CONTENTS
4.3 Identification of Noise
Sensitive Receivers
4.4 Environmental Legislation,
Standards and Guidelines
4.5 Construction Noise Impact
Assessment
4.6 Operational Noise Impact
Assessment
4.8 Environmental Monitoring and
Audit
TABLES
Table 4.1 Noise
Sensitive Receivers (NSRs) Identified within 300m Assessment Area
Table 4.2 Noise
Criteria for Daytime Construction Activities (Non-restricted Hours)
Table 4.3 Area
Sensitivity Ratings
Table 4.4 Acceptable
Noise Levels (ANLs)-5 for Fixed Plant Noise
Table 4.5 Noise
Criteria of Planned Fixed Noise Sources
Table 4.6 Representative
Construction NAPs
Table 4.7 Predicted
Construction Noise Levels under Unmitigated Scenario
Table 4.8 List
of Proposed Quieter PME
Table 4.9 Predicted
Construction Noise Levels under Mitigated Scenario
Table 4.10 Representative
Operational NAPs
Table 4.11 Predicted
Fixed Noise Levels
FIGURES
Figure 4.1 Noise Sensitive
Receivers within 300m Assessment Area
Figure 4.8 Representative
Operational Noise Assessment Points and Assessed Noise Segments
Figure 4.9 Roof
Canopy of Tung Chung Central Station
APPENDICES
Appendix
4.1 Photographs of the
Existing Noise Sensitive Receivers
Appendix
4.2 Tentative Construction
Programme
Appendix
4.3 Construction Plant
Inventory (Unmitigated Scenario)
Appendix
4.4 Details of Construction
Noise Assessment (Unmitigated Scenario)
Appendix
4.5 Schematic Drawing of Mitigation
Measures
Appendix
4.6 Construction Plant
Inventory (Mitigated Scenario)
Appendix
4.7 Details of Construction
Noise Assessment (Mitigated Scenario)
Appendix 4.8 Details of Fixed Noise Assessment
4.1.1.1
This section
presents the noise impact assessment of the Project, identifying the potential
noise issues during the construction and operational phases, evaluating the
potential noise impacts on the identified noise sensitive receivers (NSRs) in
the vicinity of the Project and recommending mitigation measures as necessary.
4.1.1.2
During the
construction phase, Powered Mechanical Equipment (PME) to be used for the
construction works will be the primary noise source. The major noise generating activities
will include the construction of ATCL alignment, stations, depot, pier and
berthing facilities and other associated works.
4.1.1.3
During the
operational phase, the potential noise sources of the Project may include zero
emission vehicles and, fixed plant at depot, plant room and marine facilities.
4.1.1.4 The noise impact assessment for the Project
has been conducted in accordance with the Annexes 5 and 13 of the Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM) and the
technical requirements in Section 3.4.5 of the EIA Study Brief (ESB-342/2021).
4.2.1 Environmental Legislation
4.2.1.2
Reference to
the EIAO and the relevant technical memoranda has been made for the assessment
of noise impacts. Annexes 5 and 13
of the EIAO-TM set out the criteria and guidelines for evaluating noise
impacts. Assessment procedures and
standards are set out in the following technical memoranda and Guidance Note:
¡P
Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM);
¡P
Technical
Memorandum on Noise from Construction Work in Designated Areas (DA-TM);
¡P
Technical
Memorandum on Noise from Construction Work other than Percussive Piling
(GW-TM);
¡P
Technical
Memorandum on Noise from Percussive Piling (PP-TM);
¡P
Technical
Memorandum for the Assessment of Noise from Places other than Domestic
Premises, Public Places or Construction Sites (IND-TM); and
¡P
EIAO
Guidance Note ¡V Preparation of Construction Noise Impact Assessment under the
Environmental Impact Assessment Ordinance (GN9/2010).
4.2.2
Description
of the Environment
4.2.2.1 The Project site is situated between Tung Chung town
centre and Hong Kong Port (HKP) Island.
The location of the Project is shown in Figure 1.1.
4.2.2.2 The noise sensitive receivers in the assessment area mainly comprise
residential uses and the government, institution or community uses at Tung
Chung town centre. The existing
noise climate is dominated by road traffic from North Lantau Highway, as well
as aircraft noise from aircraft landing at and departing from Hong Kong
International Airport (HKIA).
4.3.1.1
In accordance with Annex 13 of the EIAO-TM, any domestic premises including temporary
housing, school,
educational institution, hospitals, medical clinics, homes for the aged,
convalescent homes, places of worship, libraries, courts of law, performing
arts centres, auditoria, and amphitheatres are identified as NSRs.
4.3.1.2
The assessment
area for noise impact generally include areas within 300m from the boundary of
the Project and the works of the Project. NSRs within a distance of 300m from the boundary
of the Project and the works of the Project have been identified. NSRs located within
the first layer from the Project site and having openable windows for
ventilation were selected as representative NSRs for assessment. These NSRs include the existing,
committed and planned developments during both construction and operational
phases of the Project.
4.3.1.3
For identification
of NSRs within the defined assessment area, a review has been conducted based
on relevant available information including topographic maps, Outline Zoning
Plans (OZPs) (e.g. Chek Lap Kok
¡V OZP (Plan No. S/I-CLK/16) and Tung Chung Town Centre Area - OZP (Plan No. S/I-TCTC/24))
and other published plans in the vicinity of the Project site.
4.3.1.4
The
identified existing, committed and planned NSRs within the assessment area are
presented in Table 4.1 and their
locations are shown in Figure 4.1. The photographs of the existing NSRs are
shown in Appendix 4.1.
