TABLE OF CONTENTS

Page

10........ Landscape and Visual Impact. 10-2

10.1        Introduction. 10-2

10.2        Environmental Legislation, Standards and Criteria. 10-2

10.3        Assessment Methodology. 10-3

10.4        Review of Planning and Development Control Framework. 10-7

10.5        Baseline Study. 10-8

10.6        Landscape Impact Assessment 10-19

10.7        Visual Impact Assessment 10-24

10.8        Landscape and Visual Mitigation Measures. 10-29

10.9        Residual Impact 10-32

10.10     Environmental Monitoring and Audit 10-47

10.11     Conclusion. 10-47

 

LIST OF TABLES

Table 10.1       Relationship between Landscape Sensitivity and Magnitude of Change in Defining Impact Significance  10-5

Table 10.2       Relationship between VSRs Sensitivity and Magnitude of Change in Defining Impact Significance  10-8

Table 10.3       Summary of the Review of Planning and Development Control Framework. 10-9

Table 10.4       Baseline LRs and their Sensitivity. 10-10

Table 10.5       Baseline LCAs and their Sensitivity. 10-13

Table 10.6       Baseline VSRs and their Sensitivity. 10-17

Table 10.7       Magnitude of Landscape Impacts during Construction and Operation. 10-21

Table 10.8       Locations and Development Details of Permanent Aboveground Structures. 10-26

Table 10.9       Magnitude of Visual Impacts during Construction and Operation. 10-27

Table 10.10     Landscape and Visual Mitigation Measures for Construction Phase. 10-31

Table 10.11     Landscape and Visual Mitigation Measures for Operation Phase. 10-32

Table 10.12     Significance of Landscape Impacts during Construction and Operation Phases. 10-37

Table 10.13     Significance of Visual Impacts during Construction and Operation Phases. 10-42

 

LIST OF FIGURES

60334056/EIA/10.01       Review of Planning Control Framework
60334056/EIA/10.11       Landscape Resources
60334056/EIA/10.12       Landscape Resources Photos (Sheet 1 of 3)

60334056/EIA/10.13       Landscape Resources Photos (Sheet 2 of 3)

60334056/EIA/10.14       Landscape Resources Photos (Sheet 3 of 3)

60334056/EIA/10.21       Landscape Character Areas

60334056/EIA/10.22       Landscape Character Areas Photos (Sheet 1 of 3)  

60334056/EIA/10.23       Landscape Character Areas Photos (Sheet 2 of 3)  

60334056/EIA/10.24       Landscape Character Areas Photos (Sheet 3 of 3)  

60334056/EIA/10.31       Visual Envelope and Visually Sensitive Receivers

60334056/EIA/10.41       Landscape and Visual Mitigation Measures Plan (Sheet 1 of 4)

60334056/EIA/10.42       Landscape and Visual Mitigation Measures Plan (Sheet 2 of 4)

60334056/EIA/10.43       Landscape and Visual Mitigation Measures Plan (Sheet 3 of 4)

60334056/EIA/10.44       Landscape and Visual Mitigation Measures Plan (Sheet 4 of 4)

60334056/EIA/10.45       Landscape and Visual Mitigation Measures Sections

60334056/EIA/10.46       Landscape and Visual Mitigation Measures Elevations

60334056/EIA/10.51       Photomontage P1

60334056/EIA/10.52       Photomontage P2

60334056/EIA/10.53       Photomontage P3

60334056/EIA/10.54       Photomontage P4

60334056/EIA/10.55       Photomontage P5

60334056/EIA/10.56       Photomontage P6

 

LIST OF APPENDICES

Appendix 10.01             Broad Brush Tree Survey

Appendix 10.02             Overlay of Landscape and Visual Mitigation Measures, Landscape Resources and Landscape Character Areas


 

10                   Landscape and Visual Impact

10.1                Introduction

10.1.1.1         This section presents the findings of the assessment of potential landscape and visual impacts associated with the Project.

10.1.1.2         Landscape and visual impacts assessment are assessed in accordance with the criteria and guidelines as stated in Annexes 10 and 18 of the TM and EIAO Guidance Note No. 8/2010 on ¡§Preparation of Landscape and Visual Impact Assessment under the Environmental Impact Assessment Ordinance¡¨.

10.1.1.3         The assessment area for landscape impact assessment shall include areas within a 500m distance from the site boundary of the Project and any other areas likely to be impacted by the Project.  The assessment area for the visual impact assessment shall be defined by the visual envelope of the Project. 

10.1.1.4         The list of all DPs under Schedule 2 within the assessment area is listed in Section 1.2 of this Report.  The alternative options/alignments/designs for the Project considered are discussed in Section 2 of this Report. 

 

10.2                Environmental Legislation, Standards and Criteria

10.2.1.1         The following legislation, standards and guidelines are applicable to landscape and visual impact assessment associated with the construction and operation of the Project:

¡P         EIAO (Cap.499 S.16) and the EIAO-TM, particularly Annexes 10 and 18; 

¡P         EIAO Guidance Note No. 8/2010; 

¡P         Town Planning Ordinance (Cap. 131); 

¡P         Protection of Endangered Species of Animals and Plants Ordinance (Cap. 586); 

¡P         HKSPG Chapters 4, 10 and 11; 

¡P         AFCD Nature Conservation Practice Note No. 2 - Measurement of Diameter at Breast Height (DBH); 

¡P         AFCD Nature Conservation Practice Note No. 3 ¡V The Use of Plant Names; 

¡P         ETWB TCW No. 29/2004 - Registration of Old and Valuable Trees (OVT), and Guidelines for their Preservation; 

¡P         ETWB TCW No. 8/2005 - Aesthetic Design of Ancillary Buildings in Engineering Projects; 

¡P         DEVB TCW No. 2/2012 - Allocation of Space for Quality Greening on Roads; 

¡P         DEVB TCW No. 3/2012 - Site Coverage of Greenery for Government Building Projects; 

¡P         DEVB TCW No. 6/2015 - Maintenance of Vegetation and Hard Landscape Features; 

¡P         DEVB TCW No. 7/2015 - Tree Preservation; 

¡P         Geotechnical Engineering Office (GEO) Publication No. 1/2011 ¡V Technical Guidelines on Landscape Treatment and Bio-Engineering for Man-Made Slopes and Retaining Walls;

¡P         Guidelines on Tree Transplanting (September 2014) issued by Greening, Landscape and Tree Management (GLTM) Section of DEVB;

¡P         Guidelines on Tree Preservation during Development (April 2015) issued by GLTM Section of DevB; and

¡P         Study on Landscape Value Mapping of Hong Kong. 

10.2.1.2         The OZP gazetted under the Town Planning Ordinance provides the statutory framework for land use development.  Reference has been made to the Approved Ma On Shan OZP No. S/MOS/22 (15.1.2016) and the Approved Sha Tin OZP No. S/ST/32 (11.12.2015). 

 

10.3                Assessment Methodology

10.3.1            Landscape Impact Assessment Methodology

10.3.1.1         The landscape impacts have been assessed according to the following procedures.

¡P         Identification of the baseline landscape resources (LRs) and landscape characters found within the study area.  This is achieved by site visits and desktop study of topographical maps, information databases and photographs.

¡P         Assessment of the degree of sensitivity of the LRs and landscape character areas (LCAs).  This is influenced by a number of factors including whether the resource/character is common or rare, whether it is considered to be of local, regional, national or global importance, whether there are any statutory or regulatory limitations/requirements relating to the resource, the quality of the resource/character, the maturity of the resource and the ability of the resource/character to accommodate change. 

¡P         The sensitivity of each landscape feature and character area is classified as follows:

High:

Important landscape character or resource of particularly distinctive character or high importance, sensitive to relatively small change.

Medium:

Landscape character or resource of moderately valued landscape characteristics reasonably tolerant to change.

Low:

Landscape character or resource, the nature of which is largely tolerant to change.

¡P         Identification of potential sources of landscape changes.  These are the various elements of the construction works and operation procedures that would generate landscape impacts. 

¡P         The magnitude of landscape changes is classified as follows:

Large:

The landscape character or landscape resource would incur a major change.

Intermediate:

The landscape character or landscape resource would incur a moderate change.

Small:

The landscape or landscape resource would incur slight or barely perceptible change.

Negligible:

The landscape or landscape resource would incur no discernible change.

¡P         Identification of potential landscape mitigation measures.  These may take the form of adopting basic engineering design to prevent and/or minimise adverse landscape impacts before adopting other mitigation or compensatory measures to alleviate the impacts.  Potential mitigation measures shall also include the preservation of vegetation and natural landscape resources, transplanting trees in good condition and value, provision of screen planting, re-vegetation of disturbed lands, compensatory planting, woodland restoration, aesthetic design of aboveground structures including provision of finishes, colour scheme, texture of materials used and any measures to mitigate the impact on the existing and planned land use and visually sensitive receivers (VSRs).  A programme for the mitigation measures is provided.  The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified. 

¡P         Prediction of the significance of landscape impacts before and after the implementation of the mitigation measures.  By synthesizing the magnitude of the various impacts and the sensitivity of the various landscape resources, it is possible to categorise impacts in a logical, well-reasoned and consistent fashion.  Table 10.1 shows the rationale for dividing the degree of significance into four thresholds, namely insubstantial, slight, moderate, and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of change and a low-medium-high degree of sensitivity of landscape resource /character. 

Table 10.1     Relationship between Landscape Sensitivity and Magnitude of Change in Defining Impact Significance

Magnitude of Change

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Insubstantial / Slight

Slight / Moderate

Moderate

Negligible

Insubstantial

Insubstantial

Insubstantial

 

Low

Medium

High

Sensitivity of Landscape Character Area and Resource

Note:  All impacts are Adverse unless otherwise noted with Beneficial.

¡P         The significance of landscape impacts is categorised as follows:

Substantial:

Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing landscape quality.

Moderate:

Adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing landscape quality.

Slight:

Adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in existing landscape quality.

Insubstantial:

No discernible change in the existing landscape quality.

¡P         Prediction of Acceptability of Impacts.  An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM.

10.3.2            Visual Impact Assessment Methodology

10.3.2.1         The visual impacts have been assessed according to the following procedures.

¡P         Identification of the Visual Envelope during the construction and operation phases of the project.  This is achieved by site visit and desktop study of topographic maps, photographs and preparation of cross-sections to determine visibility of the Project from various locations. 

¡P         Identification of the VSRs within the Visual Envelope at construction and operation phases.  These are the people who would reside within, work within, play within, or travel through, the Visual Envelope.

¡P         Assessment of the degree of sensitivity of the VSRs.  Factors considered include: 

o    The type of VSRs, which is classified according to whether the person is at home, at work, at play, or travelling.  Those who view the change from their homes are considered to be highly sensitive as the attractiveness or otherwise of the outlook from their home will have a substantial effect on their perception of the quality and acceptability of their home environment and their general quality of life.  Those who view the impact from their workplace are considered to be only moderately sensitive as the attractiveness or otherwise of the outlook will have a less important, although still material, effect on their perception of their quality of life.  The degree to which this applies depends on whether the workplace is industrial, retail or commercial.  Those who view the impact whilst taking part in an outdoor leisure activity may display varying sensitivity depending on the type of leisure activity.  Those who view the impact whilst travelling on a public thoroughfare will also display varying sensitivity depending on the speed of travel. 

o    other factors which are considered (as required by EIAO GN 8/2010) include the value and quality of existing views, the availability and amenity of alternative views, the duration or frequency of view, and the degree of visibility. 

