2                                            Consideration of Alternatives

In accordance with Clause 3.3 of the EIA Study Brief (ESB-208/2009), the following section presents a consideration of the alternatives for the Project.  The section has been divided into a discussion of the following:

·            Consideration of Alternative GRS Locations;

·            Consideration of Alternative Construction Methods for the Reclamation;

·            Consideration of Alternative Installation Techniques for the Submarine Gas Pipelines; and

·            Consideration of Works Sequences.

Based on the above considerations, the Environmental Impact Assessment (EIA) of the preferred scenario is presented in subsequent sections.

2.1                                      Consideration of Alternative GRS Locations

This section presents considerations of the potential locations of the GRSs that have been assessed as part of this Project.  It represents the outcomes of a preliminary screening study undertaken by CAPCO to investigate the engineering and technical feasibility of constructing and operating a GRS at selected potential locations.  The assessment considers both the benefits / difficulties of the construction and operation of the GRS as well as some of the associated potential environmental impacts.

2.1.1                                Potential Locations

Four potential locations of the GRS were considered in CAPCO’s preliminary screening study:

·            Site A on the western side of the West Ash Lagoon;

·            Site B on a reclamation adjacent to the existing GRS compound at BPPS;

·            Site C on an area east of the existing GRS;

·            Site D within the existing GRS compound at BPPS.

Locations of these sites are depicted in Figure 2.1.  A summary description of each location is provided in Table 2.1.

 

Table 2.1        Description of Potential GRS Locations

Potential Location

Description

Site A

Site A comprises a strip of the western side of the West Ash Lagoon, which is near the existing GRS and presently accessible from the power station site via the GRS eastern boundary road.  The main vehicular access is via Lung Kwu Tan road, which also provides access to the WENT Landfill site.

Site B

Site B comprises a new reclamation adjacent to the existing GRS that would be an extension of the existing reclamation on which the existing GRS stands.  The site is presently accessible via the existing power station Seawall Road as well as the GRS eastern boundary road.  Two options (B1 & B2) based on the different locations of the reclamation were considered.

Site C

Site C comprises an area at the north eastern end of the existing GRS that would be an extension of the existing compound on which the existing GRS stands.  Much of the site area is presently natural hillside that would have to be cut to create a flat area for the GRS.  The site is presently accessible via the existing power station Seawall Road as well as the GRS eastern boundary road.  It should be noted that the existing power cables that supply electricity to Shekou cross the proposed site area and that a small portion of the existing GRS compound would have to be utilised to form the new site.

Site D

The existing GRS features three areas that do not presently have any equipment or piping installed.  Additionally, the slug catcher is redundant and could be removed, creating more space area on the south side of the pipe rack.  Work previously done for the HKLNG project showed there is sufficient space for one additional pipeline terminal and GRS.  The site is presently accessible from the power station site via the existing power station Seawall Road as well as the GRS eastern boundary road.

 

2.1.2                                Evaluation Criteria

The evaluation criteria adopted in the preliminary screening study of GRS locations included:

·            Site location: consideration is given to factors including pipeline shore crossing, fuel gas header route, constructability, operability and impact on existing operations;

·            Available space for GRS facilities;

·            GRS facilities layout options and flexibility;

·            Capacity for future expansion; and

·            Potential concerns/ constraints, such as safety, risk and health issues, environmental issues, financial impact, schedule impact and commercial/ regulatory concerns, etc.

2.1.3                                Evaluation Outcome

Evaluation outcomes are summarised in Annex 2A-1.  The preliminary screening study indicated the following key issues:

·            Site A is not preferred due to uncertainties in land acquisition and permitting / gazettal issues hence insurmountable schedule impact: the construction of a GRS at this site will involve the decommissioning of the West Ash Lagoon (or part thereof) which in itself is a Designated Project under the EIAO and will require an EIA of extensive scope.  Inclusion of such assessment in the present EIA is anticipated to lead to a delay of at least 12 months, which cannot be accommodated in the target schedule of replacement gas supply in 2012.  In addition, it is known that the HKSAR Government wishes to resume the land occupied by the West Ash Lagoon for use by the West New Territories (WENT) Landfill Extensions project.  Given such conflict in potential land-use, it is expected that land acquisition would be a very complex process with significant schedule implications.

