Environmental Permit No. EP-056/2000/B
環境許可證編號 EP-056/2000/B
ENVIRONMENTAL
IMPACT ASSESSMENT ORDINANCE
(CHAPTER 499)
環境影響評估條例
(第499章)
第 10 及 第13條
ENVIRONMENTAL PERMIT TO
CONSTRUCT AND OPERATE
A DESIGNATED PROJECT
建造及營辦指定工程項目的環境許可證
A部 (許可證主要部分)
Pursuant to
Section 10 of the Environmental Impact Assessment Ordinance (the Ordinance),
the Director of Environmental Protection (the Director) granted the Environmental
Permit (No. EP-056/2000) to KOWLOON-CANTON RAILWAY CORPORATION (the "Permit
Holder") on 25 May 2000. Pursuant to Section 13 of the Ordinance, the
Director amends the Environmental Permit No. VEP-022/2000/A/EP-056 based on
the Application No. VEP-152/2004. The
amendments described below, are incorporated into this Environmental Permit
(EP-056/2000/B). This Environmental Permit as amended is for the construction
and operation of the designated projects described in Part B of this Permit
subject to the conditions described in and attached to Part
C of this Permit.
根據環境影響評估條例 (條例) 第
10條的規定,環境保護署署長 (署長) 於 2000 年 5月
25日將環境許可證 (編號 EP-056/2000) 批予九廣鐵路公司 (下稱 "許可證持有人
")。根據條例第13條的規定,署長因應更改環境許可證的申請編號 VEP-152/2004修訂環境許可證編號 VEP-056/2000/A/EP-056。以下修訂已包含在本環境許可證內
(EP-056/2000/B)。本經修訂的環境許可證作為建造及營辦B部所說明的指定工程項目,但須遵守本許可證C部所說明或附載的條件。
This
Environmental Permit is based on the documents, approvals and permissions
described below:
本環境許可證乃依據下列文件、批准及許可條件而簽發 –
Application No. 申請書編號: |
VEP-152/2004 |
Document in the Register: 登記冊上的文件: |
Hung Hom to Tsim Sha Tsui
Extension – Environmental Impact Assessment Study (Register No. AEIAR-033/2000)
(4 volumes dated February 2000) [hereinafter referred to as
the “EIA Report”] The Director’s letter
approval of the EIA Report dated 24 May 2000 ref (9) in EP2/G/A/98 Pt. 4 東鐵廷伸段:紅磡至尖沙咀段環境評估 (登記冊編號:AEIAR-033/2000) (4卷 2000 年2月) [下稱“環評報告”] 署長已於2000年5月24日 ref (9) in EP2/G/A/98
Pt.4發出批准該環評報告的信。 Environmental Permit issued – Permit No.: EP-056/2000 issued on 25
May 2000. 已簽發的環境許可證 - 許可證編號: EP-056/2000於2000年5 月25日簽發。 Application for Variation of an Environmental Permit No.
VEP-022/2000. [Hereafter referred to as “the Application VEP-022/2000”] 申請更改環境許可證編號VEP-022/2000。 [下稱 “申請書編號VEP-022/2000”] Environmental Permit issued – Permit No.: VEP-022/2000/A/EP-056
issued on 25 August 2000. 已簽發的環境許可證 - 許可證編號: VEP-022/2000/A/EP-056於2000年8 月25日簽發。 Application for Variation of an Environmental Permit No.
