TABLE OF CONTENTS

 

EXECUTIVE SUMMARY


1.         INTRODUCTION

Background

Project Organisation

Construction Works undertaken during the Reporting Month

Summary of EM&A Requirements

2.         AIR QUALITY MONITORING

Monitoring Requirements

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Monitoring Methodology

Results and Observations

3.         WATER QUALITY MONITORING

Monitoring Requirements

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Locations

Monitoring Methodology

Laboratory Analysis

QA/QC Procedure

Results and Observations

4.         Landscape and Visual

Landscape and Visual Audit

5.         WASTE MANAGEMENT

Waste Generation Schedule

6.         ENVIRONMENTAL AUDIT

Site Environmental Audit

Review of Environmental Monitoring Procedures

Status of Environmental Licensing and permitting

Implementation Status of Environmental Mitigation Measures

Implementation Status of Event and Action Plans

Implementation Status of Environmental Complaint Handling Procedures

7.         FUTURE KEY ISSUES

Key Issues for the Coming Month

Environmental Monitoring Program for the Next Three Months

8.         CONCLUSIONS AND RECOMMENDATIONS

Conclusions

Recommendations

 


List of Tables

 

Table 2.1           TSP Monitoring Equipment

Table 2.2           Air Quality Monitoring Parameters and Frequency

Table 3.1           Water Quality Monitoring Equipment

Table 3.2           Water Quality Monitoring Parameters and Frequency

Table 3.3           Analytical Methods to be applied to Water Quality Samples

Table 3.4           Water Quality Exceedance Summary

Table 5.1           Actual Amounts of Waste Generated in July 2006

Table 6.1           Summary of Environmental Notification, Licensing and Permit Status

 

List of Figures

 

Figure 1.1          Project Organisation

Figure 1.2          Layout of Work Site

Figure 2.1          Location of Air Quality Monitoring Station

Figure 3.1          Locations of Water Quality Monitoring Stations

 

List of Appendices

 

Appendix A        Action and Limit Levels

Appendix B       Environmental Monitoring Schedule

Appendix C       Air Quality Monitoring Results

Appendix D       Meteorological Data

Appendix E       Water Quality Monitoring Results (Graphs: DOB, DOSM, SS, TUR)

Appendix F        QA/QC Procedures and Results

Appendix G       Summary of Calibration Status

Appendix H       Site Inspection Records

Appendix I         Event and Action Plan

Appendix J        Complaint Flow Diagram and Complaint Log

Appendix K       Contact of Key Environmental Personnel