Content


Chapter    Title

10.1                Introduction

10.2                Waste Management Legislation, Standards and Guidelines

10.2.1             Overview

10.2.2             Waste Disposal Ordinance

10.2.3             Waste Disposal (Chemical Waste) (General) Regulation

10.2.4             Waste Disposal (Charges for Disposal of Construction Waste) Regulation

10.2.5             Buildings Ordinance

10.2.6             Land (Miscellaneous Provisions) Ordinance

10.2.7             Dumping at Sea Ordinance

10.2.8             Public Cleansing and Prevention of Nuisances Regulation

10.3                Assessment Methodology

10.4                Identification, Prediction and Evaluation of Environmental Impact

10.4.1             Construction Phase

10.4.2             Operation Phase

10.5                Mitigation of Adverse Environmental Impact

10.5.1             Construction Phase

10.5.2             Operation Phase

10.6                Evaluation of Residual Impact

10.7                Environmental Monitoring and Audit

10.7.1             Construction Phase

10.7.2             Operation Phase

10.8                Conclusion

10.8.1             Construction Phase

10.8.2             Operation Phase

 

Tables

Table 10.1: Estimated Quantity of Inert C&D Materials to be Generated by the Project 10-6

Table 10.2:_ Yearly Generation of Inert C&D Materials 10-6

Table 10.3:_ Estimated Quantity and Sources of Fill Materials Required for the Proposed Land Formation_ 10-6

Table 10.4:_ Estimates of Inert C&D Materials to be Reused On-site as Fill Materials for Land Formation_ 10-7

Table 10.5:_ Estimates of Surplus Inert C&D Materials to be Delivered Off-site_ 10-8

Table 10.6: Summary of Chemical Testing Results for Sediment Sub-samples Collected near Field Joint Area_ 10-11

Table 10.7: Summary of Marine Sediments from Field Joint Area Requiring Disposal 10-12

Table 10.8: Estimated Quantity of CMP and Marine Sediments from Piling Works on Proposed Land Formation Area_ 10-13

Table 10.9:_ Summary of Chemical Testing Results for Sediment Sub-samples Collected within/close to TRC, APM & BHS Tunnels and Airside Tunnels Footprint 10-13

Table 10.10: Estimated Quantity of Different Categories of Sediments from Piling Works on Proposed Land Formation Area_ 10-16

Table 10.11: Summary of Chemical Testing Results for Sediment Sub-samples Collected near West End of Third Runway 10-18

Table 10.12: Summary of Chemical Testing Results for Sediment Sub-samples Collected near HKIAA Beacons 10-19

Table 10.13: Summary of Chemical Testing Results for Sediment Sub-samples Collected around the Northeast Corner of the Existing Airport Island_ 10-21

Table 10.14: Summary of Chemical Testing Results for Sediment Sub-samples Collected close to the T2 Expansion Works and APM Depot Locations from the HKBCF EIA Report 10-22

Table 10.15: Summary of Waste Arising during Construction Phase_ 10-25

Table 10.16: Summary of Waste Avoidance / Reduction through Alternative Design Options / Construction Methods 10-27

Table 10.17: Historical Records of Waste Arising from Operation of the Existing Airport (2008 – 2012) 10-28

Table 10.18: Amount of Waste Recycled by AAHK from 2008 to 2012_ 10-29

Table 10.19: Summary of Floating Refuse Collected in Chek Lap Kok Watercourse_ 10-30

Table 10.20: Universal Treatment Standards for On-site Reuse of Sediments Treated by Cement Mixing and Stabilisation_ 10-35

 

 

Drawings

MCL/P132/EIA10-001        Indicative Locations of Barging Points and Temporary Stockpile Areas for Inert C&D Materials to be Reused On-site

MCL/P132/EIA10-002        Vibrocore Locations for Submarine Cable Field Joint Area

MCL/P132/EIA10-003        Vibrocore Locations for Land Formation Area

MCL/P132/EIA10-004        Drillhole Locations for T2 Expansion Works and APM Depot

MCL/P132/EIA10-005        Vibrocore Locations around the Northeast Corner of Existing Airport Island

 

Appendices

Appendix 10.1     Estimated Quantities of Inert C&D Materials to be Generated, Reused On-site and Delivered Off-site

Appendix 10.2     Correspondence from PFC on Allocation of Space at PFRFs for Receipt of the Surplus Inert C&D

Appendix 10.3      Estimated Quantity of Excavated Sediment from Cable Field Joint Area

Appendix 10.4      Sediment Sampling and Testing Plan and Approval Letter from EPD

Appendix 10.5a   Chemical and Biological Testing Results of Sediment Sub-samples Collected near Field Joint Area

Appendix 10.5b   Chemical Testing Results of Sediment Sub-samples Collected within/close to TRC, APM & BHS Tunnels and Airside Tunnels Footprint

Appendix 10.5c   Chemical Testing Results of Sediment Sub-samples Collected near East End and West End of Third Runway and HKIAA Beacons

Appendix 10.6     Correspondence from MFC on Allocation of Space for Disposal of Marine Sediment

Appendix 10.7      Drillhole Records for T2 Expansion Works and APM Depot

Appendix 10.8a   Chemical Testing Results of Sediment Sub-samples Collected around the Northeast Corner of Existing Airport Island

Appendix 10.8b   Chemical Testing Results of Sediment Sub-samples Collected close to T2 Expansion Works and APM Depot from the HKBCF EIA Report

 


10.    Waste Management Implications


10.1       Introduction

10.1.1.1    This chapter identifies the types of wastes that are likely to be generated during the construction and operation phases of the project and evaluates the potential environmental impact that may result from these wastes in accordance with Section 3.4.8 of the EIA Study Brief (ESB-250/2012) as well as the criteria and guidelines outlined respectively in Annex 7 and Annex 15 of the EIAO-TM.

10.2       Waste Management Legislation, Standards and Guidelines

10.2.1     Overview

10.2.1.1    The criteria and guidelines for assessing waste management implications are outlined in Annex 7 and Annex 15 of the EIAO-TM respectively.

10.2.1.2    The following legislation which relates to the handling, storage and disposal of wastes in Hong Kong are relevant in the assessment of waste management implication:

¡  Waste Disposal Ordinance (Cap. 354)

¡  Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C)

¡  Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)

¡  Buildings Ordinance (Cap. 123)

¡  Land (Miscellaneous Provisions) Ordinance (Cap. 28)

¡  Dumping at Sea Ordinance (Cap. 466)

¡  Public Cleansing and Prevention of Nuisances Regulation (Cap. 132BK)

10.2.2     Waste Disposal Ordinance

10.2.2.1    The Waste Disposal Ordinance (WDO) is the principal piece of legislation for management and control of waste disposal in Hong Kong.  The WDO prohibits the unauthorised disposal of wastes. Construction waste is defined as any substance, matter or thing that is generated from construction work and abandoned, whether or not it has been processed or stockpiled before being abandoned, but does not include any sludge, screenings or matter removed in or generated from any desludging, desilting or dredging works. Under the WDO, wastes can be disposed of only at designated waste disposal facilities.

10.2.3     Waste Disposal (Chemical Waste) (General) Regulation

10.2.3.1    Under the WDO, the Waste Disposal (Chemical Waste) (General) Regulation is enacted to provide regulations for chemical waste control, and to administer the possession, storage, collection, transport and disposal of chemical wastes.

10.2.3.2    According to the Waste Disposal (Chemical Waste) (General) Regulation, all producers of chemical waste must register with EPD and treat their wastes, either utilising on-site plant licensed by EPD, or arranging for a licensed collector to transport the wastes to a licensed facility. The Regulation also prescribes the storage facilities to be provided on site, including labelling and warning signs, and requires the preparation of written procedures and training to deal with emergencies such as spillages, leakages or accidents arising from the storage of chemical wastes.

10.2.3.3    The EPD has issued a ‘guideline’ document, the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes (1992), which details how chemical waste producers should comply with the regulations on chemical wastes.

10.2.4     Waste Disposal (Charges for Disposal of Construction Waste) Regulation

10.2.4.1    Under the Waste Disposal (Charges for Disposal of Construction Waste) Regulation, construction waste delivered to a landfill for disposal must not contain more than 50% by weight of inert material. Construction waste delivered to a sorting facility for disposal must contain more than 50% by weight of inert material, whereas construction waste delivered to a public fill reception facility for disposal must consist entirely of inert material.

10.2.5     Buildings Ordinance

10.2.5.1    Regulation of private projects, as opposed to government public works projects, is subject to the Buildings Ordinance (BO) and relevant Practice Notes for Authorised Persons, Registered Structural Engineers and Registered Geotechnical Engineers (PNAPs). Measures have been introduced under PNAP ADV-19 Construction and Demolition Waste, to enhance the management of construction and demolition (C&D) material, and to minimise its generation at source. The enhancement measures include:

¡  Identifying opportunities to prevent waste during both the project planning and design stage as well as construction stage; and

¡  Requiring the contractor to prepare a Waste Management Plan (WMP) including areas described in PNAP ADV-19 and submit to the project proponent for agreement

10.2.5.2    For private projects generating more than 300,000 m3 of C&D material, the project proponent may consult the Director of Environmental Protection (DEP) for advice prior to accepting the WMP. Moreover, the Public Fill Committee (PFC) of Civil Engineering and Development Department (CEDD) is also prepared to offer advice to the Authorised Person (AP) and Resident Site Engineer (RSE) on the management and beneficial reuse of C&D material.  

10.2.6     Land (Miscellaneous Provisions) Ordinance

10.2.6.1    The Land (Miscellaneous Provisions) Ordinance requires that dumping licenses be obtained by individuals or companies who deliver public fill to public filling areas. The CEDD issues the licences under delegated powers from the Director of Lands. The current policy related to dumping of C&D material is documented in the Works Branch Technical Circular No. 2/93 Public Dumps. C&D materials that are wholly inert, namely public fill, should not be disposed of to landfill, but taken to fill banks or public filling areas.

10.2.7     Dumping at Sea Ordinance

10.2.7.1    In accordance with the Dumping at Sea Ordinance (DASO), application for dumping permits from EPD are required for marine disposal of dredged materials.

10.2.7.2    The Practice Notes for Authorised Persons, Registered Structural Engineers and Registered Geotechnical Engineers, PNAP ADV-21 – Management Framework for Disposal of Dredged/ Excavated Sediment (April 2007), set out the procedures for seeking approval to dredge/ excavate sediment and the management framework for marine disposal of such sediment. This PNAP outlines the requirements to be followed in assessing and classifying the sediment and explains the marine disposal arrangement for the classified material.

10.2.8     Public Cleansing and Prevention of Nuisances Regulation

10.2.8.1    The Public Cleansing and Prevention of Nuisances Regulation provides control on illegal tipping of wastes on unauthorised (unlicensed) sites.

10.3       Assessment Methodology

10.3.1.1    Assessment of the waste management issues associated with construction and operation phases of the project has been carried out in accordance with Clause 3.4.8 and Appendix E1 of the EIA Study Brief. The scope of the assessment has covered the following:

Analysis of Activities and Waste Generation

¡  Identify the quantity, quality and timing of waste arising as a result of the construction and operation activities of the project.

¡  Adopt appropriate design, general layout, construction methods and programme to minimise the generation of inert C&D materials and maximise the use of inert C&D  materials for other construction works.

Development of Proposals for Waste Management

¡  Prior to considering the disposal options for various types of wastes, opportunities for reducing waste generation, on-site or off-site re-use and recycling should be fully evaluated.

¡  Identify measures / proposals for potential floating refuse issues.

¡  Estimate the types and quantity of the wastes required to be disposed of.

¡  Identify the disposal methods / options for each type of waste.

¡  Identify the transportation routings and the frequency of the trucks/vessels involved.

¡  Identify the stockpiling areas and the disposal outlets for the wastes, and the need for barging points or conveyor systems.

¡  Assess the potential impact from the management of solid waste with respect to potential hazards, air and odour emissions, noise, wastewater discharges, ecology and public transport.

Identification of Any Need for Dredging / Excavation, Filling and Dumping

¡  Identify and quantify dredging/ excavation, fill extraction, filling, reclamation, sediment/ mud transportation and disposal activities and requirements.

¡  Identify potential fill source and dumping ground to be involved.

¡  Identify and evaluate the best practicable dredging / excavation methods, treatment methods, reuse/ recycling options and work programme to minimise excavation and dumping requirements and demand for fill sources.

10.4       Identification, Prediction and Evaluation of Environmental Impact

10.4.1     Construction Phase

10.4.1.1    The construction activities to be carried out for the project are expected to generate a variety of wastes that can be divided into distinct categories based on their composition and ultimate method of disposal. The identified waste types include:

¡  C&D materials

¡  Excavated marine sediment

¡  Chemical waste

¡  General refuse

¡  Floating refuse

10.4.1.2    Each type of waste arising is described below, together with an evaluation of the potential environmental impact associated with the handling, storage and transport of the waste.

Inert Construction and Demolition Materials

10.4.1.3    It is anticipated that the majority of inert C&D materials will be generated from the following key construction activities:

¡  Excavation works would be required to:

-  extend the Automated People Mover (APM) tunnels from the Terminal 2 (T2) APM Interchange Station (AIS) to the Third Runway Concourse (TRC) and associated APM stations in TRC;

-  extend the Baggage Handling System (BHS) tunnels from the T2 Baggage Hall to the Baggage Hall associated with the TRC;

-  construct the new AIS facility;

-  construct the APM Depot;

-  extend the airside road tunnels from the existing  system to serve the new TRC;

-  construct the drainage culvert; and

-  install major underground utilities.

