Contents
14. Summary of Environmental Outcomes
14.3 Environmental Benefits of Environmental Protection
Measures Recommended
14.4 Estimated Population Protected from Various
Environmental Impacts
Table
14.1 Key Design Considerations and the Associated Environmental
Benefits
Table
14.2 Key recommended mitigation measures/ good
site practices/ enhancement measures and their associated benefits
Table 14.1 Key Design Considerations and the
Associated Environmental Benefits
Design Approach |
Key Design Considerations |
Associated Environmental Benefits |
Avoidance
of Works within Tai Lam Country Park |
·
No aboveground works within Tai Lam Country
Park. Only tunnelling works and part
of temporary underground adit at the Wah Fat Works Area would be carried out
underneath Tai Lam Country Park. No aboveground works within the Tai Lam
Country Park boundary. ·
After considering the latest geological
information at Tai Lam Country Park, it has been determined that the most
suitable construction method for these tunnel sections is drill-and-blast.
Alternative tunnelling methods, including the use of TBM in Tai Lam Country
Park were duly explored but considered not suitable from the engineering
perspective. |
·
No direct loss of aboveground
natural habitat and resources within Tai Lam Country Park boundary. |
Avoidance
of Marine Works |
·
Avoid reclamation and the associated
dredging works within Tuen Mun Typhoon Shelter have been totally avoided. |
·
Avoid the disturbance of seabed,
marine habitat loss and generation and disposal of marine sediment. |
Minimisation
of Potential Water Drawdown in Tai Lam Country Park |
·
Good practices and water control
strategies such as including probing ahead, pre-grouting and posting grouting
will be implemented to minimize adverse impact. As a precautionary
measures, monitoring programme will be implemented to monitor the mitigation
measures on groundwater infiltration within Tai Lam Country Park. ·
Drill-and-blast/drill-and-break
tunnel section would be in granite and with sufficient depth below ground,
together with the good practices and mitigation measures, adverse impact on
the change in groundwater table would be insignificant. |
·
Minimised impacts on water
drawdown in Tai Lam Country Park. |
Minimisation
of Air Quality Impact |
·
Adopt mitigation measures for
fugitive dust such as regular spray, exposed earth surface covered by
tarpaulins, standard wheel washing facilities at the construction site exits,
vehicle washing at the exit of the barging facility with the provision of
vehicle washing facilities. ·
Provision of 3-side with top cover
and spraying system at unloading points at the barging facility. ·
Blasting to be carried out in a
fully enclosed environment. ·
Avoid using exempted Non-Road
Mobile Machinery (NRMM) where practicable. ·
Site hoardings of not less than
2.4m high should be provided as far as practicable along the site boundary
with provision for public crossing. Taller site hoarding may be considered
for ASRs in close vicinity to the site boundary, subject to actual site
constrains and detailed design. Good site practice shall also be adopted by
the Contractor to ensure the conditions of the hoardings are properly
maintained throughout the construction period. ·
Connect construction plant and equipment
to mains electricity supply and avoid use of diesel generators and
diesel-powered equipment as far as practicable to minimize air quality impact
arising from construction machinery. ·
Close the impermeable blast covers
at tunnel portals prior to blasting works in order to ensure blasting works
in a fully enclosed environment. ·
The engine of the barge shall be
switched-off during berthing as far as practicable. Provision of on-shore
power supply shall also be considered wherever possible to minimize air
quality impact from the marine vessels, with consideration of actual site
constraints or circumstances to be further reviewed during detail design
stage. ·
Close liaison between the
contractors of other concurrent projects and the Project would be maintained
to minimise dusty activities to be conducted concurrently as far as
practicable. ·
During the subsequent design stage
and the operational stage, the ventilation engineer should conduct reviews on
the ventilation scheme covering different periods of a day, taking into
account the contemporary circumstance such as latest traffic forecast,
traffic composition, update on the ambient air quality, etc., and then review
and update the air quality assessment as necessary to demonstrate full
compliance of the AQO. These reviews
would allow the designer and operator to optimize the operation of the
ventilation system without compromising the compliance of AQO. ·
Proper design of any planned air
sensitive uses within the satellite control building and operation area in
Lam Tei, and maintenance compound and training ground and supporting area in
Pillar Point such that any openings, openable windows, and/or FAIs will be
located and avoided from the predicted exceedance zone at 1.5mAG. (e.g., by
provision of fixed glazed window or blank facades, and FAIs to be located
away or proposed air sensitive uses outside the exceedance zone). Further
review of the layout and design of these TMB highway / tunnel operation and
maintenance facilities in Detailed Design Stage to ensure compliance of the
AQOs. For the proposed satellite control building and FAIs for maintenance