VEP-152/2004. [Hereafter referred to as “the Application VEP-152/2004”] 申請更改環境許可證編號VEP-152/2004。 [下稱 “申請書編號VEP-152/2004”] |
Application
No. 申請 編號 |
Date of
Application 申請 日期 |
List of
Amendments Incorporated into Environmental Permit 已包含在環境許可證內的修訂項目 |
Date of
Amendments 修訂 日期 |
VEP-022/2000 |
1 August 2000 |
Conditions
2.1, 2.2, 2.4, 2.12, 2.19(a), 2.20, 2.26, 3.2, 3.5 and 4.1 of EP-056/2000. |
25 August 2000 |
|
2000年 8月1日 |
環境許可證編號EP-056/2000 C部條件第2.1, 2.2, 2.4,
2.12, 2.19(a), 2.20, 2.26, 3.2, 3.5 及 4.1 |
2000年 8月25日 |
VEP-152/2004 |
13 August 2004 |
Vary
Conditions 2.21 and 2.23 |
3 September 2004 |
|
2004年 8月13 日 |
更改第 2.21 及 2.23 項條件 |
2004年 9月3日 |
3 September 2004 Date 日期 |
|
(Mr. Elvis
W.K. AU) Assistant
Director of Environmental Protection (Environmental
Assessment and Noise) for Director
of Environmental Protection 環境保護署署長 (助 理 署 長 (環 境 評 估 及 噪 音) 區 偉 光 代 行) |
PART B (DESCRIPTIONS
OF DESIGNATED PROJECT)
B部 (指定工程項目的說明)
Hereunder is the description of the designated project mentioned in
Part A of this environmental permit:
(hereinafter referred to as the “Permit”)
下列為本環境許可證(下稱“許可證”)A部所提述的指定工程項目的說明:
Title of Designated
Project 指定工程項目的名稱 |
East Rail Extension – Hung Hom to Tsim Sha Tsui [This designated project is hereinafter referred to as “the Project”] 東鐵支線:紅磡至尖沙咀段 [這指定工程項目下稱“工程項目”] |
Nature of Designated
Project |
Construction and operation of approximately 1.5 km underground railway and its associated station. 興建和運作一條長約1.5公里的地底鐵路及有關的火車站。 |
Location of Designated
Project 指定工程項目的地點 |
Hung Hom, Tsim Sha Tsui and Ho Man Tin. The location of the project is shown in Figure
1 attached to this Permit. |
Scale
and Scope of Designated Project(s) 指定工程項目的規模和範圍 |
Construction and operation of approximately 1.5 km underground railway, a new East Tsim Sha Tsui Station, a pedestrian subway system linking the new station with MTR Tsim Sha Tsui Station running under Mody Road, Blenheim Avenue, Signal Hill and Middle Road, and a traction substation at Ho Man Tin. The scope of the project is detailed in section 1.3 of the EIA Report. 興建和運作一條長約1.5 公里的地底鐵路、一個新建的尖沙咀東站、 一組連接新火車站與尖沙咀地鐵站並沿麼地道、白蘭軒道、訊號山及中間道而建的行人隧道、及一個位於何文田的變壓站。工程範圍在環評報告1.3節詳細說明。 |
PART C (PERMIT CONDITIONS)
1. General
Conditions
1.1 The
Permit Holder shall ensure full compliance with all conditions of this
environmental permit. Any non-compliance
may constitute a contravention of the EIAO and may become subject of
appropriate action to be taken under the Ordinance.
1.2
The
Permit Holder shall ensure, from time to time, full compliance with all
legislation in force including but without limitation to the Noise Control
Ordinance (Cap. 400), Air Pollution Control Ordinance (Cap. 311), Water
Pollution Control Ordinance (Cap. 358) and Waste Disposal Ordinance (Cap.
354). This Permit does not of
itself constitute any ground of defence against any proceedings instituted
under any legislation.
1.3 The
Permit Holder shall make copies of this Permit together with all documents
referred to in this Permit or the documents referred to in Part A of this Permit
readily available at all times for inspection at all sites/offices covered by
this Permit. Any reference to the
Permit shall include all documents referred to in the Permit and also the relevant
documents in the Register.
1.4 The
Permit Holder shall give a copy of this Permit to the person(s) in charge of
the site(s) and ensure that such person(s) fully understands all conditions and
all requirements incorporated by the Permit.
1.5
The
Permit Holder shall display a copy of this Permit on the construction sites at all
vehicular site entrances/exits or at a convenient location for public
information at all times. The
Permit Holder shall ensure that the most updated information about the Permit,
including any amended permit, is displayed at such locations. If the Permit Holder surrenders a part
or the whole of the Permit, the notice he sends to the Director shall also be
displayed at the same locations as the original Permit. The suspended, varied or cancelled
Permit shall be removed from display at the construction sites.
1.6
The Permit Holder
shall construct and operate the Project as described in Part
B of this Permit.
1.7
The
Permit Holder shall ensure that the Project is designed, constructed and
operated in accordance with the information and recommendations described in
the EIA Report (Register No. AEIAR-033/2000); other relevant documents in the
Register; and the information or mitigation measures described in this Permit,
or mitigation measures to be recommended in submissions that shall be deposited
with or approved by the Director as a result of permit conditions contained in
this Permit, or mitigation measures to be recommended under on-going
surveillance and monitoring activities during all stages of the Project. Where recommendations referred to in the
documents of the Register are not expressly referred to in this Permit, such
recommendations are nevertheless to be implemented unless expressly excluded or
impliedly amended in this Permit.