¡  At the current stage of project development, the construction method is still under investigation and is yet to be confirmed. It is initially proposed that the APM tunnels, BHS tunnels and baggage hall facilities may be excavated largely through the newly reclaimed land platform using the cut-and-cover method or open cut. The airside road tunnels excavated partially through the existing airport site and partially through newly reclaimed land also using cut-and-cover method or open cut. At the time of preparing this report, the proposed works would not require excavation into the marine sediments or the contaminated mud pits (CMPs) beneath the fill materials, but this is subject to review of the outcomes of a marine site investigation that will be conducted in 2014. Temporary piling wall will be carried out to act as a coffer dam to reduce groundwater intrusion during the excavation. The coffer dam piled wall will require excavation into the marine sediment and CMP.

¡  At the current stage of project development, it is anticipated that permanent piling works will be carried out for foundation construction of the TRC and other buildings within the proposed land formation area. Temporary lateral support using piling or sheet pile may be required to form a coffer dam to facilitate excavation of the basement or any underground structure. 

¡  Temporary surcharge material will be used to facilitate the settlement of individual work areas during the land formation. Upon completion of the surcharge process for a work area, the material will be reused in other work areas as fill or surcharge materials. Although every effort will be made to reduce surplus surcharge materials requiring off-site disposal, there may be surplus surcharge materials that cannot be reused (refer to Section 4.2.2).

¡  Modification of the existing northern seawall will be required to enable the proposed land formation work (refer to Section 4.2.2).

¡  Excavation and demolition works will be carried out at part of the existing T2 for its expansion (refer to Section 4.2.4).

¡  Excavation works would be required as part of the proposed foundation of new road network and improvements to the existing road networks for T2 expansion, as well as at the cargo area on the existing airport site (refer to Section 4.2.6).

¡  For diversion of the existing submarine fuel pipelines, the Horizontal Directional Drilling (HDD) method is proposed for installing new fuel pipelines directly from the west end of the existing airport island to Sha Chau by underground drilling (mostly at sub-seabed rock level), as detailed in Section 4.2.6. Minimal excavation works would be required at the proposed launching and land points of the submarine fuel pipelines.

10.4.1.4    Construction works including excavation within the land formation platform would commence once the required level of settlement has been achieved through surcharging.  Details of the proposed construction works are given in Section 4.2 while the tentative construction programme is presented in Section 4.3 and Appendix 4.2.  

10.4.1.5    Based on the tentative construction programme, initial estimates indicate that about 9,543,500 m3  of inert C&D materials would be generated from the aforementioned activities during the period from Q3 of 2015 to Q4 of 2022, as summarised in Table 10.1.  Detailed estimates of the inert C&D material volumes are given in Appendix 10.1.

Table 10.1: Estimated Quantity of Inert C&D Materials to be Generated by the Project

Key Sources of Inert C&D materials

Estimated Quantity of Inert C&D Materials Generated ( in-situ volume, m3)

Tentative Timeframe of Generation

Excavation works for APM & BHS tunnels, new APM depot and airside tunnels and piling works for TRC and other facilities as well as superstructure construction works

4,812,230

Q1 of 2017 – Q4 of 2022

Surplus surcharge material

3,793,000

Q4 of 2018 – Q3 of 2022

Modification of existing northern seawall

487,000

Q1 of 2016 – Q3 of 2021

Excavation and demolition works for T2 expansion as well as superstructure construction works

437,270

Q4 of 2016 – Q4 of 2019

Excavation works for improvement of the road networks

8,000

Q1 of 2017 Q3 of 2017

HDD for diversion of existing submarine fuel pipelines

6,000

Q3 of 2015 – Q4 of 2015

Total

9,543,500

Q3 of 2015 – Q4 of 2022

10.4.1.6    The yearly breakdown of the inert C&D material generation is as shown in Table 10.2.

Table 10.2:  Yearly Generation of Inert C&D Materials

Year

Estimated Amount of Inert C&D Materials to be Generated by the Project  (in-situ volume, m3)

2015

6,000

2016

398,000

2017

710,000

2018

4,359,230

2019

1,344,270

2020

1,531,000

2021

689,000

2022

506,000

Total

9,543,500

10.4.1.7    Initial scheme design estimates identify requirements for various types of fill materials for the proposed land formation work from 2016 to 2021, as summarised in Table 10.3.  It is currently estimated that between 8.6 and 20.7 million m3 would be sourced from public fill material with approximately 7.5 million m3 of rock fill required.

Table 10.3:    Estimated Quantity and Sources of Fill Materials Required for the Proposed Land Formation

Type of Fill Materials

Estimated Quantity (million m3)

Timeframe

Potential Sources for  Import

Sand fill

82.8-97.5

2016 – 2021

Hong Kong, Mainland China

Public fill

8.6-20.7

2016 – 2021

Concurrent projects in Hong Kong (e.g. West Kowloon Cultural District, Shatin to Central Link, Hong Kong-Zhuhai-Macau Bridge), Government’s Public Fill Reception Facilities

Rock fill

7.5

2016 – 2021

Quarries and concurrent projects in Hong Kong (limited supply), quarries from Mainland China

Rock armour & underlayer

0.6

2016 – 2021

10.4.1.8    The approach pursued by the project is a strategy that seeks to maximise the earthworks balance, thereby minimising the volumes of fill that would be required to be imported to and exported from the site. Every effort would be made to minimise the extent of excavation and to ensure that as much of the inert C&D materials generated by the project will be reused on-site as practicable.  For this, the relevant construction activities (particularly for the tunnel works) and construction programme have been carefully planned and developed.  The combination of these initiatives is anticipated to maximise the on-site reuse of inert C&D materials as fill material for the proposed land formation as far as practicable, hence minimising the quantity of any surplus inert C&D materials requiring off-site delivery and the impact resulting from the associated collection and transportation works.

10.4.1.9    While approximately 8.6 to 20.7 million m3 of public fill could be used for the proposed land formation, the scheme design estimates identify that the project would require a total of 14,551,000 m3 of public fill materials for land formation work.  While all practicable measures will be employed for reuse of inert C&D material generated by the project before consideration of importing material, it is anticipated that approximately 3,639,230 m3 (or about 38%) of the inert C&D materials generated by the project would be reused as fill material for land formation work, as summarised in Table 10.4.  Therefore, approximately 10,911,770 m3 (14,551,000 – 3,639,230 m3) of public fill materials will need to be imported to this project.  Priority will be given to maximise the use of suitable fill materials available from other concurrent projects and the Government’s Public Fill Reception Facilities (PFRF). AAHK will continue to liaise with the relevant concurrent projects for direct reuse of their surplus public fill for the proposed land formation works of this project. Details of the estimated on-site reuse and import quantity are given in Appendix 10.1.

Table 10.4:    Estimates of Inert C&D Materials to be Reused On-site as Fill Materials for Land Formation

Year

Estimated Demand of Public Fill Materials for Land Formation

(in-situ volume, m3)

Estimated Amount of Inert C&D Materials to be Reused On-site for Land Formation

(in-situ volume, m3)

Estimated Amount of Public Fill Materials to be Imported for Land Formation

(in-situ volume,m3)

2015*

0

6,000

0

2016*

1,912,000

398,000

1,508,000

2017

6,099,000

710,000

5,389,000

2018

4,788,000

773,230

4,014,770

2019

674,000

674,000

0

2020

835,000

835,000

0

2021

243,000

243,000

0

2022

0

0

0

Total

14,551,000

3,639,230

10,911,770

*Note: Inert C&D materials generated from Q3 of 2015 to Q3 of 2016 would be temporarily stored in stockpiles, which would then be reused for land formation from Q3 of 2016 onwards. 

10.4.1.10 It should be noted that temporary stockpiling of the inert C&D materials generated from Q3 of 2015 to Q3 of 2016 would be required in order to facilitate the subsequent reuse of such materials for the land formation work.  The indicative locations of such temporary stockpiling areas are as shown in Drawing MCL/P132/EIA/10-001.

10.4.1.11 It is estimated that about 5,904,270 m3 (9,543,500 – 3,639,230 m3) of inert C&D materials generated by the project could not be reused on-site. Therefore, this volume of surplus inert C&D materials would require off-site delivery to any projects that require fill materials and/or the Government’s PFRF for beneficial use by other projects in Hong Kong. Table 10.5 summarises the annual quantity of such surplus materials requiring off-site delivery. Details of the relevant estimates are given in Appendix 10.1.

10.4.1.12 For year 2018, the amount generated in Q1 to Q3 will be fully reused on-site for land formation. The surplus amount of 3,586,000 m3 is generated from Q4 of 2018 where the amount of public fill demand is much less than that of inert C&D generated. The quarterly breakdown of the inert C&D material generated and reused is detailed in Appendix 10.1.

Table 10.5:    Estimates of Surplus Inert C&D Materials to be Delivered Off-site

Year

Estimated Amount of Inert C&D Materials to be Generated by the Project

(in-situ volume, m3)

Estimated Amount of Inert C&D Materials to be Reused On-site for Land Formation

(in-situ volume, m3)

Estimated Amount of Surplus Inert C&D Materials to be Delivered Off-site

(in-situ volume, m3)

2015

6,000

6,000

0

2016

398,000

398,000

0

2017

710,000

710,000

0

2018

4,359,230

773,230

3,586,000

2019

1,344,270

674,000

670,270

2020

1,531,000

835,000

696,000

2021

689,000

243,000

446,000

2022

506,000

0

506,000

Total

9,543,500

3,639,230

5,904,270

10.4.1.13 AAHK is exploring any potential projects that could receive any surplus inert C&D materials generated from this project during the years of 2018 to 2022. Subject to the identification of such potential projects, it is anticipated that up to 5,904,270 m3 of inert C&D materials would be delivered to the PFRF from 2018 to 2022. Priority will be given to deliver the surplus inert C&D materials of this project to any identified projects that would require public fill during those years, and therefore delivery of the surplus inert C&D materials to the PFRF will be considered as the last resort.   It is also understood that any surplus inert C&D materials received by the PFRF should be not exceed 250 mm in size.   

10.4.1.14 It is anticipated that six temporary barging points would be located around the perimeter of the newly formed land as shown in Drawing MCL/P132/EIA10-001. The estimated maximum total handling capacity of inert C&D materials at the six temporary barging points will be 282,000 ton/day or 141,000 m3/day (47,000 ton/day or 23,500 m3/day for each barging point). Barges, each with a loading capacity of about 3,000 m3, will be used for delivery of the surplus inert C&D materials that could not be reused on-site from barging points to the PFRF via the Urmston Road or Ma Wan. Taking the peak quarterly amount of surplus materials requiring off-site delivery at Q4 of 2018, i.e., 3,586,000 m3 (see Appendix 10.1), it is estimated that a maximum of approximately 46,000 m3/day of surplus materials would be delivered off-site via the barging points, which is well within the total handling capacity of the six barging points.  Corresponding to this maximum daily volume, up to approximately 16 barge-trips per day will be needed for off-site delivery of the surplus inert C&D materials. The barge should be properly covered with tarpaulin and provided with frequently water spraying, to aid dust suppression, when handling and transporting these materials. The potential dust impact due to handling of materials at the barging points has been quantitatively assessed as part of the construction phase air quality impact assessment as detailed in Section 5.2.

10.4.1.15 AAHK has liaised with the PFC of CEDD regarding the allocation of space at PFRF for receipt of the estimated amount of surplus inert C&D materials from the project. Relevant correspondences on the allocation of space for receipt of the surplus inert C&D materials with PFC are provided in Appendix 10.2. A detailed C&D Material Management Plan (C&DMMP) will be provided and submitted to the PFC during the detailed design stage when more information is available. The C&DMMP will be updated from time to time during construction phase.

10.4.1.16 AAHK will continue to explore any opportunities for off-site delivery of the surplus inert C&D materials for beneficial uses by other projects.  For this, AAHK will:

¡  Continue to explore any potential projects in Hong Kong that would be able to receive the surplus inert C&D materials from this 3RS project from 2018 onwards.  One such potential project would be the Tung Chung New Town Extension, which comprises reclamation works and is targeted to commence in 2018 according to the recent communications with the project proponent.  AAHK will maintain liaison with that project proponent for the possible future arrangement.

¡  Maintain regular liaison with PFC on details of the future arrangement for off-site delivery of the surplus inert C&D materials to the PFRF.

¡  If there is a lack of any suitable outlets in Hong Kong for receipt of the surplus inert C&D materials from the 3RS project, AAHK will explore and consider cross-boundary delivery of the materials.

10.4.1.17 No construction work would be permitted to proceed until all issues on management of inert C&D materials have been resolved and all relevant arrangements have been endorsed by the appropriate authorities, including PFC and EPD.

10.4.1.18 The storage, handling, transport and disposal of surplus inert C&D materials, if not managed properly, has the potential to create visual, water quality and dust impacts. Therefore, good site practices including dust-suppression measures, use of good environmental management protocols for the storage and management of excavated materials (as detailed in Section 10.5.1) will be implemented to prevent or reduce the associated potential impacts.  With such good site practices in place, it is anticipated that storage, handling, transport and disposal of the inert C&D materials will not result in adverse dust, visual or water quality impacts.

Non-inert Construction and Demolition Materials

10.4.1.19 It is anticipated that non-inert C&D materials will be generated from the following activities:

¡  Site clearance at golf course area; and

¡  Demolition and superstructure construction works.

