Contents
7.1 Environmental Legislation,
Plans, Standards, and Guidelines
7.5 Identification of Potential
Contaminated Area and Hot Spots
7.7 Selection of RBRG Land Use
Scenario and Chemical of Concern (COCs)
7.9 Evaluation of Environmental
Impacts
7.10 Mitigation of Adverse
Environmental Impact
7.11 Evaluation of Residual
Environmental Impacts
Table 7.1 Summary
of the Sub-areas within Assessment Area
Table 7.2 Summary
of Site Appraisal for Assessment Area 6
Table 7.3 Summary
of Regular Grid Sampling Locations
Table 7.4 Summary of Hot Spot Sampling Locations
Figure 7.1 Tuen Mun Bypass Project Alignment and Assessment Area
Figure 7.2 Potential
Contaminated Area
Appendix 7.1 Contamination Assessment Plan (CAP)
·
Annex 19 of
the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM),
Guidelines for Assessment of Impact On Sites of
Cultural Heritage and Other Impacts (Section
3: Potential Contaminated Land Issues), Environment Protection
Department (EPD), 2023;
·
Guidance
Manual for Use of Risk-based Remediation Goals (RBRGs) for Contaminated Land
Management (Guidance Manual), EPD, Revised in April 2023;
Guidance Manual introduces a risk-based approach to land contamination assessment and
presents instructions for comparison of soil and groundwater data to the
Risk-Based Remediation Goals (RBRGs) for 54 chemicals of concern commonly found
in Hong Kong. The RBRGs were derived to suit Hong Kong conditions and follow a
risk-based methodology for contaminated land assessment and remediation,
designed to protect the health of people who could potentially be exposed to
land impacted by chemicals under four broad post-restoration land use
categories. The RBRGs also serve as the remediation targets if remediation is
necessary.
·
Guidance
Note for Contaminated Land Assessment and Remediation (Guidance Note), EPD,
Revised in April 2023; and
Guidance Note sets out the requirements for proper assessment and management of
potentially contaminated sites such as oil installations (e.g., oil depots, petrol
filling stations), gas works, power plants, shipyards/boatyards, chemical
manufacturing/processing plants, steel mills/metal workshops, car
repairing/dismantling workshops and scrap yards. In addition, this Guidance
Note provides guidelines on how site assessments should be conducted and analyzed and suggests practical remedial measures that can
be adopted for the cleanup of contaminated sites.
·
Practice
Guide for Investigation and Remediation of Contaminated Land (Practice Guide),
EPD, Revised in April 2023.
This guide outlines typical investigation methods and remediation
strategies for the range of potential contaminants typically encountered in
Hong Kong.
(a)
Construction of a road of about
7.5 km long running through Tuen Mun and Tai Lam Country Park, linking the
TM-CLKT and the YLH and KSWH;
(b)
Construction of tunnel portals and associated
facilities at Tuen Mun Area 40 and Lam Tei Quarry;
(c)
Construction of viaducts
/ at-grade roads from the southern tunnel portal to the roads under planning
near Lung Mun Road/Mong Fat Street, and TM-CLKT at Tuen Mun Area 40;
(d)
Provision of associated
ventilation buildings, administration building and other tunnel operation area;
(e)
Re-provisioning of facilities affected by the
proposed works;
(f)
Possible adits and
associated connection with existing roads;
(g)
Construction of temporary explosive magazines
in Lam Tei Quarry, Siu Lam and Pillar Point; and
(h)
Associated
geotechnical works, ground investigation (GI) works, drainage works, natural
terrain hazard mitigation works, sewerage works, traffic aids, directional
signs, street lightings, Traffic Control and Surveillance System, Electrical
and Mechanical (E&M) works, environmental mitigation measures, landscaping
works, and services systems for inspection, maintenance.
