2                    Project DESCRIPTIONS

2.1                Purpose, Objective and Benefits of the Project

2.1.1            The purpose and objective of the Project are to widen individual road sections of the existing TWR and construct slip road to relieve the existing traffic congestion and cope with the anticipated future traffic demand.

2.1.2            The anticipated improvement of the traffic performance (i.e. relieving potential traffic congestion, smoother traffic flow, etc.) at individual sections of TWR brought about by the Project will alleviate the air quality and noise impacts associated with traffic congestion during peak hours.  While potential noise impact on individual noise sensitive receivers due to the proposed road widening works has been identified, corresponding noise mitigation measures such as noise barriers, noise enclosures and low noise road surfacing will be provided under the Project.  Relevant noise impact assessments, the extent and locations of the proposed noise mitigation measures and their mitigation effect of the noise impacts are outlined in Section 4 of the EIA Report.

2.2                The Need of the Project

Existing Traffic Condition

2.2.1            TWR is an expressway connecting Kwai Chung Road (KCR) and Tuen Mun Road (TMR).  TWR provides traffic connection to Tsing Yi through the key junctions at Tsuen Tsing Interchange and Kwai Tsing Interchange, and traffic connection to the road networks of Tsuen Wan and Kwai Chung districts through the slip roads and interchanges along the expressway. Slow-moving traffic, or even worse, traffic congestion during morning peak hours at individual road sections of this expressway were observed from the traffic survey conducted in 2019.

Scenario “without” Project

2.2.2            Without the implementation of the Project, further traffic congestion is anticipated in 2036 and beyond at the individual road sections concerned at TWR.

Scenario “with” Project

2.2.3            With the implementation of the Project, the road capacity at individual road sections of TWR will be increased and thus alleviate the anticipated traffic congestion at these road sections.

2.3                Location and Scope of the Project

2.3.1            The location of the Project is shown in Figure 2.1. The scope of the Project mainly comprises:

(i)        Widening of a section of an elevated carriageway of TWR between Tai Ho Road and Wing Shun Street, from a three-lane carriageway to a four-lane carriageway on Kowloon bound;

(ii)       Widening of a section of an elevated carriageway of TWR between Wing Shun Street and Wing Kei Road, from a dual two-lane carriageway to a dual three-lane carriageway;

(iii)      Widening of a section of an at-grade carriageway of TWR between Wing Kei Road and Kwai Tsing Interchange (KTI), from a dual three-lane carriageway to a dual five-lane carriageway;

(iv)      Widening of a section of an elevated carriageway of TWR between KTI and Container Port Road, from a three-lane carriageway to a four-lane carriageway on Kowloon bound (its implementation is yet to be ascertained and subject to further traffic review);

(v)       Construction of a slip road connecting TWR (Kowloon bound) to Tsing Tsuen Road (Slip Road C) (its implementation is yet to be ascertained and subject to further traffic review);

(vi)      Construction of a slip road connecting TWR (Tuen Mun bound) and Hoi Hing Road (Slip Road E);

(vii)     Provision of noise mitigation measures including noise barriers/enclosures and low noise surfacing materials on associated road sections of Tsuen Wan Road; and

(viii)    Ancillary works including geotechnical, drainage, waterworks, lighting, landscaping works, installation of traffic aid facilities, etc.

2.4                Considerations of Alternative Options and Selection of Preferred Scheme

2.4.1            Detailed investigation on the possibilities of different alternative options, including Tunnel Scheme and Viaduct Scheme, have been conducted. They are brought together with the Initial Scheme for evaluation of the Preferred Scheme of the Project.

2.4.2            Details of each scheme are presented as follows.

2.4.3            Initial Scheme

The alignment and lane configuration of the Initial Scheme mainly comprises:

(i)            TWR between TMR and Tai Chung Road Interchange (TCRI) – two additional 1-lane viaducts on both bounds;

(ii)           TWR between TCRI and Tsuen Tsing Interchange (TTI) – two additional 2-lane viaducts on both bounds;

(iii)          TWR between Tsuen Tsing Interchange (TTI) and KTI – widen from dual 3-lane to dual 5-lane;

(iv)          Four 1-lane slip roads to connect the widened TWR structures to Texaco Road (eastbound) (Slip Road A), Ma Tai Pa Road (Slip Road B) and Hoi Hing Road (Slip Road D and E); and

(v)           One 1-lane slip road to provide direct access from Tsing Tsuen Road (Tsuen Wan bound) to TWR (Kowloon bound) near KCR (Slip Road C).