¡P         The sensitivity of VSRs is classified as follows:

High:

The VSR is highly sensitive to any change in their viewing experience.

Medium:

The VSR is moderately sensitive to any change in their viewing experience.

Low:

The VSR is only slightly sensitive to any change in their viewing experience.

¡P         Identification of relative numbers of VSRs.  This is expressed in terms of whether there are ¡§many¡§, ¡§medium¡¨ and ¡§few¡¨ VSRs in any one category of VSR.

¡P         Identification of potential sources of visual changes.  These are the various elements of the construction works and operation that would generate visual changes.

¡P         Assessment of the potential magnitude of visual changes.  Factors considered include:

o    the compatibility with the surrounding landscape;

o    the duration of the impact;

o    the reversibility of the impact;

o    the scale of the impact and distance of the source of impact from the viewer; and

o    the degree of visibility of the impact, and the degree of which the impact dominates the field of vision of the viewer. 

¡P         The magnitude of visual changes is classified as follows: 

Large:

The VSRs would suffer a major change in their viewing experience.

Intermediate:

The VSRs would suffer a moderate change in their viewing experience.

Small:

The VSRs would suffer a small change in their viewing experience.

Negligible:

The VSRs would suffer no discernible change in their viewing experience.

¡P         Identification of potential landscape mitigation measures.  These may take the form of adopting basic engineering design to prevent and/or minimise adverse visual impacts before adopting other mitigation or compensatory measures to alleviate the impacts.  Potential mitigation measures shall also include the preservation of vegetation and natural landscape resources, provision of screen planting, re-vegetation of disturbed lands, compensatory planting, woodland restoration, aesthetic design of aboveground structures including provision of finishes, colour scheme, texture of materials used and any measures to mitigate the impact on the existing and planned land use and VSRs.  A programme for the mitigation measures is provided.  The agencies responsible for the funding, implementation, management and maintenance of the mitigation measures are identified. 

¡P         Prediction of the significance of visual impacts before and after the implementation of the mitigation measures.  By synthesizing the magnitude of the various visual impacts and the sensitivity of the VSRs, and the numbers of VSRs that are affected, it is possible to categorise the degree of significance of the impacts in a logical, well-reasoned and consistent fashion.  Table 10.2 shows the rationale for dividing the degree of significance into four thresholds, namely, insubstantial, slight, moderate and substantial, depending on the combination of a negligible-small-intermediate-large magnitude of change and a low-medium-high degree of sensitivity of VSRs. 


 

Table 10.2     Relationship between VSRs Sensitivity and Magnitude of Change in Defining Impact Significance

Magnitude of Change

Large

Moderate

Moderate / Substantial

Substantial

Intermediate

Slight / Moderate

Moderate

Moderate / Substantial

Small

Insubstantial / Slight

Slight / Moderate

Moderate

Negligible

Insubstantial

Insubstantial

Insubstantial

 

Low

Medium

High

Sensitivity of VSRs

Note:  All impacts are Adverse unless otherwise noted with Beneficial.

¡P         The significance of visual impacts is categorised as follows:

Substantial:

Adverse / beneficial impact where the proposal would cause significant deterioration or improvement in existing visual quality.

Moderate:

Adverse / beneficial impact where the proposal would cause a noticeable deterioration or improvement in existing visual quality.

Slight:

Adverse / beneficial impact where the proposal would cause a barely perceptible deterioration or improvement in existing visual quality.

Insubstantial:

No discernible change in the existing visual quality.

¡P         Prediction of Acceptability of Impacts.  An overall assessment of the acceptability, or otherwise, of the impacts according to the five criteria set out in Annex 10 of the EIAO-TM. 

 

10.4                Review of Planning and Development Control Framework

10.4.1.1         Relevant plan(s) and/or studies which may identify areas of high landscape value, country parks, coastal protection area, GB and CA designations are reviewed.  Any guidelines on landscape and urban design strategies and frameworks that may affect the appreciation of the Project are also reviewed.  The aim is to gain an insight of the future outlook of the affected area so as to assess whether the Project can fit into the surrounding setting.  Any conflict with statutory town plan(s) is highlighted and appropriate follow-up action is recommended. 

10.4.1.2         Apart from the statutory OZPs, a number of adopted / draft departmental Layout Plans as listed below are also reviewed:

¡P         Adopted Sha Tin New Town Area 64 Layout Plan No. L/ST 64/1A

¡P         Adopted Sha Tin New Town Area 72 Layout Plan ¡V A Kung Kok Fishermen¡¦s Village No. L/ST 72/1

¡P         Draft Sha Tin Area 75 ¡V Layout Plan No. L/ST 75/2D. 

10.4.1.3         The Study Area of the Project is covered under two OZPs.  They are the Approved Ma On Shan OZP No. S/MOS/22 (15.1.2016) and the Approved Sha Tin OZP No. S/ST/32 (11.12.2015).  The landuse zones overlaid on the Project layout is shown in Figure No. 60334056/EIA/10.01.  The land uses zones to be potentially affected by the Project and the future outlook of the area is discussed and summarised Table 10.3. 

Table 10.3     Summary of the Review of Planning and Development Control Framework

OZP Plan Title and No.

Land Use Zonings

Approx. Area of the Land Use Zones to be affected

Current Design and Conservation Intention in the OZP

Potential change to the OZP and the anticipated future outlook of the area due to the Project.

Approved Sha Tin OZP No. S/ST/32 (11.12.2015) and Approved Ma On Shan OZP No. S/MOS/22 (15.1.2016)

Other Specified Uses (OU)

28ha

Sewage generated in the Sha Tin is treated in the existing STSTW. 

Under the Project, the existing STSTW will be decommissioned and demolished.  The STSTW will be relocated to Caverns.  The demolished site will be cleared and pending for future developments.  Since the future developments at the site of the existing STSTW after its decommissioning are under a separate project, any recommendation to the change in OZP shall be made later.

GB

1.41ha

The current planning intention of this zone is primarily for defining the limits of urban and sub-urban development areas by natural woodland slopes at Nui Po Shan. 

Under the Project, the existing natural woodland slopes in the GB Zone at Nui Po Shan will be removed for the construction and operation of the relocated STSTW facilities at the Main Portal Area, Secondary Portal Area, Ventilation Shaft and associated access road and site formation works.  The Project shall be carefully designed to blend in the proposed above ground structures with the existing sloped woodland backdrop. 

 

10.4.1.4         Since there would be change in the land use in the Approved Sha Tin OZP No. S/ST/32 (11.12.2015) and Approved Ma On Shan OZP No. S/MOS/22 (11.12.2016), ongoing liaison with PlanD regarding the revised boundary of the GB Zone shall be carried out throughout the design process.  It is recommended that both the Sha Tin OZP and Ma On Shan OZP shall be amended to incorporate the latest changes arising from the Project when the design layouts are finalised.

10.4.1.5         Having reviewed the adopted / draft departmental Layout Plans as listed in Para 10.4.1.2, there would not be any conflict to the Layout Plans due to the Project. 

 

10.5                Baseline Study

10.5.1            Landscape Resources

10.5.1.1         The details of Baseline LRs which will be potentially affected by the Project, together with their sensitivity are described in Table 10.4.  The locations of baseline LRs are mapped in Figure No. 60334056/EIA/10.11.  Photo views illustrating the LRs within the study area are illustrated in Figure Nos. 60334056/EIA/10.12 to 10.14. 

Table 10.4     Baseline LRs and their Sensitivity

LRs

Description

Sensitivity

LR-01

Amenity Planting in the Existing STSTW

This LR covers extensive at grade trees and shrubs planting, vertical greening and green roof within the existing STSTW Site.  Trees and shrubs are found in the landscape areas between access road and buildings/structures.  Trees found are all common landscape species.  There is no OVT nor endangered and protected species identified within this resource.  Green roofs are found on a number of utility buildings with common landscape species.  Vertical greening is found on the facade of existing sludge storage tank.    Most of the vegetation are recently established and considered as young to semi-mature.  It is a common landscape resource.  The quality of the existing vegetation is medium.  The ability to accommodate change is high and the sensitivity of this LR is considered as medium.

Medium

LR-02

Waterbodies in Shing Mun River and Sha Tin Hoi

This LR comprises waterbodies of Shing Mun River, which is an artificial river channel, and Sha Tin Hoi at the mouth of the Shing Mun River in Tolo Harbour.  These waterbodies are popular place for water sports, such as rowing, canoeing and dragon boat racing.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate change is low.  The sensitivity of this LR is considered as high. 

High

LR-03

Landscape Areas in Sha Tin Racecourse

This LR is the racecourse in the New Territories.  Penfold Park, which is the key landscape areas encircled by the racing track in the Racecourse, comprises features green areas, ornamental tree and shrub planting.  It is a unique landscape resource which is of regional importance.  The quality of this resource is high and the ability of this resource to accommodate change is low.  The sensitivity of this LR is considered as high. 

High

LR-04

Ma On Shan Promenade

This promenade locates along the coast of Ma On Shan overlooking Sha Tin Hoi and offers a magnificent view of the peaks of Pat Sin Leng, featuring a panorama of the sea and the sky.  Ma On Shan Promenade provides both active and passive recreations for the local residents.  Lush tree and shrub planting are found along the promenade.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate changes is low.  The sensitivity of this LR is considered as high. 

High

LR-05

Shing Mun River Promenade

This promenade locates at the both sides of Shing Mun River and provides places to appreciate the day and night views along Shing Mun River.  Shing Mun River Promenade is a linear space comprising cycle track and riverside walk with lush tree and shrub planting.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate changes is low.  The sensitivity of this LR is considered as high. 

High

LR-06

Landscape Areas within Kam Tai Court

Landscape areas within Kam Tai Court provide spaces for passive and active recreation for the local residents.  Ornamental trees and shrub planting are found in the landscape areas of Kam Tai Court.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate changes is low.  The sensitivity of this LR is considered as high. 

High

LR-07

Roadside Planting Areas along Ma On Shan Road

Roadside planting areas along Ma On Shan Road comprise predominately tree and shrub planting.  Plant species found are common roadside landscape species in Hong Kong.  The quality of this LR is considered as medium.  The ability to accommodate changes and the sensitivity of this LR is considered as medium.

Medium

LR-08

Woodland on Slopes of Nui Po Shan

Woodland planting on existing slope comprises canopy trees and understory vegetation.  They are common species found in woodland of Hong Kong.  This is a local hillside landscape feature in Hong Kong which provides natural green backdrop for the urban fringe of Ma On Shan region.  This LR is a common landscape resource.  The quality of these resources is high. The ability to accommodate change is low and the sensitivity of this resource is considered as high. 