Assessment Area ID |
Location |
Proposed Works |
TMB-N-R |
Southwest portion of Lam Tei Quarry |
Northern portal of TMB, ventilation building and
associated highway / tunnel operation and maintenance facilities |
TMB-N-01 |
Northwest portion of Lam Tei Quarry |
Temporary underground magazine shared use with
proposed Route 11 (under separate project) |
TMB-N-02 |
Natural Terrain and vegetation at south of Lam
Tei Quarry |
Slope works |
TMB-C-01 |
Wah Fat Playground |
Ventilation
building and slope works |
TMB-C-02 |
KW Carpark |
Temporary
re-provisioning of recreational facilities (basketball courts and public
toilet) |
TMB-C-03 |
Parking and planter at Fung On
Street |
Temporary
re-provisioning of facilities (parking area) |
TMB-C-04* |
Former Girl Guide Association (GGA) Campsite |
Building
restoration and repair works for site office and other uses |
TMB-S-R |
TM-CLKT Road and near area and Lung Mun Road |
At-grade / elevated road, ventilation building,
administration building, associated highway / tunnel operation and
maintenance facilities and slope works |
TMB-S-01 |
Former TM-CLKT Site Office |
Temporary works area for (i.e.
construction site office, construction material storage etc,) and temporary
re-provisioning of EMSD vehicle servicing centre |
TMB-S-02 |
Former TM-CLKT Site Office |
Maintenance Compound for tunnel operation and
at-grade / elevated road |
TMB-S-03 |
Area near to existing EMSD Tuen Mun Vehicle
Servicing Station |
At-graded road and slope works |
TMB-S-04 |
Existing EMSD Tuen Mun Vehicle Servicing Station |
At-graded road and slope works |
TMB-S-05* |
Site at Mong Wing Street |
Temporary works area for construction site office
and carpark |
TMB-S-06* |
Site at Pillar Point |
Temporary aboveground magazine at Pillar Point
shared use with proposed Route 11 (under separate project) |
TMB-S-07 |
Along Ho Fuk Street, Ho Yeung Street and Ho Yat
Street |
Shallow foundation works for the piers of the
temporary overhead conveyor belt. |
TMB-NL* |
TM-CLKT Northern Landfall |
Temporary works area for barging point facilities |
TMB-SL* |
Site at Siu Lam |
Temporary aboveground magazine at Siu Lam shared
use with proposed Route 11(under separate project) |
Note:
* Assessment Area will not involve any excavation
and works will not disturb the soil layer.
·
Selected
aerial photographs and topographic maps held by the Lands Department (LandsD); and
·
Records on
dangerous goods (DGs), chemical wastes and chemical spillage/leakage
incidents from Fire Services Department (FSD) and Environmental Protection
Department (EPD).
Past Land Use (1) |
Current Land Use (2) |
Site Inspections for this CAP-Accessibility |
Registered Chemical Waste Producers? (Yes/No) |
Potentially Contaminated |
Hot Spot Identified in Site Inspection? (Yes / No / N/A) |
Potential Contaminants (4), (5) |
Selection of RBRG Land Use Scenario (7) |
|
TMB-N-R |
1963-1974: Site Formation and Natural
Landscape 1986-2021: Lam Tei Quarry |
At
the time of site survey, site was inaccessible. Based on peripheral
inspection, the area is occupied by Lam Tei Quarry. |
No |
Yes |
(Yes/No) |
Cannot
be identified |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-N-01 |
1963-1974: Site Formation and Natural
Landscape 1986-2021: Lam Tei Quarry |
At
the time of site surveys, site was inaccessible. Based on peripheral
inspection, the area is occupied by Lam Tei Quarry. |
No |
Yes |
Yes |
Cannot
be identified |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-N-02 |
1963-2021: Natural Landscape and natural vegetation |
At the time of site survey, site was
inaccessible. Based on aerial photo the area is natural terrain with natural
vegetation. |
No |
No |
(Lam
Tei Quarry Area) |
N/A |
N/A |
N/A |
TMB-C-01 |
1964-1986: Village House and Natural
Landscape 1990: Site Formation and Natural
Landscape 1994-2021: Wah Fat Playground and
Natural Landscape |
During
the site walkover, Wah Fat Playground was observed including basketball court
and playground. |
Yes |
No |
Yes |
N/A |
N/A |
N/A |
TMB-C-02 |
1964: Shoreline 1978: Suspected Open Storage 1986: Under Reclamation Works 1990: Site Formation 1994: Suspected Open Storage 1999: Vegetation 2010: Construction Site Office 2016-2021: Car park |