Table 4.1 Noise Sensitive Receivers (NSRs) Identified within 300m Assessment
Area
NSR ID |
Description |
Rely on Openable Windows for Ventilation
(Y/N) [1] |
Existing/ Planned |
Uses [2] |
Selected as Representative NSRs for
Assessment (Y: Yes; N: No) [3] |
|
Construction Noise |
Operational Noise |
|||||
N01 |
Seaview Crescent |
Y |
Existing |
R |
Y |
Y |
N02 |
Novotel Citygate Hong Kong |
N |
Existing |
H |
N |
N |
N03 |
Ling Liang Church E Wun Secondary School |
Y |
Existing |
E |
Y |
N |
N04 |
Tung Chung Health Centre |
N |
Existing |
M |
N |
N |
N05 |
Ching Chung Hau Po Woon Primary School |
Y |
Existing |
E |
N |
N |
N06 |
Po On Commercial Association Wan Ho Kan Primary
School |
Y |
Existing |
E |
N |
N |
N07 |
Yu Tung Court |
Y |
Existing |
R |
N |
N |
N08 |
Fu Tung Estate |
Y |
Existing |
R |
Y |
N |
N09 |
Tung Chung Crescent |
Y |
Existing |
R |
Y |
Y |
N10 |
Priests¡¦ Quarters of the Planned Visitation
Church Development [4] |
Y |
Planned |
R |
Y |
Y |
N11 |
Planned Visitation Church Development [4] |
N |
Planned |
W |
N |
N |
N12 |
The Silveri Hong Kong ¡V
MGallery |
N |
Existing |
H |
N |
N |
N13 |
Hong Kong Airlines Training Centre |
N |
Existing |
E |
N |
N |
N14 |
Regala Skycity Hotel |
N |
Existing |
H |
N |
N |
N15 |
Hong Kong SkyCity
Marriott Hotel |
N |
Existing |
H |
N |
N |
N16 |
Campus and Dormitory of the Hong Kong
International Aviation Academy |
N |
Planned |
E/R |
N |
N |
N17 |
Ling Liang Church Sau Tak Primary School |
Y |
Existing |
E |
N |
N |
N18 |
Hong Kong Federation of Education Workers Wong
Cho Bau Secondary School |
Y |
Existing |
E |
N |
N |
N19 |
Po Leung Kuk Mrs. Ma Kam Ming Cheung Fook Sien College |
Y |
Existing |
E |
N |
N |
Note:
[1] For NSRs that do not rely on openable
windows for ventilation, they are not included in the assessment.
[2] R ¡V Residential/ Domestic Premises; H ¡V
Hotel; E ¡V Educational Institution/ School; M ¡V Medical clinics; W ¡V Place of
Public Worship
[3] Only the first layer NSRs have been
selected as representative for assessment as they would be worst-affected by
the Project during the construction and operation phases.
[4] Based on the best available information
during preparation of this EIA, the planned church does not rely on openable
windows for ventilation and the tentative intake of planned visitation church
development will be early 2026.
Further review on the list of representative NSRs will be conducted
during preparation of Construction Noise Management Plan.
4.4.1
Construction Noise
Construction Noise during Non-restricted Hours
4.4.1.1
Daytime
construction noise, excluding percussive piling, between the hours 0700 ¡V 1900
on any day not being a Sunday or general holiday, which are non-restricted
hours, should be assessed in accordance with EIAO-TM. Noise standards for daytime construction
activities are summarised in Table
4.2.
Table 4.2 Noise
Criteria for Daytime Construction Activities (Non-restricted Hours)
Noise Sensitive Uses |
Noise Criteria, Leq (30 mins), dB(A) |
All domestic premises
including temporary housing accommodation |
75 |
Hotels and hostels |
75 |
Educational institutions including kindergartens,
nurseries and all others where unaided voice communication is required |
70 |
Note:
[1] The
above standards apply to uses which rely on openable window for ventilation.
[2] The
above standards shall be viewed as the maximum permissible noise levels
assessed at 1m from the external façade.
4.4.2
Operational Noise
4.4.2.1
For fixed
noise impact assessment, the Acceptable Noise Levels (ANLs) for the Noise
Sensitive Receivers (NSRs) are based on the Area Sensitivity Rating (ASR) as
defined in the Technical Memorandum for the Assessment of Noise from Places
other than Domestic Premises, Public Places or Construction Sites (IND-TM)
issued under the Noise Control Ordinance (NCO). The ASR is based on the characteristics of
the area within which the NSRs are located, such as rural, village, low-density
residential, or urban, and the degree of impact that Influencing Factors (IFs)
have on the NSRs as illustrated in Table 4.3. Industrial
areas, major roads with an annual average daily traffic flow in excess of
30,000 or the area within the boundary of the Hong Kong International Airport
(HKIA) shall be considered to be an IF.
Table 4.3 Area
Sensitivity Ratings
Types of Area Containing NSR |
Degree to which NSR is affected by IF |
||
Not Affected |
Indirectly Affected |
Directly Affected |
|
Rural Area, including country parks or village
type developments |
A |
B |
B |
Low density
residential area consisting of low-rise or isolated high-rise developments |
A |
B |
C |
Urban area |
B |
C |
C |
Area other
than those above |
B |
B |
C |
4.4.2.2
According to
the EIAO-TM, the planned fixed noise sources shall comply with 5dB(A) below the
ANLs or the prevailing background noise levels, whichever is lower. Table 4.4 shows the ANL-5
for fixed plant noise for different Area Sensitivity Ratings during different
periods.
Table 4.4 Acceptable
Noise Levels (ANLs)-5 for Fixed Plant Noise
Time Period |
ANL-5, Leq
30-min, dB(A) |
||
ASR A |
ASR B |
ASR C |
|
Day (0700 to
1900 hours) |
55 |
60 |
65 |
Evening (1900 to 2300 hours) |
|||
Nighttime (2300 to 0700
hours) |
45 |
50 |
55 |
4.4.2.3 The assessment area for the fixed noise source
impact includes area within 300 m from the boundary of the Project and the
works of the Project. In view of
the significant impact on the aviation industry due to travel restrictions and
a decimation in demand among travellers during the COVID-19 pandemic in 2020,
the Annual Average Daily Traffic (AADT) of North Lantau Highway (NLH) before
COVID-19 pandemic was referenced, which was normally over 30,000 vehicle/day.
