TABLE OF CONTENTS
Page
5 Water
Quality Impact. 5-1
5.1 Introduction. 5-1
5.2 Environmental
Legislation, Standards and Criteria. 5-1
5.3 Description
of Environment 5-1
5.4 Water
Sensitive Receivers. 5-1
5.5 Identification
of Potential Impacts. 5-1
5.6 Assessment
Methodology. 5-1
5.7 Land-based
Construction. 5-1
5.8 Operational
Effluent Discharges to Victoria Harbour ¡V Normal THEES Operation. 5-1
5.9 Operational
Effluent Discharges to Tolo Harbour ¡V Normal Plant / THEES Operation. 5-1
5.10 THEES
Maintenance Discharge from TPSTW and CSTW to Tolo Harbour 5-1
5.11 Emergency
Discharge from STSTW to Tolo Harbour 5-1
5.12 Operational
Impact - Wastewater from Sludge Treatment 5-1
5.13 Operational
Impact - Non-point Source Storm Pollution. 5-1
5.14 Conclusion. 5-1
LIST OF TABLES
Table
5.1 Summary of Key Water Quality Objectives for
Tolo Harbour and Channel WCZ. 5-1
Table
5.2 Summary of Key Water Quality Objectives for
Victoria Harbour (Phases One, Two and Three) WCZ 5-1
Table
5.3 WSD¡¦s Target Seawater Quality Objectives at
Flushing Water Intakes. 5-1
Table
5.4 Baseline Water Quality Condition for
Victoria Harbour WCZ in 2014. 5-1
Table
5.5 Baseline Water Quality Condition for Tolo
Harbour and Channel WCZ in 2014. 5-1
Table
5.6 Baseline Water Quality Condition for Shing
Mun River and its Tributary in 2014. 5-1
Table
5.7 Baseline Water Quality Condition for Major
Inland Water Bodies in 2015 (Dry Season) 5-1
Table
5.8 Baseline Water Quality Condition for Major
Inland Water Bodies in 2015 (Wet Season) 5-1
Table
5.9 Design Standards of the Existing STSTW,
Proposed CSTW and Existing TPSTW.. 5-1
Table
5.10 Projects Incorporated in Modelling. 5-1
Table
5.11 Pollution Loading from Stonecutters Island
Sewage Treatment Works under HATS Stage 2A 5-1
Table
5.12 Dry Weather Diurnal Flow Pattern of STSTW.. 5-1
Table
5.13 Projected Dry Weather Diurnal Flow Pattern
of TPSTW.. 5-1
Table
5.14 Summary of Water Quality Modelling
Scenarios. 5-1
Table
5.15 Monthly Flow Rates of the Co-used and Not
Co-used Options. 5-1
Table
5.16 Monthly Flow Rates of the Proposed IP
Scheme Under Co-used Option for Model Input 5-1
Table
5.17 Annual Volumes of Secondarily Treated and
Disinfected Effluent Overflow to Tolo Harbour under ¡§Without Project¡¨ Scenario. 5-1
Table
5.18 Annual Volume of Secondarily Treated and
Disinfected Effluent Overflow to Tolo Harbour under ¡§With Project¡¨ Scenario. 5-1
Table
5.19 Predicted Water Quality at Selected WSD
Flushing Water Intakes. 5-1
Table
5.20 Predicted Water Quality at Kai Tak DCS
Cooling Water Intake. 5-1
Table
5.21 Predicted Water Quality at KTTS / Potential
Water Sports Area. 5-1
LIST OF DIAGRAMS
Diagram 5.01 Water
Bodies Potentially Affected by the THEES Effluent 5-39
Diagram
5.02 Generalized THEES Effluent Flow to Victoria Harbour
Considered Under Scenarios 1,
2a, 2b, 3a and 5-40
Diagram
5.03 Proposed Intake and Discharge Points of IP System.. 5-41
Diagram
5.04 Generalized Effluent Flow to Tolo Harbour Considered
Under Scenario 4. 5-45
Diagram
5.05 Generalized Effluent Flow to Tolo Harbour Considered
Under Scenario 5. 5-46
Diagram
5.06 Generalized Effluent Flow to Tolo Harbour Considered
Under Scenarios 6a and 6b. 5-47
Diagram
5.07 Generalized Effluent Flow to Tolo Harbour Considered
Under Scenario 7. 5-49
LIST OF FIGURES
60334056/EIA/5.01 Inland
Water Bodies Near the Project Works
60334056/EIA/5.02 Marine
Water Sensitive Receivers in Victoria Harbour
60334056/EIA/5.03 Marine
Water Sensitive Receivers in Tolo Harbour
LIST OF APPENDICES
Appendix 5.01a Methodology
for Background Pollution Loading Inventory
Appendix 5.01b Storm Pollution Loading
Inventory for Tolo Harbour
Appendix 5.02 Indicative Locations
of Storm Outfalls and Catchment Areas
Appendix 5.03 Contour
Plots of Water Quality Modelling Results (Scenarios 1 ¡V 3)
Appendix 5.04a Contour
Plots of Water Quality Modelling Results (Scenarios 4 ¡V 6)
Appendix 5.04b Time
Series Plots of Water Quality Modelling Results (Scenarios 5 & 6a)
Appendix 5.04c Time
Series Plots of Water Quality Modelling Results (Scenarios 5 & 6b)
Appendix 5.04d Time
Series Plots of Water Quality Modelling Results (Scenarios 7) ¡V Dry Season
(Spring Tide Mid-ebb)
Appendix 5.04e Time
Series Plots of Water Quality Modelling Results (Scenarios 7) ¡V Wet Season
(Neap Tide Low Water)
Appendix 5.05 Water
Quality Modelling Results for Marine Water Sensitive Receivers at Tolo Harbour
(Scenarios 4 ¡V 7)
Appendix 5.06 Questionnaire
Results for Suspended Solids Criterion at Cooling Water Intakes
Appendix 5.07 Existing
Contingency Plan
Appendix 5.08 Comparison
of Historical Red Tide Data and Chlorophyll-a Concentrations Before, During and After the THEES
Maintenance
5.1.1.1
This section presents the findings
of the assessment of potential water quality impacts associated with the
construction and operation of the Project. Suitable mitigation measures have
been recommended to minimize the potential adverse impacts and to ensure the
acceptability of any residual impact after mitigation.
5.1.1.2
Both the existing Tai Po Sewage
Treatment Works (TPSTW) and the existing Sha Tin Sewage Treatment Works (STSTW)
are secondary treatment plants with disinfection process. Currently, under
normal operation of the THEES, the Tai Po Effluent Pumping Station (TPEPS)
would pump the secondarily treated and disinfected sewage effluent from the
TPSTW via a rising main and a submarine pipeline to the Sha Tin Effluent
Pumping Station (STEPS). The STEPS would receive the secondarily treated and
disinfected sewage effluents from both TPSTW and STSTW. The combined effluents
from STEPS would then be pumped up to the THEES portal at A Kung Kok and then
flow to KTN (or called Kai Tak River after completion of reconstruction and
upgrading works) by gravity for discharge into Victoria Harbour. The TPEPS and
associated submarine pipeline to STEPS as well as the Effluent Export Tunnel of
the THEES are indicatively shown in Diagram 5.02 in Section 5.6 below. CSTW will maintain the
current arrangement in discharging effluent to KTN and eventually to Victoria
Harbour through the existing THEES tunnel.
5.1.1.3
In addition, secondarily
treated and disinfected sewage effluent from TPSTW and CSTW may be temporarily
discharged into Tolo Harbour during the operation of the Project under THEES
maintenance period. Primarily
treated / settled sewage from CSTW may also be temporarily discharged into Tolo
Harbour under emergency condition in an extreme case of plant or power
failure. All temporary effluent
from CSTW into Tolo Harbour will be discharged via the existing emergency
submarine outfall of STSTW as shown in Figure
No. 60334056/EIA/5.01. As
such, the Project would have potential impact on both Victoria Harbour and Tolo
Harbour. There is no existing or
planned seawall outfall for the existing STSTW and proposed CSTW.
5.2.1.1
EIAO-TM was issued by EPD under
Section 16 of the EIAO. It
specifies the assessment method and criteria that are to be followed in an EIA
Study. Reference sections in the
EIAO-TM provide the details of assessment criteria and guidelines that are
relevant to the water quality impact assessment, including:
¡P
Annex 6 ¡V Criteria for Evaluating Water
Pollution
¡P
Annex 14 ¡V Guidelines for Assessment of Water
Pollution
5.2.2.1
The Water Pollution Control
Ordinance (WPCO) provides major statutory framework for the protection and
control of water quality in Hong Kong.
According to the Ordinance and its subsidiary legislation, Hong Kong
waters are divided into ten Water Control Zones (WCZs). Corresponding statements of Water
Quality Objectives (WQOs) are stipulated for different water regimes (marine
waters, inland waters, bathing beaches subzones, secondary contact recreation
subzones and fish culture subzones) in the WCZs based on their beneficial
uses.
5.2.2.2
The construction works and
emergency discharge location of the Project are located in the Tolo Harbour and
Channel WCZ. Under the normal plant
operation, the Project effluent will be discharged to the KTN and eventually to
the marine water of Kai Tak Approach Channel (KTAC), which is located in the Victoria
Harbour (Phase Two) WCZ. The
Victoria Harbour WCZ has been divided into three phases (namely Phases One, Two
and Three respectively) and the associated marine WQOs for all the three phases
as defined under the WPCO are the same.
Selected WQOs for the Tolo Harbour and Channel WCZ and Victoria Harbour
(Phases One, Two and Three) WCZ are listed in Table 5.1
and Table 5.2 respectively.
Table 5.1 Summary
of Key Water Quality Objectives for Tolo Harbour and Channel WCZ
Parameters
|
Objectives
|
Sub-Zone
|
Offensive odour,
tints
|
Not to be present
|
Whole zone
|
Visible foam, oil
scum, litter
|
Not to be present
|
Whole zone
|
Dissolved oxygen
(DO)
|
Not less than 2mg/L within two metres
of the bottom, or not less than 4mg/L in the remainder of the water column
|
Marine Waters in Harbour Subzone
|
Not less than 3mg/L within two metres
of the bottom, or not less than 4mg/L in the remainder of the water column
|
Marine Waters in Buffer Subzone
|
Not less than 4mg/L at any point in the
water column
|
Marine Waters in Channel Subzone
|
Not less than 4 mg/L or 40% saturation
(at 150C) at any time
|
Inland Waters
|
pH
|
Not to cause the normal pH range to be
extended by more than ¡Ó0.5 pH units at any time.
|
Marine Waters in Harbour Subzone
|
Not to cause the normal pH range to be
extended by more than ¡Ó0.3 pH units at any time.
|
Marine Waters in Buffer Subzone
|
Not to cause the normal pH range to be
extended by more than ¡Ó0.1 pH units at any time.
|
Marine Waters in Channel Subzone
|
Not exceed the normal pH range of 6.5 ¡V
8.5 at any time
|
Inland Waters in Shing Mun (A, B, C, F,
G, H) subzones
|
Not exceed the normal pH range of 6.0 ¡V
9.0 at any time
|
Inland Waters in Shing Mun (D, E, I)
subzones and other watercourses
|
Light Penetration
|
Should not reduce light transmission by
more than 20% of the normal level at any location or any time.
|
Marine Waters in Harbour Subzone
|
Should not reduce light transmission by
more than 15% of the normal level at any location or any time.
|
Marine Waters in Buffer Subzone
|
Should not reduce light transmission by
more than 10% of the normal level at any location or any time.
|
Marine Waters in Channel Subzone
|
Salinity
|
Not to cause the normal salinity range
to be extended by more than ¡Ó3 parts per thousand at any time.
|
Marine Waters
|
Temperature
|
Not to cause the natural daily
temperature range to be extended by greater than ¡Ó1.0 ¢XC at any location or
time. The rate of temperature change
shall not exceed 0.5 ¢XC per hour at any location, unless due to natural
phenomena.
|
Marine Waters
|
Not to cause the natural daily
temperature range to be extended by greater than ¡Ó2.0 ¢XC at any location or
time.
|
Inland Waters
|
Chemical oxygen demand (COD)
|
Not exceed 15 mg/L at any time
|
Inland Waters in Shing Mun (B, F, G)
subzones
|
Not exceed 30 mg/L at any time
|
Inland Waters in Shing Mun (A, C, D, E,
H, I) subzones and other watercourses
|
5-day biochemical oxygen demand (BOD)
|
Not exceed 3 mg/L at any time
|
Inland Waters in Shing Mun (B, F, G)
subzones
|
Not exceed 5 mg/L at any time
|
Inland Waters in Shing Mun (A, C, D, E,
H, I) subzones and other watercourses
|
Suspended solids
(SS)
|
Not to cause the annual median level to
exceed 20 mg/L.
|
Inland Waters in Shing Mun (A, B, C, F,
G, H) subzones
|
Not to cause the annual median level to
exceed 25 mg/L.
|
Inland Waters in Shing Mun (D, E, I)
subzones and other watercourses
|
Settleable
Material
|
Bottom deposits or submerged objects
should not adversely influence bottom-living communities, alter the basic
Harbour geometry or shipping channels, present any hazard to shipping or
diving activities, or affect any other beneficial use of the waters.
|
Whole zone
|
Ammonia Nitrogen (NH3-N)
|
Not to exceed 0.5 mg/L at any time
|
Inland Waters
|
E. coli Bacteria
|
Not exceed 610 per 100mL, calculated as
the geometric mean of all samples collected in one calendar year
|
Secondary Contact Recreation Subzone
and Fish Culture Zone
|
Not exceed 1000 per 100mL, calculated
as a running median of the most recent 5 consecutive samples taken at
intervals of between 7 and 21 days (or 14 and 42 days)
|
Inland Waters in Shing Mun (A, C, D, E,
H, I) subzones and other watercourses
|
Not exceed 0 per 100mL, calculated as a
running median of the most recent 5 consecutive samples taken at intervals of
between 7 and 21 days (or 14 and 42 days)
|
Inland Waters in Shing Mun (B, F, G)
subzones
|
Chlorophyll-a
|
Not to cause the level of chlorophyll-a in waters of the subzone to exceed
20 mg/m3, calculated as a running arithmetic mean of 5 daily
measurements for any single location and depth.
|
Marine Waters in Harbour Subzone
|
Not to cause the level of chlorophyll-a in waters of the subzone to exceed
10 mg/m3, calculated as a running arithmetic mean of 5 daily
measurements for any single location and depth.
|
Marine Waters in Buffer Subzone
|
Not to cause the level of chlorophyll-a in waters of the subzone to exceed 6
mg/m3, calculated as a running arithmetic mean of 5 daily
measurements for any single location and depth.
|
Marine Waters in Channel Subzone
|
Toxic substances
|
Should not attain such a level as to
produce significant toxic effects in humans, fish or any other aquatic
organisms.
|
Whole zone
|
Source: Statement of Water Quality
Objectives (Tolo Harbour and Channel Water Control Zone).
Note: The
WQOs for inland waters are only reported for Shing Mun River catchment, which
is within the Study Area of this Project.
There are 9 subzones of inland waters in Shing Mun River catchment,
namely SM(A) to SM(I) respectively, as delineated under Schedule 3 of Cap 358F
Tolo Harbour and Channel Water Control Statement of Water Quality Objectives
for Watercourses under the WPCO.
Please refer to http://www.legislation.gov.hk/blis_pdf.nsf/CurAllEngDoc/D436F5EC4700FCAD482575EE007087E9/$FILE/CAP_358F_e_b5.pdf for the
delineation of Shing Mun River Subzone
Table 5.2 Summary
of Key Water Quality Objectives for Victoria Harbour (Phases One, Two and
Three) WCZ
Parameters
|
Objectives
|
Sub-Zone
|
Offensive odour,
tints
|
Not to be present
|
Whole zone
|
Visible foam, oil
scum, litter
|
Not to be present
|
Whole zone
|
Dissolved oxygen
(DO) within 2m of the seabed
|
Not less than 2.0 mg/l for 90% of
samples
|
Marine waters
|
Depth-averaged DO
|
Not less than 4.0 mg/l for 90% of
samples
|
Marine waters
|
pH
|
To be in the range of 6.5 - 8.5, change
due to human activity not to exceed 0.2
|
Marine waters
|
Salinity
|
Change due to human activity not to
exceed 10% of ambient
|
Whole zone
|
Temperature
|
Change due to human activity not to
exceed 2¢XC
|
Whole zone
|
Suspended solids
(SS)
|
Not to raise the ambient level by 30%
caused by human activity
|
Marine waters
|
Unionized ammonia
(UIA)
|
Annual mean not to exceed 0.021 mg/l as
unionized form
|
Whole zone
|
Nutrients
|
Shall not cause excessive algal growth
|
Marine waters
|
Total inorganic
nitrogen (TIN)
|
Annual mean depth-averaged inorganic
nitrogen not to exceed 0.4 mg/l
|
Marine waters
|
Toxic substances
|
Should not attain such levels as to
produce significant toxic, carcinogenic, mutagenic or teratogenic effects in
humans, fish or any other aquatic organisms.
|
Whole zone
|
Human activity should not cause a risk
to any beneficial use of the aquatic environment.
|
Whole zone
|
Source: Statement of Water Quality
Objectives (Victoria Harbour (Phases One, Two and Three) WCZ)
5.2.3.1
The Hong Kong Planning
Standards and Guidelines (HKPSG), Chapter 9 (Environment), provides additional
guidelines against water pollution for sensitive uses such as aquaculture and
fisheries zones, bathing waters and other contact recreational waters.
5.2.4.1
The Water Supplies Department
(WSD) has specified a set of target seawater quality objectives for their
flushing water intakes. The list is
shown in Table 5.3 below. These target objectives will be applied
at the points of seawater abstraction along the coastlines of Tolo Harbour and
Victoria Harbour for flushing purpose.
Table 5.3 WSD¡¦s
Target Seawater Quality Objectives at Flushing Water Intakes
Parameter (in
mg/L unless otherwise stated)
|
WSD¡¦s Target
Water Quality Limit at Flushing Water Intake
|
Colour (Hazen Unit)
|
< 20
|
Turbidity (NTU)
|
< 10
|
Threshold Odour Number (odour unit)
|
< 100
|
Ammonia Nitrogen (NH3-N)
|
< 1
|
Suspended Solids (SS)
|
< 10
|
Dissolved Oxygen (DO)
|
> 2
|
Biochemical Oxygen Demand (BOD)
|
< 10
|
Synthetic Detergents
|
< 5
|
E. coli (no./100mL)
|
< 20,000
|
5.2.5.1
The suspended solids (SS)
criterion for cooling water intakes is different from that for the WSD¡¦s
intakes as their beneficial uses are different (the former is used for cooling
water system and the latter for flushing purpose).
Victoria Harbour
5.2.5.2
There are a number of cooling
water intakes identified in Victoria Harbour. Cooling water intakes in vicinity
of the Project discharge point include the Dairy Farm Ice Plant, Kai Tak
District Cooling System
(DCS), North Point Government Office and Taikoo Place
Cooling Water Intake. No statutory water quality guideline is available for
these cooling water intakes.
Questionnaires were sent out to the operators of the cooling water
intakes in order to ascertain the corresponding SS criterion. Based on the results of the
questionnaire survey, no specific SS requirement is available for the cooling
water intakes. Regarding the
closest cooling water intake to the Project discharge point, namely Kai Tak
DCS, the written reply from the operator of Electrical and Mechanical Services
Department (EMSD) is documented in Appendix 5.06.
Tolo Harbour
5.2.5.3
There is only one cooling water
intake point in Tolo Harbour for the Marine Science laboratory of the
CUHK. No specific SS limit is
available for this intake point based on the review of the EIA for ¡§Development
of a Bathing Beach at Lung Mei, Tai Po¡¨.
As this EIA report was completed several years ago, a questionnaire was
conducted with the operator of this cooling water intake to update the SS
requirement. It was advised by the
CUHK that there is no specific SS requirement for the cooling water intake at
the Marine Science Laboratory since it has its own filtration system after
water intake to remove SS. The
written reply from the CUHK is documented in Appendix 5.06.
5.2.6.1
Besides setting the WQOs, the
WPCO controls effluent discharging into the WCZs through a licensing
system. Guidance on the permissible
effluent discharges based on the type of receiving waters (foul sewers,
stormwater drains, inland and coastal waters) is provided in the Technical
Memorandum on Standards for Effluents Discharged into Drainage and Sewerage
Systems, Inland and Coastal Waters (TM-DSS). The limits given in the TM cover the
physical, chemical and microbial quality of effluents. Any effluent discharge during the
construction and operational stages should comply with the relevant standards
as stipulated in the TM-DSS.
5.2.7.1
The Practice Note (PN) for
Professional Persons on Construction Site Drainage (ProPECC PN 1/94) issued by
EPD provides good practice guidelines for dealing with various types of
discharge from a construction site.
Practices outlined in the PN should be followed as far as possible
during construction to minimize the water quality impact due to construction
site drainage.
5.2.8.1
Potential impacts on benthic
organisms, including corals, may arise through excessive sediment
deposition. The magnitude of the
potential impacts will be assessed based on the predicted sedimentation rate.
5.2.8.2
There is no existing
legislative standard on sedimentation rate available. According to Pastorok and Bilyard
and Hawker and Connell,
a sedimentation rate higher than 0.1 kg/m2/day would introduce
moderate to severe impact upon corals. This sedimentation rate of no more
than 0.1 kg/m2/day will be adopted as the assessment criterion for
protecting the sediment sensitive ecological resources in Tolo Harbour and
Victoria Harbour, following the approach used in the approved EIA projects in Tolo
Harbour such as ¡§Development of a Bathing Beach at Lung Mei, Tai Po¡¨ and ¡§TPSTW
Stage V¡¨ as well as the recent EIA projects in Victoria Harbour such as ¡§Wan
Chai Development Phase II and Central-Wan Chai Bypass¡¨ and ¡§Sha Tin to Central
Link - Hung Hom to Admiralty Section¡¨ etc.
This sedimentation rate criterion is considered to offer sufficient
protection to marine ecological sensitive receivers and is anticipated to guard
against unacceptable impacts. This
protection has been confirmed by previous EM&A results which have indicated
no adverse impacts to corals have occurred when this assessment criterion has
been adopted.
5.2.8.3
It should be noted that the
sedimentation criterion was derived for protection of important subtidal
habitats (e.g. corals) only and hence it is not applicable to other Water
Sensitive Receivers (WSRs) such as bathing beach users and seawater intakes
where the main concern would be on the surface / mid-depth water quality. No sedimentation criterion specific to
bathing beach users and seawater intakes is available and therefore the
sedimentation rate for these WSRs will not be presented in this assessment.
5.3.1.1
The study area for this water
quality impact assessment covered the Tolo Harbour and Channel WCZ and Victoria
Harbour WCZ as designated under the WPCO.
5.3.1.2
The baseline conditions of the
water bodies in the study area were established with reference to the routine
river and marine water quality monitoring data collected by EPD. Descriptions
of the baseline conditions provided in the subsequent sections are extracted
from the EPD¡¦s reports ¡§River Water Quality Monitoring in Hong Kong 2014¡¨ and
¡§Marine Water Quality Monitoring in Hong Kong 2014¡¨.
5.3.1.3
Additional water quality
surveys were also conducted at other inland water bodies within 500m from the
Project works to collect additional field data for both dry and wet seasons to
supplement the EPD routine water quality monitoring data. Additional survey locations namely Shing
Mun River (R1), Streams along / around Mui Tsz Lam Road (R2a, b and c), and Ma
Tai Stream (R3) are shown in Figure
No. 60334056/EIA/5.01.
Water quality surveys were carried out on 23, 25 and 27 March 2015 for
dry season, and 9, 11 and 13 June 2015 for wet season.
Victoria Harbour
Water Quality in Victoria Harbour
5.3.2.1
The water quality monitoring
results at stations in vicinity of the Project discharge, namely VT4, VM1, VM2
and VM4 are shown in Table 5.4 below. The selected marine water quality
monitoring stations are shown in Figure
No. 60334056/EIA/5.02. Full
compliances with the WQO for TIN, DO (depth average) and UIA were recorded at
VM1, VM2 and VM4 in 2014. For the
bottom DO, non-compliance with the WQO was recorded at VM1 and VM2, whilst full
compliance was achieved at VM4 in 2014. The water quality recorded at VT4 in
2014 breached the WQO for TIN whilst achieved WQO compliance for DO (depth
average and bottom layer) and UIA.
Table 5.4 Baseline
Water Quality Condition for Victoria Harbour WCZ in 2014
Parameter
|
Victoria Harbour (East)
|
Victoria Harbour (Central)
|
Kwun Tong Typhoon Shelter
|
WPCO WQO
(in marine waters)
|
VM1
|
VM2
|
VM4
|
VT4
|
Temperature (¢XC)
|
22.4
|
22.9
|
22.9
|
23.6
|
Change due to waste discharge not to exceed 2¢XC
|
(16.1 - 29.1)
|
(16.2 - 29.0)
|
(16.2 - 29.0)
|
(17.1 - 29.0)
|
Salinity
|
32.4
|
31.8
|
31.7
|
29.7
|
Change due to waste discharge not to
exceed 10% of natural ambient level
|
(30.5 - 33.4)
|
(28.0 - 33.2)
|
(27.6 - 33.2)
|
(26.8 - 32.0)
|
Dissolved Oxygen (mg/L)
|
Depth Average
|
5.7
|
5.5
|
5.3
|
5.8
|
Not less than 4 mg/l for 90% of the
samples
|
(2.5 - 8.2)
|
(3.2 - 8.0)
|
(3.3 - 7.6)
|
(4.5 - 6.4)
|
Bottom
|
5.7
|
5.2
|
5.0
|
5.4
|
Not less than 2 mg/l for 90% of the samples
|
(2.1 - 8.2)
|
(1.2 - 8.1)
|
(0.6 - 8.1)
|
(2.8 - 7.0)
|
Dissolved Oxygen (% Saturation)
|
Depth Average
|
78
|
76
|
73
|
81
|
Not available
|
(37 - 102)
|
(48 - 99)
|
(49 - 94)
|
(64 - 97)
|
Bottom
|
77
|
71
|
68
|
76
|
Not available
|
(30 - 103)
|
(17 - 100)
|
(8 - 101)
|
(42 - 107)
|
pH
|
7.9
|
7.9
|
7.9
|
7.8
|
6.5 - 8.5 (¡Ó 0.2 from natural range)
|
(7.5 - 8.2)
|
(7.5 - 8.2)
|
(7.5 - 8.2)
|
(7.5 - 8.0)
|
Secchi Disc Depth (m)
|
2.9
|
2.6
|
2.5
|
1.8
|
Not available
|
(2.0 - 4.0)
|
(1.5 - 3.5)
|
(1.5 - 4.0)
|
(0.4 - 2.5)
|
Turbidity (NTU)
|
2.7
|
2.0
|
2.1
|
1.9
|
Not available
|
(0.6 - 4.7)
|
(0.6 - 3.7)
|
(0.4 - 5.6)
|
(0.8 - 3.9)
|
Suspended Solids (SS) (mg/L)
|
4.3
|
3.0
|
3.3
|
3
|
Not more than 30% increase
|
(0.9 - 12.2)
|
(1.5 - 5.8)
|
(0.8 - 9.9)
|
(0.9 - 7.3)
|
5-day Biochemical Oxygen Demand (BOD5)
(mg/L)
|
0.7
|
1.0
|
1.3
|
1.5
|
Not available
|
(0.1 - 1.9)
|
(0.5 - 2.8)
|
(0.2 - 4.6)
|
(0.4 - 2.6)
|
Ammonia Nitrogen (NH3-N)
(mg/L)
|
0.064
|
0.120
|
0.127
|
0.291
|
Not available
|
(0.025 - 0.113)
|
(0.041 - 0.237)
|
(0.048 - 0.257)
|
(0.190 - 0.460)
|
Unionised Ammonia (UIA) (mg/L)
|
0.002
|
0.003
|
0.003
|
0.007
|
Not more than 0.021 mg/l for annual mean
|
(<0.001 - 0.003)
|
(<0.001 - 0.006)
|
(<0.001 - 0.007)
|
(0.002 - 0.011)
|
Nitrite Nitrogen (NO2-N)
(mg/L)
|
0.020
|
0.025
|
0.027
|
0.095
|
Not available
|
(0.009 - 0.043)
|
(0.011 - 0.052)
|
(0.011 - 0.055)
|
(0.051 - 0.163)
|
Nitrate Nitrogen (NO3-N)
(mg/L)
|
0.114
|
0.135
|
0.139
|
1.61
|
Not available
|
(0.062 - 0.203)
|
(0.071 - 0.240)
|
(0.085 - 0.246)
|
(0.530 - 3.330)
|
Total Inorganic Nitrogen (TIN)
(mg/L)
|
0.20
|
0.28
|
0.29
|
2
|
Not more than 0.4 mg/l for annual mean
|
(0.12 - 0.33)
|
(0.17 - 0.48)
|
(0.16 - 0.51)
|
(0.89 - 3.90)
|
Total Kjeldahl Nitrogen (TKN) (mg/L)
|
0.22
|
0.30
|
0.32
|
0.63
|
Not available
|
(0.12 - 0.34)
|
(0.15 - 0.42)
|
(0.17 - 0.46)
|
(0.52 - 0.90)
|
Total Nitrogen (TN) (mg/L)
|
0.36
|
0.46
|
0.49
|
2.33
|
Not available
|
(0.21 - 0.49)
|
(0.27 - 0.65)
|
(0.27 - 0.66)
|
(1.21 - 4.34)
|
Orthophosphate Phosphorus (PO4)
(mg/L)
|
0.019
|
0.025
|
0.027
|
0.356
|
Not available
|
(0.013 - 0.029)
|
(0.016 - 0.039)
|
(0.018 - 0.043)
|
(0.183 - 0.703)
|
Total Phosphorus (TP) (mg/L)
|
0.03
|
0.04
|
0.04
|
0.43
|
Not available
|
(0.02 - 0.05)
|
(0.02 - 0.06)
|
(0.03 - 0.06)
|
(0.24 - 0.87)
|
Silica (as SiO2) (mg/L)
|
0.91
|
0.91
|
0.97
|
2.36
|
Not available
|
(0.19 - 1.80)
|
(0.15 - 1.93)
|
(0.19 - 2.07)
|
(1.30 - 4.17)
|
Chlorophyll-a (£gg/L)
|
3.2
|
3.7
|
3.8
|
9.3
|
Not available
|
(0.2 - 12.2)
|
(0.2 - 16.2)
|
(0.3 - 16.0)
|
(1.1 - 20.3)
|
E. coli (no./100mL)
|
520
|
2700
|
3500
|
1600
|
Not available
|
(120 - 9700)
|
(320 - 8600)
|
(860 - 19000)
|
(150 - 33000)
|
Faecal Coliforms
(no./100mL)
|
1100
|
5500
|
8600
|
3900
|
Not available
|
(150 - 23000)
|
(400 - 23000)
|
(1600 - 27000)
|
(260 - 83000)
|
Notes:
1. Data source: EPD Marine Water Quality in Hong Kong in
2014.