During
the site surveys, the area was located within a fee-paying car park was
observed. |
Yes |
No |
(Lam
Tei Quarry Area) |
No |
Metal,
PCRs, VOCs, SVOCs |
Public
Park |
TMB-C-03 |
1964: Open Sea 1978: Under Reclamation Works 1986: Site Formation 1990-2021: Parking Lots and Open Area |
During the site walkover, a
fee-paying parking lots and planter area were observed. |
Yes |
No |
No |
N/A |
N/A |
N/A |
TMB-C-04 |
1950s-1980s: School (building
structures were built and developed throughout the period) 1988: Convert into a campsite
operation by GGA. (Historical use of the TMB-C-04 can
be refer to Section 12) |
During the site walkover, the
campsite is currently abandoned. The building structures were remained. |
Yes |
No |
No |
N/A |
N/A |
N/A |
TMB-S-R |
1978-1985: Site Formation and
Vegetation 1997: Open Storage, Vegetation and
Refugee Camp 2002: Site Formation, Vegetation and
Refugee Camp 2008-2012: Site Formation, Vegetation
and Vacant 2017: Construction Site 2021: TM-CLKT and associated area had
developed |
At the time of site surveys,
site was inaccessible. Based on peripheral inspection, TM-CLKT and associated
area were occupied the area and Lung Mun Road was observed. |
No |
Yes |
Yes |
N/A |
N/A |
N/A |
TMB-S-01 (Former TM-CLKT Site Office) |
1978-1985: Site Formation 1997-2002: Refugee Camp 2008-2012: Open Storage (West Portion),
Vacant (East Portion) 2017-2021: TM-CLKT Site Office and
Construction Site |
During the site survey, site
office for Contract No. HY/2021/12 with storage of construction material, no
use/ storage of chemical / chemical waste was observed at west portion of the
area. During the site survey,
vacant land was observed at the east portion of the area. |
Yes |
Yes |
(Previous
Suspected Open Storage area) |
No |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-S-02 |
1978-1985: Site Formation 1997-2002: Refugee Camp 2008-2012: Open Storage (West
Portion), Vacant (East Portion) 2017-2021: TM-CLKT Site Office and
Construction Site |
At the time of site surveys,
site was inaccessible. Based on peripheral inspection, open storage for
precast construction material was observed. During the site survey,
vacant land was observed at the east portion of the area. |
Yes |
Yes |
No |
No |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-S-03 |
1978-1997: Site Formation 2002-2021: Road, slope
and vegetation |
During the site walkover,
slope, vegetation, pedestrian and vehicle access
road were observed. |
Yes |
Yes |
No |
N/A |
N/A |
N/A |
TMB-S-04 |
1978: Site Formation 1980: Government Depot under
construction 1985-1997: Government Depot 2002-2022: Existing EMSD Tuen Mun
Vehicle Servicing Station |
During the site walkover, the
existing EMSD Tuen Mun Vehicle Servicing Station occupied the area. The existing EMSD Tuen Mun
Vehicle Servicing Station consists of Car Parking Area, Disused Petrol
Refilling Area, Maintenance Workshop Area and
Storage Area of New Vehicle Parts. Hotspots were identified
including: · Disused Petrol Refiling
Station · Underground Petrol and Diesel
Tank · Underground waste oil tank · Storage of Waste Batteries
and Metal Scrap · Storage of Drums of Motor Oil
· Waste oil discharge points at
inspection pits · Refilling area and chemical
waste storage · Storage of Chemical Waste, Automatic
Transmission Fluid, Drums of Motor Oil and Oil Drums · Oil stains |
Yes |
Yes |
No |
Yes |
Metal,
PCRs, VOCs, SVOCs |
Lower
of Industrial or Public Park |
TMB-S-05 |
1978-1985: Site Formation / Vacant 1997: Site Formation 2002: Open storage 2008: Construction Site Office 2012: Open Storage 2017: Open Storage/ Construction Site
Office 2021: Vacant Land |
At the time of site surveys,
site was inaccessible. Based on peripheral inspection, storage area for
construction trucks and equipment were observed. |
No |
Yes |
Yes |
Cannot
be identified |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-S-06 |
1978-1980: Natural Landscape 1985-1997: Open Storage 2002-2008: Vacant 2012-2017: Open Storage 2022: Vacant |
During the site survey,