·            Site C is not preferred due to the need for vegetation and slope cutting for site formation: this site is presently on undeveloped land and the construction of a GRS at this site will involve the need to conduct an environmental assessment covering different technical issues to this EIA, e.g. one that considers aspects such as terrestrial ecology, land excavation and associated waste management.  Acquisition of the land could be a complex process because of its current natural state.  Also site formation would necessitate clearance of all vegetation and aggressive slope cutting, which are less favourable from an environmental perspective and cannot be accommodated in the target schedule of replacement gas supply in 2012.

Sites D and B therefore represent the preferred options.  Given the space requirement of two proposed GRSs, none of these two sites is ideal for accommodating both GRSs, and thus it is recommended to accommodate one GRS at each site.  This would also reduce the extent of seabed reclamation at Site B to the maximum practicable extent since only one GRS will be located on newly reclaimed land.

Of the two options under Site B, Site B1 is preferred over Site B2 since it is situated exactly on the location proposed in the HKLNG EIA ([1]) for which an Environmental Permit has already been granted and hence may represent few potential uncertainties (i.e. from an environmental, engineering and permitting perspective).

 

Sites D and B1 are thus regarded as the preferred scenario for locating the GRSs in this EIA.

2.2                                      Consideration of Alternative Construction Methods for the Reclamation Works

In accordance with Clause 3.3.1 of the EIA Study Brief (ESB-208/2009), this section presents the consideration of alternative construction methods for the reclamation required for one of the GRS.

The assessment has been conducted to investigate potential methods and plant for the construction of the proposed reclamation.  The objective of the assessment is to identify the preferred alternative to avoid the likelihood of unacceptable adverse environmental impacts.

On the basis of these requirements, the following alternative methods have been considered for the construction of key facilities:

·            Reclamation: no-reclamation alternative and partially- vs fully-dredged method; and

·            Seawalls: dredged (with vertical vs sloping seawall) and non-dredged methods.

Regarding the onsite GRS facilities since they are highly specialised and will be constructed to best industry standard, alternatives for construction will not be discussed.

2.2.1                                No–reclamation Alternative

The no-reclamation alternative for the GRS site, i.e. piling, is discussed in Box 1.  Piling is considered as a potential option to form new land as the platform area for the GRS.  There is a lack of precedence in Hong Kong for gas installations on piled deck structures.  Also, there are potential safety concerns with the piled deck structure.  These issues would require further detailed investigation and it cannot be confirmed at this stage that this option is feasible.

Consequently, this alternative is not considered further in the remainder of this Report.

 

Box 1              Formation of New Platform Area for GRS – the Piling Option

Consideration

Piling to create a decked structure – Details

Environmental

Unmitigated piling activities produce elevated underwater sound levels which may affect Chinese White Dolphins.  Mitigation measures such as the use of bubble curtains / bubble jackets and seasonal work closure periods may be expected to be required pending further analysis.

There would be potential aesthetic concerns of a high profile visual structure.

 

Engineering

The GRS facility may be supported on a deck structure founded on a large number of piles socketted into bed rock.  It will involve a significantly large number of piles (assuming that about 80 nos. of piles are required at 8x8m grid over the proposed 50m x100m area).  A key constraint is that the soffit of the deck structure will need to be placed a few metres above the highest tide level resulting in the GRS facilities at least 5-10m above the adjacent ground level.

 

Safety

Piled structure poses potential safety concerns for gas installations due to ground movement or accidental collision by marine traffic.

 

Schedule

The piling works for the decked structure could take up to 10 months and mitigation measures such as no piling during peak calving season for dolphins could significantly delay the replacement gas schedule in 2012 (assuming construction at 1 pile/week by 2 rigs).

 

Conclusion

Potentially feasible option with further detailed investigation required.