High

LR-09

Landscape Areas within Chevalier Garden

Landscape areas within Chevalier Garden provide open spaces for passive and active recreation for the local residents.  Ornamental trees and shrub planting are found in the landscape areas of Chevalier Garden.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate changes is low.  The sensitivity of this LR is considered as high. 

High

LR-10

Roadside Planting Areas along Tolo Highways

Roadside planting areas along Tolo Highways comprise predominately tree and shrub planting.  Plant species found are common roadside landscape species in Hong Kong.  The quality of this LR is considered as medium.  The ability to accommodate changes and the sensitivity of this LR is considered as medium.

Medium

LR-11

Woodland on Slopes of Kau To Shan

Woodland planting on existing natural slopes and man-made slopes at Kau To Shan comprises mature trees and understory vegetation.  Vegetation found is common native and exotic species in woodlands of Hong Kong.  It is a common landscape resource.  The quality of these resources is medium. The ability to accommodate changes and the sensitivity of this LR is considered as medium.

Medium

LR-12

Landscape Areas at Ah Kung Kok Fishermen Village

Landscape Areas found at Ah Kung Kok Fishermen Village are mainly amenity planting along the internal road of the village.  Vegetation found is common landscape species in Hong Kong.  It is a common landscape resource.  The quality of these resources is medium. The ability to accommodate changes and the sensitivity of this LR is considered as medium.

Medium

LR-13

Stream Running along Mui Tsz Lam Road

This is an engineered stream course running along Mui Tsz Lam Road.  There is no landscape treatment at the embankment and the bottom of the stream course.  It is a common landscape resource.  The ability to accommodate changes is high and the sensitivity of this LR is considered low. 

Low

LR-14

Landscape Areas in Shatin Hospital

Amenity tree and shrub planting is found within the landscape areas of Shatin Hospital.  It is a common landscape resource.  The quality of this resource is medium and the ability of this resource to accommodate changes is medium.  The sensitivity of this LR is considered as medium. 

Medium

LR-15

Landscape Areas in Hyatt Regency Hong Kong, Sha Tin

Landscape areas within Hyatt Regency provide amenity landscape for the hotel residents.  Ornamental trees and shrub planting are found in the landscape areas.  It is a common landscape resource.  The quality of this resource is high and the ability of this resource to accommodate changes is low.  The sensitivity of this LR is considered as high. 

High

LR-16

Landscape Areas in Marine Outer Waters District Headquarter and Water Supplies Department (WSD) Salt Water Pumping Station

Buffer tree planting is found at the periphery of Marine Outer Waters District Headquarter (HQ) and WSD Salt Water Pumping Station.  It is a common landscape resource.  The quality of this resource is medium and the ability of this resource to accommodate changes is medium.  The sensitivity of this LR is considered as medium. 

Medium

LR-17

Cycle Track connecting the waterfront promenade and A Kung Kok Street

This is a two-way cycle track connecting the waterfront promenade at Shing Mun River Channel and A Kung Kok Street.  The total length of this section of the cycle track is approximately 300m.  It is a common recreational resource. The quality of this resource is medium and the ability to accommodate changes is medium.  The sensitivity of this LR is considered as medium. 

Medium

 

10.5.2            Landscape Character Areas (LCAs)

10.5.2.1         The details of Baseline LCAs which will be potentially affected by the Project, together with their sensitivity are described in Table 10.5.  The locations of baseline LCAs are mapped in Figure No. 60334056/EIA/10.21.  Photo views illustrating the LCAs within the study area are illustrated in Figure Nos. 60334056/EIA/10.22 to 10.24. 


 

Table 10.5     Baseline LCAs and their Sensitivity

LCAs

Description

Sensitivity

LCA-01

Sha Tin Waterfront Industrial LCA

This LCA comprises low-lying reclaimed land adjoining the Shing Mun River Channel.  It is primarily characterised by an extensive area of STSTW including tanks, associated plants buildings, car park and pumping station.  Trees, shrubs, vertical greening and roof greening have been extensively planted to the STSTW Site.  Most of the greening works were implemented in 2011.  The maturity of the vegetation found on site is considered as young.  Marine Outer Waters District HQ is located at the northern end of this LCA.  This LCA has high ability to accommodate change.  The overall sensitivity of this LCA is therefore considered as low.

Low

LCA-02

Sha Tin Hoi and Shing Mun River Inshore Water LCA

This is an area of artificial river channel and coastal water lying close to the shore and enclosed to a certain degree by landmasses which create a sense of enclosure.  This is a common landscape character in Hong Kong which has low ability to accommodate change.  The sensitivity of this LCA is therefore considered as High. 

High

LCA-03

Ma On Shan Waterfront Residential LCA

This is an area which comprises of high rise residential buildings, schools, public open spaces.  It is characterised by the mixes of landscape areas of various sizes which distribute between buildings providing passive and active recreation for the local residents.  Lush amenity areas are commonly found within the landscape areas of this LCA.  This is a common residential landscape in Hong Kong which has low ability to accommodate change.  The sensitivity of this LCA is therefore considered as High. 

High

LCA-04

Ma On Shan Transportation Corridor LCA

This LCA is characterised by major highways corridors in Ma On Shan.  Major features include flyovers, signage gantries, interchange, traffic islands and associated roadside buffer planting areas.  This type of LCA is common to Hong Kong.  It has high ability to accommodate changes.  The sensitivity is considered as low. 

Low

LCA-05

A Kung Kok and Tai Shui Hang Miscellaneous Urban Fringe LCA

This LCA is found on the periphery of the urban area of Ma On Shan and Sha Tin.  It is characterised by the scattered village houses at A Kung Kok and Tai Shui Hang, medium rise residential development of Chevalier Garden and Shatin Hospital, site offices developed along the edge of hillsides.  They are transitional landscapes which are characterised by a diverse range of features, significant vegetation cover and incoherent human structures with features having little formal relationship to each other.  This LCA has medium ability to accommodate change.  The sensitivity of this LCA is considered as high. 

High

LCA-06

Nui Po Shan Upland and Hillside LCA

This LCA consists of hillsides, knolls, ridges and spurs in Nui Po Shan.  It contains few human features and retains a rugged, tranquil character, with rocky outcrops or boulder fields and muted natural colours.  Woodland is found at the lower slopes.  This LCA has low ability to accommodate change.  The sensitivity of this LCA is considered as high. 

High

LCA-07

A Kung Kok Settled Valley LCA

This LCA lies between spurs at A Kung Kok defined largely by the valley topography.  Low rise institutional uses, which include Cheshire Home Shatin, Breakthrough Youth Village, Richard Bulter Chalets, Shing Mun Springs and the Neighbourhood Advice-Action Council Harmony Manor, are settled at the both sides of A Kung Kok Shan Road running along the valley.  At the lower part of the valley, woodlands are found between developments and at the both sides of the A Kung Kok Shan Road.  This LCA has low ability to accommodate changes.  The sensitivity of this LCA is considered as high. 

High

LCA-08

Sha Tin Racecourse LCA

This LCA comprises of low-lying reclaimed land for horse racing course adjoining the Shing Mun River in Sha Tin.  It is primarily characterised by racing tracks with grass lawn.  Penfold Park is encircled by the tracks.  This LCA has low ability to accommodate change.  The overall sensitivity of this LCA is therefore considered as high.

High

LCA-09

Ma Liu Shui Transportation Corridor LCA

This LCA is characterised by major highways corridors in Ma Liu Shui.  Major features include flyovers, signage gantries, interchange, traffic islands and associated roadside buffer planting areas.  This type of LCA is common to Hong Kong.  It has high ability to accommodate changes.  The sensitivity is considered as low. 

Low

LCA-10

Kau To Shan Residential Urban Fringe LCA

This LCA comprises of low-density residential developments at the hillsides of Kau To Sha.  This landscape is characterised by individual houses or villas built on hillside with narrow winding roads and a backdrop of mature hillside vegetation.  It is a fairly coherent residential landscape with a high coverage of vegetation which possesses a relatively informal and tranquil character.  This type of LCA is of local importance and common to Hong Kong.  It has low ability to accommodate changes.  The sensitivity is considered as high. 

High

LCA-11

Tai Shui Hang Upland and Hillside LCA

This LCA consists of hillsides, knolls, ridges and spurs in Tai Shui Hang.  It is generally covered in scrub vegetation with rocky outcrops or boulder fields.  Woodland is found on lower slopes.  It contains few human features and retains a rugged, tranquil character.  This LCA has low ability to accommodate change.  The sensitivity of this LCA is considered as high. 

High

LCA-12

Tai Shui Hang Settled Valley LCA

This LCA lies between spurs at Tai Shui Hang in close proximity to the urban areas, defined largely by the valley topography.  Mui Tsz Lam Road and a natural meandering stream course are found at the valley.  At the lower part of the valley, woodlands are found on both sides of the stream course and Mui Tsz Lam Road.  It retains a tranquil character with little human influence.  This LCA has low ability to accommodate change.  The sensitivity of this LCA is considered as high. 

High

LCA-13

Nui Po Shan Peak LCA

This LCA is located at the peak of the knoll of Nui Po Shan.  It has a remote, rugged and exposed character with little human influence.  It is characterised by its steep terrain and muted natural colours, covered predominantly with grasses and shrubs.  This LCA has low ability to accommodate change.  The sensitivity of this LCA is considered as high. 

High

 

10.5.3            Broad Brush Tree Survey

10.5.3.1         A board brush tree survey was carried out in accordance with the Appendix J of the EIA Study Brief to identify dominant tree species, maturity, rarity and any plant species of conservation interest, etc. which would be potentially affected to provide baseline information on the LRs and LCAs.  The broad brush tree survey findings including tree survey plans and tree schedule are illustrated in Appendix 10.01. 

10.5.3.2         Six tree groups were that would be potentially affected were surveyed.  It is estimated that approximately 2,086 nos. of trees were surveyed within the groups.  The dominant tree species include Acacia confusa, Aporusa chinensis, Casuarina equisetifolia, Cleistocalyx operculatus, Hibiscus tiliaceus, Leucaena leucocephala, Lophostemon confertus, Pinus massoniana, Schefflera heptaphylla, Sterculia lanceolata, Syzygium jambos, and Terminalia mantaly.  They are generally of mature size.  There is no OVT identified within the project boundary.  All tree species surveyed are common in Hong Kong.  There is no tree of specific conservation interest. 

10.5.4            Visual Envelope

10.5.4.1         The prominent lowland location of the Study Area gives rise to a large visual envelope which extends beyond the vicinity in several directions.  The visual envelope of the Project is embraced by the ridgeline of Ma On Shan to the East, the ridgeline of Kau To Shan to the West, the high-rise residential developments which include Kam Tai Court, Yan On Estate and Heng On Estate to the north and the high-rise residential developments which include Jubilee Garden, The Palazzo, Royal Ascot, Wo Che Estate, City One - Shatin, Yue Tin Court and Yu Chui Court to the south.  The Visual Envelope of the Project is shown in Figure No. 60334056/EIA/10.31.

10.5.5            Visually Sensitive Receivers (VSRs)

10.5.5.1         Within the Visual Envelope, a number of key VSRs have been identified during construction and operation phases.  They are listed, together with their baseline assessment and sensitivity, in Table 10.6 and mapped in Figure No. 60334056/EIA/10.31. 

