Contents
9.1 Legislation, Standards
and Guidelines
9.3 Landfill Gas
Hazard Assessment Criteria and Methodology
9.5 Potential for
the Project to Intercept Landfill Gas
9.6 Sensitive
Targets for Landfill Gas Risk
9.7 Qualitative
Assessment of Risks due to Landfill Gas
9.8 General Hazards
Related to Landfill Gas
Table
9.1 Classification of Risk Category
Table
9.2 Summary of General Categorisations of Risk
Table 9.3 Summary of Landfill Gas Monitoring Results
of the Perimeter Monitoring Wells at PPVL (From August 2021 to July 2022)
Table
9.5 Summary of Groundwater Monitoring Results at PPVL (From July 2021 to July
2022)
Table
9.6 Qualitative Assessment of Landfill Gas Hazard Associated with PPVL
Table
9.7 Actions in the Event of Gas Being Detected
Figure 9.1 250m Consultation Zone of PPVL
Figure 9.2 Location
of Landfill Gas and Groundwater Monitoring Wells at PPVL
Figure 9.3 Geological
Map
Figure 9.4 Location
of the Proposed Facilities
Appendix 9.1 Landfill Gas Monitoring Results of the
Perimeter Monitoring Wells at PPVL
Appendix 9.2 Groundwater Monitoring Results at PPVL
Appendix 9.3 Typical Designs for Precautionary and Protection Measures for Design Phase
·
review
background information (including landfill gas and groundwater monitoring data)
and studies related to the PPVL;
·
identify the
nature and extent of the PPVL which might have potential impacts on the construction
and operation of the Project;
·
identify
possible pathways through the ground, underground cavities and utilities and
the nature of these pathways through which landfill gas must traverse if they
were to reach the Project site;
·
identify the
potential receivers which are sensitive to the landfill gas risk;
·
conduct a
qualitative assessment of the degree of risk which the landfill gas migration
may impose on the identified receivers for each of the source-pathway-receiver
combinations; and
·
recommend
and design suitable level of precautionary measures and contingency plan for
the potential receivers, if needed.
· Source
– the rate and concentration of landfill gas generation by the concerned
landfill(s);
· Pathway
– the nature of and length of potential pathways through which landfill gas can
migrate and leachate flow, such as geological strata, utility services; and
· Target
– the level of vulnerability of various elements of the Project site or
facilities to landfill gas.
Major Recently filled landfill site at
which there is little or no control to prevent migration of gas or at which the
efficacy of the landfill gas control measures has not been assessed; or
Any landfill site at which monitoring has demonstrated that there is
significant migration of landfill gas beyond the site boundary.
Medium Landfill site at which some form of
landfill gas control has been installed (e.g., lined site or one where vents or
barriers have been retrospectively installed) but where there are only limited
monitoring data to demonstrate its efficacy to prevent migration of landfill
gas; or
Landfill site where comprehensive monitoring has demonstrated that there
is no migration of landfill gas beyond the landfill boundary but where the
control of landfill gas relies solely on an active gas extraction system or any
other single control system which is vulnerable to failure.
Minor Landfill sites at which landfill gas
controls have been installed and proven to be effective by comprehensive
monitoring which has demonstrated that there is no migration of landfill gas
beyond the landfill boundary (or any specific control measures) and at which
control of landfill gas does not rely solely on an active gas extraction system
or any other single control measure which is vulnerable to failure; or
Old landfill sites where the maximum concentration of methane within the
waste, as measured at several locations across the landfill and on at least
four occasions over a period of at least 6 months, is less than 5% (v/v).
·
Man-made pathways e.g., utility connections,
stormwater channels, etc.,
·
Natural pathways such as rock jointing planes,
fissures and other naturally occurring phenomena which may promote or give rise
to the transmission of gas over distances; and
·
A
combination of the previous two categories. An example of the latter may
be, for instance, where a specific geological feature promotes gas transmission
but which stops short of directly linking the landfill and target. A man made
connection, however may also co-exist near the edge of the geological feature,
which in combination with the former, may act to link the two sites. In this
instance, careful assessment of the likelihood of the mechanism acting to link
the two pathways needs to be undertaken before assigning an appropriate pathway
classification.