The layout and typical sections of the Initial Scheme are shown in Figure 2.2.1, Figure 2.2.2, Figure 2.2.3, Figure 2.2.4, Figure 2.2.5 and Figure 2.2.6.

As the Initial Scheme was formulated more than ten years ago, the clearance between kerbline and the structure erected on the parapet allowed in the design could not meet the requirement of the latest design manual. Currently, the Structures Design Manual for Highways and Railway has imposed a more stringent working width requirement of 800mm from kerbline or profile barrier edge to obstacle (e.g. noise barrier post, sign gantry post, etc.) to avoid vehicular impact to the structure erected on the parapet. The aforesaid clearance was thus increased in the Initial Scheme with a view to fulfilling the prevailing design requirement.  However, incorporation of the prevailing clearance requirement in the design would render the Initial Scheme technically infeasible due to potential conflict with existing buildings at some locations alongside TWR.

2.4.4            Tunnel Scheme

The alignment and lane configuration of the Tunnel Scheme mainly comprises:

(i)            Between TMR and TWR near KTI – dual 2-lane tunnel connecting TMR and TWR near KTI via Yeung Uk Road with no intermediate entry or exit ramps;

(ii)           TWR between KTI and KCR – widen from dual 3-lane to dual 4-lane on both bounds; and

(iii)          One 1-lane slip road to provide direct access from TTI (Kowloon bound) to TWR (Kowloon bound) near KTI (Slip Road C)

The layout of the Tunnel Scheme is shown in Figure 2.3.

This option is an approximately 3.95km dual 2-lane tunnel scheme connecting TMR and TWR near KTI via Yeung Uk Road with no intermediate entry or exit ramps. This option will make use of Kwai Fuk Road corridor, which is constrained by CITIC Telecom Tower and PCCW Kwai Shing Telephone Exchange, and enter Yeung Uk Road.

Two ventilation buildings with approximate 2000m2 site coverage each are required and proposed to be situated next to TMR (Kowloon bound) at Chai Wan Kok, and next to Wing Kei Road near Kerry Cargo Centre, to avoid resumption of private land. Provision of vehicular access will be required to each ventilation building.

Climbing lanes, of approximately 0.5km and 1km long, at 8% gradient (absolute maximum) are required at both ends of the tunnel due to the large level difference between the tunnel and the connecting TWR/TMR. This arrangement is undesirable from traffic and vehicle emission perspectives when vehicles are running along the long climbing lanes with steep gradient.  According to the respective requirement in the Transport Planning and Design Manual (TPDM), a desirable maximum gradient of 4% should be adopted for new roads with a design speed of 80km/h or above. Given no intermediate entry/exit ramps under Tunnel Scheme, the Scheme would be limited with low traffic connectivity with TWR and Tsuen Wan district. The proposed tunnel alignment would also encroach significantly into the planned industrial sites at Kwai Hei Street and hence would result in loss of industrial site in Tsuen Wan.  In general, Tunnel Scheme was not preferable taking into account the above undesirable factors.

2.4.5            Viaduct Scheme

This option is to widen individual sections of the existing TWR at both bounds to address the forecast traffic flow at the road sections concerned. The widening works are to be carried out by utilizing the available space such as the existing roadside verge and the space of the existing 4m gap between the bridge structures of Tuen Mun bound and Kowloon bound.   No private land resumption is involved. The layout and typical sections of the Viaduct Scheme are shown in Figure 2.4, Figure 2.4.1, Figure 2.4.2, Figure 2.4.3, Figure 2.4.4, Figure 2.4.5, Figure 2.4.6, Figure 2.4.7, Figure 2.4.8, Figure 2.4.9 and Figure 2.4.10.

Throughout the evaluation process of the scheme options for the Project, all environmental considerations including air quality, noise, waste management, landfill gas hazard, landscape and visual and cultural heritage during construction and operation phases have been thoroughly reviewed and evaluated.  Apart from the environmental considerations, other engineering aspects such as traffic, land requirement, buildability, key interface with other development projects as well as public perception, construction time and cost, and maintenance requirements have also been taken into consideration. 

Taking into account the environmental considerations and engineering aspects, Viaduct Scheme was pursued as the Preferred Scheme.