storage area of construction materials was observed. No chemical, stain, leakage or seepage was observed. |
Yes |
No |
(Previous
Open Storage Area at Northwest and Southwest Portions) |
No |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
TMB-S-07 |
Before 1985: Open
Sea 1985: Reclamation
completed, and site formed for most of the section. 1997: Ho Fuk
Street, and Ho Yeung Street already presented and remained unchanged. Sawmill
at the TM-CLKT Northern Landfall section. 2014-2020: 2021: The sawmill was demolished; a
construction works area remained and grassland / plantation was developed. |
During the site survey, Lung Mun Road, Ho Fuk Street, Ho Yeung
Street was observed. A vacant land was observed at
the TM-CLKT Northern Landfall section. |
Yes |
No |
Yes |
N/A |
N/A |
N/A |
TMB-NL |
Before 1980: Open Sea 1985: Reclamation completed, and site
formed at the furthest north. Remaining area at open sea. 1988: Sawmill at furthest north.
Remaining area at open sea. 2014-2020: Reclamation works under
TM-CLKT construction, and used as construction works area. 2021: The sawmill was demolished; a
construction works area remained and grassland. / plantation
was developed |
During the site survey,
majority area with grassland / plantation and access road were observed and a
vacant land noted at the TM-CLKT Northern Landfall
and the demolished sawmill area was remained vacant. |
Yes |
No |
(Previous
Open Storage Area at Northwest and Southwest Portions) |
N/A |
N/A |
N/A |
TMB-SL |
Before 1986:
Natural Landscape 1986: Site
Formation and Vacant 1999: Vacant Land 2008: Open Storage 2015: Magazine Site
2021: Vacant Land |
During the site survey, vacant
land with vegetation was observed. |
Yes |
No |
No |
No |
Metal,
PCRs, VOCs, SVOCs |
Industrial |
Notes:
• N/A = Not Applicable
(1)
To
identify any past land uses that may cause potential land contamination issues,
the historical land uses of the Assessment Area has been reviewed with the aid
of selected historical photographs in the years from 1963 to 2022 available
from the LandsD. The referenced aerial photographs
are attached in Appendix A of the CAP.
(2)
The
current land use for each identified area is determined based on the site
inspection (including the peripheral inspection) and the available information
from the internet.
(3)
The
hot spots that have been identified at this stage are not exhaustive as changes
of land use in future may give rise to further hot spots. As such, the site
re-appraisal should be conducted to cover the whole Assessment Area to ensure
that any additional hot spots are identified once site access is available
(e.g., the completion of the land resumption).
(4)
Metal,
PCRs, VOCs and SVOCs, all-inclusive as listed in Appendix F of the CAP.
(5)
The
potential contaminants that have been identified at this stage are not
exhaustive as changes of land use in future may give rise to further hot spots.
As such, the site re-appraisal should be conducted to cover the whole
Assessment Area to ensure that any additional potential contaminants are
identified once site access is available (e.g., the completion of the land
resumption).
(6)
At
the time of preparation of this CAP, TMB-N-R, TMB-N-01, TMB-N-02, TMB-S-R,
western portion of TMB-S-02 and TMB-S-05 were inaccessible during the time of
preparation of the CAP, and it was observed that the all the potential
contaminated area are in operation and infeasible to conduct site investigation
(SI) and sampling works at EIA. Therefore, prior to the development of these
areas, site re-appraisal of the whole project should be carried out in order to
address any new contamination issues caused by the (i)
changes in operation of the identified potentially contaminated site and (ii)
changes in land use within the Project Area. The supplementary CAP(s),
incorporating the findings of the site re-appraisal and the updated sampling
and testing strategy, should be prepared and submitted
to EPD for agreement prior to the commencement of SI works.
(7)
The
RBRGs Land Use Scenario is selected for each Assessment Area with potential
contamination by the future land use as summarised in Table 7.2.