Very short/direct Path length of less than 50m for
unsaturated permeable strata and fissured rock or less than 100m for man-made
conduits
Moderately short/direct Path length of 50 to 100m for unsaturated
permeable soil or fissured rock or 100 to 250 m for man-made conduits
Long/indirect Path length of 100 to 250m
for unsaturated permeable soils and fissured rock
· a broad assessment of the
specific permeability of the soil;
· spacing, tightness and direction of the
fissures/joints;
· topography;
· depth and thickness of the medium through
which the landfill gas may migrate (which may be affected by groundwater
level);
· the nature of the strata over the potential
pathway;
· the number of different media involved; and
· depth to groundwater table
and groundwater flow patterns.
High Sensitivity Buildings and structures with
ground level or below ground rooms/voids or into which services enter directly
from the ground and to which members of the general public have unrestricted
access or which contain sources of ignition.
This would include any developments where there is a possibility of
additional structures being erected directly on the ground on an ad hoc basis
and thereby without due regard to the potential risks.
Medium Sensitivity Other buildings, structures or service
voids where there is access only by authorised, well trained personnel, such as
the staff of utility companies, who have been briefed on the potential hazards
relating to landfill gas and the specific safety procedures to be followed, and
deep excavations.
Low Sensitivity Buildings/structures which are
less prone to gas ingress by virtue of their design (such as those with a
raised floor slab), shallow excavations, and developments which involve
essentially outdoor activities but where evolution of gas could pose potential
problems.
Table 9.1 Classification of Risk Category
Source |
Pathway |
Target Sensitivity |
Risk Category |
Major |
Very
short/direct |
High |
Very
high |
Medium |
High |
||
Low |
Medium |
||
Moderately
short/direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long/indirect |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Medium |
Very
short/direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderately
short/direct |
High |
High |
|
Medium |
Medium |
||
Low |
Low |
||
Long/indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very
low |
||
Minor |
Very
short/direct |
High |
High |
Medium |
Medium |
||
Low |
Low |
||
Moderately
short/direct |
High |
Medium |
|
Medium |
Low |
||
Low |
Very
low |
||
Long/indirect |
High |
Medium |
|
Medium |
Low |
||
Low |
Very
low |
Table 9.2 Summary
of General Categorisations of Risk
Level of Risk |
Implication |
Very high |
At the very
least, extensive engineering measures and alarm systems are likely to be
required. An emergency actions plan
should also be developed so that appropriate actions may be immediately taken
in the event of high landfill gas concentrations being detected within the
development. |
High |
Significant
engineering measures will be required to protect the planned development. |
Medium |
Engineering
measures required to protect the development. |
Low |
Some
precautionary measures will be required to ensure that the planned
development is safe. |
Very low |
No
protection or precautionary measures are required. |
·
Placement of
a high integrity cap across the top platform of the landfill to reduce infiltration,
reduce leachate generation and control leachate levels;
·
Modification
to the existing leachate and groundwater collection systems to intercept and
direct leachate to the onsite leachate treatment works;
·
Passive
venting of landfill gas in specific areas to mitigate gas migration off-site;
·
Active
landfill gas extraction to control and collect landfill gas for use at the
leachate treatment works;
·
Realignment
of a natural stream at the toe of the landfill and the formation of a platform
on the eastern left bank of the stream for the construction of the treatment
compound; and
·
Construction
of leachate treatment works for the treatment of the collected leachate.