 

 

2.2.2                                Reclamation

A small-scale reclamation will be required to form new land as the platform area for the GRS.  One of the methods to construct the reclamation area is to dredge away all soft seabed materials beneath the seawall and under the entire reclamation area.  This option is referred to as a ‘Fully-dredged Construction Method’.

Recently in Hong Kong there has been an increasing reliance on only dredging soft mud from beneath the seawall and to leave the soft mud under the proposed reclamation area.  This option is referred to as ‘Partially-dredged Construction Method’.  According to the Practice Note for Authorized Persons and Registered Structural Engineers (PNAP) No. 252 issued by the Buildings Department, project proponents must plan projects on the assumption of keeping the mud in place, and time for consolidation and consequential programme constraints shall be allowed for in programming.  In line with local construction practice, the Partially-dredged Method will be adopted for this Project.

 

The partially-dredged method is regarded as the preferred method for the construction of the reclamation to accommodate one GRS.

2.2.3                                Seawalls

Permanent vertical seawalls will be constructed around the seaward boundaries of the proposed reclamation to protect it from wave and tidal action.  Vertical seawalls are preferred over sloping seawalls as they involve a smaller environmental footprint for the marine works area (a reduction of 0.38 ha, Table 2.2).  As a consequence of the small footprint less dredging will be required (a reduction of about 26,000 m3, Table 2.2) which will consequently have benefits in reducing the scale of potential waste management, water quality and marine ecological impacts.  The total length of vertical seawalls to be built along the reclamation is approximately 200 m.

Table 2.2        Comparison of Dredging and Filling Requirements for Vertical and Sloping Seawalls

 

Vertical Seawall

Sloping Seawall

Reclamation Area

0.5 ha

0.5 ha

Affected Seabed Footprint Area

1.35 ha

1.73 ha

Dredging of Marine Mud (Bulk Volume)

0.156 Mm3

0.182 Mm3

Total Fill Required

0.170 Mm3

0.222 Mm3

 

The design of the seawall should achieve a minimum Factor of Safety to ensure stability against slope failure and provide adequate bearing capacity to support the seawall without significant settlement.  Both dredged and non-dredged options with ground improvement methods have been considered.

A dredged method, i.e. removal of the soft material beneath the seawall, will ensure the stability requirement is met without significant settlement.  However, in order to minimise dredging of marine deposit, the feasibility of non-dredged option with ground improvement measure for the seawall was considered.  Ground improvement measures such as the use of vertical band drains and surcharge were considered to be inadequate as they cannot improve the shear strength of marine deposits to ensure the seawall stability.  A preliminary investigation of alternative ground improvement methods has been conducted and presented below.

The first alternative makes use of Sand Compaction Pile (SCP) as the seawall foundation.  SCP is considered to be one of the effective ground improvement methods for seawall structure on the soft marine deposit.  This is because SCP can increase the shear strength of ground by installing well compacted sand piles in the ground and stabilises the seawall structure.  There is, however, a lack of track record in the application of SCP in Hong Kong, although the use of SCP as the seawall foundation has been adopted in reclamation projects in Japan and Korea.  A full-scale trial may be required to establish the viability of SCP prior to its adoption in Hong Kong.

An important issue of SCP is the up-heaving of seabed after installation of SCP.  In shallow waters, the up-heaved seabed may affect the operation of the SCP barges as well as other vessels.  With the consideration of up-heaving, the seabed level should be -6 mPD or below to allow adequate water depth to ensure the proper operation of SCP barge without being affected by the up-heaving of the seabed.  However, within the proposed reclamation seabed level varies between -2 mPD to -5 mPD which is not sufficient to operate SCP barge.  Also given the seawall length is relatively short, the overall cost-effectiveness for the use of SCP is considered to be low.  With the above constraints, SCP is not considered a feasible option.