10.4.1.20 It is estimated that the top 0.3 m of soil layer would be removed from site clearance works at the golf course area where the new APM depot will be constructed, hence approximately 8,700 m3 of non-inert C&D materials will be generated in 2017. These non-inert C&D materials would mainly be a mixture of topsoil and vegetative materials, which are considered as unsuitable for direct reuse during any earthworks on site due to its non-inert contents, and will therefore be disposed of at designated landfill sites by a reputable licensed waste collector. The contractor should separate such non-inert C&D materials from the inert C&D materials on-site.

10.4.1.21 Based on initial scheme design information, it is estimated that approximately 87,500 m3 of non-inert C&D materials would be generated from the demolition works for T2 expansion and various superstructure construction works from 2016 to 2021. The contractor should separate these non-inert C&D materials from the inert C&D materials on site.  Any recyclable materials (e.g., metal) should be segregated from the non-inert C&D materials for collection by reputable licensed recyclers.  The remaining non-recyclable waste materials will be disposed of at designated landfill sites by a reputable licensed waste collector.

10.4.1.22 The non-inert C&D materials (after the recyclable materials have been segregated for recycling) will be delivered to designated landfill sites by dump trucks through North Lantau Highway. With a loading capacity of about 6 m3 per dump truck, it can be estimated that up to 8 vehicle-trips per day would be required for delivery of the non-inert C&D materials, which would not impose significant traffic loading on North Lantau Highway. The storage, handling, transport and disposal of non-inert C&D materials, if not managed properly, would have the potential to create visual, dust and water quality impacts. Therefore, good site practices as detailed in Section 10.5.1 will be implemented to prevent or reduce the associated potential impacts.

Excavated Marine Sediments

10.4.1.23 As the proposed land formation will be carried out by non-dredged methods only (see Section 4.2.2), dredging of marine sediments will not be required. 

10.4.1.24 Diversion of the submarine fuel pipelines will be conducted by adopting the HDD method, involving tunnel drilling at the sub-sea bedrock level (see Section 4.2.6).  Therefore, no marine sediments are required to be excavated from the pipeline diversion work.

10.4.1.25 However, the activities that are likely to involve excavation of marine sediments include:

¡  Diversion of the submarine 11 kV cable – the field joint area;

¡  Foundation piling works within the proposed land formation area (after land formation);

¡  Piling works for the marine sections of the new approach lights required at either end of the proposed third runway;

¡  Piling works for the proposed Hong Kong International Airport Approach Area (HKIAAA) beacons;

¡  Basement work for the proposed T2 expansion; and

¡  Excavation works for the proposed APM depot.

Diversion of submarine 11 kV cable – field joint area

10.4.1.26 As detailed in Section 4.2.6, the preferred option for diversion of the existing submarine 11kV cable is to lay a new submarine 11 kV cable by water jetting method from west of the existing airport island to the south of the Sha Chau and Lung Kwu Chau (SCLKC) Marine Park where the new cable will be connected to the existing cable via a field joint.  Laying of the new cable by water jetting will not require localised dredging or disposal of any marine sediment.  However, excavation of the seabed will be carried out at the field joint area to expose a segment of the existing cable, which will then be lifted up to a barge for connection to the new cable.  The proposed field joint area is approximately 120 m in length, 32 m in width and 5 m in depth, and its boundary will be over 500 m from the boundary of the SCLKC Marine Park.  It is estimated that about 10,200 m3 of marine sediment will be dredged from the field joint area.  Details of the marine sediment quantity estimation are given in Appendix 10.3. 

10.4.1.27 Sediment sampling and laboratory testing was undertaken in the field joint area in accordance with the requirements in PNAP ADV-21. The sampling locations, measurement and testing methodology are detailed in the Sediment Sampling and Testing Plan (SSTP), which was approved by EPD on 13 March 2013.  Details of SSTP and the approval letter from EPD are given in Appendix 10.4.

10.4.1.28 As given in the SSTP, vibrocore sampling was carried out at two locations, namely, RV12 and RV13, in the vicinity of the field joint area as shown in Drawing No MCL/P132/EIA/10-002. The vibrocore sampling locations are at about 120 m away from the existing cable location, which is the buffer distance recommended by CLP to safeguard the existing cable from any potential damage by the vibrocore sampling work.  At each sampling location, sediment sub-samples were collected at the seabed and at depths of 0.9 m down, 1.9 m down 2.9 m down and then at every 3 m to the bottom of the sediment layer.  The chemical and biological testing results of the collected sediment sub-samples are given in Appendix 10.5a and are also summarised in Table 10.6.  In summary, the testing results show that according to the PNAP ADV-21, 10 of the sediment sub-samples are classified as Category L with no exceedance of any LCEL while the remaining four sub-samples are classified as Category M with exceedance of the LCEL for arsenic only. However, the four sub-samples with arsenic exceedance passed the required biological tests in accordance with the requirements in PNAP ADV-21.

Table 10.6: Summary of Chemical Testing Results for Sediment Sub-samples Collected near Field Joint Area

Sampling Location

Depth of Sub-samples

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

RV12

0.10 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

8.90 – 11.90 m

12.00 – 14.90 m

Nil

Nil

Category L

RV13

0.10 – 0.90 m

Arsenic (18 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (14 mg/kg)

Nil

Category M

1.90 – 2.90 m

Nil

Nil

Category L

2.90 – 5.90 m

Arsenic (15 mg/kg)

Nil

Category M

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 12.90 m

Nil

Nil

Category L

12.00 – 14.90 m

Arsenic (13 mg/kg)

Nil

Category M

*Values inside brackets represent concentrations of the parameters that exceeded the corresponding Lower Chemical Exceedance Level (LCEL) or Upper Chemical Exceedance Level ( UCEL) as specified in the PNAP ADV-21.

10.4.1.29 Based on the tentative construction programme (refer to Appendix 4.2), dredging of marine sediments from the field joint area would take place in 2015/2016, which is over one year before the majority of the filling works for the proposed land formation is scheduled to begin.  Due to this non-alignment with the overall construction programme, the opportunity for on-site treatment and reuse of the marine sediments generated by field joint dredging would be unlikely.  Therefore, it is anticipated that off-site disposal of the sediments would be needed.

10.4.1.30 Based on PNAP ADV-21, the disposal methods for sediments classified as Category L and Category M with biological tests passed (or Category Mp) are open sea disposal and open sea disposal at dedicated sites respectively.  Therefore, marine dumping permit for disposal of marine sediments to be dredged from the field joint area will need to be obtained in advance according to the relevant requirements of PNAP ADV-21.   Based on the sediment testing results, the sub-samples at RV12 down to a depth of 5 m (i.e., the dredging depth of the field joint area) are all classified as Category L whereas majority of the sub-samples at RV13 down to the depth of 5 m are classified as Category Mp.  Therefore, it can be roughly estimated that about 50% of the sediments to be dredged from the field joint area would be of Category L and the remaining 50% would be of Category Mp, as summarised in Table 10.7. 

Table 10.7: Summary of Marine Sediments from Field Joint Area Requiring Disposal

Category

Quantity to be Disposed (in-situ volume, m3)

Disposal Method*

Category L

5,100

Type 1 – Open Sea Disposal

Category Mp

5,100

Type 1 – Open Sea Disposal (Dedicated Site)

*Based on PNAP ADV-21

10.4.1.31 AAHK has been liaised with the Marine Fill Committee (MFC) of CEDD to seek their approval on the rationale for removal of sediment from the field joint excavation and to request for provisional allocation of disposal capacity at appropriate marine disposal site for the sediments. Relevant correspondences on the provisional allocation of space for disposal of marine sediment with MFC are provided in Appendix 10.6. No field joint excavation work would be permitted to proceed until all matters on marine sediment disposal have been resolved and all relevant arrangements have been endorsed by the appropriate authorities, including MFC and EPD.

Piling Works within the Proposed Land Formation Area

10.4.1.32 It is anticipated that the work including pile cap that would be required for construction of the TRC, APM & BHS tunnels, airside tunnels and other facilities would result in the excavation of marine sediment. However, it is anticipated that a number of the piles and pile cap would pass through CMP material.  The expected volumes will vary depending on the location and depth of the piles and the depth of the CMP area.  Based on current project design information, the volumes of CMP material and marine sediments estimated to be excavated as a result of the foundation piling, based on 100% excavation and 0% consolidations, are summarised in Table 10.8.  A description of the likely chemical characteristics of such materials is provided below.

Table 10.8: Estimated Quantity of CMP and Marine Sediments from Piling Works on Proposed Land Formation Area

Sediments

Estimated Quantity of Sediments Generated from Piling Works ( in-situ volume, m3)

Tentative Timeframe of Generation

CMP Sediments

499,550

Q2 of 2017 to Q1 of 2022

Marine Sediments (from outside CMP area)

205,800

Q1 of 2017 to Q3 of 2022

Total

705,350

Q1 of 2017 to Q3 of 2022

10.4.1.33 As detailed in the SSTP, vibrocore sampling was carried out within the area that is proposed as the land formation footprint. The investigation included 11 locations (AV01 to AV11) within the CMP area and 11 locations (RV01 to RV11) outside the CMP area as shown in Drawing No. MCL/P132/EIA/10-003. At each sampling location, sediment sub-samples were collected at the seabed, 0.9 m down, 1.9 m down 2.9 m down and then every 3 m to the bottom of the sediment layer.  In preparation for the Deep Cement Mixing (DCM) trial completed in February 2012, similar vibrocore sampling was also conducted at 20 locations (TC1A to TC20A) within the CMP area in April 2011, with the sampling locations shown in Drawing No. MCL/P132/EIA/10-003.  The chemical testing results of sediment sub-samples collected at the relevant sampling locations within the CMP and non-CMP areas where the future TRC, APM & BHS tunnels and airside tunnels will be constructed, i.e., AV08, AV10, TC7A to TC9A, TC15A to TC16A and RV07 to RV11, are given in Appendix 10.5b and are also summarised in Table 10.9. 

10.4.1.34 In summary, the testing results show that:

¡  Seven of the sub-samples collected within the CMP are classified as Category H according to the PNAP ADV-21 with exceedance of the LCEL for silver, chromium, mercury, arsenic, copper, lead, zinc and/or high molecular weight Polycyclic Aromatic Hydrocarbons (PAH) and exceedance of the UCEL for copper, nickel, zinc and/or mercury.  For the remaining 47 sub-samples, 29 of them are classified as Category L with no exceedance of any LCEL while the other 18 sub-samples are classified as Category M with exceedance of the LCEL for arsenic, silver, copper, lead, zinc and/or mercury.

¡  Nineteen of the sub-samples taken from outside the CMP area are classified as Category L with no exceedance of any LCEL while the remaining 13 sub-samples are classified as Category M with exceedance of the LCEL for arsenic only.

Table 10.9:    Summary of Chemical Testing Results for Sediment Sub-samples Collected within/close to TRC, APM & BHS Tunnels and Airside Tunnels Footprint

Sampling Location

Depth of Sub-samples

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

Testing Results within CMP Area

AV08

0.20 – 0.90 m

Arsenic (16 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (16 mg/kg)

Nil

Category M

1.90 – 2.90 m

Nil

Nil

Category L

2.90 – 5.90 m

Arsenic (14 mg/kg)

Nil

Category M

6.00 – 8.90 m

Copper (76 mg/kg)

Nil

Category M

8.90 – 11.90 m

Nil

Nil

Category L

12.00 – 14.90 m

Arsenic (25 mg/kg)

Nil

Category M

14.90 – 16.90 m

Nil

Nil

Category L

AV10

0.00 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

8.90 – 10.60 m

Nil

Nil

Category L

TC7A

0.10 – 0.90 m

Arsenic (13 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (20 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (14 mg/kg)

Chromium (89 mg/kg)

Copper (121 mg/kg)

Nickel (52 mg/kg)

Category H

2.90 – 3.90 m

Silver (1.2 mg/kg)

Copper (130 mg/kg)

Nickel (44 mg/kg)

Category H

6.00 – 6.90 m

Chromium (81 mg/kg)

Copper (100 mg/kg)

Nickel (45 mg/kg)

Category H

8.90 – 9.90 m

Silver (1.1 mg/kg)

Copper (106 mg/kg)

Nil

Category M

12.00 – 12.90 m

14.90 – 15.90 m

18.00 – 18.90 m

20.90 – 21.90 m

Nil

Nil

Category L

TC8A

0.00 – 0.90 m

Arsenic (23 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (23 mg/kg)

Nil

Category M

1.90 – 2.90 m

2.90 – 3.90 m

6.20 – 6.90 m

8.90 – 9.90 m

Nil

Nil

Category L

12.00 – 13.00 m

Lead (80 mg/kg)

Zinc (212 mg/kg)

Mercury (0.57 mg/kg)

Nil

Category M

TC9A

0.00 – 0.90 m

Arsenic (13 mg/kg)

Nil

Category M

0.90 – 1.90 m

Nil

Nil

Category L

1.90 – 2.90 m

Arsenic (17 mg/kg)

Nil

Category M

2.90 – 3.90 m

Silver (1.1 mg/kg)

Lead (85 mg/kg)

Zinc (218 mg/kg)

High molecular weight PAH  (2,040 µg/kg)

Copper (122 mg/kg)

Nickel (43 mg/kg)

Category H

6.40 – 6.90 m

6.90 – 7.90 m

8.90 – 9.90 m

12.00 – 12.90 m

Nil

Nil

Category L

14.90 – 15.90 m

Arsenic (13 mg/kg)

Nickel (143 mg/kg)

Zinc (310 mg/kg)

Category H

18.00 – 18.90 m

Nil

Nil

Category L

TC15A

0.00 – 0.90 m

Arsenic (14 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (14 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (14 mg/kg)

Lead (80 mg/kg)

Mercury (1.24 mg/kg)