For example, according to Annual Traffic Census 2018 and 2019, the AADT of NLH were
recorded 57,100 and 62,420 in year 2018 and 2019, respectively. In addition, with reference to the
approved EIA report on Expansion of Hong Kong International Airport (HKIA) into
a Three-Runway System (Register No.: AEIAR-185/2014), noise from NLH was
noticeable at existing NSRs (i.e. Tung Chung Town Centre) and the NLH was
considered as an IF. Therefore, NLH
is also considered as an IF for the assessment. Besides, HKIA is also considered as an
IF, which is in the vicinity of the identified representative NSRs of fixed
noise impact.
4.4.2.4 The planned land use in the vicinity of the
area is mainly for commercial or government/institutional use. The viaduct section and Tung Chung
Central Station in Tung Chung New Town are closed to residential area. The nearest representative NSRs (i.e.
Seaview Crescent and Tung Chung Crescent) are high-rise development. A site visit was carried out in Oct 2021
in Tung Chung Town Centre where the existing NSRs (i.e. Seaview Crescent and
Tung Chung Crescent) are located, the noise from NLH and aircraft approaching
and departing from HKIA were observed.
4.4.2.5
Seaview
Crescent (NAP ID: N01a and N01b) is a high density residential development
located in an area with mixed residential and commercial developments (outside
100m of Citygate). Therefore, the
type of area containing the NSR is considered as ¡§Area other than those above¡¨.
N01a and N01b are indirectly
affected by HKIA, and directly affected by NLH. The ASR of the NSR is thus classified as
¡§C¡¨ as defined in the IND-TM.
4.4.2.6
Tung Chung
Crescent (NAP ID: N09a) is a high density residential development located in an
area with mixed residential and commercial developments, and public transport
interchange. Therefore, the type of
area containing the NSR is considered as ¡§Urban area¡¨. N09a is indirectly affected by HKIA and
NLH. The ASR of the NSR is thus
classified as ¡§C¡¨ as defined in the IND-TM.
4.4.2.7
The priests¡¦ quarters
of planned visitation church development (NAP ID: N10a) is a residential
premise. The premise is located in an area with mixed residential (outside 100m
of the quarters) and commercial developments, hence, the type of area
containing the NSR is considered as ¡§Area other than those above¡¨. N10a is directly affected by NLH, but
indirectly affected by HKIA. The
ASR of the NSR is thus classified as ¡§C¡¨ as defined in the IND-TM.
4.4.2.8 Taking into account the results of the
background noise measurement, the proposed criteria for fixed noise source impact
assessment at different representative NSRs are presented in Table 4.5.
Table 4.5 Noise
Criteria of Planned Fixed Noise Sources
NSR ID |
NAP |
Description |
ASR |
ANL - 5, Leq
(30 mins), dB(A) (Day & Evening time/ Nighttime) |
Reference Prevailing Background Noise, dB(A) (Day
& Evening time/ Nighttime) [1] |
Noise Criteria, Leq (30 mins), dB(A) |
N01 |
N01a |
Seaview
Crescent Block 1 |
C |
65 /
55 |
65 /
55 [2] |
65 /
55 |
N01b |
Seaview
Crescent Block 3 |
C |
65 /
55 |
65 /
55 [2] |
65 /
55 |
|
N09 |
N09a |
Tung Chung
Crescent |
C |
65 / 55 |
66 / 62 [3] |
65 / 55 |
N10 |
N10a |
Priests¡¦
Quarters of the Planned Visitation Church Development |
C |
65 / 55 |
66 / 62 [3] |
65 / 55 |
[1] Prevailing
background noise surveys was conducted on 21 and 22 November 2021. However, the
traffic flow of NLH and the background noise was observed as exceptionally low,
due to travel restrictions and a decimation in demand among travellers during
the COVID-19 pandemic. Therefore, to properly reflect the prevailing noise
level under normal situation, prevailing background noise from other previous
approved EIA before COVID-19 pandemic is adopted in this EIA. During the
preparation of this EIA, both the traffic flow at NLH and aircraft movements
are still much lower than that in the pre-COVID-19 pandemic period. Therefore, re-measurement of prevailing
noise could be considered during the EM&A for fixed noise sources criteria
review after the COVID-19 pandemic if necessary.
[2] The
prevailing background noise is reference to Playground next to Seaview Crescent
Block 1 (Location ID: P1) of approved EIA report - Expansion of Hong Kong
International Airport into a Three-Runway System (Register No.: AEIAR-185/2014)
[3] The
prevailing background noise is reference to Podium of Tung Chung Crescent Block
7 (Location ID: P2) of approved EIA report - Expansion of Hong Kong
International Airport into a Three-Runway System (Register No.: AEIAR-185/2014)
4.5.1
Identification
of Noise Impact
4.5.1.1
The
assessment area for construction noise impact generally includes areas within
300m from the boundary of the Project Area and the works of
the Project. The construction works
area and 300m assessment area are shown in Figure 4.2 to Figure 4.7.
4.5.1.2
Construction
noise assessment points (NAPs) have been assigned for the representative NSRs which
are closest to the construction activities and are summarised in Table 4.6. The construction NAPs locations are shown
in Figure 4.2 to Figure 4.7.
Table 4.6 Representative
Construction NAPs
NSR ID |
NAP ID |
Location/ Description |
No. of Storey |
Distance from the site boundary, m |
Uses [1] |
Noise Criteria, Leq (30 mins), dB(A) |
N01 |
N01a |
Seaview Crescent Block 1 |
49 |
183 |
R |
75 |
N01b |
Seaview
Crescent Block 3 |
49 |
185 |
R |
75 |
|
N03 |
N03a |
Ling
Liang Church E Wun Secondary School |
7 |
190 |
E |
70 |
N08 |
N08a |
Fu
Tung Estate Tung Ma House |
28 |
125 |
R |
75 |
N09 |
N09a |
Tung
Chung Crescent Block 5 (Point 1) |
34 |
165 |
R |
75 |
N09b |
Tung Chung
Crescent Block 3 |
31 |
163 |
R |
75 |
|
N09c |
Tung
Chung Crescent Block 5 (Point 2) |
34 |
183 |
R |
75 |
|
N10[2] |
N10a |
Priests¡¦
Quarters of the Planned Visitation Church Development |
3 |
1 |
R |
75 |
Note:
[1] R
¡V Residential/ Domestic Premises; E ¡V
Educational Institution/ School.