compound located within the exceedance zone at 1.5mAG, installation of air
filtering system is recommended. Further review of the air filtering system
and NO2 removal efficiency to ensure compliance of the AQOs in
Detailed Design Stage. |
·
Minimised fugitive dust generation
and emissions; and ·
Ensure compliance with the
requirements in Annex 4 of the EIAO-TM at the ASRs. |
Minimisation
of Noise Impact |
·
Adopt noise mitigation measures
such as of use of Quality Powered Mechanical Equipment (QPME) and/or quieter
mechanical equipment, quieter construction method, temporary/ moveable noise
enclosure will be considered during construction. ·
Installation of temporary full
enclosure is recommended at the bulk excavation area, temporary adit portal
and spoil storage area of MVB at Wah Fat Playground to minimise construction
noise impacts on the NSRs. ·
Install suitable noise control
measures such as silencers and sound attenuators will also be used to reduce
the noise generated by noisy machines and plants in operation stage |
·
Minimised construction, road
traffic noise and fixed noise impacts. |
Minimisation
of the C&D Material & Risk if Unauthorised Filling Activities |
·
During design phase, a
Construction and Demolition (C&D) Material Management Plan (C&DMMP)
will be prepared in accordance with Section
4.1.3 “Construction and Demolition Materials” of the Project
Administration Handbook for Civil Engineering Works and will be submitted
together with the EIA Report to the department Vetting Committee for
endorsement and then to Public Fill Committee (PFC) for approval. ·
Segregate C&D materials will
be segregated from other wastes to avoid contamination. Ensure acceptability
at PFRFs or reclamation sites. ·
Carry out on-site sorting. ·
Make provisions in the Contract
documents to allow and promote the use of recycled aggregates where
appropriate. ·
Implement a trip-ticket system for
each works contract in accordance with DEVB TC(W) No. 6/2010 to ensure that
the disposal / handling of C&D materials is properly documented and
verified, so as to avoid the illegal dumping and landfilling of C&D
materials. ·
All dump trucks and vessels engaged
on site should be equipped with Global Positioning System (GPS) or equivalent
automatic system for real time tracking and monitoring of their travel
routings and parking locations to prohibit illegal dumping and landfilling of
C&D materials. |
·
Minimisation of the C&D
Material & Risk if Unauthorised Filling Activities. |
Minimisation
of Cultural Heritage Impact |
· Avoid ·
Any vibration and building
movement induced from the proposed works will be strictly monitored to ensure
no disturbance and physical damages made to the heritage sites during the
course of works. · Avoided direct impact on the Built Heritage at the
former Girl Guide Associate Campsite, no excavation works will be carried out
and existing building structures will not be demolished or removed but only
require some necessary restoration/ refurbishment/ repair. |
·
Avoided direct impact on SAIs and
minimise impacts on the heritage site and historical building/ structure/
feature/ site. |
Table 14.2 Key
Recommended Mitigation Measures/ Good Site Practices/ Enhancement Measures and
their Associated Benefits
Aspect |
Key Recommended
Mitigation Measures/ Good Site Practices/ Enhancement Measures |
Associated
Environmental Benefits |
Air
Quality Impact |
·
Adopt dedicated spoil transportation routes
away from the identified Air Sensitive Receivers (ASRs) as practicable. ·
Install 3-sided screen with top cover and
provide water sprays at the unloading point to barges at the barging
facility. ·
Avoid using exempted NRMM as much as
practicable and when alternatives are available from the local market at the
time of construction. ·
Site
hoardings of not less than 2.4m high should be provided as far as practicable
along the site boundary with provision for public crossing. Taller site hoardings may be considered for ASRs in close
vicinity to the site boundary, subject to actual site constrains and detailed
design. Good site practice shall also be adopted by the Contractor to ensure
the conditions of the hoardings are properly maintained throughout the
construction period. ·
Adopt water spraying system for areas with
heavy construction activities. ·
Connect construction plant and equipment to
mains electricity supply, and avoid use of diesel generators and
diesel-powered equipment as far as practicable to minimize air quality impact
arising from construction machinery. ·
Close the impermeable blast covers at tunnel
portals prior to blasting works in order to ensure blasting works in a fully
enclosed environment. ·
Water spray before open blasting and on
blasted material prior to transportation ·
Provide vehicle washing facilities at the
exit of the barging facility and exit of works sites. ·
The engine of the barge shall be
switched-off during berthing as far as practicable. Provision of on-shore
power supply shall also be considered wherever possible to minimize air
quality impact from the marine vessels, with consideration of actual site
constraints or circumstances to be further reviewed during detail design
stage ·
Close liaison between the contractors of
other concurrent projects and the Project would be maintained to minimise
dusty activities to be conducted concurrently as far as practicable. ·
