TABLE OF CONTENTS

Page

14           Environmental Monitoring and Audit (EM&A) Requirements. 14-1

14.1        Introduction. 14-1

14.2        Air Quality Impact 14-1

14.3        Noise Impact 14-1

14.4        Water Quality Impact 14-2

14.5        Land Contamination. 14-3

14.6        Hazard to Life. 14-4

14.7        Ecological Impact (Terrestrial and Marine) 14-4

14.8        Fisheries Impact 14-5

14.9        Landscape and Visual Impact 14-6

14.10     Cultural Heritage Impact 14-7

14.11     Waste Management Implications. 14-7

14.12     Health Impact 14-8


 


14                   Environmental Monitoring and Audit (EM&A) Requirements

14.1                Introduction

14.1.1.1         This section further elaborates the requirements of EM&A for the construction and operation phases of the Project and associated works, based on the assessment results of the various environmental issues.

14.1.1.2         The purpose of the EM&A programme is to ascertain and verify the assumptions implicit to, and accuracy of, EIA study predictions. The EM&A programme includes the scope of the EM&A requirements for the Project to ensure compliance with the EIA study recommendations, to assess the effectiveness of the recommended mitigation measures and to identify any further need for additional mitigation measures or remedial action.

14.1.1.3         Methodology and requirement of monitoring work are detailed in a standalone EM&A Manual.

 

14.2                Air Quality Impact

14.2.1            Construction Phase

14.2.1.1         With the implementation of the proposed dust suppression measures stipulated in the Air Pollution Control (Construction Dust) Regulation, good site practices and proposed mitigation measures on the work sites, no adverse dust impact would be expected at the ASRs in the vicinity of the Project.  Dust monitoring and site audit programme during construction phase of the Project have been recommended in EM&A Manual to ensure that the mitigation measures would be properly implemented.

14.2.2            Operation Phase

14.2.2.1         Since no adverse operational air quality impact would be expected, no monitoring and audit is required during operation phase. However, a commissioning test on deodorisers is recommended to ensure the effectiveness of deodorization treatment.

 

14.3                Noise Impact

14.3.1            Construction Phase

14.3.1.1         The EIA study of the Project concluded that with proper implementation of practicable mitigation measures, including use of quiet construction plant, movable noise barriers, acoustic mats, and limitation of the number of on-time operating PME, no adverse noise impact would be expected. An EM&A programme is recommended to be established according to the expected occurrence of noisy activities.  All the recommended mitigation measures for daytime normal working activities should be incorporated into the EM&A programme for implementation during construction.  Details of the EM&A requirements are provided in the EM&A Manual.

14.3.1.2         For the temporary modification works at the merging point of Ma On Shan Road and temporary access haul road, the re-provision of 220m length noise barrier with 10mPD on temporary access haul road to replace the existing 150m length noise barrier with 9.2mPD to 10mPD on Ma On Sha Road would pose negligible difference in the overall traffic noise level at the sensitive facades in the vicinity.  Once the construction work is completed, the noise barrier on the concerned road section of Ma On Shan Road would be re-installed according to the existing configuration.  Therefore, no monitoring and audit is required.

14.3.2            Operation Phase

14.3.2.1         The assessment has indicated that the fixed plant noise from ventilation shaft, cooling tower at the administration building, ventilation fan for chiller plant room and ventilation buildings of the CSTW would comply with the EIAO-TM standards.  Having said that, commissioning tests for these fixed plant noise sources during the testing and commissioning stage are recommended to verify the compliance of the EIAO-TM criteria.

 

14.4                Water Quality Impact

14.4.1            Land-based Construction

14.4.1.1         The potential water quality impact from land-based construction works can be controlled by the recommended mitigation measures.  No water quality monitoring specific to the land-based construction works is thus proposed.  However, regular site inspections should be undertaken during the construction phase to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.  Details of the EM&A programme are presented in the standalone EM&A Manual. 