[2] The
tentative intake of planned visitation church development will be early
2026. However, construction noise
impact assessment before the intake date was conducted, in case there is a
mis-match of the programme.
4.5.1.3
Potential
source of noise impact arising from the construction of the Project would be
the use of PME for various construction activities. As broadly indicated in the construction
programme in Appendix 4.2, the construction of the ATCL Project would
be tentatively commence in Q4 2025 to Q1 2028, for commissioning in July 2028. Major construction works of the Project
include:
ATCL
¡P
Construction
of about 5km long road with approximately 2,660m at grade section, 880m land
viaduct and 230m marine viaduct and a provision spur line of an approximate
980m long connecting the planned Aviation Academy for future extension;
¡P
Construction
of 4 at-grade and 1 elevated ATCL stations;
¡P
Construction
of a depot; and
¡P
Realignment/Reprovision of affected facilities and construction of
ancillary facilities such as walkways, footbridges and plant room(s);
Marine
Facilities
¡P
Construction
of a pier and berthing facilities with about 73 berths;
¡P
Construction
of ancillary facilities including floating platforms, gangs, wave attenuator,
guide piles, etc; and
¡P
Maintenance
dredging for the marine facilities.
4.5.2
Assessment
Methodology
4.5.2.1
The
assessment of noise impacts from the construction (excluding percussive piling)
of the Project has been based on the methodology given in Annex 13 of the EIAO-TM. The typical approach is summarised as
follows:
¡P
Formulate
construction programme and work sequences;
¡P
Identify
representative construction NSR that may be affected by the construction of the
Project;
¡P
Establish
the construction plant inventory;
¡P
Assign
Sound Power Level (SWL) for each piece of PME based on the GW-TM and the list
of Sound Power Level of other commonly used PME;
¡P
Calculate
the correction factors based on the distance between the NSR and the notional
noise source positions at different construction works areas;
¡P
Apply
noise corrections in the calculations for distance, operation time, screening
and façade correction, if any;
¡P
Predict
the construction noise levels at NSR and compare against the noise criteria (Table 4.7); and
¡P
Determine
mitigation measures, as necessary, and assess any residual impacts.
4.5.2.2 Groups of PME have been assigned to various construction activities of
the ATCL Project. The construction
plant inventory will be subject to change by the Contractor in future. However, the proposed construction plant
inventory in Appendix 4.3 is considered technically feasible and confirmed by the Project
engineer as workable, and would represent a realistic worst-case scenario for assessment purposes. It is assumed for
the assessment that construction activities for the Project will be undertaken during the daytime working hours of 0700 to 1900 hours on any day not being a
Sunday or public holiday. No
percussive piling will be conducted during the construction and confirmed by
the Project engineer. Although part
of the works location falls within designated area, based on the current
construction programme, no works will be required during restricted hours as
defined under the NCO. In case of
any construction activities during restricted hours, the contractor shall be responsibility
to ensure compliance with the NCO and the relevant TMs. The contractor will be required to
submit Construction Noise Permit (CNP) application to the Noise Control
Authority and abide by any conditions stated in the CNP, should one be issued. Despite any descriptions made in this
EIA Report, there is no guarantee that a CNP will be issued for the
construction of this Project.
4.5.2.3
In order to provide a realistic assessment, the percentages on
time of powered mechanical equipment (PME) operating in construction work areas
have also been considered when calculating the cumulative Sound Power Levels
(SWL) for the construction activities.
Such percentage on time was also confirmed by the Project engineer as
workable. Construction noise levels
at the NSRs have been assessed on a monthly basis with respect to the
individual noise levels induced by the construction work tasks. The predicted construction noise level (CNL)
at the NSR is calculated based on the equation defined below:
CNL = SWL + CD + Cs + CT + CF
Where,
SWL =
Sound power level of PME, dB(A);
CD = Distance correction, dB(A);
Cs = Screening correction, dB(A);
CT = Percentage on time correction, dB(A);
CF =
Façade correction, dB(A).
4.5.2.4
The
construction works will be separated into 16 construction work areas, only the construction
works areas A to F are located within the 300m from the construction NAPs. Thus, the construction noise impact from construction
works areas A to F have been assessed.
4.5.3
Prediction
and Evaluation of Construction Noise Impact (Unmitigated Scenario)
4.5.3.1
The unmitigated construction noise impacts at the identified NSRs
have been predicted accordingly. Details of unmitigated construction
noise assessment are presented in Appendix 4.4 with the
results summarized in Table
4.7.
4.5.3.2
As shown in Table
4.7, the construction
noise levels at the identified representative construction NAPs would range from
57 to 97dB(A) under the unmitigated scenario. The predicted construction noise levels
would exceed the relevant noise criteria. Noise mitigation measures are therefore
required to alleviate the construction noise impact on the affected NSRs.
Table 4.7 Predicted
Construction Noise Levels under Unmitigated Scenario
NSR ID |
NAP ID |
Location / Description |
Uses [1] |
Predicted Construction Noise
Level, Unmitigated, |
N01 |
N01a |
Seaview
Crescent Block 1 |
R |
60 -
78 |
N01b |
Seaview Crescent Block 3 |
R |
61 - 78 |
|
N03 |
N03a |
Ling Liang Church E Wun
Secondary School |
E |
57 - 75 |
N08 |
N08a |
Fu Tung Estate Tung Ma House |
R |
59 - 78 |
N09 |
N09a |
Tung Chung Crescent Block 5
(Point 1) |
R |
62 - 78 |
N09b |
Tung Chung Crescent Block 3 |
R |
61 - 78 |
|
N09c |
Tung Chung Crescent Block 5
(Point 2) |
R |
61 ¡V 76 |
|
N10[2] |
N10a |
Priests¡¦ Quarters of the Planned
Visitation Church Development |
R |
68 - 97 |
Note:
[1] R ¡V Residential/
Domestic Premises; E ¡V Educational Institution/ School.