During the subsequent design stage and the
operational stage, the ventilation engineer should conduct reviews on the
ventilation scheme covering different periods of a day, taking into account
the contemporary circumstance such as latest traffic forecast, traffic
composition, update on the ambient air quality, etc., and then review and
update the air quality assessment as necessary to demonstrate full compliance
of the AQO. These reviews would allow
the designer and operator to optimize the operation of the ventilation system
without compromising the compliance of AQO. ·
The planned air sensitive uses within the
highway / tunnel operation and maintenance facilities of the TMB shall be
properly designed such that any openings, openable windows, and/or fresh air
intakes will be located and avoided from the predicted exceedance zone at
1.5mAG. Further review of the layout and design of operation area will be
conducted in Detailed Design Stage to ensure compliance of the AQOs. |
·
Protect Air Sensitive Receivers (ASRs) by
reducing fugitive dust generation and emissions. ·
Ensure compliance with the requirements in
Annex 4 of the EIAO-TM at the ASRs. |
Noise
Impact |
·
Follow good site practices to limit
construction noise emissions at the sources. ·
Use of quality powered mechanical equipment
and quieter construction methods. ·
Use of temporary noise barriers and noise
enclosures to screen noise from relatively static PMEs. ·
Install acoustic tunnel door or enclosure at
the tunnel portal opening for tunnelling activities. ·
Install temporary noise enclosures for the
construction sites near Wah Fat Playground. ·
Provide mitigation measures for fixed noise
sources (e.g., quieter equipment, silencer, barrier and enclosure) with
reference to EPD’s “Good Practices on Ventilation System Noise Control”. ·
Orientate louvres away from adjacent NSRs,
preferably onto main roads which are less noise sensitive. ·
Select façade for ventilation shafts with adequate
sound insulation properties. |
·
Protect Noise Sensitive Receivers (NSRs) by
reducing construction, road traffic and fixed noise impacts. ·
Ensure compliance with the respective road traffic
noise requirements at neighbouring NSRs. ·
Ensure compliance with the respective fixed
noise requirements at neighbouring NSRs. |
Water
Quality Impact |
·
Follow Best Management Practices (BMPs) of
mitigation measures in controlling water pollution and good site management
as specified in the ProPECC PN 1/94 “Construction Site Drainage” and
Environment, Transport and Works Bureau (ETWB) Technical Circular (Works)
(TC(W)) No. 5/2005. ·
Adopt suitable water control strategies as
far as practicable, including probing ahead, pre-grouting and post-grouting,
during tunnelling works. ·
Control impact on groundwater through
adopting toe grouting and installation of recharge well during temporary
dewatering for excavation works. ·
Provide adequate and sufficient portable chemical
toilets for construction workforce and temporary storage tank for collection
of wastewater. ·
Comply with the Conditions for Working
within Water Gathering Grounds ·
Carry out construction works close to inland
waters in dry season as far as practicable. ·
Conduct watercourse removal and flow
diversion in dry season as far as practicable. ·
Size all vessels to maintain adequate
clearance between vessels and the seabed in all tide levels. ·
Control loading of barges and hoppers to
prevent splashing of materials into the surrounding water. ·
Install and maintain roadside gullies and
oil / grease interceptors for removal of pollutants from storm water as
necessary. ·
Collect and treat wastewater generated by
washing and maintenance activities, and discharge to public sewerage system
properly. |
·
Protect the neighbouring WSRs during
construction and operational phases. |
Waste
Management Implications |
·
During design phase, a Construction and
Demolition (C&D) Material Management Plan (C&DMMP) will be prepared
in accordance with Section 4.1.3
“Construction and Demolition Materials” of the Project Administration
Handbook for Civil Engineering Works and will be submitted together with the
EIA Report to the department Vetting Committee for endorsement and then to
Public Fill Committee (PFC) for approval. ·
Carry out on-site sorting, re-use and
recycled C&D materials, implement a trip-ticket system for each works
contract to in accordance with Development Bureau TC(W) No. 6/2010 ensure
that the disposal / handling of C&D materials is properly documented and
verified so as to avoid the illegal dumping and landfilling of C&D
materials. ·
All dump trucks and vessels engaged on site
should be equipped with Global Positioning System (GPS) or equivalent automatic
system for real time tracking and monitoring of their travel routings and
parking locations ·
Chemical wastes (e.g., spent lubricant oil)
should be recycled at an appropriate facility as far as possible, while the
chemical waste that cannot be recycled should be disposed of at either the
CWTC, or another licensed facility, in accordance with the Waste Disposal
(Chemical Waste) (General) Regulation. ·
Standard formwork should also be used as far
as practicable in order to minimise the arising of non-inert C&D
materials. The use of more durable formwork (e.g., metal hoarding) or plastic
facing should be encouraged in order to enhance the possibility of recycling.
