP8 and VP10 Upon Year 10 of operation: ·
Negligible residual impact on VP1, VP3, VP4, VP5,
VP6 and VP12 ·
Sight residual impact on VP2, VP9 and VP11 ·
Moderate residual impact on VP7, VP8 and VP10 |
|
Hazard to Life |
|||||
·
Existing and planned population in the vicinity of
the planned desalination plant, existing SNG production plant, proposed EPP,
explosive off-loading pier and proposed green fuel station (GFS) |
·
The off-site individual risk level is far below 1×10-5
per year for the planned desalination plant and proposed EPP, while the 1×10-5
per year is confined within the plant boundary for the existing SNG
production plant and proposed GFS. Thus, it is considered acceptable and in
compliance with the relevant criterion in Annex 4 of EIAO-TM ·
The societal risks fall
within the “Acceptable” region in both assessment years ·
No
foreseeable risk implication on the Project as the explosive off-loading pier
will be decommissioned before commencement of construction activities within
500m from the pier |
·
Annex 4 of the EIAO-TM |
·
N/A |
·
No adverse impact is anticipated. |
·
No residual impact anticipated |
Electric and Magnetic Field |
|||||
·
Proposed EFs and Electricity Substation |
·
Maximum electric field strength anticipated to be up
to 10 V/m ·
Maximum magnetic flux anticipated to be up to 72
μT ·
Both electric field strength and magnetic flux
density comply with criteria. No adverse electric and magnetic field impact
would be anticipated. |
·
International Commission on Non-ionizing Radiation
Protection 1998 (Standard for General Public Exposure: 5,000 V/m & 100
μT; Standard for Occupational Exposure 10,000 V/m & 500 μT) ·
Hong Kong Planning Standards and Guidelines |
·
N/A |
·
Not necessary |
·
No residual impact anticipated |
[1] The CWHF to be provided in TKO 132 may also
incorporate the function of the temporary construction waste sorting facility
(temp. CWSF) currently located in TKO 137. Unlike the existing open air
operation at the temp. CWSF, such future operation, if any, will be carried out
in enclosed environment.
[2] The MRCP was proposed during the PODP stage
and has been excluded from the RODP.
[3] The EFs are a strategic infrastructure that
will account for about 30% of Hong Kong total fuel mix
for electricity generation for enhancing
Hong Kong’s capability to import zero-carbon energy through
regional cooperation and meeting the
decarbonisation target of reducing Hong Kong’s carbon emissions by 50% before
2035 as compared to the 2005 level, with a view to achieving carbon neutrality
before 2050.
[4] Location of JBDGA is extracted from Marine
Chart by Marine Department’s “eSeaGo”