2. Unless otherwise specified, data presented are
depth-averaged (A) values calculated by taking the means of three depths:
Surface (S), Mid-depth (M), Bottom (B).
3. Data presented are annual arithmetic means of
depth-averaged results except for E. coli and faecal coliforms that are
annual geometric means.
4. Data in brackets indicate the ranges.
Trend of Water Quality in Victoria Harbour
5.3.2.2
The overall WQO compliance rate
of Victoria Harbour WCZ in 2014 was 77%.
Compliance with the DO objective meanwhile was 40% due to hot summer
weather in 2014. Compliance rate with the TIN objective improved from 60% in
2013 to 90% in 2014. The overall
annual average level of TIN in Victoria Harbour increased since 2009 and
reached 0.45 mg/L in 2012, then dropped to 0.38 mg/L in 2013 and further
reduced to 0.34 mg/L in 2014.
5.3.2.3
The TIN level in the Victoria
Harbour WCZ could be affected by a higher background TIN level under the
influence of Pearl River discharge, as reflected in the relatively high TIN
level in many stations in the Northwestern and Southern WCZs, the year-to-year
normal range of fluctuation of the discharge from THEES and surface run-off, as
well as the effluent discharged from the remaining preliminary treatment plants
located between North Point and Central.
5.3.2.4
In 2014, sewage discharged from
the four remaining preliminary treatment plants in the middle and western parts
of Hong Kong Island were still contributing to the relatively high levels of E.
coli in central Victoria Harbour.
To further improve the water quality of Victoria Harbour, the Harbour
Area Treatment Scheme (HATS) Stage 2A has recently been commissioned in
2015. Under the HATS Stage 2A,
sewage tunnels are used to collect the remaining 25% of the sewage generated
daily from North Point to Ap Lei Chau in the middle and western parts of Hong
Kong Island, and convey the sewage to the SCISTW for treatment.
Tolo Harbour
Water Quality in Tolo Harbour and Channel
5.3.2.5
The water quality monitoring
results at stations in vicinity of the Project Works, namely TM2, TM3 and TM4
in Harbour Subzone are shown in Table 5.5 below. The selected marine water quality
monitoring stations are shown in Figure
No. 60334056/EIA/5.03. Full
compliances with the WQO was recorded at all the three selected stations for
DO, chlorophyll-a and E. coli in 2014.
Table 5.5 Baseline
Water Quality Condition for Tolo Harbour and Channel WCZ in 2014
Parameter
|
Harbour Subzone
|
WPCO WQO
(in marine waters)
|
TM2
|
TM3
|
TM4
|
Temperature (¢XC)
|
24.2
|
23.9
|
23.8
|
Change due to waste discharge not to exceed 1¢XC
|
(15.4 - 30.3)
|
(15.4 - 29.9)
|
(15.4 - 30.0)
|
Salinity
|
29.7
|
30.6
|
30.7
|
Change due to waste discharge not to be greater than ¡Ó3%
|
(24.1 - 32.3)
|
(25.2 - 32.6)
|
(26.0 - 32.6)
|
Dissolved Oxygen (mg/L)
|
Depth Average
|
6.8
|
6.8
|
6.8
|
Not less than 4 mg/l in the water
column (except for the bottom water later within 2 m from the seabed)
|
(4.0 - 10.0)
|
(4.7 - 9.4)
|
(4.7 - 8.8)
|
Bottom
|
7.7
|
6.4
|
5.9
|
Not
less than 2 mg/l within
2 m from the seabed)
|
(6.3 - 10.0)
|
(2.0 - 9.8)
|
(2.1 - 9.5)
|
Dissolved Oxygen (% Saturation)
|
Depth Average
|
97
|
95
|
95
|
Not available
|
(61 - 144)
|
(74 - 122)
|
(71 - 121)
|
Bottom
|
109
|
89
|
83
|
Not available
|
(79 - 143)
|
(27 - 125)
|
(29 - 121)
|
pH
|
8
|
8.1
|
8.0
|
Change due to waste discharge not to be greater than ¡Ó 0.5
from natural range)
|
(7.8 -
8.3)
|
(7.7 -
8.4)
|
(7.8 -
8.4)
|
Secchi Disc Depth (m)
|
2.3
|
2.5
|
2.3
|
Not available
|
(1.3 -
3.0)
|
(1.3 -
3.5)
|
(1.0 -
4.0)
|
Turbidity (NTU)
|
1.1
|
1.1
|
1.1
|
Not available
|
(0.5 -
1.7)
|
(0.6 -
2.4)
|
(0.5 -
1.7)
|
Suspended Solids (SS) (mg/L)
|
2.8
|
3.3
|
3.0
|
Not available
|
(0.8 -
8.5)
|
(1.3 -
9.6)
|
(1.0 -
10.5)
|
5-day Biochemical Oxygen Demand (BOD5)
(mg/L)
|
1.9
|
1.8
|
1.8
|
Not available
|
(0.6 -
3.8)
|
(0.8 -
3.4)
|
(0.8 -
2.9)
|
Ammonia Nitrogen (NH3-N)
(mg/L)
|
0.038
|
0.042
|
0.037
|
Not available
|
(0.007 -
0.090)
|
(0.012 -
0.105)
|
(0.007 -
0.079)
|
Unionised Ammonia (UIA) (mg/L)
|
0.002
|
0.002
|
0.001
|
Not available
|
(<0.001
- 0.005)
|
(<0.001
- 0.005)
|
(<0.001
- 0.003)
|
Nitrite Nitrogen (NO2-N)
(mg/L)
|
0.003
|
0.003
|
0.004
|
Not available
|
(<0.002
- 0.007)
|
(<0.002
- 0.005)
|
(<0.002
- 0.007)
|
Nitrate Nitrogen (NO3-N) (mg/L)
|
0.032
|
0.022
|
0.018
|
Not available
|
(0.003 -
0.146)
|
(0.004 -
0.095)
|
(<0.002
- 0.070)
|
Total Inorganic Nitrogen (TIN)
(mg/L)
|
0.07
|
0.07
|
0.06
|
Not available
|
(0.02 -
0.21)
|
(0.02 -
0.14)
|
(0.02 -
0.14)
|
Total Kjeldahl Nitrogen (TKN) (mg/L)
|
0.29
|
0.29
|
0.28
|
Not available
|
(0.19 -
0.42)
|
(0.21 -
0.40)
|
(0.21 -
0.41)
|
Total Nitrogen (TN) (mg/L)
|
0.33
|
0.31
|
0.31
|
Not available
|
(0.19 -
0.45)
|
(0.21 -
0.47)
|
(0.21 -
0.48)
|
Orthophosphate Phosphorus (PO4)
(mg/L)
|
0.005
|
0.005
|
0.005
|
Not available
|
(<0.002
- 0.007)
|
(0.002 -
0.006)
|
(0.002 -
0.010)
|
Total Phosphorus (TP) (mg/L)
|
0.03
|
0.03
|
0.03
|
Not available
|
(<0.02
- 0.04)
|
(<0.02
- 0.04)
|
(<0.02
- 0.04)
|
Silica (as SiO2) (mg/L)
|
0.98
|
0.82
|
0.84
|
Not available
|
(0.06 -
2.10)
|
(0.06 -
1.51)
|
(0.18 -
1.51)
|
Chlorophyll-a (£gg/L)
|
10.0
|
7.2
|
7.0
|
Not to exceed 20 £gg/L for a running arithmetic mean of 5
daily measurements
|
(2.0 -
30.2)
|
(1.1 -
16.7)
|
(1.2 -
13.7)
|
E. coli
(no./100mL)
|
28
|
14
|
9
|
Not to exceed 610 no./100mL for geometric mean
|
(<1 -
3200)
|
(1 - 260)
|
(<1 -
150)
|
Faecal Coliforms
(no./100mL)
|
240
|
72
|
42
|
Not available
|
(2 - 8200)
|
(4 - 1100)
|
(1 - 790)
|
Notes:
1. Data source: EPD Marine Water Quality in Hong Kong in
2014.
2. Unless otherwise specified, data presented are
depth-averaged (A) values calculated by taking the means of three depths:
Surface (S), Mid-depth (M), Bottom (B).
3. Data presented are annual arithmetic means of
depth-averaged results except for E. coli and faecal coliforms that are
annual geometric means.
4. Data in brackets indicate the ranges.
Trend of Water Quality in Tolo Harbour and Channel
5.3.2.6
Since the implementation of the
Tolo Harbour Action Plan in the mid-80s, which includes the control of
livestock wastes, the improvement of sewage treatment facilities, the export of
treated effluent outside Tolo Harbour and the extension of village sewerage,
there has been a steady improvement in water quality in Tolo Harbour in the
past decade including a decrease in the levels of BOD5, E. coli,
nitrogen and orthophosphate phosphorus.
Moreover, Tolo Harbour is also able to comply with the bacteriological
WQO of ≤
610 E. coli no./100mL (annual geometric mean) for secondary contact
recreation.
5.3.2.7
The 2014 overall WQO compliance
rate of the Tolo Harbour and Channel WCZ was 57%, due to the low compliance
rate with the DO objective at 14%. The low DO levels were recorded at the outer
stations (namely TM6, TM7 and TM8) in Buffer and Channel Subzones further away
from the Project discharge point. Since Tolo Harbour is a shallow semi-enclosed
water body with low water exchange rate with Mirs Bay, the harbour¡¦s
essentially landlocked situation often leads to stratification of the water
column and lower bottom DO levels particularly during the hot summer months,
hence resulting in non-compliance with the DO objective in the summer months.
Water Quality in Shing Mun River and its Tributary
5.3.3.1
The water quality monitoring
results at stations in Shing Mun River, namely TR17, TR17L, TR19I, TR23L and
TR23A (closest to the Project site), are shown in Table
5.6 below. The
selected river water quality monitoring stations are shown in Figure No. 60334056/EIA/5.01.
Table 5.6 Baseline
Water Quality Condition for Shing Mun River and its Tributary in 2014
Parameter
|
Fo Tan
Nullah
|
Shing Mun
Main Channel
|
Siu Lek
Yuen Nullah
|
WPCO WQO
(in inland
waters)
|
TR17
|
TR17L
|
TR19I
|
TR23L
|
TR23A
|
Dissolved oxygen (mg/L)
|
8.6
|
6.9
|
7.8
|
8.9
|
6.8
|
≥4 mg/L or
40% saturation
|
(7.0 - 10.9)
|
(5.3 - 9.1)
|
(4.6 - 8.9)
|
(8.0 - 10.5)
|
(5.1 - 9.5)
|
pH
|
8.2
|
7.5
|
7.8
|
8.7
|
7.5
|
Within 6.5 ¡V 9.0 (TR19I);
Within 6.5 - 8.5 (Others)
|
(7.5 - 9.7)
|
(7.1 - 8.0)
|
(7.4 - 8.4)
|
(8.1 - 8.8)
|
(6.9 - 7.8)
|
Suspended solids (mg/L)
|
8
|
2
|
4
|
2
|
3
|
Annual median:
≤ 25 mg/L (TR19I);
≤ 20 mg/L (Others)
|
(2 - 36)
|
(<1 - 13)
|
(2 - 23)
|
(<1 - 12)
|
(<1 - 12)
|
5-day Biochemical Oxygen Demand
(mg/L)
|
18
|
2
|
4
|
<1
|
2
|
≤3 mg/L (TR23A,
TR23L);
≤5 mg/L (Others)
|
(2 - 57)
|
(2 - 4)
|
(2 - 9)
|
(<1 - 2)
|
(<1 - 3)
|
Chemical Oxygen Demand (mg/L)
|
22
|
9
|
9
|
3
|
7
|
≤15 mg/L (TR23A,
TR23L);
≤30 mg/L (Others)
|
(3 - 47)
|
(5 - 18)
|
(3 - 28)
|
(<2 - 8)
|
(4 - 19)
|
Oil & grease (mg/L)
|
<0.5
|
<0.5
|
<0.5
|
<0.5
|
<0.5
|
Not available
|
(<0.5 - 1.0)
|
(<0.5 - 0.7)
|
(<0.5 - <0.5)
|
(<0.5 - 0.6)
|
(<0.5 - 0.7)
|
Faecal coliforms (cfu/100mL)
|
52,000
|
33,000
|
10,000
|
20,000
|
26,000
|
Not available
|
(<100 - 1,000,000)
|
(230 - 480,000)
|
(110 - 120,000)
|
(3,400 - 240,000)
|
(300 - 370,000)
|
E. coli (cfu/100mL)
|
12,000
|
4,100
|
1,300
|
840
|
5,000
|
Running median of 5 consecutive samples:
≤ 1000 cfu/100mL (TR23A, TR23L);
≤ 0 cfu/100mL (Others)
|
(<100 - 250,000)
|
(80 - 44,000)
|
(10 - 54,000)
|
(130 - 4,900)
|
(30 - 150,000)
|
Ammonia-nitrogen (mg/L)
|
0.13
|
0.29
|
0.16
|
0.01
|
0.38
|
Not more than 0.5 mg/L
|
(<0.01 - 1.90)
|
(0.07 - 0.69)
|
(0.03 - 0.38)
|
(<0.01 - 0.03)
|
(0.15 - 1.50)
|
Nitrate-nitrogen (mg/L)
|
0.46
|
0.34
|
0.19
|
0.23
|
0.35
|
Not available
|
(<0.01 - 0.79)
|
(0.21 - 0.59)
|
(0.04 - 0.74)
|
(0.13 - 0.63)
|
(0.18 - 0.56)
|
Total Kjeldahl nitrogen (mg/L)
|
1.75
|
0.61
|
0.46
|
0.15
|
0.68
|
Not available
|
(0.15 - 4.50)
|
(0.41 - 1.60)
|
(0.30 - 0.76)
|
(0.06 - 0.40)
|
(0.34 - 2.10)
|
Ortho-phosphate (mg/L)
|
0.03
|
0.02
|
<0.01
|
0.01
|
0.03
|
Not available
|
(<0.01 - 0.09)
|
(<0.01 - 0.04)
|
(<0.01 - 0.05)
|
(<0.01 - 0.03)
|
(<0.01 - 0.11)
|
Total phosphorus (mg/L)
|
0.08
|
0.05
|
0.04
|
<0.02
|
0.06
|
Not available
|
(0.03 - 0.53)
|
(0.03 - 0.12)
|
(0.03 - 0.08)
|
(<0.02 - 0.04)
|
(0.02 - 0.26)
|
Total sulphide (mg/L)
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
Not available
|
(<0.02 - 0.03)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
Aluminium (µg/L)
|
82
|
99
|
59
|
83
|
84
|
Not available
|
(<50 - 158)
|
(<50 - 245)
|
(<50 - 166)
|
(<50 - 395)
|
(<50 - 238)
|
Cadmium (µg/L)
|
<0.1
|
<0.1
|
<0.1
|
<0.1
|
<0.1
|
Not available
|
(<0.1 - 2.7)
|
(<0.1 - <0.1)
|
(<0.1 - 0.1)
|
(<0.1 - <0.1)
|
(<0.1 - 0.2)
|
Chromium (µg/L)
|
1
|
3
|
3
|
<1
|
3
|
Not available
|
(<1 - 4)
|
(<1 - 6)
|
(1 - 6)
|
(<1 - <1)
|
(<1 - 4)
|
Copper (µg/L)
|
6
|
5
|
7
|
<1
|
4
|
Not available
|
(2 - 16)
|
(1 - 10)
|
(3 - 12)
|
(<1 - 2)
|
(2 - 5)
|
Lead (µg/L)
|
1
|
1
|
<1
|
<1
|
<1
|
Not available
|
(<1 - 3)
|
(<1 - 2)
|
(<1 - <1)
|
(<1 - 3)
|
(<1 - 3)
|
Zinc (µg/L)
|
43
|
21
|
19
|
13
|
21
|
Not available
|
(12 - 83)
|
(13 - 37)
|
(13 - 27)
|
(<10 - 60)
|
(15 - 52)
|
Flow (L/s)
|
114
|
NM
|
NM
|
56
|
NM
|
Not available
|
(55 - 218)
|
|
|
(11 - 207)
|
|
Notes:
1. Data source: EPD River Water Quality in Hong Kong in
2014.
2. Data presented are in annual medians of monthly
samples; except those for faecal coliforms
and E. coli which are in annual
geometric means.
3. Figures in brackets are annual ranges.
4. NM indicates no measurement taken.
5. cfu ¡V colony forming unit.
Trend of Water Quality in Shing Mun River and its
Tributary
5.3.3.2
Although Shing Mun River in the
Tolo Harbour and Channel WCZ has not yet reached 100% WQO compliance in 2014,
it showed marked improvement during the last two decades. The compliance rate of Shing Mun River
rose from 78% in 1997 to 93% in 2014.
Water Quality in Other Inland Water Bodies
5.3.3.3
Additional field data were
collected in other inland water bodies within 500m of the Project works, namely
R1 (in downstream section of Shing Mun River), R2a, R2b, R2c (in Streams along
/ around Mui Tse Lam Road) and R3 (in Ma Tai Stream). The collected field data
are presented in Table 5.7 and Table
5.8 for dry and wet seasons respectively. The selected water quality
survey locations are shown in Figure
No. 60334056/EIA/5.01.
Table 5.7 Baseline
Water Quality Condition for Major Inland Water Bodies in 2015 (Dry Season)
Parameter
|
Shing Mun River
|
Streams along / around Mui Tsz Lam
Road
|
Ma Tai Stream
|
R1
|
R2a
|
R2b
|
R2c
|
R3
|
Dissolved oxygen (mg/L)
|
6.4
|
5.6
|
7.3
|
8.6
|
8.1
|
(6.3 - 6.5)
|
(4.4 - 7.1)
|
(6 - 8.9)
|
(8.3 - 8.8)
|
(7.2 - 9)
|
pH
|
8.2
|
8.4
|
8.9
|
8.5
|
7.9
|
(7.7 - 8.6)
|
(8.3 - 8.5)
|
(8.1 - 9.7)
|
(8.2 - 8.8)
|
(7.4 - 8.2)
|
Suspended solids (mg/L)
|
4
|
4
|
3
|
1
|
2
|
(<1 - 6)
|
(3 - 4)
|
(2 - 4)
|
(1 - 2)
|
(1 - 3)
|
5-day Biochemical Oxygen Demand
(mg/L)
|
3
|
2
|
2
|
<1
|
<1
|
(2 - 4)
|
(2 - 2)
|
(2 - 2)
|
(<1 - <1)
|
(<1 - <1)
|
Chemical Oxygen Demand (mg/L)
|
<40 See Note
(2)
|
<40 See Note (2)
|
3
|
3
|
7
|
(<40 - <40)
|
(<40 - <40)
|
(2 - 3)
|
(2 - 4)
|
(3 - 16)
|
Oil & grease (mg/L)
|
1.2
|
1.4
|
2.5
|
0.9
|
1.2
|
(0.9 - 1.5)
|
(1 - 1.7)
|
(0.9 - 4.1)
|
(0.7 - 1)
|
(1.2 - 1.2)
|
Faecal coliforms (cfu/100mL)
|
707
|
2,979
|
637
|
219
|
3,520
|
(9 ¡V 2,100)
|
(36 ¡V 7,300)
|
(240 ¡V 1,000)
|
(77 - 470)
|
(460 ¡V 8,700)
|
E. coli (cfu/100mL)
|
639
|
2,812
|
637
|
209
|
1,710
|
(9 ¡V 1,900)
|
(36 ¡V 6,800)
|
(240 ¡V 1,000)
|
(77 - 440)
|
(430 ¡V 3,300)
|
Ammonia-nitrogen (mg/L)
|
0.16
|
0.05
|
0.03
|
0.02
|
0.21
|
(0.06 - 0.23)
|
(0.04 - 0.09)
|
(0.02 - 0.03)
|
(0.02 - 0.02)
|
(0.02 - 0.46)
|
Nitrate-nitrogen (mg/L)
|
<0.01
|
0.02
|
0.16
|
0.2
|
0.27
|
(<0.01 - <0.01)
|
(0 - 0.04)
|
(0.12 - 0.22)
|
(0.11 - 0.34)
|
(0.17 - 0.35)
|
Total Kjeldahl nitrogen (mg/L)
|
0.43
|
0.39
|
0.1
|
0.11
|
0.38
|
(0.38 - 0.51)
|
(0.36 - 0.41)
|
(0.08 - 0.12)
|
(0.09 - 0.12)
|
(0.06 - 0.64)
|
Ortho-phosphate (mg/L)
|
0.01
|
<0.01
|
<0.01
|
<0.01
|
0.04
|
(<0.01 - 0.01)
|
(<0.01 - 0.01)
|
(<0.01 - <0.01)
|
(<0.01 - 0.01)
|
(<0.01 - 0.04)
|
Total phosphorus (mg/L)
|
0.03
|
0.02
|
<0.02
|
<0.02
|
0.05
|
(0.02 - 0.05)
|
(0.02 - 0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(0.02 - 0.07)
|
Total sulphide (mg/L)
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
Aluminium (µg/L)
|
86
|
100
|
106
|
89
|
56
|
(42 - 130)
|
(40 - 160)
|
(49 - 199)
|
(80 - 106)
|
(40 - 69)
|
Cadmium (µg/L)
|
0.2
|
0.1
|
<0.1
|
<0.1
|
0.1
|
(0.2 - 0.2)
|
(0.1 - 0.1)
|
(<0.1 - <0.1)
|
(<0.1 - <0.1)
|
(0.1 - 0.1)
|
Chromium (µg/L)
|
6
|
7
|
1.3
|
1.5
|
2
|
(4 - 8)
|
(5 - 9)
|
(1 - 2)
|
(1 - 2)
|
(2 - 2)
|
Copper (µg/L)
|
10
|
9
|
1
|
<1
|
2
|
(9 - 10)
|
(8 - 10)
|
(1 - 1)
|
(<1 - <1)
|
(2 - 2)
|
Lead (µg/L)
|
<1
|
<1
|
<1
|
1
|
<1
|
(<1 - <1)
|
(<1 - <1)
|
(<1 - <1)
|
(1 - 2)
|
(<1 - <1)
|
Zinc (µg/L)
|
29
|
19
|
19
|
<10
|
13
|
(20 - 36)
|
(18 - 20)
|
(19 - 19)
|
(<10 - <10)
|
(13 - 13)
|
Average Flow Velocity (m/s)
|
0.2
|
0.1
|
<0.1
|
0.1
|
0.2
|
(0.2 - 0.2)
|
(0.1 - 0.1)
|
(<0.1 - <0.1)
|
(0.1 - 0.2)
|
(0.1 - 0.3)
|
Notes:
(1) Dry season water quality surveys were conducted on
23,
25 and 27 March 2015.
(2) Reporting limit was amplified since dilution was required
for the laboratory test due to interference of high chloride content in the
water samples. The high
chloride content in samples collected at downstream of Shing Mun River (R1) and
streams along Mui Tsz Lam Road (R2a) was due to the effect of marine water
(with Sodium Chloride) at the adjacent Sha Tin Hoi.
(3) cfu ¡V colony forming unit.