1.8
All
deposited submissions as required under this Permit, shall be rectified in
accordance with the comments, if any, made by the Director, within one month of
the receipt of the Director’s comments or otherwise specified by the Director.
1.9
All submissions approved
by the Director, all submissions deposited without comments by the Director,
or all submissions rectified in accordance with comments by the Director under
this Permit shall be construed as part of the permit conditions described
in Part C of this Permit. Any variation of the submissions shall be approved by the Director
in writing or as prescribed in the relevant permit conditions. Any non-compliance with the submissions
may constitute a contravention of the EIAO.
1.10
The
Permit Holder shall release all finalized submissions, as required under this
Permit, to the public by depositing copies in the EIAO Register Office, or in
any other places, or any internet websites as specified by the Director, or by
any other means as specified by the Director for public inspection. For this purpose, the Permit Holder shall
provide sufficient copies of the submissions.
1.11
The
Permit Holder shall notify the Director in writing the commencement date of
construction of the Project at least 4 weeks before the commencement of
construction of the Project. The Permit Holder shall notify the Director in
writing immediately if there is any change of the commencement date of the
construction.
1.12
All
submissions to the Director required under this Permit shall be delivered
either in person or by registered mail to the EIAO Register Office (currently
at 27/F, Southorn Centre, 130 Hennessy Road, Wanchai, Hong Kong).
2.
Special Conditions
2.1 An
Environmental Team (ET) shall be established at least one month before the
commencement of construction. The
ET shall be headed by the ET Leader who has at least 7 years’ experience in
environmental monitoring and audit (EM&A) or environmental management. The ET Leader shall be responsible for
the implementation of the EM&A programme in accordance with the EM&A
requirements as contained in the EM&A Manual in Appendix I of the EIA
Report, or the approved EM&A Manual submitted and approved under 3.1 of this Permit. In addition, the ET Leader shall be
responsible for certifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions.
2.2
An
Independent Environmental Checker (IEC) shall be employed at least one month
before the commencement of construction of the Project. The IEC shall have at least 7 years’
experience in EM&A or environmental management. The IEC shall audit the overall EM&A programme including
the implementation of all environmental mitigation measures, submissions
relating to EM&A, and any other submissions required under this
Permit. In addition, the IEC shall
be responsible for verifying the environmental acceptability of permanent and
temporary works, relevant design plans and submissions under this Permit.
2.3
At
least 2 weeks before commencement of the construction of the Project, the
Permit Holder shall submit to and obtain approval from the Director an EM&A
Manual for the construction of the Project in accordance with details as set
out in Condition 3.1 of this Permit.
2.4
Before
the submission of the EM&A Manual required under Condition 2.3 to the
Director, the EM&A Manual shall be certified by the ET Leader and verified
by the IEC as conforming to the information and recommendations contained in
the EIA Report. All measures
recommended in the EM&A Manual shall be fully implemented in accordance
with the requirements and time schedule(s) set out in the EM&A Manual.
2.5
The
Permit Holder shall set up a Community Liaison Office to receive and respond to
complaints or enquiries from the public, the press and television media and
community groups.
2.6
The
Permit Holder shall, within 4 weeks after the commencement of construction of
the Project, inform the Director in writing the management organization of the
main construction companies and/or any form of joint ventures associated with
the construction of the Project.
The submitted information shall include at least an organization chart,
names of responsible persons and their contact details.
2.7
Three
sets of Waste Management Plan for the construction stage of the Project shall
be submitted to the Director for approval within 6 weeks after the commencement
of construction of the Project.
The Plan shall be certified by the ET Leader and verified by the IEC as
conforming to the information and recommendations contained in the EIA
Report. The Plan shall describe
the arrangements for avoidance, reuse, recovery and recycling, storage,
collection, treatment and disposal of different categories of waste to be
generated from the construction activities and shall include the recommended
mitigation measures on waste management in section 9 of the EIA Report. Such a management plan shall include
the designation of areas for segregation and temporary storage of reusable and
recyclable materials and disposal location of different categories of
waste. All measures in the
approved Waste Management Plan shall be fully implemented throughout the entire
construction period.