Category H

2.90 – 3.90 m

6.00 – 6.90 m

Nil

Nil

Category L

8.90 – 9.90 m

Arsenic (17 mg/kg)

Nil

Category M

9.90 – 10.90 m

Arsenic (13 mg/kg)

Nil

Category M

TC16A

0.00 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

Nil

Nil

Category L

2.90 – 3.90 m

Arsenic (16 mg/kg)

Nil

Category M

6.00 – 6.90 m

Silver (2 mg/kg)

Mercury (0.51 mg/kg)

Copper (197 mg/kg)

Category H

8.90 – 9.80 m

Nil

Nil

Category L

Testing Results outside CMP Area

RV07

0.00 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.90 m

Arsenic (13 mg/kg)

Nil

Category M

12.00 – 14.90 m

Arsenic (18 mg/kg)

Nil

Category M

RV08

0.00 – 0.90 m

Arsenic (14 mg/kg)

Nil

Category M

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

Nil

Nil

Category L

5.90 – 8.90 m

Arsenic (25 mg/kg)

Nil

Category M

8.90 – 9.70 m

Nil

Nil

Category L

RV09

0.00 – 0.90 m

Arsenic (13mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (13 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (14 mg/kg)

Nil

Category M

2.90 – 5.90 m

Nil

Nil

Category L

6.00 – 8.90 m

Arsenic (20 mg/kg)

Nil

Category M

8.90 – 9.90 m

Arsenic (27mg/kg)

Nil

Category M

RV10

0.10 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

Nil

Nil

Category L

2.90 – 5.90 m

Arsenic (14 mg/kg)

Nil

Category M

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.70 m

Arsenic (19 mg/kg)

Nil

Category M

RV11

0.10 – 0.90 m

Arsenic (13 mg/kg)

Nil

Category M

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.90 m

Arsenic (19 mg/kg)

Nil

Category M

12.00 – 14.90 m

Nil

Nil

Category L

*Values inside brackets represent concentrations of the parameters that exceeded the corresponding Lower Chemical Exceedance Level (LCEL) or Upper Chemical Exceedance Level ( UCEL) as specified in the PNAP ADV-21.

10.4.1.35 Based on the sediment characterisation results as summarised in Table 10.10, it can be estimated that about 54.4%, 35.3% and 10.3% of the sediments to be excavated from within the CMP areas would be classified as Category L, M and H respectively.  For sediments to be excavated from outside the CMP areas, around 56.5% and 43.5% of them would be characterised as Category L and M respectively (no sediments of Category H). 

Table 10.10: Estimated Quantity of Different Categories of Sediments from Piling Works on Proposed Land Formation Area

Item

CMP Sediments

Marine Sediments (from outside CMP areas)

 

Category*

Total

Category*

Total

 

L

M

H

L

M

H

 

No. of sub-samples

29

18

7

54

19

13

0

32

Depth of sub-samples (m)

37

24

7

68

35

27

0

62

% depth of sub-samples

54.4%

35.3%

10.3%

100%

56.5%

43.5%

0%

100%

Estimated quantity of sediments (in-situ volume, m3)

271,820

176,310

51,420

499,550

116,180

89,620

0

205,800

* Based on PNAP-ADV21

10.4.1.36 In order to avoid disposal of the sediments generated from the foundation / piling work, it is proposed to treat all the sediments using cement mixing and stabilisation / solidification method.  It is currently proposed that the treated material would then be reused as backfilling materials on-site, although treatment level / details and the reuse mode are under further development.  Initially, a minimum cement content of 5% weight per weight (w/w) is proposed as treatment of the CMP sediments and marine sediments. The treated sediment will then be tested against the relevant Risk Based Remediation Goals (RBRGs), the Toxicity Characteristics Leaching Procedure (TCLP) and the Unconfined Compressive Strength (UCS) before reuse. Subject to the TCLP and UCS test results, the cement content may need to be increased.  Details of the sediment treatment are presented in Section 10.5.1. Excavation/ dredging of sediment should not proceed until all issues on management of excavated/ dredged sediment have been resolved and all relevant arrangements have been endorsed by the relevant authorities including MFC and EPD.

Piling works for the Approach Lights of the Proposed Third Runway

10.4.1.37 Approach lights will be installed within the paved areas of both the new third runway and the centre runway.  For the proposed new third runway, a section of the approach lights will extend off either end of the eastern and western edges of the land formation area into the adjacent marine waters.

10.4.1.38 At the current stage of project design, it is proposed that the sections of the approach lights that would be erected in the sea will be bore-piled with a pile cap, on top of which the light barrette will be placed.     

10.4.1.39 It is anticipated that the eastern section of the approach lights for the new runway will extend into an area of CMP.  Therefore, it is currently proposed that the area beneath each light stand will be treated with reduced cement ratio DCM prior to piling.  A description of the characteristics of the material that is likely to be encountered is provided below.  This approach will facilitate the management of the material extracted from piling and provide additional support during installation of the piles. 

10.4.1.40 Based on the project design information, it is estimated that approximately 530 m3 of marine sediments would be excavated from the piling work for the western approach lights whereas about 1,060 m3 of DCM-treated sediments would be excavated from the piling work for the eastern approach lights.  The construction programme for the piling works is subject to the detailed design.  Nevertheless, as both the western and eastern approach lights will have to be completed by 2021 when the proposed third runway will commence its operation (see Section 4.3), it is anticipated that the piling works for the approach lights would be carried out in 2018 to 2019 when majority of the land formation work for the proposed third runway would be completed.

10.4.1.41 As detailed in the SSTP, vibrocore sampling was conducted at RV01 and RV02 near the west end of the proposed third runway, as shown in Drawing No. MCL/P132/EIA/10-003.  At each sampling location, sediment sub-samples were collected at the seabed, 0.9 m down, 1.9 m down 2.9 m down and then every 3 m to the bottom of the sediment layer. The chemical testing results of the collected sediment sub-samples are given in Appendix 10.5c and are also summarised in Table 10.11. In summary, the testing results show that according to the PNAP ADV-21, eight of the sediment sub-samples are classified as Category L with no exceedance of any LCEL while the remaining five sub-samples are classified as Category M with exceedance of the LCEL for arsenic only.

10.4.1.42 Vibrocore sampling was conducted at AV11 and TC17A near the east end of the proposed third runway, as shown in Drawing No. MCL/P132/EIA/10-003. The chemical testing results of the collected sediment sub-samples are given in Appendix 10.5c and are also summarised in Table 10.11. In summary, the testing results show that according to the PNAP ADV-21, eight of the sediment sub-samples are classified as Category L with no exceedance of any LCEL, nine sub-samples are classified as Category M with exceedance of the LCEL for arsenic, silver and copper, , while the remaining three sub-samples are classified as Category H with exceedance of the LCEL for cadmium, silver and lead as well as with exceedance of the UCEL for silver, chromium, copper, nickel and zinc.

10.4.1.43 Marine sediments excavated from the piling work for the west-end approach lights will be treated and reused on-site as described earlier.

Table 10.11: Summary of Chemical Testing Results for Sediment Sub-samples Collected near West End of Third Runway

Sampling Location

Depth of Sub-sample

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

West-end Approach Lights

RV01

0.00 – 0.90 m

Arsenic (14 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (14 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (14 mg/kg)

Nil

Category M

2.90 – 5.90 m

Arsenic (13 mg/kg)

Nil

Category M

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.90 m

Nil

Nil

Category L

12.00 – 14.40 m

Arsenic (16 mg/kg)

Nil

Category M

RV02

0.60 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

8.90 – 11.80 m

Nil

Nil

Category L

East-end Approach Lights

AV11

0.00 – 0.90 m

Arsenic (15 mg/kg)

Nil

Category M

0.90 – 1.90 m

Silver (1.5 mg/kg)

Copper (77 mg/kg)

Nil

Category M

1.90 – 2.90 m

Cadmium (2 mg/kg)

Lead (76 mg/kg)

Silver (18.2 mg/kg)

Chromium (218 mg/kg)

Copper (523 mg/kg)

Nickel (177 mg/kg)

Zinc (347 mg/kg)

Category H

2.90 – 5.90 m

Arsenic (13 mg/kg)

Nil

Category M

6.20 – 8.90 m

Silver (2 mg/kg)

Lead (79 mg/kg)

Copper (139 mg/kg)

Category H

8.90 – 11.90 m

12.00 – 13.55 m

Nil

Nil

Category L

TC17A

0.00 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 3.90 m

Nil

Nil

Category L

6.00 –6.90 m

Nil

Copper (117 mg/kg)

Category H

8.90 – 9.90 m

Copper (80 mg/kg)

Nil

Category M

12.00 –12.90 m

Nil

Nil

Category L

14.90 – 15.90 m

Arsenic (14 mg/kg)

Nil

Category M

18.00 – 18.90m

Nil

Nil

Category L

20.90 – 21.90 m

24.00 – 24.90 m

Arsenic (16 mg/kg) Arsenic (25 mg/kg)

Nil

Category M

25.90 – 26.90 m

Arsenic (13 mg/kg)

Nil

Category M

26.90 – 27.80 m

Arsenic (18 mg/kg)

Nil

Category M

*Values inside brackets represent concentrations of the parameters that exceeded the corresponding Lower Chemical Exceedance Level (LCEL) or Upper Chemical Exceedance Level ( UCEL) as specified in the PNAP ADV-21

Piling work for the Proposed HKIAAA beacons

10.4.1.44 A line of new HKIAAA beacons will be installed to mark the northern boundary of the restricted zone around the third runway.

10.4.1.45 At the current stage of project design, it is proposed that rock socketed H piles will be used to support the beacons. Based on the project design information, it is estimated that approximately 220 m3 of marine sediments would be excavated from the piling work for the beacons. The construction programme for the piling works is subject to the detailed design.  Nevertheless, as HKIAAA beacons will have to be completed by 2021 when the proposed third runway will commence its operation (see Section 4.3.1), it is anticipated that the piling works for the beacons would be carried out in 2018 to 2019 when majority of the land formation work for the proposed third runway would be completed.

10.4.1.46 As detailed in the SSTP, vibrocore sampling was conducted at RV01 to RV05 near the locations of proposed beacons, as shown in Drawing No. MCL/P132/EIA/10-003.  At each sampling location, sediment sub-samples were collected at the seabed, 0.9 m down, 1.9 m down 2.9 m down and then every 3 m to the bottom of the sediment layer. The chemical testing results of the collected sediment sub-samples are given in Appendix 10.5c and are also summarised in Table 10.12. In summary, the testing results show that according to the PNAP ADV-21, 20 of the sediment sub-samples are classified as Category L with no exceedance of any LCEL while the remaining 14 sub-samples are classified as Category M with exceedance of the LCEL for arsenic only.

10.4.1.47 Marine sediments excavated from the piling work for HKIAAA beacons will be treated and reused on-site as described earlier.

Table 10.12: Summary of Chemical Testing Results for Sediment Sub-samples Collected near HKIAA Beacons

Sampling Location

Depth of Sub-sample

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

RV01

0.00 – 0.90 m

Arsenic (14 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (14 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (14 mg/kg)

Nil

Category M

2.90 – 5.90 m

Arsenic (13 mg/kg)

Nil

Category M

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.90 m

Nil

Nil

Category L

12.00 – 14.40 m

Arsenic (16 mg/kg)

Nil

Category M

RV02

0.60 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

8.90 – 11.80 m

Nil

Nil

Category L

RV03

0.00 – 0.90 m

Arsenic (14 mg/kg)

Nil

Category M

0.90 – 1.90 m

Arsenic (16 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (17 mg/kg)

Nil

Category M

2.90 – 5.90 m

Arsenic (15 mg/kg)

Nil

Category M

6.00 – 8.90 m

8.90 – 11.90 m

12.00 – 14.90 m

Nil

Nil

Category L

RV04

0.10 – 0.90 m

Nil

Nil

Category L

0.90 – 1.90 m

Arsenic (15 mg/kg)

Nil

Category M

1.90 – 2.90 m

Arsenic (15 mg/kg)

Nil

Category M

2.90 – 5.90 m

Arsenic (16 mg/kg)

Nil

Category M

6.10 – 8.90 m

Arsenic (14 mg/kg)

Nil

Category M

8.90 – 11.90 m

Arsenic (13 mg/kg)

Nil

Category M

12.00 – 14.90 m

Nil

Nil

Category L

RV05

0.00 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

8.90 – 11.90 m

12.90 – 14.90 m

Nil

Nil

Category L

*Values inside brackets represent concentrations of the parameters that exceeded the corresponding Lower Chemical Exceedance Level (LCEL) or Upper Chemical Exceedance Level ( UCEL) as specified in the PNAP ADV-21

Basement work for the Proposed T2 Expansion and Excavation works for the Proposed APM Depot

10.4.1.48 The existing T2 building will be expanded in order to provide space to meet the future passenger demand. The expanded T2 building is generally bounded by the airport road networks to the north, south and east, with the Ground Transportation Centre (GTC) to the west. The proposed T2 expansion works will consist of three key parts, i.e., expansion of the T2 building, construction of the new North Annex Building, and construction of the new South Annex Building.

10.4.1.49 The existing underground APM depot beneath the existing T2 building will be relocated to the east of T2 in order to accommodate the future APM network capacity. The new underground APM depot will be established at the existing golf course.

10.4.1.50 According to the preliminary ground investigation (GI) woks undertaken during October to November 2013, excavation of marine deposit (mainly sand) would be encountered at some of the T2 expansion works including the proposed North Annex Building and northern part of proposed T2 expansion area as well as at the proposed new APM depot which was historically seabed area as shown in Drawing MCL/P132/EIA/10-004.