10.5.5.2         The sensitivity of VSRs is assessed in accordance with EIAO Guidance Note No. 8/2010.  Key factors including type of VSRs, number of individuals within the VSRs, quality of existing view, availability of alternative views, degree of visibility, duration of view and frequency of view of the VSRs are evaluated. 

10.5.5.3         There are four types of Key VSR Types identified in the Visual Envelope of the Project.  They include Residential VSRs who are living in the adjacent high rise residential developments to the East and the South of the Site and the low rise private housing on Kau To Shan, Institutional VSRs at work or at study including temporarily occupants in hotel or hospital etc., Recreational VSRs at play in open space, promenade, hiking trail and waterbody and Travelling VSRs travelling on a public thoroughfare. 


Table 10.6     Baseline VSRs and their Sensitivity

VSR ID.

VSRs

Type of VSRs

Number of Individuals

(Many/ Medium/ Few)

Quality of Existing View

(Good/Fair/ Poor)

Availability of Alternative Views

(Yes/No)

Degree of Visibility

(Full/ Partial/ Glimpse)

Duration of View

 (Long/ Medium/ Short)

Frequency of View

(Frequent/ Occasional/ Rare)

Sensitivity

R-01

Residents in Chevalier Garden

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-02

Residents in Pictorial Garden, Garden Vista, Ravana Garden, etc.

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-03

Residents in City One

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-04

Residents in Wo Che Estate

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-05

Residents in Fo Tan including Jubilee Garden and The Palazzo

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-06

Residents in Royal Ascot

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-07

Residents in Low Rise Private Residential Developments at Kau To Shan including Windsor Park, Kam On Gardens, Greenland Villas, Yucca Villa, Pine Villa, Jade Villa, Windsor Heights, Evergreen Gardens, Double Haven House, Forest Hill, Greenery Villas and Shatin Knoll, etc.

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-08

Residents in Potential Residential Development at Lai Ping Road

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-09

Residents in Ah Kung Kok Fishermen Village

Residential

Few

Fair

No

Partial

Long

Frequent

Medium

R-10

Residents in the Hong Kong Jockey Club Shatin Staff Quarters

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-11

Residents in Sui Wo Court

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-12

Residents in Kam Tai Court

Residential

Many

Good

Yes

Full

Long

Frequent

High

R-13

Residents in Shek Mun Estate

Residential

Many

Good

Yes

Full

Long

Frequent

High

I-01

Occupants in Tsung Tsin Secondary School and Kowloon City Baptist Church Hay Nien Primary School

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-02

Occupants in Shatin Hospital, Bradbury Hospice and Cheshire Home

Institutional

Medium

Good

Yes

Full

Medium

Occasional

Medium

I-03

Occupants in Hyatt Regency Hong Kong

Institutional

Medium

Good

Yes

Full

Medium

Occasional

Medium

I-04

Occupants in Chinese University of Hong Kong

Institutional

Medium

Good

Yes

Full

Medium

Occasional

Medium

I-05

Occupants in Hong Kong Science Park

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-06

Occupants in Jockey Club Ti-I College

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-07

Occupants in Hong Kong Institute of Vocational Education

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-08

Occupants in the Neighbourhood Advice-Action Council Harmony Manor

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-09

Occupants in Hong Kong Sports Institute

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-10

Occupants in Shek Mun Industrial Area

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

I-11

Occupants in Shatin Hospital

Institutional

Medium

Good

Yes

Partial

Medium

Occasional

Medium

O-01

Recreational Users in Ma On Shan Promenade

Recreational

Many

Good

Yes

Partial

Medium

Occasional

High

O-02

Recreational Users including cyclists along cycle track in the promenades at both sides of the Shing Mun River Channel

Recreational

Many

Good

Yes

Partial

Medium

Occasional

High

O-03

Water based recreational users in the waterbodies from Tolo Harbour to Shing Mun River Channel

Recreational

Medium

Good

Yes

Partial

Medium

Occasional

High

O-04

Recreational Users in Sha Tin Racecourse and Penfold Park

Recreational

Many

Good

Yes

Partial

Medium

Occasional

High

O-05

Hikers in Walking Trails

Recreational

Medium

Good

Yes

Full

Medium

Occasional

High

O-06

Recreational Users Pak Shek Kok Promenade

Recreational

Many

Good

Yes

Partial

Medium

Occasional

High

T-01

Travellers along Tolo Highways

Travelling

Many

Fair

Yes

Glimpse

Short

Rare

Low

T-02

Travellers along Tate¡¦s Cairn Highways

Travelling

Many

Fair

Yes

Glimpse

Short

Rare

Low

T-03

Passengers on MTR East Rail Line

Travelling

Many

Fair

Yes

Glimpse

Short

Rare

Low

T-04

Travellers along Ma On Shan Road and MTR Ma On Shan Rail

Travelling

Many

Fair

Yes

Glimpse

Short

Rare

Low

 


10.6                Landscape Impact Assessment

10.6.1            Sources of Landscape Impacts

10.6.1.1         The sources of landscape impacts in the construction phase would include: 

¡P         Decommission and demolition of the existing STSTW;

¡P         Construction of Main Tunnel Portals and ancillary facilities at Main Portal Area at A Kung Kok Street including Administration Building, Ventilation Building No. 1, Electrical Substation No. 1, etc. and associated site formation and natural terrain mitigation works including check dams; 

¡P         Construction of Secondary Tunnel Portal and ancillary facilities at Secondary Portal Area at Mui Tsz Lam Road including Ventilation Building No. 2, Electrical Substation No.2, etc. and associated site formation; 

¡P         Construction of Ventilation Shaft and a temporary project specific magazine at Nui Po Shan and associated access road connecting to existing A Kung Kok Shan Road; 

¡P         Decommission of the temporary project specific magazine after the completion of the construction of caverns;

¡P         Construction of an underground twin 2m dia. pipe connecting the relocated STSTW and the existing emergency outfall; 

¡P         Temporary works at Area between A Kung Kok Street and Ma On Shan Road including construction of temporary site access and the temporary stockpiling area; and

¡P         Temporary works at Area 73 including temporary site access, staff office area, temporary stocking piling area and workshops, etc. 

10.6.1.2         The sources of landscape impacts in the operation phase would include: 

¡P         Ancillary facilities at Main Portal Area at A Kung Kok Street including Main Tunnel Portals, Administration Building, Ventilation Building No. 1, Electrical Substation No. 1 and associated site formation and natural terrain mitigation works including check dams; 

¡P         Ancillary facilities at Secondary Portal Area at Mui Tsz Lam Road including Secondary Tunnel Portal, Ventilation Building No. 2 and Electrical Substation No. 2 and associated site formation; and

¡P         Ventilation Shaft at Nui Po Shan and associated access road connecting to existing A Kung Kok Shan Road.

10.6.1.3         As the construction of tunnels and caverns are conducted below ground, it is anticipated that there would not be any potential landscape impacts.  

10.6.1.4         Since the sewage and sludge treatment facilities of the CSTW and the water reclamation facilities for the non-potable use of treated effluent from the CSTW would be installed inside the caverns, there would not be any potential landscape impacts due to installation of these facilities. 

10.6.2            Magnitude of Landscape Impacts

10.6.2.1         The magnitude of unmitigated landscape impacts associated with the construction phase and operational phases of the Project are assessed and described in Table 10.7.  

Table 10.7     Magnitude of Landscape Impacts during Construction and Operation

ID

Landscape Resources/ Character Areas

Potential Source of Impact

Description of Impacts

Magnitude of Change

(Large/ Intermediate/ Small/ Negligible)

Construc-tion

Oper-ation

Landscape Resources

LR-01

Amenity Planting in the Existing STSTW

¡P   Decommission and demolition of existing STSTW.

Under the demolition works, majority of the at-grade vegetation will be preserved where possible.  Only green roofs, vertical greening attached to existing buildings and vegetation above existing underground structures will be removed. 

Small

Small

LR-02

Waterbodies in Shing Mun River and Sha Tin Hoi

¡P   Construction of an underground twin 2m dia. pipe connecting the relocated STSTW and the existing emergency outfall.

The outfall shall be constructed by trenchless method under the Shing Mun River bed, it is anticipated that there would not be any temporary loss of waterbodies during construction.  As the outfall is an underground structure, it is anticipated that there would not be any landscape impact on the waterbodies during operation. 

Negligible

Negligible

LR-03

Landscape Areas in Sha Tin Racecourse

Nil

Nil

Negligible

Negligible

LR-04

Ma On Shan Promenade

Nil

Nil

Negligible

Negligible

LR-05

Shing Mun River Promenade

Nil

Nil

Negligible

Negligible

LR-06

Landscape Areas within Kam Tai Court

Nil

Nil

Negligible

Negligible

LR-07

Roadside Planting Areas along Ma On Shan Road

¡P   Temporary Works at Area between A Kung Kok Street and Ma On Shan including construction of temporary site access and the temporary stockpiling area; and

¡P   Temporary Works at Area 73 including temporary site access, staff office area, temporary stocking piling area and workshops, etc.

Based on a broad brush estimate, approximately 190 nos. of existing trees will be removed during construction.  Affected tree species include Aleurites moluccana, Bauhinia purpurea, Bombax ceiba, Casuarina equisetifolia, Delonix regia, Ficus microcarpa, Leucaena leucocephala and Melaleuca cajuputi subsp. Cumingiana.  They are generally of medium form and fair amenity value. 

Affected trees are in the range of 4-10m high, 3-9m spread and 100-600mm trunk diameter. 

Intermediate

Intermediate

LR-08

Woodland on Slopes of Nui Po Shan

¡P   Construction and Operation of facilities at Main Portal Area and associated natural terrain mitigation works including check dams; 

¡P   Construction and Operation of facilities at Secondary Portal Area; 

¡P   Construction of a temporary project specific magazine and associated site formation works;

¡P   Decommission of the temporary project specific magazine; and

¡P   Construction and Operation of Ventilation Shaft at  Nui Po Shan and associated access road connecting to existing A Kung Kok Shan Road. 

Based on a broad brush estimate, approximately 638 nos. of existing trees will be removed during construction. Affected tree species include Acacia confusa, Aporusa dioica, Cleistocalyx operculata, Litchi chinensis, Cratoxylum cochinchinense, Ficus microcarpa, Macaranga tanarius, and Schefflera heptaphylla.  They are generally of medium form and fair to poor amenity value. 

Affected trees are in the range of 3-14m high, 3-10m spread and 95-800mm trunk diameter. 

Large

Large

LR-09

Landscape Areas within Chevalier Garden

Nil

Nil

Negligible

Negligible

LR-10

Roadside Planting Areas along Tolo Highways

Nil

Nil

Negligible

Negligible

LR-11

Woodland on Slopes of Kau To Shan

Nil

Nil

Negligible

Negligible

LR-12

Landscape Areas at Ah Kung Kok Fishermen Village

Nil

Nil

Negligible

Negligible

LR-13

Stream Running along Mui Tsz Lam Road

Nil

Nil

Negligible

Negligible

LR-14

Landscape Areas in Shatin Hospital

Nil

Nil

Negligible

Negligible

LR-15

Landscape Areas in Hyatt Regency Hong Kong, Sha Tin

Nil

Nil

Negligible

Negligible

LR-16

Landscape Areas in Marine Outer Waters District HQ and WSD Salt Water Pumping Station

Nil

Nil

Negligible

Negligible

LR-17

Cycle Track connecting the waterfront promenade and A Kung Kok Street

Temporary Works at Area 73 including temporary site access, staff office area, temporary stocking piling area and workshops, etc.