Table 9.3 Summary of Landfill Gas Monitoring Results
of the Perimeter Monitoring Wells at PPVL (From August 2021 to July 2022)
Location |
Methane (% gas) |
Carbon Dioxide (% gas) |
||
Range |
Average |
Range |
Average |
|
GM1 |
0.0
– 0.0 |
0.0 |
7.2
– 11.9 |
9.6 |
GM2 |
0.0
– 0.0 |
0.0 |
2.0
– 10.9 |
7.3 |
GVQ1 |
0.0
– 0.0 |
0.0 |
0.1
– 10.5 |
6.2 |
GVQ2 |
0.0
– 0.0 |
0.0 |
0.1
– 13.5 |
6.8 |
GVQ3 |
0.0
– 0.0 |
0.0 |
0.0
– 4.1 |
2.1 |
GM4 |
0.0
– 0.0 |
0.0 |
4.1
– 6.9 |
5.0 |
GM5 |
0.0
– 0.0 |
0.0 |
2.8
– 8.1 |
5.3 |
P5 |
0.0
– 0.1 |
0.0 |
0.9
– 3.7 |
1.9 |
Table 9.4 Summary of Groundwater Monitoring Results
at PPVL (From July 2021 to July 2022)
Location |
Ammoniacal nitrogen (mg/L) |
Chemical Oxygen Demand (COD) (mg/L) |
||
Range |
Average |
Range |
Average |
|
PWQM2 |
0.11
– 0.14 |
0.13 |
<4
– 11 |
7 |
PWQM3 |
0.11
– 0.26 |
0.15 |
4
– 17 |
9 |
PWQM4 |
0.11
– 0.27 |
0.15 |
2
– 7 |
4 |
PWQM5 |
0.11
– 0.62 |
0.27 |
6
– 12 |
8 |
PWQM6 |
0.11
– 0.14 |
0.13 |
2
– 10 |
5 |
PWQM7 |
0.10
– 0.15 |
0.13 |
5
– 12 |
8 |
PWQM8 |
0.11
– 0.14 |
0.12 |
5
– 77 |
31 |
PWQM9 |
0.11
– 5.80 |
2.22 |
4
– 14 |
8 |
GV2 |
0.11
– 0.15 |
0.13 |
3
– 8 |
5 |
GV4 |
0.11
– 0.14 |
0.13 |
<2
– 4 |
3 |
GV5 |
0.10
– 0.14 |
0.12 |
2
– 5 |
4 |
GWQ(A)2 |
0.11
– 0.14 |
0.13 |
<4
– 5 |
5 |
GWQ(A)3 |
0.11
– 0.14 |
0.13 |
<2
– 6 |
4 |
GWQ(A)4 |
0.58
– 0.74 |
0.66 |
4
– 9 |
7 |
GWQ(B)1 |
-
* |
-
* |
-
* |
-
* |
GWQ(B)2 |
0.10
– 1.50 |
0.40 |
<2
– 5 |
3 |
GWQ(B)3 |
0.11
– 0.14 |
0.13 |
<2
– 6 |
3 |
GWQ(B)4 |
0.11
– 0.14 |
0.13 |
3
– 5 |
4 |
Notes: *
No groundwater detected. |
Target 1 – Construction Site of the Project
Target 2
– Operation of the Administration Building, Maintenance Compound,
temporary re-provisioning of EMSD Vehicle Servicing Centre
Table 9.5 Qualitative Assessment of Landfill Gas
Hazard Associated with PPVL
Source |
Pathway |
Target |
Qualitative Risk |
PPVL – Passive control, active
extraction, comprehensive monitoring (Category:
Medium) |
Less than 50m from PPVL, no fault/fissure,
no man-made conduits (Category:
Very short/ direct) |
Target 1 (Construction site of the
Project) – Open excavation works, working in confined space by trained staffs (Category:
Medium sensitivity) |
Medium |
Around 150 m from PPVL, no
fault/fissure, no man-made conduits (Category: Long/indirect) |
Target 2 (Operation of the Administration Building) – Underground
confined spaces and ground level rooms with underground utility connections
with restricted access (Category:
Medium sensitivity) |
Low |
|
Target 2 (Operation of the Administration Building) –Ground level rooms
of unrestricted staff access, or with source of ignition (Category:
High sensitivity) |
Medium |
||
Around 90 m from PPVL, no
fault/fissure, no man-made conduits (Category: Moderately
short/direct) |
Target 2 (Operation of the Maintenance Compound) – Underground confined spaces
and ground level rooms with underground utility connections with restricted
access (Category:
Medium sensitivity) |
Medium |
|
Target 2 (Operation of the Maintenance Compound) –Ground level rooms of unrestricted
staff access, or with source of ignition (Category:
High sensitivity) |
High |
||
Less than 50 m from PPVL, no
fault/fissure, no man-made conduits (Category:
Very short/ direct) |
Target 2 (Operation of the temporary re-provisioning of EMSD vehicle servicing centre)
– Underground confined spaces and ground level rooms with underground utility
connections with restricted access (Category:
Medium sensitivity) |
Medium |
|
Target 2 (Operation of the temporary re-provisioning of
EMSD vehicle servicing centre) – Ground level rooms of
unrestricted staff access, or with source of ignition (Category:
High sensitivity) |
High |
Safety Measures
·
During all
works, safety procedures should be implemented to minimise the risks of fires
and explosions and asphyxiation of construction team (especially in confined
space).