14.4.2            Effluent Discharge under Normal THEES Operation, After Commissioning of this Project

14.4.2.1         Under normal operation of THEES, the effluent from the CSTW and TPSTW would be transported to the Victoria Harbour WCZ for discharge into the KTN (or called Kai Tak River after completion of reconstruction and upgrading works).  A 3-month water quality monitoring programme is proposed for KTN at a frequency of once per month after the commissioning of this Project.  The monitoring results should be compared with the routine river water quality monitoring data collected by EPD to verify whether there is any potential water quality impact at KTN as compared to that before the implementation of this Project.  In case adverse impact on KTN is identified from the monitoring results, the operating conditions of the treatment and THEES system should be investigated.  In case adverse impact on KTN is identified from this Project with reference to the effluent and water quality monitoring results, the operating conditions of the treatment and THEES system should be investigated, and DSD should extend the water quality monitoring programme for at least three months or as agreed by the Director of Environmental Protection.  Details of the monitoring programme are provided in the standalone EM&A Manual.

14.4.2.2         Monitoring of the treated effluent quality from the relocated STSTW should also be carried out in accordance with the WPCO license to ensure that the effluent quality would comply with the design standards, which is under the ambit of RO of EPD.

14.4.3            THEES Maintenance Discharge from CSTW and TPSTW to Tolo Harbour

14.4.3.1         Maintenance of the THEES tunnel is required under the existing practice to ensure proper functioning and integrity of the tunnel.  During the inspection or maintenance of the THEES tunnel, temporary suspension of the normal THEES operation with treated effluent bypasses into the Tolo Harbour is unavoidable to provide a safe and dry working zone.  Thus, the necessity of effluent bypass to Tolo Harbour during the THEES maintenance is not induced by this Project.

14.4.3.2         Marine water quality monitoring is recommended in Tolo Harbour for THEES maintenance during both construction and operational phases of this Project.  A seven-month baseline monitoring programme covering the period from June to December (outside the algae blooming season) is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points.  In case of THEES maintenance during the construction and operational phases of this Project, marine water quality in Tolo Harbour should be monitored at a frequency of 3 times per week throughout the maintenance period until the baseline water quality is restored or at least 1 month after termination of the effluent bypass (whichever is longer).

14.4.3.3         The monitoring programme for THEES maintenance during the construction and operational phases of this Project as discussed above shall continue in the first 3 years after commissioning of this Project.  After 3 years of post-Project commission period, a review shall be conducted by the Project Proponent to determine whether such monitoring shall be continued. The review results shall be submitted to EPD, AFCD, WSD and other relevant parties. Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD. Details of the monitoring programme and an event and action plan for the THEES maintenance are provided in the standalone EM&A Manual.

14.4.4            Emergency Discharge from CSTW to Tolo Harbour

14.4.4.1         Emergency discharges from the Project would be the consequence of complete pump failure, interruption of the electrical power supply or failure of treatment units.  To provide a mechanism to minimise the impact of emergency discharges and facilitate subsequent management of any emergency, a contingency plan has been formulated to set out the emergency response procedure and actions to be followed in case of equipment or sewage treatment works failure.  The existing contingency plan is attached in Appendix 5.07.  The plant operators of CSTW should carry out necessary follow-up actions according to the procedures of this existing contingency plan to minimise any impact on the identified WSRs due to emergency bypass.

14.4.4.2         Marine water quality monitoring is recommended in Tolo Harbour for emergency discharge during operational phase of this Project.  A one-year baseline monitoring programme covering both dry and wet seasons is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points.  In case of emergency discharge during the operational phase of this Project, marine water quality in Tolo Harbour should be monitored daily throughout the emergency discharge period until the baseline water quality is restored or at least 2 weeks after termination of the discharge (whichever is longer). 

14.4.4.3         The monitoring programme for emergency discharge during the operational phase of this Project as discussed above shall continue in the first 3 years after commissioning of this Project. After 3 years of post-Project commission period, a review shall be conducted by DSD to determine whether such monitoring shall be continued. The review results shall be submitted to EPD, AFCD, WSD and other relevant parties. Any amendment on the monitoring programme shall be agreed by EPD AFCD and WSD. Details of the monitoring programme and an event and action plan for the emergency discharge are provided in the standalone EM&A Manual.

