4.             Noise

Introduction

4.1          This section presents an assessment of potential airborne noise impacts during the construction of the Project, and recommends appropriate mitigation measures, where necessary.

 

Environmental Legislation, Standards and Guidelines

General

4.2          Noise impacts have been assessed in accordance with the criteria and methodology given in the Technical Memoranda (TMs) under the Noise Control Ordinance (NCO), and Annexes 5 and 13 in the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).

4.3          The NCO, Cap. 400 and Environmental Impact Assessment Ordinance, Cap. 499 (EIAO) provide the statutory framework for noise control.  Assessment procedures and standards are set out in the following TMs:

Ÿ   Technical Memorandum on Environmental Impact Assessment Process

Ÿ   Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM)

Ÿ   Technical Memorandum on Noise from Percussive Piling (PP-TM)

Ÿ   Technical Memorandum on Noise form Construction Work in Designated Areas (DA-TM)

Ÿ   Technical Memorandum for the Assessment of Noise from Places Other Than Domestic Premises, Public Places or Construction Sites (IND-TM)

4.4          Percussive piling is governed under the PP-TM and a construction noise permit (CNP) is required in order to carry out such work.  As the issuance of a CNP by the Noise Control Authority would depend on the compliance of percussive piling noise impact with the limits set out within the PP-TM, the assessment of this type of noise would not be covered in the EIA Report.

 

Construction Noise during Non-restricted Hours - EIAO-TM

4.5          Daytime general construction works (excluding percussive piling) between the hours 0700 – 1900 on weekdays, i.e. non-restricted hours, is controlled under the EIAO.  Annex 5 of the EIAO-TM sets out the construction noise assessment criteria, which are Leq(30 min) 75dB(A) for domestic premises, hotels and hostels; and Leq(30 min) 70dB(A) for schools during normal hours (65dB(A) during examination periods) and all other places where unaided voice communication is required. The criteria are summarized in Table 4.1. 

 

Table 4.1           Air-borne Daytime Construction Noise Criteria

Uses

Daytime Noise Criteria,

(Leq, 30min, dB(A))

Domestic premises, hotel, hostel

75

 

Educational Institution

70

 

Educational Institution (during examination)

65

 

                Note: The above standards apply to uses which rely on opened windows for ventilation

 

Construction Noise Standard during Restricted Hours

4.6          Between 1900 and 0700 hours and all day on Sundays and public holidays, activities involving the use of powered mechanical equipment (PME) for the purpose of carrying out construction work is prohibited unless a CNP has been obtained.  A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the NSRs.  ANLs are assigned depending upon the Area Sensitivity Ratings (ASRs).  The corresponding basic noise levels (BNLs) for evening and night-time periods are given in Table 4.2.

Table 4.2           Construction Noise Criteria for Activity other than Percussive Piling during Restricted Hours

Time Period

ANL on Different ASR During Restricted Hours (Leq, 30min, dB(A))

ASR A

ASR B

ASR C

Evening (1900 to 2300 hours) [a]

60

65

70

Night (2300 to 0700 hours)

45

50

55

                Notes:     [a] Includes Sundays and Public Holidays during daytime and evening

 

Construction Noise Permits

4.7          Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a CNP will be issued for the project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TMs issued under the NCO. The Noise Control Authority will take into account contemporary conditions/ situations of adjoining land uses and any previous complaints against construction activities at the site before deciding whether to grant a CNP.  Nothing in the EIA Report should bind the Noise Control Authority in making its decision.  If a CNP is to be issued, the Noise Control Authority should include in the permit any condition it thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO.

4.8          Under the DA-TM, the use of five types of Specified Powered Mechanical Equipment (SPME) and three types of Prescribed Construction Work (PCW) within a designated area during restricted hours would require a valid CNP (The Project falls within DA).  The SPME includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker.  The PCW are:

Ÿ   Erecting or dismantling of formwork or scaffolding;

Ÿ   Loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material; and

Ÿ   Hammering

4.9          In general, it should not be presumed that a CNP would be granted for carrying out PCW within a designated area during restricted hours.  The CNP may be granted for the execution of construction works during restricted hours involving the use of PME and/or SPME if the relevant Acceptable Noise Levels and criteria stipulated in the GW-TM and DA-TM can be met. The construction noise criteria are presented in Table 4.3.

