s
Contents
2.1 Purposes and Objectives of the Project
2.3 Consideration of “With” and “Without” Project
Scenarios
2.4 Design Changes to the Project
2.5 Consideration of Alternatives / Options
2.6 Consideration of Construction Methodologies
2.7 Tackling Environmental Challenges
2.8 Preliminary Design for the Project
2.9 Tentative Construction Programme
2.11 Collating and Addressing Public Views
2.12 Summary of Key Environmental Outcome
Table 2.1 Evaluation
for Alignment Options A1 and A2 (Near Wu Shan Road)
Table 2.2 Evaluation
for Alignment Options B1, B2 and B3 (at Sam Shing Estate)
Table 2.3 Evaluation
for Option C1, C2 and C3 (Near Lam Tei Irrigation Reservoir)
Table 2.4 Summary
of Recommended Alignment Options for Sub-Areas
Table 2.5 Evaluation
for Southern Interchange and Portal
Table 2.6 Summary
of Consideration for Northern Portal
Table 2.7 Evaluation
for MVB Schemes
Table 2.8 Evaluation
for Options of SVB
Table 2.9 Evaluation
for Options of NVB
Table 2.10 Summary
of Adopted Design Option
Table 2.11 Consideration
for Magazine Sites
Table 2.12 Comparison
of Construction Methods for Tunnel Sections
Table 2.13 Key
Elements of the Project
Table 2.14 Summary
of the Key Construction Works for the Project
Table 2.15 Summary
of Potential Concurrent Projects
Table 2.16 Summary
of Key Concerns from Public Consultation and Follow Up Actions
Table 2.17 Key Recommended Mitigation Measures/ Good Site Practices/ Enhancement
Measure and their Associated Benefit 38
Figure 2.1 Preliminary
Alignment Options – Option 1 & 2
Figure 2.2 Alignment Options
Figure 2.2a Alignment Options - Option A1 and A2
Figure 2.2b Alignment Options - Option B1, B2 and B3
Figure 2.2c Alignment Options - Option C1, C2 and C3
Figure 2.3a Southern Interchange Options – Option S1
Figure 2.3b Southern Interchange Options –
Option S2
Figure 2.3c Southern Interchange Options – Option
S3
Figure 2.4a Northern Portal Options – Option
N1
Figure 2.4b Northern Portal Options – Option
N2
Figure 2.4c Northern Portal Options – Option
N3
Figure 2.5 Middle Ventilation Building
Options
Figure 2.6 Southern Ventilation Building
Options
Figure 2.7 Northern Ventilation Building
Options
Figure 2.8 Tunnel Construction Method
Figure 2.9 Key Elements for the Project
Figure 2.10 Longitudinal Profile for the Tuen
Mun Bypass
Figure 2.11 Locations of the Concurrent
Project
Table 2.1 Evaluation for Alignment
Options A1 and A2 (Near Wu Shan Road)
Option A1 |
Option A2 |
|
Engineering Factors |
· Option
A1 has a major direct conflict with CLP 132 kV tunnel shaft, which in term results in larger TBM with minimal
separation with the nearby building piles.
Diversion of this existing CLP 132kV in operation will require
extremely long lead time. · Option
A1 encroaches into the geological complex area, which has lower
constructability and require longer construction time. |
·
Option
A2 locates underneath the Consultation Zone (CZ) of ExxonMobil LPG Storage
Installation at Tuen Mun Area 44 Consultation Zone, careful planning and
risk assessment are required during detail design stage. There are Minimal
conflict with existing structure and geotechnical complex area. |
Environmental Factors |
· Conflicts
with existing CLP 132kV tunnel shaft which demolition and relocation of
tunnel shaft may be required. The
demolition required would generate more construction and demolition
(C&D) waste. |
· Option
A2 locates underneath the CZ of the
ExxonMobil LPG Storage Installation at Tuen Mun Area 44 which is a
Potentially Hazardous Installation (PHI), at more than 30m from the storage.
Tunnelling using TBM could avoid blasting in the vicinity of this PHI.