 

14.5                Land Contamination

14.5.1.1         Any environmental monitoring in relation to land remediation is not required.  However, regular site audit during construction phase is required to ensure the implementation of proposed mitigation measures effectively.

 

14.6                Hazard to Life

14.6.1.1         Blasting activities regarding storage, transport and use of explosives should be supervised and audited by competent site staff to ensure strict compliance with the blasting permit conditions. 

 

14.7                Ecological Impact (Terrestrial and Marine)

14.7.1            Terrestrial Ecology

14.7.1.1         Recommended mitigation measures proposed in the Section 8.8 (e.g. avoidance of stream and riparian habitats; control of site runoff, reduction in glare / lighting) should be monitored and audited monthly by local ecologist(s) with at least 10 years relevant experience throughout the construction phase to ensure proper implementation.

14.7.1.2         All flora species of conservation importance (e.g. Cibotium barometz, Canthium dicoccum, and Peristylus tentaculatus) should be protected as far as practicable. As a mitigation measure, all the unavoidably affected individuals should be preserved on site, or transplanted to nearby suitable habitat(s) prior to the commencement of site clearance as a last resort.  A Detailed Vegetation Survey should be conducted by a suitably qualified botanist / ecologist to identify and record the affected individuals prior to the commencement of any site clearance works.  A Protection and Transplantation Proposal including the subsequent monitoring visit for the affected individuals should be prepared and conducted by a suitably qualified local ecologist / horticulturist with at least 10 years relevant experience.  The Proposal should be submitted for approval from EPD at least one month before works commencement.  

14.7.1.3         Compensatory planting would be provided within the works area, including the main portal, secondary portal and along access road to compensate for the affected woodland habitat.  A detailed Woodland Compensation Plan should be prepared by local ecologist / botanist with at least 10 years relevant experience to form the basis of the proposed compensatory planting.  The Woodland Compensation Plan should include implementation details, management requirement, as well as monitoring requirements (e.g. frequency and parameters) of the compensatory planting area.  Upon completion of compensatory planting, monitoring by local ecologist / botanist with at least 10 years relevant experience is recommended.  The monitoring frequency should be monthly within the first year after planting.  Parameters, such as health condition and survival rate of the plant, presence of weedy plant, should be monitored.  Maintenance works (e.g. irrigation, weeding, pruning, control of pests and disease, replacement planting, repair of damage, etc.) should also be conducted as necessary.  The Woodland Compensation Plan should be submitted for approval from EPD at least three months before commencement of compensatory woodland planting.

14.7.1.4         It is anticipated that the construction of rock caverns would not have adverse impacts on groundwater in Nui Po Shan.  Nonetheless, precautionary measures should be taken in cavern design and construction to minimize the potential impacts from the change in groundwater level.  Surface water level or groundwater level near the caverns will be closely monitored during the construction and operation stage. 

14.7.2            Marine Ecology

14.7.2.1         As described in Section 5 of EIA Report, monitoring of water quality parameters would be required to ensure the effectiveness of the mitigation measures.

14.7.2.2         The potential water quality impact from the land-based construction works can be controlled by the recommended mitigation measures.  Regular site inspections should be undertaken during the construction phase to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.  Details of the EM&A programme are presented in Section 4 of the EM&A Manual. 

14.7.2.3         During normal plant / THEES operation, monitoring of the treated effluent quality from the CSTW should be carried out in accordance with the WPCO license to ensure that the effluent quality would comply with the design standards, which is under the ambit of RO of EPD.  

14.7.2.4         Marine water quality monitoring is recommended in Tolo Harbour for THEES maintenance during both construction and operational phases of this Project.  Marine water quality parameters such as SS, BOD, E.coli, chlorophyll-a, TIN, UIA and NH3-N should be monitored.  A seven-month baseline monitoring programme covering the period from June to December (outside the algae blooming season) is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points.  In case of THEES maintenance during the construction and operational phases of this Project, marine water quality in Tolo Harbour should be monitored at a frequency of 3 times per week throughout the maintenance period until the baseline water quality is restored or at least 1 month after termination of the effluent bypass (whichever is longer).