Approximately 300m of the cycle track will be temporary alienated during the construction phase. 

Large

Large

LCAs

LCA-01

Sha Tin Waterfront Industrial LCA

¡P   Decommission and demolition of existing STSTW.

There would be permanent change in landscape character of the area under decommission and demolition works due to the clearance of aboveground and underground facilities and associated green roof and vertical greening and associated vegetation within the STSTW.  All other vegetation that would not be affected by the demolition works will be retained. 

Small

Small

LCA-02

Sha Tin Hoi and Shing Mun River Inshore Water LCA

¡P   Construction of an underground twin 2m dia. pipe connecting the relocated STSTW and the existing emergency outfall.

The outfall shall be constructed by trenchless method under the Shing Mun River bed, it is anticipated that there would not be impact on the waterbodies during construction.  As the outfall is an underground structure, it is anticipated that there would not be any landscape impact on this LCA during operation. 

Negligible

Negligible

LCA-03

Ma On Shan Waterfront Residential LCA

Nil

Nil

Negligible

Negligible

LCA-04

Ma On Shan Transportation Corridor LCA

¡P   Temporary Works at Area between A Kung Kok Street and Ma On Shan including construction of temporary site access and the temporary stockpiling area; and

¡P   Temporary Works at Area 73 including temporary site access, staff office area, temporary stocking piling area and workshops, etc.

During construction approximately 17,700 m2 of existing vegetation along roadside within the LCA will be removed.  There would be temporary change in character in this LCA due to the construction activities including temporary site assess, staff office and temporary stockpiling at the Area between A Kung Kok Street and Ma On Shan and Area 73.

During operation, the irreversible unmitigated impact will be the same as the construction phase. 

Intermediate

Intermediate

LCA-05

A Kung Kok and Tai Shui Hang Miscellaneous Urban Fringe LCA

¡P   Construction and Operation of facilities at Main Portal Area and associated natural terrain mitigation works including check dams; and 

¡P   Construction and Operation of facilities at Secondary Portal Area. 

 

During construction, approximately 30,100m2 and 7,300m2 of woodland within this LCA would be removed due to the construction works at Main Portal Area and Secondary Portal Area.  There would be temporary change in character in this LCA due to the construction activities.  

During operation, the irreversible unmitigated impact will be the same as the construction phase. 

Large

Large

LCA-06

Nui Po Shan Upland and Hillside LCA

Nil

Nil

Negligible

Negligible

LCA-07

A Kung Kok Settled Valley LCA

¡P   Construction of a temporary project specific magazine and associated site formation works;

¡P   Decommission of the temporary project specific magazine; and

¡P   Construction and Operation of Ventilation Shaft at  Nui Po Shan and associated access road connecting existing to A Kung Kok Shan Road. 

During construction, approximately 22,500m2 of woodland within this LCA would be removed due to the construction and decommission of the temporary project specific magazine, construction of Ventilation Shaft at Nui Po Shan and associated access road.  There would be temporary change in character in this LCA due to the construction activities.  

During operation, the irreversible unmitigated impact will be the same as the construction phase. 

Large

Large

LCA-08

Sha Tin Racecourse LCA

Nil

Nil

Negligible

Negligible

LCA-09

Ma Liu Shui Transportation Corridor LCA

Nil

Nil

Negligible

Negligible

LCA-10

Kau To Shan Residential Urban Fringe LCA

Nil

Nil

Negligible

Negligible

LCA-11

Tai Shui Hang Upland and Hillside LCA

Nil

Nil

Negligible

Negligible

LCA-12

Tai Shui Hang Settled Valley LCA

Nil

Nil

Negligible

Negligible

LCA-13

Nui Po Shan Peak LCA

Nil

Nil

Negligible

Negligible

 

10.6.3            Significance of Unmitigated Landscape Impacts

10.6.3.1         The significance of landscape impacts, before implementation of mitigation measures, in the construction and operation phases are assessed and presented in Table 10.12.

 

10.7                Visual Impact Assessment

10.7.1            Sources of Visual Impacts

10.7.1.1         The sources of visual impacts in the construction phase would include: 

¡P         Decommission and demolition of the existing STSTW;

¡P         Construction of Main Tunnel Portals and ancillary facilities at Main Portal Area at A Kung Kok Street including Administration Building, Ventilation Building No. 1, Electrical Substation No. 1, etc. and associated site formation and natural terrain mitigation works including check dams; 

¡P         Construction of Secondary Tunnel Portal and ancillary facilities at Secondary Portal Area at Mui Tsz Lam Road including Ventilation Building and Electrical Substation, etc. and associated site formation; 

¡P         Construction of Ventilation Shaft and a temporary project specific magazine at Nui Po Shan and associated access road connecting to existing A Kung Kok Shan Road; 

¡P         Decommission of the temporary project specific magazine;

¡P         Construction of an underground twin 2m dia. pipe connecting the relocated STSTW and the existing emergency outfall; 

¡P         Temporary Works at Area between A Kung Kok Street and Ma On Shan Road including construction of temporary site access and the temporary stockpiling area; and

¡P         Temporary Works at Area 73 including temporary site access, staff office area, temporary stocking piling area and workshops, etc. 

10.7.1.2         The sources of visual impacts in the operation phase would include: 

¡P         Ancillary facilities at Main Portal Area at A Kung Kok Street including Main Tunnel Portals, Administration Building, Ventilation Building No. 1, Electrical Substation No. 1, etc. and associated site formation and natural terrain mitigation works including check dams; 

¡P         Ancillary facilities at Secondary Portal Area at Mui Tsz Lam Road including Secondary Tunnel Portal, Ventilation Building No. 2 and Electrical Substation No. 2, etc. and associated site formation; and

¡P         Ventilation Shaft at Nui Po Shan and associated access road connecting existing A Kung Kok Shan Road. 

10.7.1.3         The locations and development details of permanent aboveground structures that would cause potential visual impact are summarised in Table 10.8. 


 

Table 10.8     Locations and Development Details of Permanent Aboveground Structures

Location

Approximate Building Height (m) and Level (mPD) of the roof of the structure [Note]

Approximate Coverage (m) [Note]

Main Portal Area

 

 

Administration Building

32m (+39mPD)

115m x 35m

Ventilation Building No. 1

51m (+59mPD)

55m x 20m

Electrical Substation No. 1

16m (+23.5mPD)

30m x 20m

Secondary Portal Area

 

 

Ventilation Building No. 2

36m (+51mPD)

50m x 25m

Electrical Substation No. 2

16m (+30.5mPD)

30m x 20m

Nui Po Shan Area

 

 

Ventilation Shaft

5m (+182mPD)

12m dia.

Note:   Exact levels, heights and dimensions would be subject to detailed design.

 

10.7.1.4         As the construction of tunnels and caverns are conducted below ground, it is anticipated that there would not be any potential visual impacts.  

10.7.1.5         Since the sewage and sludge treatment facilities of the CSTW and the water reclamation facilities for the non-potable use of treated effluent from the CSTW would be installed inside the caverns, there would not be any potential visual impacts due to installation of these facilities. 

10.7.2            Magnitude of Visual Impacts

10.7.2.1         The magnitude of changes during construction and operation phases is assessed based on the viewing distance, compatibility of the project with the surrounding landscape, duration of changes, scale of development, reversibility of change, potential blockage of view as shown in Table 10.9. 

10.7.2.2         During construction, the proposed temporary works at the existing STSTW, the areas at the both sides of Ma On Shan Road and the hillsides of A Kung Kok and along Mui Tsz Lam Road are generally at low level but cover a relatively large area.  The compatibility of the Project during construction phase is considered as medium.  The construction works will last for a few years and the duration of impact would be medium.  The scale of development is considered large as the Project covers large temporary works areas.  All permanent works including site formation constructed during construction phase are considered irreversible.  Generally, there would not be any potential blockage of view during construction. 

10.7.2.3         During the operation, the compatibility of the Project is considered high as there will not be any aboveground structures at STSTW and the proposed facilities at Main Portal Area, Secondary Portal Area, Ventilation Shaft and access road are relatively localised and would fit in well with the surrounding landscape and visual context.  The compatibility of the Project during operation is considered as high.  The duration of impact due to permanent aboveground works is long.  The scale of development is medium as all the proposed permanent works are small scale and localised.  All permanent works during operation phase are considered as irreversible.  Generally, there would not be any potential blockage of view during operation. 

10.7.2.4         It is predicted that there would be large to medium magnitude of impact on VSRs at low level who are immediately close to the Project and adjacent elevated VSRs who have an overview of the Project; and slight to insubstantial magnitude of impact on distant VSRs during construction and operation. 


Table 10.9     Magnitude of Visual Impacts during Construction and Operation

VSR ID.

VSR

Source of Visual Impact

Viewing Distance

(m)

Compatibility of the Project with the Surrounding Landscape

(High/ Medium/ Low)

Duration of Impacts

(Long/ Medium/ Short)

Scale of Development

(Large/ Medium/ Small)

Reversibility of Change

(Yes/ No)

Potential Blockage of View

(Full/ Partial/ Nil)

Magnitude of Change

(Large/ Intermediate/ Small/ Negligible)

Const-ruction

Operat-ion

Const-ruction

Operat-ion

Const-ruction

Operat-ion

Const-ruction

Operat-ion

Const-ruction

Operat-ion

Const-ruction

Operat-ion

R-01

Residents in Chevalier Garden

As listed in Para. 10.7.1

50m

Medium

High

Medium

Long

Large

Medium

No

No

Partial

Partial

Large

Large

R-02

Residents in Pictorial Garden, Garden Vista, Ravana Garden etc.

As listed in Para. 10.7.1

750m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

R-03

Residents in City One

As listed in Para. 10.7.1

1500m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

R-04

Residents in Wo Che Estate

As listed in Para. 10.7.1

2100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

R-05

Residents in Fo Tan including Jubilee Garden and The Palazzo

As listed in Para. 10.7.1

1200m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

R-06

Residents in Royal Ascot

As listed in Para. 10.7.1

700m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

R-07

Residents in Low Rise Private Residential Developments at Kau To Shan including Windsor Park, Kam On Gardens, Greenland Villas, Yucca Villa, Pine Villa, Jade Villa, Windsor Heights, Evergreen Gardens, Double Haven House, Forest Hill, Greenery Villas and Shatin Knoll, etc.