Table 5.8 Baseline
Water Quality Condition for Major Inland Water Bodies in 2015 (Wet Season)
Parameter
|
Shing Mun River
|
Streams along / around Mui Tsz Lam Road
|
Ma Tai Stream
|
R1
|
R2a
|
R2b
|
R2c
|
R3
|
Dissolved oxygen (mg/L)
|
5.1
|
3.1
|
7.1
|
7.1
|
6.5
|
(4.8 - 5.3)
|
(2.7 - 3.8)
|
(6.3 - 7.7)
|
(6.6 - 8)
|
(6 - 7.1)
|
pH
|
7.6
|
7.7
|
8.8
|
8.4
|
7.6
|
(7.4 - 7.8)
|
(7.6 - 7.8)
|
(8.1 - 9.7)
|
(7.3 - 9.1)
|
(7.1 - 8)
|
Suspended solids (mg/L)
|
4
|
2
|
1
|
1
|
3
|
(2 - 7)
|
(2 - 4)
|
(1 - 1)
|
(1 - 1)
|
(3 - 4)
|
5-day Biochemical Oxygen Demand (mg/L)
|
1
|
1
|
<1
|
<1
|
4
|
(1 - 1)
|
(1 - 1)
|
(<1 - <1)
|
(<1 - <1)
|
(1 - 6)
|
Chemical Oxygen Demand (mg/L)
|
<40 See Note (2)
|
<40 See Note (2)
|
2
|
3
|
17
|
(<40 - <40)
|
(<40 - <40)
|
(2 - 2)
|
(2 - 3)
|
(4 - 28)
|
Oil & grease (mg/L)
|
0.8
|
0.6
|
1.1
|
0.8
|
1.7
|
(0.8 - 0.8)
|
(0.6 - 0.6)
|
(1 - 1.1)
|
(0.6 - 0.9)
|
(0.8 - 2.6)
|
Faecal coliforms (cfu/100mL)
|
103
|
693
|
257
|
14,945
|
114,600
|
(4 - 270)
|
(250 ¡V 1,200)
|
(150 - 420)
|
(86 ¡V 44,000)
|
(1300 ¡V 340,000)
|
E. coli (cfu/100mL)
|
99
|
663
|
247
|
14,929
|
104,400
|
(3 - 260)
|
(210 ¡V 1,200)
|
(120 - 420)
|
(78 ¡V 44,000)
|
(1300 ¡V 310,000)
|
Ammonia-nitrogen (mg/L)
|
0.05
|
0.05
|
0.01
|
0.02
|
0.32
|
(0.02 - 0.06)
|
(0.02 - 0.06)
|
(0.01 - 0.02)
|
(0.02 - 0.02)
|
(0.07 - 0.75)
|
Nitrate-nitrogen (mg/L)
|
0.06
|
0.08
|
0.1
|
0.07
|
0.19
|
(0.03 - 0.08)
|
(0.06 - 0.1)
|
(0.09 - 0.1)
|
(0.06 - 0.09)
|
(0.13 - 0.25)
|
Total Kjeldahl nitrogen (mg/L)
|
0.36
|
0.17
|
0.15
|
0.09
|
1.24
|
(0.32 - 0.45)
|
(0.14 - 0.2)
|
(0.07 - 0.22)
|
(0.09 - 0.09)
|
(0.61 - 1.85)
|
Ortho-phosphate (mg/L)
|
<0.01
|
<0.01
|
<0.01
|
<0.01
|
0.31
|
(<0.01 - <0.01)
|
(<0.01 - <0.01)
|
(<0.01 - <0.01)
|
(<0.01 - <0.01)
|
(0.21 - 0.39)
|
Total phosphorus (mg/L)
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
0.6
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(0.3 - 1.1)
|
Total sulphide (mg/L)
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
<0.02
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
(<0.02 - <0.02)
|
Aluminium (µg/L)
|
24
|
64
|
89
|
67
|
132
|
(18 - 31)
|
(51 - 73)
|
(68 - 100)
|
(52 - 80)
|
(72 - 214)
|
Cadmium (µg/L)
|
<0.1
|
<0.1
|
<0.1
|
<0.1
|
<0.1
|
(<0.1 - <0.1)
|
(<0.1 - <0.1)
|
(<0.1 - <0.1)
|
(<0.1 - <0.1)
|
(<0.1 - <0.1)
|
Chromium (µg/L)
|
4
|
3
|
2
|
1
|
<1
|
(4 - 4)
|
(2 - 3)
|
(1 - 2)
|
(1 - 2)
|
(<1 - <1)
|
Copper (µg/L)
|
6
|
3
|
<1
|
<1
|
4
|
(4 - 7)
|
(2 - 5)
|
(<1 - <1)
|
(<1 - <1)
|
(1 - 5)
|
Lead (µg/L)
|
<1
|
<1
|
<1
|
<1
|
<1
|
(<1 - <1)
|
(<1 - <1)
|
(<1 - <1)
|
(<1 - <1)
|
(<1 - <1)
|
Zinc (µg/L)
|
15
|
11
|
<10
|
63
|
19
|
(15 - 15)
|
(11 - 11)
|
(<10 - <10)
|
(10 - 116)
|
(17 - 21)
|
Average Flow Velocity (m/s)
|
0.3
|
0.2
|
<0.1
|
0.2
|
0.3
|
(0.3 - 0.3)
|
(0.1 - 0.2)
|
(<0.1 - <0.1)
|
(0.2 - 0.2)
|
(0.3 - 0.3)
|
Notes:
(1) Wet season water quality surveys were conducted on
9,
11 and 13 June 2015.
(2) Reporting limit was amplified since dilution was
required for the laboratory test due to interference of high chloride content
in the water samples. The
high chloride content in samples collected at downstream of Shing Mun River
(R1) and streams along Mui Tsz Lam Road (R2a) was be due to the effect of
marine water (with Sodium Chloride) at the adjacent Sha Tin Hoi.
(3) cfu ¡V colony forming unit.
5.3.3.4
In general, the levels of SS
and BOD5 measured at all stations were low. The DO levels measured at all the
stations are considered satisfactory except at the lower reach of Miu Tsz Lam
Road Stream (Station R2a) where backflow of seawater and poor water circulation
is observed, and the DO levels recorded at this station were thus relatively
low in the wet season. Relatively
high E.coli Levels were measured in both Miu Tsz Lam Road Stream and Ma
Tai Stream which indicated that these inland waters could be contaminated by
sewage discharges.
5.4.1.1
WSRs in Tolo Harbour and
Victoria Harbour were identified with reference to Annex 14 of the EIAO-TM.
5.4.2.1
The treated sewage effluent
from daily operation of the Project would be discharged into the marine water
within the Victoria Harbour WCZ under the THEES. Major WSRs identified in Victoria
Harbour are listed below and their indicative locations are given in Figure No. 6.334056/EIA/5.02.
¡P
WSD Flushing Water Intakes;
¡P
Cooling Water Intakes;
¡P
Typhoon Shelters; and
¡P
Potential Water Sports Area at Kai Tak.
5.4.2.2
The feasibility of locating a
potential water sports center within the Kai Tak Development (KTD) area is
being investigated under a separate KTD study. The potential water sports area was
included as a planned WSR for water quality impact assessment as shown in Figure No. 60334056/EIA/5.02.
5.4.2.3
The existing intake of the DCS
at Kai Tak (currently in operation) is shown in Figure No. 60334056/EIA/5.02. A new Kai Tak DCS
scheme with different intake location is currently being proposed and planned
under the separate KTD study. The
proposed changes in the DCS intake location were considered and assessed under
this EIA as detailed in Sections 5.6.2.35 to 5.6.2.39. The locations of the planned
Kai Tak DCS intake points are also shown in Figure No. 60334056/EIA/5.02.
5.4.2.4
Based on the review of routine
river water quality monitoring data collected by EPD in 2014, the existing
baseline water quality of KTN significantly exceeded the WQO for inland water
of several parameters such as E.coli and BOD. Although river improvement
works are currently carried out at KTN, the proposed works do not aim to
improve the water quality of the nullah water (i.e. comprised of treated sewage
effluent and urban runoff). Therefore, it is suitable to consider this nullah
as a non-sensitive receiver for the treated effluent discharge. The same
approach has been adopted in the past relevant EIAs such as the approved EIAs for
¡§STSTW Stage III Extension¡¨, ¡§TPSTW Stage V¡¨ and ¡§KTD¡¨.
5.4.3.1
Any discharges from the Project
works would potentially affect both the inland and marine waters within the
Tolo Harbour and Channel WCZ. The
existing emergency submarine outfall of the STSTW will be retained under the
Project for emergency discharge, if required, in the future. There is no existing or planned seawall
outfall available for the emergency discharge. Location of this emergency
outfall in relation to the identified WSRs is shown in Figure No. 60334056/EIA/5.01
and Figure No.
60334056/EIA/5.03.
Marine Water
5.4.3.2
Key marine WSRs in Tolo Harbour
are listed below and their indicative locations are shown in Figure No. 60334056/EIA/5.03.
¡P
Two WSD Flushing Water Intakes at Sha Tin and
Tai Po respectively;
¡P
Cooling Water Intake for Marine Science
Laboratory of CUHK;
¡P
Bathing Beach at Lung Mei;
¡P
Shuen Wan Typhoon Shelter;
¡P
Various Corals / Mangroves along the Coastlines
of Tolo Harbour;
¡P
Four Fish Culture Zones (FCZs) at Yim Tin Tsai,
Yim Tin Tsai (East), Yung Shue Au and Lo Fu Wat respectively;
¡P
Three Sites of Special Scientific Interest
(SSSI) at Ting Kok, Kei Ling Ha Mangal and Hoi Ha Wan respectively;
¡P
Potential Subzone of Yim Tin Tsai FCZ near
Centre Island; and
¡P
Important Nursery Area for Commercial Fisheries
Resources at Three Fathoms Cove.
Inland Water
5.4.3.3
Major inland water bodies
within 500m from the site boundary of the Project works are listed below and
their indicative locations are shown in Figure
No. 60334056/EIA/5.01.
¡P
Shing Mun River;
¡P
Streams along Mui Tse Lam Road and in Turret
Hill around Mui Tse Lam Road; and
¡P
Ma Tai Stream.
5.4.3.4
Full descriptions and locations
of the ecological / fisheries resources in the Study Area are separately
presented in Section 8
and Section 9 of
this EIA Report.
Water Gathering Grounds
5.4.3.5
The existing water gathering
grounds are located outside the works area of the Project and upstream to the
Project works. That is, the
watercourses identified at or near the Project works areas are running from the
water gathering grounds towards the Project works areas. No aboveground
structure would be constructed within the water gathering grounds and the
nearest aboveground structure would be located within the secondary portal (as
shown in Figure No.
60334056/EIA/5.01) which would be located outside the boundary of the
water gathering grounds. Thus, the
water source of the existing water gathering grounds is not expected to be
affected during both construction and operational phases of the Project.
Water Recreational Uses
5.4.3.6
The inland water (i.e. Shing
Mun River) and the marine water in Tolo Harbour and Channel WCZ are designated
under the WPCO as secondary contact recreation subzone, which can be used for
water sports and water recreational activities (e.g. dragon boating, sailing,
rowing etc.). The E. coli
bacteria would be the principle parameter for assessing the acceptability of
using the inland and marine water for water sports or secondary contact
recreation activities with a WQO of not exceeding 610 no./100mL (calculated as
the geometric mean of all samples collected in one calendar year).
Overview of
Project Construction
5.5.1.1
Construction of the Project
will be carried out in the Tolo Harbour and Channel WCZ only. No construction works will be undertaken in the Victoria Harbour WCZ.
5.5.1.2
The proposed construction works
would not alter any streams and water courses identified in the study area and
also will be designed not to affect normal operation of the existing
STSTW.
Justifications of No Disturbance to
Marine or Riverbed Sediments
5.5.1.3
This Project will only involve
land-based construction works. Under the Project design, any Project
effluent bypass to the Tolo Harbour will be discharged through the existing
emergency submarine outfall of the STSTW, which is located in Sha Tin Hoi as
shown in Figure No.
60334056/EIA/5.01.
5.5.1.4
Different emergency outfall
options that have been considered for this Project are described in Section 2 (also see Figures No. 60334056/EIA/2.05 - 2.09). The existing emergency submarine outfall of STSTW would have the
best environmental performance as compared to other new outfall options,
according to the distance from the shore (which affects the current speed and
tendency of horizontal mixing and dispersion of pollutants) as well as the
water depth (which affects the tendency of vertical mixing). The existing emergency submarine outfall
is located in the deepest location of Sha Tin Hoi (where local dredging was
previously carried out) and also at a point farthest from the surrounding
seawalls. All the other new outfall
options can only be built in shallower waters and closer to the seawall with
slower currents and thus poorer pollutant dispersion. Together with other factors as discussed
in Section 2, the existing submarine
outfall has been selected as the final scheme for this Project. Since the level of the CSTW is much higher
than the existing emergency submarine outfall, it is not expected that the
hydraulic performance of this outfall during the Project operation is worse
than the existing condition.
5.5.1.5
According to the condition
survey of existing emergency submarine outfall, the overall performance is in a
good condition and there is no sign of clogging, capacity and aging. Thus, this
existing emergency submarine outfall is suitable for temporary effluent bypass
under both regular THEES maintenance events and emergency situations. Regular
outfall survey / maintenance / repair works will be conducted to avoid
malfunctioning of this existing emergency submarine outfall (twin pipe) during
operation of the CSTW, following the existing practice of STSTW. Currently,
there is only one existing emergency submarine outfall available for emergency
discharge from the existing STSTW.
Since the existing emergency submarine outfall will be adopted for the
CSTW, construction of new outfall is not required. The Project construction would not
disturb the marine sediments and would not affect the sediment quality.
5.5.1.6
New land-based emergency
discharge pipes connecting the CSTW to the existing emergency submarine outfall
will be constructed under this Project.
A section of these new emergency discharge pipes will be built underneath Shing
Mun River by trenchless method i.e. pre-drilling of a hole of appropriate size
beneath the riverbed of Shing Mun River and insertion of a pipeline along the
pre-drilled hole (beneath the riverbed) by hydraulic jack. This construction method would not cause
disturbance to the riverbed sediments and thus is not expected to affect the
river sediment quality.
THEES Connection Works
5.5.1.8
On the other hand, under the
existing practice, regular inspection and repair of the THEES would be carried
out when necessary to maintain proper functioning and integrity of the THEES
according to the requirement under Clause 5.1of the existing Environmental Permit (EP) for ¡§TPSTW Stage V¡¨ (No. EP-265/2007/A). During each THEES maintenance event,
secondarily treated and disinfected effluent from TPSTW and STSTW would be
temporarily discharged to the Tolo Harbour to provide a dry zone within the
THEES tunnel for a maximum duration of 4 weeks as discussed in the EIA Report
for ¡§TPSTW Stage V¡¨. In order to avoid potential cumulative water quality
impact to the sensitive Tolo Harbour, the necessary THEES connection works
required for this Project will
be split into smaller sections and each section will be arranged to be
undertaken within the regular THEES maintenance windows for a duration not
longer than 4 weeks each outside the algae blooming season in accordance with
the existing EP requirement and the frequency of THEES maintenance will be no
more than once per year during the construction phase of the Project, as
confirmed by DSD. Hence, no
additional cumulative water quality effect on the Tolo Harbour waters will be
induced by the proposed THEES connection works. DSD will closely liaise with
the Contractor during the construction phase of the Project so that the THEES
connection works will be conducted within the regular THEES maintenance windows
and also outside the algae blooming season (January to May).
Key
Sources of Water Quality Impacts
5.5.1.9
Potential sources of water
quality impact associated with the Project during the construction phase would
be limited to the land-based construction works as identified as follows:
¡P
General construction activities;
¡P
Construction site run-off;
¡P
Accidental spillage and potential contamination
of surface water and groundwater;
¡P
Sewage effluent from construction workforce;
¡P
Construction works in close proximity of inland
water;
¡P
Infiltration of groundwater arising from the
cavern formation; and
¡P
Groundwater from potentially contaminated areas
Land-Based
Construction
General Construction Activities
5.5.1.10
Various types of construction
activities may generate wastewater. These include general cleaning and
polishing, wheel washing, dust suppression and utility installation. These
types of wastewater would contain high concentrations of SS. Various
construction works may also generate debris and rubbish such as packaging,
construction materials and refuse.
Uncontrolled discharge of site effluents, rubbish and refuse generated
from the construction works could lead to deterioration in water quality.
Construction Site Run-off
5.5.1.11
Potential pollution sources of
site run-off may include:
¡P
Run-off and erosion of exposed bare soil and earth,
drainage channel, earth working area and stockpiles;
¡P
Release of any bentonite slurries, concrete
washings and other grouting materials with construction run-off or storm water;
¡P
Wash water from dust suppression sprays and
wheel washing facilities; and
¡P
Fuel, oil and lubricants from maintenance of
construction vehicles and equipment.
5.5.1.12
During rainstorms, site run-off
would wash away the soil particles on unpaved lands and areas with the topsoil
exposed. The run-off is generally
characterized by high concentrations of SS. Release of uncontrolled site run-off
would increase the SS levels and turbidity in the nearby water
environment. Site run-off may also
wash away contaminated soil particles and therefore cause water pollution.
5.5.1.13
Wind blown dust would be generated
from exposed soil surfaces in the works areas. It is possible that wind blown dust
would fall directly onto the nearby water bodies when a strong wind
occurs. Dispersion of dust within
the works areas may increase the SS levels in surface run-off causing a
potential impact to the nearby sensitive receivers.
Accidental Spillage and Potential Contamination of Surface
Water and Groundwater
5.5.1.14
The use of engine oil and
lubricants, and their storage as waste materials has the potential to create
impacts on the water quality of adjacent inland water bodies or storm drains if
spillage occurs. Waste oil may infiltrate into the surface soil layer, or
run-off into local water courses, increasing hydrocarbon levels. Groundwater
pollution may also arise from the improper use and storage of chemicals and
petroleum products within the site area where groundwater infiltrates into the
area. Infiltration of groundwater may occur at area where there are faults
and/or fissures in the rock mass. The spillage of petroleum products and
chemicals shall be handled properly to avoid any potential surface water or
groundwater contamination.
Sewage Effluent from Construction Workforce
5.5.1.15
During the construction of the
Project, the workforce on site will generate sewage effluents, which are
characterized by high levels of BOD, ammonia and E. coli counts.
Potential water quality impacts upon the local drainage and fresh water system
may arise from these sewage effluents, if uncontrolled.
Construction
Works in Close Proximity of Inland Water
5.5.1.16
Construction activities in
close vicinity to the inland water courses may pollute the inland water bodies
due to the potential release of construction wastes. Construction wastes are
generally characterized by high concentration of SS and elevated pH. Mitigation
measures should be implemented to control the release of construction waste and
site effluent into the nearby inland water bodies.
Groundwater
Infiltration and Change in Groundwater Level arising from Formation of Caverns
5.5.1.17
Construction of rock caverns
and tunnels may result in infiltration of groundwater. The major concern from
these construction activities would be the increase in site runoff and the
associated potential drawdown of groundwater in any soil and aquifer layers).
Groundwater infiltration would affect the construction works and infiltrated
water could carry away silt and other contaminants from site into the site
drainage. Considerations should be taken in cavern design to minimize the
infiltration of groundwater and the potential impacts from the change in
groundwater level.
Groundwater from Potentially Contaminated Area
5.5.2
Operational Impacts
Effluent Discharges
5.5.2.1
The key water quality issue of
this Project is the impact of sewage effluent discharged from the CSTW.
Design Flow and Effluent Standards
5.5.2.3
The Enhanced 2011-based TPEDM,
complied in January 2015 by PlanD, was the latest authoritative data on
population and employment projection at the time this EIA Report was
prepared. This set of data was
designed for Years 2011, 2021, 2026, 2031, 2036 and 2041 scenarios.
Table 5.9 Design
Standards of the Existing STSTW, Proposed CSTW and Existing TPSTW
Parameter
|
Unit
|
Design Standards
|
95th Percentile
|
Annual Average
|
Upper Limit
|
Monthly Geometric Mean
|
BOD5
|
mg/L
|
20
|
-
|
40
|
-
|
SS
|
mg/L
|
30
|
-
|
60
|
-
|
NH3-N
|
mg/L
|
-
|
5
|
10
|
-
|
Total-N
|
mg/L
|
-
|
20
|
35
|
-
|
E. coli
|
no./100mL
|
15,000
|
-
|
-
|
1,000
|
Treated Effluent Reuse
Occasional
Effluent Overflow
Key Sources of Water Quality Impacts from Existing STSTW and CSTW
5.5.2.8
Major sources of water quality
impacts as listed below are identified for the operation of the existing STSTW
under the baseline ¡§without Project¡¨ scenario. Since this Project only involves
relocation of the STSTW to caverns without changing the effluent flow and load
as well as the discharge location of the existing STSTW, the key sources of
water quality impact identified for the future CSTW under the ¡§with Project¡¨
scenario would be the same as that identified for the existing STSTW as listed
below.
¡P
Secondarily treated and disinfected effluent
discharge to Victoria Harbour under the THEES including the effluents from
STSTW (or CSTW) and TPSTW during normal plant operation;
¡P
Emergency discharge of primarily treated/
settled sewage effluent to Tolo Harbour from the STSTW (or CSTW) in case of
power / plant failure (including both duty and standby) ;
and
¡P
Secondarily treated and disinfected effluent
discharge to Tolo Harbour including the effluents from STSTW (or CSTW) and
TPSTW during maintenance or closure of the THEES effluent export tunnel.
5.5.2.9
Concurrent discharge of raw
sewage from both STSTW and TPSTW has never occurred according to the past
records available from DSD. Backup power supply, standby equipment and standby
treatment units will be provided for the proposed CSTW. In terms of the
upstream pumping stations, standby pump and backup power supply in the form of
dual / ring circuit power supply or generator would be provided to secure electrical
power supply. Hence, the likelihood of complete failure of both ¡§normal¡¨ and
¡§standby¡¨ power / equipment at both STSTW (or CSTW) and TPSTW and / or the
upstream pumping stations together at the same time is considered as an
extremely remote situation according to the past operation record. Following
the approach of past approved EIAs for ¡§TPSTW Stage V¡¨ and ¡§STSTW Stage III
Extension¡¨, scenario with power / plant failure of two or more of these
facilities together will not be considered in this assessment.
5.5.3.1
Sludge from daily operation of
the existing STSTW as well as the proposed CSTW in the future would require
sludge dewatering before final disposal.
Any wastewater generated from the sludge treatment process may cause
water pollution, if uncontrolled.
5.5.4.1
The future CSTW will be fully
enclosed inside the rock cavern, and hence no non-point source surface runoff
will be generated from the main Project site during the operational phase. However, non-point source storm
pollution would be generated from the open paved areas associated with the
cavern development including the access road and the main and secondary portal
areas.
5.6.1.1
The WSRs that may be affected
by the Project construction have been identified. Potential sources of water quality
impact that may arise during the construction works were described. Pollutants from point discharges and
non-point sources that could affect the quality of surface and ground water
have been identified. All the
identified sources of potential water quality impact were then evaluated and
their impact significance determined.
The need for mitigation measures to reduce any identified adverse
impacts on water quality to acceptable levels was determined.
Modelling
Tools
5.6.2.1
Computer modelling was used to
assess the water quality impacts due to the sewage effluent discharge.
5.6.2.2
Delft3D suite of models,
developed by Deltares, was used as the modelling platforms with the
Deflt3D-FLOW module and the Delft3D-WAQ module used for hydrodynamic
simulations and water quality simulations respectively. To simulate the potential impact from
the Project on both Tolo Harbour and Victoria Harbour, two Delft3D models were
used respectively:
¡P
Tolo Harbour (TH) Model; and
¡P
Kai Tak Development (KTD) Model.
5.6.2.3
Delft3D-FLOW is a 3-dimensional
hydrodynamic simulation programme which calculates non-steady flow and
transport phenomena that result from tidal and meteorological forcing on a
curvilinear, boundary fitted grid.
5.6.2.4
Delft3D-WAQ is a water quality
model tool for numerical simulation of various physical, biological and
chemical processes including the sedimentation and sediment erosion processes
in 3 dimensions. It solves the advection-diffusion-reaction equation for a
predefined computational grid and for a wide range of model substances.
TH Model
5.6.2.5
The TH Model accepted by EPD
and developed and updated under the approved EIA for ¡§TPSTW Stage V¡¨, was used
for hydrodynamic and water quality modelling in Tolo Harbour. This detailed model was fully calibrated
and verified by comparing computational results with field measurements. The
set-up of this TH model was developed following the same set-up of the Tolo
Harbour and Mirs Bay (THMB) Model developed by EPD under Agreement No. WP01-27.
KTD Model
5.6.2.6
The detailed KTD model
developed under approved EIA for KTD was used for hydrodynamic and water quality
modelling in Victoria Harbour. It
was updated according to the changes in coastline configurations and changes in
bathymetry due to the planned projects as listed in Table 5.10. The grid layout of the KTD model has a
high resolution at the KTAC and Kowloon Bay area. There are a total 4 grid cells across
the KTAC to resolve transverse variations of the KTAC. The performance of KTD model was
extensively calibrated and verified by comparing computational results with the
field measurements collected in the KTAC, Kowloon Bay and Victoria Harbour
Channel under the KTD project.
Model Bathymetry
5.6.2.7
The bathymetry schematization of
the above two models has been updated based on the depth data from the latest
marine charts (Charts for Local Vessels 2013) produced by the Hydrographic
Office of Marine Department, with incorporation of the projects affecting
bathymetry including Central Kowloon Route, Sha Tin to Central Link, Kai Tak
Cruise Terminal and Dredging Works for Sufficient Depth for Kwai Tsing
Container Terminal and its Basin as listed in Table 5.10.
Simulation Periods
5.6.2.8
For both TH and KTD Models, the
water quality simulations (using Delft3D-WAQ) were conducted for 1 complete
calendar year. The hydrodynamic simulations
(using Delft3D-FLOW) were performed for both dry and wet seasons. For each season, the simulation period
of the hydrodynamic model covers a 15-day full spring-neap cycle (excluding the
spin-up period). The hydrodynamic
results were used repeatedly to drive the water quality simulations for one
complete calendar year (excluding the spin-up period). The monthly variations in solar
radiation and wind velocity over the entire year were incorporated into the
water quality simulation.
Spin-up Periods
5.6.2.9
For TH Model, a spin-up period
of 1 complete calendar year was provided for each of the hydrodynamic
simulation and water quality simulation.
The long spin-up periods were confirmed under approved EIA for ¡§TPSTW
Stage V¡¨ to be necessary to produce acceptable model results, following the
same modelling approach adopted for the THMB Model developed under Agreement
No. WP01-27.
Other Model Settings and Model Parameters
5.6.2.11
The general settings of the TH
and KTD Models such as the approach to the setup of boundary and initial
conditions as well as the model coefficients and parameters followed those
adopted under the approved EIA for ¡§TPSTW Stage V¡¨ and ¡§KTD¡¨ respectively. It
should be noted that the TH Model was developed following the same methodologies
and settings developed for the THMB Model under Agreement No. WP01-27.
Assessment
Year and Coastline Configurations
5.6.2.12
Major factors that would affect
the water quality simulated would be (i) the change in pollution loading
discharged to marine waters; and (ii) the change in coastline configurations in
different time horizons.
5.6.2.13
The recommended design capacity
of the Project is 340,000 m3 per day (which is same as the existing
design capacity of STSTW) as discussed in Sections 5.5.2.2
to 5.5.2.4. The Ultimate Design Scenario (UDS) was selected as the time
horizon for reviewing the operational water quality impact as it would
represent the worst case in terms of the amount of Project flow. The maximum Project design capacity of
340,000 m3 per day was adopted under the UDS for worst case
assessment.
5.6.2.14
In UDS, the planned
reclamations as listed in Table 5.10 would be completed and therefore would
represent a worst case in terms of the tidal flushing and assimilation capacity
of the marine water. Table 5.10 shows the coastal
development projects incorporated in the coastline configurations for
modelling.
Table 5.10 Projects
Incorporated in Modelling
5.6.2.15
The coastal project ¡§Cross Bay
Link (CBL), Tseung Kwan O¡¨ was not considered in the modelling. The CBL is a bridge project which would
involve construction of marine piers / piles only with limited effect on the
tidal flushing (as predicted in the approved EIA for CBL). The proposed CBL is located in Junk Bay
outside the Victoria Harbour WCZ.
It is therefore considered that the CBL project would unlikely affect
the overall modelling results for the present Study.
Background
Pollution Loading
5.6.2.17
The pollution loading of the
existing STSTW / proposed CSTW and the TPSTW used for modelling was compiled
with reference to their design flow and loads as detailed in Table
5.14 below. The pollution loading of other background discharges to the
marine water was also compiled for input to the water quality model for
cumulative assessment.
Harbour Area Treatment Scheme
Table 5.11 Pollution
Loading from Stonecutters Island Sewage Treatment Works under HATS Stage 2A
Parameters
|
HATS Stage 2A (1)
|
Design Flow (m3 per
day)
|
2.45M
(2)
|
Biochemical Oxygen Demand (BOD)
(mg/L)
|
68
|
Suspended Solids (SS) (mg/L)
|
42
|
Organic Nitrogen (mg N/L)
|
9.93
|
Ammonia Nitrogen (NH3-N)
(mg N/L)
|
17.43
|
E. coli (no./100mL)
|
20,000
|
Total Phosphorus (mg P/L)
|
3
|
Orthophosphate (mg P/L)
|
1.8
|
Silicate (mg SiO2/L)
|
8.6
|
Copper (mg/L)
|
0.023
|
Total Nitrite and Nitrate (mg N/L)
|
0
|
Note: (1) Based on the assumptions adopted under the
approved EIA for HATS Stage 2A.