· Lam Tei Quarry involves the
usage of chemicals for blasting, asphalt, and concrete production at TMB-N-R
and TMB-N-01;
· Former open storage area at TMB-C-02, TMB-S-01
(Western Portions) and TMB-S-02 (Western Portions), TMB-S-05, TMB-S-06 and
TMB-SL (Northern Portion); and
·
Maintenance
workshop area and disused petrol refilling area of the existing EMSD Tuen Mun Vehicle Servicing Station (TMB-S-04).
·
Disused Petrol Refiling Station
·
Underground Petrol and Diesel Tank
·
Underground Waste Oil Tank
·
Storage of Waste Batteries and Metal Scrap
·
Storage of Drums of Motor Oil
·
Waste oil discharge points at inspection pits
·
Refilling area and chemical waste storage
·
Storage of Chemical Waste, Automatic Transmission Fluid, Drums of Motor
Oil and Oil Drums
·
Oil stains
Assessment Area |
Approximate Potential Contaminated Area (m2) |
Regular Sampling Grid Size (9) |
Number of Regular Grid Sampling Locations (9),
(11) |
Regular Grid SI Location ID |
Drilling Depth and Method |
Soil |
Groundwater |
||||
Sample Depths (2) ,
(11) |
Parameter to be Analysed (3), (4), (5),
(6), (10) |
Sample Depths |
Parameters to be Analysed (4), (5), (7),
(8), (10) |
||||||||
TMB-N-R |
1,700 |
13m x 13m |
14 |
TMB-N-R TP1 to TP14 |
Trial pit by manual excavation down to 3.0m bgl
(10) |
Manual excavation of trial pit (0-3.0m bgl): · To manually collect disturbed
samples at 0.5m, 1.5m and 3.0m bgl |
Metal, PCRs, VOCs, SVOCs |
To collect one groundwater sample at static groundwater level (If present) |
Mercury, PCRs, VOCs, SVOCs |
||
TMB-N-01 |
1,550 |
13m x 13m |
12 |
TMB-N-01 TP1 to TP12 |
|||||||
TMB-C-02 |
1,200 |
13m x 13m |
8 |
TMB-C-02 BH1 to BH8 |
Borehole constructed by rotary drilling to 6.0m-6.5m below
ground level (bgl) and 2.0m below ground water
level. |
Manual excavation of inspection pit (0-1.5m bgl): ·
To manually collect disturbed samples at 0.5m and 1.5m. Rotary drilling of boreholes: · Continuous drilling from bottom
of the inspection pit and collected undisturbed samples at 3.0m and 6.0m bgl. |
Metal, PCRs, VOCs, SVOCs |
To collect one groundwater sample at static groundwater level |
Mercury, PCRs, VOCs, SVOCs |
||
TMB-S-01 |
11,400 |
19m x 19m |
34 |
TMB-S-01 BH1 to BH34 |
|||||||
TMB-S-02 |
6,700 |
17m x17m |
26 |
TMB-S-02 BH1 to BH26 |
|||||||
TMB-S-04 |
700 |
13m x 13m |
4 |
TMB-S-03 BH1 to BH4 |
|||||||
Note:
(1)
Exact
coordinates to be confirmed by contractor after sub-surface utility scanning
and will be provided in the CAR;
(2)
Sampling
depths may be changed if there is presence of rock/big boulders during rotary
drilling. Exact sampling locations shall be subject to the instructions of land
contamination specialist during supervision;
(3)
Metals
for soil samples: Antimony, Arsenic, Barium, Cadmium, Chromium III, Chromium
VI, Cobalt Copper, Lead, Manganese, Mercury, Molybdenum, Nickel, Tin and Zinc,
all-inclusive as listed in Appendix D of the CAP (Appendix 7.1 refers);
(4)
Petroleum
Carbon Ranges: C6-C8, C9-C16, C17-C35, all-inclusive as listed in in Appendix F
of the CAP;
(5)
VOCs:
Acetone, Benzene, Bromodichloromethane, 2- Butanone, Chloroform, Ethylbenzene,
Methyl tert-Butyl Ether, Methylene Chloride, Styrene, Tetrachloroethene,
Toluene, Trichloroethene, and Xylenes (Total);
(6)
SVOCs
for Soil: Acenaphthene, Acenaphthylene, Anthracene, Benzo(a)anthracene,
Benzo(a)pyrene, Benzo(b)fluoranthene, Benzo(g,h,i)perylene, Benzo(k)fluoranthene,
bis-(2-Ethylhexyl)phthalate, Chrysene, Dibenzo(a,h)anthracene,
Fluoranthene, Fluorene, Hexachlorobenzene, Indeno(1,2,3-cd)pyrene,
Naphthalene, Phenanthrene, Phenol, and Pyrene;
(7)
SVOCs
for Groundwater: Acenaphthene, Acenaphthylene, Anthracene,
Benzo(b)fluoranthene, Chrysene, Fluoranthene, Fluorene, Hexachlorobenzene,
Naphthalene, Phenanthrene, and Pyrene; and
(8)
Mercury
will be analysed for groundwater samples;
(9)
Grid
size and number of sampling points were determined proportionally from Table
2.1 of the Practice Guide.