As listed in Para. 10.7.1

300m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

R-08

Residents in Potential Residential Development at Lai Ping Road

As listed in Para. 10.7.1

900m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

R-09

Residents in Ah Kung Kok Fishermen Village

As listed in Para. 10.7.1

100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

R-10

Residents in The Hong Kong Jockey Club Shatin Staff Quarters

As listed in Para. 10.7.1

1600m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

R-11

Residents in Sui Wo Court

As listed in Para. 10.7.1

2000m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

R-12

Residents in Kam Tai Court

As listed in Para. 10.7.1

150m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Large

Large

R-13

Residents in Shek Mun Estate

As listed in Para. 10.7.1

1300m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-01

Occupants in Tsung Tsin Secondary School and Kowloon City Baptist Church Hay Nien Primary School

As listed in Para. 10.7.1

100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

I-02

Occupants in Shatin Hospital, Bradbury Hospice and Cheshire Home

As listed in Para. 10.7.1

250m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

I-03

Occupants in Hyatt Regency Hong Kong

As listed in Para. 10.7.1

200m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

I-04

Occupants in Chinese University of Hong Kong

As listed in Para. 10.7.1

600m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

I-05

Occupants in Hong Kong Science Park

As listed in Para. 10.7.1

1500m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-06

Occupants in Jockey Club Ti-I College

As listed in Para. 10.7.1

1800m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-07

Occupants in Hong Kong Institute of Vocational Education

As listed in Para. 10.7.1

2000m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-08

Occupants in The Neighbourhood Advice-Action Council Harmony Manor

As listed in Para. 10.7.1

100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

I-09

Occupants in Hong Kong Sports Institute

As listed in Para. 10.7.1

1000m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-10

Occupants in Shek Mun Industrial Area

As listed in Para. 10.7.1

1200m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

I-11

Occupants in Shatin Hospital

As listed in Para. 10.7.1

800m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

O-01

Recreational Users in Ma On Shan Promenade

As listed in Para. 10.7.1

50m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

O-02

Recreational Users including cyclists along cycle track in the promenades at the both sides of the Shing Mun River Channel

As listed in Para. 10.7.1

10m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

O-03

Water based recreational users in the waterbodies from Tolo Harbour to Shing Mun River Channel

As listed in Para. 10.7.1

20m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

O-04

Recreational Users in Sha Tin Racecourse and Penfold Park

As listed in Para. 10.7.1

300m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

O-05

Hikers in Walking Trails

As listed in Para. 10.7.1

300m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Small

Small

O-06

Recreational Users Pak Shek Kok Promenade

As listed in Para. 10.7.1

1400m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Negligible

Negligible

T-01

Travellers along Tolo Highways

As listed in Para. 10.7.1

100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

T-02

Travellers along Tate¡¦s Cairn Highways

As listed in Para. 10.7.1

100m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Large

Large

T-03

Passengers on MTR East Rail Line

As listed in Para. 10.7.1

120m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Intermediate

Intermediate

T-04

Travellers along Ma On Shan Road and MTR Ma On Shan Rail

As listed in Para. 10.7.1

10m

Medium

High

Medium

Long

Large

Medium

No

No

Nil

Nil

Large

Large


10.7.3            Significance of Unmitigated Visual Impacts

10.7.3.1         The significance of visual impacts, before the implementation of mitigation measures, in the construction phase and operation phase are assessed in accordance with the methodology set out in Table 10.2 of the Report and described in Table 10.13.

10.7.4            Recommended Photomontage Viewpoints

10.7.4.1         Computer generated photomontages will be prepared to illustrate the potential landscape and visual impact of the Project.  The criteria for the selection of representative viewpoints for photomontages include: -

¡P         the viewpoints which cover the aboveground structure viewed from major public viewpoint represents key VSRs or VSR groups who would be potentially affected by the proposed Project; and

¡P         the viewpoints which shall be able to represent the worst case scenarios and demonstrate the compatibility of the aboveground structures to the adjacent visual context and illustrate the visual effect during Day 1 without mitigation measures, Day 1 with mitigation measures and Year 10 with mitigation measures. 

10.7.4.2         Based on the location of the proposed aboveground structures, proposed viewpoint from key representative VSRs are mapped in Figure No. 60334056/EIA/10.31 and the computer generated photomontages to illustrate the potential landscape and visual impact of the Project is shown in Figure Nos. 60334056/EIA/10.51 to 10.56.  They are described as follow:

¡P         Viewpoint P1 near Tsung Tsin Secondary School and Kowloon City Baptist Church Hay Nien Primary School to illustrate the potential landscape and visual impact due to the works at Main Portal Area; 

¡P         Viewpoint P2 from Ma On Shan Country Trail to illustrate the potential landscape and visual impact due to the works at Secondary Portal Area; 

¡P         Viewpoint P3 near The Neighbourhood Advice-Action Council Harmony Manor to illustrate the potential landscape and visual impact due to the works at the Ventilation Shaft, temporary project specific magazine site and associated access road;

¡P         Viewpoint P4 from Ah Kung Kok Fishermen Village to illustrate the potential landscape and visual impact due to the works at the Main Portal Area; 

¡P         Viewpoint P5 from Waterfront Promenade along Shing Mun River to illustrate the potential landscape and visual impact due to the works at the Main Portal Area from a distant view; and 

¡P         Viewpoint P6 from Tate¡¦s Cairn Highways to illustrate the potential landscape and visual impact due to the works at the Main Portal Area from an elevated highway.  

 

10.8                Landscape and Visual Mitigation Measures

10.8.1.1         The proposed engineering works have been designed to minimise any potential landscape and visual impact as much as possible.  Unavoidably, there would be some potential landscape and visual impact.  Landscape and Visual Mitigation Measures are therefore proposed to alleviate the potential adverse landscape and visual impact.

10.8.1.2         The proposed landscape and visual mitigation measures in the construction and operation are listed in Tables 10.10 and 10.11 below, together with an indication of Funding, Implementation and Maintenance Agencies and illustrated in Figure Nos. 60334056/EIA/10.41 to 10.46.

Table 10.10  Landscape and Visual Mitigation Measures for Construction Phase

ID No.

Landscape and Visual Mitigation Measures

Funding Agency

Implement-action Agency

CM1

Preservation of Existing Vegetation

All the existing Trees to be retained and not to be affected by the Project shall be carefully protected during construction accordance with DEVB TCW No. 7/2015 - Tree Preservation and the latest Guidelines on Tree Preservation during Development issued by GLTM Section of DevB.  Any existing vegetation in landscaped areas and natural terrain not to be affected by the Project shall be carefully preserved. 

 DSD

DSD

CM2

Transplanting of Affected Trees

Trees unavoidably affected by the works shall be transplanted as far as possible in accordance with DEVB TCW No. 7/2015 - Tree Preservation and the latest Guidelines on Tree Transplanting issued by GLTM Section of DevB. 

DSD

DSD

CM3

Compensatory Tree Planting

Any Trees to be felled under the Project shall be compensated in accordance with DEVB TCW No. 7/2015 - Tree Preservation.  For trees to be compensated on slopes, the guidelines for tree planting stipulated in GEO Publication No. 1/2011 will be followed. 

DSD

DSD

CM4

Control of Night-time Lighting Glare

Any lighting provision of the construction works at night shall be carefully control to prevent light overspill to the nearby VSRs and into the sky. 

DSD

DSD

CM5

Erection of Decorative Screen Hoarding

Decorative Hoarding, which is compatible with the surrounding settings, shall be erected during construction to minimise the potential landscape and visual impacts due to the construction works and activities. 

DSD

DSD

CM6

Management of Construction Activities and Facilities

The facilities and activities at works sites and areas, which include site office, temporary storage areas, temporary works etc., shall be carefully managed and controlled on the height, deposition and arrangement to minimise any potential adverse landscape and visual impacts. 

DSD

DSD

CM7

Reinstatement of Temporarily Disturbed Landscape Areas

All hard and soft landscape areas disturbed temporarily during construction due to temporary excavations, temporary works sites and works areas shall be reinstated to equal or better quality, to the satisfaction of the relevant Government Departments.

DSD

DSD

 

Table 10.11  Landscape and Visual Mitigation Measures for Operation Phase

ID No.

Landscape and Visual Mitigation Measures

Funding Agency

Implement-action Agency

Maintenance/ Management Agency

OM1

Tree and Shrub Planting at the Temporary Project Magazine Site after Completion of Engineering Works

The Temporary Project Magazine Site shall be planted with tree and shrub planting after completion of works. 

DSD

DSD

DSD

OM2

Aesthetically pleasing design of Aboveground Structures

The Aboveground Structures of the Project including Tunnel Portals, Administration Buildings, Electrical Substations and Ventilation Shaft in the regard of layouts, forms, materials and finishes shall be sensitively designed so as to blend in the structures to the adjacent landscape and visual context. 

DSD

DSD

DSD

OM3

Aesthetically pleasing design of Highways Structures

Highways Structures proposed shall be sensitively designed in the regard of form, tonal colour and texture so as to minimise any potential adverse landscape and visual impact. 

DSD

DSD

HyD

OM4

Reprovision of Cycle Track

The affected cycle track shall be reprovided after construction on a like to like basis. 

DSD

DSD

HyD

OM5

Provision of Green Roof

Green Roof shall be proposed to enhance the landscape quality of the Aboveground Structures including Administration Buildings and Electrical Substations and mitigate any potential adverse visual impact on adjacent VSRs.

DSD

DSD

DSD

OM6

Provision of Buffer Planting

Buffer Planting shall be provided at the perimeter of the Main and Secondary Portal Areas to screen and soften the proposed Aboveground Structures. 

DSD

DSD

DSD

OM7

Hydroseeding on the disturbed ground surface after demolition works prior to future redevelopment of the existing STSTW

Hydroseeding will be provided as a temporary landscape and visual mitigation measure for disturbed ground surface after demolition of aboveground and underground facilities in the existing STSTW in case the redevelopment of the STSTW site could not commence immediately after the completion of demolition works. 

DSD

DSD

Lands Department

(LandsD) or future development agent in existing STSTW*

OM8

Woodland Mix Planting on Soil Slopes

Woodland Mix Planting, tree whips and/or shrub mix, shall be applied to new soil cut and fill slopes in accordance with technical guidelines set out in GEO Publication No. 1/2011 at the tunnel portals and site formation works for Access Road to Nui Po Shan Ventilation Shaft and Temporary Project Magazine Site. 

DSD

DSD

DSD

* Remarks:    The future development agent has yet to be identified as there is no confirmed planning and schedule for the development of the vacated site. Nevertheless, the arrangement of maintenance/management agencies shall follow the prevailing government practices as given in DEVB TCW No. 6/2015 or its version. 

10.8.1.3         The construction phase mitigation measures listed above shall be implemented as early as possible in order to minimise the landscape impacts in the construction stage.  The operation phase mitigation measures listed above shall be adopted during the detailed design and be built as part of the construction works at the last stage of the construction period so that they are in place at the date of commissioning of the Project.  However, it should be noted that the full effect of the soft landscape mitigation measures would not be appreciated for several years.  Photomontages of the proposed project without and with mitigation measures illustrating the appearance after 10 years of the proposed works are shown in Figure Nos. 60334056/EIA/10.51 to 10.56. 

 

10.9                Residual Impact

10.9.1            Significance of Residual Landscape Impacts

10.9.1.1         The potential significance of the landscape impacts during the construction and operation phases, before and after mitigation, is provided in Table 10.12.  The assessment follows the proposed methodology and assumes that the appropriate mitigation measures identified in Tables 10.10 and 10.11 above would be implemented, and the full effect of the soft landscape mitigation measures would be realised after ten years.