Table 4.3           Construction Noise Criteria for SPME

Time Period

Basic Noise Level (BNLs)

ASR ‘A

ASR ‘B’

ASR ‘C’

Evening (1900 to 2300 hours) (1)

45

50

55

Night (2300 to 0700 hours)

30

35

40

Note:    (1)   Includes Sundays and Public Holidays during daytime and evening

 

 

Description of the Existing Environment

4.10        The SCL Protection Works is located entirely offshore within the CBTS.  Dredging would be carried out at the southeast corner of the CBTS.

4.11        The proximities of the Project area include a mix of commercial, Government/Institution/Community and residential uses. Traffic noise from Hing Fat Street, Victoria Park Road and Gloucester Road has been identified to be the dominant noise source.

 

Noise Sensitive Receivers

4.12        Existing and planned/committed noise sensitive receivers within 300m from the Project (i.e. Assessment Area) have been identified based on Annex 13 of the EIAO-TM, Survey and Mapping Office drawings of the assessment areas, Outline Zoning Plans, and Outline Development Plans and Layout Plans, while existing receivers have been confirmed through a site visit. 

4.13        Only the first layer of Noise Sensitive Receivers (NSRs) was identified for assessment because it would provide acoustic shielding to those receivers at further distance behind, and would represent the worst-case scenario.  The assessment points have been agreed with EPD. Locations of the representative NSRs for the construction noise impact assessment are shown in Figure Nos. NEX2213/C/331/ENS/M52/501 and NEX2213/C/331/ENS/M52/502. Details of the representative NSRs are presented in Table 4.4.

Table 4.4           Representative Noise Sensitive Receivers for Noise Impact Assessment

NSR ID

Description

Land Use

No. of storey

N11

Mayson Garden

Residential

24

N13

Belle House

Residential

24

CH1

Hoi Deen Court

Residential

17

CH2

Hoi Kung Court

Residential

19

CH3

Elizabeth House, Block C

Residential

21

CH4

Macro Polo Mansion

Residential

15

 

Assessment Methodology

4.14        The Project is scheduled to be commenced in early 2012 and to be completed by early 2014. According to the construction programme (Appendix 2.3 refers), there are three major construction tasks. All construction tasks are planned to be carried out during unrestricted hours.

4.15        The methodology for the noise impact assessment is in accordance with the procedures outlined in the GW-TM. The general approach is summarized below:

Ÿ   Locate the NSRs which would most likely be affected by noise from the construction work;

Ÿ   Determine the items of PME for each discrete construction activity, based on available information or agreed plant inventories;

Ÿ   Assign sound power levels (SWLs) to the proposed PME according to the GW-TM or other sources;

Ÿ   Calculate distance attenuation to NSRs from notional noise source;

Ÿ   Apply corrections in the calculations such as potential screening effects and acoustic reflection, if any;

Ÿ   Predict construction noise levels at NSRs in the absence of any mitigation measures;

Ÿ   Consider cumulative impact from the concurrent projects within 300m of the NSRs, if any; and

Ÿ   Compare the cumulative construction noise level against the noise criteria and propose suitable mitigation measures;

4.16        SWLs of the equipment from Table 3 of GW-TM were used for the assessment.  Where no relevant SWL to be found in the GW-TM, reference was made to British Standard 5228:Part 1:2009 Noise Control on Construction and Open Sites and previous similar studies or from measurements taken at other sites in Hong Kong.  Groups of PME were assigned for various construction activities of the proposed Project. 

4.17        The construction programme and plant inventory as presented in Appendices 2.3 and 4.1 respectively for various construction activities were developed by the engineering consultants of the Project Proponent.  Highways Department (HyD) has confirmed the proposed plant inventory as being practical and adequate for completing the works within the scheduled timeframe.