(10) TMB-N-R and TMB-N-01 are both within Lam Tei Quarry, Lam Tei
Quarry with topsoil less than 3m thick and no groundwater is anticipated,
therefore, trial pit method is proposed. Previous ground investigation record
at Lam Tei Quarry is presented in Appendix G of the CAP for reference.
(11) Sampling strategic shall be further reviewed
based actual site condition. Alternative sampling strategic shall be proposed
and agreed with EPD in Supplementary CAP(s).
Potential Contaminated Area ID |
Identified Hot Spot (9) |
Hot Spot SI Location ID |
Drilling Depth and Method (3), (10) |
Soil |
Groundwater |
||
Sample Depths (2), (10) |
Parameter to be Analysed (3), (4), (5), (6) |
Sample Depths |
Parameters to be Analysed (7), (8) |
||||
TMB-S-04 |
Storage of Drum of Motor Oil |
TMB-S-04 BH5 |
Borehole constructed by rotary drilling to 6.0m to 6.5m below
ground level (bgl) and 2.0m below ground water
level |
Manual excavation of inspection pit (0-1.5m bgl): ·
To manually collect disturbed samples at 0.5m bgl and 1.5m bgl. for laboratory analysis Rotary drilling of boreholes: · Continuous drilling from bottom
of the inspection pit and collected undisturbed samples at 3.0m bgl and at 6.0m bgl. |
Metal, PCRs, VOCs, SVOCs |
To collect one groundwater sample at static groundwater level |
Mercury, PCRs, VOCs, SVOCs |
Oil Stains at Tyre tChanging Machines |
TMB-S-04 BH6 |
||||||
Chemical Waste Storage |
TMB-S-04 BH7 |
||||||
Storage of Automatic Transmission Fluid and Equipment |
TMB-S-04 BH8 |
||||||
Storage of Drums of Motor Oil |
TMB-S-04 BH9 |
||||||
Chemical Waste Storage |
TMB-S-04 BH10 |
||||||
Storage of Automatic Transmission Fluid |
TMB-S-04 BH11 |
||||||
Chemical Waste Storage |
TMB-S-04 BH12 |
||||||
Refilling Area |
TMB-S-04 BH13 |
||||||
Storage of Drums of Motor Oil |
TMB-S-04 BH16 |
||||||
Storage of Metal Scraps |
TMB-S-04 BH17 |
||||||
Storage of Waste Batteries |
TMB-S-03 BH18 |
||||||
Disused Petrol Refilling Station |
TMB-S-03 BH22 |
||||||
Waste Oil Discharge Points |
TMB-S-03 BH14 |
Borehole constructed by rotary drilling to 6.0m to 6.5m below the EMSD maintenance
inspection pit and 2.0m below ground water level |
Rotary drilling of boreholes: · Continuous drilling from bottom of the EMSD maintenance inspection pit and collected undisturbed samples at 0.5m, 1.5m, 3.0m and 6.0m
below bottom of maintenance inspection pit. |
Metal, PCRs, VOCs, SVOCs |
To collect one groundwater sample at static groundwater level |
Mercury, PCRs, VOCs, SVOCs |
|
Waste Oil Discharge Points |
TMB-S-04 BH15 |
||||||
Underground Waste Oil Tank |
TMB-S-04 BH19 |
Borehole constructed by rotary drilling to 6.0m to 6.5m below
underground tank and 2.0m below ground water level |
Rotary drilling of boreholes: · Continuous drilling from bottom of
underground tank and collected undisturbed samples at 0.5m, 1.5m, 3.0m and
6.0m below bottom of underground tank. |
Metal, PCRs, VOCs, SVOCs |
To collect one groundwater sample at static groundwater level |
Mercury, PCRs, VOCs, SVOCs |
|