2.5                Key Design Elements

2.5.1            Road Section between Tai Ho Road to Wing Shun Street

This section of TWR is in the form of viaduct structure and is to be widened to provide one additional lane at Kowloon bound, through utilising the space of the existing 4m gap between the bridge structure of Tuen Mun bound and Kowloon bound to provide the required space for the additional lane.

2.5.2            Road Section between Wing Shun Street and Wing Kei Road

This section of TWR is in the form of viaduct structure and is to be widened from dual 2-lane to dual 3-lane, through constructing new viaduct structures at the side of the TWR (Kowloon bound) to provide the required space for the additional lanes.  

2.5.3            Road Section between Wing Kei Road and KTI

This section of TWR is mainly in the form of at-grade road and is to be widened from dual 3-lane to dual 5-lane, mainly through utilising the space of the existing roadside verge to provide the required space for the additional lanes.

2.5.4            Road Section between KTI to Container Port Road (i.e. a potential item as its implementation is yet to be ascertained and subject to further traffic review)

This section of TWR is in the form of viaduct structure and is to be widened to provide one additional lane on Kowloon bound. 

HyD is implementing a road improvement project, i.e. “Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road project”, at the immediate downstream of this road section.  It is anticipated that the aforesaid road improvement project may also bring along traffic improvement to the adjoining road section. In this regard, the implementation of the proposed road widening of this TWR section (from KTI to Container Port Road) will not proceed subject to confirmation on its satisfactory traffic performance in a traffic review to be conducted upon completion of the “Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road project” in 2025/26 tentatively.

2.5.5            Slip Road C (i.e. a potential item as its implementation is yet to be ascertained and subject to further traffic review)

Slip Road C (SRC) is a proposed single lane vehicular bridge structure connecting from Tsing Tsuen Road (Tsuen Wan bound) to TWR (Kowloon bound) in front of Wing Kei Road Flyover.  The proposed slip road can provide a bypass route from Tsing Tsuen Road (Tsuen Wan bound) towards TWR southbound (Kowloon bound), thereby further relieving the traffic condition of TTI, if needed.

HyD is implementing a road improvement project, i.e. “Improvement Works at Tsuen Tsing Interchange” (IWTTI project), in the vicinity of SRC.  It is anticipated that upon completion of the aforesaid road improvement project, TTI will operate at satisfactory traffic condition during the peak hours.  In this regard, the implementation of the proposed Slip Road C will not proceed subject to confirmation on satisfactory performance of the TTI in a traffic review to be conducted upon completion of the IWTTI project tentatively in 2026.

2.5.6            Slip Road E

Slip Road E is a proposed two-lane vehicular bridge structure to improve the connectivity between TWR (Tuen Mun bound) and Hoi Hing Road and relieve the occasional traffic congestion at the downramp of TWR (Tuen Mun bound) fronting the Tsuen Wan West MTR station.

2.6                Consideration of Different Construction Methods for Viaduct

2.6.1            The proposed viaduct structures under the Project can be erected by cast in-place concrete construction method, prefabricated steel structure construction method and precast concrete construction method.  Having considered the scale and site condition of the proposed viaduct, it is recommended to adopt precast concrete construction method which is a more effective and environmentally friendly approach.

2.6.2            Comparison of the merits and demerits between these three construction methods is shown in Table 2.1 below.

Table 2.1     Comparison of Different Construction Methods for Viaduct

Construction Methods

Cast In-place Concrete

Prefabricated Steel Structure

Precast Concrete

Merits

·      Conventional construction method and require relatively less special skilled labour force and specialists when comparing with other construction methods.

·      Durable and less maintenance cost.

·      Minimise concrete mixing truck travelling in site area, thus minimise potential air and noise impact to the surrounding environment.

·      Fabricate the whole bridge deck structure by steel plates / members which does not require formwork, thus less C&D waste / materials will be generated.

·      Shorten construction time relatively, bridge deck construction can be non-linear (multiple work fronts), with minimising on-site potential environmental impacts and cumulative environmental impacts with concurrent projects.

·      Requires less temporary steel platforms, relatively, for construction of light weight steel structure, thus less C&D waste / materials will be generated.

·      Carry out prefabrication works in fabrication yard away from the site.

·      Better control of quality and workmanship for works in fabrication yard.