·
Safety
officers, specifically trained with regard to landfill gas related hazards and
the appropriate actions to take in adverse circumstances, should be present on
the site throughout the works, in particular, when works are undertaken below
grade.
·
All personnel
who work on site and all visitors to the site should be made aware of the
possibility of ignition of gas in the vicinity of the works.
·
Those staff
who work in, or have responsibility for “at risk” areas, including bore piling
and excavation works, should receive appropriate training on working in areas
susceptible to landfill gas.
·
Any
offices/quarters set up on site should take precautions against landfill gas
ingress, such as landfill gas monitoring and alarm devices. Other storage premises, e.g. shipping
containers, where this is not possible should be well ventilated prior to
entry.
·
Adequate
precautions to prevent the accumulation of landfill gas under site buildings
and within storage shed should be taken by raising buildings off the ground where
appropriate and “airing” storage containers prior to entry by personnel and
ensuring adequate ventilation at all times.
·
Smoking and
naked flames should be prohibited within confined spaces. “No Smoking” and “No Naked Flame” notices in
Chinese and English should be posted prominently around the construction
site. Safety notices should be posted
warning of the potential hazards.
·
During the
construction works, adequate fire extinguishers and breathing apparatus sets
should be made available on site and appropriate training given in their use.
·
Welding,
flame-cutting or other hot works may only be carried out in confined spaces
when controlled by a “permit to work” procedure, properly authorised by the
Safety Officer. The permit to work procedure should set down clearly the
requirements for continuous monitoring of methane, carbon dioxide and oxygen
throughout the period during which the hot works are in progress. The procedure should also require the
presence of an appropriately qualified person who shall be responsible for
reviewing the gas measurements as they are made, and who shall have executive
responsibility for suspending the work in the event of unacceptable or
hazardous conditions. Only those staffs
who are appropriately trained and fully aware of the potentially hazardous
conditions which may arise should be permitted to carry out hot works in
confined areas.
Monitoring
·
Periodically
during ground-works construction, the works area should be monitored for
methane, carbon dioxide and oxygen using appropriately calibrated portable gas
detection equipment. The equipment should be intrinsically safe and calibrated
according to the manufacturer’s instructions.
·
The
monitoring frequency and areas to be monitored should be set down prior to
commencement of works either by the Safety Officer or by an appropriate
qualified person.
·
Routine
monitoring should be carried out in all excavations, manholes and chambers and
any other confined spaces that may have been created by, for example, the
temporary storage of building materials on the site surface.
·
All
measurements in excavations should be made with the monitoring tube located not
more than 10mm from the exposed ground surface.
·
A standard
form, detailing the location, time of monitoring and equipment used together
with the gas concentrations measured, should be used when undertaking manual
monitoring to ensure that all relevant data are recorded.
·
Monitoring
of excavations should be undertaken as follows:
For excavations deeper than 1m, measurements should be made:
-
at the
ground surface before excavation commences;
-
immediately
before any staff enters the excavation;
-
at the
beginning of each working day for the entire period the excavation remains
open; and
-
periodically
through the working day whilst the construction team is in the excavation.
For
excavations between 300mm and 1m deep, measurements should be made:
-
directly
after the excavation has been completed; and
-
periodically
whilst the excavation remains open.
For excavations
less than 300mm deep, monitoring may be omitted, at the discretion of the Safety Officer
or other appropriately qualified person.
·
If methane
(flammable gas) or carbon dioxide concentrations are in excess of the trigger
levels or that of oxygen is below the levels specified in the Emergency
Management in the following section, then evacuation will be initiated.
Actions in the Event of Gas Being Detected
Table 9.6 Actions in the Event of Gas Being Detected
Parameter |
Measurement |
Action |
O2 |
<
19% v/v |
Increase
underground ventilation to restore O2 to >19% v/v |
<
18% v/v |
Stop works Evacuate all personnel Increase
ventilation further to restore O2 to >19% v/v |
|
CH4 |
>
10% LEL |
Prohibit
hot works Increase
ventilation to restore CH4 to <10% LEL |
>20%
LEL |
Stop works Evacuate all personnel Increase
ventilation further to restore CH4 to <10% LEL |
|
CO2 |
>0.5%
v/v |
Increase
ventilation to restore CO2 to <0.5% v/v |
>
1.5% v/v |
Stop works Evacuate all personnel Increase
ventilation further to restore CO2 to <0.5% v/v |
Emergency Management
·
Hong Kong
Police Force;
·
Fire
Services Department; and
·
Environmental
Protection Department.