2.8
No
rock crushing or on-site concrete batching activity shall be implemented
throughout the entire construction period. No blasting activity shall be conducted except for the
construction of the East Tsim Sha Tsui Station (ETS) and the subway under the
Signal Hill.
Rail Alignment
2.9
The
underground alignment shall be constructed in accordance with section 1.3 of
the EIA Report. It shall have the
ETS station lying close to the Salisbury Road and completely clear of the
Signal Hill, with the concourse under the Middle Road Children’s Playground and
Wing On Plaza Garden.
Avoidance of Cutting Signal
Hill
2.10
Except
for the tunnelling works of the subway, no part of the Signal Hill shall be cut
or excavated throughout the entire construction period.
Measures to Mitigate Construction Noise
Impacts
2.11 As
recommended in section 5.2.7 of the EIA Report, all relevant Levels 1, 2, 3 and
4 noise mitigation measures shall be fully implemented throughout the entire
construction period for the relevant areas of works.
2.12 At least 4 weeks
before the commencement of relevant construction works, the Permit Holder shall
provide indirect technical remedies (ITR), in the form of upgraded glazing and
air-conditioners and in accordance with section 5.2.7.3 and Appendix D4 of the
EIA Report, to:
(a) the housing
units at Far East Mansion at Middle Road (N4) before the construction works at
ETS (Worksite 5A) and Middle Road (Worksite 6); and
(b) the units
in the following housing blocks before the construction works at Mody Road and
Blenheim Avenue (Worksite 7):
(i) Minden House at Minden & Blenheim Avenue
(N6);
(ii) No. 30 Mody Road (N7);
(iii) No. 18 Mody Road (N8);
(iv) Peninsula Apartment at Mody Road (N9);
(v) Mirador Mansion at Mody Road (N10);
(vi) Ocean View Court at Mody Road & Chatham
Road (N13 & N14); and
(vii) Lyton Building at Mody Road & Chatham Road (N16).
2.13 With
reference to Condition 2.12, the Permit Holder shall notify the Director, at
least 2 weeks before the commencement of the construction of the ETS and/or the
subway(s), of the following:
(a) the number of flats which have
been equipped with ITR; and
(b) those flats which are
eligible but eventually not equipped with ITR and the justifications behind
these, and any alternative measures proposed.
The submission(s) shall be certified by the ET and verified by the IEC.
2.14 During
the construction of the subway(s), the following Level 3 noise mitigation
measures as recommended in the EIA Report shall be implemented:
(a)
a
detailed phasing and sequencing of construction activities as specified in
Appendix D8 of the EIA Report;
(b)
use
electrically driven plant as specified in Appendix D2 of the EIA Report;
(c)
eliminate
mobile generators through the use of temporary mains supply;
(d)
use
containers to accommodate concrete pumping equipment;
(e) use
alternative quieter construction plant;
(f) use
shrouds to mitigate noise wherever practicable; and
(g) deck the worksites during
excavation and subway box construction.
2.15 The
reduced plant inventory and the use of quiet plant as specified in Appendix D2
of the EIA Report, or the equivalent combination of plant, shall be adopted for
the relevant areas of works.
2.16
All Levels 1 & 2 measures described in Annex
A to mitigate construction noise impacts shall be fully implemented for
the relevant areas of works throughout the entire construction period.
2.17 Construction
works which affect the Coliseum Podium area shall be suspended when there are
performances at the Coliseum.
Measures to Mitigate Operational Noise Impacts
2.18 The
Permit Holder shall submit to the Director for approval 3 copies of design
drawings for the ground borne noise mitigation measures (including the floating
slab track) with explanatory statements within one year after commencement of
construction. The drawings shall
be certified by the ET and verified by the IEC as conforming to the information
and recommendations in section 5.3.2.1 of the EIA Report. All measures in the drawings shall be
fully implemented before the operation of the rail.
Measures
to Mitigate Dust Impacts due to Blasting
2.19 The
following measures to mitigate the dust impacts due to blasting shall be fully
implemented:
(a)
blasting
works shall be restricted in daytime, and affected sensitive receivers shall be
informed of the blasting schedule; and
(b)
the
blasting operations shall be well managed and appropriate precautions be taken
to minimize dust generations through the use of blast nets and canvas covers.
Measures
to Mitigate Landscape and Visual Impacts
2.20 Within
4 weeks after the commencement of construction of the Project, 5 sets of
detailed master landscape drawing(s) shall be submitted to the Director for
approval. The drawing(s) shall
show the locations of no less than a total of 1500 trees that will remain within the project boundary.