·      More efficient construction works as the deck structure can be fabricated off-site concurrently with the substructure works (i.e. allow time overlap of construction activities).

·      Minimise concrete mixing truck travelling in site area, thus minimise potential air and noise impact to the surrounding environment.

·      Use steel mould as formworks to maximise the reuse of formworks, thus less C&D waste/ materials will be generated.

·      Shorten construction time, bridge deck construction can be non-linear (multiple work fronts), with minimising on-site potential environmental impacts and cumulative environmental impacts with concurrent projects.

·      Relatively requires less temporary steel platform for construction of precast structure, thus less C&D waste / materials will be generated.

·      Carry out precasting works in fabrication yard away from the site.

·      Better control of quality and workmanship for works in fabrication yard.

·      More efficient construction works as the deck segments can be casted off-site concurrently with substructure works (i.e. allow time overlap of construction activities).

·      Durable and less maintenance cost.

Demerits

·      Use of timber formwork, thus more C&D waste/ materials will be generated.

·      Prepare concrete mix at a central concrete batching plant, where control of the materials should be monitored much carefully.

·      For transporting concrete to the site, proper mixing in truck, discharging from the truck and depositing in the forms, and handling for placement, finishing and curing are all subject to the level of responsibility and craft exercised by the workers involved.

·      Site conditions in terms of accessibility and weather can be highly critical to the work, requirement of extreme measures in some situations to control all stages in the production process. Possibility of site run-off might be higher under bad weather conditions.

·      Longer construction time – carry out bridge deck construction only (1) after substructure works is completed and (2) after completion of previous span for cast in-place span by span.

·      Require substantial temporary steel platform / falsework for construction of the bridge deck section over existing live traffic.

·      Subject to high risk of steel corrosion.

·      High maintenance cost.

·      Less durable.

·      Require another trade of skilled workers and additional construction equipment for erecting steelwork structures.

·      Require another trade of skilled workers and additional construction equipment for erecting precast segments.

2.6.3            Based on the considerations above, precast concrete construction method is the preferred construction method and the bridge form would be prestressed segmental bridge structure.

2.6.4            The bridge deck section will be designed to allow for the use of precast concrete construction method.  The deck will be formed from precast concrete sections which will be manufactured at a casting yard offsite and stitched together at their final positions on-site.  This approach will minimise the quantities of C&D waste/materials to be generated on-site, and also minimise the extent and duration of construction activities required on-site and hence the potential environmental impacts on nearby sensitive receivers during construction.

2.7                Construction Programme

2.7.1            The construction works of the Project will tentatively commence in 2028. Under scenario without SRC, the Project will tentatively complete in 2033.  Under scenario with SRC, the Project will tentatively complete in 2036. A tentative construction programme for the Project is provided in Appendix 2.1.

2.7.2            In order to minimize the adverse impacts to the sensitive receivers during construction, the construction programme and sequence of works will be carefully planned such that the environmental impacts would be kept to minimum and within acceptable limits.  The followings are the measures recommended to be taken during construction:

·         Avoid noisy construction activities during school examination period and schedule the construction works in the vicinity of schools and kindergartens during summer recess as much as possible if programme allows; and

·         Close liaison with the contractors of other concurrent projects in order to avoid overlapping of construction activities and allow sufficient buffer for works at project interface due to potential delays in the programme so that the cumulative effects of environmental impacts could be minimized.

2.8                Concurrent Projects

2.8.1            Concurrent projects in the vicinity of the Project site are identified.  The status of these concurrent projects is based on the available information obtained during the course of the EIA Study.  It should be noted that the implementation of individual project would be subject to further development and subsequent actions of the respective project proponent.

Improvement Works at Tsuen Tsing Interchange (IWTTI project)

2.8.2            IWTTI project is a modification to the Completion of Texaco Road / Tsuen Wan Bypass Interchange and Improvements to Texaco Road Phase II (TDD Contract No.: TW74/90), which was completed in 1995. IWTTI project mainly comprises extension of a single lane new bridge connecting Texaco Road (Tsing Yi bound) and the incomplete bridge above TTI and realignment of the affected section of Texaco Road; provision of an exclusive left turn lane from TWR (Tuen Mun bound) to Tsing Tsuen Road (Tsing Yi bound); junction improvement works at TTI roundabout including refinement of channelised left turn lane at Texaco Road fronting Sandoz Centre, provision of channelised left turn lane from TWR (Kowloon bound) offramp to Texaco Road (Ma Tau Pa Road bound), and refinement of TTI roundabout and associated arms refinement road side works. The construction of the IWTTI project is anticipated to commence in end 2023 for completion in 2026. Upon completion of the IWTTI project, the current congested traffic condition at TTI will be alleviated.