Transportation routes for the explosives for the drill-and-blast sections in
other areas could also avoid the CZ of the PHI. · Individual
risk contour and societal risk of this LPG storage installation would be the
same as that predicted in the approved EIA report of Tuen Mun South
Extension (see details in Section 8). |
Other
Factors |
· Option
A1 is close to various stakeholders and planned housing site, it requires
close liaison with nearby stakeholders. |
· Option
A2 is close to various stakeholders and planned housing site, it requires
close liaison with nearby stakeholders. |
Table 2.2 Evaluation
for Alignment Options B1, B2 and B3 (at Sam Shing Estate)
Consideration |
Option B1 |
Option B2 |
Option B3 |
Engineering Factors |
· Tunnel
construction beneath rockhead, comparatively with higher constructability. |
· Tunnel
construction beneath rockhead, comparatively with higher constructability. |
· Tunnel
construction through complicated fault zone, which has low constructability
and require longer construction time affecting critical path. |
Environmental Factors |
· It
passes beneath two residential zones (Sam Shing Estate and Kam Fai Garden)
and has more implications to the residential zone. |
· It
passes beneath one residential zone (Sam Shing Estate) and has less
implications to the residential zone. |
· It
passes beneath two residential zones (Palm Cove and Dragon Inn) and has more
implications to the residential zone. |
Other Factors |
· It
passes through 2 residential zones and requires close liaison with
stakeholders. |
· It
passes through 1 residential zone and requires close liaison with
stakeholders. |
· It
passes through 2 residential zone and requires close liaison with
stakeholders. |
Table 2.3 Evaluation for Option C1, C2 and C3 (Near Lam
Tei Irrigation Reservoir)
Consideration |
Option C1 |
Option C2 |
Option C3 |
Engineering Factors |
· Tunnel
construction through fault zone, constructability is low and required longer
construction duration affecting critical path. · The
closest to the existing Lam Tei Irrigation Reservoir, only 70m away from the
dam of Lam Tei Irrigation Reservoir, higher construction risk. |
· Tunnel
construction beneath rockhead comparatively with higher constructability. · It
is designed to avoid the fault zone but still close to the existing Lam Tei
Irrigation Reservoir, risk to the dam of the Lam Tei Irrigation Reservoir is
still considerable high. |
· Tunnel
construction beneath rockhead comparatively with higher constructability. · It
is furthest away from Lam Tei Irrigation Reservoir, risk to the dam of the
Lam Tei Irrigation Reservoir is still considerable low. · It
is closer to Route 11 tunnel portal, allows an integrated site formation for
tunnel portal of Tuen Mun Bypass and Route 11. |
Environmental Factors |
· Aboveground
works in Tai Lam Country Park is avoided. · Potential
groundwater infiltration, lead to potential drawdown of surface water bodies
and groundwater. Impact can be managed by good practices and mitigation
measures. |
· Aboveground
works in Tai Lam Country Park is avoided. · Potential
groundwater infiltration, lead to potential drawdown of surface water bodies
and groundwater. Impact can be managed by good practices and mitigation
measures. |
· Aboveground
works in Tai Lam Country Park is avoided. · Potential
groundwater infiltration, lead to potential drawdown of surface water bodies
and groundwater. Impact can be managed by good practices and mitigation
measures. |
Other Factors |
· Limited
local community and hence minimal impact to the stakeholder. |
· Limited
local community and hence minimal impact to the stakeholder. |
· Limited
local community and hence minimal impact to the stakeholder. |
Table 2.4 Summary
of Recommended Alignment Options for Sub-Areas
Sub-area of the
Alignment |
Recommended Option |
Near Wu Shan Road |
Option A2 |
At Sam Shing Estate |
Option B2 |
Near Lam Tei Irrigation
Reservoir |
Option C3 |
Table 2.5 Evaluation for Southern Interchange and
Portal
Consideration |
Option S1 |
Option S2 |
Option S3 |
Engineering Factor |
· Minimal
clearance underneath existing under pass with live traffic · Demolition
of existing footbridge and modification to existing bridge. |
· Marginal
clearance under sewage culvert. · Preserve
existing footbridge and bridge. |
· Balance
between clearance to sewage culvert and clearance to underpass. · Preserve
existing footbridge and bridge. |
Environmental Factor |
· Require
demolition of existing footbridge which additional noise impact and C&D
materials will be generated. |
· Demolition
of existing footbridge can be avoided. |
· Demolition
of existing footbridge can be avoided. |
· Greater
encroachment to Tuen Mun Area 46. · Constraint
to future Lung Mun Road upgrading at roundabout. · Insufficient
tunnel portal weaving length, insufficient length for placement of
directional sign. · Buses
using the Project cannot use bus-bus interchange. · No
encroachment on existing EMSD Tuen Mun Vehicle Servicing Station. |
· Encroachment
to Tuen Mun Area 46 has been minimised. · Embed
to future Lung Mun Road upgrading at roundabout. · Sufficient
tunnel portal weaving length, sufficient length for placement of directional
sign. · Buses
using the Project can use bus-bus interchange. · Permanent relocation of the existing EMSD Tuen Mun Vehicle Servicing
Station is required; temporary re-provisioning may also be required. |
· Encroachment
to Tuen Mun Area 46 has been minimised. · Embed
to future Lung Mun Road upgrading at roundabout. · Sufficient
tunnel portal weaving length, sufficient length for placement of directional
sign. · Buses
using the Project can use bus-bus interchange. · Permanent relocation of the existing EMSD Tuen Mun Vehicle Servicing
Station is required; temporary re-provisioning may also be required. |
Table 2.6 Summary of Consideration for Northern Portal
Consideration |
Option N1 |
Option N2 |
Option N3 |
Engineer Factors |
· The