2.21 Trees
to be felled, retained and/or transplanted shall be implemented in accordance
with the Landscape Masterplans (Revision 8) submitted under Condition 2.20 and
Condition 2.22. The Champion Tree No. 251 as identified in section 11.1.3 of
the EIA Report shall be protected throughout the entire construction
period.
2.22 Within
two years after the commencement of construction of the project, 5 sets of
layout plans, for the area on top of the proposed ETS showing the compensatory
planting of large trees and shrubs, adequate open space(s) and sitting out
area(s) to at least equitably replace those lost on the existing Middle Road
Children’s Playground and Wing On Plaza, shall be deposited with the Director.
2.23a The
compensatory planting and tree transplanting works as recommended in the
Landscape Masterplans (Revision 8) submitted under Condition 2.20 and Condition
2.22 shall be fully implemented in three stages as follows:
(i)
Stage
1: all trees to be planted within the project boundary at least 1 week before
the Project commences operation, except for those trees to be implemented under
the later Stage 2 and Stage 3 as stipulated below;
(ii)
Stage 2: 12 number
of trees to be planted along the Salisbury Road section of the Salisbury Road
Underpass and Associated Road Improvement Works including Middle Road Circulation
System project adjacent to Middle Road Children’s Playground, as shown in
Figure 2, upon the reinstatement of
relevant section of the Salisbury Road surface;
(iii)
Stage 3: About 400
number of trees affected by the Public Transport Interchange to be located
at the Wing On Plaza Garden under the Transport Link in Tsim Sha Tsui project
and its associated works area at Centenary Garden, as shown in Figure
3 and 4, by no later than 12 weeks
after the completion of construction of the Public Transport Interchange at
Wing On Plaza Garden under the Transport Link in Tsim Sha Tsui project.
2.23b The
Permit Holder shall notify the Director in writing:
(i)
Stage 1: the commencement date of operation of
the Project at least 2 weeks before the commencement of operation of the
Project;
The
Permit Holder shall also notify the Director in writing the dates for the
staged completion of the following works:
(ii)
Stage 2: at least 2 weeks before the completion
of construction of reinstatement for the section of Salisbury Road Underpass
and Associated Road Improvement Works including Middle Road Circulation System
project adjacent to Middle Road Children’s Playground;
(iii)
Stage 3: at least 2 weeks before the completion
of construction of the Public Transport Interchange at Wing On Plaza Garden and
its associated works area at Centenary Garden.
2.23c Five (5) sets of detailed landscape
as-built drawing(s) showing the final locations of tree plantings within the
project boundary to demonstrate compliance with the Landscape Masterplans
(Revision 8) submitted under Condition 2.20 and Condition 2.22 shall be
deposited with the Director in accordance with the following staged schedule:
(i)
Stage 1 tree planting: at least 1 week before
the Project commences operation for all trees within the project boundary,
except for those to be implemented later during Stage 2 and Stage 3;
(ii)
Stage 2 tree planting: within 1 month after the
completion of the reinstatement works for the 12 number of trees to be planted
within the area shown in Figure 2;
(iii)
Stage 3: within 3 months after the completion of
construction of the Public Transport Interchange at Wing On Plaza Garden for
those trees to be planted within the areas shown in Figure
3 and 4;
The
final set of as-built submission(s) to be deposited with the Director shall be
certified by the ET and verified by the IEC to demonstrate full compliance with
Condition 2.20 and Condition 2.22.
2.24 All
measures described in Annex
B to mitigate landscape and visual impacts shall be fully implemented
throughout the entire construction period.
Measures
to Mitigate Water Quality Impacts during Construction Stage
2.25 All
measures described in Annexes C and D to
mitigate environmental impacts from site run-off shall be fully implemented
throughout the entire construction period.
Measures
to Mitigate Archaeological/Cultural Heritage Impacts
2.26 Within
4 weeks before the commencement of the construction of the ETS or the subway under the Signal Hill, whichever is
earlier, the Permit Holder shall complete a condition survey on the historic
objects (including buildings and structures) at the Signal Hill.