4.18        It was assumed that all PME items required for a particular construction activity would be located at the notional or probable source position of the segment where such activity is to be performed.  The assessment was based on the cumulative SWL of PME likely to be used for each location, taking into account the construction period in the vicinity of the receiver location.  To predict the noise level, PME was divided into groups required for each discrete construction task. The objective was to identify the worst case scenario representing those items of PME that would be in use concurrently at any given time. The sound pressure level of each construction task was calculated, depending on the number of plant and distance from receivers. The noise levels at NSRs were then predicted by adding up the SWLs of all concurrent construction tasks. Noise sources from the areas greater than 300m of a given NSR are excluded from the assessment.

4.19        A positive 3 dB(A) façade correction was added to the predicted noise levels in order to account for the facade effect at each NSR. The unmitigated construction noise impacts at the identified NSRs were predicted accordingly. Practicable direct mitigation measures including use of quieter equipment, movable barriers, enclosures and quieter alternative methods were considered if exceedance of relevant criteria was predicted. In case where the mitigated noise levels still exceeded the relevant criteria, the duration of the noise exceedance would be estimated.

 

Identification of Environmental Impacts

4.20        The potential source of noise impact during the construction phase of the Project would mainly be the use of PME for various construction activities.  Major construction works that would contribute to air-borne construction noise impacts would include temporary reclamation, relocation of temporary RHKYC jetty, and dredging works.

4.21        The key elements involved for air-borne construction noise at different works sections are summarized in Table 4.5

 

Table 4.5          Construction Phase Elements

Sections

Key Construction Items

Nearby Representative NSR

Protection Works at Causeway Bay Typhoon Shelter (CBTS)

§       Dredging works at southeast corner of CBTS to provide space for  relocation of anchorage area

 

§  Bella House

§  Mayson Garden

 

§       Marine piling for the temporary relocation of jetty at RHKYC

§  Temporary reclamation

§       Diaphragm walls

§       Seawalls

§       Approximately 160m long cut-and-cover tunnel

§       Bottom-up construction  

§       Removal of temporary Reclamation

(Same construction method as CWB)

§  Hoi Deen Court

§  Hoi Kung Court

§  Elizabeth House, Block C

§  Marco Polo Mansion

 

4.22        Since the Project would be constructed together with the CWB project at the CBTS, potential cumulative noise impact arising from the CWB project and the Project would be expected. The potential cumulative noise impact arising from the construction of the Project and CWB project was therefore considered in this assessment.

4.23        Based on the available construction programme of the SCL (HUH-ADM) at the time of this EIA study, the SCL (HUH-ADM) would not interface with the Project. As such, cumulative noise impact from the construction activities of the SCL (HUH-ADM) is not expected.

 

Prediction and Evaluation of Environmental Impacts

Construction Phase during Normal Working Hours

4.24        To strike a balance between the need for providing a railway system to the public and the public concerns on the adverse impacts, the following key features have been considered during the design of the Project to alleviate the construction noise impacts as far as practicable:

·                     Minimisation of number of PME; and

·                     Works would be implemented in phases, where possible, in order to reduce the number of PME required to be on-site.

4.25        The unmitigated noise levels at representative NSRs were predicted and presented in Table 4.6 based on the construction programme and plant inventory (Appendices 2.3 and 4.1). Locations of notional sources and distance to NSRs are shown in Appendix 4.3 and corresponding figure.

4.26        Sample calculations and a summary of unmitigated construction noise levels during normal daytime working hours for the representative NSRs are presented in Appendix 4.4 and 4.5, respectively.

 

Table 4.6          Unmitigated Construction Noise Levels due to construction of the Project

NSR ID

Description

Predicted Unmitigated Construction Noise Levels, dB(A)

EIAO-TM Noise Criteria,

dB(A)

N11

Mayson Garden

64

75

N13

Belle House

70

75

CH1

Hoi Deen Court

64 - 84

75

CH2

Hoi Kung Court

63 - 83

75

CH3

Elizabeth House, Block C

65 - 79

75

CH4

Macro Polo Mansion

67 - 81

75

Note:

Bold figures indicate exceedances of the EIAO-TM  noise criteria


4.27        The predicted noise levels at the representative NSRs would range from 63 to 84 dB(A), and some of which would exceed the EIAO-TM noise criterion of 75 dB(A).  Mitigation measures would be required to abate the construction noise impacts.