[2] The tentative
intake of planned visitation church development will be early 2026. However, construction noise impact
assessment before the intake date was conducted, in case there is a mis-match
of the programme.
4.5.4
Prediction
and Evaluation of Construction Noise Impact (Mitigated Scenario)
4.5.4.1
In order to alleviate the construction noise impacts at the
affected NSR, implementation of noise mitigation measures such as the use of quieter
construction methods, quieter PME, noise barriers, noise enclosure and noise
insulating fabric are recommended. The
plant inventory and noise mitigation measures have been confirmed by Project engineer as workable. The plant inventory is presented in Appendix 4.6 and the
recommended measures to be applied are presented below:
Quieter Construction Methods
4.5.4.2
Quieter construction equipment /
methods have been considered and assumed to be applied in all construction
works areas, and listed as below:
¡P
Hydraulic concrete
crusher will be used for rock breaking activities during site establishment,
instead of traditional hydraulic breaker.
The operation principle of hydraulic breaker is by percussive striking
actions of its chisels, while hydraulic concrete crusher is by clamping action.
Thus, less noise would be generated from the hydraulic concrete crusher. According to EPD website, the sound
pressure level at 7m from the equipment is 67-69 dB(A).
¡P
Non-explosive
chemical expansion agent will be used for concrete breaking activities during
site establishment, instead of traditional hydraulic breaker. The agent is a slow-acting chemical
compound and expand, and cracks the structure. Significant noise, ground vibration, fly
rock, gas, dust or any other environmental pollution would not be generated
during the process.
¡P Self-compacting concrete will be used for concreting works, instead of traditional vibratory poker. Self-compacting concrete is highly fluid and non-segregate, which can spread into place, fill the formwork, and encapsulate the steel bar reinforcement without using vibratory poker or other PME.
¡P
Silent piling by Press-in
Method (Press-in piling) will be used for sheet piling works, instead of
traditional massive augering and piling machines
(e.g.: Piling, vibrating hammer). Press-in method is a pile penetration
method which accurately installs pre-formed piles through static loading
piling. The construction work can
also be completed in shorter duration so that the noise impact to nearby NSRs
can also be further alleviated. According to the EPD website, the sound
pressure level at 7 meters from the equipment is 70 dB(A).
Use of Quieter PME
4.5.4.3
Quieter PME has been assumed to be applied. The use of quieter PME is specified for
the list of equipment detailed in Table 4.8 below.
Table 4.8 List of
Proposed Quieter PME
PME |
Reference |
Sound Power Level, dB(A) |
Crane, mobile |
QPME: EPD-10143 |
100 [1] |
Generator |
QPME: EPD-12349 |
90 [1] |
Excavator, wheeled/tracked |
QPME: EPD-12254 |
97 [1] |
Air Compressor |
QPME: EPD-11726 |
100 [1] |
Concrete Lorry Mixer |
Ref: AEIAR-173/2013 |
96 [2] |
Lorry (24t) |
Ref: AEIAR-173/2013 |
96 [2] |
Concrete pump |
Ref: AEIAR-173/2013 |
106 [2] |
Asphalt Paver |
Ref: AEIAR-173/2013 |
101 [2] |
Roller, vibratory |
Ref: AEIAR-173/2013 |
101 [2] |
Hydraulic Concrete Crusher |
EPD |
94 [3] |
Press-in piling |
EPD |
95 [3] |
Note:
[1] The SWL is prescribed in Quality Powered
Mechanical Equipment (QPME) in EPD website.
[2] The SWL of the PME is referenced to the EIA
report of the Tseung Kwan O ¡V Lam Tin Tunnel and Associated Works (Register No.
AEIAR-173/2013).
[3] The SWL is converted from SPL by distance
attenuation in point source, and the SPL at 7m from the equipment is referenced
to EPD website:
https://www.epd.gov.hk/epd/misc/construction_noise/contents/index.php/en/home2/quieter-construction-methods.html.
Use of Noise Barrier, Noise Enclosure and Noise Insulating Fabric
4.5.4.4
Cantilevered noise barriers with a surface density of at least
10kg/m2 have been proposed to screen noise from movable and
stationary plant to NSRs. Noise
barrier shall be placed as close to the PME as possible and a location
intercepting the line of sight between NSRs and PME. With reference to EIAO Guidance Note
No.9/2010, noise reduction of 5dB(A) and 10dB(A) can be achieved by noise
barriers for movable and stationary plant respectively. The schematic drawing of noise barrier and
section drawing are shown in Appendix 4.5.
4.5.4.5
Noise enclosures with covers at top and three sides have been proposed
to screen noise from generally static noisy plant such as air compressors. The open side shall be faced away to the
NSRs. The surface density shall be
of at least 10kg/m2 with internal sound absorptive material. With reference to EIAO Guidance Note
No.9/2010, it is capable of a 15dB(A) reduction of noise. The schematic drawing of enclosure is
shown in Appendix 4.5.
4.5.4.6
Noise insulating fabric can also be adopted for certain PME (e.g.
Piling, large diameter bored, reverse circulation drill). According to the approved West Island
Line EIA Report (Register No.: AEIAR-153/2008), a noise reduction of 10dB(A)
can be achieved for the PME lapped with the noise insulating fabric. The fabric should be lapped such that
there would be no openings or gaps on the joints. Subject to the work arrangement in
construction stage, the Contractor may propose other form of mitigation
measures to achieve the full compliance.
Assessment Results
4.5.4.7
With the implementation of quieter construction methods, QPME,
noise barriers, noise enclosures and noise insulating fabric, the predicted
construction noise levels at representative construction NSRs have been
predicted and are summarised in Table 4.9 below. Detailed results are presented in Appendix 4.7.
