Content
> Review of the Operation of
Environmental Impact Assessment (EIA) Ordinance and Continuous
Improvement Measures > Appendix
A > Appendix B >
Appendix C > Appendix
D > Appendix E
Review
of the Operation of Environmental Impact Assessment (EIA) Ordinance
and Continuous Improvement Measures
Background
- The Environmental
Impact Assessment (EIA) Ordinance was enacted on 4 February 1997
with the Appeal Board Regulation and Fees Regulation made in November
1997. The Ordinance and its regulations came into operation on
1 April 1998. As at to date, the Ordinance has been in operation
for about 18 months.
- The EIA
Ordinance provides a statutory framework for the assessment of
environmental impacts of designated projects* and the implementation
of prevention and mitigation measures to protect the environment.
The Environmental Protection Department (EPD) is responsible for
regulating and enforcing the EIA Ordinance and is committed to
continuous improvement. It has always been EPD's intention to
review the operation of the EIA Ordinance, with a view to seeking
continuous improvement measures. The 1998 Policy Objectives also
included the carrying out of a Review of the Operation of the
EIA Ordinance.
* Designated
project is a project under the control of the EIA Ordinance as
defined in Schedule 1 and listed in Schedule 2 and 3 of the Ordinance.
- The Review
was completed by EPD in August 1999. This paper presents the key
findings and the proposed continuous improvement measures.
The Focus of the Review
- The Review
focused on the first 18 months of operation of the EIA Ordinance.
In particular, views on the following areas were solicited:
- the comparison
of the processing time for various key steps in the EIA process
before the commencement of the EIA Ordinance with the time required
for applications under the EIA Ordinance;
- the increase
in the level and extent of public involvement in the statutory
EIA process and the time implication on the processing of applications,
when compared with the EIA system before the commencement of
the EIA Ordinance;
- the efficiency
and effectiveness of the operation of the EIA Ordinance and
ways for further improvement;
- the coverage
of the EIA Ordinance;
- the comparison
of the consultation with the Advisory Council on Environment
before and after the implementation of the Ordinance;
- the processing
of the various applications under the EIA Ordinance including
the preparation of project profiles, the issue of EIA study
briefs, the review and approval of EIA reports and the issue
of environmental permits;
- the effectiveness
of prescriptive permit conditions when compared with performance-based
conditions, particularly in relation to fast-track projects
subject to successive rapid changes in the detailed design stage;
and
- whether
there are any tangible benefits to different stakeholders as
a result of the implementation of the EIA Ordinance.
Approaches
in Reviewing the Operation
- The Review
aimed to collect information, feedback and statistics from various
sources in order to provide inputs from various angles and different
stakeholder groups. Every effort has been made to ensure that
the Review was based on the best available and impartial information.
Data and information were collected and views and opinions acquired
in the following forum/steps:
- compilation
of statistics based on the actual applications under the EIA
Ordinance and processing data from the EIA Ordinance Register
Office;
- participation
in public forums/seminars with various stakeholder groups
to obtain their views and direct feedback from over a total
of 200 participants, including the following:
- an
open forum on 10 April 1999 jointly organised by the Hong
Kong Institute of Environmental Impact Assessment and
the Advisory Council on Environment (ACE) EIA Sub-committee
to discuss the EIA process in Hong Kong held at the Chinese
University of Hong Kong;
- a
seminar on 17 April 1999 on Policing Pollution- Application
of Environmental Impact Assessment (EIA) Law in Hong Kong
and China jointly organised by the Hong Kong Environmental
Law Association and the Centre for Chinese and Comparative
Law, School of Law of City University of Hong Kong;
- a
forum on 21 April 1999 organised by EPD involving all
proponent departments and the relevant authorities to
discuss the first year's operation of the EIA Ordinance;
- a
forum on 29 April 1999 involving the various EPD specialist
groups to discuss the first year's operation of the Ordinance;
- presentation
and discussion sessions for all 18 Provisional District Boards
between April and July 1999 to solicit views from PDB members
on the operation of the EIA Ordinance.
-
Appendix A gives a full
list of the meetings and forums organised or attended by
EPD to solicit views for the Review. In addition, the findings
of the review were presented to the Planning, Environment
and Lands Bureau in May 1999 and at an EIA Ordinance seminar
jointly organised by Hong Kong Institute of EIA and EPD
on 11 September 1999.
The Application Statistics in the first 18 months of Operation
-
Appendix B is a Summary
Facts Sheet on the statistics of various EIA Ordinance applications.
Between April 1998 and August 1999, there were a total 145
applications under various categories including applications
for study briefs, permissions to apply an permit direct,
approvals of EIA reports and applications for environmental
permits.