2.27 The
following measures to mitigate the potential archaeological / cultural heritage
impacts during construction in accordance with section 10.4 of the EIA Report
shall be fully implemented:
(a) Prior
to commencement of any construction works for the ETS and subways, protective
scaffolding with a cover shall be erected around the Signal Hill Tower to
mitigate against any unforeseen damage during construction;
(b) To
prevent any major movement of the following historic structures, protective
scaffolding shall be erected around and/or within the Signal Hill Tower, Old
Office and Toilet Block prior to the commencement of construction work;
(c)
During
construction, structural monitoring techniques shall be applied to all the
historic objects on the site, including the Signal Hill Tower, the Pre-World
War II Brick Structures, the Battery & Retaining Wall, the Iron Winch, the
Bolts & Anchors associated with Hoisting Operation, the Stone Blocks and
remains of old structures;
(d)
All
Signal Hill historic objects as listed in Condition 2.27(c) shall be protected
during blasting. Blasting works
shall be restricted, with full controls employed to minimize impacts to areas
outside the blasting site;
(e)
In
order to partially replace the lost of public areas due to the project, the
existing disused footpaths on the north slope of the site above Minden Road
shall be upgraded and made safe for use by the public; and
(f)
The
exact specifications for all necessary protective measures for the
archaeological/ cultural heritage shall be reported under the EM&A
programme.
Measures
to Mitigate Land Contamination
2.28 At
least 10 weeks before the commencement of construction of the Project, the
Permit Holder shall submit 3 copies of the Contamination Assessment Report (CAR)
to the Director for approval.
2.29 The
CAR shall include but not limit to an investigation of potentially contaminated
land to define the full extent of any soil and/or groundwater contamination as
demonstrated through the collection of soil samples from representative
boreholes and ground water samples from representative standpipes according to
section 8.4.1 of the EIA Report.
2.30 If
land contamination is confirmed by the findings of the approved CAR as
described in Condition 2.29, the Permit Holder shall, at least 6 weeks before
the commencement of construction of the project, submit 3 copies of the
Remediation Action Plan, to the Director for approval.
2.31 All
remediation actions recommended in the approved RAP shall be fully implemented.
3. Environmental Monitoring
and Audit (EM&A) during the Construction Period
3.1 At
least 2 weeks before the commencement of construction of the Project, the
Permit Holder shall submit to and obtain approval from the Director an EM&A
Manual for the construction of the Project. Apart from those stated in Appendix I of the EIA Report, the
EM&A Manual shall also contain the necessary remedial measures in the event
that the construction noise levels exceed the worst case scenario(s) predicted
in the EIA Report.
3.2 At
least 2 weeks before the commencement of any
construction works along
Middle Road and/or Mody Road, the Permit Holder shall set up a continuous noise
monitoring mechanism to the satisfaction of the Director. The mechanism shall
include a system to report the monitoring results on KCRC’s website within a
period of time, to be agreed by the Director, after the relevant noise
monitoring data are collected or become available. This system shall be
provided throughout the entire construction period. In the event that the
measured noise levels exceed the worst case scenario(s) predicted in the EIA
report, the Permit Holder shall take immediate action(s) to activate
remediation measures following the
procedures specified in the EM&A Manual.
3.3 Samples
and measurements shall be taken in accordance with the requirements in the
EM&A Manual by:
(a) conducting baseline
monitoring on noise and air quality and a condition survey on the historic
objects at the Signal Hill, as set out in the EM&A Manual;
(b) conducting impact
monitoring on noise, air quality and cultural heritage as set out in the
EM&A Manual;
(c) carrying out remedial
actions in accordance with the Event and Action Plan, as set out in the
EM&A Manual, in cases where specified criteria in the EM&A Manual are
exceeded; and
(d) logging and keeping
records of the details of (a) to (c) above for all parameters except for
construction noise, within 3 working days of the collection of data or
completion of remedial action(s), for the purposes of preparing and submitting
the monthly EM&A Reports and to make available the information for inspection
on site.
3.4 All
EM&A data submitted under this Permit shall be true, valid and correct.
3.5 One
hard copy and one soft copy of the Baseline Monitoring Report shall be
submitted to the Director at least 4 weeks before the commencement of any construction
works. The Report shall include but without limitation to the
details of the baseline background noise and air quality, and a condition
survey on the historic objects at Signal Hill as described in Condition 3.3(a).
The submissions shall be
certified by the ET Leader and verified by the IEC. Additional copies of the submission shall be provided upon
request from the Director.
3.6 One hard copy and one soft
copy of monthly EM&A Report shall be submitted to the Director within 2
weeks from the end of the reporting month. The submissions shall be certified by the ET Leader and
verified by the IEC. Additional
copies of the submission shall be provided upon request from the Director.