10.4.1.51 Based on the preliminary drillhole record of P282-DH2 as shown in Appendix 10.7, marine deposit would be encountered between the depths of -0.40 mPD and -3.51 mPD, whereas the anticipated excavation level at the North Annex Building is down to about -6.5 mPD. No marine deposit was found in the drillhole record of P282-DH4 as shown in Appendix 10.7 and part of the North Annex Building is located at the historical Chek Lap Kok island where marine deposit would not be expected, as shown in Drawing MCL/P132/EIA/10-004. Based on the drillhole record and the latest engineering design, it can be estimated that about 44,400 m3 of marine deposit would be generated from the excavation at North Annex Building.

10.4.1.52 Based on the preliminary drillhole record of P282-DH3 as shown in Appendix 10.7, marine deposit would be encountered between the depths of -5.91 mPD and -11.91 mPD, whereas the anticipated excavation level at the T2 expansion area is down to about -6.5 mPD. Based on the drillhole record of P282-DH6 as shown in Appendix 10.7, no marine deposit was found. Based on the drillhole record and the latest engineering design, it can be estimated that about 6,330 m3 of marine deposit would be generated from the excavation at T2 expansion area.

10.4.1.53 Based on the preliminary drillhole record of P283-DH036 and P283-DH038 as shown in Appendix 10.7, marine deposit would be encountered between the depths of 0.52 mPD and -0.21 mPD and between the depths of 1.50 mPD and -1.60 mPD respectively, whereas the anticipated excavation level at the APM depot is down to about -6.5 mPD. No marine deposit was recorded in P283-DH039, P283-DH041 and P283-DH042 as shown in Appendix 10.7. A large part of the APM depot is located at the historical Chek Lap Kok island where marine deposit would not be expected, as shown in Drawing MCL/P132/EIA/10-004.  Based on the drillhole record and the latest engineering design, it can be estimated that about 9,770 m3 of marine deposit would be generated from the excavation at APM depot.

10.4.1.54 It is estimated that approximately 50,730 m3 of marine deposit would be excavated from the basement work for the proposed T2 expansion during the period from Q4 of 2016 to Q1 of 2019 while approximately 9,770 m3 of marine deposit would be generated from the excavation work for the proposed APM depot during the period from Q1 of 2018 to Q3 of 2020.

10.4.1.55 As part of the completed sampling and testing work at the proposed land formation footprint, vibrocore sampling and testing works were completed at seabed locations around the northeast corner of the existing airport island (RV10 and RV11), which are not far away from the T2 expansion works or APM depot locations as shown in Drawing MCL/P132/EIA/10-005. The chemical testing results of the collected sediment sub-samples are given in Appendix 10.8a and are also summarised in Table 10.13.

Table 10.13: Summary of Chemical Testing Results for Sediment Sub-samples Collected around the Northeast Corner of the Existing Airport Island

Sampling Location

Depth of Sub-samples

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

RV10

0.10 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

Nil

Nil

Category L

2.90 – 5.90 m

Arsenic (14 mg/kg)

Nil

Category M

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.70 m

Arsenic (19 mg/kg)

Nil

Category M

RV11

0.10 – 0.90 m

Arsenic (13 mg/kg)

Nil

Category M

0.90 – 1.90 m

1.90 – 2.90 m

2.90 – 5.90 m

6.00 – 8.90 m

Nil

Nil

Category L

8.90 – 11.90 m

Arsenic (19 mg/kg)

Nil

Category M

12.00 – 14.90 m

Nil

Nil

Category L

*Values inside brackets represent concentrations of the parameters that exceeded the corresponding Lower Chemical Exceedance Level (LCEL) or Upper Chemical Exceedance Level ( UCEL) as specified in the PNAP ADV-21.

10.4.1.56 As identified from the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (HKBCF) EIA Report (Register No.: AEIAR-145/2009), vibrocore sampling and testing works were done at seabed locations (BCF/VC-A03, BCF/VC-B06, BCF/VC-B09 and BCF/VC-C11) that are close to the T2 expansion works and APM depot locations as shown in Drawing MCL/P132/EIA/10-005. The chemical testing results of the collected sediment sub-samples are given in Appendix 10.8b and are also summarised in Table 10.14.

Table 10.14: Summary of Chemical Testing Results for Sediment Sub-samples Collected close to the T2 Expansion Works and APM Depot Locations from the HKBCF EIA Report

Sampling Location

Depth of Sub-samples

Parameters Exceeding LCEL*

Parameters Exceeding UCEL*

Classification

BCF/VC-A03

0.20 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

4.90 – 5.90 m

7.90 – 8.90 m

Nil

Nil

Category L

12.00 – 12.90 m

14.90 – 15.90 m

15.90 – 16.35 m

Arsenic (14 mg/kg)

Arsenic (15 mg/kg)

Arsenic (15 mg/kg)

Nil

Category M

BCF/VC-B06

0.35 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

4.90 – 5.90 m

7.90 – 8.90 m

9.90 – 10.90 m

10.90 – 11.35 m

Nil

Nil

Category L

BCF/VC-B09

0.10 – 0.90 m

0.90 – 1.90 m

Arsenic (12 mg/kg)

Arsenic (14 mg/kg)

Nil

Category M

1.90 – 2.90 m

4.90 – 5.90 m

7.90 – 8.90 m                     

12.10 – 12.90 m

Nil

Nil

Category L

14.90 – 15.90 m

18.00 – 18.90 m

Arsenic (14 mg/kg)

Arsenic (13 mg/kg)

Nil

Category M

BCF/VC-C11

0.30 – 0.90 m

0.90 – 1.90 m

1.90 – 2.90 m

4.90 – 5.90 m

Nil

Nil

Category L

7.90 – 8.90 m

9.90 – 10.80 m

Arsenic (14 mg/kg)

Arsenic (13 mg/kg)

Nil

Category M

Source:   Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities  EIA Report (Register No.: AEIAR-145/2009)

10.4.1.57 The tested parameters of all sediment samples as shown in Table 10.13 and Table 10.14 did not exceed their corresponding LCEL, as defined in PNAP ADV-21, with the exception of arsenic which exceeded its LCEL for some sub-samples. Therefore, all these sediment samples are classified as either Category L or Category M with arsenic exceedance based on the criteria of PNAP ADV-21. Based on the above available sediment testing results around the northeast corner of the existing airport island, it is anticipated that the marine deposit to be excavated from the proposed T2 expansion works and APM depot would likely be Category L or Category M with arsenic exceedance.

10.4.1.58 Marine deposit to be excavated from the T2 expansion works and APM depot will be treated and reused on-site as described earlier.

Chemical Waste

10.4.1.59 The operation, maintenance and servicing of construction plant and equipment has the potential to generate chemical waste such as cleansing fluids, solvents, oil, fuel, etc. It is difficult to quantify the amount of chemical waste that will arise from the construction activities as this will be dependent on the contractor’s on-site maintenance requirements and the amount of plant ultimately utilised. However, it is anticipated that the quantity of chemical waste would be relatively small. The amount of chemical waste to be generated will be quantified in the site Waste Management Plan to be prepared by contractors. 

10.4.1.60 Chemical waste generated during construction has the potential to pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner, in accordance with the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:

¡  Toxic effects to workers;

¡  Adverse impact on water quality and wildlife from spills; and

¡  Fire hazards.

10.4.1.61 Materials classified as chemical wastes will require special handling and storage arrangements before off-site disposal at Chemical Waste Treatment Centre or other licensed chemical waste recycling/ treatment facilities. The chemical wastes will be delivered to the off-site licensed facilities by trucks through North Lantau Highway and Tsing Sha Highway. Due to the anticipated small amount of chemical wastes requiring delivery, the extra traffic loading on North Lantau Highway/ Tsing Sha Highway would be minimal.  Wherever possible opportunities will be taken to reuse and recycle materials, preferably on site. Mitigation and control requirements for chemical wastes are detailed in Section 10.5.1. Provided that the handling, storage and disposal of chemical wastes are implemented in accordance with these requirements, adverse environmental impact would not be expected.

General Refuse

10.4.1.62 The construction workforce would generate general refuse comprising food scraps, waste paper, empty containers, etc. These waste materials must be collected, stored and managed in a manner that minimises the risk of intentional or accidental release to the surrounding environment, and eliminates the potential to produce Foreign Object Debris (FOD) – a safety risk when operating in an active airport environment. Release of any general refuse into marine waters should be strictly prohibited in order to avoid adverse impact on water quality in the area. Disposal of refuse at sites other than approved waste transfer or disposal facilities will be prohibited. The effective collection and storage of site waste would be required to prevent waste materials from being blown around by wind, flushed or leached into the surrounding environment or creating an odour nuisance. Waste storage areas will be well maintained and cleaned regularly so as to avoid attracting pests and vermin to work sites. The management of sewage that would be generated by construction workforce during the construction phase of the project is assessed in Chapter 8.

10.4.1.63 A provisional estimate based on the current tentative phasing of construction works anticipates that the maximum number of workers on site would be up to 14,000. Based on a generation rate of 0.65 kg per worker per day, the maximum daily arising of general refuse from construction workers would be up to 9,100 kg. Corresponding to this maximum daily volume, up to around 10 vehicle-trips per day would be needed for delivery of the general refuse by dump trucks (each with a loading capacity of about 6 m3) to the West New Territories Landfill (WENT) landfill via North Lantau Highway.  Given this small daily number of vehicle-trips, the extra traffic loading on North Lantau Highway would be negligible.  With the adequate implementation of appropriate waste management practices on the site during construction (as recommended in Section 10.5.1), significant adverse environmental impact would not be expected from the storage, handling and transportation of refuse.

10.4.1.64 The refuse should be temporarily stored in enclosed bin to avoid adverse impact to the surroundings. Recycling bins should be provided to maximise waste reuse and recycle volume. A reputable licensed collector should be employed to collect the general refuse for disposal at designated landfill sites.

Floating Refuse

10.4.1.65 Floating refuse may be trapped or accumulated in the existing seawall or the newly constructed seawall during the construction phase.  As detailed in Section 10.4.2, it can be estimated based on the historical records that roughly 65 m3 of floating refuse will be collected from the newly constructed seawall during each year of construction.

10.4.1.66 The future artificial seawall of the proposed airport expansion area has been properly designed to achieve a shoreline that does not have any sharp turns or abrupt indentation in order to avoid or minimise any trapped or accumulated refuse.  The construction contractors will be required to regularly check and clean any refuse trapped or accumulated along the newly constructed seawall.  Floating refuse will be collected by a reputable licensed waste collector for disposal at WENT landfill by dump trucks through North Lantau Highway.  Given the small estimated quantity of floating refuse requiring delivery every year, the additional traffic loading on North Lantau Highway would be negligible.  With the proper seawall design and regular checking and cleaning of such refuse, no adverse environmental impact associated with such refuse are anticipated.

Summary

10.4.1.67 Table 10.15 presents a summary of the key types of waste that are expected to be generated during the construction phase of the project. Table 10.16 presents a summary of the methods by which wastes arising are avoided or reduced through consideration of alternative design options and/or construction methods.


Table 10.15: Summary of Waste Arising during Construction Phase

Waste Type

Key Sources of Waste Generation

Timing of Waste Generation

Estimated Total Quantity of Waste Generation

Waste Reuse or Disposal

Handling Methods

Inert C&D Material

Excavation for APM & BHS tunnels, new APM depot and airside tunnels; piling works for TRC & other buildings; superstructure construction works; surplus surcharge material; modification of existing northern seawall; excavation and demolition as well as superstructure construction works for T2 expansion; excavation for improvement of road networks; and HDD for diversion of existing submarine pipelines

Q3 of 2015 to Q4 of 2022

9,543,500 m3

(in-situ volume)

About 3,639,230 m3 of the inert C&D materials generated would be reused on-site as fill materials for the proposed land formation works. 

The remaining 5,904,270 m3 would be delivered off-site to any identified projects that would need fill materials and/or to the government’s PFRF for beneficial use by other projects in Hong Kong.  

Segregation of  inert C&D material to avoid contamination from other waste arising

Stockpile areas should be covered and applied with regular water spraying

Non-inert C&D Material

Site clearance of the golf course area; demolition works for T2 expansion; and superstructure construction works for various buildings/ facilities

Q4 of 2016 to Q4 of 2021

96,200 m3

(in-situ volume)

The non-inert C&D material will be disposal of at landfills after on-site sorting and segregation of recyclable materials

Separation of non-  inert C&D materials from inert C&D materials

Stored in compatible containers in designated area on-site

Excavated Marine Sediments

Excavation at the cable field joint area

2015/2016

About 10,200 m3

 (in-situ volume)

Type 1 open sea disposal for Category L sediment or Type 1 open sea disposal at dedicated sites for Category Mp sediment, according to PNAP ADV-21 (subject to endorsement by MFC of CEDD and EPD  as well as obtaining dumping permit from EPD under DASO)

Stockpile with tarpaulin covers with earth bunds and sand bags barriers, if applicable.

 

Piling works of the TRC, APM & BHS tunnels, airside tunnels and other facilities on the proposed land formation area

Q1 of 2017 to Q3 of 2022

About 705,350 m3

 (in-situ volume)

Treatment by cement mixing and stabilisation and on-site reuse of treated sediments as backfilling materials, although the treatment level / details and the reuse mode are under further development.

 

 

Piling works of marine sections of the approach lights for the third runway

2018 to 2019 (subject to detailed design)

Western approach lights: about 530 m3 of marine sediments (in-situ volume)

Eastern approach lights: about 1,060 m3 of DCM-treated sediment (in-situ volume)

Treatment by cement mixing and stabilisation and on-site reuse of treated sediments as backfilling materials, although the treatment level / details and the reuse mode are under further development.