10.9.1.2         Under the proposed decommissioning and demolition works for the existing STSTW, the existing buildings and underground structures will be removed.  Majority of the existing at-grade vegetation will be preserved in-situ.  Green roofs, vertical greening attached to existing buildings and vegetation above existing underground structures and utilities will be removed during demolition.  The magnitude of impact is considered small.  The sensitivity of the Amenity Planting in the Existing STSTW (LR-01) is medium and the resultant unmitigated landscape impact on this LR would be slight during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting and hydroseeding on the disturbed ground surface after demolition works, there would not be any discernible net gain or loss to LR-01 with proposed mitigation measures.  It is predicted that there would be slight residual impact on LR-01 during construction, insubstantial residual impact during day 1 and year 10 of operation. 

10.9.1.3         Under the construction of temporary works at area between A Kung Kok Street and Ma On Shan Road including construction of temporary site access and the temporary stockpiling area, it is estimated that approximately 190 nos. of existing trees and 17,700m2 of vegetation in the Roadside Planting Areas along Ma On Shan Road (LR-07) would be affected during the construction.  Affected trees species include Aleurites moluccana, Bauhinia purpurea, Bombax ceiba, Casuarina equisetifolia, Delonix regia, Ficus microcarpa, Leucaena leucocephala and Melaleuca cajuputi subsp. Cumingiana.  They are generally of medium form and fair amenity value.  The affected trees are in the range of 4-10m high, 3-9m spread and 100-600mm trunk diameter.  The sensitivity of this LR is medium and the magnitude of impact is intermediate.  The resultant unmitigated landscape impact on this LR would be moderate during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, reinstatement of temporarily disturbed landscape areas, there would not be any discernible net gain or loss in area to LR-07 with proposed mitigation measures.  Based on a broad brush estimate, approximate 190 nos. heavy standard trees can be compensated within the reinstated landscape area of this LR.  It is predicted that there would be moderate residual impact during construction, slight residual impact during day 1 of operation and insubstantial residual impact on LR-07 when the proposed compensatory planting and roadside amenity planting become mature during year 10 of the operation. 

10.9.1.4         Based on a broad brush estimate, approximately 638 nos. of existing trees and 59,900m2 existing vegetation will be removed on Slopes of Nui Po Shan (LR-08) for the construction at Main Portal Area, Secondary Portal Area, Ventilation Shaft at Nui Po Shan and associated access road, and site formation for Temporary Project Magazine.  Affected tree species include Acacia confusa, Aporusa dioica, Cleistocalyx operculata, Litchi chinensis, Cratoxylum cochinchinense, Ficus microcarpa, Macaranga tanarius, and Schefflera heptaphylla.  They are generally of medium form and fair to poor amenity value.  Affected trees are in the range of 3-14m high, 3-10m spread and 95-800mm trunk diameter.  The sensitivity of this LR is high and the magnitude of impact is large.  The resultant unmitigated landscape impact on this LR would be substantial during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees and compensatory tree planting, reinstatement of temporarily disturbed landscape areas, tree and shrub planting at the Temporary Project Magazine Site after construction, provision of green roof, buffer planting and woodland mix planting on new soil slopes.  Based on a broad brush estimate, approximately 140 nos. heavy standard trees can be compensated in Temporary Project Magazine Site (within approximate 3,900m2 compensatory woodland mix planting) after Completion of Engineering Works and approximately 10,000 nos. of tree whips  can be compensated on the woodland mix planting areas on new slopes and the reinstatement planting areas (approximately 30,800m2 planting areas) of this LR.  As such, there would be a net permanent loss of 25,200m2 of LR-08 due to the Project.  It is predicted that there would be substantial residual impact during construction, moderate residual impact during day 1 of operation after implementation of landscape works and slight residual impact on LR-08 when the proposed compensatory planting, buffer planting and woodland mix planting become mature during year 10 of the operation. 

10.9.1.5         During construction, approximately 300m of the cycle track connecting the waterfront promenade at Shing Mun River Channel and A Kung Kok Street will be temporarily alienated in order to form a temporary access road connecting to the works area at Area 73.  The sensitivity of this LR is medium and the magnitude of impact is large.  The resultant unmitigated landscape impact on the cycle track would be moderate during construction and operation.  With the implementation of proposed mitigation measures, there would not be any net gain or loss to this landscape resource with proposed mitigation measures.  It is predicted that there would still be moderate residual impact during construction and the residual impact would be reduced to insubstantial after the affected cycle track is reprovided. 

10.9.1.6         Apart from LR-01, LR-07, LR-08 and LR-17, it is predicted that there would not be any discernable change in other LRs identified within the study boundary of the Project.

10.9.1.7         Under the Project, it is anticipated that there would be permanent change in Sha Tin Waterfront Industrial LCA (LCA-01) due to the decommission and demolition of the existing STSTW including clearance of aboveground and underground facilities and associated green roof and vertical greening and associated vegetation during construction.  Majority of existing vegetation at-grade will be retained.  The sensitivity of this LCA is low.  The magnitude of impact is small.  The resultant unmitigated landscape impact on this LCA would be slight during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding, management of construction activities and facilities and hydroseeding on the disturbed ground surface after demolition works, it is predicted that there would be slight residual impact during construction, insubstantial residual impact during day 1 and year 10 of the operation. 

10.9.1.8         It is predicted that there would be a temporary change in Ma On Shan Transportation Corridor LCA (LCA-04) due to the construction of temporary site assess, temporary staff office, stockpiling and associated works during construction phase.  It is estimated that approximate 17,700 m2 of existing vegetation along roadsides in the LCA will be removed during construction.  The magnitude of impact is intermediate.  The sensitivity of this LCA is low.  The resultant unmitigated landscape impact on this LCA would be moderate during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding, management of construction activities and facilities, reinstatement of temporarily disturbed landscape areas, reprovisioning of the affected cycle track and provision of roadside amenity planting, it is predicted that there would be moderate residual impact during construction, slight residual impact during day 1 of operation and insubstantial residual impact on LCA-04 when the proposed compensatory planting and roadside amenity planting become mature during year 10 of the operation. 

10.9.1.9         It is predicted that there would be a temporary change in A Kung Kok and Tai Shui Hang Miscellaneous Urban Fringe LCA (LCA-05) due to the construction activities at Main Portal Area and Secondary Portal and associated temporary works and permanent change in landscape character due to the operation of the Project.  It is estimated that approximate 37,400m2 woodland on the hillside slope at Nui Po Shan will be lost during construction.  The magnitude of impact is large. The sensitivity of this LCA is high.  The resultant unmitigated landscape impact on this LCA would be substantial during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding, management of construction activities and facilities, reinstatement of temporarily disturbed landscape areas, aesthetically pleasing design of aboveground structures, provision of green roof on aboveground structures, provision of buffer planting and woodland mix planting on new soil slopes, it is predicted that there would be substantial residual impact during construction, moderate residual impact during day 1 of operation after implementation of landscape works and slight residual impact on LCA-05 when the proposed compensatory planting, buffer planting and woodland mix planting become mature during year 10 of the operation. 

10.9.1.10      It is predicted that there would be a temporary change in A Kung Kok Settled Valley LCA (LCA-07) due to the construction of Ventilation Shaft, temporary Magazine Site and associated access road and permanent change in the landscape character due to the operation of the Project.  It is estimated that approximate 22,500m2 woodland on the valley of Nui Po Shan will be lost during construction.  The magnitude of impact is large. The sensitivity of this LCA is high.  The resultant unmitigated landscape impact on this LCA would be substantial during construction and operation.  With the implementation of proposed mitigation measures, including preservation of existing vegetation, transplanting of affected trees, compensatory tree planting, control of night-time lighting glare, erection of decorative screen hoarding, management of construction activities and facilities, reinstatement of temporarily disturbed landscape areas, tree and shrub planting of the Temporary Magazine Site after construction, aesthetically pleasing design of the Ventilation Shaft and retaining structures for the access road, provision woodland mix planting on new soil slopes, it is predicted that there would be substantial residual impact during construction, moderate residual impact during day 1 of operation after implementation of landscape works and slight residual impact on LCA-07 when the proposed compensatory planting, tree and shrub planting on the Temporary Magazine Site and woodland mix planting on new soil slopes become mature during year 10 of the operation. 

10.9.1.11      Apart from LCA-01, LCA-04, LCA-05 and LCA-07, it is predicted that there would not be any discernable change in other LCAs identified within the study boundary of the Project.


Table 10.12  Significance of Landscape Impacts during Construction and Operation Phases

ID  No.

Landscape Resource / Character Areas

Sensitivity

(Low, Medium, High)

Magnitude of Change (Negligible, Small, Intermediate, Large)

Impact Significance before Mitigation (Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Significance of Residual Impact

(Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

Day 1

Year 10

Landscape Resources

LR-01

Amenity Planting in the Existing STSTW

Medium

Medium

Small

Small

Slight

Slight

CM1, CM2, CM3, OM7

Slight

Insubstantial

Insubstantial

LR-02

Waterbodies in Shing Mun River and Sha Tin Hoi

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-03

Landscape Areas in Sha Tin Racecourse

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-04

Ma On Shan Promenade

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-05

Shing Mun River Promenade

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-06

Landscape Areas within Kam Tai Court

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-07

Roadside Planting Areas along Ma On Shan Road

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM7

Moderate

Slight

Insubstantial

LR-08

Woodland on Slopes of Nui Po Shan

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM7, OM1, OM5, OM6, OM8

Substantial

Moderate

Slight

LR-09

Landscape Areas within Chevalier Garden

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-10

Roadside Planting Areas along Tolo Highways

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-11

Woodland on Slopes of Kau To Shan

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-12

Landscape Areas at Ah Kung Kok Fishermen Village

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-13

Stream Running along Mui Tsz Lam Road

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-14

Landscape Areas in Shatin Hospital

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-15

Landscape Areas in Hyatt Regency Hong Kong, Sha Tin

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-16

Landscape Areas in Marine Outer Waters District HQ and WSD Salt Water Pumping Station

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LR-17

Cycle Track connecting the waterfront promenade and A Kung Kok Street

Medium

Medium

Large

Large

Moderate

Moderate

CM7 and OM4

Moderate

Insubstantial

Insubstantial

Landscape Character Area

LCA-01

Sha Tin Waterfront Industrial LCA

Low

Low

Small

Small

Slight

Slight

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM7

Slight

Insubstantial

Insubstantial

LCA-02

Sha Tin Hoi and Shing Mun River Inshore Water LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-03

Ma On Shan Waterfront Residential LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-04

Ma On Shan Transportation Corridor LCA

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM4

Moderate

Slight

Insubstantial

LCA-05

A Kung Kok and Tai Shui Hang Miscellaneous Urban Fringe LCA

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM2, OM5, OM6, OM8

Substantial

Moderate

Slight

LCA-06

Nui Po Shan Upland and Hillside LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-07

A Kung Kok Settled Valley LCA

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM8

Substantial

Moderate

Slight

LCA-08

Sha Tin Racecourse LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-09

Ma Liu Shui Transportation Corridor LCA

Low

Low

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-10

Kau To Shan Residential Urban Fringe LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-11

Tai Shui Hang Upland and Hillside LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-12

Tai Shui Hang Settled Valley LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

LCA-13

Nui Po Shan Peak LCA

High

High

Negligible

Negligible

Insubstantial

Insubstantial

Not Required

Insubstantial

Insubstantial

Insubstantial

 


10.9.2            Significance of Residual Visual Impacts

10.9.2.1         The potential significance of the Visual impacts during the construction and operation phases, before and after mitigation, is provided in Table 10.13.  The assessment followed the proposed methodology and assumed that the appropriate mitigation measures identified in Tables 10.10 and 10.11 above would be implemented, and the full effect of the visual mitigation measures should be realised after ten years. 