The purchasing of construction materials should be carefully planned in order
to avoid over ordering and wastage. ·
Implement an education programme for
workforce relating to avoiding, reducing, reusing and recycling general
waste. Participation in a local collection scheme should be considered by the
Contractor to facilitate waste reduction. ·
Measures and good site practices to be
implemented at the works area during construction (Details to refer to Section 6) |
·
Minimize waste generation. ·
Ensure proper handling of chemical waste. ·
Ensure the C&D materials are disposed
and delivery to designated sites. |
Land
Contamination |
·
Prior to the commencement of the site
investigation (SI) works, review the Contamination Assessment Plan (CAP)
provided in Appendix 7.1 and
conduct site re-appraisal to confirm whether the proposed SI works (e.g.,
sampling locations, testing parameters etc.) are still valid, and to confirm
the appropriate RBRGs land use scenario for the development. ·
Should any changes in operation which lead
to any new or the relocation of contamination hotspots or occurrence of
spillage or accident be found in the review, supplementary CAP(s), presenting
the findings of the review, the latest site conditions and updated sampling
strategy and testing protocol, should be submitted to EPD for approval. ·
The SI works should be carried out according
to EPD’s approved CAP(s). ·
Contamination Assessment Report(s) (CAR(s))
should be prepared to present the findings of the SI works and to discuss the
presence, nature and extent of contamination. If contamination is identified
in the CAR(s), Remediation Action Plan(s) (RAP(s)) which provides details of
the remedial actions for the identified contaminated soil and/or groundwater
should be developed prior to construction works at the concerned areas.
Submission to EPD for approval of the supplementary CAP(s), CAR(s) and, if
required, RAP would be carried out in stages according to the programme of
TMB. ·
If required, carry out soil/groundwater
remediation works according to EPD approved RAP(s) and submit Remediation
Report(s) (RR(s)) afterwards for EPD approval prior to the commencement of
construction works at the contaminated areas. |
·
Land
contamination issues could be resolved before commencement of construction
works. |
Hazard
to Life |
·
Reduce the amount of combustibles in the
cabin of truck. The fuel carried in the fuel tank should also be minimized to
reduce the duration of any fire. ·
Implement defensive driving attitude and
dedicate training programme for both driver and his attendants. ·
Transport the required quantity of explosive
for a particular blast. ·
Combine explosive deliveries for a given
work area as far as practicable. ·
Maintain a minimum headway between two
consecutive truck convoys of 10 minutes whenever practicable. ·
Implement a better emergency response and
training to ensure adequate fire extinguishers are used and attempt is made
to evacuate the area of the incident or securing the explosive load if
possible. ·
Equip bigger capacity AFFF-type
extinguishers on all explosive vehicles. ·
Implement good practices as per Practice
Note for Authorized Persons and Registered Structural Engineers – Control of
Blasting (APP-72), and Mines Division Guidance Note Nos. GN 8 How to Apply
for a Mode A Licence for Storage of Schedule 1 Dangerous Goods (Blasting Explosives)
and GN 3 Application and Handling of a Conveyance Permit. ·
Formulate a Hazard Management Plan with a
view to aligning the understanding of the risk of the three projects (i.e.