 

Construction Phase during Restricted Hours

4.28        According to the construction programme, no construction works would be carried out during non-restricted hours.  In case of any construction activities during restricted hours (1900 – 0700), it is the Contractor’s responsibility to ensure compliance with the NCO and the relevant TMs. The Contractor will be required to submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.

 

Mitigation of Adverse Environmental Impacts

4.29        The construction noise assessment indicated that, in the absence of any mitigation measures, there would be exceedance of the construction noise criteria at some of the NSRs. Various mitigation options have thus been considered in accordance with the guidelines laid down in the Environmental Impact Assessment Ordinance, Guidance Note No. 9/2004 “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” (GN 9/2004).  It should be noted that the assumptions used in formulating mitigation measures and their practicality were based on the best available information at the preliminary design stage of the Project. Alternative mitigation proposals which could achieve the same noise reduction effect may be considered in the detailed design stage. The recommended mitigation measures are discussed below.

Good Site Practice

4.30        Although the noise mitigation effects are easily quantifiable and the benefits may vary with site conditions and operating conditions, good site practices are easy to implement and do not impact upon the works schedule.  The site practices listed below should be followed during each phase of construction:

Ÿ   Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction program;

Ÿ   Silencers or mufflers on construction equipment should be utilized and should be properly maintained during the construction program;

Ÿ   Mobile plant, if any, should be sited as far from NSRs as possible;

Ÿ   Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

Ÿ   Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs; and

Ÿ   Material stockpiles and other structures should be effectively utilized, wherever practicable, in screening noise from on-site construction activities.

Adoption of Quiet PME

4.31        In order to reduce the excessive noise impacts at the affected NSRs during normal daytime working hours, quieter PME are recommended.  The Contractors may use other types of quiet plant instead of specific items of quiet plant adopted in this assessment, which have the same total SWL, to meet their needs.  Quiet PME adopted in the assessment were taken from the BS5228: Part 1:2009. It should be noted that the selected quiet PME for assessment could be found in Hong Kong.

4.32        A list of quiet PME recommended for adoption during the construction phase is presented in Table 4.7.

Table 4.7          Quiet PME Recommended for Adoption during Construction Phase

PME

Reference

SWL, dB(A)

Air Compressor

BS D7/16

96

Concrete Pump

BS D6/36

106

Crane

BS D7/113

101

Dump Truck

BS D9/27

105

Excavator

BS D3/97

105

Generator

CNP 103

95

Hand-held Breaker

BS D2/10

110

Air Compressor*

Table C7/16

96

Bulldozer*

Table C9/2

104

Concrete Lorry Mixer*

Table C6/35

100

Concrete Pump*

Table C6/36

106

Crane*

Table C7/114

101

Dump Truck*

Table C9/27

105

Excavator*

Table C3/97

105

Poker Vibrator*

Table C6/32

100

Roller*

TableC8/27

104

Trucks*

TableC9/27

105

Remark:

* Reference has been made to the approved WDII & CWB EIA Report

 

Use of Movable Noise Barrier

4.33        The use of movable barrier for certain PME could further alleviate the construction noise impacts.  In general, 5dB(A) reduction for movable PME and 10dB(A) for stationary PME can be achieved depending on the actual design of movable noise barrier. 

4.34        Table 4.8 shows the assumed noise reduction effects achieved by the movable noise barrier for certain items of PME.  The Contractor shall be responsible for design of the movable noise barrier with due consideration given to the size of the PME and the requirement of intercepting the line of sight between the NSRs and PME.  Barrier material of surface mass in excess of 10 kg/m2 is recommended to achieve the predicted screening effect. 

4.35        A summary of the assumed noise reduction effects achieved by the use of movable noise barrier for certain item of PME is presented in Table 4.8.