3.7 The
actions described in the Event and Action Plans of the EM&A Manual shall be
fully and properly carried out, in accordance with the time frame set out in
the Event and Action Plans, or as agreed by the Director.
4. Electronic Reporting of
EM&A Information
4.1 To facilitate public
inspection of the Baseline Monitoring Report and monthly EM&A Reports via the
EIAO Internet Website and at the EIAO Register Office, electronic copies of
monthly EM&A Reports, prepared in Hyper Text Markup Language (HTML)
(version 4.0 or later) and in Portable Document Format (PDF version 4.0 or
later) unless otherwise agreed by the Director and shall be submitted at the
same time as the hard copies as described in Conditions 3.5 and 3.6 above. For the HTML version, a content page
capable of providing hyperlink to each section and sub-section of the EM&A
Reports shall be included in the beginning of the document. Hyperlinks to all figures, drawings and
tables in the EM&A Reports shall be provided in the main text from where
the respective references are made.
All graphics in the report shall be in interlaced GIF format unless
otherwise agreed by the Director.
The content of the electronic copies of the monthly EM&A Reports
must be the same as the hard copies.
4.2 All environmental
monitoring data described in Condition 4.1 above, except for construction noise
data described in Condition 3.2, shall be made available to the public via
internet access in the form of a website, in the shortest possible time and in
no event later than 2 weeks after the relevant environmental monitoring data
are collected or become available, unless otherwise agreed with the
Director. The Permit Holder shall
notify the Director in writing within 6 weeks after the commencement of works
the internet address where the environmental monitoring data are to be placed.
The internet address and the environmental monitoring data shall be made
available to the public via the EIAO Internet Website and the EIAO Register
Office.
4.3 The internet website as
described in Condition 4.2 above shall enable user-friendly public access to
the monitoring data with features capable of:
(a)
providing
access to all environmental monitoring data collected since the commencement of
works;
(b)
searching
by date;
(c)
searching
by types of monitoring data (air quality, noise and cultural heritage); and
(d)
hyperlinks
to relevant monitoring data after searching;
or
otherwise as agreed by the Director.
Notes:
1.
This Permit consists
of three parts, namely, PART A (Main Permit), PART
B (Description of Designated Project) and PART C
(Permit Conditions). Any person relying on this Permit should
obtain independent legal advice on the legal implications under the Ordinance,
and that the following notes are for general information only.
2.
The
Permit Holder may apply under section 13 of the Ordinance to the Director for a
variation of the conditions of this Permit. The Permit Holder shall replace the original Permit
displayed on the construction site by the amended Permit.
3.
A
person who assumes the responsibility for the whole or a part of the designated
project may, before he assumes responsibility of the designated project, apply
under section 12 of the Ordinance to the Director for a further environmental
permit.
4.
Under
section 14 of the Ordinance, the Director may, with the consent of the
Secretary for Environment and Food, suspend, vary or cancel this Permit. The suspended, varied or cancelled
Permit shall be removed from the display at the construction site.
5.
If
this Permit is cancelled or surrendered during the construction or operation of
the Project, another environmental permit must be obtained under the Ordinance
before the Project could be continued.
It is an offence under section 26(1) of the Ordinance to construct or
operate a designated project listed in Part I of schedule 2 of the Ordinance
without a valid environmental permit.
6.
Any
person who constructs or operates the Project contrary to the conditions in the
Permit, and is convicted of an offence under the Ordinance, is liable-
(i)
on
a first conviction on indictment to a fine of $2 million and to imprisonment
for 6 months;
(ii)
on
a second or subsequent conviction on indictment to a fine of $5 million and to
imprisonment for 2 years;
(iii)
on
a first summary conviction to a fine at level 6 and to imprisonment for 6
months;
(iv)
on
a second or subsequent summary conviction to a fine of $1 million and to
imprisonment for 1 year; and
(v)
in
any case where the offence is of a continuing nature, the court or magistrate
may impose a fine of $10,000 for each day on which he is satisfied the offence
continued.
7. The
Permit Holder may appeal against any condition of this Permit under section 17
of the Ordinance within 30 days of receipt of this Permit.
Environmental Permit No. EP-056/2000/B
Figure 1 | Figure 2 | Figure 3 | Figure 4
[ Back to First Page ] / [ Back to Main Index ]