Disused Underground Petrol and Diesel Tank |
TMB-S-04 BH20 |
||||||
Disused Underground Petrol and Diesel Tank |
TMB-S-04 BH21 |
Note:
(1)
Exact
coordinates to be confirmed by contractor after sub-surface utility scanning
and will be provided in the CAR;
(2)
Sampling
depths may be changed if there is presence of rock/big boulders during rotary
drilling. Exact sampling locations shall be subject to the instructions of land
contamination specialist during supervision;
(3)
Metals
for soil samples: Antimony, Arsenic, Barium, Cadmium, Chromium III, Chromium
VI, Cobalt Copper, Lead, Manganese, Mercury, Molybdenum, Nickel, Tin and Zinc,
all-inclusive as listed in Appendix F of the CAP;
(4)
Petroleum
Carbon Ranges: C6-C8, C9-C16, C17-C35, all-inclusive as listed in in Appendix F
of the CAP;
(5)
VOCs:
Acetone, Benzene, Bromodichloromethane, 2- Butanone, Chloroform, Ethylbenzene,
Methyl tert-Butyl Ether, Methylene Chloride, Styrene, Tetrachloroethene,
Toluene, Trichloroethene, and Xylenes (Total);
(6)
SVOCs
for Soil: Acenaphthene, Acenaphthylene, Anthracene, Benzo(a)anthracene,
Benzo(a)pyrene, Benzo(b)fluoranthene, Benzo(g,h,i)perylene, Benzo(k)fluoranthene,
bis-(2-Ethylhexyl)phthalate, Chrysene, Dibenzo(a,h)anthracene,
Fluoranthene, Fluorene, Hexachlorobenzene, Indeno(1,2,3-cd)pyrene,
Naphthalene, Phenanthrene, Phenol, and Pyrene;
(7)
SVOCs
for Groundwater: Acenaphthene, Acenaphthylene, Anthracene, Benzo(b)fluoranthene,
Chrysene, Fluoranthene, Fluorene, Hexachlorobenzene, Naphthalene, Phenanthrene,
and Pyrene; and
(8)
Mercury
will be analysed for groundwater samples;
(9)
Sampling
strategic shall be further reviewed based actual site condition. Alternative sampling
strategic shall be proposed and agreed with EPD in Supplementary CAP(s).
·
Excavation profiles must be properly designed and executed with
attention to the relevant requirements for environment, health and safety;
·
Excavation shall be carried out during dry season as far as possible to minimise contaminated runoff from contaminated soils;
·
Supply of suitable clean backfill material (or treated soil) after excavation;
·
Stockpiling site(s) shall be lined with impermeable sheeting and bunded.
Stockpiles shall be fully covered by impermeable sheeting to reduce dust emission;
·
Vehicles containing any excavated materials shall be suitably covered to
limit potential dust emissions or contaminated wastewater run-off, and truck
bodies and tailgates shall be sealed to prevent any discharge during transport
or during wet conditions;
·
Speed control for the trucks carrying contaminated materials shall be enforced;
·
Vehicle wheel and body washing facilities at the site’s exit points
shall be established and used; and
·
Pollution control measures for air emissions (e.g.
from biopile blower and handling of cement), noise
emissions (e.g. from blower or earthmoving equipment), and water discharges
(e.g. runoff control from treatment facility) shall be implemented and complied
with relevant regulations and guidelines.