(2) Ultimate Design Flow
adopted for HATS Stage 2A.
Kai Tak Development Area
Tolo Harbour
¡P
Tai Po Kau Stream
¡P
Tung Tze Stream
¡P
Shan Liu Stream
¡P
Lam Tsuen River and Tai Po River
¡P
Shing Mun River
5.6.2.21
These five storm catchments
were selected as the indicative discharge points in the water quality model for
distribution of background storm pollution loading generated in the Tolo
Harbour catchment, while the other streams were considered less significant in
terms of the amount of developed areas within their catchments such as streams
at country park areas with negligible developed areas. Indicative catchment areas of the five
storm catchments are shown in Appendix 5.02. Theses indicative catchment areas were
adopted as the basic boundaries for compiling the background storm pollution
load. The background storm
pollution loading was compiled to the level of these catchment areas and the
associated loading was distributed to the five selected river outlets (as shown
in Appendix 5.02)
respectively. The storm pollution
could be contributed from sewage discharge from aged sewerage / drainage
systems or unsewered developments or expedient / cross connections, if any,
within the catchment. The method in
estimation of the dry weather storm pollution contributed from aged sewerage /
drainage or unsewered developments or expedient / cross connections within the
catchment of Tolo Harbour is described in Sections
5.6.2.22 and 5.6.2.23 below.
The rainfall related non-point source pollution was separately estimated
for the catchment areas in accordance with the methodology given in Sections
2.8 to 2.14 of Appendix
5.01a. The rainfall related
pollution load was added on top of the dry weather storm pollution to give the
overall pollution loading. The final background storm pollution loading
inventory (with incorporation of the rainfall related load) compiled for the
five major storm catchments in Tolo Harbour are presented in Appendix 5.01b.
5.6.2.23
The projected population from
the TPEDM is however provided at Planning Vision and Strategy (PVS) zones,
which are different from the layout of the five catchment areas as defined in Appendix
5.02. Population and employment data for each
river catchment area were estimated by overlaying the PVS zones on top of the
river catchment area. Pro-rata
method was used to allocate the population data to the river catchment area
according to the share of the PVS zone area accounted by the river catchment
area. The Enhanced 2011-based TPEDM
were available for Years 2011, 2021, 2026, 2031, 2036 and 2041. The population used to estimate the
amount of background dry weather storm pollution in the modelling year (UDS)
was based on a 10% extrapolation of the projected population for 2041. The purpose of adding a prudence
allowance of 10% in the load estimation for these background discharges was to
adopt a conservative approach to address the uncertainties on the population
projection. It was assumed that 5%
of the total pollution load generated in these catchments would be lost to the
storm water and discharged to the marine water as a result of aged sewerage /
drainage systems or unsewered properties and expedient connections (if any).
Since the Government will continue to remove the pollution sources and rectify
expedient connections, it is expected that the storm pollution situations in the
future will be minimized. Thus, the
percentage of pollution load lost to the storm system of 5% is considered
reasonable. This percentage was also adopted in other approved EIAs such as the
EIA for ¡§TPSTW Stage V¡¨. The key steps for calculation of the background pollution load are
summarized as follows:
¡P
Total Population within the catchment area in
UDS = Year 2041 Population Data x 1.1
¡P
Total Pollution Load (TPL) generated in the
catchment area in UDS = Total Population within the catchment area in UDS x Per
Head Load Factor (as listed in Section 4.3 of Appendix 5.01a)
¡P
Pollution Load discharged into the marine water
from the catchment area in UDS for model input = TPL generated in the catchment
area in UDS x (5% sewage lost to the drainage system)
Other Background Sources
5.6.2.24
Domestic, commercial and
industrial activities are the principle sources of background pollution load
discharge into the marine water.
The pollution loading for the background discharges outside the
catchments of KTD waters and Tolo Harbour was also compiled theoretically for
UDS using the Enhanced 2011-based TPEDM.
Appendix 5.01a
gives the detailed methodology for compiling the background pollution
loading. The inventory has
incorporated all possible background pollution sources within the Hong Kong
waters for input to water quality models for cumulative assessment.
Diurnal
Flow Pattern
5.6.2.25
The average diurnal flow pattern
of STSTW derived from dry days data measured in the period from December 2013
to November 2014 is shown in Table 5.12. The percentages in Table
5.12 were applied to the daily flow as shown in Table
5.14 to derive the hourly dry weather diurnal load from the Project as
model inputs. The same 24-hour
diurnal load pattern was used in the model throughout the simulation year.
Table 5.12 Dry
Weather Diurnal Flow Pattern of STSTW
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
0:00
|
5.80%
|
6:00
|
2.29%
|
12:00
|
4.35%
|
18:00
|
4.28%
|
1:00
|
4.35%
|
7:00
|
3.14%
|
13:00
|
4.12%
|
19:00
|
4.77%
|
2:00
|
3.16%
|
8:00
|
4.56%
|
14:00
|
4.09%
|
20:00
|
5.14%
|
3:00
|
2.55%
|
9:00
|
4.71%
|
15:00
|
3.84%
|
21:00
|
5.58%
|
4:00
|
2.18%
|
10:00
|
4.63%
|
16:00
|
3.72%
|
22:00
|
6.09%
|
5:00
|
2.06%
|
11:00
|
4.51%
|
17:00
|
3.90%
|
23:00
|
6.19%
|
5.6.2.26
The average diurnal flow pattern
of TPSTW derived from the approved EIA for ¡§TPSTW Stage V¡¨ is shown in Table
5.13, which will also be applied to the daily flow of TPSTW as shown in Table
5.14 to derive the hourly dry weather diurnal load from the TPSTW as
model inputs. Again, the same
24-hour diurnal load pattern was used in the model throughout the simulation
year.
Table 5.13 Projected
Dry Weather Diurnal Flow Pattern of TPSTW
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
Hour
|
% of Daily Flow
|
0:00
|
4.51%
|
6:00
|
2.71%
|
12:00
|
4.72%
|
18:00
|
4.21%
|
1:00
|
4.44%
|
7:00
|
3.08%
|
13:00
|
4.58%
|
19:00
|
4.95%
|
2:00
|
3.83%
|
8:00
|
4.72%
|
14:00
|
4.11%
|
20:00
|
4.86%
|
3:00
|
3.36%
|
9:00
|
4.35%
|
15:00
|
4.06%
|
21:00
|
5.32%
|
4:00
|
2.94%
|
10:00
|
4.44%
|
16:00
|
4.35%
|
22:00
|
5.09%
|
5:00
|
2.71%
|
11:00
|
3.97%
|
17:00
|
4.11%
|
23:00
|
4.58%
|
Summary
of Modelling Scenarios for
Construction and Operational Phases
Table 5.14 Summary
of Water Quality Modelling Scenarios
Scenario
|
Phase
|
Daily
Flow
(m3
per day)
|
Description
|
Effluent
Standard
|
Biochemical
Oxygen Demand (BOD)
(mg/L)
|
Total
Suspended Solids (SS)
(mg/L)
|
Total
Kjeldahl Nitrogen (TKN)
(mg/L)
|
Total
Nitrogen (Total N)
(mg/L)
|
Ammonia
Nitrogen (NH3-N)
(mg/L)
|
E.
coli
(no./100mL)
|
Kai Tak Development Model
|
1 (UDS)
|
Baseline
(without KTD
mitigation measure + normal THEES operation with or without this Project)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
¡P No
opening at former airport runway
¡P Do-nothing
condition in KTD waters
¡P THEES
loading based on design effluent standards of TPSTW and STSTW
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
STSTW /
CSTW: current & future
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
2a (UDS)
|
Cumulative
impact
(with KTD
mitigation measure + normal THEES operation with or without this Project)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
¡P No
opening at former airport runway but use of Interception and Pumping (IP)
Scheme to divert some water from KTN and KTAC to Kowloon Bay (following the
final recommendation of Agreement No. CE30/2008 (CE))
¡P THEES
loading based on design effluent standards of TPSTW and STSTW
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
STSTW /
CSTW: current & future
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
2b (UDS)
|
Cumulative impact
(with KTD mitigation measure + normal THEES
operation with or without this Project)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
¡P 150m
opening at former airport runway (following the alternative option considered
under Agreement No. CE30/2008 (CE))
¡P THEES
loading based on design effluent standards of TPSTW and STSTW
|
TPSTW: current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
STSTW / CSTW: current & future
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
3a (UDS)
|
Cumulative
impact
(with KTD
mitigation measure + normal THEES operation with or without this Project)
|
120,000
(TPSTW) (1) + 340,000 ( STSTW / CSTW)
|
¡P No
opening at former airport runway but use of Interception and Pumping (IP)
Scheme to divert some water from KTN and KTAC to Kowloon Bay (following the
final recommendation of Agreement No. CE30/2008 (CE))
¡P THEES
loading input based on actual performance of TPSTW and STSTW
|
TPSTW:
current
|
9.85
(7)
|
22.00
(7)
|
7.78 (7)
|
16.7 (7)
|
4.11 (7)
|
1,000 (6)
|
STSTW /
CSTW: current & future
|
9.40
(7)
|
20.15
(7)
|
5.04 (7)
|
17 (7)
|
2.64 (7)
|
1,000 (6)
|
3b (UDS)
|
Cumulative impact
(with KTD mitigation measure + normal THEES
operation with or without this Project)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
¡P 150m opening at
former airport runway (following of the alternative option considered under
Agreement No. CE30/2008 (CE))
¡P THEES
loading input based on actual performance of TPSTW and STSTW
|
TPSTW: current
|
9.85 (7)
|
22.00 (7)
|
7.78 (7)
|
16.7 (7)
|
4.11 (7)
|
1,000 (6)
|
STSTW / CSTW: current & future
|
9.40 (7)
|
20.15 (7)
|
5.04 (7)
|
17 (7)
|
2.64 (7)
|
1,000 (6)
|
Tolo Harbour Model
|
4 (UDS)
|
¡§Without
Project¡¨ condition
|
Partial
overflow, see Table 5.17 below
|
Partial
overflow of secondarily treated and disinfected effluent from TPSTW and
existing STSTW under ¡§without Project¡¨ situation (10)
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
Existing
STSTW: current
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
5 (UDS)
|
¡§With
Project¡¨ condition
(normal
operation)
|
Partial
overflow, see Table 5.18 below
|
Partial overflow
of secondarily treated and disinfected effluent from TPSTW only after Project
commission (11)
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
6a (UDS)
|
THEES
maintenance discharge (following existing practice)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
Temporary
bypass of secondarily treated and disinfected effluent from TPSTW and STSTW /
CSTW within algae blooming season
(for 4
weeks)
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
STSTW /
CSTW: current & future
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
6b (UDS)
|
THEES
maintenance discharge (outside algae blooming season)
|
120,000
(TPSTW) (1) + 340,000 (STSTW / CSTW)
|
Temporary
bypass of secondarily treated and disinfected effluent from TPSTW and STSTW /
CSTW outside algae blooming season
(for 4
weeks)
|
TPSTW:
current
|
20 (2)
|
30 (2)
|
11.80 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
STSTW /
CSTW: current & future
|
20 (2)
|
30 (2)
|
13.28 (3)
|
20 (4)
|
5 (5)
|
1,000 (6)
|
7 (UDS)
|
Emergency
discharge (complete power failure)
|
340,000
(STSTW / CSTW)
|
Emergency
bypass of primarily treated / settled effluent from STSTW / CSTW
(for 6
hours)
|
STSTW /
CSTW: current & future
|
230 (8)
|
482 (8)
|
52 (8)
|
53 (8)
|
36 (8)
|
2 x107
(9)
|
Remarks:
(1)
During EIA stage of the ¡§TPSTW Stage V¡¨, the design
capacity of TPSTW was proposed to be 130,000 m3/day. The design
capacity has been reviewed and changed to 120,000 m3/day according
to the latest operation information of TPSTW.
(2)
At 95th percentile value of the effluent
standard (refer to Table 5.9). Using the 95th
percentile value as the effluent concentration for continuous discharge was
considered conservative, given that the effluent concentrations would be lower
than the 95th percentile value for most of the times.
(3)
Based on the ratio of TKN : Total N adopted in the
approved EIA for ¡§TPSTW Stage V¡¨.
(4) At mean value of the
effluent standard (refer to Table 5.9). Unlike the WQO for DO which
is a 10th percentile value, the WQOs for TIN and UIA is an annual
mean objective and the WQO for chlorophyll-a
is a 5-day running averaged value. Thus, using the mean effluent standard in
model prediction was considered appropriate for comparison with the relevant
WQOs. In addition, based on the analysis of the effluent data of STSTW and
TPSTW (between January 2007 and March 2015), the yearly averaged ratio of the
measured 95th percentile value to the measured maximum value of
Total N in the effluent was calculated to be 0.61 and 0.5 for STSTW and TPSTW
respectively, which implied that the 95th percentile value could be
much lower than the maximum value of the Total N levels. By applying these
measured ratios of 0.61 and 0.5 for STSTW and TPSTW to the maximum effluent
standard of 35 mg/L (refer to Table 5.9), the calculated 95th
percentile values would be about 21 mg/L and 17.5 mg/L for STSTW and TPSTW
respectively, which are similar or lower than the mean effluent standard of 20
mg/L. Using the mean effluent standard of 20 mg/L for modelling was considered acceptable.
(5) At mean value of the
effluent standard (refer to Table 5.9). Unlike the WQO for DO which
is a 10th percentile value, the WQOs for TIN and UIA is an annual
mean objective and the WQO for chlorophyll-a
is a 5-day running averaged value. Thus, using the mean the effluent standard
in model prediction was considered appropriate to for comparison with the
relevant WQOs. In addition, based
on the analysis of the effluent data of STSTW and TPSTW (between October 2012
and March 2015; October 2012 is the earliest published record for NH3-N),
the yearly averaged ratio of the measured 95th percentile value to
the measured maximum value of NH3-N in the effluent was calculated
to be only 0.23 and 0.32 for STSTW and TPSTW respectively, which implied that
the 95th percentile value could be much lower than the maximum value
of the NH-3N levels. By
applying these measured ratios of 0.23 and 0.32 for STSTW and TPSTW to the
maximum effluent standard of 10 mg/L (refer to Table 5.9), the calculated 95th
percentile values would be about 2.3 mg/L and 3.2 mg/L for STSTW and TPSTW
respectively, which are much lower than the mean effluent standard of 5 mg/L.
Using the mean effluent standard of 5 mg/L for modelling was considered
acceptable.
(6) At mean value of the
effluent standard (refer to Table 5.9). Unlike the WQO for DO which
is a 10th percentile value, the WQO for E. coli in Tolo Harbour is a geometric mean objective. Thus, using
the mean effluent standard for continuous discharge is considered appropriate
to provide a more realistic prediction for comparison with the relevant WQO.
The same approach of using the mean E.
coli standard for modelling was also adopted under the approved EIA for
HATS Stage 2A.
(7)
Based on maximum of all moving yearly 95th
percentile values from actual measurements of effluents from TPSTW and STSTW
(between 2007 and 2014). A yearly
95th percentile value was defined as the 95th percentile
value over a one-year period (e.g. from 8 March 2007 to 7 March 2008).
(8)
Maximum value of monthly averaged data measured in
crude sewage of STSTW (between 2010 and 2014).
(9)
Based on projected load and design concentrations for
CSTW.
(10)
Occasional overflow of effluent from TPSTW / STSTW during
storm event when the effluent flow above the capacity of the TPEPS / STEPS.
(11)
All secondarily treated and disinfected effluent from
CSTW will directly flow to the THEES tunnel by a new gravity sewer. Partial overflow of secondarily treated
and disinfected effluent would only occur at TPEPS.
Modelling
Scenarios for Victoria Harbour under Normal Plant Operation
Diagram 5.01 Water
Bodies Potentially Affected by the THEES Effluent
5.6.2.31
It was assumed under this
modelling exercise that the TPSTW and CSTW would reach their full design
capacities in UDS. UDS was selected
as the assessment time horizon for identification of the changes induced by the
recent KTD project. The interim
years before UDS would represent a less critical case with a lower degree of
cumulative impacts as the effluent flow of TPSTW and CSTW would be smaller
during the interim years. Any water
quality change induced by the effluent flow builds up between the interim years
and the ultimate stage would not be caused by this relocation project and
therefore should not be the focus of this EIA Study. Thus, additional scenario to represent
the existing or interim flow condition of the TPSTW and CSTW was considered
unnecessary for the purpose of this modelling exercise.
Scenario 1 - UDS Baseline without KTD Mitigation Measures, Normal
THEES Operation with or without this Project (Do Nothing for KTD Waters)
5.6.2.32
Scenario 1 represents the
baseline condition under normal operation of the TPSTW, CSTW and THEES in UDS,
which serves as a yardstick to measure the potential water quality changes
caused by the latest KTD proposal.
An average dry weather flow of 120,000m3 per day and 340,000m3
per day for TPSTW and CSTW, respectively, was assumed for modelling. This scenario represents the situation
when all the treated effluent from TPSTW and CSTW is discharged into Victoria
Harbour via KTN, as illustrated in Diagram 5.02 below. The effluent design standards were
employed together with the hourly dry weather diurnal flow to derive the hourly
pollution loadings as model inputs.
5.6.2.33
This scenario represents the
¡§do-nothing¡¨ situation for the KTD waters without considering the effect of the
alternative IP / runway opening schemes considered under Agreement No.
CE30/2008 (CE). The background
storm pollution loading data for the KTD waters derived from the Year 2013/14
storm pollution loading survey available from Agreement No. CE30/2008 (CE)
(refer to Section 5.6.2.19) were adopted under
Scenario 1 for conservative assessment.
It is believed that the Government will continuously rectify storm
pollution and thus the future background storm loading under the UDS would not
be worse than the existing condition.
Diagram
5.02 Generalized
THEES Effluent Flow to Victoria Harbour Considered Under Scenarios 1, 2a, 2b, 3a and
Scenarios 2a and 2b - UDS Cumulative Impact with KTD Mitigation
Measures, Normal THEES Operation with or without this Project (Design Effluent
Quality for THEES)
Scenario 2a ¡V Interception and Pumping (IP) Scheme
Diagram
5.03 Proposed
Intake and Discharge Points of IP System
5.6.2.36
As shown in Diagram
5.03, the IP system consists of two intake points (Intakes 1 and 2
respectively) and one discharge point (Discharge 1) at middle of
ex-runway. Two water pumping
options, namely Co-used with the Kai Tak DCS and Not Co-used with the Ka Tak
DCS respectively, have been considered under Agreement No. CE30/2008 (CE). For the Co-used Option, for Intake 1, a
new pumping station will be set up solely for pumping water to Discharge
1. For Intake 2, co-use with DCS is
possible by modifying the original intake point of the DCS South Plant to
Intake 2, and hence the flow rates will be the monthly rates of the South
Plant. For the Not Co-used Option,
the arrangement is the same as the Co-used Option except that intake 2 will
also cater for the flow for the DCS North Plant. Hence the flow rates at intake 2 will be
the combined monthly rates of the South Plant and the North Plant.
5.6.2.37
The monthly flow rates of the
Co-used and Not Co-used Options are summarized in Table 5.15
below. From the table, it is shown
that the Co-used Option will involve a lower pumping rate and thus generate a
smaller water circulation in the KTAC and KTTS, and since the main purpose of
the KTD improvement proposal is to enhance the water quality of KTAC and KTTS,
the Co-used Option is considered a worse case in terms of the water quality
impact at KTAC and KTTS (where THEES effluent is discharged). Therefore, the Co-used Option was
adopted in Scenario 2a for conservative assessment. In case the Not Co-used Option is
selected as the final scheme, the associated water quality impact would not be
worse than that resulted from the Co-used Option as assumed in Scenario
2a. The flow rates of the IP system
presented in this EIA are based on the best available information obtained
during the course of this modelling exercise. It was however found after completion of
this modelling exercise that the flow rate of Intake 1 has been revised from
4.88 m3/s to 4 m3/s under the KTD study. Nevertheless, it was also found under
the separate KTD study that the pumping rate of 4 m3/s at Intake 1
could achieve similar water quality improvement performance as a pumping rate
of 4.88 m3/s.
Furthermore, according to the KTD study, the pollution loading in both
wet and dry weather conditions would be reduced significantly following the
rectification of expedient connections and upgrading of existing Dry Weather
Flow Interceptors currently being planned in the catchment areas. Therefore, it is believed that the
pumping rate of 4 m3/s at Intake 1 would be sufficient to achieve
the water quality improvement at KTAC and KTTS as predicted in this modelling
exercise.
Table 5.15 Monthly
Flow Rates of the Co-used and Not Co-used Options
|
Flow of South Plant of DCS
|
Flow of North Plant of DCS
|
Co-used Option
|
Not Co-used Option (Scenario 2)
|
|
Flow at Intakes
|
Flow at Outfall
|
Flow at Intakes
|
Flow at Outfall
|
|
Intake 1
|
Intake 2
|
Discharge 1 from new pumping station
|
Discharge 1 from DCS
|
Intake 1
|
Intake 2
|
Discharge 1 from new pumping station
|
Discharge 1 from DCS
|
Month
|
(m3/d)
|
(m3/s)
|
(m3/d)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
(m3/s)
|
Jan
|
85,000
|
0.98
|
80,000
|
0.93
|
4.88
|
0.98
|
4.88
|
0.98
|
4.88
|
1.91
|
4.88
|
1.91
|
Feb
|
93,000
|
1.08
|
88,000
|
1.02
|
4.88
|
1.08
|
4.88
|
1.08
|
4.88
|
2.09
|
4.88
|
2.09
|
Mar
|
109,000
|
1.26
|
115,000
|
1.33
|
4.88
|
1.26
|
4.88
|
1.26
|
4.88
|
2.59
|
4.88
|
2.59
|
Apr
|
146,000
|
1.69
|
161,000
|
1.86
|
4.88
|
1.69
|
4.88
|
1.69
|
4.88
|
3.55
|
4.88
|
3.55
|
May
|
182,000
|
2.11
|
212,000
|
2.45
|
4.88
|
2.11
|
4.88
|
2.11
|
4.88
|
4.56
|
4.88
|
4.56
|
Jun
|
213,000
|
2.47
|
253,000
|
2.93
|
4.88
|
2.47
|
4.88
|
2.47
|
4.88
|
5.39
|
4.88
|
5.39
|
Jul
|
230,000
|
2.66
|
266,000
|
3.08
|
4.88
|
2.66
|
4.88
|
2.66
|
4.88
|
5.74
|
4.88
|
5.74
|
Aug
|
227,000
|
2.63
|
266,000
|
3.08
|
4.88
|
2.63
|
4.88
|
2.63
|
4.88
|
5.71
|
4.88
|
5.71
|
Sep
|
212,000
|
2.45
|
247,000
|
2.86
|
4.88
|
2.45
|
4.88
|
2.45
|
4.88
|
5.31
|
4.88
|
5.31
|
Oct
|
170,000
|
1.97
|
193,000
|
2.23
|
4.88
|
1.97
|
4.88
|
1.97
|
4.88
|
4.20
|
4.88
|
4.20
|
Nov
|
134,000
|
1.55
|
144,000
|
1.67
|
4.88
|
1.55
|
4.88
|
1.55
|
4.88
|
3.22
|
4.88
|
3.22
|
Dec
|
99,000
|
1.15
|
97,000
|
1.12
|
4.88
|
1.15
|
4.88
|
1.15
|
4.88
|
2.27
|
4.88
|
2.27
|
5.6.2.38
The proposed IP Scheme would
utilize the water abstracted from KTN and KTAC in the DCS before discharges into
the Kowloon Bay with potential thermal impact. However, as temperature change is not a
potential concern for this Project, details of the possible integration of this
IP Scheme with the DCS are considered irrelevant and therefore not presented in
this EIA Report. However, the
Intake Points 1 and 2 as shown in Diagram 5.03 are
considered as WSRs (or cooling water intakes) under this modelling scenario for
conservative assessment.
Table
5.16 Monthly
Flow Rates of the Proposed IP Scheme Under Co-used Option for Model Input
Month
|
Flow at Intakes (m3/s)
|
Intake 1
|
Intake 2
|
January
|
4.88
|
0.98
|
February
|
4.88
|
1.08
|
March
|
4.88
|
1.26
|
April
|
4.88
|
1.69
|
May
|
4.88
|
2.11
|
June
|
4.88
|
2.47
|
July
|
4.88
|
2.66
|
August
|
4.88
|
2.63
|
September
|
4.88
|
2.45
|
October
|
4.88
|
1.97
|
November
|
4.88
|
1.55
|
December
|
4.88
|
1.15
|
5.6.2.40
Due to the recent background storm
pollution reduction as a result of the hinterland improvement measures
implemented in the KTD areas after approval of the EIA Report for KTD, the need
of a wide (600m) opening at the former airport runway to enhance the water
quality at KTAC as proposed under the approved EIA would not be required. The
600m runway opening proposal will be superseded by this IP Scheme recently
proposed under Agreement No. CE30/2008 (CE) and therefore will not be further
considered in this modelling exercise.
Furthermore, opening a wide (600m) gap at the former airport runway is
considered a more conservative improvement measure and would result a greater
water quality improvement and flushing at the KTAC as compared to the IP Scheme
considered in Scenario 2a and therefore will be a less critical case for
cumulative water quality impacts at or near the THEES discharge point. The IP Scheme is considered a worst case
for cumulative water quality impact at KTAC (as compared to the 600m runway
opening proposal).
Scenario 2b ¡V 150m
Runway Opening Option
Scenarios 3a and 3b - UDS Cumulative Impact with KTD
Mitigation Measures, Normal THEES Operation with and without the Project
(Realistic Effluent Quality for THEES)
5.6.2.42
Scenarios 3a and 3b are
basically same as Scenarios 2a and 2b respectively except that a more realistic worst case of THEES loading was adopted. The THEES effluent discharge arrangement for Scenarios 3a and 3b is
however same as that under Scenarios 1, 2a and 2b as indicatively shown in Diagram 5.02 above.
5.6.2.43
Review of the actual effluent
measurements (between January 2007 and October 2014) for the STSTW and TPSTW
revealed that the actual effluent quality for these 2 STWs has been maintained
at a level better than design effluent standards. The treatment level of the future CSTW will
follow that of the existing STSTW.
As far as the effect of THEES on the water quality impact assessment
under this EIA Study is concerned (Remark: This modelling exercise aimed only
to assess the changes of cumulative impacts induced by the KTD project and not
to assess the water quality change induced by the CSTW), it was not
unreasonable to take the THEES loading for the 5 key parameters (including BOD,
TSS, TKN, NH3-N and Total N) based on the 95th percentile
value from actual measurements. The
95th percentile values adopted under Scenarios 3a and 3b for these 5
parameters are the maximum of all the running yearly 95th percentile
values over the period from January 2007 to October 2014, which is a
conservative value. The measured mean values are much smaller than these
measured 95th percentile value. Use of the measured 95th
percentile value for modelling would provide a reasonable worst case for
cumulative impact assessment.
Modelling Scenarios for Tolo
Harbour
Scenario 4 - UDS ¡§Without Project¡¨ Condition of Tolo Harbour -
Overflow at Both TPSTW and Existing STSTW
5.6.2.47
Normally, the TPEPS would pump
the effluent from the TPSTW via a rising main and a submarine pipeline to the
STEPS. The STEPS would receive the effluent from both TPSTW and STSTW for
combined discharge to the KTN as illustrated in Diagram 5.02 above. Under the ¡§without Project¡¨ scenario, it is assumed that
effluent from TPSTW would occasionally exceed the existing capacity of the
TPEPS and hence part of the secondarily treated and disinfected effluent would
then be discharged via the existing emergency bypass outfall near TPSTW. On the
other hand, combined flow from TPSTW and STSTW would also occasionally exceed
the capacity of STEPS and part of the flow would then be discharged via the
existing emergency outfall of STSTW. The indicative discharge locations of
effluent overflow from TPEPS and STEPS considered under Scenario 4 are shown in
Diagram 5.04 below. The daily flow and pollution load overflowed into Tolo
Harbour would vary seasonally due to the seasonal change in storm water flow.