14.7.2.5         The monitoring programme for THEES maintenance during the construction and operational phase of this Project as discussed above shall continue in the first 3 years after commissioning of this Project.  After 3 years of post-Project commission period, a review shall be conducted by DSD to determine whether such monitoring shall be continued.  The review results shall be submitted to EPD, AFCD, WSD and other relevant parties.  Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD.  Details of the monitoring programme and an event and action plan for the THEES maintenance are provided in Section 4 of the EM&A Manual.

14.7.2.6         Marine water quality monitoring is also recommended in Tolo Harbour for emergency discharge during operational phase of this Project. Marine water quality parameters such as SS, BOD, E.coli, chlorophyll-a, TIN, UIA and NH3-N should be monitored. A one-year baseline monitoring programme covering both dry and wet seasons is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points. In case of emergency discharge during the operational phase of this Project, marine water quality in Tolo Harbour should be monitored daily throughout the maintenance period until the baseline water quality is restored or at least 2 weeks after termination of the discharge (whichever is longer).

14.7.2.7         The monitoring programme for emergency discharge during the operational phase of this Project as discussed above shall continue in the first 3 years after commissioning of this Project. After 3 years of post-Project commission period, a review shall be conducted by DSD to determine whether such monitoring shall be continued. The review results shall be submitted to EPD, AFCD, WSD and other relevant parties. Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD. Details of the monitoring programme and an event and action plan for the emergency discharge are provided in Section 4 of the EM&A Manual.

 

14.8                Fisheries Impact

14.8.1.1         No unacceptable residual fisheries impact is expected from the Project.  No monitoring program specific for fisheries is required.  However, monitoring of water quality parameters would be required to ensure the effectiveness of the mitigation measures.

14.8.1.2         The potential water quality impact from the land-based construction works can be controlled by the recommended mitigation measures.  Regular site inspections should be undertaken during the construction phase to inspect the construction activities and works areas in order to ensure the recommended mitigation measures are properly implemented.  Details of the EM&A programme are presented in Section 4 of the EM&A Manual. 

14.8.1.3         During normal plant / THEES operation, monitoring of the treated effluent quality from the CSTW should be carried out in accordance with the WPCO license to ensure that the effluent quality would comply with the design standards, which is under the ambit of RO of EPD.  

14.8.1.4         Marine water quality monitoring is recommended in Tolo Harbour for THEES maintenance during both construction and operational phases of this Project.  Marine water quality parameters such as SS, BOD, E.coli, chlorophyll-a, TIN, UIA and NH3-N should be monitored.  A seven-month baseline monitoring programme covering the period from June to December (outside the algae blooming season) is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points.  In case of THEES maintenance during the construction and operational phases of this Project, marine water quality in Tolo Harbour should be monitored at a frequency of 3 times per week throughout the maintenance period until the baseline water quality is restored or at least 1 month after termination of the effluent bypass (whichever is longer).

14.8.1.5         The monitoring programme for THEES maintenance during the construction and operational phase of this Project as discussed above shall continue in the first 3 years after commissioning of this Project.  After 3 years of post-Project commission period, a review shall be conducted by DSD to determine whether such monitoring shall be continued.  The review results shall be submitted to EPD, AFCD, WSD and other relevant parties.  Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD.  Details of the monitoring programme and an event and action plan for the THEES maintenance are provided in Section 4 of the EM&A Manual.

14.8.1.6         Marine water quality monitoring is also recommended in Tolo Harbour for emergency discharge during operational phase of this Project. Marine water quality parameters such as SS, BOD, E.coli, chlorophyll-a, TIN, UIA and NH3-N should be monitored. A one-year baseline monitoring programme covering both dry and wet seasons is proposed at a frequency of twice per month to establish the baseline water quality conditions at selected monitoring points. In case of emergency discharge during the operational phase of this Project, marine water quality in Tolo Harbour should be monitored daily throughout the maintenance period until the baseline water quality is restored or at least 2 weeks after termination of the discharge (whichever is longer).