The second alternative makes use of ground improvement technique, such as Deep Cement Mixing (DCM), to enhance the strength of the marine deposits before filling up for the seawall.  In DCM, the soft soil is mixed in situ with an appropriate additive, typically cement or lime, using an auger or other mixing device.  No spoil removal is required.  A similar technique called Deep Cement Method has been developed in Japan, using cement slurry.  Previous studies have investigated the use of cement stabilization work as part of the ground improvement method, however, these have only been performed on the bench-scale test but such technology has not been taken forward on site with pilot trial ([2]).  The efficiency and cost-effectiveness of the improvement method has not been tested and as such it is not possible to assess the environmental and safety impact attached to this alternative.  The use of Deep Cement Mixing is, therefore, not the preferred construction alternative for the present Study.

The third alternative requires a long counter fill on the seaward side of the seawall to provide toe stability against slip failure during construction.  The use of this method is, however, considered to be unsuitable for this Project as it is likely to lead to significant ongoing settlement of the seawall after the GRS is in operation.

On the basis of the above, none of the alternative methods is preferred over the conventional method of dredging beneath the seawall.

 

The conventional method of carrying out dredging of the marine deposits before filling up for the seawall is recommended as the preferred method for the construction of the seawalls for the GRS reclamation.

 

2.3                                      Consideration of Alternative Installation Techniques for the Submarine Gas Pipelines

The two proposed submarine pipelines will be installed in two separate seabed trenches to the necessary burial depths.  Installation of the submarine pipelines would involve either pre-trenching (i.e. dredging a trench and then laying the pipeline in the trench) or post-trenching (i.e. direct lay and burial of the pipeline typically using a jetting machine).  The alternatives considered for installation of the submarine gas pipelines are:

·           Grab dredging;

·           Trailing suction hopper dredger (TSHD) dredging; and

·           Jetting.

Other non-dredged alternatives for submarine pipeline installation are discussed in Box 2.  These alternatives are not considered as viable options for this Project due to the potential engineering or schedule constraints and are thus not considered further in the remainder of this Report.


Box 2              Other Non-dredged Alternatives for Installation of Submarine Gas Pipelines

Consideration

Ploughing

Horizontal Directional Drilling (HDD)

Engineering

Feasibility of ploughing will depend on sediment characteristics and seabed stability/ conditions, since the plough (machine) is a very heavy mechanical object and is not suitable for unstable seabed.  In particular ploughing is not suitable for soft marine clay found in the Project Area, since the plough sinks into the mud and the trench cannot be maintained open as the plough usually cuts a steeper slope.  Ploughing cannot provide sufficient depth for pipeline burial for armour rock protection, and there does not seem to be any precedence of the use of ploughing for trenching to a depth of 3 m.

 

Sea to Sea HDD is an extremely high technology with high risk.  Feasibility will be determined by sediment and geotechnical characteristics.  The soft marine clay seabed of the Project Area may not be suitable as it will be very difficult to maintain an open hole.  Failure caused of the HDD due to drill hole collapse may cause the loss of the entire pipe string.  In addition, the pipeline size with large diameter (> = 32”) will make this HDD operation extremely difficult, and the distance for which the HDD can construct/ operate is quite short (~ 2 km).  Also future pipeline repair or inspection will be impossible.  HDD cannot be adopted solely for the shore end with a subsea tie in as the geotechnical conditions at the BPPS landfall do not appear to be suitable.  A temporary reclamation would be required to allow access for the HDD rig due to space constraints at BPPS.

 

Environmental

A non-dredged option which does not generate dredged material. The spread of suspended sediment generated by the plough is expected to be less than for the jetting machine.  Compliance with WQO would need to be demonstrated.  Safety concerns may be the overriding issue as the pipeline may not be able to be ploughed to the required safe depth.

 

A non-dredged option which does not generate dredged material.  Water quality impacts are also expected to be minimal.  However spoil from drilling will need to be disposed of which lead to potential waste management concern.

Schedule

Similar to the working rate of a jetting machine.  However a full-scale trial and detailed site survey will be required to establish its engineering and environmental viability prior to its adoption in Hong Kong, which will lead to significant schedule delay beyond the current plan for replacement gas by 2012.