Table 4.9 Predicted
Construction Noise Levels under Mitigated Scenario
NSR ID |
NAP ID |
Location / Description |
Uses [1] |
Predicted Construction Noise
Level, Mitigated, Leq (30mins),
dB(A) |
N01 |
N01a |
Seaview
Crescent Block 1 |
R |
53 - 63 |
N01b |
Seaview Crescent Block 3 |
R |
54 - 62 |
|
N03 |
N03a |
Ling Liang Church E Wun
Secondary School |
E |
50 - 57 |
N08 |
N08a |
Fu Tung Estate Tung Ma House |
R |
52 - 59 |
N09 |
N09a |
Tung Chung Crescent Block 5
(Point 1) |
R |
55 - 62 |
N09b |
Tung Chung Crescent Block 3 |
R |
54 - 60 |
|
N09c |
Tung Chung Crescent Block 5
(Point 2) |
R |
54 - 59 |
|
N10[2] |
N10a |
Priests¡¦ Quarters of the Planned
Visitation Church Development |
R |
61 - 75 |
Note:
[1] R ¡V Residential/ Domestic Premises; E ¡V
Educational Institution/ School.
[2] The tentative intake of planned visitation
church development will be early 2026.
However, construction noise impact assessment before the intake date was
conducted, in case there is a mis-match of the programme.
4.5.4.8 With the implementation of quieter construction methods, quieter plant, appropriate temporary noise barriers, noise insulating fabric and noise enclosure, the predicted construction noise level would comply with the relevant noise criteria, adverse construction noise impact would not be anticipated.
Good Site Practices
4.5.4.9
In addition to the mitigation measures listed above, there are
also some good site practices that can further reduce the noise levels at
NSRs. However, they are
non-quantifiable and thus not included in the assessment. These include:
¡P
Only
well-maintained plant should be operated on-site and plants should be serviced
regularly during the construction period;
¡P
Mobile
plant, if any, should be sited as far from NSRs as possible;
¡P
Plant
known to emit noise strongly in one direction should, wherever possible, be
properly orientated so that the noise is directed away from the nearby NSRs;
¡P
Use of
site hoarding as a noise barrier to screen noise at low level NSRs;
¡P
Machines
and plant that may be used intermittently should be shut down between works
periods or should be throttled down to a minimum; and
¡P
Any
material stockpiles and other structures should be effectively utilised,
wherever practicable, to screen the noise from on-site construction activities.
4.5.4.10 With the implementation of the abovementioned further mitigation
measures, no adverse construction noise impact is expected. The abovementioned
mitigation measures were proposed based on the current project planning and
design. A Construction Noise
Management Plan (CNMP) with reference to Section 8 and Annex 21 of the EIAO-TM, will be
prepared to submit during pre-tender stage, if any, and before commencement of construction
works, so that both the verification of the inventory of noise sources, and the
assessment of the effectiveness and practicality of all identified measures for
mitigating the construction noise impact of the Project, will be performed
during the design, tendering and implementation stage of the construction works.
To further mitigate construction
noise impacts, additional quieter construction equipment / methods, would be
adopted in the CNMP as far as practicable.
The use of quieter construction equipment / methods, if necessary, will
be further reviewed in detailed design and construction stages, and in the
CNMP. A clear method statement of
all the recommended mitigation measures for controlling the construction noise
impacts should be formulated in the CNMP to be prepared by future Contractors,
such that all the recommended mitigation measures will be implemented and
executed properly.
4.5.5
Residual
Impacts
4.5.5.1
Construction noise impacts on the representative construction NSRs
have been assessed and comply with the daytime construction noise standards. No residual impact is anticipated during
the construction phase of the Project.
4.6.1
Identification
of Noise Impacts
4.6.1.1
The assessment area for noise impact generally includes
areas within 300m from the boundary of the Project area and the works of the
Project. The assessment area is
shown in Figure 4.1.
4.6.1.2 Operational noise assessment points (NAPs)
have been assigned for the NSRs for fixed noise impact assessment which are
closest to the fixed noise sources. The
proposed
fixed noise criteria and operational NAPs are summarised in Table
4.10. Locations
of the proposed fixed plants are shown in Figure 4.1and Figure 4.8.
4.6.1.3 The fixed noise impact from ATCL alignment
outside 300m to the representative operational NAPs are predicted as negligible
due to great advantage in distance attenuation.
Table 4.10 Representative
Operational NAPs
NSR ID |
NAP ID |
Location/ Description |
No. of Storey |
Distance from the ATCL, m |
Uses [1] |
Noise Criteria, Leq
(30 mins), dB(A) (Day & Evening time/ Nighttime) |
N01 |
N01a |
Seaview Crescent Block 1 |
49 |
195 |
R |
65 /
55 |
N01b |
Seaview
Crescent Block 3 |
49 |
197 |
R |
65 / 55 |
|
N09 |
N09a |
Tung
Chung Crescent Block 5 |
34 |
176 |
R |
65 / 55 |
N10 |
N10a |
Priests¡¦
Quarters of the Planned Visitation Church Development |
3 |
15 |
R |
65 / 55 |
Note:
[1] R ¡V Residential/ Domestic Premises.
Potential Noise Sources
4.6.1.4
For the
proposed depot and plant room, noise will be generated by operation of workshop
for vehicle maintenance, Mechanical, electrical and plumbing (MEP) systems and
building services equipment of the office.
However, the proposed depot and plant room will be located at approximately 620m and 550m
respectively from the nearest representative operational NAP (i.e. N01a). Given the large separation, significant fixed
noise sources impact due to the proposed facilities is not anticipated.
4.6.1.5
For the
marine facilities, noise will be generated by MEP system and building services
equipment of the office. However, the marine facilities will be located at 2.3km
from the nearest representative operational NAP (i.e. N01a). Given the large separation, significant fixed
noise impact due to the proposed facilities is not anticipated.
4.6.1.6
For the
proposed stations, natural ventilation will be adopted. Noise impact from
mechanical ventilation system is not expected. There are no other fixed plant at the
proposed stations.
4.6.1.7
During the
operational phase, zero emission vehicles (e.g. electric vehicle) will be used
for the ATCL. Motor noise and tyre/road
noise will be major noise contributions on the zero emission vehicles during
operation. Noise generated by zero
emission vehicles from proposed TCC station will be partially screened by roof
canopy and the roof canopy is shown in Figure 4.9. Idling,
manoeuvring, cruise, accelerating and decelerating operation mode of zero
emission vehicles have been considered as follow:
¡P
Idling: Idling
will occur only when there is a pick-up or drop-off of passengers in proposed
stations. No tyre/road noise will
be generated. Minor motor noise and
internal cooling system noise will be partially screened by the roof
canopy. The predicted noise impact
to the NSRs is minimal.
