Contents
1.2 Policy
1.4 Scope of the EM&A Programme
1.6 Terminology
2 DESCRIPTION OF PROJECT AND ASSUMPTIONS
2.1 Background
2.2 Tank Farm and Onshore Facilities
2.3 Berthing Jetty
2.4 Pipeline
2.6 Emergency Backup Facilities
3.1 Introduction
3.3 Mitigation Measures During Construction
4 NOISE
4.1 Introduction
4.3 Mitigation Measures During Construction
5 ECOLOGY
5.1 Introduction
6.2.1 Dissolved Oxygen and Temperature Measuring Equipment
6.2.2 Turbidity Measurement Instrument
6.2.3 Suspended Solids
6.2.4 Water Depth Detector
6.2.5 Salinity
6.2.6 pH Measuring Equipment
6.2.7 Location of the Monitoring Sites
6.2.8 Calibration of Equipment
6.2.9 Back-up Equipment
6.8 Water Quality Mitigation Measures
7.1 Introduction
7.5 Construction and Operational Phase Audit
8.1 Introduction
8.2 Applicable Environmental Standards and Guidelines
8.4 Waste Disposal Recommendations
10 LAND CONTAMINATION, HAZARD TO LIFE AND FUEL SPILL RISK
10.1 Introduction
10.2 Mitigation Measures
10.3 Design Phase Audit
10.4 Operational Impact Monitoring
11.1 Site Inspections
11.2 Compliance with Legal and Contractual Requirements
11.4 Choice of Construction Method
12 REPORTING
12.1 General
12.2 Documentation
12.3 Design Audit Report
12.4 Baseline Monitoring Report
12.5 EM&A Reports
12.6 First EM&A Report
12.8 Quarterly EM&A Summary Reports
12.9 Annual/Final EM&A Review Reports
12.10 Data Keeping
12.11 Interim Notifications of Environmental Quality Limit Exceedances
Tables
Table 1.1 Summary of EM&A Requirements
Table 2.1 Summary of Tank Farm Improvements
Table 2.2 Tanker Frequency Estimate
Table 3.1 Dust Management Checklist
Table 4.1 Action and Levels for Construction Noise
Table 4.2 Event/Action Plan for Construction Noise
Table 5.1 Summary of Equipment Requirements
Table 5.2 Event/Action Plan for Post Construction Dolphin Abundance Monitoring
Table 6.1 Detection Limits and Precision for Water Quality Determinands
Table 6.2 Location of Marine Water Quality Monitoring Stations
Table 6.3 Action and Limit Levels for Water Quality
Table 6.4 Event and Action Plan for Water Quality
Table 7.1 Event/Action Plan for Design Phase
Table 7.2 Construction/Operational Phase Audit Checklist
Table 7.3 Event / Action Plan for Construction Phase
Table 8.1 Recommended Waste Disposal Sites
Table 8.2 Waste Management Checklist
Table 9.1 Sub-surface Targets
Table 9.2 Event / Action Plan for Construction Phase
Table 10.1 Event/Action Plan for Design Phase
Figures
Figure 1.1 Permanent Aviation Fuel Facility Study Area
Figure 1.2 Design Phase EM&A Procedure and Organisation
Figure 1.3 Construction and Operational Phase Procedure and Organisation
Figure 2.1a Previous Concept Layout of Permanent Aviation Fuel Facility Tank Farm and Jetty within Tuen Mun Area 38
Figure 2.1b Interim Layout of Permanent Aviation Fuel Facility for Variation to Environmental Permit
Figure 2.1c Current Concept Layout of Permanent Aviation Fuel Facility Tank Farm and Jetty within Tuen Mun Area 38
Figure 2.1d Cross Section towards Shiu Wing Steel
Figure 2.1e Cross Section towards EcoPark
Figure 2.2 Pipeline Sections
Figure 3.1 Data Sheet for TSP Monitoring
Figure 4.1 Noise Monitoring Field Record Sheet
Figure 5.1 Construction Phase Ecological EM&A Procedure
Figure 5.2 The Extent of Urmston Road at the Subsea Pipeline Alignment
Figure 6.1 Water Quality Monitoring Data Record Sheet
Figure 6.2 Proposed Water Quality Monitoring Locations
Figure 12.1 Sample Template for Interim Notifications of Environmental Quality Limits Exceedance
Appendices
Appendix A Environmental Mitigation Implementation Schedules
Appendix B Proforma for EM&A Programme