- Designated
projects with a total estimated cost of HK $ 151 billion- including
16 km of roads, 47 km of railway and over 380 ha of development
projects- were successfully processed under the Ordinance and
designed to meet relevant environmental standards and criteria.
So far, the EIA Ordinance has protected about 570,000 people and
more than 51 ha. of environmentally sensitive areas.
- During this
period, there were 27,838 visitors to the dedicated EIA Ordinance
website and there were 1,392 visitors to the EIA Ordinance Register
Office in EPD headquarters. 76 documents were exhibited for the
public to comment.
- Based on
the actual data on the processing time and compared to an independent
government study in 1995 for the previous EIA process, the time
taken for the EIA process has been shortened by at least 3 to
4 months.
General Findings
-
In light of the diverse interests of different stakeholder
groups involved in the EIA process, it is not surprising
that different views were collected. Detailed comments from
members of the Provisional District Boards are summarised
in Appendix C and comments
from other parties attended the various forums are tabulated
in Appendix D. The following
is a summary of the key views and suggestions collected:
- it has
been quite encouraging that many attendees from various stakeholder
groups opined that the spirit of EIA Ordinance is noble and
essential to protect the environment and achieve environmental
sustainability, particularly in the long run;
- the
EIA system in Hong Kong is also seen as one of the pioneers
in the Asian cities and is considered as one of the most efficient
and practical EIA systems when compared with the practices
in Western countries;
- some
attendees and district board members considered that the EIA
Ordinance has facilitated public access to the statutory EIA
process and made the process more transparent compared with
the previous EIA system;
- some
attendees from the private sector were of a view that the
statutory EIA process has a clear statutory time frame that
can facilitate them to better plan their project programme;
- some
attendees pointed out that with the implementation of the
Ordinance, comments from the Advisory Council on Environment
(ACE) were better received and project proponents have taken
into account the environmental issues raised more seriously;
- some
attendees considered that the statutory EIA process is more
transparent and the decision making process more clear when
compared with previous EIA system;
- public
comments during the early project profile stage were considered
useful in avoiding any late focus and any possible delays
during the later EIA report stage, as the project proponents
could address the public comments received at the project
profile stage in the preparation of the EIA reports;
- conditions
in environmental permits are considered effective to bind
proponents to carry out the agreed mitigation measures that
need to be put in place by permit holders and their agents
to prevent environmental problems. However, on the other hand,
some other attendees viewed that permit conditions are sometimes
too prescriptive;
- there
were also other views, specifically from Provisional District
Board members, that public consultation should be further
improved to facilitate more public comments and participation
in the process. The advertising of the availability of project
profiles and EIA reports in newspapers was not considered
adequate. It was suggested that the consultation should go
down to the local level to those being affected;
- many
commented that the dedicated EIA Ordinance Website is very
useful in facilitating public access to and retrieval of information
on various applications, EIA reports and environmental permits.
They also suggested EPD to consider placing the public comments
received on the Website; and
- some
applicants and their consultants considered that with the
publication of the Technical Memorandum on the EIA Process,
environmental criteria and standards are now generally much
more clearer than before. However, there are still rooms for
further improvements to provide more guidance on the criteria
and approaches in the Technical Memorandum and to disseminate
the experiences in the actual applications and interpretation
of the Technical Memorandum.
Continuous Improvement Strategy
-
In response to the views and opinions collected from attendees
of the various review forums, continuous improvement measures
have been developed and are listed in Appendix
D.
The continous
improvement strategy comprises the following key elements:
-
enhance public participation by reaching out to the Provisional
District Boards (PDB) and by directly notifying PDB members
on the availability of project profiles and EIA reports for
public comment. Moreover, project profiles to be submitted
will have to be in both English and Chinese to facilitate
people at local levels to comment;
-
set up a "Cyber EIAO Help Bench" to provide consistent
advice, examples and resource materials through the EIA Ordinance
website to help proponents and consultants on common issues
or enquiries they often encounter during their preparation
of project profiles and EIA reports;
-
publish more guidance notes and other materials on areas of
interest to help the proponents and their consultants;
-
facilitate the public and consultants to know the status of
the various projects and promote the sharing of knowledge
and experiences by setting up "a Cyber EIAO Project Template"
for major projects that have commenced construction;
- promote
communication and experiences sharing by setting up "EIAO
Users Liaison Groups" for both government and private
sector proponents, and "EIAO Practitioners Liaison Group"
for consultants, and work together on developing the "Cyber
EIAO Help Bench";
-
allow public comments via email or through the web site; and
-
set up a web-based interest group so that interested members
of the public can receive information and news on the EIA
Ordinance or any latest guidance notes issued.
|