 

 

Piling works of new HKIAAA beacons

2018 to 2019 (subject to detailed design)

About 220 m3

(in-situ volume)

Treatment by cement mixing and stabilisation and on-site reuse of treated sediments as backfilling materials, although the treatment level / details and the reuse mode are under further development.

 

 

Basement works of T2 expansion

Q4 of 2016 to Q1 of 2019

About 50,730 m3

 (in-situ volume)

Treatment by cement mixing and stabilisation and on-site reuse of treated sediments as backfilling materials, although the treatment level / details and the reuse mode are under further development.

 

 

Excavation works of APM depot

Q1 of 2018 to Q3 of 2020

About 9,770 m3

 (in-situ volume)

Treatment by cement mixing and stabilisation and on-site reuse of treated sediments as backfilling materials, although the treatment level / details and the reuse mode are under further development.

 

Chemical Waste

Used cleansing fluids, solvents, lubricating oil, waste fuel, etc., from maintenance and servicing of construction plant and equipment

2015 to Early 2023

Anticipated as small quantity

To be quantified in the site Waste Management Plan to be prepared by the Contractor

Disposal of at the Chemical Waste Treatment Centre or other licensed recycling facilities

Stored in compatible containers in designated area on-site

General Refuse & Floating Refuse

Food scraps, waste paper, empty containers, etc. generated from the construction workforce

 

2015 to Early 2023

General refuse: maximum daily arising of up to 9,100 kg

 

Encourage segregation of recyclable materials (e.g., paper, tin-cans, etc.) for collection by outside recyclers

Collection of non-recyclable refuse by a reputable collector for disposal at designated landfill sites.

Provide on-site collection points together with recycling bins

 

 

 

Floating refuse trapped or accumulated in the newly constructed seawall

2015 to Early 2023

Floating refuse: roughly 65 m3/year to be collected from the newly constructed seawall

Collection by a reputable waste collector for disposal at designated landfill sites

Provide on-site collection points

Table 10.16: Summary of Waste Avoidance / Reduction through Alternative Design Options / Construction Methods

Design / Works Component

Design Option / Construction Segment

Waste Avoidance / Reduction Mechanism

Land Formation

Ground improvement

The use of only non-dredge methods for ground improvement will completely avoid bulk removal and disposal of any dredged materials.

 

Seawall

Most sloping seawall options can allow for the reuse of all rock armour from the existing northern seawall to minimise waste generation.

 

Filling works

Priority will be given to maximise the use of suitable fill materials available from other concurrent projects and the Government’s PFRF.

Construction of Various Buildings and Infrastructure Facilities

Excavation works for various facilities and buildings

In order to minimise the extent of excavation and to maximise on-site reuse of the inert C&D materials generated by the project as far as practicable, the relevant construction activities (particularly for the tunnel works) and construction programme have been carefully planned and developed.  As a result, the quantity of any surplus inert C&D materials requiring off-site delivery and the impact resulting from the associated collection and transportation works will be minimised.

 

Foundation/ piling works for various tunnels, buildings, approach lights and new HKIAAA beacons as well as excavation works for the new APM depot

All the marine sediments to be generated from such works will be treated and reused on-site as backfilling materials, thus avoiding the need for disposal of the sediments.

Diversion of Submarine Aviation Fuel Pipelines

-

Using HDD method to construct the new pipeline will avoid dredging of seabed, thus removal and disposal of any dredged materials will be totally avoided.  The inert C&D materials generated during the HDD work would be of small quantity (approximately 6,000 m3), which would be fully reused in the proposed land formation.

Diversion of Submarine 11 kV Cables

-

Use of water jetting method to lay the new cable will avoid generation and disposal of any marine sediment.   Although it is required to excavate and dispose of about 10,200 m3 of marine sediment from the field joint area where the new cable will be connected to the existing cable, the alignment of the newly laid cable will be substantially shortened and will not need to extend to within the Sha Chau and Lung Kwu Chau Marine Park area.

 

 


10.4.2     Operation Phase

10.4.2.1    Wastes produced during operation phase of the project would be generated by a variety of landside and airside activities and mainly comprise general refuse, chemical waste and floating refuse that may be trapped on the artificial seawall of the expanded airport site. The management of sewage that would be generated during the operational phase of the project is assessed in Chapter 9.

General Refuse

10.4.2.2    General refuse (such as waste paper, empty containers and packaging, food scraps, redundant equipment and machinery parts, etc.) would be generated from operation of passenger concourses, aircraft cabins, terminal buildings, offices, commercial establishments (e.g., restaurants, retail outlets, etc.), as well as ground handling agents activities and various airport infrastructure facilities.  According to AAHK’s historical records of total waste arisings (before recovery of recyclable materials) per passenger from 2008 to 2012, it can be estimated that the 5-year average of waste arising is 0.366 kg/pax as detailed in Table 10.17. Based on HKIA long term traffic forecast from the International Air Transport Association (IATA), the anticipated number of passengers/ visitors in 2038 (i.e., 15 years after the planned commencement of operation of the 3RS in 2023) is about 126.2 million pax. Therefore, it is estimated that about 46,190 ton/year of general refuse will be generated in 2038. Corresponding to this waste volume and with a loading capacity of about 12 ton per refuse collection vehicle (RCV), it can be estimated that up to around 11 vehicle-trips per day would be needed for delivery of the general refuse by RCV to the designated landfill sites, which will be via North Lantau Highway.  Given this small daily number of vehicle-trips, the extra traffic loading on North Lantau Highway would be negligible.

Table 10.17: Historical Records of Waste Arising from Operation of the Existing Airport (2008 – 2012)

Item

Total Waste Generation per Passenger (kg/pax)

2008

2009

2010

2011

2012

5-Year Average

Waste arising

0.371

0.365

0.354

0.360

0.382

0.366

Source: AAHK’s waste collection records

10.4.2.3    In line with the existing airport operational policy to encourage recycling, recyclable materials, including paper, cardboard, metals, plastics, glass bottles, food waste, wooden pallets, etc., will be segregated and stored separately for delivery to outside licensed recyclers. The non-recyclable portion of the general refuse will be properly stored and collected by reputable waste collector for delivery to the landfill sites in Hong Kong by refuse collection vehicles for final disposal.  According to HKIA annual reports, the amounts of recyclable materials collected for recycling by AAHK had been increasing from 2008 to 2012 as detailed in Table 10.18.   In 2012, a total of 2,957 tons of recyclable waste materials were collected for recycling by AAHK, representing a waste recycling rate of around 18%. With continuation and strengthening of the current waste recycling initiatives in both existing and future facilities of the project, it is anticipated that waste recycling rate would be improved in future years and the amount of general refuse to be disposal will be accordingly reduced.

Table 10.18: Amount of Waste Recycled by AAHK from 2008 to 2012

 

Amount Collected for Recycling (ton)

Recyclable Materials

2008

2009

2010

2011

 2012

Cardboard

264

413

456

531

511

Paper

372

372

536

843

1,089

Metals

152

107

99

88

48

Plastics

13

16

14

57

53

Glass Bottles

16

17

3

6

9

Food Waste

19

42

37

115

1,133

Wooden Pallets, Vehicle Tyres, Lubricating Oil, Fluorescent Tubes, Toners, Batteries and Waste Cooking Oil

5

5

10

28

114

Total

840

972

1,154

1,668

2,957

Source: HKIA Annual Reports 2007/08, 2008/09, 2009/10, 2010/11 and 2011/12.

10.4.2.4    Storage of general refuse would generate odour nuisance and visual impact if they are not managed in a proper manner. Vermin and pests may also be attracted if the waste containers are not cleaned or maintained properly and frequently. Therefore, the general refuse should be temporarily stored in proper containers with covers, which should be regularly cleaned and checked, to avoid adverse impact to the surroundings. A reputable licensed waste collector should be employed to collect the general refuse daily for disposal at designated landfill sites. With proper implementation of waste management practices, the environmental impact from handling and disposal of general refuse would not be anticipated.

Chemical Waste

10.4.2.5    According to AAHK’s historical records of chemical waste arisings during the period from 2011 to 2013, it can be estimated that the average chemical waste arising was roughly 15 ton per month, and the major types of chemical wastes generated included lubricating oil, spent fuel, non-halogenated solvent, waste batteries, etc. It is anticipated that similar types of chemical waste will be generated from maintenance, servicing and repairing of various electrical & mechanical (E&M) equipment during operation phase of the project. However, it is difficult to quantify the additional amount of chemical waste that will arise during the operation phase since it will be dependent on the maintenance and servicing requirements of various new E&M equipment and the amount of such equipment. All chemical wastes generated will require special handling and storage arrangements before removal for appropriate treatment at the Chemical Waste Treatment Centre or other licensed facility.  The chemical wastes will be delivered to the off-site licensed facilities by trucks through North Lantau Highway and Tsing Sha Highway. As it is anticipated that the additional amount of chemical wastes to be generated by project would not be substantial, the extra traffic loading on North Lantau Highway/ Tsing Sha Highway would not be significant.

10.4.2.6    Chemical wastes arising during the operation phase may pose environmental, health and safety hazards if not stored and disposed of in an appropriate manner as stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. The potential hazards include:

¡  Toxic effects to workers;

¡  Adverse impact on water quality and wildlife from spills; and

¡  Fire hazards.

10.4.2.7    Materials classified as chemical wastes will require special handling and storage arrangements before off-site disposal at licensed chemical waste treatment facilities. Wherever possible opportunities should be taken to reuse and recycle materials. Mitigation and control requirements for chemical wastes are detailed in Section 10.5.2. Provided that the handling, storage and disposal of chemical wastes are in accordance with these requirements, adverse environmental impact would not be expected.

Floating Refuse

10.4.2.8    Floating refuse may wash up onto the project site through the effect of currents and wind, with waste then trapped and accumulated on the artificial seawall of the existing airport island or the expanded airport island.  According to the historical records provided by Marine Department (MD), the amounts of floating refuse collected by MD’s contractor within the project area from 2010 to 2012 are as shown in Table 10.19. It is noted that the quantity of floating refuse collected was higher in the summer months, which may be attributed to heavy rains and/or typhoons bringing more refuse into the harbour.

Table 10.19: Summary of Floating Refuse Collected in Chek Lap Kok Watercourse

 

Monthly Quantity of Floating Refuse Collected (ton)

Year

Jan

Feb

Mar

Apr

May

Jun

Jul

Aug

Sep

Oct

Nov

Dec

2010

1.4

0.3

1.5

2.3

1.7

1.5

1.4

1.5

1.9

1.6

1.3

1.1

2011

1.4

1.7

2.6

1.7

1.4

1.6

4.6

1.6

1.5

1.5

1.4

1.5

2012

1.6

1.8

1.6

1.4

2.2

1.9

4.1

3.1

1.7

2.7

1.1

1.1

Source:   Marine Department

10.4.2.9    Current practice is that regular cleaning of floating refuse trapped or accumulated on the existing seawall along the North Perimeter Road is carried out once per year whereas regular cleaning for other existing seawalls is performed twice a year subject to cleaning conditions.  According to the cleaning contractor, roughly 13 m3 of refuse and 70 pieces of bamboos/ wood were collected from the seawall along the North Perimeter Road in early 2013 while roughly 26 m3 of refuse and 50 pieces of bamboos/ wood were collected from the other seawalls in early 2012.  Since the extent and design of the newly constructed seawall is similar to the existing seawall, it is anticipated that the amount of floating refuse trapped or accumulated during operation phase will be similar to the historical records. Therefore, it can be estimated that roughly 65 m3 (13 m3 + 26 m3 x 2) of floating refuse would be collected from the new artificial seawall of the proposed Airport expansion area every year.  Floating refuse will be collected together with general refuse by a reputable licensed waste collector for disposal at designated landfill sites by RCV through North Lantau Highway.  Given the small estimated quantity of floating refuse requiring delivery every year, the additional traffic loading on North Lantau Highway would be negligible. 

10.4.2.10 Entrapment or accumulation of floating refuse on the artificial seawall of the expanded airport island, if not properly controlled, may cause aesthetic and/or hygiene issues. Therefore, the artificial seawall has been properly designed to achieve a shoreline that does not have any sharp turns or abrupt indentation in order to avoid or minimise any trapped or accumulated refuse.  With the proper seawall design and implementation of management control practices as detailed in Section 10.5.2, no adverse environmental impact associated with such refuse are anticipated.

Sludge from Proposed Greywater Treatment Plant

10.4.2.11 It is proposed to install a greywater treatment plant to treat a portion of greywater from the project and reuse the treated greywater for irrigation and general cleaning activities. The design capacity of the proposed treatment plant is 700 m3/day, the details of which are described in Section 8.7.2. 

10.4.2.12 Sludge generated from the proposed greywater treatment plant will be mechanically dewatered, which will then be delivered by trucks via the North Lantau Highway to the designated landfill sites for final disposal.  Based on the operation records of the existing greywater treatment facility, it can be estimated that the quantity of dewatered sludge from the proposed greywater treatment plant would be approximately 0.23 ton/day.  To avoid odour emission during the transportation, the dewatered sludge should be stored in tight containers or skips for delivery to the designated landfill sites by a reputable licensed waste collector. Given the small daily quantity of sludge, the extra traffic loading on North Lantau Highway would be negligible. The sludge generated needs to be carefully handled and properly managed to minimise the adverse impact of odour and potential health risks to the operators by attracting pests and other disease vectors. 