Table 4.8          Noise Mitigation Measures for Certain PME during Construction Phase

PME

Mitigation Measures Proposed

Noise Reduction, dB(A)

Air Compressor*

Movable Barrier

10

Bar Bender*

Movable Barrier

10

Bentonite Plants*

Movable Barrier

5

Concrete pump*

Movable Barrier

10

Diaphragm Wall Rigs*

Movable Barrier

5

Excavator*

Movable Barrier

5

Poker Vibrator*

Movable Barrier

5

Remarks:

* Reference has been made to the approved WDII&CWB EIA Report

 

Mitigated Construction Noise Impacts

4.36        Having taken into account the noise reduction achieved by the above-mentioned mitigation measures, the total SWLs of each activity were predicted, and are presented in Appendix 4.6. Predicted mitigated noise levels from the Project itself at all the representative NSRs would comply with the EIAO-TM noise criteria.  Table 4.9 summarises the mitigated levels at the representative NSRs. The sample calculations and the summary of mitigated construction noise levels during normal daytime working hours are presented in Appendices 4.7 and 4.8, respectively.

Table 4.9          Mitigated Construction Noise Levels due to construction of the Project

NSR ID

Description

Predicted Mitigated Construction Noise Levels, dB(A)

EIAO-TM Noise Criteria,

dB(A)

N11

Mayson Garden

64

75

N13

Belle House

70

75

CH1

Hoi Deen Court

61 – 73

75

CH2

Hoi Kung Court

60 – 73

75

CH3

Elizabeth House, Block C

60 – 68

75

CH4

Macro Polo Mansion

61 - 70

75

 

 

 

 

 

 

 

 

 

 

 

 

Cumulative Construction Noise Impact

4.37        The concurrent project in the vicinity of the Project works area is CWB project. Construction of the CWB project in the vicinity would involve the temporary reclamation and cut and cover tunnel works at Ex-Public Cargo Working Area and CBTS.

4.38        Cumulative construction noise impacts from the CWB project were assessed by using the maximum mitigated construction noise levels predicted in the approved WDII & CWB EIA Report during the overlapping period.

4.39        Table 4.10 summaries the cumulative noise levels from the Project and CWB project. Detailed calculation of the cumulative noise impacts are presented in Appendix 4.9. The results indicate that the cumulative noise levels at all the NSRs would comply with the EIAO-TM noise criteria.

Table 4.10         Cumulative Construction Noise Levels from Other Concurrent Projects (Mitigated)

NSR

ID

EIAO-TM Noise Criteria,

dB(A)

Predicted Mitigated Noise Levels, dB(A)

Cumulative Noise Level, dB(A)

The Project

CWB Project[*]

N11

75

64

64

64 67

N13

75

70

67

67 72

CH1 [a]

75

61 – 73

68 [a]

68 74

CH2 [a]

75

60 – 73

68 [a]

68 74

CH3

75

60 – 68

68

68 71

CH4

75

61 - 70

73

73 75

Note:

[*]      Maximum mitigated construction noise level from CWB project at the particular NSR within the overlapping period is based on the approved WDII & CWB EIA Report.

[a]     Since no construction noise level was predicted at CH1 and CH2 in the approved WDII & CWB EIA Report, the maximum mitigated construction noise level at the nearest NSR (CH3) was adopted to predict the cumulative construction noise levels from CWB project.

 

Evaluation of Residual Impacts

4.40        With the use of quiet PME and movable noise barriers, the predicted construction noise levels at all representative NSRs would comply with the noise criteria stipulated in the EIAO-TM.

 

Environmental Monitoring and Audit

4.41        An EM&A programme is recommended to be established according to the predicted occurrence of noisy activities. All the recommended mitigation measures for daytime normal working activities should be incorporated into the EM&A programme for implementation during construction. Details of the programme are provided in a stand-alone EM&A Manual.

 

Conclusion

4.42        Noise arising from the construction activities of the project would have unavoidable potential impact on the NSRs located in the vicinity of the works areas. Unmitigated construction noise levels at the representative NSRs have been predicted, which are found to be in the range of 63 to 84 dB(A).

4.43        Mitigation measures including good site practices, quieter plant, and movable noise barrier are recommended to reduce the noise levels so as to meet the EIAO-TM noise criterion.  With the recommended mitigation measures in place, noise levels due to the Project and the cumulative impact with CWB project at all representative NSRs are predicted to comply with the EIAO-TM daytime construction noise criterion.  No adverse residual impact would be envisaged.