Passive
control measures:
·
Gas-resistant
polymeric membranes which can be incorporated into floor or wall construction
as continuous sealed layer (see Illustration
1 in Appendix 9.3). Membranes should be able to
demonstrate low gas permeability and resistance to possible chemical attack and
may incorporate aluminium wafers to improve performance.
·
Other
building materials such as dense well-compacted concrete or steel shuttering
which provide a measure of resistance to gas permeation.
·
Creation of
a clear void under the structure which is ventilated by natural air movements
such that any emissions of gas from the ground are mixed and diluted by air
(see Illustration 2 in Appendix 9.3).
·
Synthetic
composite geotextiles which provide a free-venting cellular structure and
provide preferential pathways for release of gas.
Active
control measures:
·
A void under
the structure, as discussed for passive control, but which is continuously
ventilated by a fan, such that any emissions of gas from the ground are mixed
and diluted in the air flow before discharge to atmosphere (see Illustration 2 in Appendix 9.3). The rate of ventilation is usually expressed in
terms of the number of air changes (volume of the void) per hour and is
designed to ensure that, based on the potential rate at which gas will enter
the void, the size of the room/pits, the chance of methane to accumulate to the
lower exposure limit (i.e. 5% gas) is not possible. Discharge to atmosphere usually takes place
above the eaves level of the building or, in the case of high-rise structures,
at a minimum height of 10 m above ground and away from air intakes to the
building.
·
Construction
of a granular layer incorporating perforated collector pipes which is
continually ventilated by a fan, such that any emissions of gas from the ground
are drawn towards the end of the pipes and diluted in the air flow before
discharge to atmosphere above the eaves level of the building, or in the case
of high-rise structures, at a minimum height of 10 m above ground and away from
air intakes to the building.
·
Creation of
a positive pressure zone below the building structure by injection of air from
a blower into the granular layer.
·
Creation of
a positive air pressure zones within building structures to counteract possible
leakage of gas into the building from the ground.
Active control should always be used in conjunction
with passive barriers such as low gas permeable membranes or paint in floors,
in order that there is no leakage of air/gas flow through a floor or wall into
a structure. Gas detection systems should also be used to monitor gas in
extracted air flow, and to monitor internal spaces inside buildings. Active systems are normally required for
high-risk sites where landfill gas has been measured in the ground at or close
to the development site, and where buildings are close to the source of
landfill gas.
Gas
Barriers
·
Barriers
used to prevent movement of landfill gas through service entries may be made of
clay (or clay-rich soils), bentonite or polymeric membranes (such as
HDPE). The design detail at the point
where the service penetrates the membrane is important and use should be made
of pre-formed shrounds (or cloaks), skirts and fillets. A schematic for a natural material cut-off
barrier is shown in Illustration 3 in Appendix 9.3.
·
It will also
be appropriate to consider routing all services through a sealed culvert or
duct which is either completely lined in naturally gas-resistant material (e.g.
clay, low permeability paint) or which is lined with an HDPE membrane.
·
In the case
of water pipes and sewers which are not always fully filled, water traps, such
as U-bends, should be provided to effectively seal off the conduit and prevent
gas-phase transport.
·
In order to
prevent the ingress of landfill gas into a building via the interface between
the service pipe and the backfilled soil, it is important that the annulus
around any service entry points is effectively blocked by means of sealant,
collars or puddle flanges as appropriate (see Illustration 4 in Appendix 9.3).
Gas
Vents
·
Vent pipes
or griddled manhole covers may be used to avoid build-up of landfill gas in
underground utilities manholes. Venting stacks may be built into inspection
chambers or connected to collection pipes within high permeability drainage
layers adjacent to landfill gas barriers. A typical vented manhole arrangement
is shown in Illustration 5 in Appendix 9.3.
·
A further
type of venting arrangement, which may be appropriate to multiple service
entries, comprises a vented gas interceptor cavity through which service pipes
pass, as shown in Illustration 6 in Appendix 9.3. The
aim of this protection measure is to locate the barrier component within the
building sub-structure in a sealed entry box which is fitted with a vent stack.