It is also assumed that the overflow would occur only occasionally within a day
and would be discharged intermittently. The pollution levels in the storm water
would be the same as those in the effluent and no dilution of the treated
effluent is assumed as conservative approach. The annual volumes of overflow
assumed for modelling as adopted in the ¡§TPSTW Stage V¡¨ are listed in the Table
5.17 below.
Table
5.17 Annual
Volumes of Secondarily Treated and Disinfected Effluent Overflow to Tolo
Harbour under ¡§Without Project¡¨ Scenario
Discharge Location
|
Total Volume of Secondarily Treated and Disinfected Effluent
Overflow discharged in a year (m3/year)
|
Existing
Emergency Bypass of TPSTW
|
9,832,240
|
Existing
Emergency Bypass of STSTW
|
4,656,300
|
Total
|
14,488,540
|
Diagram 5.04 Generalized
Effluent Flow to Tolo Harbour Considered Under Scenario 4
Scenario 5 ¡V UDS ¡§With Project¡¨ Condition (Normal
Operation after Project Commission) in Storm Events with Overflow at TPSTW only
Table 5.18 Annual
Volume of Secondarily Treated and Disinfected Effluent Overflow to Tolo Harbour
under ¡§With Project¡¨ Scenario
Discharge Location
|
Total Volume of Secondarily Treated and
Disinfected Effluent Overflow discharged in a year (m3/year)
|
Existing
Emergency Bypass of TPSTW
|
9,832,240
|
Existing
Emergency Bypass of STSTW
|
0
|
Total
|
9,832,240
|
Diagram 5.05 Generalized
Effluent Flow to Tolo Harbour Considered Under Scenario 5
Scenarios 6a and 6b ¡V UDS THEES Maintenance Discharges
Scenario 6a - UDS THEES Maintenance
following Existing Practice
Diagram 5.06 Generalized
Effluent Flow to Tolo Harbour Considered Under Scenarios 6a and 6b
Scenario 6b - UDS THEES Maintenance outside Algae Blooming
Season
Scenario 7 ¡V UDS Emergency Sewage Discharge from STSTW / CSTW
5.6.2.52
Currently, emergency discharge
of primarily treated / settled effluent from the existing STSTW may be allowed
via the existing submarine outfall of STSTW in case of power / plant
failure. However, based on the past
record, emergency sewage discharge to the Tolo Harbour from the existing STSTW
had never happened before. This
Project only involves relocation of the existing STSTW to caverns without
changing the flow and load of the existing STSTW. Following the same
arrangement of the existing STSTW, backup / standby facilities will be provided
for the future CSTW to minimize the chance of emergency discharge. Thus, this
Project will not change the flow, load and chance of any possible emergency
discharge (as compared to the existing situation).
5.6.2.53
Scenario 7 thus represents an
extremely remote event of emergency discharge from the CSTW. For the purpose of illustrating the
possible water quality effect under this emergency situation, it is assumed
under Scenario 7 that the emergency discharge would occur for a period of 6
hours with a total discharge volume of 85,000 m3. Since emergency discharge had never
occurred at the existing STSTW, reference was made to the past record from
existing TPSTW (with similar treatment processes). Based on the past record
from TPSTW, emergency sewage discharge had occurred only once since 1995 due to
CLP power supply failure to TPSTW Stage IV inlet works. The duration of the emergency discharge
from TPSTW was less than 3 hours with a total discharge volume of less than
9,000 m3. Thus, this
scenario of assuming a total discharge volume of 85,000 m3 over a
6-hour period would be a very adverse situation. This emergency discharge scenario was
simulated for both dry and wet seasons. Under each season, four separate model
runs were conducted to simulate the impacts for four emergency discharge
periods centred at namely neap tide high water, neap tide low water, spring
tide mid-flood and spring tide mid-ebb respectively. Amongst all the discharge
timings simulated, the predicted impacts under spring tide mid-ebb and neap
tide low water were found to be the worse under dry and wet seasons
respectively and therefore the model results are only presented for these two
worse case discharge timings in the subsequent assessment. It is assumed that
the sewage would be discharged via the existing emergency submarine outfall of
STSTW during the dry season in March and the wet season in July. In case of
power failure, the emergency discharge from CSTW would still be subject to
settlement / sedimentation prior to the discharge and thus would represent
primarily treated sewage effluent. However, the quality of the emergency
discharge is assumed under this scenario to be similar to that of the crude
sewage for conservative assessment. The loading conditions not during emergency
bypass would be the same as those adopted in Scenario 5 (see Section
5.6.2.50). The indicative
location of the emergency discharge is shown in Diagram 5.07
below.
Diagram 5.07 Generalized
Effluent Flow to Tolo Harbour Considered Under Scenario 7
Model Limitations
5.7.1
Prediction and Evaluation of Potential
Impacts
5.7.1.1
The potential water quality
impacts arising from the land-based construction works of this Project are
evaluated in this section.
General Construction Activities
5.7.1.2
Effluent discharged from
temporary site facilities should be controlled to prevent direct discharge to
the neighbouring inland waters and storm drains. Such effluent may include wastewater
resulting from wheel washing of site vehicles at site entrances. Debris and rubbish such as packaging,
construction materials and refuse generated from the construction activities
should also be properly managed and controlled to avoid accidental release to
the local storm system and inland waters.
Adoption of the guidelines and good site practices for handling and
disposal of construction discharges as specified in Section
5.7.2 would minimize the potential impacts.
Construction Site Run-off
5.7.1.3
Construction site run-off and
drainage may cause local water quality impacts. Increase in SS arising from the
construction site could block the drainage channels. High concentrations of suspended
degradable organic material in marine water could lead to reduction in DO
levels in the water column.
5.7.1.4
It is important that proper
site practice and good site management (as specified in the ProPECC PN 1/94
¡§Construction Site Drainage¡¨) be followed to prevent run-off with high level of
SS from entering the surrounding waters.
With the implementation of appropriate measures to control run-off and
drainage from the construction site, disturbance of water bodies would be
avoided and deterioration in water quality would be minimal. Thus, unacceptable impacts on the water
quality are not expected, provided that the relevant mitigation measures as
specified in the ProPECC PN 1/94 ¡§Construction Site Drainage¡¨ are properly
implemented.
Accidental Spillage and Potential
Contamination of Surface Water and Groundwater
5.7.1.5
A large variety of chemicals
may be used during construction activities. These chemicals may include petroleum
products, surplus adhesives, spent lubrication oil, grease and mineral oil,
spent acid and alkaline solutions/solvent and other chemicals. Accidental spillage of chemicals in the
works areas may contaminate the surface water or groundwater nearby. The
potential impacts could however be mitigated by practical mitigation measures
and good site practices (as given in Section 5.7.2).
Sewage Effluent from Construction Workforce
5.7.1.6
Domestic sewage would be
generated from the workforce during the construction phase. However, this temporary sewage can be
adequately treated by interim sewage treatment facilities, such as portable
chemical toilets. Based on the Drainage Services Department (DSD) Sewerage
Manual, the sewage production rate for construction workers is estimated at
0.35 m3 per worker per day. For every 100 construction workers
working simultaneously at the construction site, about 35 m3 of
sewage would be generated per day.
Provided that sewage is not discharged directly into storm drains or
inland waters adjacent to the construction site, and temporary sanitary
facilities are used and properly maintained, it is unlikely that sewage
generated from the site would have a significant water quality impact.
Construction Works in Close Proximity of
Inland Water
5.7.1.7
Construction activities in
close vicinity to the inland water courses may pollute the inland water bodies
due to the potential release of construction wastes. Construction wastes are
generally characterized by high concentration of SS and elevated pH. The
implementation of measures to control runoff and drainage will be important for
the construction works adjacent to the inland water in order to prevent runoff and
drainage water with high levels of SS from entering the water environment. With
the implementation of adequate construction site drainage as specified in the
ProPECC PN 1/94 ¡§Construction Site Drainage¡¨ and the provision of mitigation
measures as described in the ETWB TC (Works) No. 5/2005 ¡§Protection of natural
streams/rivers from adverse impacts arising from construction works¡¨, it is
anticipated that unacceptable water quality impacts would not arise.
Groundwater Infiltration and Groundwater Drawdown
5.7.1.8
Construction of rock caverns
and tunnels may result in infiltration of groundwater. The major concern from
these construction activities would be the increase in site runoff and the
associated potential drawdown of groundwater in any soil and aquifer layers).
Practical groundwater control measures are given in Section
5.7.2 to minimize the potential impacts.
Groundwater from Potentially Contaminated Area
5.7.1.9
According to separate CAP
prepared for the Project, it is identified that the works areas at the existing
STSTW site would have land contamination issues. Any contaminated material
disturbed, or material which comes into contact with the contaminated material,
has the potential to be washed with site run-off into watercourses. Mitigation
measures should be implemented to control site runoff from the contaminated areas, and to prevent
runoff entering the adjacent waters.
5.7.1.10
Groundwater pumped out or from
dewatering process during excavation works in the existing STSTW site would be
potentially contaminated. Proper treatment, discharge or recharge of contaminated groundwater, if
any, following the mitigation measures given in Section 5.7.2 would minimize the potential impacts. No
direct discharge of contaminated groundwater will be allowed.
THEES Connection Works
5.7.1.11
As discussed in Section
5.5.1.8 above, the necessary THEES connection works required for this
Project will be undertaken within the regular THEES maintenance windows for a duration
not longer than 4 weeks each outside the algae blooming season (January to May)
and the frequency of THEES maintenance will be no more than once per year
during the construction phase of the Project, as confirmed by DSD. Hence, no additional cumulative water
quality effect on the Tolo Harbour waters will be induced by the proposed THEES
connection works. DSD will closely liaise with the Contractor during the
construction phase of the Project to ensure that the THEES connection works
would be conducted within the regular THEES maintenance periods and also
outside the algae blooming season (January to May).
5.7.2.1
Mitigation measures as listed
below are recommended to minimize the potential water quality impacts from the
land-based construction works.
Construction Site Run-off and General
Construction Activities
Boring and Drilling Water
5.7.2.2
Water used in ground boring and drilling for site investigation or rock
/ soil anchoring should as far as practicable be re-circulated after sedimentation.
When there is a need for final
disposal, the wastewater should be discharged into storm drains via silt
removal facilities.
Wheel Washing Water
5.7.2.3
All vehicles and plant should be cleaned before they leave a construction
site to minimize the deposition of earth, mud, debris on roads. A wheel washing
bay should be provided at every site exit if practicable and wash-water should
have sand and silt settled out or removed before discharging into storm drains. The section of construction road between the wheel washing bay and the public road
should be paved with backfall to reduce vehicle tracking of soil and to prevent
site run-off from entering public road drains.
Rubbish and Litter
5.7.2.4
Good site practices should be adopted
to remove rubbish and litter from construction sites so as to prevent the rubbish and
litter from spreading from the site area. It is recommended to clean the
construction sites on a regular basis.
Construction Site
Run-off
5.7.2.5
The site practices outlined in ProPECC PN 1/94 ¡§Construction Site
Drainage¡¨ should be followed as far as practicable to minimise surface run-off
and the chance of erosion. The following measures are
recommended to protect water quality and sensitive uses of
the coastal area, and when properly implemented should be sufficient to
adequately control site discharges so as to avoid water quality impact:
5.7.2.6
Surface run-off from construction sites should be discharged into storm
drains via adequately designed sand/silt removal facilities such as sand traps, silt traps and sedimentation basins.
Channels or earth bunds or sand bag barriers should be provided on site to
properly direct stormwater
to such silt removal facilities. Perimeter channels at site boundaries should
be provided on site boundaries where necessary to intercept storm run-off from
outside the site so that it will not wash across the site. Catchpits and
perimeter channels should be constructed in advance of site formation works and
earthworks.
5.7.2.7
Silt removal facilities, channels and manholes should be maintained and
the deposited silt and grit should be removed regularly, at the onset of and
after each rainstorm to prevent local flooding. Before disposal at the public
fill reception facilities, the deposited silt and grit should be solicited in
such a way that it can be contained and delivered by dump truck instead of
tanker truck. Any practical options
for the diversion and re-alignment of drainage should comply with both engineering and environmental requirements in
order to provide adequate hydraulic capacity of all drains. Minimum distance of
100m should be maintained between the discharge points of construction site
run-off and the existing saltwater intakes. No effluent will be discharged into
typhoon shelter.
5.7.2.8
Construction works should be programmed to minimize soil excavation
works in rainy seasons (April to September). If excavation in soil cannot be avoided in these months or at
any time of year when rainstorms are likely, for the purpose of preventing soil erosion, temporary
exposed slope surfaces should be covered e.g. by tarpaulin, and temporary
access roads should be protected by crushed stone or gravel, as excavation
proceeds. Intercepting channels should be provided (e.g. along the crest / edge
of excavation) to prevent storm runoff from washing across exposed soil
surfaces. Arrangements should always be in place in such a way that adequate
surface protection measures can be safely carried out well before the arrival
of a rainstorm.
5.7.2.9
Earthworks final surfaces should be well compacted and the subsequent
permanent work or surface protection should be carried out immediately after
the final surfaces are formed to prevent erosion caused by rainstorms. Appropriate drainage like intercepting channels should
be provided where necessary.
5.7.2.10
Measures should be taken to minimize the ingress of rainwater into
trenches. If excavation of trenches in wet seasons is necessary, they should be dug and backfilled in short sections.
Rainwater pumped out from trenches or foundation excavations should be
discharged into storm drains via silt removal facilities.
5.7.2.11
Construction materials (e.g. aggregates, sand and fill material) on
sites should be covered with tarpaulin or similar fabric during rainstorms.
5.7.2.12
Manholes (including newly constructed ones) should always be adequately
covered and temporarily sealed so as to prevent silt, construction materials or
debris from getting into the drainage system, and to prevent storm run-off from
getting into foul sewers. Discharge of surface run-off into foul sewers must
always be prevented in order not to unduly overload the foul sewerage system.
5.7.2.13
Good site practices should be adopted to remove rubbish and litter from
construction sites so as to prevent the rubbish and litter from spreading from the site area. It is recommended to
clean the construction sites on a regular basis.
Site Effluent
5.7.2.14
There is a need to apply to EPD
for a discharge licence for discharge of effluent from the construction site
under the WPCO. The discharge
quality must meet the requirements specified in the discharge licence. All the runoff and wastewater generated
from the works areas should be treated so that it satisfies all the standards
listed in the TM-DSS. The
beneficial uses of the treated effluent for other on-site activities such as dust suppression, wheel
washing and general cleaning etc., can minimise water consumption and reduce
the effluent discharge volume. If
monitoring of the treated effluent quality from the works areas is required
during the construction phase of the Project, the monitoring should be carried
out in accordance with the relevant WPCO licence which is under the ambit of
regional office (RO) of EPD.
Accidental Spillage and Potential Contamination of Surface Water and Groundwater
5.7.2.15
Contractor must register as a chemical
waste producer if chemical wastes would be produced from the construction activities. The Waste Disposal Ordinance (Cap 354)
and its subsidiary regulations in particular the Waste Disposal (Chemical
Waste) (General) Regulation, should be observed and complied with for control
of chemical wastes.
5.7.2.16
Any service shop and
maintenance facilities should be located on hard standings within a bonded
area, and sumps and oil interceptors should be provided. Maintenance of vehicles and equipment involving activities with potential for
leakage and spillage should only be undertaken within the areas appropriately
equipped to control these discharges.
5.7.2.17
Disposal of chemical wastes
should be carried out in compliance with the Waste Disposal
Ordinance. The Code of Practice on
the Packaging, Labelling and Storage of Chemical Wastes published under the
Waste Disposal Ordinance details the requirements to deal with chemical
wastes. General requirements are
given as follows:
¡P
Suitable containers should be used to hold the
chemical wastes to avoid leakage or spillage during storage, handling and
transport;
¡P
Chemical waste containers should be suitably
labelled, to notify and warn the personnel who are handling the wastes, to
avoid accidents; and
¡P
Storage area should be selected at a safe
location on site and adequate space should be allocated to the storage area.
Sewage Effluent from Construction
Workforce
5.7.2.19
Notices should be posted at
conspicuous locations to remind the workers not to discharge any sewage
or wastewater into the surrounding environment. Regular environmental audit of the
construction site will provide an effective control of any malpractices and can
encourage continual improvement of environmental performance on site. It is anticipated that sewage generation
during the construction phase of the project would not cause water pollution
problem after undertaking all required measures.
Construction Works in Close
Proximity of Inland Waters
¡P
Construction works close to the inland waters
should be carried out in dry season as far as practicable where the flow in the
surface channel or stream is low.
¡P
The use of less or smaller construction plants may
be specified in areas close to the water courses to reduce the disturbance to
the surface water.
¡P
Temporary storage of materials (e.g. equipment,
chemicals and fuel) and temporary stockpile of construction materials should be
located well away from any water courses during carrying out of the
construction works.
¡P
Stockpiling of construction materials and dusty
materials should be covered and located away from any water courses.
¡P
Construction debris and spoil should be covered
up and/or disposed of as soon as possible to avoid being washed into the nearby
water receivers.
¡P
Proper shoring may need to be erected in order
to prevent soil or mud from slipping into the watercourses.
Groundwater Infiltration and Groundwater Drawdown
5.7.2.21
Appropriate measures during the
construction of the cavern construction should be implemented to minimize the
groundwater infiltration. The water control strategies include:
¡P
Probing Ahead: As normal practice, the
Contractor will undertake rigorous probing of the ground ahead of excavation
works to identify zones of significant water inflow. The probe drilling results
will be evaluated to determine specific grouting requirements in line with the
tunnel / cavern advance. In such zones of significant water inflow that could
occur as a result of discrete, permeable features, the intent would be to
reduce overall inflow by means of cut-off grouting executed ahead of the tunnel
/ cavern advance.
¡P
Pre-grouting: Where water inflow quantities are
excessive, pre-grouting will be required to reduce the water inflow into the
tunnel / cavern. The pre-grouting will be achieved via a systematic and
carefully specified protocol of grouting.
¡P
In principle, the grout pre-treatment would be
designed on the basis of probe hole drilling ahead of the tunnel / cavern face.
¡P
The installation of waterproof lining would also
be adopted after the formation of the tunnels and caverns.
5.7.2.22
In the event of excessive infiltration being observed as a result of the
tunnelling or excavation works even after incorporation of the water control
strategies, post-grouting should be applied as far as practicable as described
below:
¡P
Post-grouting: Groundwater drawdown will be most
likely due to inflows of water into the tunnel / cavern that have not been
sufficiently controlled by the pre-grouting measures. Where this occurs post
grouting will be undertaken before the lining is cast. Whilst unlikely to be
required in significant measure, such a contingency should be allowed for
reduction in permeability of the tunnel / cavern surround (by grouting) to
limit inflow to acceptable levels.
5.7.2.23
The practical groundwater
control measures stated above are proven technologies and have been extensively
applied in other past projects. These measures or other similar methods, as
approved by the Engineer to suit the works condition shall be applied to
minimize the groundwater infiltration.
5.7.2.24
In case seepage of groundwater
occurs, groundwater should be pumped out from works areas and discharged to the
storm system via silt trap.
Uncontaminated groundwater from dewatering process should also be
discharged to the storm system via silt removal facilities.
Groundwater from Potentially Contaminated Area
5.7.2.25
No directly discharge of groundwater from contaminated areas if any
should be adopted. Prior to any
excavation works within the potentially contaminated areas at the existing
STSTW site (if found to be), the baseline groundwater quality in these areas
should be reviewed based on the relevant site investigation data and any
additional groundwater quality measurements to be performed with reference to Guidance Note for Contaminated Land
Assessment and Remediation and the review results should be
submitted to EPD for examination. If the review results indicated that the
groundwater to be generated from the excavation works would be contaminated,
this contaminated groundwater should be either properly treated or properly
recharged into the ground in compliance with the requirements of the
TM-DSS. If wastewater
treatment is to be deployed for treating the contaminated groundwater, the
wastewater treatment unit shall deploy suitable treatment processes (e.g. oil
interceptor / activated carbon) to reduce the pollution level to an acceptable
standard and remove any prohibited substances (such as TPH) to an undetectable
range. All treated effluent from the wastewater treatment plant shall meet the
requirements as stated in TM-DSS and should be either discharged into the foul
sewers or tankered away for proper disposal.
THEES Connection Works
5.7.2.27
The THEES connection works
required for this Project (see Section 5.5.1.8)
shall be undertaken within the regular THEES maintenance windows for a duration
not longer than 4 weeks each outside the algae blooming season (January to May)
and the frequency of THEES maintenance shall be no more than once per year
during the construction phase of the Project.
5.7.3.1
The potential water quality
impact from the land-based construction works can be controlled by the
recommended mitigation measures. No water quality monitoring specific to the
land-based construction works is thus proposed. However, regular site inspections should
be undertaken during the construction phase to inspect the construction
activities and works areas in order to ensure the recommended mitigation measures
are properly implemented. Details of the EM&A programme are presented in
the standalone EM&A Manual.
5.7.4.1
No unacceptable residual
land-based water quality impacts are anticipated during land-based construction
with the above mitigation measures implemented.
5.8
Operational Effluent Discharges to Victoria Harbour ¡V Normal
THEES Operation
5.8.1.1
A total of 5 modelling
scenarios (namely Scenarios 1, 2a, 2b, 3a and 3b) were simulated to assess the
potential cumulative water quality impacts upon the Victoria Harbour during the
normal plant operation of this Project. Details of these modelling scenarios
are provided in Sections 5.6.2.28 and 5.6.2.43 above.
5.8.1.2
The model results of the 5
scenarios are compared in Appendix
5.03 as contour plots for BOD, TIN, UIA, E. coli, SS, and
sedimentation rate. All contour
plots are presented as annual arithmetic averages except for the E. coli
levels, which are annual geometric mean. Since the marine WQO in Victoria
Harbour for depth-averaged (DA) DO and bottom DO is defined as not less than 4
and 2 mg/L respectively for 90% of times over a complete calendar year, the
contour plots for DO are presented as 10th percentile (10%ile)
values for comparison with the WQO.
Dissolved Oxygen
5.8.1.3
Under the baseline ¡§do-nothing¡¨
condition without any further water quality improvement work at Kai Tak (Scenario 1), the 10%ile bottom DO at KTAC
would not meet the WQO of no less than 2 mg/L. Under Scenarios 2a and 3a (with
the IP scheme to intercept the polluted water from KTN and KTAC to Kowloon
Bay), significant improvement in the bottom DO levels would occur as compared
to the baseline situation. For
Scenario 2a (a conservative case using the design effluent standards for
compiling the THEES effluent load), the bottom DO in the upper part of the KTAC
would still exceed the WQO, whilst the exceedance in the lower reach of the
KTAC was eliminated. Under Scenario 3a (adopting a more realistic worst case
for the THEES effluent load, see Section 5.6.2.43), the exceedance for bottom DO in the whole KTAC area was removed.
Under the alternative scheme (Scenarios 2b and 3b) with a 150m opening at the
ex-airport runway to enhance natural flushing at KTAC, the exceedance for
bottom DO in the whole KTAC would also be totally eliminated. Under all the 5 scenarios, full compliance
with the WQO for bottom DO was predicted in KTTS, Kowloon Bay and the open
water in Victoria Harbour outside the breakwaters of KTTS as shown in Appendix 5.03.
5.8.1.4
In terms of the DA DO, the
10%ile levels predicted in the whole KTAC and KTTS would exceed the WQO of less
than 4 mg/L under Scenario 1 (baseline condition). Under Scenarios 2a and 3a
(with the IP scheme), the exceedance in the KTTS area would be eliminated but
residual exceedance was still predicted in the KTAC water. On the other hand, least improvement in
the DA DO was predicted under Scenario 2b (i.e. the alternative runway opening
scheme with a conservative THEES effluent load). Scenario 2b only eliminated
the exceedance in the lower reach of the KTTS with residual exceedance in the
upper part of the KTTS and the whole area of KTAC. Scenario 3b (runway opening
scheme with a realistic THEES effluent load) however showed the best water
quality effects as compared to Scenarios 2a, 2b and 3a. The exceedance for DA
DO in the whole KTTS and most areas of KTAC would be removed under Scenario
3b. Under Scenarios 1 and 3a,
higher DO level was predicted at the upper corner of Kowloon Bay when compared
to Scenario 2a, owing to different loading assumptions adopted for these
scenarios. Scenarios 1 and 2a
adopted the same magnitude of overall pollution loading to KTD waters. However, Scenario 2a has diverted some
loading from KTAC for discharge at the middle of the ex-airport runway and this
additional discharge point is relatively close to Kowloon Bay, affecting the
water quality at Kowloon Bay, whereas Scenario 1 assumed that there is no
loading diversion from KTAC. As a
result, there would be a slight DO decrease in the upper corner of Kowloon Bay
under Scenario 2a as compared to the baseline condition under Scenario 1. Although Scenario 3a has a very similar
setting as compared to Scenario 2a with load diversion from KTAC, the overall
pollution loading to the KTD waters was significantly smaller under Scenario 3a
with a more realistic loading assumption (see Sections
5.6.2.42 and 5.6.2.43). For example, the BOD level assumed for
the THEES effluent is 20 mg/L (for Scenarios 1 and 2a) and <10 mg/L (for
Scenario 3a). Hence, it can be
observed that there would be a significant DO improvement in the KTD waters
under Scenario 3a, not only at the upper corner of Kowloon Bay but also in the
whole KTAC and KTTS area. Under all
the 5 scenarios, full compliance with the WQO for DA DO was predicted in
Kowloon Bay and the open water in Victoria Harbour outside the breakwaters of
KTTS as shown in Appendix 5.03.
5.8.1.5
The cumulative water quality
changes brought by the latest KTD improvement measures (under Scenarios 2a, 2b,
3a and 3b) are actually positive effects, minimizing the DO impact at KTAC and
KTTS as compared to the baseline situation (Scenario 1). As there are no biological nor
ecological sensitive receivers in KTAC and KTTS, the residual DO exceedance in
KTAC / KTTS is considered not a critical concern for this Project, and in view that the overall
impact zone with low DO levels in the KTAC and KTTS would be significantly
improved and minimized with the latest KTD improvement measures, no
unacceptable cumulative DO impact would arise.
Biochemical Oxygen
Demand
5.8.1.6
There is no marine WQO for
BOD. Under the baseline condition
(Scenario 1), the BOD levels ranged from about 3 to <20 mg/L in KTAC and
about 1.5 to 3 mg/L in KTTS. The predicted BOD levels in Kowloon Bay and the
open water of Victoria Harbour were low (ranged from <0.5 to about 1.5 mg/L
only) under Scenario 1.
5.8.1.7
Under Scenarios 2a and 3a (with
the IP Scheme), the BOD levels in KTAC and KTTS would be reduced to about 2.5
to <10 mg/L and about 1 to 2.5 mg/L respectively. No significant change in the overall BOD
pattern in Kowloon Bay and the open Victoria Harbour would be induced by the IP
scheme (under Scenarios 2a and 3a) as compared to the baseline situation under
Scenario 1.
5.8.1.8
Scenarios 2b and 3b (the
alternative runway opening scheme) would also induce some BOD improvements at
KTAC and KTTS similar to the improvement achieved under Scenarios 2a and 3a
(the IP scheme). However, the runway opening under Scenarios 2b and 3b would
introduce a higher BOD levels in Kowloon Bay and a slight change of the BOD
pattern in the Kowloon Bay as compared to the baseline situation (Scenario 1)
as a result of the broader mixing between Kowloon Bay and KTAC waters induced
by the runway opening. The BOD level at the upper corner of the Kowloon Bay
would be increased to >2 mg/L under Scenarios 2b and 3b.