14.8.1.7         The monitoring programme for emergency discharge during the operational phase of this Project as discussed above shall continue in the first 3 years after commissioning of this Project. After 3 years of post-Project commission period, a review shall be conducted by DSD to determine whether such monitoring shall be continued. The review results shall be submitted to EPD, AFCD, WSD and other relevant parties. Any amendment on the monitoring programme shall be agreed by EPD, AFCD and WSD. Details of the monitoring programme and an event and action plan for the emergency discharge are provided in Section 4 of the EM&A Manual.

 

14.9                Landscape and Visual Impact

14.9.1            Mitigation Measures

14.9.1.1         Potential landscape and visual impacts have been carefully considered during the development of the Project design to avoid impacts on important landscape resources as the first priority; and locate, design and reduce the physical extent of works as far as possible, as well as identify mitigation measures, so as to minimise the degree of visual impacts and the impacts on existing landscape resources.

14.9.1.2         Mitigation measures proposed in the EIA for the construction and operation phases are presented in Section 10.8. The construction phase mitigation measures should be adopted throughout the entire construction period while the mitigation measures for the operation phase should be adopted during the detailed design stage and be built as part of the construction works so that they are in place during the commissioning of the Project.  

14.9.1.3         Any potential conflicts among the proposed mitigation measures, the Project works, and operational requirements should also be identified and resolved at early stage. Any changes to the mitigation measures should be incorporated in the detailed design. 

14.9.2            Baseline Review

14.9.2.1         A baseline review shall be undertaken at the commencement of the construction contracts.  The purpose of the review is: 

¡P         to check the status of the Landscape Resources and Character Areas within the construction works sites and works areas and the VSRs within the visual envelope; 

¡P         to determine whether any change has occurred to the status of the Landscape Resources, Character Areas and VSRs since the EIA; 

¡P         to determine whether such change warrants a change in the design of the landscape and visual mitigation measures; and 

¡P         to recommend any necessary changes to the recommended landscape and visual mitigation measures in the EIA. 

14.9.3            Audit Requirements

14.9.3.1         Site audit should be undertaken regularly during the construction phase of the Project to check that the proposed landscape and visual mitigation measures are properly implemented and maintained as per their intended objectives.  Details of the EM&A requirements are provided in the EM&A Manual.

 

14.10              Cultural Heritage Impact

14.10.1.1      No cultural heritage resources are located within the 50m study area from the site boundary of the Project and no potential direct or indirect impact to these cultural heritage resources is anticipated.   On this basis, mitigation measures, and monitoring and audit programme are not considered necessary.

 

14.11              Waste Management Implications

14.11.1.1      Waste management will be the contractor¡¦s responsibility to ensure that all wastes produced during the construction of the Project are handled, stored and disposed of in accordance with the recommended good waste management practices, regulations and requirements.  Mitigation measures recommended in Section 12.6 should form the basis of the site Waste Management Plan to be developed by the Contractor at the construction stage.

14.11.1.2      It is recommended that waste generated from construction activities should be audited periodically to determine if wastes are being managed in accordance with approved procedures and the site WMP.  The audits should look at all aspects of waste management including waste generation, storage, recycling, transport and disposal.  Apart from site inspections, documents including licences, permits, disposal and recycling records should be reviewed and audited for compliance with the legislation and Contract requirements.  In addition, the routine site inspections should check the implementation of the recommended good site practices and other waste management mitigation measures.

14.11.1.3      A WMP, as part of the EMP should be prepared in accordance with ETWB TC(W) No.19/2005 and submitted to the Engineer for approval.  The recommended mitigation measures should form the basis of the WMP.  The monitoring and auditing requirement stated in ETWB TC(W) No.19/2005 should be followed with regard to the management of C&D materials.

14.11.1.4      Adverse environmental impacts generated from handling, storage and disposal of waste are not expected from the operation of the Project with the implementation of good waste management practices. Therefore, waste monitoring and audit programme for the operation phase of the Project would not be required.

 

14.12              Health Impact

14.12.1.1      Since no adverse health impact is expected from the Project, EM&A program specified for health impact is not required.

<End of Section 14>