10.5       Mitigation of Adverse Environmental Impact

10.5.1     Construction Phase

Opportunities for Reducing Waste Generation and Maximising Reuse / Recycling

10.5.1.1    Opportunities to minimise waste generation and maximise the reuse of waste materials generated by the project have been incorporated where possible into the planning, design and construction stages, and the following measures have been recommended:

¡  The relevant construction methods (particularly for the tunnel works) and construction programme have been carefully planned and developed to minimise the extent of excavation and to maximise the on-site reuse of inert C&D materials generated by the project as far as practicable.  Temporary stockpiling areas will also be provided to facilitate on-site reuse of inert C&D materials.  Considering all these initiatives, the quantity of any surplus inert C&D materials requiring off-site delivery will be minimised as far as practicable. According to the project design information, initial estimates show that about 38% (or 3,639,230 m3) of the inert C&D materials generated by the project would be reused on-site as fill materials for the proposed land formation whereas the remaining 62% (or 5,904,270 m3) would be delivered to any identified projects that would need fill materials and/or to the Government’s PFRF for beneficial reuse by other projects in Hong Kong.

¡  Priority will be given to collect and reuse suitable inert C&D materials generated from other concurrent projects and the Government’s PFRF as fill materials for the proposed land formation works. Based on the project design information, it is estimated that about 10,911,770 m3 of public fill materials would be collected from any available concurrent projects and/or from the Government’s PFRF, and reused in this project for the proposed land formation.

¡  Only non-dredged ground improvement methods (see Section 4.2.2 for details) will be adopted in order to completely avoid the need for dredging and disposal of marine sediment for the proposed land formation work.

¡  Excavation work for constructing the APM tunnels, BHS tunnels and airside tunnels will not be down to the CMPs beneath the fill materials in order to avoid excavating any sediments.

¡  For marine sediments expected to be excavated from the piling works of TRC, APM & BHS tunnels, airside tunnels and other facilities on the proposed land formation area, piling work of marine sections of the approach lights and HKIAAA beacons, basement works for some of T2 expansion area and excavation works for the proposed APM depot (a total quantity of about 767,660 m3) will be treated and reused on-site as backfilling materials, although required treatment level / detail and the specific re-use mode are under development. 

Good Site Practices

10.5.1.2    Adverse impact related to waste management such as dust, odour and noise are not expected to arise, provided that good site practices are strictly followed. Recommendations for good site practices during the construction activities include:

¡  Nomination of an approved person, such as a site manager, to be responsible for good site practices, arrangements for collection and effective disposal to an appropriate facility, of all wastes generated at the site.

¡  Training of site personnel in proper waste management and chemical waste handling procedures.

¡  Provision of sufficient waste disposal points and regular collection for disposal.

¡  Appropriate measures to minimise windblown litter and dust during transportation of waste by either covering trucks by tarpaulin/ similar material or by transporting wastes in enclosed containers. The cover should be extended over the edges of the sides and tailboards.

¡  Stockpiles of C&D materials should be kept covered by impervious sheets to avoid wind-blown dust.

¡  All dusty materials including C&D materials should be sprayed with water immediately prior to any loading transfer operation so as to keep the dusty material wet during material handling at the barging points/ stockpile areas.

¡  C&D materials to be delivered to and from the project site by barges or by trucks should be kept wet or covered to avoid wind-blown dust.

¡  The speed of the trucks including dump trucks carrying C&D or waste materials within the site should be controlled to about 10 km/hour in order to reduce adverse dust impact and secure the safe movement around the site.

¡  To avoid or minimize dust emission during transport of C&D or waste materials within the site, each and every main temporary access should be paved with concrete, bituminous hardcore materials or metal plates and kept clear of dusty materials.  Unpaved parts of the road should be sprayed with water or a dust suppression chemical so as to keep the entire road surface wet.

Waste Reduction Measures

10.5.1.3    Good management and control can prevent the generation of a significant amount of waste. Waste reduction is best achieved at the planning and design stage, as well as by ensuring the implementation of good site practices. Recommendations to achieve waste reduction include:

¡  Use of steel or aluminium formworks and falseworks for temporary works as far as practicable.

¡  Adoption of repetitive design to allow reuse of formworks as far as practicable.

¡  Segregation and storage of different types of waste in different containers, skips or stockpiles to enhance reuse or recycling of materials and their proper disposal.

¡  Encourage collection of aluminium cans, PET bottles and paper by providing separate labelled bins to enable these wastes to be segregated from other general refuse generated by the work force.

¡  Any unused chemicals or those with remaining functional capacity should be collected for reused as far as practicable.

¡  Proper storage and site practices to minimise the potential for damage or contamination of construction materials.

¡  Plan and stock construction materials carefully to minimise amount of waste generated and avoid unnecessary generation of waste.

10.5.1.4    In addition to the above measures, specific mitigation measures are recommended below for the identified waste arisings to minimise environmental impact during handling, transportation and disposal of these wastes.

Inert and Non-inert C&D Materials

10.5.1.5    Inert and non-inert C&D materials should be handled and stored separately to avoid mixing the two types of materials.  Any recyclable materials (e.g., metals) should be segregated from the non-inert C&D materials for collection by reputable licensed recyclers whereas the non-recyclable waste materials should be disposed of at the designated landfill site by a reputable licensed waste collector.

10.5.1.6    In order to monitor the off-site delivery of surplus inert C&D materials (about 5,904,270 m3 in total) that could not be reused on-site for the proposed land formation work at the PFRF and to control fly tipping, a trip-ticket system promulgated under DEVB TC(W) No. 6/2010 shall be included as one of the contractual requirements for implementation by the contractor.  In addition, it is also recommended that the contractor should be required to prepare and implement a Waste Management Plan detailing various waste arising and waste management practices in accordance with the relevant requirements of the Technical Circular (Works) No. 19/2005 Environmental Management on Construction Site.

Marine Sediments

Marine Sediments from Foundation Piling Works for the TRC, Approach Lights, New HKIAAA Beacons, Basement Works for T2 Expansion and Excavation for APM Depot

10.5.1.7    At this stage of project development, it is proposed that all CMP and marine sediments that are excavated through the piling works required for the TRC, APM & BHS tunnels, airside tunnels and other facilities on the proposed land formation area, the piling works for marine sections of the approach lights and new HKIAAA beacons, basement works for some of T2 expansion area and excavation works for proposed APM depot (with a total quantity of about 767,660 m3) are treated on-site using cement mixing and stabilisation / solidification method. Currently, a minimum cement content of 5% weight per weight (w/w) is proposed for treating the CMP and marine sediments. The treated sediments will then be tested against the TCLP and UCS before reuse. Subject to the TCLP and UCS test results, the cement content may need to be increased.  If the treated sediments do not comply with UTS or UCS, re-stabilization has to be undertaken to meet compliance of UTS and UCS before reusing the treated sediment as backfilling material. As described in the following paragraphs, the proposed approach for management of the treated sediment is that it will be reused on-site as backfilling materials within the project area.  A pilot trial will be conducted for the concerned sediments (in particular the contaminated sediment excavated from within the CMP area) in order to identify / confirm the appropriate treatment conditions for the stabilisation / solidification methods. However, it should be noted that the treatment level / details and the reuse mode are subject to further development during the detailed design stage. 

10.5.1.8    On-site reuse of treated sediment has been proposed for other projects in Hong Kong including Tseung Kwan O – Lam Tin Tunnel and Associated Works (EIA Register No. AEIAR-173/2013) and Public Housing Development at Kai Tak Site 1A of Housing Department1. These reports have been reviewed for reference.

1 Hong Kong Institution of Engineers Environmental Division, Hong Kong, Green Treatment of Marine Mud for Insitu Backfilling, 2010.

10.5.1.9    EPD has expressed support to the beneficial reuse of treated sediment as fill materials for in-situ backfilling and has no objection to the proposed sediment treatment method.

10.5.1.10 Possible re-use locations for the treated sediments include the non-critical areas (e.g. landscape areas) within the land formation area. As the project is still under detailed design, the locations for re-use of the treated sediment will be subject to further development during detailed design stage of the project.

10.5.1.11 The criteria for reuse of treated sediments are proposed with reference to the Universal Treatment Standards (UTS), which specify the TCLP test limits as given in Table 4.6 of the Practice Guide for Investigation and Remediation of Contaminated Land, as shown in below table.


Table 10.20: Universal Treatment Standards for On-site Reuse of Sediments Treated by Cement Mixing and Stabilisation

Parameters(1),(2)

TCLP Limit (mg/L)

Arsenic

5

Cadmium

0.11

Chromium

0.6

Lead

0.75

Mercury

0.025

Nickel

11

Zinc

4.3

Notes:

(1)         Universal Treatment Standard – US 40 CFR 268.48

(2)         For other metal contaminants under RBRGs, e.g., copper, silver, they must be reduced by at least 90% in mobility for respective metals through cement stabilization/solidification remedial treatment.  The reduction of mobility of metal contaminants (leachable metals contaminants) should be confirmed through TCLP tests (i.e. to carry out TCLP test for the untreated sediment and for the sediment after treatment and to compare the concentrations of the metals in the leachates).

10.5.1.12 According to the result of sediment sampling and testing (see Table 10.9 and Table 10.11), some of the sediments would be classified as Category M or Category H primarily due to high natural background levels of arsenic and/or elevated levels of lead, zinc, copper, chromium, nickel, sliver and mercury.

10.5.1.13 After exploring different possibilities of carrying out on-site remediation and reuse of treated sediment, the current preliminary proposal is to mix sand/ soil and cement with the sediments to stabilise any contaminants so that the treated sediments can be used as backfilling within the project site. A minimum cement content of 5% is proposed for treating the sediments subject to the corresponding test results.  The on-site sediment treatment is expected to be carried out in an enclosed/ covered area provided with proper site drainage, and therefore significant odour emissions and/or uncontrolled release of contaminated runoff would not be anticipated during the on-site treatment works.  

10.5.1.14 The sediment treatment facility is expected to be located within the project site depending on the construction phasing.  The initially proposed treatment process is expected to begin with initial mixing of the sediments with inert C&D materials/ soil in batches using an excavator and/or backhoe. Cement slurry will then be added to the initially mixed sediment for the stabilisation/ solidification process. The treated sediments will be placed at a temporary storage area covered by tarpaulin sheets, while samples are taken for laboratory testing. The testing frequency will be one sample per 50 m3 for the first 1,000 m3 of treated sediment (two further samples should be collected at the same time and kept for contingency in case of damage to the sample being tested). Provided that the samples meet the UTS for the tested parameters shown in
Table 10.20
and the UCS test, the subsequent testing frequency will be reduced to be at least two samples per 10,000 m3. In the event that required levels are not achieved, the sample should be crushed and the sediment should be treated with a higher cement content (e.g. 10%, 20% or 30%). The testing frequency should be revised to one sample per 50 m3 (with two further samples kept for contingency) and treated samples should be taken for laboratory testing. Once the UTS and UCS for the relevant tested parameters is attained, the previous sampling frequency should be resumed but the revised cement content should be maintained for treatment.  

10.5.1.15 From Table 10.9, only one sub-sample (at a depth of 2.90 - 3.90 m from TC9A) was found to have high molecular weight PAH exceeding the LCEL. Therefore, it is suggested to collect samples of the sediments that are excavated from the vicinity of TC9A for testing of semi-volatile organic compound (sVOC) against the relevant RBRGs. Should there be any exceedance of the RBRGs, those sediments will require extra treatment such as air purging or bio-pile (in addition to mixing with sand / soil and cement) to achieve compliance with the RBRGs prior to on-site reuse.  After formation of the bio-pile, soil samples should be taken monthly at one sample per 20m3 for the analysis of pH, moisture content and sVOCs. Soil sampling from bio-pile will be accomplished using the hand-driven sampler.

10.5.1.16 As the proposal is to treat all excavated sediments from the foundation/ piling/ excavation works for on-site reuse, off-site disposal of such sediments via marine dumping is not expected to be required although this aspect will be subject to further consideration and development at the scheme design / detailed design stage Subject to confirmation of the proposed treatment method, significant adverse impact from such excavated sediment is not anticipated.

10.5.1.17 The following mitigation measures are recommended during excavation and treatment of the sediments:

¡ On-site remediation should be carried out in an enclosed area in order to minimise odour/ dust emissions;

¡ The loading, unloading, handling, transfer or storage of treated and untreated sediment should be carried out in such a manner to prevent or minimise dust emissions;

¡ All practical measures, including but not limited to speed control for vehicles, should be taken to minimise dust emission;

¡ Good housekeeping should be maintained at all times at the sediment treatment facility and storage area;

¡ Treated and untreated sediment should be clearly separated and stored separately; and

¡ Surface runoff from the enclosed area should be properly collected and stored separately, and then properly treated to levels in compliance with the relevant effluent standards as required by the Water Pollution Control Ordinance before final discharge.

Marine Sediments from the Cable Field Joint

10.5.1.18 The marine sediments to be dredged from the cable field joint area (with a quantity of about 10,200 m3) would, however, need to be disposed off-site due to non-alignment with the overall construction programme. The basic requirements and procedures for marine sediment disposal are specified under the PNAP ADV-21. The Marine Fill Committee (MFC) of CEDD is responsible for the provision and management of disposal capacity for dredged/ excavated sediment. At least three months prior to commencement of the dredging work, the contractor will have to submit a Sediment Quality Report (SQR) in accordance with PNAP ADV-21 in order to apply for a dumping permit from EPD for marine disposal of the sediments under the provisions of DASO.  No dredging work is allowed to proceed until all matters on management of dredged sediments have been resolved and all relevant arrangements have been endorsed by the relevant authorities including MFC and EPD.