 

A full-scale trial and detailed site survey will be required to establish its engineering and environmental viability prior to its adoption in Hong Kong, which will lead to significant schedule delay beyond the current plan for replacement gas by 2012.

Conclusion

Not considered as a feasible option

 

Not considered as a feasible option

 

 

Dredging will be employed at the landing sites of the pipelines, due to the proximity of these locations to the shoreline requiring accurate removal of potential marine muds and rock fill.  In addition, dredging and backfilling with a combination of gravel and rock armour will be required when the pipelines cross fairways and other specific locations in order to provide adequate protection from third party damage.

There are two common dredging plants that are employed for the removal of marine sediments in Hong Kong.  These are grab dredgers or trailing suction hopper dredgers (TSHD).  Each plant would be available as alternatives for the construction of the pipeline trenches.  The potential environmental benefits and dis-benefits of each are discussed below.

Alternatively, along the pipeline routes, there is the potential to employ jetting in order to trench these facilities to the required depths.  A description of the jetting method is also presented below.

2.3.1                                Grab Dredgers

A grab dredger comprises a rectangular pontoon on which is mounted a revolving crane equipped with a grab.  The dredging operation consists of lowering the grab to the bottom, closing the grab, raising the filled grab to the surface and discharging the contents into a barge.  Grab dredgers are usually held in position while working by anchors and moorings but some have a spud or pile, which can be dropped onto the bottom while the dredger is operating.

Grab dredgers may release sediment into suspension by the following mechanisms:

·           Impact of the grab on the seabed as it is lowered;

·           Washing of sediment off the outside of the grab as it is raised through the water column and when it is lowered again after being emptied;

·           Leakage of water from the grab as it is hauled above the water surface;

·           Spillage of sediment from over-full grabs;

·           Loss from grabs which cannot be fully closed due to the presence of debris;

·           Release by splashing when loading barges by careless, inaccurate methods;

·           Disturbance of the seabed as the closed grab is removed.

During the transport of dredged materials, sediment may be lost through leakage from barges.  However, dredging permits in Hong Kong include requirements that barges used for the transport of dredging materials shall have bottom-doors that are properly maintained and have tight-fitting seals in order to prevent leakage.

Sediment is also lost to the water column when discharging material at disposal sites.  The amount that is lost depends on a large number of factors including material characteristics, the speed and manner in which it is discharged from the vessel, and the characteristics of the disposal sites.

2.3.2                                Trailing Suction Hopper Dredgers

A Trailing Suction Hopper Dredger (TSHD) is designed to use a suction mouth at the end of a long tremie pipe.  As the barge moves, the suction hopper trails along and sucks up the soft seabed sediments.  During dredging the drag head will sink below the level of the surrounding seabed and the seabed sediments will be extracted from the base of the trench formed by the passage of the drag head. 

The main source of sediment release is the bulldozing effect of the drag head when it is immersed in the mud.  This mechanism means that sediment is generally lost to suspension very close to the level of the surrounding seabed.  Due to the relatively large volumes of material removed during dredging the instantaneous loss of sediment during dredging (in terms of kg per second) can be higher than grab dredging even though the net total amount of mud lost to suspension over an entire dredging programme is lower than more conventional methods.

During dredging marine sediments are pumped into the vessel’s hopper.  Once the hopper is loaded the dredging operation will be stopped and the vessel will sail to a designated disposal area.  A TSHD is usually positioned by dynamic positioning, thus they have no anchor wires.  In comparison to grab dredgers, TSHDs generally have a higher production rate.

2.3.3                                Jetting

The jetting machine will either be self-propelled or be towed by barge.  The self-propelled machine has wheels resting on the pipeline and uses the pipe for traction.  Stability is achieved with the use of buoyancy aids.  A ‘Non-conventional’ jetting machine may be utilised, as it does not use air to assist with discharge of the sediment.  This results in less adverse effect on the water quality of the surrounding areas.

From the soil data, a nozzle configuration that best suits the in situ soil characteristics will be determined.  The method is based on fluidising the muds allowing the pipe to sink to the chosen depth.