10.9.2.2         Photomontages illustrating the potential visual impact during operation with and without mitigation measures from representative VSRs due to the Project are shown in Figure Nos. 60334056/EIA/10.51 to 10.56.  The potential visual impacts are assessed and summarised as below: 

¡P         Viewpoint P1 near Tsung Tsin Secondary School and Kowloon City Baptist Church Hay Nien Primary School (I-01) which is an at-grade view approximately 100m form the Main Portal Area representing the potential visual impact on the VSRs to the north.  The layout and massing of the above ground structures at the Main Portal Area have been carefully planned and designed.  A variation of building profile is proposed with the taller Ventilation Building at the hillside and lower Administration Building and Electrical Substation near the development edge.  The step down profile can avoid the wall effect and fits in well with the natural slope profile of the hillside. With the implementation of proposed mitigation measures which include aesthetically pleasing architectural design of the aboveground structures at Main Portal Area, provision of green roof on administration and ventilation buildings, provision of buffer planting at the edge of the Main Portal Area and woodland mix planting on the soil slopes of the portals, it is considered that the proposed facilities at the Main Portal Area are visually compatible with the adjacent hillside landscape and visual setting of the area. 

¡P         Viewpoint P2 is taken from the Ma On Shan Country Trail (O-05) which is approximately 300m from the Secondary Portal Area.  A step down building profile with the tallest Ventilation Building at the hillside and lower Electrical Substation near the development edge is proposed.  The step down building profile can avoid the wall effect and fits in well with the natural slope profile of the hillside.  With the implementation of proposed mitigation measures which include aesthetically pleasing architectural design of the aboveground structures at Secondary Portal Area, provision of green roof on ventilation building, provision of buffer planting at the edge of the Secondary Portal Area and woodland mix planting on the soil slopes of the portals, it is considered that the proposed facilities at the Secondary Portal Area are visually compatible with the adjacent hillside landscape and visual setting of the area. 

¡P         Viewpoint P3 from The Neighbourhood Advice-Action Council Harmony Manor (I-08) to illustrate the potential visual impact due to the works at the Ventilation Shaft and associated access road.  The access road has been designed to follow the existing topography of the Nui Po Shan to minimise extent of slope works and retaining structures.  It is anticipated that there would be potential adverse visual impact due to the loss of existing vegetation and the creation of new retaining structures on Nui Po Shan.  With the implementation of proposed mitigation measures which include application of texture and finishes to the retaining wall and ventilation shafts, provision of buffer planting along the retaining structures of the access road and the Ventilation Shaft, provision of woodland mix planting on soil slopes, it is considered that the proposed Ventilation Shaft and associated access road are visually compatible with the adjacent hillside landscape and visual setting of the area.

¡P         Viewpoint P4 from Ah Kung Kok Fishermen Village which is an at-grade view approximately 100m away from the proposed Administration Building representing the potential visual impact on the Residents in Ah Kung Kok Fishermen Village (R-09).  The layout and massing of the Main Portal Area have been carefully planned and designed.  A step down building profile is proposed to match the slope profile of the existing natural terrain.  With the implementation of proposed mitigation measures which include aesthetically pleasing architectural design of the aboveground structures at Main Portal Area, provision of green roof on administration and ventilation building, provision of buffer planting at the edge of the Main Portal Area and woodland mix planting on the soil slopes of the portals, it is considered that the proposed Administration Building is visually compatible with the adjacent hillside landscape and visual setting of the area.   

¡P         Viewpoint P5 from Waterfront Promenade along Shing Mun River which is an at-grade view approximately 700m away from the Main Portal Area representing potential visual impact on Recreational Users along Shing Mun River (O-02) and other VSRs from the south-east of the site.  The proposed building profile fits in well with the adjacent natural slope profile.  With the implementation of proposed mitigation measures which include aesthetically pleasing architectural design of the aboveground structures at Main Portal Area, provision of green roof on administration and ventilation building, provision of buffer planting at the edge of the Main Portal Area and woodland mix planting on the soil slopes of the portals, it is considered that the proposed facilities at the Main Portal Area are visually compatible with the adjacent hillside landscape and visual setting of the area. 

¡P         Viewpoint P6 from Tate's Cairn Highways which is an elevated view approximately 200m away from the Main Portal Area representing potential visual impact on Travellers along Tate's Cairn Highways (T-02) and other distant VSRs from the west of the site.  The proposed building profile has preserved the view to the ridge line of Nui Po Shan behind.  With the implementation of proposed mitigation measures which include aesthetically pleasing architectural design of the aboveground structures at Main Portal Area, provision of green roof on administration and ventilation buildings, provision of buffer planting at the edge of the Main Portal Area and woodland mix planting on the soil slopes of the portals, it is considered that the proposed facilities at the Main Portal Area are visually compatible with the adjacent hillside landscape and visual setting of the area. 

10.9.2.3         As a whole, there would be moderate residual impact during construction and day 1 of operation on immediately adjacent elevated VSRs R-01 and R-12 who have full overview of the project.  It is predicted the residual impact on these VSRs would be reduced to slight when the proposed landscape works become mature during year 10 of operation.  

10.9.2.4         There would be slight residual impact during construction and day 1 of operation on elevated VSRs further away and VSRs at low level who are close to the Project including R-02, R-06 R-07, R-08, R-09, I-01, I-02, I-03, I-08, O-01, O-02, O-03, O-04, O-05, T-01, T-02, T-03, and T-04.  It is predicted the residual impact on these VSRs would be reduced to insubstantial when the proposed landscape works become mature during year 10 of operation.  

10.9.2.5         It is predicted that there would be insubstantial residual visual impact during construction and operation on long distant VSRs including R-03, R-04, R-05, R-10, R-11, R-13, I-04, I-05, I-06, I-07, I-09, I-10, I-11 and O-06. 


Table 10.13  Significance of Visual Impacts during Construction and Operation Phases

ID. No.

Key VSRs

Receptor Sensitivity

(Low, Medium, High)

Magnitude of Change

(Negligible, Small, Intermediate, Large)

Impact Significance Threshold BEFORE Mitigation              (Insubstantial, Slight, Moderate, Substantial)

Recommended Mitigation Measures

Residual Impact Significance Threshold   AFTER Mitigation                            (Insubstantial, Slight, Moderate, Substantial)

Construction

Operation

Construction

Operation

Construction

Operation

Construction

Operation

DAY 1

YEAR 10

R-01

Residents in Chevalier Garden

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Moderate

Moderate

Slight

R-02

Residents in Pictorial Garden, Garden Vista, Ravana Garden etc.

High

High

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

R-03

Residents in City One

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

R-04

Residents in Wo Che Estate

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

R-05

Residents in Fo Tan including Jubilee Garden and The Palazzo

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

R-06

Residents in Royal Ascot

High

High

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

R-07

Residents in Low Rise Private Residential Developments at Kau To Shan including Windsor Park, Kam On Gardens, Greenland Villas, Yucca Villa, Pine Villa, Jade Villa, Windsor Heights, Evergreen Gardens, Double Haven House, Forest Hill, Greenery Villas and Shatin Knoll, etc.

High

High

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

R-08

Residents in Potential Residential Development at Lai Ping Road

High

High

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

R-09

Residents in Ah Kung Kok Fishermen Village

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

R-10

Residents in the Hong Kong Jockey Club Shatin Staff Quarters

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

R-11

Residents in Sui Wo Court

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

R-12

Residents in Kam Tai Court

High

High

Large

Large

Substantial

Substantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Moderate

Moderate

Slight

R13

Residents in Shek Mun Estate

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-01

Occupants in Tsung Tsin Secondary School and Kowloon City Baptist Church Hay Nien Primary School

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

I-02

Occupants in Shatin Hospital, Bradbury Hospice and Cheshire Home

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

I-03

Occupants in Hyatt Regency Hong Kong

Medium

Medium

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

I-04

Occupants in Chinese University of Hong Kong

Medium

Medium

Small

Small

Slight

Slight

CM1, CM2,  CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-05

Occupants in Hong Kong Science Park

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-06

Occupants in Jockey Club Ti-I College

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-07

Occupants in Hong Kong Institute of Vocational Education

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-08

Occupants in the Neighbourhood Advice-Action Council Harmony Manor

Medium

Medium

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

I-09

Occupants in Hong Kong Sports Institute

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-10

Occupants in Shek Mun Industrial Area

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

I-11

Occupants in Shatin Hospital

Medium

Medium

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

O-01

Recreational Users in Ma On Shan Promenade

High

High

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

O-02

Recreational Users including cyclists along cycle track in the promenades at the both sides of the Shing Mun River Channel

High

High

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

O-03

Water based recreational users in the waterbodies from Tolo Harbour to Shing Mun River Channel

High

High

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

O-04

Recreational Users in Sha Tin Racecourse and Penfold Park

High

High

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

O-05

Hikers in Walking Trails

High

High

Small

Small

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

O-06

Recreational Users Pak Shek Kok Promenade

High

High

Negligible

Negligible

Insubstantial

Insubstantial

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Insubstantial

Insubstantial

Insubstantial

T-01

Travellers along Tolo Highways

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

T-02

Travellers along Tate¡¦s Cairn Highways

Low

Low

Large

Large

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

T-03

Passengers on MTR East Rail Line

Low

Low

Intermediate

Intermediate

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

T-04

Travellers along Ma On Shan Road and MTR Ma On Shan Rail

Low

Low

Large

Large

Moderate

Moderate

CM1, CM2, CM3, CM4, CM5, CM6, CM7, OM1, OM2, OM3, OM4, OM5, OM6, OM7, OM8

Slight

Slight

Insubstantial

 


10.10              Environmental Monitoring and Audit

10.10.1.1      The detailed landscape and engineering design of the Project shall be undertaken so as to ensure compliance with the landscape and visual mitigation measures described in Section 10.8.

10.10.1.2      A baseline review shall be undertaken at the commencement of the construction contracts to update the status of landscape resources, character areas and VSRs.

10.10.1.3      Implementation of the recommended mitigation measures would be regularly audited during construction phase.  Details of EM&A requirement are discussed in the separate EM&A Manual.

 

10.11              Conclusion

10.11.1.1      It is considered that the residual landscape and visual impact is acceptable with mitigation measures implemented during construction and operation phases.  

 

<End of Section 10>