Suspended Solids
5.8.1.9
Under the baseline condition
(Scenario 1), the SS level is generally over 20 mg/L in KTAC and generally over
10 mg/L in KTTS. The predicted SS levels in Kowloon Bay and the open water of
Victoria Harbour were lower (< 8 mg/L in general) under Scenario 1. Under
Scenarios 2a and 3a (with the IP scheme), the impact zone of high SS (>20
mg/L) in KTAC would be significantly reduced. The SS levels in most of the KTTS
would also be reduced to <10 mg/L under Scenarios 2a and 3a. No significant change in the
overall SS pattern in Kowloon Bay and the open Victoria Harbour would be
induced by the IP scheme (under Scenarios 2a and 3a) as compared to the
baseline situation under Scenario 1.
5.8.1.10
Scenarios 2b and 3b (the
alternative runway opening scheme) would induce an even greater SS improvements
at KTAC and KTTS. The impact zone of high SS (over 20 mg/L) in KTAC was totally
removed under Scenarios 2b and 3b, refer to Appendix 5.03. However, the runway opening under Scenarios 2b and 3b would
introduce a higher SS levels in Kowloon Bay and a slight change of the SS pattern
in the Kowloon Bay as compared to the baseline situation (Scenario 1). The SS
level at the upper corner of the Kowloon Bay would be increased to about 10
mg/L under Scenarios 2b and 3b.
However, the SS increase in Kowloon Bay predicted under Scenarios 2b and
3b would still fully comply with the WQO for SS (of no more than 30% increase
from the baseline). No unacceptable cumulative SS impacts would be anticipated.
Unionized Ammonia
5.8.1.11
Under the worst case assumption
of Scenario 1 (adopting the discharge license standards for compiling the THEES
effluent load for continuous discharge), the UIA levels exceed the WQO of 0.021
mg/L in KTAC and KTTS. The predicted UIA levels in KTAC were generally over 0.1
mg/L under the baseline condition, which is considered high. The predicted UIA
levels in Kowloon Bay and the open water of Victoria Harbour outside the
breakwaters of KTTS would be substantially lower and comply well with the WQO.
5.8.1.12
Under Scenarios 2a and 3a (with
the IP scheme), exceedance was still predicted inside KTAC and KTTS but the
extent of UIA level would be reduced as compared to the baseline
condition. The area of high UIA
impact zone (of >0.1 mg/L) in KTAC would be reduced by about 50% under
Scenario 2a (adopting a conservative THEES effluent load) and totally removed
under Scenario 3a (using a realistic THEES effluent load) as shown in Appendix 5.03. The IP scheme (under Scenarios 2a and 3a) would however divert some
UIA from KTAC to the Kowloon Bay area, which causes a slight UIA increase in
the Kowloon Bay area but full compliance of UIA would still be achieved in the
whole Kowloon Bay water and the open water of Victoria Harbour under Scenarios
2a and 3a.
5.8.1.13
Scenarios 2b and 3b (the alternative
runway opening scheme) would induce an even greater UIA improvements at KTAC
and KTTS. The impact zone of high UIA (of over 0.1 mg/L) in KTAC was totally
removed under Scenarios 2b and 3b, refer to Appendix 5.03. However, the runway opening under Scenarios 2b and 3b would allow
broader mixing between Kowloon Bay and KTAC waters, discharging a relatively
larger amount of UIA from KTAC to Kowloon Bay and causing an UIA increase in
the Kowloon Bay waters. The UIA level would marginally exceed the WQO in a
small area at the upper most corner of Kowloon Bay under Scenario 2b (using a
conservative THEES load), whereas full UIA compliance in the whole Kowloon Bay
area would still be maintained under Scenario 3b (using a realistic worst case
of the THEES effluent load). Full
UIA compliance would be achieved in the open Victoria Harbour channel outside
the KTTS breakwaters under both Scenarios 2b and 3b.
5.8.1.14
As there are no biological nor
ecological sensitive receivers in embayed waters of KTAC, KTTS and in areas
near the upper corner of Kowloon Bay, the UIA exceedance (predicted in these
embayed waters only) is considered not a critical concern. Although the alternative KTD improvement
options (under Scenarios 2a, 2b, 3a and 3b) would induce a slight UIA increase
in the Kowloon Bay waters, the overall extent of UIA impact in the KTD waters
(including KTAC and KTTS) as a whole would be significantly improved as better
water circulation would be introduced under the KTD improvement options. Thus,
no unacceptable cumulative UIA impact would be anticipated.
Total Inorganic
Nitrogen
5.8.1.15
Under the baseline condition
(Scenario 1), the TIN levels exceeded the WQO of 0.4 mg/L in KTAC and KTTS. The
predicted TIN levels in KTAC were generally over 5 mg/L. The predicted TIN
levels in Kowloon Bay and the open water of Victoria Harbour would be
substantially lower and generally comply with the WQO under Scenario 1 except
in a very small area at the upper most corner of Kowloon Bay where the TIN
level is slightly over 0.4 mg/L, which exceeded the WQO and is caused by the
nearby background polluted stormwater discharge assumed in the modelling
exercise.
5.8.1.16
Under Scenarios 2a and 3a (with
the IP scheme), exceedance was still predicted inside KTAC and KTTS but the
extent of TIN level would be reduced.
The area of high TIN impact zone (of >5 mg/L) in KTAC would be
reduced by about 50% under Scenarios 2a and 3a as compared to the baseline
condition (Scenario 1) as shown in Appendix 5.03. The IP scheme (under Scenarios 2a and 3a) would however divert
some TIN from KTAC to the Kowloon Bay area, which causes a TIN increase in the
Kowloon Bay. Thus, the area of
marginal TIN exceedance in Kowloon Bay predicted under the baseline scenario
(Scenario 1) would be further expanded under Scenarios 2a and 3a but the
maximum TIN level in Kowloon Bay would still be less than 0.6 mg/L as compared
to the WQO of 0.4 mg/L.
5.8.1.17
Scenarios 2b and 3b (the
alternative runway opening scheme) would induce an even greater TIN improvement
at KTAC and KTTS. The impact zone of high TIN (over 5 mg/L) in KTAC was totally
removed under Scenarios 2b and 3b, refer to Appendix 5.03. However, the runway opening under Scenarios 2b and 3b would allow
broader mixing between Kowloon Bay and KTAC waters, discharging a significant
portion of TIN from KTAC to Kowloon Bay, which causes a TIN increase in the
Kowloon Bay waters. The TIN level in the Kowloon Bay water would be increased
to less than 5 mg/L in the upper most corner of Kowloon Bay under Scenarios 2b
and 3b.
Implication of High TIN Level in Victoria Harbour
5.8.1.21
It should
however be highlighted that red tides are natural phenomena which occur seasonally in both polluted and unpolluted waters (EPD¡¦s publication ¡§Marine
Water Quality in Hong Kong 2014¡¨ refers) and could be induced
by many factors other than the availability of nutrients in marine waters
(e.g. availability of sunlight, water circulation, temperature and wind
conditions etc.). Red tide occurrence would depend on a combination of different factors including flow condition, light penetration,
salinity distribution, nutrient concentrations, nutrient ratios and species
competition, etc.
5.8.1.22
Based on the EPD¡¦s publications
¡§Marine Water Quality in Hong Kong in 2014¡¨, red tides occurred more frequently
in the eastern (72%) and southern (18%)
waters. In 2014, a total of 23 red tides were recorded in Hong Kong waters.
Of these, 16 occurred in the eastern, 5 in Southern, 1 in Western Buffer, 1 in
North Western and none in Victoria Harbour.
5.8.1.23
For
the background nutrient levels in 2014, with reference
to the ¡§Marine Water Quality in Hong
Kong in 2014¡¨, the range of TIN in the eastern waters
was 0.01 - 0.21 mg/L (with a mean level of 0.04 -0.07 mg/L) whilst that of the
central Victoria Harbour (VM1, VM2 and VM4 closest to the KTD waters) was 0.12
¡V 0.51 mg/L (with a mean level of 0.2 -0.29 mg/L). The range of PO4
in the eastern waters was 0.002 - 0.023 mg/L (with a mean level 0.005 - 0.008
mg/L) whilst that of the central Victoria Harbour was 0.013 ¡V 0.043 mg/L (with
a mean level of 0.019 ¡V 0.027 mg/L).
It could be concluded that the background nutrient levels, considering
both N and P, were far higher in the Victoria Harbour. From the 2014 records
for eastern water, it can be concluded that algal bloom could readily take off
at a low N and P level provided that other environmental conditions were
suitable.
5.8.1.24
In the open water environment
in the Victoria Harbour, the effect of tidal flushing was high. As the water was frequently diluted by
horizontal advection or vertical mixing, the accumulation of algal biomass and
hence the chance of algal bloom was more effectively minimized.
Likelihood of Algal
Bloom in KTD Waters
5.8.1.25
The KTD water is subject to the
direct influence of the polluted stormwater discharges from the hinterlands as well as the
background water quality in the open Victoria Harbour where the nutrient levels
are also affected by the polluted runoff generated from the old urbanized areas
on both sides of the Victoria Harbour as well as the influences from other
background nutrient sources such as the Pearl River discharges. The overall
nutrient level in the KTD water is thus considered high. However,
implementation of the proposed IP scheme or opening a gap at the runway would
enhance the water circulation in the embayed waters of KTD which could reduce
the potential for algal biomass accumulation and thus minimize the potential of
red tide formation in the KTD area.
5.8.1.26
Based on the data provided in Section 5.8.1.23, it can be concluded that nutrient level in Kowloon Bay is already
abundant (more than that in the eastern waters) but the existing red tide
occurrence in the water was rare. Thus, it is expected that the potential
increase or redistribution of nutrients in the future due to the proposed IP
scheme or runway opening would unlikely cause any further effect on the algal
bloom formation as the existing red tide occurrence in Kowloon Bay is limited
by other factors. As shown in Appendix
5.03, there would be no significant change in the
overall harbour water quality due to the proposed IP scheme or the runway
opening. On the other hand, the proposed IP scheme or
runway opening would further enhance the water circulation in the KTD waters to
minimize the algae accumulation. Hence, the KTD improvement options would
unlikely increase the risk of algal bloom as compared to the existing
condition.
E. coli
5.8.1.27
There is no WQO for E. coli
available for the KTD waters under the existing situation. Under the baseline condition (Scenario 1), the predicted E. coli
levels were over 2000 no./100mL in KTAC and in general marginally below or
around 610 no./100mL inside KTTS. The predicted E. coli levels in the
open water of Victoria Harbour were generally below 610 no./100mL. However, high E. coli levels
(> 2000 no./100mL) are also predicted in the nearshore area along the
coastline of Victoria Harbour which is subject to the background polluted storm
water discharges assumed in the modelling exercise.
5.8.1.28
Under Scenarios 2a and 3a (with
the IP system) and Scenarios 2b and 3b (with the alternative runway opening
scheme), slight E. coli improvement in KTAC and KTTS was observed as
compared to the baseline conditions. However the overall E. coli pattern
in the KTD waters is considered similar under all the 5 modelling scenarios,
refer to Appendix 5.03.
Sedimentation
5.8.1.29
There is no WQO for
sedimentation rate available for the KTD waters. No ecological sensitive receiver of great importance (such as coral
communities) is identified in the KTD waters. Under the baseline
condition (Scenario 1), the predicted mean sedimentation rate were less than 5
g/m2/day in the Study Area except for some small areas in the KTTS
and the lower reach of KTAC where the mean sedimentation rates were over 10 g/m2/day.
5.8.1.30
Under Scenarios 2a and 3a (with
the IP system) and Scenarios 2b and 3b (with the alternative runway opening
scheme), slight sedimentation reduction in KTAC and KTTS was observed as
compared to the baseline conditions. The areas with relatively high
sedimentation rate of over 10 g/m2/day in KTAC and KTTS were
completely removed under Scenarios 2a, 2b, 3a and 3b. As shown in Appendix 5.03, the overall sedimentation pattern in the KTD waters is considered
similar amongst the modelling scenarios.
Impact on WSRs
5.8.1.31
Following the same approach
adopted under the approved EIA for KTD and the recent KTD studies under
Agreement No. CE30/2008 (CE), this water quality assessment focussed only on
the KTD water bodies (as shown in Diagram 5.01 above), which are within the potential influence zone of the KTD
improvement measures and the THEES effluent discharge (refer to Section
5.6.2.29). Thus, the model results are only
presented for the WSRs that are within the potential influence zone of the
THEES effluent, including the WSD flushing water intakes at Tai Wan (W8) and
Cha Kwo Ling (W12), the intake of the Kai Tak DCS and KTTS as well as the
possible water sports area in KTTS currently being investigated under separate
studies. Other WSRs were found not
to be affected by the KTD improvement works and are therefore not presented.
WSD Flushing Water
Intakes
5.8.1.32
Based on the model results as
summarized in Table 5.19 below, the pollution level
predicted at the WSD intake points including Tai Wan (W8) and Cha Kwo Ling
(W12) intakes would fully comply with the relevant WSD water quality standards
for all the parameters of concern under all the assessment scenarios. Full compliance of WQO was predicted
under all 5 scenarios at these two WSD flushing water intakes closest to the
Project discharge.
Table 5.19 Predicted Water Quality
at Selected WSD Flushing Water Intakes
Parameter
|
Scenario
(see Remarks)
|
WSD Flushing Water Intakes
(see Figure No. 60334056/EIA/5.02)
|
Tai Wan (W8)
|
Cha Kwo Ling (W12)
|
WSD WQC
|
Maximum
Ammonia Nitrogen
(mg/L)
|
1
|
0.206
|
0.359
|
≤1
|
2a
|
0.281
|
0.223
|
2b
|
0.263
|
0.292
|
3a
|
0.204
|
0.197
|
3b
|
0.199
|
0.209
|
Maximum
Suspended Solids (mg/L)
|
1
|
7.7
|
7.6
|
≤10
|
2a
|
8.3
|
7.8
|
2b
|
7.9
|
7.8
|
3a
|
8.2
|
7.7
|
3b
|
7.9
|
7.7
|
Minimum
Dissolved Oxygen (mg/L)
|
1
|
5.6
|
5.6
|
≥2
|
2a
|
5.5
|
5.6
|
2b
|
5.6
|
5.6
|
3a
|
5.6
|
5.6
|
3b
|
5.6
|
5.6
|
Maximum BOD5 (mg/L)
|
1
|
2.0
|
1.7
|
≤10
|
2a
|
2.1
|
1.6
|
2b
|
2.0
|
1.8
|
3a
|
2.1
|
1.6
|
3b
|
2.0
|
1.8
|
Maximum
E. coli (no./100mL)
|
1
|
4,484
|
764
|
≤20,000
|
2a
|
5,953
|
1,208
|
2b
|
4,317
|
787
|
3a
|
5,944
|
1,202
|
3b
|
4,311
|
773
|
Remarks: Data presented are in
mid-depth water level.
Scenario 1: UDS
baseline condition of Victoria Harbour (w/o KTD improvement measures)
Scenario 2a: UDS Cumulative Impact Scenario (THEES based on design effluent
standards) with IP scheme to intercept waters at KTN and KTAC to Kowloon Bay
Scenario 2b: UDS Cumulative Impact Scenario (THEES based on design effluent
standards) with 150m opening at former Kai Tak runway
Scenario 3a: UDS Cumulative Impact Scenario (THEES based on actual measurements)
with IP scheme to intercept waters at KTN and KTAC to Kowloon Bay
Scenario 3b: UDS Cumulative Impact Scenario (THEES based on actual measurements)
with 150m opening at former Kai Tak runway
Kai Tak DCS Cooling
Water Intake
5.8.1.33
There are no specific
criteria/requirements for the Kai Tak DCS cooling water intake from EMSD. The model results at the Kai Tak DCS
cooling water intake are summarized in Table 5.20 below. Under Scenarios
1, 2b and 3b, the intake of the DCS is assumed to be at its existing location
next to the To Kwa Wan Typhoon Shelter (TKWTS). Under Scenarios 2a and 3a, the proposed
IP scheme will alter the intake point of the DCS. The alternative intake points of the
DCS, namely Intake 1 and Intake 2, assumed under Scenarios 2a and 3a are shown
in Diagram 5.02 above. The DCS operation is not sensitive to the
water quality changes at the intake point as confirmed by EMSD. No unacceptable
water quality impact upon the cooling water intake(s) would be resulted.
Table 5.20 Predicted
Water Quality at Kai Tak DCS Cooling Water Intake
Parameter
|
Scenario
(see Remarks)
|
Kai Tak DCS Cooling Water Intakes
(see Figure No. 60334056/EIA/5.02)
|
C11
|
C12
|
C13
|
Maximum Ammonia Nitrogen
(mg/L)
|
1
|
0.245
|
-
|
-
|
2a
|
-
|
7.315
|
3.288
|
2b
|
0.641
|
-
|
-
|
3a
|
-
|
4.798
|
1.971
|
3b
|
0.374
|
-
|
-
|
Maximum Suspended Solids (mg/L)
|
1
|
7.8
|
-
|
-
|
2a
|
-
|
60.7
|
31.8
|
2b
|
8.6
|
-
|
-
|
3a
|
-
|
50.9
|
27.8
|
3b
|
8.5
|
-
|
-
|
Minimum Dissolved Oxygen (mg/L)
|
1
|
5.5
|
-
|
-
|
2a
|
-
|
0.7
|
1.4
|
2b
|
5.4
|
-
|
-
|
3a
|
-
|
1.0
|
2.2
|
3b
|
5.5
|
-
|
-
|
Maximum BOD5 (mg/L)
|
1
|
2.0
|
-
|
-
|
2a
|
-
|
28.5
|
10.5
|
2b
|
2.2
|
-
|
-
|
3a
|
-
|
17.8
|
7.0
|
3b
|
2.1
|
-
|
-
|
Maximum E. coli
(no./100mL)
|
1
|
1,992
|
-
|
-
|
2a
|
-
|
1 E+06
|
30,410
|
2b
|
1,688
|
-
|
-
|
3a
|
-
|
1 E+06
|
29,182
|
3b
|
1,631
|
-
|
-
|
Remarks: Data presented are
in mid-depth water level.
Scenario 1: UDS
baseline condition of Victoria Harbour (w/o KTD improvement measures)
Scenario 2a: UDS Cumulative Impact Scenario (THEES based on design
effluent standards) with IP scheme to intercept waters at KTN and KTAC to
Kowloon Bay
Scenario 2b: UDS Cumulative Impact Scenario (THEES based on
design effluent standards) with 150m opening at former Kai Tak runway
Scenario 3a: UDS Cumulative Impact Scenario (THEES based on actual
measurements) with IP scheme to intercept waters at KTN and KTAC to Kowloon Bay
Scenario 3b: UDS Cumulative Impact Scenario (THEES based on actual
measurements) with 150m opening at former Kai Tak runway
Kwun Tong Typhoon
Shelter / Potential Water Sports Area at Kai Tak
5.8.1.34
The model results at the KTTS
are summarized in Table 5.21 below. Under Scenarios 2a,
2b, 3a and 3b (with the KTD improvement measures), the DO exceedance at KTTS
would be completely eliminated and significant UIA and TIN reduction in the
KTTS would also be achieved. Although UIA and TIN exceedances were still
predicted in KTTS, there is no ecological sensitive receiver of significant
important located in the typhoon shelter. The TIN exceedance in KTD waters was
also assessed to be acceptable in Sections 5.8.1.19 to
5.8.1.26 above. The KTD improvement
measures would actually contribute a positive water quality effect in the KTTS as
compared to the baseline scenario. No unacceptable cumulative water quality
impact would be anticipated.
5.8.1.35
The feasibility of locating a
potential water sports area in KTTS will be investigated under separate studies
of Agreement No. CE30/2008 (CE) and Agreement No. CE73/2014 (TP) . The WQO laid down for secondary contact
and recreational uses stipulates that the annual geometric mean E. coli
level should not exceed 610 no./100mL. The model results showed that the annual
geometric mean E. coli level predicted at the KTTS (where the potential
water sports area is proposed) would be below or around 610 no./100mL as shown
in Table 5.21 below. It should be highlighted that this
potential water sports centre is not a confirmed project and its feasibility is
still subject to confirmation under separate studies. Since this STSTW
relocation project will not change the existing THEES effluent load, and if
this potential water sports centre is carried forward under the separate KTD project,
detailed justifications on the acceptability of using the KTTS for water sports
activities (taking into account the cumulative effect of the existing THEES
discharge as well as any additional mitigation measure required to further
improve the water quality) will be provided under the separate KTD studies.
Table 5.21 Predicted
Water Quality at KTTS / Potential Water Sports Area
Parameter
|
Scenario (see Remarks)
|
WS1 (see Figure No.60334056/EIA/5.02)
|
WQO
|
10%ile Bottom Dissolved Oxygen (mg/L)
|
1
|
1.7
|
≥2
|
2a
|
2.9
|
2b
|
2.2
|
3a
|
3.7
|
3b
|
3.1
|
10%ile Depth-Averaged Dissolved Oxygen (mg/L)
|
1
|
3.3
|
≥4
|
2a
|
4.8
|
2b
|
4.3
|
3a
|
5.2
|
3b
|
4.9
|
Unionised Ammonia
(Annual Average) (mg/L)
|
1
|
0.068
|
≤0.021
|
2a
|
0.033
|
2b
|
0.038
|
3a
|
0.019
|
3b
|
0.022
|
Total Inorganic Nitrogen
(Annual Average) (mg/L)
|
1
|
2.66
|
≤0.4
|
2a
|
1.56
|
2b
|
1.79
|
3a
|
1.59
|
3b
|
1.79
|
Geometric Mean E.
coli (no./100mL)
|
1
|
578
|
≤610
|
2a
|
508
|
2b
|
623
|
3a
|
486
|
3b
|
604
|
Remarks: Bolded
values indicate non-compliance of WQO.
Scenario
1: UDS
baseline condition of Victoria Harbour (w/o KTD improvement measures)
Scenario
2a: UDS Cumulative Impact
Scenario (THEES based on design effluent standards) with IP scheme to intercept
waters at KTN and KTAC to Kowloon Bay
Scenario
2b: UDS Cumulative
Impact Scenario (THEES based on design effluent standards) with 150m opening at
former Kai Tak runway
Scenario
3a: UDS Cumulative
Impact Scenario (THEES based on actual measurements) with IP scheme to
intercept waters at KTN and KTAC to Kowloon Bay
Scenario
3b: UDS Cumulative
Impact Scenario (THEES based on actual measurements) with 150m opening at former
Kai Tak runway
5.8.2.1
The Project operation will not
change the THEES effluent flow and load to the Victoria Harbour. Relocation of
the existing STSTW to cavern will not cause any adverse water quality impact
upon the Victoria Harbour including Kowloon Bay, KTAC and KTTS. The latest mitigation options proposed
under the KTD project would significantly improve the water quality in KTAC and
KTTS (where the THEES effluent is discharged) for all the key water quality
parameters (including SS, BOD, TIN, UIA, DO and sedimentation) as compared to
the baseline condition. The KTD project will in fact cause a beneficial
cumulative water quality effect in the KTD water, minimizing the pollution
level in KTAC and KTTS in the long term.
The latest KTD measures (involving water pumping system or runway
opening option) would however divert some pollution from KTAC waters to Kowloon
Bay, resulting a slight higher pollution level in particular the nutrient level
in the Kowloon Bay waters. However,
as the overall pollution level in the KTAC would be significantly improved and
no exceedance was predicted at the WSRs identified in Kowloon Bay, the overall
cumulative water quality impact resulted from the KTD project during the
operational phase would be acceptable.
Thus, no further mitigation measure is proposed under this Project.
5.8.3.1
Under normal operation of
THEES, the effluent from the CSTW and TPSTW would be transported to the
Victoria Harbour for discharge into the KTN. A 3-month water quality monitoring
programme is thus proposed for KTN at a frequency of once per month after
commissioning of this Project. The monitoring results should be compared with
the routine river water quality monitoring data collected by EPD to verify
whether there is any adverse water quality impact at Kai Tak Nullah as compared
to that before the implementation of this Project. Monitoring parameters should
include DO, SS, BOD, NH3-N, nitrate-nitrogen (NO3-N) and E.
coli. Daily effluent monitoring for the same parameters shall also be
conducted at both TPSTW and STSTW during the water quality monitoring programme
to provide necessary data to assist in identification of the potential impact.
In case adverse impact on KTN is identified from the effluent and water quality
monitoring results, the operating conditions of the treatment and THEES system
should be investigated. In case adverse impact on KTN is identified from this
Project with reference to the effluent and water quality monitoring results,
the operating conditions of the treatment and THEES system should be
investigated, and DSD should extend the water quality monitoring programme for
at least three months or as agreed by the Director of Environmental Protection. Details of the monitoring programme are
provided in the standalone EM&A Manual.
5.8.3.2
Monitoring of the treated
effluent quality from the CSTW should also be carried out in accordance with
the WPCO license to ensure that the effluent quality would comply with the
design standards, which is under the ambit of RO of EPD.
5.8.4.1
This Project would not change
the flow and load of the THEES discharges to Victoria Harbour. No unacceptable
residual water quality impacts would be expected.
5.9.1.1
Two modelling scenarios for
Tolo Harbour were simulated for normal operation of the STSTW under the UDS,
namely Scenarios 4 and 5 respectively.
Scenario 4 is the ¡§without Project¡¨ condition in the UDS where the
existing partial effluent overflow from TPSTW and existing STSTW (due to the
storm effect and capacity constraint of TPEPS and STEPS) would be continued in
the future. Scenario 5 is the ¡§with
Project¡¨ condition in the UDS where the STSTW will be relocated to cavern and
the existing partial effluent overflow from STEPS will be removed, details
refer to Sections 5.6.2.46 to
5.6.2.48 above.
5.9.1.2
The water quality simulation
results of the 2 scenarios are presented in Appendix
5.04a as contour
plots for DO, BOD, TIN, UIA, E. coli, SS, chlorophyll-a and
sedimentation rate. All contour plots in Appendix
5.04a are presented
as annual arithmetic averages except for the annual geometric mean E. coli
levels, minimum DA DO and minimum bottom DO. The model results at different WSR
points are summarized in Appendix
5.05. These WSR points include seawater
intakes (WSD¡¦s flushing water intakes and cooling water intake of CUHK),
ecological resources (mangroves, SSSI, FCZ and corals), Shuen Wan Typhoon
Shelter and Lung Mei Beach as shown in Figure No.
60334056/EIA/5.03. The model results (in Appendix 5.05) for ecological resources, Shuen Wan Typhoon Shelter and Lung Mei
Beach are presented as minimum DO, geometric mean E. coli and maximum
5-day moving mean chlorophyll-a over the 1-year simulation period for
comparison with the assessment criteria (based on the WQOs specified under the
WPCO). In addition, the model
results for sedimentation rate (in Appendix 5.05) are presented as maximum values for comparison with the reference
sedimentation limit to address the potential sedimentation impact upon the
coral communities. The model results for seawater intakes are presented as
maximum values (for BOD, NH3-N and E. coli) and minimum value
(for DO) to check against the target seawater quality objectives specified by
the WSD.
Dissolved Oxygen
5.9.1.3
The DO levels in Tolo Harbour
predicted under Scenarios 4 and 5 are compared in Appendix 5.04a. The DO levels
predicted under the 2 scenarios are considered within a similar range. The DO levels predicted at all WSRs
would meet the WQO except for the mangrove site at Tolo Pond (M1) where the
minimum surface and middle DO was only 1.5 and 3.4 mg/L respectively under the
¡§without Project¡¨ scenario (Scenario 4) as compared to the WQO of no less than
4 mg/L (see Appendix 5.05). Operation of this Project (under Scenario 5) would improve
the minimum middle DO level at this mangrove site to 3.5 mg/L (by about 1
mg/L). No change in the minimum surface DO at this mangrove site was predicted
between the 2 scenarios. The
low DO at M1 was mainly contributed from the background pollution loading
assumed in the model and not induced by this Project.