During the installation of the submarine utilities using jetting technology, it would be expected that seabed sediment would be released close to the seabed and will settle out relatively quickly.  The sediment would, therefore, only be in suspension for a short period of time and as such, the potential for impacts to occur, such as through the exertion of the oxygen demand on the receiving waters, will be limited.

The significant environmental advantage of the use of jetting in pipeline installation works is that the method avoids the need to remove material from the seabed and therefore avoids the need for off-site disposal.

2.3.4                                Consideration of Installation Technique

An evaluation of the three techniques presented above was undertaken to evaluate their engineering feasibility, schedule implications and overall environmental performance, in particular their environmental acceptability in terms of dredged material management and water quality impacts.  Outcomes of the evaluation are presented below.

Environmental Considerations

The impact on water quality for grab dredging, TSHD dredging and jetting options was examined for the northwestern waters in Hong Kong as part of this EIA Study.  Modelling results demonstrated that, under the working rate and working programme assumptions (detailed in Section 6 and Annexes 6A and 6I), all three methods did not result in any exceedance of the Water Quality Objectives (WQOs) at sensitive receivers.  The spread of suspended sediment generated by a jetting machine or a TSHD was, however, predicted to extend further and would be more concentrated than that generated by grab dredgers (for details see Annex 6I).  Therefore, in terms of potential water quality impacts, all three methods are considered to be acceptable on the grounds that they all meet the relevant assessment criteria.

As for the potential impact on dredged material management, unlike grab or TSHD dredging, the jetting machine does not generate any mud requiring offsite disposal.  It is important to recognise that existing capacity for contaminated sediment disposal is very limited.  A reduction of dredged material arisings is seen as highly advantageous to both the project and to the Government’s management of the limited capacity for contaminated mud disposal.  The potential merit of the jetting method is thus considered as critical to the overall environmental acceptability of this Project.

Engineering Considerations

Along the shore approach and some sections of the proposed pipeline alignment, the water depths are too shallow (sometimes as shallow as -3 mPD only) to utilise a TSHD which typically has a draft of at least 5 m.  For the section of pipelines in deeper waters, i.e. along Urmston Road at about -15 mPD, it is considered possible to use TSHD, though the cost-effectiveness and practicality of utilising a TSHD just for this short section (less than 1.8 km) is low ([3]).

In contrast, the use of the jetting method along the Urmston Road pipeline section which requires the most intensive protection from large anchor drop and drag is not considered feasible from an engineering point of view.  This is because a jetted pipeline trench with armour rock protection reaching only the seabed level cannot offer sufficient level of protection from the risk of large anchor drop/ drag ([4]).  The engineering feasibility for using jetting in other pipeline sections has been investigated and confirmed to be viable.

Grab dredging is widely adopted for pipeline pre-trenching in Hong Kong and no engineering constraints are expected should this method be used.

Schedule Considerations

Trenching by a jetting machine offers a schedule benefit as the working rate by a jetting machine is much higher than that of a grab dredger, thus allowing the works to be completed in a shorter timeframe.  Dredging by a TSHD also presents similar schedule benefits since the dredging speed is also higher than that of a grab dredger.  Overall, when the same daily working time is considered, grab dredging will result in the longest construction programme among the three proposed methods but is acceptable to the project schedule.

Summary of Key Considerations

·            A reduction of dredged material arisings is paramount to the overall environmental acceptability of this Project, hence the use of jetting is preferred and the majority of the pipeline route is planned to be installed by jetting.  An added benefit is that the pipeline installation works may be completed in a shorter timeframe than using grab dredging only.

·            Due to insurmountable engineering constraints the Urmston Road Crossing pipeline section cannot be installed by jetting and this pipeline section will be installed by dredging method.

·            For dredging methods, whilst it is considered that grab dredging and dredging by a TSHD would offer similar overall environmental performance and acceptability, grab dredging will have a higher cost-effectiveness than dredging by a TSHD.  Therefore grab dredging is the preferred method for pipeline installation along the Shore Approach and Urmston Road Crossing pipeline section.