Proposed Columbarium Building at Site No. 10 Tsing Tsuen Road

2.8.3            A 4-floor columbarium building will be constructed at Tsing Tsuen Road which is anticipated to commence in Q2 2024 and complete in Q2 2030.

2.8.4            Although there is no overlap of works area between the proposed columbarium building project and this Project, the proposed columbarium building project falls inside the Study Area of the Project. The overlapping of construction period between the two projects from 2028 (tentative commencement year of the Project) to 2030 (tentative completion year of proposed columbarium building project) may induce potential cumulative impact on air quality and noise to the Project during construction phase. In view that the most dusty and noisy construction works of the proposed columbarium building project would be the site formation and foundation works for the building which are anticipated to be substantially completed by the time when the construction for the Project commence in 2028, the tentative construction programme and works between the two projects could be arranged efficiently through close liaison between HyD’s and the Board of Management of the Chinese Permanent Cemeteries (BMCPC)’s contractors to avoid construction works of respective works contracts to be carried out concurrently at the close proximity areas. Cumulative construction environmental impacts could be minimised.

2.8.5            Given the nature of the proposed columbarium building, no cumulative environmental impact is anticipated during operation phase of the Project in association with the columbarium building project.

Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road

2.8.6            The “Flyover from Kwai Tsing Interchange (KTI) Upramp to Kwai Chung Road (KCR)” will introduce an additional traffic lane for the section of the southbound carriageway of TWR between KTI and KCR, together with other related traffic improvement and road reconstruction works which are needed to cope with the continuous increase of traffic demand due to the existing, committed and planned developments.

2.8.7            “Flyover from KTI Upramp to KCR” is a designated project under the EIAO and is controlled by an environmental permit (EP-541/2017) for construction and operation. The EIA report (Register: AEIAR-190/2015) was approved on 3 August 2015.

2.8.8            Construction works for the “Flyover from KTI Upramp to KCR” will be completed in Q1 2025 tentatively which is before the commencement of the construction for the Project (i.e. not concurrent project under construction phase), and potential cumulative impacts involving this project during the construction of the Project is not anticipated.  Furthermore, as the forecast traffic flow data adopted for the air quality and noise impact assessments in the Project has already included the effect of the completion of “Flyover from KTI Upramp to KCR”, the cumulative impact during the operation phase of the Project in association with the “Flyover from KTI Upramp to KCR” has been considered. Apart from this, no other cumulative environmental impacts would be anticipated during operation phase of the “Flyover from KTI Upramp to KCR”.

Improvement Works at Tai Chung Road Interchange (IWTCRI project)

2.8.9            IWTCRI project is a modification to the existing Tai Chung Road Interchange (TCRI). IWTCRI project mainly comprises provision of exclusive left-turn lane from Hoi Hing Road to TWR (Tuen Mun bound); provision of free-flow left-turn lane from Tai Chung Road to TWR (Kowloon bound); and refinement of TCRI roundabout and associated arms refinement road side works. The construction of the IWTCRI project is anticipated to commence in 2028 for completion in 2030. Upon completion of the IWTCRI project, the current congested traffic condition at TCRI will be alleviated. With reference to the tentative construction programme of the Project, the construction works of IWTCRI and that of Slip Road E would not be conducted concurrently while the construction works of other parts of this Project will be carried out with separation distance of more than 300m. Hence, the cumulative adverse impact arising from this concurrent project is insignificant. Furthermore, as the forecast traffic flow data adopted for environmental assessments in the Project already included the effect of the completion of IWTCRI project, the cumulative impact during the operation phase of the IWTCRI project has been considered. No other cumulative environmental impacts would be anticipated during operation phase of the IWTCRI.

2.8.10          The key details of the abovementioned planned/committed concurrent projects are summarized in Table 2.2 and their locations presented in Figure 2.5. Potential cumulative environmental impacts arising from these concurrent projects during construction and operation phase of the Project have been considered in the EIA Report and presented in respective sections. No cumulative impact is expected for environmental aspects such as waste management, land contamination and cultural heritage.  