Route 11, Tuen Mun Bypass (TMB) and Lam Tei Underground Quarrying (LTUQ)) so
that all the working populations at Lam Tei Quarry area, which includes the
workforce induced under the construction and operational stage of three
projects, could be considered as on-site populations in the QRA for all the
three projects. The measures
stipulated in the Hazard Management Plan may include, but not limited to, the
adjustment of the blasting schedules of the three projects to minimize the
potential cumulative impact, provision of common trainings and drills to the
workforce of all the three projects, etc. The Hazard Management Plan, which
would be agreed among the three projects, would be submitted to EPD for
agreement prior to the tender invitation of construction phases of Route 11,
TMB and LTUQ, whichever is earlier. |
·
Protect nearby sensitive receivers from
adverse impacts due to transportation, overnight storage and use of explosive
for blasting. |
Landfill
Gas Hazard |
·
Implementation of appropriate safety
measures during construction works to minimise the risk of fire and
explosions and asphyxiation of works, especially in confined space. ·
Periodically during ground-works
construction, the works area should be monitored for methane, carbon dioxide
and oxygen using appropriately calibrated portable gas detection equipment. ·
All access to confined spaces should be
restricted only to authorized personnel and should be informed of the
landfill gas hazard. No general public
should be permitted or allowed to access the service voids, manholes,
chambers or wells. ·
During operation, regular monitoring of
landfill gas should be conducted at buildings and enclosures (e.g. proposed
Administration Building, Maintenance Compound, temporary re-provisioning of
EMSD Servicing Centre, service manholes, etc.) within the Consultation Zone
to verify the effectiveness and to ensure the continued performance of the
implemented protection measures. |
·
Minimise the risk of fire and explosions and
asphyxiation of works. |
Ecology
Impact (Terrestrial) |
·
No aboveground works at the recognized sites
of conservation importance (including Lam Tei and Yick Yuen Conservation Area
and Tai Lam Country Park). All
aboveground works including site formation works at the northern portal will
be located away from the Tai Lam Country Park as far as further reduce
disturbance impacts. Provision
of screening (e.g., hoarding) during construction phase is recommended to
confine the proposed works within Project footprint and hence outside Tai Lam
Country Park to avoid disturbance to adjacent habitats from the construction
phase activities. ·
Shifting the portal and the mainline
eastward away from the Lam Tei Irrigation Reservoir so as to allow integrated
site formation for tunnel portals of TMB and which can also reduce environmental
impact associated with site formation. ·
Shifting the works area at Wah Fat
Playground away from the perennial stream where two freshwater crab species
of conservation importance were recorded. ·
Upon the completion of construction works,
the proposed works area and magazine sites would be decommissioned and
reinstated to its original condition in principle. ·
Detailed vegetation survey should be
conducted within mixed woodland and shrubland/grassland at Pillar Point and
near Wah Fat Playground prior to the commencement of construction activities
to confirm the presence of flora species of conservation interest. Transplantation and/or mitigation measures
would be recommended as far as possible (Details to refer to Section 10). ·
Prior to commencement of the stream
diversion and construction works near Wah Fat Playground, an update
Freshwater Crab survey should be conducted and cover the stretch of the
watercourse S2 and S2A. Should species
of conservation importance be found within the affected watercourse sections,
a Freshwater Crab Translocation Plan should be prepared. Freshwater crab
translocation should be conducted to move the affected individuals from the
Project area to suitable recipient site(s). (Details to refer to Section 10). ·
Measure and good site practices to be implemented
at the works area during construction (Details to refer to Section 10). ·
Stream
diversion works with green channel design elements incorporated will be carried out to divert any water
flow from the upper sections of the watercourses within Project Area (i.e.
S1, S2 and S3) to the lower sections of the watercourses with similar
ecological features and/or hydrology setting outside the Project Area so as
to maintain the flow between unaffected sections of the stream and to avoid
excessive water flow entering the construction area. Detailed design of any
stream diversion should follow the guidelines in ETWB Technical Circular
(Works) No. 5/2005 (Protection of natural streams/rivers from adverse impacts
arising from construction works) and appropriate construction methods should
be used. ·
Adopt
suitable water control strategies, which are applicable to both TBM
tunnelling and drill-and-blast / drill-and-break tunnelling, as far as
practicable (Refer to Section
5 for details). ·
Compensatory
woodland planting is suggested to mitigate the loss of approximately ~2.2ha
of mixed woodland. (Details to refer
to Section 10). |
·
Minimize the direct and indirect impacts to
the habitat and species of conservation importance during construction phase. ·
Minimise
physical disturbance to the surrounding habitats. |
Landscape
and Visual Impacts |
·
Tree protection
works and tree transplantation to be undertaken in accordance with DEVB TC(W)
4/2020 on “Tree Preservation”. In accordance with DEVB TC(W) No. 4/2020, the
