Agreement No. CE 75/2002
(WS)
EXTENSION OF SIU HO WAN WATER
TREATMENT WORKS - INVESTIGATION
ENVIRONMENTAL IMPACT ASSESSMENT
ENVIRONMENTAL MONITORING &
AUDIT MANUAL
CONTENT
Purpose of the Manual.......................................................................................................... 1-1
Project Description............................................................................................................... 1-2
Environmental Monitoring and Audit Requirements................................................................. 1-3
Project Organisation.............................................................................................................. 1-5
Introduction.......................................................................................................................... 2-1
Air Quality Parameters.......................................................................................................... 2-1
Monitoring Equipment........................................................................................................... 2-1
Monitoring Locations............................................................................................................ 2-2
Baseline Monitoring...............................................................................................................
2-4
Impact Monitoring of
Construction Air Quality Impact........................................................... 2-4
Compliance Assessment........................................................................................................ 2-4
Event and Action Plan (EAP)................................................................................................ 2-5
Mitigation Measures.............................................................................................................. 2-7
Introduction.......................................................................................................................... 3-1
Noise Parameters.................................................................................................................. 3-1
Monitoring Equipment........................................................................................................... 3-1
Monitoring Locations............................................................................................................ 3-1
Baseline Monitoring............................................................................................................... 3-2
Impact Monitoring of Construction Noise.............................................................................. 3-2
Event and Action Plan for Construction Noise........................................................................ 3-3
Mitigation Measures.............................................................................................................. 3-5
Introduction.......................................................................................................................... 4-1
Water Quality Mitigation Measures........................................................................................ 4-1
Introduction.......................................................................................................................... 5-1
Mitigation Measures............................................................................................................... 5-1
Environmental
Monitoring and Audit...................................................................................... 5-2
Introduction.......................................................................................................................... 6-1
Mitigation Measures for Construction and Operation
Phases.................................................. 6-1
Construction and Operation Phases Audit..............................................................................
6-2
Introduction.......................................................................................................................... 7-1
Waste
Control and Mitigation Measures................................................................................ 7-1
Introudction.......................................................................................................................... 8-1
Mitigation Measures..............................................................................................................
8-1
Site Inspection...................................................................................................................... 9-1
Compliance with Legal and Contractual Requirements............................................................ 9-2
Environmental Complaints..................................................................................................... 9-2
General............................................................................................................................... 10-1
Baseline Monitoring Report................................................................................................. 10-1
Monthly EM&A Reports..................................................................................................... 10-2
Quarterly EM&A Summary Reports.................................................................................... 10-7
Final EM&A Review Reports.............................................................................................. 10-8
Data Keeping...................................................................................................................... 10-9
Interim Notifications of Environmental Quality Limit
Exceedances......................................... 10-9
List of Tables
Table 2.1 Air Monitoring Stations during
Construction Phase..................................................
2-3
Table 2.2 Impact Monitoring Programme
(TSP)..................................................................... 2-4
Table 2.3 Proposed Action and Limit Levels
for Impact Monitoring........................................
2-5
Table 2.4 Event / Action Plan for Ambient
Air Quality Monitoring (Construction).................... 2-6
Table 3.1 Noise Monitoring Stations during
Construction Phase.............................................. 3-2
Table 3.2 Action and Limit Levels for
Construction Noise...................................................... 3-3
Table 3.3 Event / Action Plan for
Construction Noise............................................................. 3-4
List of Figures
Figure 1.1
Location Plan – Siu Ho Wan
Figure
1.2 Location Plan – Pui O
Figure 1.3
Preliminary Construction Programme
Figure 1.4
Project Organisation
Figure 2.1
Locations of Air Quality Monitoring
Stations
Figure 3.1
Locations of Noise Monitoring Stations
List of Appendices
Appendix A Implementation Schedule
Appendix B Sample
Data Sheets for Air Quality and Noise Monitoring
Appendix C Sample
Template for the Interim Notification
Abbreviations
A/L
Action and Limit
AQOs Air Quality Objectives
ASRs air sensitive receivers
C&D construction and demolition
DEP Director of Environmental
Protection
EAP
Event and Action Plan
EIA environmental impact assessment
EIAO Environmental Impact Assessment
Ordinance
EIAO-TM Technical Memorandum on
Environmental Impact Assessment Process
EM&A environmental monitoring and
audit
EPD Environmental
Protection Department
ER Engineer’s
Representative
ET Environmental
Team
HOKLAS Hong
Kong Laboratory Accreditation Scheme
HVS high
volume sampler
IC(E) Independent
Checker (Environment)
NCO Noise
Control Ordinance
NSRs noise
sensitive receivers
QA/QC quality
assurance / quality control
TSP total suspended particulates
USEPA United States Environmental
Protection Agency
WBTC Works Bureau Technical Circular