¡P
Manoeuvring: Manoeuvring
will occur only in proposed stations and moving in and out to pick-up or
drop-off location. Minor motor noise and tyre/road noise are expected. Maximum travelling of 20 kph is assumed
in manoeuvring mode.
¡P
Cruise: During
the cruise mode, the zero emission vehicle will travel at a steady speed with maximum
design speed at 40 kph. Maximum motor
and tyre/road noise is expected under this operation mode.
¡P
Acceleration: Higher
power is required for accelerating the zero emission vehicle. However, gentle acceleration
of the zero emission vehicles shall be maintained, significant noise generated during
acceleration is not anticipated. For comparison with manoeuvring mode, motor
noise may be higher but relatively quieter from tyre/road noise. Overall, the noise emission during
acceleration should be similar with noise during manoeuvring mode.
¡P
Deceleration: Power
input for the electric motor will reduce, the corresponding decrease in motor
noise and tyre/road noise are expected. Also, gentle deceleration of the zero
emission vehicles shall be maintained.
As such, grinding or rubbing brake noise is not anticipated.
Frequency and Alignment
4.6.1.8
Base on the design traffic flow confirmed by Traffic Consultant
and AAHK, the design maximum traffic flow of zero emission vehicles between
chainage CH 0.00 and CH 600.00, as shown in Figure 4.8, would be 140
vehicles per 30 minutes for two-way traffic during day and evening period (0700 ¡V 2300), while 14 vehicles
per 30 minutes for two-way traffic during nighttime
(2300 ¡V 0700).
4.6.2
Assessment
Methodology
4.6.2.1
Predicted noise
levels from the movement of zero
emission vehicles on the ATCL shall be based on standard acoustic principles, ISO 9613-2 Acoustics- Attenuation of sound
during propagation outdoors ¡V Part 2: General method of calculation and
IND-TM, and maximum permissible SWL for zero emission vehicles is calculated as
below:
Where:
Maximum
Permissible SWL = Maximum Permissible
Sound Power Level in dB(A)
SPL =
Noise criteria in dB(A)
Q =
Directivity factor (Semi-sphere = 2)
r =
Distance between noise assessment point from the centre of the segment and
noise receiver, in meters (m)
V =
Number of vehicles per 30 minutes
t =
Time duration of zero emission vehicles in the segment in second
Cfaçade =
Façade Correction in dB(A)
4.6.2.2
A positive
3dB(A) correction would be added to predicted fixed noise levels at the NSRs
due to façade effect. If the noise
exhibits any tonal, impulsive or intermittent characteristics during the
operation of the zero emission vehicles, the measured noise level should be
corrected in accordance with the recommendations given in Section 3.3 of
IND-TM.
4.6.3
Evaluation of
Fixed Noise
4.6.3.1
The fixed noise source impact assessment of the worst operation
mode representing the maximum noise emission has been conducted with respect to
the criteria set out in Annex 5 of the TM.
The maximum SWL (i.e. 100 dB(A)) of zero emission vehicles has been
predicted based on backward calculation of separation distance, time duration
and maximum traffic flow. Validity
of the operation modes have been confirmed with the Project Proponent. Also, the Project Proponent is committed
to acquire zero emission vehicles with a maximum SWL of 100 dB(A) or below, and
confirmed that which are available in the market today.
4.6.3.2
The predicted fixed noise levels at the representative operational
NAPs using the maximum permissible SWL of the zero emission
vehicle are summarized in Table
4.11. Details of calculation are presented in Appendix
4.8. The predicted noise
levels at all the representative NSRs comply with both day and evening time,
and night-time noise criteria and thus, there would be no adverse fixed noise
impact arising from the Project.
Table 4.11 Predicted
Fixed Noise Levels
NSR ID |
NAP ID |
Maximum
Permissible SWL of Zero Emission Vehicle, dB(A) |
Predicted Fixed Noise Level, Leq (30 mins), dB(A) |
|
Day & Evening time |
Night-time |
|||
N01 |
N01a |
100 |
54 |
44 |
N01b |
54 |
44 |
||
N09 |
N09a |
54 |
44 |
|
N10 |
N10a |
65 |
55 |
4.6.4
Residual Fixed
Noise Impact
4.6.4.1
With proper selection of zero emission vehicles with maximum SWL
of 100dB(A), no noise mitigation measures shall be required and no residual
impact is expected at the representative operational NSRs.
4.7.1.1
Key concurrent projects in
the vicinity of the proposed ATCL Project are identified in Section 2.9. Noise impacts
of all concurrent projects have been discussed below.
Tung Chung New Town Extension
4.7.1.2
According to the approved EIA Report for the Tung Chung New Town
Extension (TCNTE) (Register No.: AEIAR-196/2016), construction works for the
TCNTE project was commenced in 2021 and be completed in
2030. The worksites of TCNTE are
far away from the identified NSRs, the approximate distance to the nearest NSR
(i.e. Seaview Crescent) is outside 300m assessment area of the Project,
therefore, adverse cumulative construction and operation noise impact are not
anticipated.
Tung Chung Line Extension
4.7.1.3
According to the approved EIA report for the Tung Chung Line
Extension (Register No.: AEIAR-235/2022), the construction of the Tung Chung
Line Extension will commence in Q2 2023.
It is targeted to be completed in Q4 2029. Hence, there will be concurrent
construction with the ATCL.
4.7.1.4
Cumulative construction noise impact at Tung Chung Crescent is
assessed as some of the NSRs at Tung Chung Crescent (i.e. NAP N09b and N09c)
may see both the construction site of Tung Chung Line Extension and that of
ATCL. Hence, Tung Chung Crescent is considered as the most affected NSR.