Unionized Ammonia / Total Inorganic Nitrogen / Ammonia Nitrogen
5.9.1.4
The UIA and TIN levels
predicted under Scenarios 4 and 5 are compared in Appendix 5.04a.
Operation of this Project will improve the UIA and TIN level in the Sha Tin Hoi
area of the Tolo Harbour. There is no WQO available for UIA and TIN in the
marine water of Tolo Harbour. In
terms of the NH3-N level, the WSD has
specified a target objective for their flushing water intakes. The model
results showed that full compliance with the target NH3-N objective would be achieved at the WSD flushing
water intakes at Sha Tin (W1) and Tai Po (W2) under both Scenarios 4 and 5. The maximum NH3-N
level predicted at W1 and W2 under the ¡§without Project¡¨ scenario (Scenario 4) was 0.339 and 0.202 mg/L respectively
as compared to the target objective of 1 mg/L (see Appendix 5.05). Operation of this Project (under Scenario 5) would
improve the maximum NH3-N level at
W1 to 0.242 mg/L as compared to the ¡§without Project¡¨ condition of 0.339 mg/L. No significant change in the
NH3-N level was however observed at W2
between the 2 scenarios.
Suspended Solids
5.9.1.5
The SS levels predicted under
Scenarios 4 and 5 are compared in Appendix 5.04a.
Operation of this Project under Scenario 5 would slightly reduce the mean SS
level in Sha Tin Hoi waters. There is no WQO available for SS in the marine
water of Tolo Harbour. The WSD has however specified a target SS objective for their flushing water intakes. Under the ¡§without
Project¡¨ scenario (Scenario 4), the maximum SS level predicted at the WSD flushing water intake at
Sha Tin (W1) was 11.1 mg/L, which as compared to the
WSD¡¦s target objective of no more than 10 mg/L (see Appendix 5.05). Operation of this Project under Scenario 5 would reduce
the maximum SS level at W1 to 10.2 mg/L as compared to the objective of 10
m/L. Full compliance with the
target SS objective was observed at the WSD flushing water intake at Tai Po
(W2) under both scenarios.
Biochemical Oxygen Demand
5.9.1.6
The BOD levels predicted under
Scenarios 4 and 5 are compared in Appendix 5.04a.
Operation of this Project under Scenario 5 would significantly reduce the mean
BOD level in the whole Tolo Harbour and Channel WCZ. There is no WQO available
for BOD in the marine water of Tolo Harbour. The WSD
has however specified a target BOD objective
for their flushing water intakes. Under the ¡§without Project¡¨ condition
(Scenario 4), the maximum BOD level predicted at W1
and W2 was 12.2 and 10.5 mg/L respectively, as compared to the WSD¡¦s target
objective of no more than 10 mg/L. With implementation of this Project (under
Scenario 5), the BOD at W1 and W2 would fully comply with the target BOD
objective of 10 mg/L (see Appendix 5.05).
E. coli
5.9.1.7
The E. coli levels
predicted under Scenarios 4 and 5 are compared in Appendix 5.04a. No obvious change in
the E. coli pattern was observed between the 2 scenarios as seen from
the contour plots. The geometric
mean E. coli levels predicted in most areas of Tolo Harbour and Channel
WCZ including all the FCZs are well below 610 no./100mL under both Scenarios 4
and 6, and complied with the WQO for secondary contact recreation subzone and
FCZ. The geometric mean E. coli
levels in the outer main channel of Shing Mun River (which are closest to the
emergency submarine outfall of STSTW / CSTW) also complied well with the WQO of
610 no./100mL. Also, this Project (Scenario 5) would not cause any increase in
the E. coli level in the Shing Mun River, as compared to Scenario 4
(without this Project). The geometric mean E. coli level predicted at
Lung Mei Beach (B1) was predicted to be less than 10 no./100mL, which also
complied with the beach WQO of 180 no./100mL (see Appendix 5.05). The maximum E.coli levels predicted at the WSD flushing
water intakes (W1 and W2) are similar with and without this Project and all the
maximum values are less than 1,500 no./100mL, which comply well with the WSD¡¦s
target objective of 20,000 no./100mL. E. coli exceedance was only
predicted at one isolated WSR, namely the mangrove site at Tolo Pond (M1) where
the geometric mean level would be 806 and 787 no./100mL for Scenarios 4 and 5
respectively, as compared to the WQO of no less than 610 no./100mL (see Appendix 5.05). As the exceedance was predicted under both Scenarios 4 (without
Project scenario) and 5 (with Project scenario) and the E. coli level
would be slightly improved under Scenario 5 (with Project scenario), the E.
coli exceedance at M1 was not caused by this Project. No adverse E. coli
impact is predicted from the Project operation.
Sedimentation
5.9.1.8
The sedimentation rates predicted
under Scenarios 4 and 5 are compared in Appendix 5.04a. No obvious change in the sedimentation
pattern was observed between the 2 scenarios as seen from the contour plots.
The maximum sedimentation levels predicted in Tolo Harbour including all the
coral sites are well below 100 g/m2/day under both scenarios and
fully complied with the sedimentation criterion. No adverse sedimentation impact is
predicted.
Chlorophyll-a
5.9.1.10
The chlorophyll-a levels
predicted under Scenarios 4 and 5 are compared in Appendix 5.04a. Operation of this Project under Scenario 5 would reduce the
chlorophyll-a concentration in the Harbour and Buffer Subzones of the
Tolo Harbour and Channel WCZ. Tolo Harbour is a shallow landlocked water body
with low water exchange rate and poor flushing capacity, which is susceptible
to algal formation and accumulation of algae. Thus, the maximum chlorophyll-a
levels at all WSRs are considered high under the ¡§without Project¡¨ condition
(Scenario 4). Implementation of this
Project (Scenario 5) would minimize the chlorophyll-a level at the WSRs. In comparison with
the ¡§without Project¡¨ levels of 9 - 64 µg/L
(under Scenario 4), the maximum chlorophyll-a predicted during operation
of this Project (Scenario 5) would be reduced to 8 ¡V 58 µg/L at the WSRs. Thus, this Proejct would potentially
minimize the risk of red tide in Tolo Harbour.
5.9.1.11
It should be
highlighted that not all WSRs are likely to be
adversely affected by high level of chlorophyll-a. Since the
primary concern of red tides is oxygen depletion, the key WSRs that are most
sensitive to red tides is considered to be the fisheries operations at the FCZs
and the sensitive fisheries resources in Tolo Harbour, If the bloom comprises
toxin-producing species, the bloom could harm cultured fish or impact their
marketability.
5.9.1.12
The water quality model used in
this EIA incorporates various physical / biochemical processes. Biochemical
processes such as nitrification, algal growth and decay and the decay of
organic matter, were all taken into account in the modelling exercise. However,
in terms of the effects on oxygen levels, the model results indicates that
oxygen levels in the water of the four FCZs (namely F1, F2, F3 and F4
respectively) and the two sensitive fisheries resources (namely potential
subzone of Yim Tin Tsai FCZ near Centre Island and important nursery area for
commercial fisheries resources at Three Fathoms Cove respectively) would not be
depleted under the modelling scenarios.
In terms of chlorophyll-a, the maximum levels predicted at these FCZs
and sensitive fisheries resources would be minimized from 18 ¡V 36 µg/L (under the ¡§without Project¡¨ scenario) to 12 - 25
µg/L (under the ¡§with Project¡¨ scenario).
Impacts to Mangroves
5.9.1.14
The low DO and high E.coli
levels predicted at the mangrove site at Tolo Pond M1 was mainly contributed
from the background pollution loading assumed in the model and not induced by
this Project as discussed in Sections 5.9.1.3 and 5.9.1.7. This Project would actually improve the DO
and E. coli levels at M1 and thus no adverse water quality impact upon
this mangrove site is predicted from the Project.
5.9.2.1
The Project operation will
improve the water quality in Tolo Harbour as compared to the ¡§without Project¡¨
condition. This Project will not cause any adverse water quality impact upon
the Tolo Harbour. This Project will in fact have a positive water quality
effect in Tolo Harbour, minimizing the pollution level and thus potentially
reduce the risk of algal bloom in the Tolo harbour (due to the predicted
decrease in the chlorophyll-a and nutrient level) in the long term. No further mitigation measure is
recommended for normal plant operation.
5.9.3.1
Monitoring of the treated
effluent quality from the CSTW should be carried out in accordance with the
WPCO license to ensure that the effluent quality would comply with the design
standards, which is under the ambit of RO of EPD. No other monitoring programme specific
to normal Project operation is considered necessary.
5.9.4.1
This Project would not
adversely affect the Tolo Harbour water quality under normal plant
operation. No unacceptable
residual water quality impact is predicted.
5.10.1.1
A continuous THEES maintenance
discharge for a period of 4 weeks under the UDS was simulated under Scenarios
6a and 6b. During the THEES
maintenance period, secondarily treated and disinfected effluent would be
discharged from both CSTW and TPSTW.
Scenario 6a follows the existing practice where the THEES maintenance
events could be scheduled in March (within the algae blooming season identified
in this EIA). Scenario 6b however
assumed that the THEES maintenance will be avoided in algae blooming season as
recommended by this Project, details refer to Sections
5.6.2.49 to 5.6.2.51. The model results for Scenarios 6a and 6b (with
THEES maintenance discharge) are compared with the model results for Scenario 5
(normal Project operation without THEES maintenance) to identify the water
quality changes due to the THEES maintenance. Scenario 5 (¡§with Project¡¨
condition) is basically same as Scenario 4 (¡§without Project¡¨ condition) except
that the existing partial effluent flow from STEPS would be removed under
Scenario 5 as discussed in Section 5.6.2.48.
5.10.1.3
As shown in Appendix 5.04a
and Appendix 5.05,
the extent of water quality impact is generally larger under the THEES
maintenance (Scenarios 6a and 6b) than that of the normal plant operation
(under Scenario 5).
5.10.1.4
Although the maintenance
discharge event would inevitably cause an increase in pollution levels in Tolo
Harbour, it should be highlighted that the potential impact would be
reversible. The time for recovery
at selected WSRs are presented as time series plots in Appendix
5.04b and
Appendix 5.04c for Scenarios 6a and 6b respectively. Selected WSRs include WSD flushing water
intakes at Sha Tin (W1) and Tai Po (W2), coral communities at Sha Tin Hoi North
(CR16) and Sha Tin Hoi South (CR17), mangrove site at Tolo Pond (M1), fish
culture zones at Yam Tin Tsai (F1), Yam Tin Tsai East (F2), Yung Shue Au (F3)
and Lo Fu Wat (F4), beach at Lung Mei (B1), coral communities at Tai Po
Industrial Estate (CR1) and EPD monitoring stations (TM4 and TM6) as shown in Figure No. 60334056/EIA/5.03. It should be noted
that the water quality recovery time at the two sensitive fishery resources
(namely potential subzone of Yim Tin Tsai FCZ near Centre Island and important
nursery area for commercial fisheries resources at Three Fathoms Cove
respectively) are assessed with reference to the time series plots for TM4 and
F3 respectively (see Section 5.9.1.13 above).The time series plots for W1, W2, CR16, CR17, F1, F2, F3, F4,
B1, TM4 and TM6 are presented for key parameters of concern including TIN, SS,
chlorophyll-a, E. coli to illustrate the spatial changes of
pollution elevations at WSRs both close to and further away from the
maintenance discharge points. In
addition, the time series plots also include DO at M1 and BOD (at W1 and W2) to
show the water quality recovery trends at these WSR points, which are
relatively close to the effluent bypass locations.
Dissolved Oxygen
5.10.1.5
The dissolved oxygen (DO)
levels in Tolo Harbour predicted under Scenarios 5, 6a and 6b are compared in Appendix
5.04a. The contour plots showed that the mean DO levels in the inner Tolo
Harbour near the TPSTW discharge would slightly increase under the maintenance
discharge (Scenarios 6a and 6b) as compared to the baseline mean DO levels
under Scenario 5. The THEES
maintenance discharge under Scenario 6a would however decrease the minimum DO
and minimum bottom DO values predicted over the simulation period in the inner
Tolo Habour. Since the bypass of nutrient-rich effluent could simulate algal
growth in the receiving water, DO increase may occur during the maintenance
discharge period due to photosynthesis of green algae, which could produce oxygen
in marine water, and hence, resulting an overall increase in the mean DO level
over the simulation period. A decrease in the DO level could however occur
after termination of the maintenance discharge due to the degradation of dead
algal material when the algal growth is subsided, and thus causing a decrease
in the minimum DO levels predicted over the simulation period, whilst the
overall mean DO levels over the simulation period could be maintained to above
or around the baseline levels. Scenario 6b (THEES maintenance outside algae
blooming season) would however cause no obvious change in the pattern of
minimum DA DO and minimum bottom DO as compared to the normal condition under
Scenario 5.
5.10.1.6
The DO levels predicted at all
WSRs under Scenarios 6a and 6b would meet the DO criterion except for the
mangrove site at Tolo Pond (M1) where the minimum surface and middle DO would
be 1.5 and 3.2 mg/L as well as 1.5 and 3.5 mg/L for Scenarios 6a and 6b respectively, as
compared to the WQO of no less than 4 mg/L (see Appendix
5.05).
However, the baseline minimum DO under Scenario 5 was also low with a surface
and middle value of 1.5 and 3.5 mg/L respectively. Hence, the low DO at M1 was
not caused by this Project and is mainly contributed from the background
pollution loading. The change in DO at M1 caused by
the THEES maintenance is considered small or negligible. The time series plots
in Figure 19 of Appendix
5.04b and Appendix
5.04c also
showed that the maintenance discharge would not cause any obvious DO decrease
at M1. It should also be noted that the DO levels mentioned
above represent the minimum values over the entire 1-year simulation period for
comparison with the WQO. The time series plots showed that the DO levels at M1
would actually be higher than these minimum values for most of the times.
Please also observe the model limitations as stated in Sections 5.6.2.54 and 5.6.2.55.
Unionized Ammonia / Total Inorganic Nitrogen /
Ammonia Nitrogen
5.10.1.7
The unionized ammonia (UIA) and
total inorganic nitrogen (TIN) levels predicted under Scenarios 5, 6a and 6b
are compared in Appendix
5.04a. The
maintenance discharge under Scenarios 6a and 6b
would inevitably cause a UIA and TIN increase in the inner Tolo Harbour. There
is no WQO available for UIA and TIN in the marine water of Tolo Harbour. In terms of the ammonia nitrogen (NH3-N) level, the WSD has specified a target objective for their
flushing water intakes. The maximum NH3-N level predicted at W1 was about 1.1 mg/L under Scenario
6a, which is near the WSD¡¦s target objective of no more than 1 mg/L. However,
for comparison, the normal NH3-N level at W1 (under Scenario 5) was only 0.242 mg/L (see Appendix
5.05). For the maintenance event outside algae blooming season
(Scenario 6b), the maximum NH3-N level at W1 was reduced to 0.314
mg/L, which is well below the WSD target objective of 1 mg/L. Full compliance of NH3-N
was predicted at the remaining WSD flushing water intake at Tai Po (W2) during
the maintenance bypass event under Scenarios 5, 6a and 6b. It should be noted that the NH3-N
levels mentioned above represent the maximum values over the entire 1-year
simulation period. The NH3-N
levels would actually be lower than these maximum values for most of the times.
5.10.1.8
As shown in the time series
plots in Figures 10 to 12of Appendix 5.04b and Appendix 5.04c,
greater TIN impact was found at the WSD flushing water intakes at Sha Tin (W1)
and Tai Po (W2), coral communities at Sha Tin Hoi North (CR16) and Sha Tin Hoi
South (CR17), which are relatively closer to the discharge points of the
effluent bypass. The TIN increase
at Yam Tin Tsai FCZ (F1), Yam Tin Tsai East FCZ (F2), Yung Shue Au FCZ /
important nursery area for commercial fisheries resources at Three Fathoms Cove
(F3), Lo Fu Wat FCZ (F4), beach at Lung Mei (B1), EPD monitoring station (TM6)
and potential subzone of Yim Tin Tsai FCZ near Centre Island / EPD monitoring
station (TM4), which are further away from the effluent bypass locations, would
be less significant. Since the TIN level is the sum of NH3-N and
oxidized nitrogen, the time series plots for TIN presented in Appendix 5.04b
and Appendix 5.04c
can also reflect the recovery period for NH3-N at the WSD flushing
water intakes W1 and W2. The time
series plots showed that the TIN levels at W1 and W2 would significantly
increase during the maintenance discharge event (under Scenario 6a). TIN
increase was also observed at W1 and W2 for the maintenance
event outside algae blooming season under Scenario 6b but the magnitude
of increase is significantly smaller. The TIN levels at W1 and W2 would return
to the baseline condition within about 2 weeks after termination of the
effluent bypass under both Scenarios 6a and 6b.
Suspended Solids
5.10.1.9
The suspended solids (SS)
levels predicted under Scenarios 5, 6a and 6b are compared in Appendix 5.04a. The maintenance discharge under Scenarios 6a and 6b would not
cause any obvious change in the mean SS pattern in the Tolo Harbour as compared
to the normal condition under Scenario 5. There is no WQO available for SS in
the marine water of Tolo Harbour. The WSD has however specified a target SS objective for their flushing water intakes. The maximum SS levels predicted at the WSD flushing water intakes
at Sha Tin (W1) and Tai Po (W2) were 10.7 and 10.8 mg/L (under Scenario 6a), and 11.2 and
10.7 mg/L (under Scenario 6b) respectively, which are slightly above the WSD¡¦s
target objective of no more than 10 mg/L. Since the normal SS levels at W1 and
W2 under Scenario 5 (of 10.2 and 9.3 mg/L respectively) are already high
as compared to the WSD criterion of 10 mg/L., the SS contribution from the
effluent bypass is considered small. . It should be noted that the SS levels
mentioned above represent the maximum values over the entire 1-year simulation
period. The SS levels would
actually be lower than these maximum values and meet the SS objective for most
of the times.
5.10.1.10
As shown in the time series
plots in Figures 13 to 15 of Appendices 5.04b and 5.04c, greater SS increase was observed at W1, W2, CR16
and CR17 under Scenario 6a, whilst the SS increase at F1, F2, F3, F4, TM4, TM6
and B1, which are further away from the maintenance discharge, is less
significant. The maintenance event outside algae blooming season
(Scenario 6b) would however cause a smaller SS in
5.10.1.11
crease at all the selected
WSRs. The time series plots showed that the SS impact at W1 and W2 would return
to the normal levels within about 1 month after the end of the discharge
period.
Biochemical Oxygen Demand
5.10.1.12 The BOD levels predicted under Scenarios 5, 6a and 6b are compared
in Appendix 5.04a. The maintenance discharge under Scenario 6a
and 6b would inevitably cause a BOD increase in the Tolo Harbour. There
is no WQO available for BOD in the marine water of Tolo Harbour. The WSD has however specified a target BOD objective for their flushing water intakes. The maximum BOD levels predicted at W1 and W2 were 15.9 and
20.3 mg/L respectively under Scenario 6a, which are considered high as compared
to the WSD¡¦s target objective of no more than 10 mg/L (see Appendix
5.05). For
comparison, the maximum BOD level at W1 and W2 under the normal THEES and
Project operation (Scenario 5) was 9.1 and 8.5 mg/L respectively. The maintenance event outside algae blooming season (Scenario 6b) would reduce the maximum BOD level predicted at W1 and
W2 to 9.1 and 8.5 mg/L respectively, which is
same as the condition under normal THEES and Project operation (Scenario 5) and
fully met the BOD criterion. It should be noted that the BOD levels
mentioned above represent the maximum values over the entire 1-year simulation
period. The BOD levels would
actually be lower than these maximum values for most of the times.
5.10.1.13
As shown in the time series
plots in Figures 20 and 21 of Appendices 5.04b and 5.04c, the BOD levels at W1
and W2 would increase during and after the maintenance discharge. The time
series plots showed that the BOD levels at W1 and W2 would return to a
condition similar to the baseline situation within about 2 months after
termination of the maintenance discharge under Scenarios 6a, whilst the
recovery time under Scenario 6b would be much shorter in 2 weeks after the end
of the maintenance discharge.
E. coli
5.10.1.14 The E. coli levels predicted under Scenarios 5, 6a and 6b are
compared in Appendix
5.04a. The E.coli levels in Tolo Harbour
are predicted to be not significantly changed by the bypass of disinfected
effluent. The E. coli pattern
simulated under the maintenance discharge (Scenarios 6a and 6b) is similar to
that of the normal Project operation (under Scenario 5). The geometric mean E. coli levels
predicted in most areas of Tolo Harbour and Channel WCZ including all the FCZs
are well below 610 no./100mL under Scenarios 6a and 6b, and fully complied with
the WQO for secondary contact recreation subzone and FCZ. The geometric mean E. coli levels
in the outer main channel of Shing Mun River (which are closest to the
emergency submarine outfall of STSTW / CSTW) also complied well with the WQO of
610 no./100mL. Also, the THEES maintenance discharges (under Scenarios 6a and
6b) would not cause any increase in the E. coli level in the Shing Mun
River, as compared to Scenario 5 (without THEES maintenance). The geometric
mean E. coli level predicted at Lung Mei Beach (B1) was predicted to be
less than 10 no./100mL under both scenarios, which also complied with the beach
WQO of 180 mg/L (see Appendix
5.05). The maximum E.coli
levels predicted at the WSD flushing water intakes (namely W1 and W2) are
similar with and without the maintenance event and all the predicted maximum
values are less than 1,500 no./100mL, which comply well with the WSD¡¦s target
objective of 20,000 no./100mL. No adverse E. coli impact would be caused
by the maintenance discharge.
5.10.1.15
E. coli exceedance was only predicted at one isolated WSR, namely the
mangrove site at Tolo Pond (M1) where the geometric mean level would be 803 and
792 no./100mL for Scenarios 6a and 6b respectively, as compared to the WQO of
no less than 610 no./100mL (see Appendix 5.05).
However, the baseline E. coli under Scenario 5 would also exceed the WQO
with geometric mean value of 787 no./100mL. Hence, the E. coli
exceedance at M1 was mainly caused by the background pollution loading. The E.coli contribution from the
maintenance discharge is considered small.
5.10.1.16
The time series plots in
Figures 16 to 18 of Appendices
5.04b and 5.04c
also showed that the maintenance discharge would cause no obvious change to the
baseline E. coli levels at W1, W2, CR16, CR17, F1, F2, F3, F4, B1, TM4
and TM6.
Sedimentation
5.10.1.17
The sedimentation rates
predicted under Scenarios 5, 6a and 6b are compared in Appendix 5.04a. The model predicted that the
sedimentation in Tolo Harbour was not adversely affected by the THEES
maintenance discharge event. The
sedimentation pattern simulated under all the scenarios is similar. The maximum sedimentation levels
predicted in Tolo Harbour including all the coral sites are well below 100 g/m2/day
under Scenarios 6a and 6b, and fully complied with the sedimentation
criterion. No adverse sedimentation
impacts would be caused by the maintenance discharge.
Chlorophyll-a
5.10.1.18
Tolo Harbour is a shallow landlocked
water body with low water exchange rate and poor flushing capacity, which is
susceptible to algal formation and accumulation of algae (see Section
5.9.1.9 above). Hence, the maximum
chlorophyll-a levels at all WSRs under normal operation of the THEES in
UDS (Scenario 5) is already considered high (see Appendix 5.05).
The model predicted that the THEES
discharge under the existing practice (Scenario 6a) would further increase the
peak levels of chlorophyll-a at the WSRs. In
comparison with the normal peak levels of 8 ¡V 58 µg/L (under Scenario 5), the
peak chlorophyll-a values predicted at the WSRs under Scenario 6a would
range from 11 ¡V 159 µg/L. The largest difference between Scenarios 5 and 6a was
found at the coral site at Tai Po Industrial Estate (CR1) with an absolute
difference of 77 µg/L. The maximum
value of 159 µg/L would however occur at the mangrove site at Tolo Pond
(M1). Please also observe the model limitations
as stated in Sections 5.6.2.54 and 5.6.2.55. The maintenance event outside algae blooming
season (Scenario 6b) would significantly reduce the peak chlorophyll-a
values at the WSRs to 8 ¡V 58 µg/L, which is same as the normal range under Scenario 5. The trends of chlorophyll-a during and after the maintenance discharge are illustrated in the time series plots in Figures 01 to 09 of
Appendices 5.04b and 5.04c for W1, W2, CR16, CR17, F1, F2, F3, F4, TM4,
TM6 and B1.
5.10.1.19
The key WSRs that are most
sensitive to red tides is considered to be the fisheries operations at the FCZs
and the sensitive fisheries resources in Tolo Harbour (refer to Sections 5.9.1.10 to 5.9.1.13 above), The peak
chlorophyll-a values predicted at the four FCZs at Yam Tin Tsai (F1),
Yam Tin Tsai East (F2), Yung Shue Au (F3) and Lo Fu Wai (F4) respectively, the
potential subzone of Yam Tin Tsai FCZ and the important nursery area for
commercial fisheries resources at Three Fathoms Cove would range from 22 ¡V 79 µg/L under the existing practice of
THEES maintenance (Scenarios 6a), as compared to the normal situation (Scenario
5) of 12 ¡V 25 µg/L. This Project would optimize the THEES
maintenance operation and reduce the peak chlorophyll-a levels at the
FCZs and sensitive fisheries resources to a range of 12 ¡V 49 µg/L under Scenario 6b. It should be noted that the chlorophyll-a
levels mentioned above represent the maximum 5-day running means over the
entire 1-year simulation period.
The actual
chlorophyll-a levels at these fisheries resources would be varying and the
predicted peak chlorophyll-a levels would only occur
for a short period of times as indicated in the time series plots in Figures 01
¡V 09 of Appendices 5.04b and 5.04c.
5.10.1.20
The time series plots in Appendices 5.04b and 5.04c also showed that the
chlorophyll-a elevations caused by the THEES maintenance
discharge would be reversible. The
model predicted that the chlorophyll-a levels can return to the
condition similar to the baseline levels within about 1.5 months after
termination of the effluent bypass under Scenario 6a, whilst Scenario 6b is
predicted to have a shorter recovery time of about 2 weeks after the end of the
maintenance discharge.
Discussion on Potential Impacts on WSRs
5.10.1.21
THEES maintenance discharge
would increase the NH3-N, SS and BOD levels at the WSD flushing
water intakes at Sha Tin (W1) and Tai Po (W2), the chlorophyll-a levels
at all WSRs as well as the E. coli levels at the mangrove site (M1)
under Scenarios 6a and 6b. The implications of these pollution increases
including the potential impacts upon the users of the recreational waters due
to the discharge of secondarily treated and disinfected effluent into the Tolo
Harbour are discussed in the sections below.
Impact to WSD Flushing Water Intakes (W1 and W2)
5.10.1.22
The THEES maintenance operation
outside algae blooming season as recommended
under this Project (Scenario 6b) would generally minimize the pollution levels
at the flushing water intakes. The
NH3-N and BOD exceedances predicted at the flushing water intakes
under the existing THEES maintenance practice (Scenario 6a) would be eliminated
under this Project with the THEES maintenance discharge outside algae blooming season (Scenario 6b), refer to Sections 5.10.1.7 and 5.10.1.12.
However, residual SS impact was still predicted at the flushing water intake
under the maintenance event outside algae blooming
season. As compared to the target SS standard of 10 mg/L, the maintenance event outside algae blooming season
would cause a SS exceedance level of only 1.2 and 0.7 mg/L at W1 and W2
respectively and this degree of SS exceedance is considered minor. Considering that the E. coli
bacterial level at the intake points would not be adversely affected by the
discharge of disinfected effluent and the SS increase induced by the THEES
maintenance discharge would be small as compared to the background levels (see Section 5.10.1.9) and in view that this minor SS
exceedance would only occur in a very short period of time and the pollution
increase caused by the maintenance discharge would be reversible, no
significant environmental / health impacts to the end users of the intake water
would be anticipated from the THEES maintenance discharge. As a general
measure, to minimize any impact on the flushing water intakes due to planned
maintenance discharge, close communication between DSD and WSD is considered to
be an effective means. Should it
appear necessary, silt screen may be installed at the flushing water intakes to
reduce the SS impacts arising from the planned maintenance discharge.
