Page
1.2 Designated
Projects under EIAO
1.4 Objectives
of this EIA Study
1.5 Structure
of the EIA Report
¡P
DP1 ¡V |
Sewage
treatment works with an installed capacity of more than 15,000 m3
per day under Item F.1 in Schedule 2 Part I; |
¡P
DP2 ¡V |
Sewage treatment works under Item F.2 in Schedule 2
Part I--- ¡±
With an installed
capacity of more than 5,000 m3 per day; and ¡±
A boundary of
which is less than 200m from the nearest boundary of an existing or planned
residential area, educational institution and health care institution. |
¡P
DP3 ¡V |
An
activity for the reuse of treated sewage effluent from a treatment plant
under Item F.4 in Schedule 2 Part I; |
¡P
DP4 ¡V |
Underground
rock caverns under Item Q.2 in Schedule 2 Part I; |
¡P
DP5 ¡V |
An explosives depot in a stand‑alone, purpose built building under Item K.10 in
Schedule 2 Part I; and |
¡P
DP6 ¡V |
Decommissioning of an explosives depot under Item 11
in Schedule 2 Part II. |
¡P the acceptability of potential environmental consequences that are likely to arise as a result of the Project;
¡P the conditions and requirements for the design, construction and operation of the Project and related activities to mitigate against potential environmental consequences; and
¡P the acceptability of residual impacts after the proposed mitigation measures are implemented.
(i) to describe the Project and associated works together with the requirements, environmental benefits and dis-benefits for carrying out the Project;
(ii) to identify and describe the elements of the community and environment likely to be affected by the Project and/or likely to cause potential impacts to the Project, including both the natural and man-made environment and the associated environmental constraints;
(iii) to provide information on the consideration of alternatives options of the location, layout, design, layout of the Project and the construction methods with a view to avoiding and minimising potential environmental impacts to environmentally sensitive areas and sensitive uses; to compare the environmental benefits and dis-benefits of different options; to provide reasons for selecting the preferred option(s) and to describe the part of environmental factors played in the selection of the preferred option(s);
(iv) to identify and quantify emission sources (including odour, air quality, noise, water quality and waste, etc. as appropriate) and determine the significance of impacts on sensitive receivers and potential affected uses;
(v) to identify and quantify any potential loss or damage and other potential impacts to fisheries, flora, fauna and natural habitats;
(vi) to identify and quantify waste management requirements and to propose measures to mitigate impacts;
(vii) to identify any negative impacts on sites of cultural heritage and to propose measures to mitigate these impacts;
(viii) to identify any potential landscape and visual impacts and to propose measures to mitigate these impacts;
(ix) to propose the provision of infrastructures or mitigation measures to minimise pollution, environmental disturbance and nuisance during construction and operation of the Project including decommissioning and demolition of the existing STSTW and related activities;
(x) to investigate the feasibility, practicability, effectiveness and implications of the proposed mitigation measures;
(xi) to identify, predict and evaluate the residual environmental impacts (i.e. after practicable mitigation) and the cumulative effects expected to arise during the construction and operation of the Project and related activities in relation to the sensitive receivers and potential affected uses;
(xii) to identify, assess and specify methods, measures and standards to be included in the detailed design, construction and operation of the Project and related activities and which are necessary to mitigate these residual environmental impacts and cumulative effects and reduce them to acceptable levels;
(xiii) to investigate the extent of the secondary environmental impacts that may arise from the proposed mitigation measures and to identify constraints associated with the mitigation measures recommended in the EIA study, as well as the provision of any necessary modification;
(xiv) to design and specify environmental monitoring and audit (EM&A) requirements to check the effective implementation of the recommended environmental protection and pollution control measures; and
(xv) to identify any additional studies necessary to implement the mitigation measures or monitoring and proposals recommended in the EIA report.
¡P Section 3: Air Quality Impact
¡P Section 4: Noise Impact
¡P Section 5: Water Quality Impact
¡P Section 6: Land Contamination
¡P Section 7: Hazard to Life
¡P Section 8: Ecological Impact (Terrestrial and Marine)
¡P Section 9: Fisheries Impact
¡P Section 10: Landscape and Visual Impact
¡P Section 11: Cultural Heritage Impact
¡P Section 12: Waste Management Implications
¡P Section 13: Health Impact
¡P Volume 1 of 4 ¡V Main Text (This booklet)
¡P Volume 2 of 4 ¡V Figures
¡P Volume 3 of 4 ¡V Appendices (Part 1)
¡P Volume 4 of 4 ¡V Appendices (Part 2)
<End of Section 1>