4.7.1.5
In the construction noise impact assessment of this EIA (Section 4.5), the predicted maximum
construction noise levels from the Project at the most affected NSR under
mitigated scenario is 60 dB(A). The
maximum mitigated construction noise level at the nearest NSR to the site of
Tung Chung Line Extension in Tung Chung Crescent is 74 dB(A) according to the
Tung Chung Line Extension EIA report Register (No.: AEIAR-235/2022). As such, the cumulative construction
noise level is predicted as 74 dB(A), which is below the assessment criterion
of 75 dB(A). Hence, it is
considered that there would be no adverse cumulative construction impact.
4.7.1.6
Although adverse cumulative construction noise impact is not
anticipated, the cumulative construction noise impacts should be further
reviewed during the preparation of the CNMP.
4.7.1.7
Cumulative fixed noise impact at Tung Chung Crescent is assessed
as it is considered as the most affected NSR. The predicted fixed noise levels
at Tung Chung Crescent is 54 dB(A) (daytime and evening time) and 44 dB(A)
(night time). For conservative
approach, the predicted fixed noise level in Tung Chung Crescent Block 3 is
adopted in this assessment, which is 60 dB(A) for day and evening, and 53 dB(A)
for nighttime according to the Tung Chung Line
Extension EIA report Register (No.: AEIAR-235/2022).
4.7.1.8
The predicted cumulative impact at the most affected NSR is 61
dB(A) and 54 dB(A) for day and evening, and nighttime
respectively. Thus, it is
anticipated that the cumulative fixed noise impact will comply with the
relevant noise criteria.
4.7.1.9 In conclusion, adverse cumulative fixed noise impacts are not anticipated.
Planned Visitation Church Development
4.7.1.10
According to
the best available information by AAHK, the tentative construction works was
target to complete in early 2026.
The projects will be overlapped with ATCL Project from late 2025 to
early 2026. The detailed
construction programme and plant inventory for construction of planned
visitation church development are not available during preparation of this EIA
report. However, the major
construction works for the planned visitation church including site formation,
excavation and foundation works are expected to be completed before the
commencement of the construction of the Project, and only minor superstructure
and fitting-out works of the planned visitation church are expected in this
overlapped period. Furthermore, the
nearest NSRs (e.g. N09) is located from the planned visitation church development
at around 190m and the construction works of the planned visitation church is
in small scale, thus, the cumulative construction noise impact with the Project
is not anticipated. The
construction programme of the planned visitation church development
will be further reviewed during the preparation of the CNMP.
Commercial
Development-cum-Public Market in Tung Chung Area 6
4.7.1.11
The size of
the potential development is relatively small with approximate 0.6 hectare and
only includes a commercial building. The development programme has yet confirmed during the course of this EIA
study. Considering limited noise
impacts would be arisen from a small-scale commercial building development, the
cumulative construction noise impact with the Project is not anticipated.
Other Adjacent Developments
4.7.1.12
The construction works period of each concurrent project with
approximately distance to nearest NSR (i.e.: N01) is identified and shown in Table 4.12. The projects are overlapped with ATCL
Project, but there are no identified NSRs within 300m assessment area, and
hence, adverse cumulative construction and operation noise impact is not anticipated.
Table 4.12 Construction
Period of Adjacent Developments and Approximately Distance to Noise Sensitive
Receiver
Project Name |
Construction Commencement Dates |
Construction Completion Dates |
Approximately distance from site boundary
to nearest NSR |
11 SKIES |
2017 |
2023 |
~2.8km |
Airportcity
Link |
2022 |
2025 |
~2.8km |
SkyPier
Terminal Bonded Bridge |
2020 |
2023 |
~2.8km |
Commercial Developments at East Coast Support Area |
2025 |
2035 |
~ 0.6km |
Development of Airport-related Supporting Uses at HKP Island |
2021 |
2030 |
~ 2.5km |
Planned Commercial Development |
Programme not available and under planning |
~ 2.4km |
4.7.1.13
As discussed in Section 4.7.1.1
to Section 4.7.1.12, concurrent projects have been considered and adverse cumulative
construction and operational noise impacts are not anticipated.
4.8.1
Construction
Phase
4.8.1.1 The assessment has concluded that, with the
implementation of noise mitigation measures, no adverse construction noise impacts
would be anticipated during the construction phase. Details of the monitoring and auditing
programme are provided in a standalone EM&A Manual.
4.8.2
Operational
Phase
4.8.2.1
The assessment has indicated that the noise from zero emission
vehicles would be comply with the EIAO-TM noise criteria. The zero emission vehicles would meet the maximum
permissible SWL. Monitoring of fixed
noise from the zero emission vehicle during the
testing and commissioning stage prior to operation of ATCL shall be conducted
to check the compliance of the noise criteria.
4.9.1.1
The potential noise impacts associated with the Project in the
construction and operational phases have been
assessed.
4.9.1.2
The noise impacts arising from daytime construction activities for
the Project have been evaluated. No
evening or night-time construction works will be scheduled. With proper implementation of noise
mitigation measures (e.g. quieter construction methods, quieter PMEs, temporary
barrier / enclosure etc.), the predicted construction noise levels at all
representative construction NAPs will comply with the relevant construction
noise criteria. Hence, no adverse
construction noise impacts are anticipated. In addition, a CNMP will be prepared to
submit during pre-tender stage, if any, and before commencement of construction
works, so that both the verification of the inventory of noise sources, and the
assessment of the effectiveness and practicality of all identified measures for
mitigating the construction noise impact of the Project, will be performed
during the design, tendering and implementation stage of the construction
works.
4.9.1.3 Fixed noise
from depot, plant room and marine facilities are minimal to the nearest
representative NSRs due to large separation. Natural ventilation will be adopted for
proposed stations and there is no other fixed noise plant at the stations. For the fixed noise from zero emission
vehicle, with the proper selection of zero emission vehicle (i.e. maximum SWL
of 100 dB(A)), adverse fixed noise impacts from the Project are not
anticipated. Specific noise
mitigation measures in operational phase are therefore not required. However, noise commissioning test for
zero emission vehicles shall be conducted prior to operation of ATCL to check
the compliance of the noise criteria.