Chlorophyll-a Impacts at Fisheries Resources
5.10.1.23
This Project would optimize the
THEES maintenance discharge and reduce the peak chlorophyll-a levels at
all important fisheries resources identified in Tolo Harbour as compared to
that induced by the existing THEES maintenance practices. This Project would thus have a
beneficial effect to the fisheries resources and potentially minimize the risk
of red tides during the regular THEES maintenance events (Please also see Section 5.10.1.9 above).
5.10.1.24
It should
however be highlighted that red tides are natural phenomena which occur seasonally in both polluted and unpolluted waters (EPD¡¦s
publication ¡§Marine Water Quality in Hong Kong 2014¡¨ refers) and could be induced by many factors other than the availability of
nutrients in marine waters (e.g. availability of sunlight, water
circulation, temperature and wind conditions etc.). Red tide occurrence would
depend on a
combination of different factors including flow condition, light penetration,
salinity distribution, nutrient concentrations, nutrient ratios and species
competition, etc. . Past research studies on long-term water quality data in Hong Kong
suggested that, under favourable environmental conditions (e.g. in stagnant
water, under calm wind condition and with sufficient light energy), red tide
can be trigged at a very low nutrient level.
5.10.1.25
From the past records, the last
THEES maintenance event with significant volume of effluent bypass to Tolo
Harbour under complete closure of the THEES effluent export tunnel occurred in
December 2010. Appendix
5.08 compares the historic chlorophyll-a levels and red tide
occurrences recorded in Tolo Harbour from January 2010 to December 2011 (i.e.
before, during and after this historic THEES closure period). Other than one THEES closure event in
December 2010, no other THEES closure period was recorded in January 2010 to
December 2011. The comparison plot showed that, despite the high volume of
effluent discharge to Tolo Harbour in December 2010, there is no marked
increase in the chlorophyll-a levels and the frequency of red tide
occurrence during and after the THEES closure event. Also, no correlation
between the chlorophyll-a levels, the red tide occurrences and the
historic THEES maintenance discharge is identified from the comparison plot. Thus, the THEES maintenance discharge may
not be a critical or major factor for triggering red tide in Tolo Harbour. Nevertheless, specific water quality
monitoring programme and mitigation measures are recommended under this Project
to minimize any potential water quality impacts during the THEES maintenance
discharge as presented in Sections 5.10.2 and 5.10.3 below.
5.10.1.26
It should also be noted that
any potential impacts from red tide or harmful algal blooms (HABs) that may
arise in the Tolo Harbour is currently managed and responded under the routine
red tide monitoring and management protocol and response plan adopted by the
government in Hong Kong. AFCD is acting as the coordinator of the Red Tide
Reporting Network, to receive reports of red tide, conduct investigation and
provide warning of the risk associated and appropriate mitigation measures. The
objectives of this red tide monitoring programme are to provide coordination of
monitoring and response to red tides/HABs and fish kills and to compile and
synthesize data necessary to effectively manage fisheries resources, protect
human health and the marine ecosystems.
Details of the existing red tide monitoring and management plan are
provided in the website (http://www.hkredtide.org/).
5.10.1.27
With implementation of the
mitigation measures and monitoring programme recommended under this Project,
the potential impacts from the maintenance discharge events would be minimized.
Impact to Mangroves
5.10.1.28
The low DO and high E.coli
levels predicted at the mangrove site at Tolo Pond M1 was not caused by this
Project and is mainly contributed from the background pollution loading as
discussed in Sections 5.10.1.6 and 5.10.1.14.
Although the high E. coli and low DO levels were predicted at the
mangrove site at Tolo Pond (M1), the natural pollution tolerance (or pollution
exclusion) displayed by mangroves is well documented. Past studies of mangroves
concluded that the mangrove habitats are able to grow in areas of rich
nutrient, low oxygen and high bacteria level and not adversely affected by high
pollution loads (including concentrated sewage effluent) . It is considered that the temporary and
minor E. coli increase caused by the Project discharge would not
adversely affect the mangrove site.
No long-term insurmountable water quality impact upon the mangrove site
would be caused by the maintenance discharge.
Impacts upon Water Recreational Uses
5.10.1.29
The marine water in Tolo Harbour
and Channel WCZ is designated under the WPCO as secondary contact recreation
subzone for water sports and water recreational activities. Since all the
maintenance discharge effluents would be secondarily treated and disinfected
prior to their discharge into the sea, the potential health impact upon the
users of the recreational waters could be minimized. As shown in Figure 07 of Appendix 5.04a,
the maintenance discharge would not cause any obvious elevation of E. coli
levels in Tolo Harbour and Shing Mun River as compared to the baseline
condition with full compliance with the WQO for E. coli (≤ 610 no./100mL) in
most of the Tolo Harbour and Channel WCZ.
As shown in Figure 07 of Appendix 5.04a,
the temporary disinfected effluent would not induce any E. coli plume in
Tolo Harbour. Thus, no health
implication upon the users of the secondary recreational water would be
anticipated from the maintenance discharge.
5.10.2.1
THEES is currently in operation
and is not proposed under this Project. To maintain proper functioning and
integrity of the THEES, regular inspection and maintenance of the THEES system
are inevitable under the existing practice. It should be highlighted that this
Project will not change the frequency, flow and load of the existing THEES
maintenance discharge. In fact, a number of additional mitigation measures
(which are not adopted under the existing practice) are proposed under this
Project to further minimize the water quality impact. These measures are described as follows.
5.10.2.2
Relevant government departments including EPD, WSD and AFCD as
well as key stakeholders for mariculture and
fisheries in Tolo
Harbour should be informed of the THEES maintenance event prior to any THEES
maintenance discharge.
5.10.2.3
It is also recommended under this Project that any THEES maintenance
period should be shortened as far as possible and should be avoided in the
algae blooming season (i.e. January to May).
5.10.3.1
Marine water quality monitoring
is recommended in Tolo Harbour for THEES maintenance during both construction
and operational phases of this Project. Marine water quality parameters such as
SS, BOD, E.coli, chlorophyll-a,
TIN, UIA and NH3-N should be monitored. A seven-month baseline
monitoring programme covering the period from June to December (outside the
algae blooming season) is proposed at a frequency of twice per month to establish
the baseline water quality conditions at selected monitoring points. In case of
THEES maintenance during the construction and operational phases of this
Project, marine water quality in Tolo Harbour should be monitored at a
frequency of 3 times per week throughout the maintenance period until the
baseline water quality is restored or at least 1 month after termination of the
effluent bypass (whichever is longer).
5.10.3.2
The monitoring programme for
THEES maintenance during the construction and operational phases of this
Project as discussed above shall continue in the first 3 years after
commissioning of this Project. After 3 years of post-Project commissioning
period, a review shall be conducted by DSD to determine whether such monitoring
shall be continued. The review results shall be submitted to EPD, AFCD, WSD and
other relevant parties. Any amendment on the monitoring programme shall be
agreed by EPD, AFCD and WSD. Details of the monitoring programme and an event
and action plan for the THEES maintenance are provided in the standalone
EM&A Manual.
5.10.4.1
This Project would optimize
the existing THEES maintenance works to improve the water quality during the
THEES maintenance. No unacceptable residual water quality impacts are
anticipated from the Project.
5.11.1.1
Emergency discharge due to
emergency situations (e.g. power / treatment failure) may occur at the existing
STSTW and future CSTW. This Project
would only involve relocation of the existing STSTW into caverns and would not
change the flow, load and location of the emergency discharge as well as the
chance of occurrence for the emergency discharge. Scenario 7 assumed that an
emergency discharge from the STSTW would occur for a period of 6 hours in case
of power or plant failure. In case
of power failure, the emergency discharge from STSTW would still be subject to
settlement / sedimentation prior to the discharge and thus would represent
primarily treated sewage effluent. However, the quality of the emergency
discharge is assumed under this scenario to be similar to that of the crude
sewage for conservative assessment.
5.11.1.2
The model results for Scenario
7 are presented in Appendix
5.05 for DO, UIA, NH3-N, TIN, SS, BOD, E.coli,
chlorophyll-a and sedimentation rate. The water quality parameters presented in
Appendix 5.05
are also described in Section 5.9.1.2 above. Contour plots (e.g. in terms of annual
mean value or maximum level) are not considered an effective means to
illustrate the potential impact of this short-term discharge and therefore not
included for this scenario.
Dissolved Oxygen
5.11.1.3
Full compliance of DO was
predicted at all WSRs under Scenario 7 except for the mangrove site at Tolo
Pond (M1) where the minimum surface and middle DO was only 1.5 and 3.5 mg/L
respectively, as compared to the WQO of no less than 4 mg/L (see Appendix 5.05).
However, under the normal operation of the Project (Scenario 5), the background
minimum DO level at M1 was also 1.5 and 3.5 mg/L for surface and middle value
respectively. The short-term emergency discharge would contribute zero impact upon the minimum DO predicted
at this mangrove site. No adverse DO impact would be induced by the emergency
discharge.
Unionized Ammonia / Total Inorganic Nitrogen / Ammonia Nitrogen
5.11.1.4
The short-term discharge under
Scenario 7 would cause zero or negligible impact upon the predicted mean UIA
and TIN level at all identified WSRs as compared to the normal plant operation
under Scenario 5. There is no WQO available for UIA and TIN in the marine water
of Tolo Harbour. In terms of the
ammonia nitrogen (NH3-N) level, the WSD
has specified a target objective for their flushing water intakes. The
model results showed that the maximum NH3-N level predicted at the
WSD flushing water intake at Sha Tin (W1) and Tai Po (W2) (under Scenario 7
with emergency discharge) was 0.464 and 0.201 mg/L
respectively, which complied well with the target objective of 1 mg/L.
Suspended Solids
5.11.1.5
The short-term discharge under
Scenario 7 would cause zero or negligible impact upon the predicted mean SS
level at all identified WSRs as compared to the normal plant operation under
Scenario 5 as shown in Appendix
5.05. There is no WQO available for SS in the marine water of Tolo
Harbour. The
WSD has however specified a target SS
objective for their flushing water intakes. The maximum SS level predicted at the WSD flushing water intake at
Sha Tin (W1) under the emergency discharge event (Scenario 7) was 10.3 mg/L, which is slightly above the WSD¡¦s target
objective of no more than 10 mg/L. However, under the normal operation
of the Project (Scenario 5), the maximum SS level at W1 of 10.2 mg/L is already
considered high as compared to the SS objective. The
emergency discharge would induce only a 0.1 mg/L or negligible SS increase at
this intake point. Full compliance with the SS
objective would be achieved at the WSD flushing water intake at Tai Po (W2)
under the emergency discharge event (Scenario 7).
Biochemical Oxygen Demand
5.11.1.6
The short-term discharge under
Scenario 7 would cause zero or negligible impact upon the predicted BOD level
in Tolo Harbour. There is no WQO available for BOD in the marine water of Tolo
Harbour. The WSD has however specified a target BOD objective for their flushing water intakes. The maximum BOD level predicted at W1 and W2 was 9.1 and 8.7
mg/L respectively under the emergency discharge event (Scenario 7), which complied
with the WSD¡¦s target objective of 10 mg/L (see Appendix 5.05). No adverse BOD impact is predicted in Tolo Harbour.
E. coli
5.11.1.7
The short-term discharge under
Scenario 7 would cause only a minor increase in the geometric mean E. coli
levels in Tolo Harbour and Shing Mun River. The geometric mean E. coli
levels predicted in most areas of Tolo Harbour and Channel WCZ including all
the FCZs are still well below the WQO of 610 no./100mL for secondary contact
recreation subzone and FCZ. The
geometric mean E. coli levels in the outer main channel of Shing Mun
River (which are closest to the emergency submarine outfall of STSTW / CSTW)
also complied well with the WQO of 610 no./100mL. Also, the emergency
discharges (Scenario 7) would not cause any obvious change in the annual
geometric mean E. coli levels in the Shing Mun River, as compared to
Scenario 5 (without emergency discharge). The geometric mean E. coli
level predicted at Lung Mei Beach (B1) was predicted to be less than 10
no./100mL, which also complied with the beach WQO of 180 no./100mL (see Appendix 5.05).
The short-term discharge of primarily treated sewage would however inevitably
induce a significant E. coli elevation at the WSR points close to the
discharge point. The maximum E.coli level predicted at the WSD flushing
water intake at Sha Tin (W1) would reach 27,020 no./100mL under the emergency
situation, as compared to the WSD¡¦s target limit of 20,000 no./100mL. The
maximum value predicted at the WSD flushing water intake at Tai Po (W2) was
below 1,100 no./100mL, which is well below the WSD¡¦s target objective of 20,000
no./100mL. It is however believed that WSD would provide necessary treatment
including disinfection for the seawater extracted from the flushing water
intakes and hence the potential health / environmental implications to the end
users of these flushing waters would be minimized.
Sedimentation
5.11.1.8
The short-term discharge under
Scenario 7 would cause negligible impact upon the maximum sedimentation rates
in Tolo Harbour as shown in Appendix
5.05. The maximum sedimentation levels predicted in Tolo Harbour including
all the coral sites are still less than 100 g/m2/day under Scenario
7, and fully complied with the sedimentation criterion. No adverse sedimentation impacts would
be caused by the emergency discharge.
Chlorophyll-a
5.11.1.9
The short-term discharge under
Scenario 7 would cause only a minor impact upon the maximum chlorophyll-a levels
in Tolo Harbour as shown in Appendix
5.05. In comparison with the normal situation
(under Scenario 5), the emergency discharge (under Scenario 7) would cause a chlorophyll-a
increase at 3 WSR points, namely the coral site at Tai Po Industrial Estate
(CR1), coral site at Whitehead Peninsula (CR16)
and the mangrove site at Tolo Pond (M1) respectively. The emergency discharge
would increase the maximum
chlorophyll-a predicted at CR1, CR6 and M1 by only 1 - 4 µg/L
respectively as compared to the normal level (under Scenario 5) of 17 - 58
µg/L. The chlorophyll-a
level predicted in all the remaining WSRs including the FCZs and sensitive
fisheries resources are found to be not affected by the emergency discharge.
Time Series Results at Selected WSRs
5.11.1.10
In order to identify the worst
case scenarios for the emergency discharge, four separate model runs have been
conducted to simulate the impacts for four temporary discharge periods centred
at namely neap tide high water, neap tide low water, spring tide mid-flood and
spring tide mid-ebb respectively under both wet and dry seasons. The impacts under different discharge
scenarios were reviewed to identify the worst discharge situations in both dry
and wet seasons, which would occur in spring tide mid-ebb and neap tide low
water respectively. The time for recovery under the worst discharge situations
at selected WSRs are presented as time series plots in Appendix 5.04d
and Appendix 5.04e.
Selected WSRs include WSD flushing water intakes at Sha Tin (W1) and Tai Po
(W2), coral communities at Sha Tin Hoi North (CR16) and Sha Tin Hoi South
(CR17), mangrove site at Tolo Pond (M1), fish culture zones and sensitive
fisheries resources (F1, F2, F3, F4 and TM4, refer to Sections
5.9.1.13 and 5.10.1.4 above), beach at
Lung Mei (B1) and EPD marine water quality monitoring station (TM6) as shown in
Figure No. 60334056/EIA/5.03. The time series plots for W1, W2, CR16,
CR17, F1, F2, F3, F4, B1, TM4 and TM6 are presented for key parameters of
concern including TIN, SS, chlorophyll-a and E. coli to
illustrate the spatial changes of pollution elevations at WSRs both close to
and further away from the emergency discharge point. The time series plots for W1 and W2 are
also presented for BOD to compare with the WSD target objective for BOD. As a relatively low DO level was only
predicted at M1, the time series plot for DO was only presented for M1.
5.11.1.11
As shown in the time series plots,
the chlorophyll-a levels at all selected WSRs are not sensitive to the
emergency discharge. The model
results showed that the discharge would not induce any obvious elevation of
chlorophyll-a at all the selected WSR points.
5.11.1.12
Elevation of TIN, SS and E.
coli was however observed at only three WSR points close to the emergency
discharge, namely W1, CR16 and CR 17 respectively. Some elevation of TIN, SS
and E. coli was observed at W1, CR16 and CR17 right after the emergency
discharge. The TIN and SS levels at
W1, CR16 and CR17, however, would be recovered to the baseline normal condition
within about 2 weeks and a few days after termination of the emergency
discharge for dry and wet seasons respectively. For the E. coli level at W1, C16
and C17, the background normal condition would be recovered within a few days
after termination of the emergency discharge under both dry and wet seasons.
The TIN, SS and E. coli levels at the distant WSRs (namely W2, F1, F2,
F3, F4, B1, TM4 and TM6) is found not to be elevated during or after the
emergency discharge event.
5.11.1.13
The time series plots also
showed the BOD level at W1 and W2 and the DO level at M1 would not be
significantly changed during and after the emergency discharge period.
5.11.2.1
Emergency discharges from the
Project would be the consequence of complete pump failure, interruption of the
electrical power supply or failure of treatment units. Dual power supply or
ring main supply from CLP should be provided to prevent the occurrence of power
failure. In addition, standby facilities for the main treatment units and
standby equipment parts / accessories should also be provided in order to
minimize the chance of emergency discharge. CLP should be consulted in order to
ascertain the power supply for normal plant operation within the caverns. It is recommended that government
departments including EPD, WSD and AFCD as well as the key stakeholders for
mariculture and
fisheries in Tolo Harbour should be informed as soon as
possible in case of any emergency discharge so that
appropriate actions can be taken. In view of the potential E. coli
elevation at the WSD flushing water intake at Sha Tin (W1), WSD may also
consider, should it appear necessary, to shut down the Sha Tin seawater pumping
station for a short period of time in case of emergency discharge in order to
minimize any adverse impacts.
5.11.2.2
To provide a mechanism to
minimise the impact of emergency discharges and facilitate subsequent
management of any emergency, a contingency plan has been formulated to set out
the emergency response procedure and actions to be followed in case of
equipment or sewage treatment works failure. The existing contingency plan is
attached in Appendix
5.07. The plant operators
of CSTW should carry out necessary follow-up actions according to the
procedures of this existing contingency plan to minimize any impact on the
identified WSRs due to emergency bypass.
5.11.3.1
A contingency plan has been
formulated for the existing STSTW to set out the emergency response procedure
and actions to be followed in case of equipment or sewage treatment works
failure. The plant operators of CSTW should carry out necessary follow-up
actions according to the procedures of this existing contingency plan to
minimize any impact on the identified WSRs due to emergency bypass.
5.11.3.2
Marine water quality monitoring
is also recommended in Tolo Harbour for emergency discharge during operational
phase of this Project. Marine water quality parameters such as SS, BOD, E.coli, chlorophyll-a, TIN, UIA and NH3-N should be
monitored. A one-year baseline monitoring programme covering both dry and wet seasons
is proposed at a frequency of twice per month to establish the baseline water
quality conditions at selected monitoring points. In case of emergency
discharge during the operational phase of this Project, marine water quality in
Tolo Harbour should be monitored daily throughout the emergency discharge
period until the baseline water quality is restored or at least 2 weeks after
termination of the discharge (whichever is longer).
5.11.3.3
The monitoring programme for
emergency discharge during the operational phase of this Project as discussed
above shall continue in the first 3 years after commissioning of this Project.
After 3 years of post-Project commission period, a review shall be conducted by
DSD to determine whether such monitoring shall be continued. The review results
shall be submitted to EPD, AFCD, WSD and other relevant parties. Any amendment
on the monitoring programme shall be agreed by EPD, AFCD and WSD. Details of the monitoring programme and an event and
action plan for the emergency discharge are provided in the standalone EM&A
Manual.
5.11.4.1
No unacceptable residual water
quality impacts are anticipated from the emergency discharge with the above
mitigation measures implemented.
5.12.1.1
During the operational phase,
sludge from the CSTW will be dewatered by the dewatering facilities at the
CSTW. Wastewater from the dewatering process will be fed back into the STSTW
for treatment. There is no discharge of wastewater from the dewatering process.
No adverse water quality impact associated with the wastewater from sludge
treatment would be expected.
5.12.2.1
No adverse water quality impact
is identified from the sludge treatment process. Mitigation measures specific to the
sludge treatment is considered not necessary.
5.12.3.1
No adverse water quality impact
is identified from the sludge treatment process. Water quality monitoring specific to the
sludge treatment is considered not necessary.
5.12.4.1
No unacceptable residual water
quality impact would arise from the sludge treatment process.
5.13.1.1
Other potential source of
impact on water quality during the operational phase would be non-point source
surface runoff from the open paved areas including the access road and main and
secondary portals of the cavern development. Based on the paved area of
approximately 0.035 km2 and a runoff coefficient of 1, the total
peak runoff generated from the Project sites would be in the order of about
7,400 m3 per hour under a 10-year-return-period rainstorm and design
duration of 5 minutes according to the Stormwater Drainage Manual of the DSD.
The surface runoff may contain small amount of oil and grit that may cause
water quality impacts to the nearby receiving inland waters. However, impacts
upon water quality will be minimal provided that a proper drainage system will
be provided to receive surface run-off at the planning and design stages. With
proper implementation of recommended mitigation measures and best management
practices described in Section 5.13.2, adverse
impact associated with the discharge of runoff is not anticipated.
5.13.2.1
The design of the operational
stage mitigation measures for the Project shall take into account the
guidelines published in ProPECC PN 5/93 ¡§Drainage Plans subject to Comment by
the EPD¡¨.
5.13.2.2
Best Management Practices
(BMPs) to reduce storm water and non-point source pollution are also proposed
as follows:
Design Measures
¡P
Exposed
surface shall be avoided within the road and portal sites to minimize soil
erosion. The access road and the
portal areas shall be either hard paved or covered by landscaping area where
appropriate.
¡P
The streams near the Project site will be
retained to maintain the original flow path. The drainage system
will be designed to avoid flooding.
¡P
Green areas / planting etc. should be introduced
alongside the access road and within the portal areas, as far as possible, to
minimize runoff pollution.
Devices/ Facilities to Control Pollution
5.13.2.3
In addition to the above, the
following devices/ facilities should be incorporated into the design:
¡P
Screening
facilities such as standard gully grating and trash grille, with spacing which
is capable of screening off large substances such as fallen leaves and rubbish
should be provided at the inlet of drainage system.
¡P
Road gullies
with standard design and silt traps should be provided to remove particles
present in stormwater runoff, where appropriate.
Administrative Measures
5.13.2.4
Good management measures such
as regular cleaning and sweeping of road surface/ open areas are suggested. The
road surface/ open area cleaning should also be carried out prior to occurrence
rainstorm.
5.13.2.5
Manholes, as well as stormwater
gullies, ditches provided at the Project site should be regularly inspected and
cleaned (e.g. monthly). Additional
inspection and cleansing should be carried out before forecast heavy rainfall.
5.13.3.1
No adverse water quality
impacts are anticipated from the non-point source pollution with the above
mitigation measures implemented.
Water quality monitoring specific to the non-point source pollution is
not necessary
5.13.4.1
No unacceptable residual water
quality impacts are anticipated from the non-point source pollution with the
above mitigation measures implemented.
Land-based Construction
5.14.1.1
Minor water quality impact
would be associated with land-based construction. Impacts may result from the
surface runoff, accidental spillage, sewage from on-site construction workers and groundwater infiltration. Impacts could be controlled to comply
with the WPCO standards by implementing the recommended mitigation measures.
THEES Connection Works
5.14.1.2
Both the existing TPSTW and
existing STSTW are secondary treatment plants with disinfection process. Under
the normal operation of the THEES, the TPEPS would pump the secondarily treated
and disinfected effluent of TPSTW via a rising main and a submarine pipeline to
the STEPS. The STEPS would receive the secondarily treated and disinfected
effluent from both TPSTW and STSTW for combined discharge to the KTN in the
Victoria Harbour WCZ.
5.14.1.3
In order to maintain the
current arrangement in discharging effluent to KTN through THEES tunnel,
provision of a dry construction zone within the THEES tunnel to allow
connection to the CSTW would be essential for the Project. The necessary
construction activities for the THEES connection works would include
pre-inspection of the THEES tunnel, modification of the existing THEES inlet
chamber and strengthening works to the existing THEES tunnel. During the
connection works, the THEES Tunnel needs to be temporarily suspended from its
normal operation with effluent bypasses into the Tolo Harbour.
5.14.1.4
Under the existing practice,
regular inspection and repair of the THEES would be carried out when necessary
to maintain proper functioning and integrity of the THEES. During each THEES
maintenance event, secondarily treated and disinfected effluent from TPSTW and
STSTW would be temporarily discharged to the Tolo Harbour to provide a dry zone
within the THEES tunnel for a maximum duration of 4 weeks. To avoid cumulative
water quality impact to Tolo Harbour, the necessary THEES connection works
required for this Project will be split into smaller sections and each section will be arranged to be
undertaken within the regular THEES maintenance windows for a duration not
longer than 4 weeks each outside the algae blooming season (January to May) and the frequency of THEES maintenance will be no more than once per
year during the construction phase of the Project. Therefore, no additional cumulative
water quality effect on the Tolo Harbour waters would be resulted from the
proposed THEES connection works.
5.14.2.1
The Project effluent together
with the TPSTW effluent will be discharged to the Victoria Harbour under the
THEES during normal operation. It should be highlighted that the existing STSTW
already has a design flow capacity of 340,000m3 per day and this
existing design capacity as well as the existing effluent design standard of
STSTW will be retained for the CSTW.
Hence, this Project will not induce any change to the flow and loading
of THEES effluent to the Victoria Harbour.
5.14.2.2
Maintenance of the THEES tunnel is required to ensure proper functioning and integrity of the tunnel. During the
inspection or maintenance of the THEES tunnel, temporary suspension of the
normal THEES operation with effluent bypass into the Tolo Harbour is
unavoidable to provide a safe and dry zone within the THEES tunnel for the
necessary inspection / maintenance works. Since the THEES is currently in
operation, the temporary effluent bypass under normal THEES maintenance is not
induced by this Project.
5.14.2.3
Mathematical modelling was
undertaken under this EIA to study the water quality impact arising from a
4-week THEES maintenance discharge in algae blooming season (January to May) under
the ultimate development scenario.
The model results indicated that the pollution level in Tolo Harbour
would be increased during the maintenance period, but the pollution elevation
associated with the maintenance discharge would be reversible.
5.14.2.4
The current design capacity,
effluent design standards and effluent discharge points of the existing STSTW
will be retained for the CSTW. This
Project will not change the flow, load and discharge points of THEES effluents
to Victoria Harbour and Tolo Harbour. The flow, load and discharge points of
THEES would be the same with and without this Project. Thus, no adverse water
quality in both Victoria Harbour and Tolo Harbour would arise from this Project.
5.14.2.5
In order to further minimize
the water quality impact, it is recommended under this Project to schedule the
THEES maintenance outside the algae blooming season (January to May). The water quality model predicted that
the pollution elevation in Tolo Harbour and the associated water
quality recovery period would be significantly reduced
and minimized for the THEES maintenance discharge outside
algae blooming season (January to May). An event and action plan and a
water quality monitoring programme (as presented in the standalone EM&A
Manual) is also proposed for the THEES maintenance events during both
construction and operational phases to minimize the water quality impacts.
5.14.2.6
Emergency discharges from the
Project would be the consequence of pump failure, interruption of the
electrical power supply or failure of treatment units. Mitigation measures, including dual
power supply or ring main supply from CLP, standby pumps, treatment units and
equipment, would be provided to avoid the occurrence of any emergency
discharge. A contingency plan has
also been formulated to minimize the impact of emergency discharges and
facilitate subsequent management of the emergency. An event and
action plan and a water quality monitoring programme (as presented in the
standalone EM&A Manual) is also proposed for the emergency discharge events during operational phase to minimize the water quality
impacts.
<End of
Section 5>