Reference Number |
Date of Submission |
Project Title |
Permit Holder |
Status |
SEP-167/2023 |
5 Dec 2023 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Highways Department |
The Permit Holder surrendered part of EP-364/2009/H on 5 December 2023.
Link to other related information |
SEP-163/2023 |
10 Jul 2023 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Chun Wo - CRGL - MBEC Joint Venture |
The Permit Holder surrendered FEP-07/364/2009/H on 10 Jul 2023
Link to other related information |
SEP-156/2022 |
26 Apr 2022 |
Wan Chai Development Phase II and Central-Wan Chai Bypass |
Civil Engineering and Development Department |
The Permit Holder surrendered EP-356/2009 on 1 Jun 2022.
Link to other related information |
SEP-154/2021 |
4 Nov 2021 |
Central Reclamation Phase III |
Civil Engineering and Development Department |
The Permit Holder surrendered EP-122/2002/E on 1 Dec 2021.
Link to other related information |
SEP-149/2021 |
12 May 2021 |
Wan Chai Development Phase II - Central - Wan Chai Bypass - Tunnel (Slip Road 8 Section) (Contract No. HY/2010/08) - Marine Works |
China State Construction Engineering (Hong Kong) Limited |
The Permit Holder surrendered FEP-07/356/2009 on 12 May 2021.
Link to other related information |
SEP-148/2021 |
12 May 2021 |
Wan Chai Development Phase II - Central - Wan Chai Bypass - Tunnel (Slip Road 8 Section) (Contract No. HY/2010/08) - Road Tunnel and Slip Roads |
China State Construction Engineering (Hong Kong) Limited |
The Permit Holder surrendered FEP-10/364/2009/B on 7 Jun 2021.
Link to other related information |
SEP-147/2021 |
5 Mar 2021 |
Central - Wan Chai Bypass - Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning (Contract No. HY/2011/08) |
Leighton Joint Venture |
The Permit Holder surrendered FEP-11/364/2009/B on 27 Jan 2021.
Link to other related information |
SEP-146/2021 |
9 Feb 2021 |
Central - Wan Chai Bypass - Tunnel Buildings, Systems and Fittings, and Works Associated with Tunnel Commissioning (Contract No. HY/2011/08) |
Leighton Joint Venture |
The Permit Holder surrendered FEP-11/364/2009/E on 27 Jan 2021.
Link to other related information |
SEP-140/2020 |
6 Apr 2020 |
DP2-Road P2 and other roads which are classified as primary/district distributor roads |
China State - Build King Joint Venture |
The Permit Holder surrendered FEP-02/376/2009 on 15 Apr 2020.
Link to other related information |
SEP-139/2020 |
6 Apr 2020 |
DP2-Road P2 and other roads which are classified as primary/district distributor roads |
China State Leader Joint Venture |
The Permit Holder surrendered FEP-01/376/2009 on 15 Apr 2020.
Link to other related information |
SEP-138/2020 |
6 Apr 2020 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
China State - Build King Joint Venture |
The Permit Holder surrendered FEP-12/364/2009/D on 15 Apr 2020.
Link to other related information |
SEP-131/2019 |
18 Oct 2019 |
Wan Chai Development Phase II and Central-Wan Chai Bypass |
China State - Build King Joint Venture |
The Permit Holder surrendered FEP-08/356/2009 on 15 Oct 2019.
Link to other related information |
SEP-113/2016 |
16 Aug 2016 |
Demolition of buildings and structures in the proposed Kennedy Town Comprehensive Development Area Site
|
New World First Bus Services Limited |
|
SEP-098/2014 |
7 Oct 2014 |
Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line
|
Gammon - Leader Joint Venture |
|
SEP-097/2014 |
7 Oct 2014 |
Wan Chai Development Phase II - Central-Wan Chai Bypass over MTR Tsuen Wan Line (Contract no. HK/2010/06) - Marine Work
|
Gammon - Leader Joint Venture |
|
SEP-093/2014 |
7 Apr 2014 |
Central Reclamation Phase III
|
Leighton - China State - Van Oord Joint Venture |
|
SEP-071/2011 |
11 Feb
2011 |
Central-Wanchai Bypass - Modification of Public Transportation Interchange (PTI) at Man Yiu Street, Central
|
Chiu Hing Contruction and Transportation Co. Ltd. |
|
SEP-070/2011 |
12 Apr
2011 |
Landslide Preventive Works at Po Shan, Mid-Levels
|
Civil Engineering and Development Department |
|
SEP-058/2009 |
8 Dec
2009 |
Expansion of Heliport Facilities at Macau Ferry Terminal
|
Hip Hing Construction Co., Ltd. |
|
SEP-057/2009 |
4 Nov
2009 |
Reprovisioning and Upgrading of Salt Water Service Reservoirs in Western District for Water Supplies Department
|
The University of Hong Kong |
|
SEP-043/2006 |
7 Dec
2006 |
Landslide Preventive Works at Po Shan, Mid-levels
|
Civil Engineering and Development Department
|
|