10.5.1.19 The dredged marine sediments would be loaded onto barges, transported to and disposed of at the designated disposal sites to be allocated by the MFC depending on their level of contamination or at other disposal sites after consultation with the MFC and EPD. Based on the relevant chemical and biological testing results of the sediment samples, the marine sediment to be dredged from the field joint area is classified as Category L or Category Mp and would be disposed by Type 1 open sea disposal (for Category L sediment) or Type 1 open sea disposal at dedicated sites (for Category Mp sediment) respectively, according to PNAP ADV-21. The contaminated sediments should be dredged and transported with great care, and the following mitigation measures should be strictly followed to minimise potential impact on water quality during transportation of the sediments requiring Type 1 disposal:

¡  Bottom opening of barges shall be fitted with tight fitting seals to prevent leakage of material;

¡  Monitoring of the barge loading shall be conducted to ensure that loss of material does not take place during transportation. Transport barges or vessels shall be equipped with automatic self-monitoring devices as specified by EPD; and

¡  Barges or hopper barges shall not be filled to a level that would cause the overflow of materials or sediment laden water during loading or transportation.

Chemical Waste

10.5.1.20 As it is anticipated that chemical wastes will be produced during construction, all construction contractors will be required to register with the EPD as a chemical waste producers and to follow the guidelines stated in the “Code of Practice on the Packaging Labelling and Storage of Chemical Wastes”. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately. Appropriate labels must be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. The contractor will use a licensed collector to transport and dispose of the chemical wastes at the approved Chemical Waste Treatment Centre or other licensed recycling facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

General Refuse

10.5.1.21 Release of any general refuse into marine waters should be strictly prohibited. General refuse should be stored in enclosed bins or compaction units separated from inert C&D material. A reputable waste collector should be employed by the contractor to remove general refuse from the site for disposal at designated landfill sites. Preferably an enclosed and covered area should be provided to reduce the occurrence of 'wind blown' light material. 

Floating Refuse

10.5.1.22 The future artificial seawall of the proposed airport expansion area has been properly designed to achieve a shoreline that does not have any sharp turns or abrupt indentation in order to avoid or minimise any trapped or accumulated refuse.  The construction contractors will be required to regularly check and clean any refuse trapped or accumulated along the newly constructed seawall.  Such refuse will then be stored and disposed of together with the general refuse.

10.5.2     Operation Phase

General Refuse

10.5.2.1    General refuse should be temporarily stored in proper containers with covers, which should be regularly cleaned and checked for maintenance. General refuse should be collected on daily basis and delivered to the refuse collection point accordingly. A reputable waste collector should be employed to remove the general refuse regularly for off-site disposal at designated landfill sites in order to avoid odour nuisance or pest/ vermin problem.  AAHK’s current initiatives in segregating recyclable materials (such as cardboard, paper, metals, plastics, glass bottles, food waste, etc.) from general refuse for recycling should be extended to cover the expanded airport.  Such waste recycling initiatives include:

¡  Recycling facilities are provided in prominent areas in passenger terminal buildings to facilitate separation of recyclable waste by passengers;

¡  Recycling facilities are also provided in refuse rooms of the passenger terminal buildings to facilitate separation of recyclable waste by tenants;

¡  Food waste recycling programme has been implemented at the airport to collect and recycle food waste;

¡  Food waste can be delivered to EPD’s Organic Waste Treatment Facilities for recycling as compost;

¡  Food & beverage tenants are encouraged to recycle waste cooking oil (e.g., recycling of waste cooking oil to biodiesel); and

¡  AAHK has stepped up on-site waste separation and recycling at the Airside Waste Station to raise the amount of recyclable materials recovered from aircraft cabin waste.

Chemical Waste 

10.5.2.2    Where chemical wastes are expected to be produced during the operation phase, AAHK and/or owners/ operators of the relevant facilities should register with the EPD as a chemical waste producer and follow the guidelines stated in the Code of Practice on the Packaging, Labelling and Storage of Chemical Wastes. Good quality containers compatible with the chemical wastes should be used, and incompatible chemicals should be stored separately.  Appropriate labels should be securely attached on each chemical waste container indicating the corresponding chemical characteristics of the chemical waste, such as explosive, flammable, oxidizing, irritant, toxic, harmful, corrosive, etc. Licensed collector should be deployed to transport and dispose of the chemical wastes at the approved Chemical Waste Treatment Centre or other licensed recycling facilities, in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

Floating Refuse

10.5.2.3    The artificial seawall of the expanded airport island has been properly designed to achieve a shoreline without any sharp turns or abrupt indentation where floating refuse would easily be trapped or accumulated. 

10.5.2.4    As the current practices, regular cleaning of floating refuse trapped or accumulated on the existing seawall along the North Perimeter Road is carried out once per year.  For other existing seawalls, the regular cleaning is performed twice a year subject to cleaning conditions, which has been handed over to the contractor of the Hong Kong - Zhuhai - Macao Bridge (HZMB) project since May 2012.  It is anticipated that similar regular cleaning of floating refuse from the seawalls of the expanded airport island will continue to be implemented.  In addition to regular cleaning, it is also recommended to implement the following management control measures.

10.5.2.5     Weekly inspection will be carried out along the artificial seawall of the expanded airport island to check for any entrapment or accumulation of floating refuse. Where an appreciable amount of floating refuse is found on the artificial seawall during the weekly inspection, the locations of such refuse will be recorded and arrangements with the contractor will immediately be made to collect and clear the refuse from the seawall.

Sludge from Proposed Greywater Treatment Plant

10.5.2.6    Sludge generated from the proposed greywater treatment plant will be mechanically dewatered, which will then be delivered to the designated landfill sites for final disposal.  To avoid odour emission during the transportation, the dewatered sludge should be stored in tight containers or skips for delivery to the designated landfill sites by a reputable licensed waste collector. The sludge generated should be carefully handled and properly managed to minimise the adverse impact of odour and potential health risks to the operators by attracting pests and other disease vectors.

10.6       Evaluation of Residual Impact

10.6.1.1    With the implementation of the recommended mitigation measures for the handling, transportation and disposal of the identified waste arisings, no adverse residual impact are anticipated during both construction and operation phases of the project.

10.7       Environmental Monitoring and Audit

10.7.1     Construction Phase

10.7.1.1    It will be the contractor’s responsibilities to ensure that all wastes produced during the construction phase of the project are handled, stored and disposed of in accordance with good waste management practices and the relevant regulations and requirements.  The recommended mitigation measures shall form the basis of the Waste Management Plan to be developed by the contractor in the construction phase.

10.7.1.2    During construction phase, regular site inspection as part of the EM&A procedures should be carried out to check if various types of waste are being managed in accordance with approved procedures and the Waste Management Plan. It should cover different aspects of waste management including waste generation, storage, recycling, treatment, transport and disposal.

10.7.2     Operation Phase

10.7.2.1    During operation phase, weekly inspection should be carried out along the artificial seawall of the expanded airport island to check for any entrapment or accumulation of floating refuse. Where an appreciable amount of floating refuse is found on the artificial seawall during the weekly inspection, the locations of such refuse will be recorded and arrangements with the contractor will immediately be made to collect and clear the refuse from the seawall.

10.8       Conclusion

10.8.1     Construction Phase

10.8.1.1    The major waste types generated by the construction activities will include:

¡   Inert C&D materials from excavation works, demolition works, seawall modification, piling works and superstructure construction works on the existing airport island/ proposed land formation area as well as from HDD during diversion of the existing submarine pipelines;

¡   Non-inert C&D materials from site clearance at the golf course area, demolition works for the T2 expansion and various superstructure construction works;

¡   Marine sediments dredged from the cable field joint area;

¡   CMP and marine sediments excavated from the foundation / piling / basement / excavation works for constructing the various tunnels, facilities and buildings;

¡   Chemical waste from maintenance and servicing of construction plant and equipment;

¡   General refuse from the workforce; and

¡   Floating refuse trapped/ accumulated on the newly constructed seawall.

10.8.1.2    Every effort would be made to minimise the extent of excavation and to ensure that as much of the inert C&D materials generated by the project will be reused on-site as practicable. Based on the initial scheme design estimates, it is anticipated that a total of approximately 9,543,500 m3 of inert C&D materials will be generated from 2015 to 2022, the majority of which would be from excavation works for APM and BHS tunnels, new APM depot and airside tunnels, and piling works for TRC and other facilities. Of this total amount of inert C&D materials, it is estimated that approximately 3,639,230 m3 (or about 38%) could be reused on-site as fill materials for the proposed land formation works. The remaining 5,904,270 m3 (or about 62%) would be transferred off-site to any identified projects that would require fill materials and/ or the PFRF for beneficial use by any other projects in Hong Kong.  Despite maximising the on-site reuse of inert C&D materials, it is estimated that the project would require importing approximately 10,911,770 m3 of public fill materials for land formation during the period from 2016 to 2018.

10.8.1.3    Based on initial scheme design information, it is estimated that approximately 96,200 m3 of non-inert C&D materials would be generated during the period from 2016 to 2021. The contractor should separate the non-inert C&D materials from the inert C&D materials on site.  Any recyclable materials (e.g., metal) will be segregated from the non-inert C&D materials for collection by reputable licensed recyclers.  The remaining non-recyclable waste materials would be disposed of at designated landfill sites by a reputable licensed waste collector.

10.8.1.4    It is estimated that in total approximately 777,860 m3 of marine sediments will be generated by the various construction activities from 2015 to 2022. Majority of this total amount of marine sediments, i.e., about 767,660 m3 (or about 98.7%), would be generated from the foundation / piling works for the tunnels, buildings, approach lights and new HKIAAA beacons as well as excavation works for the new APM depot. These marine sediments will be treated and reused on-site as backfilling materials, thus avoiding the need for disposal of the sediments off-site. The remaining minority, i.e., about 10,200 m3 (or about 1.3%), it is estimated to be generated from excavation of the cable field joint area during the advance works in 2015/16. This material would require open sea disposal (for Category L sediments) or open sea disposal at dedicated sites (for Category Mp sediments) as such sediments cannot be treated and reused as backfilling materials on-site due to mis-match with the overall construction programme (i.e., the estimated time of generation of such sediments would be over one year before majority of the filling works for the proposed land formation work is scheduled to begin).

10.8.1.5    At this stage, the daily general refuse arising from the construction workforce is estimated to be approximately 9,100 kg. A Construction Waste Management Plan will be prepared, which will prioritise the provision and arrangement of recycling facilities to maximise the diversion of construction waste from being sent to landfill. Non-recycling waste will be disposed of at designated landfill sites. With the appropriate design of the artificial seawall to avoid or minimise any trapped or accumulated refuse, it is estimated that roughly 65 m3 of floating refuse will be collected during each year of construction from the newly constructed seawall. The floating refuse will be sorted and recycled or disposed of at designated landfill sites, as appropriate. It is expected that minor volumes of chemical waste would be generated during construction, which would be properly handled, stored, labelled and disposed of in accordance with the Waste Disposal (Chemical Waste) (General) Regulation. 

10.8.1.6    Provided that all the identified wastes are handled, transported and reused/ disposed of in strict accordance with the relevant legislative and recommended requirements and that the recommended good site practices and mitigation measures are properly implemented, no adverse environmental impact is expected during the construction phase.

10.8.2     Operation Phase

10.8.2.1    During the operation phase, the key waste types generated will include general refuse from operation of passenger concourses, aircraft cabins, terminal buildings, offices, commercial establishments (e.g., restaurants from various restaurants, retail outlets, etc.) and various airport infrastructure facilities as well as chemical waste from maintenance, servicing and repairing of various E&M equipment.  There would also be entrapment or accumulation of floating refuse on the artificial seawall of the expanded airport island. With the proposed installation of a new greywater treatment plant, sludge from the proposed treatment plant would also be generated and disposed of in accordance with the relevant guidance and regulations.

10.8.2.2    It is estimated that approximately 46,190 tons of general refuse would be generated by the project in 2038 (i.e., 15 years after the planned commencement of operation of the 3RS in 2023). The initiatives currently implemented at HKIA in segregating recyclable waste materials (such as cardboard, paper, metals, plastics, glass bottles, food waste, etc.) from general refuse for recycling should be extended to cover the expanded airport.  The non-recyclable waste will be disposed of at designated landfill sites. 

10.8.2.3    The new artificial seawall has been properly designed to achieve a shoreline that does not have any sharp turns or abrupt indentation in order to avoid or minimise any trapped or accumulated refuse. With the proper seawall design, it is estimated that roughly 65 m3 of floating refuse will be collected from the new artificial seawall of the proposed airport expansion area every year.  The floating refuse will be disposed of at designated landfill sites, as appropriate.

10.8.2.4    It is difficult to quantify the amount of chemical waste that would arise during operation phase of the project at this stage since it would be dependent on the equipment maintenance requirements and the amount of equipment utilised. As per current requirements at the airport, all chemical waste would be properly handled, stored, labelled and disposed of in accordance with the Waste Disposal (Chemical Waste) (General) Regulation.

10.8.2.5    Based on the operation records of the existing greywater treatment facility, it is estimated that the quantity of dewatered sludge from the proposed new greywater treatment plant would be approximately 0.23 ton/day.  The dewatered sludge will be stored in tight containers or skips and delivered to the designated landfill sites for final disposal by a reputable licensed waste collector.  The sludge generated would be handled and managed to minimise the adverse impact of odour and potential health risks to the operators by attracting pests and other disease vectors.

10.8.2.6    Provided that all the identified wastes are handled, transported and disposed of in strict accordance with the relevant legislative requirements and the recommended mitigation measures are properly implemented, no adverse environmental impact is expected during the operation phase.