Table 2.2          Summary of the Other Projects in the Vicinity of the Project Site

Project

Project Proponent

Construction Programme

Potential Cumulative Impact

Start

Complete

Construction

Operation

Improvement Works at Tsuen Tsing Interchange

Highways Department

2023

[1]

2026

[1]

Note [4]

Proposed Columbarium Building at Site No. 10 Tsing Tsuen Road

The Board of Management of the Chinese Permanent Cemeteries (BMCPC)

Q2 2024

[1]

Q2 2030

[1]

Nil

Flyover from Kwai Tsing Interchange Upramp to Kwai Chung Road

Highways Department

June 2021

[2]

February 2025 [2]

Note [4]

Improvement Works at Tai Chung Road Interchange

Highways Department

2028

[3]

2030

[3]

Note [4]

Note:

” may have potential cumulative impact;

[1]      The project is currently under detailed design stage and the construction programme shown is tentatively only.

[2]      Source: HyD’s website at https://www.hyd.gov.hk/en/our_projects/road_projects/856th/index.html

[3]      The project is currently under investigation stage and the construction programme shown is tentatively only.

[4]      No potential cumulative impact for air quality, noise, water quality, waste management, land contamination, landscape and visual and cultural heritage.

2.9                Public Concern

2.9.1            The project profile was submitted to the Environmental Protection Department (EPD) on 17 June 2021 and was exhibited for public inspection between 18 June 2021 to 1 July 2021.

2.9.2            In February – March 2023, the traffic and transport committees under the Kwai Tsing District Council (DC) and Tsuen Wan DC as well as relevant area committees of Kwai Tsing district and Tsuen Wan district were consulted on the proposed works to be taken forward under the Project (i.e. all works items except (iv) and (v) as detailed in Paragraph 2.3.1 above). The traffic and transport committees under the Kwai Tsing DC and Tsuen Wan DC gave support to the proposed works to be taken forward under the Project, and the ACs generally supported/had no comments on the proposed works to be taken forward under the Project.  Briefings to the interested group of the residential estates along TWR were also conducted in February – April 2023. During the above consultations and briefing sessions, some LegCo/DC/AC members and local residents raised the following concerns / issues about the Project and the follow-up actions to be taken are summarized in Table 2.3.

Table 2.3          Summary of Concerns and Follow-up Actions

Concerns / Issues

Follow-up Actions to be Taken

·      Concern on the height of the proposed noise barriers/enclosures

·       The height of the proposed noise barriers/enclosures will be designed to below the lowest residential floor level of the adjacent residential premises (e.g. City Point) as far as practicable to minimize the visual impact.

 

·      Concern on construction noise to the nearby residential estates during the construction phase of the Project

 

·       The construction of the Project will be carried out with suitable temporary noise mitigation measures in place. Construction arrangements will be carefully planned in the upcoming project stages such that construction noise impact to the nearby residential estates will be kept to minimum during construction of the Project.

 

·      Concern on the potential glare resulted from the top of the proposed noise barriers/enclosures

 

·       Roof panels of the proposed barriers/enclosures will be designed in such a way to minimise the potential glare induced.

 

·      Request for reviewing the form of the originally proposed noise enclosure fronting the Parc City Block 2 and the Pavilia Bay in view of various environmental concern (e.g. visual, noise and air quality)

 

·       The proposed noise enclosure form at the road section concerned has been reviewed/refined from the form of semi-enclosure to full enclosure. The scope of the proposed noise mitigation measures is given in Section 4 of this Report.

 

·      Request for extension of the proposed noise enclosure to cover other sections of TWR fronting the Parc City Block 3 to the Ocean Pride Block 7

·       According to the result of noise impact assessment, the Project will comply with the EIAO criteria with the proposed noise mitigation measures in place, of which no noise enclosures are required at the TWR sections fronting Parc City Block 3 to Ocean Pride Block 7.  Therefore, the requested extension of the noise enclosure is outside the ambit of the Project. The scope of the proposed noise mitigation measures is given in Section 4 of this Report.

 

·      Concern on traffic impact on TWR during construction of the Project

·       The construction of the Project will be carried out with suitable temporary traffic arrangements implemented.  Construction arrangements will be carefully planned in the upcoming project stages such that traffic impact on TWR will be kept to minimum during construction of the Project.