compensatory planting proposal should have the basic primary objective of
planting compensatory trees in a ratio not less than 1:1 in terms of quantity
as far as practicable. ·
Construction area
control, where possible, to ensure that the landscape and visual impacts
arising from the construction activities are minimized. ·
Advance
Implementation of Mitigation Planting. ·
Decorative screen
hoarding will be erected along areas of the construction works site boundary
where the works site borders publicly accessible routes and/or is close to
visually sensitive receivers (VSRs) to screen undesirable views of the works
site. ·
Control of
night-time lighting and Construction traffic (land and sea) reduced to
practical minimum. ·
The alignment and
structures associated with the new road should be integrated, as far as
technically feasible, with existing roadside structures and the landscape
context to reduce the potential cumulative impact of the proposed works. ·
Aesthetic
treatment and Design of the building and tunnel ventilation shaft should be
vetted and advised upon by ArchSD in accordance with ETWB TCW No. 8/2005 –
Aesthetic Design of Ancillary Buildings in Engineering Projects. ·
Greening
Provision in the early project planning stage and shall be in accordance with
DEVB TCW No. 2/2012- allocation of space for quality greening on Roads. ·
Post-planting
monitoring of the compensatory trees shall be undertaken (namely, duration of
the post-planting monitoring and monitoring methodology). The monitoring will
be aimed to assess the success and performance of the compensatory planting
trees, monitor the growth performance of the planted seedlings and whips, and
identify any need of vegetation and site maintenance work. ·
The design and
implementation of the aesthetic appearance of the retaining wall and slopes
will be undertaken in accordance with GEO Publication No. 1/2011 – Technical
Guidelines on Landscape Treatment for Slopes (2011), and WBTC No. 17/2000 on Improvement to the Appearance of
Slopes. ·
Wah Fat
Playground will be impacted during construction stage. Areas temporarily
disturbed will be reinstated after completion of construction of TMB. All
hard and soft landscape areas disturbed temporarily during construction due
to temporary excavations, temporary works sites shall be reinstated to equal
or better quality, to the satisfaction of the relevant Government
Departments. |
·
Minimize landscape and visual impacts during
construction and operational phases. |
Cultural
Heritage Impact |
·
Three sites of Archaeological Interest,
namely Shek Kok Tsui, Fu Tei Ha and So Kwu Wat, will not be impacted. ·
Avoid direct impact on the Built Heritage
BH-03 at the GGA campsite, no excavation works will be carried out and
existing building structures will not be demolished or removed but only
require some necessary restoration/ refurbishment/ repair. Appropriate protective
and mitigation measures are to be recommended during detail design stage of
the Project when the structural condition and assessment of the Site and the
historical buildings/ structures/ features are verified during detailed
design stage of the Project. The protective and mitigation measures should be
agreed by AMO, and to be implemented to the satisfaction of AMO to safeguard
against any potential adverse impact. ·
Any vibration and building movement induced
from the proposed works should be strictly monitored to ensure no disturbance
and physical damages made to the heritage sites during the course of works. ·
Special attention should be paid to avoid
adverse physical impact arising from the construction works to the heritage
site. Design proposal, method of works and choice of machinery should be
targeted to minimize adverse impacts to the heritage site. Any vibration and
building movement induced from the construction works should be strictly
monitored to ensure no disturbance and physical damages made to the heritage
site during the course of works. ·
Excavation works in close vicinity to the
heritage site should not jeopardize stability of the historic structures. It
should not undermine or cause damage to foundation of the historic
structures. Foundation information of the historic structures shall be
verified on site if needed, sufficient lateral support should be provided and
de-watering (if required) should be carried out with great cautions to
control ground movement and change of ground water regime at the heritage
site. ·
Installation of monitoring checkpoints shall
be carried out in great care and adequate protection shall be provided so as
to avoid unnecessary disturbance / damage to the historic fabrics. Photo
records of monitoring checkpoints shall be submitted upon installation for
AMO's records. Monitoring records should be submitted to AMO on regular basis
and please alert AMO should the monitoring reach Alert/ Alarm/ Action levels. ·
As a precautionary measure, the project
proponent and his/her contractor are required to inform AMO immediately when
any antiquities or supposed antiquities under the Antiquities and Monuments
Ordinance (Cap. 53) are discovered during the course of works. |
·
Minimise adverse impact on any Sites of
Archaeological Interest and historical building building/ structure/ feature/
site. ·
Ensure
compliance with all statutory requirements and those recommendations in the
EIA report. |
General |
·
Implement a comprehensive Environmental
Monitoring System throughout the entire construction period. ·
Employ an Environmental Team (ET) and
Independent Environmental Checker (IEC) |
·
Ensure compliance with all statutory
requirements and those recommendations in the EIA report |