 

Taking the above into consideration it was concluded that although from an environmental perspective all three options appear to be suitable, grab dredging and the jetting method were considered to be the more practicable options.

2.4                                      Consideration of Works Sequences

The EIAO-TM specifies the priorities for addressing impacts is avoidance and minimization.  This philosophy was referred to in designing the marine works construction programme by reducing the overall duration of marine works.  This has been seen by leading local marine mammal specialists (Würsig, Jefferson, Hung pers comm.) as the most effective approach to reduce impacts on marine mammals.

Dredging works in Hong Kong typically take place during daylight hours and the same approach will be adopted for this Project.  However, because of marine traffic constraints and navigation safety concern, dredgers may need to operate 24 hours on the pipeline section which crosses the Urmston Road channel off Black Point enabling completion in the shortest possible time.  This scheduling measure will be adopted for the Urmston Road Crossing pipeline section.

In order to achieve the master construction programme for the Project all other activities associated with the pipeline installation, i.e. pipe-laying and the placement of armour rock protection will operate over 24 hour periods and throughout the year.  Neither of these works activities cause adverse impacts to the marine environment as discussed in Section 3.3.4.

In addition to the above the Project is planned to be conducted in two phases: the First Phase for one pipeline and the co-located GRS and the Second Phase for the other pipeline plus the GRS on reclamation.  The phasing is discussed in further detail in Section 3.  Such a Phased Construction approach is a result of an optimisation of the Project’s implementation schedule to resolve potential concerns regarding dredged material management.

2.5                                      Selection of Preferred Scenario

For the GRS location the preferred scenario/alternative to be taken forward to the EIA stage is Site D (Co-located GRS) with Site B1 (GRS on B1 Reclamation) Layout.  Full details of the components of the preferred scenario are detailed in Section 3 of this EIA Report.

The preferred construction method of the GRS reclamation to be taken forward is the partially-dredged method, while for the submarine gas pipelines the installation methods to be considered are grab dredging and jetting in Hong Kong waters.  The selection of the preferred scenario and construction method has brought about a series of environmental benefits to the Project, including:

·            The use of jetting for certain sections of the pipelines alignment will reduce the volumes of dredged material substantially from 0.428 Mm3 to 0.253 Mm3 (bulk volume) per pipeline;

·            The adoption of jetting will shorten the period for marine construction works and hence reduce the severity of impacts to marine ecological resources;

·            A reduction in the seabed areal extent of the reclamation, as one of the new GRSs will be located on existing land within BPPS;

·            Avoidance of potential impacts on terrestrial ecology as vegetation clearance and slope cutting is avoided;

·            A reduction in the seabed footprint area by 0.38 ha through the use of vertical instead of sloping seawall for the reclamation, hence reducing the dredging volumes by about 26,000 m3; and

·            A reduction in dredging volumes through siting one GRS on existing land and through selection of reclamation design and construction methodology, hence reducing off site impacts during disposal of dredged muds.



([1])     ERM (2006) Liquefied Natural Gas (LNG) Receiving Terminal and Associated Facilities. EIA Report (EIA-125/2006). Prepared for CAPCO

([2])     Aas, PM & Engen A (1993) Hong Kong Seawall Design Study.  GEO Report No. 31. Geotechnical Engineering Office, Civil Engineering and Development Department, Hong Kong SAR Government.

([3])         There are no TSHDs based in Hong Kong and the plant would need to be imported from overseas.

([4])         Protection from anchor drop and drag can be achieved using a combination of burial depth and rock armour.  A deeper burial depth can be used in place of the rock armour to position the pipe below the normal dragging depth of the anchors.  Along the Urmston Road pipeline section, options for protection of a jetted pipeline include: (a) deep burial (e.g. to -10 to -12m) below existing seabed level where the larger anchors cannot reach, which is not feasible with existing jetting technology; or (b) provision of a fit-for-purpose rock armour berm, which may protrude above the seabed and is compromised by the fluidized state of the mud.  On the basis of these, jetting is considered to be not feasible for the Urmston Road Crossing pipeline section.