Environment Protection  DepartmentThe Operation of Environmental Impact Assessment Ordinance in Hong Kong
HomeContentPreviousNextImageChinese VersionEIAO Website
Image
Facts and Statistics of Applications under the EIA Ordinance

Content > The Statutory EIA Process in Action > Decisions Made Regarding Applications > Project Profiles and EIA Reports for Public Inspections and Comments > Appeal Cases

The Statutory EIA Process in Action

Types of Applications Received

From 1 April 1998 to the end of December 2001, a total of 464 applications were received by the Environmental Protection Department for over 190 projects in Hong Kong in relation to various steps within the EIA process. The distribution of these applications is shown in the following Figure 3A:

Figure 3A: Distribution of Applications
Figure 3A: Distribution of Applications

Development Pressures

Hong Kong is a dynamic and fast-moving city, with growth creating enormous developmental pressures. Among the 464 EIA Ordinance applications received within the past two years, projects involved:

* highway/bridge construction
* housing developments
* drainage/sewerage projects
* power stations/overhead power lines/felling of stacks
* railway construction
* reclamation of land/dredging of seabed
* waste incinerator/transfer stations
* land contamination work
* planning and feasibility studies.

Types of Designated Projects

Figure 3B: Applications by Designated Project Types
Figure 3B: Applications by Designated Project Types

Of these 464 applications, the majority of designated projects were for roads, railways and depots, which represented 39% of all applications. Other key project types included reclamation work (15%), drainage (9%), sewage disposal and miscellaneous small projects in environmentally sensitive areas (7% each respectively).

Please see Appendix II for a full breakdown of project types.

The distribution of designated project types amongst different categories of applications are shown in Figure 3B:

 

A summary of the cost and physical dimensions of designated projects are shown in Figure 3C:

Projects with a total estimated cost of over HK$326 billion covering

Photo of Over 93 km road of works
Over 93 km road of works;
Photo of Over 25 km of drainage works and related facility plants
Over 25 km of drainage works and related facility plants;
Photo of Over 24 km of power lines and 1 power station
Over 24 km of power lines and 1 power station;
Photo of Over 355 ha of reclamation/dredging
Over 355 ha of reclamation/dredging;
Photo of Engineering feasibility studies with a total study area of over 355 ha
Engineering feasibility studies with a total study area of over 355 ha; and
Photo of Over 75 km of railways
Over 75 km of railways;
Figure 3C:Type and Scale of Projects Covered by Applications under the EIA Ordinance

Processing Time of Applications

The EIA Ordinance stipulates a set of comprehensive timeline requirements for all key applications. Records of the first 3-1/2 years of operation indicate 100% compliance with the processing time stipulated in the EIA Ordinance.