tunnel portals are placed closest to then dam of Lam Tei Irrigation
Reservoir, with higher construction risk comparatively. |
· The
tunnel portals are placed close to the dam of Lam Tei Irrigation Reservoir
with higher construction risk comparatively. |
· The
tunnel portals are placed furthest away from the dam of Lam Tei Irrigation
Reservoir with lower construction risk comparatively. |
Environmental Factors |
· Encroachment
of the tunnel portal to Tai Lam Country Park · Minimised
potential impacts with separate distance from air and noise sensitive
receiver. |
· No
encroachment of the tunnel portal to Tai Lam Country Park · Minimised
potential impacts with separate distance from air and noise sensitive
receiver. |
· No
encroachment of the tunnel portal to Tai Lam Country Park · Minimised
potential impacts with separate distance from air and noise sensitive
receiver. |
Other Factors |
· Additional
land requirement would result in disturbances near Lam Tei Irrigation
Reservoir and Lam Tei Quarry. |
· Additional land requirement would
result in disturbances near Lam
Tei Irrigation Reservoir and Lam Tei Quarry. |
· No
Additional land requirement that would result in disturbances near Lam Tei
Irrigation Reservoir and Lam Tei Quarry. |
Table 2.7 Evaluation for MVB Schemes
Evaluation Criteria |
Preliminary Scheme |
Alternative Scheme 1 |
Alternative Scheme 2 |
Engineering Factors |
·
Permanent reclamation
required for shaft excavation and MVB construction. ·
Significant reconfiguration of the Tuen Mun Typhoon Shelter is
required. ·
No adit/carven
construction is required. ·
MVB construction can only be commenced after TBM retrieval. |
·
No
reclamation required for shaft excavation. ·
An extensive underground excavation and site
formation is required. · Adit/carven construction is required. · Interface
in carvern between parallel activities: drill-and-blast works, MVB
construction and TMB retrieval. Allow enhancement programme and decrease
risk. ·
Reprovisioning of Wah Fat Playground during construction phase is
required. |
·
No
reclamation required for shaft excavation. ·
Site formation is required. ·
Adit but
no carven construction is required. ·
Decoupling
of MVB construction and tunnelling works: parallel activities without
interface. Allow enhancement programme
and decrease risk. ·
Reprovisioning of Wah Fat Playground during construction phase is
required. |
Environmental Factors |
·
Ventilation
shaft will be located at breakwater and away from air sensitive receivers,
resulting in less environmental impacts. ·
Permanent
reclamation will be required and may result in additional environmental
impact particularly on water quality, marine ecology and fisheries. ·
Tree
felling is not required. ·
Visual impact caused by the MVB to the Sam Shing Area. ·
Disposal of sediment generated from reclamation and dredging works. |
·
Permanent
reclamation will not be required, and hence associated impacts on water
quality, marine ecology and fisheries are not anticipated. ·
Tree
felling required for site formation at Wah Fat Playground. ·
Less
visual impact caused by the MVB underground structures at Wah Fat Playground. ·
Larger
underground excavation volumes, more C&D materials are expected to be
generated compared to Alternative Scheme 2. |
·
Permanent
reclamation will not be required, and hence associated impacts on water
quality, marine ecology and fisheries are not anticipated. ·
Tree
felling required for site formation at Wah Fat Playground. ·
Visual impact caused by to MVB half-submerged structure at Wah Fat
Playground area. ·
Smaller
underground excavation volumes and less C&D materials are expected to be
generated compared to Alternative Scheme 1. ·
Aboveground
works located further away from Tai Lam Country Park as compared with
Alternative Scheme 1. |
Other Factors |
· More
flexibility and easier for replacement / easier planning and logistic support
for the installation of the Mechanical, Electrical Plumbing (MEP) plants for
an aboveground building during operation. · Larger
fan pressure loss and more energy consumption as long ventilation adit is
required. ·
Direct EVA access to the MVB and
direct route to reach the Ultimate Place of Safety during operation. |
· More
complexity and difficulty for replacement/ more challenging logistic support
for the installation of MEP plants for an aboveground building during
operation. · Smaller
fan pressure loss and less energy consumption as long ventilation adit is
omitted. ·
Indirect EVA access to the MVB and
indirect route to reach the Ultimate Place of Safety during operation. |
· More
flexibility and easier for replacement/ easier planning and logistic support
for the installation of the MEP plants for an aboveground building during
operation. ·
Smaller fan pressure loss and less
energy consumption as long ventilation adit is omitted. ·
Direct EVA access to the MVB and
direct route to reach the Ultimate Place of Safety during operation. |
Table
2.8 Evaluation
for Options of SVB
Consideration |
Preliminary Scheme |
Alternative Scheme 1 |
Alternative Scheme 2 |
Engineering Factors |
· Very low ground cover between the TMB tunnel and
TM-CLKT (less than 3m). |
· More ground cover between the TMB project
and TM-CLKT and roundabout. |
· It is located right above the TM-CLKT, with a low clearance with it, which
can be managed by applying the appropriate mitigation measures. · Close
to the existing pylons on the hillside, which can be managed by applying the
appropriate mitigation measures. |
Environmental Factors |
· Trees and vegetation close at the
hillside will not be disturbed. |
· Trees
and vegetation close to hillside will require transplant or felling, disturb
aboveground habitat. |
· Trees
and vegetation close to hillside will be required transplant or fell, disturb
aboveground habitat. · Ventilation shaft more
further up from ground level
with
less impact on the nearby
air quality sensitive receivers, future users and operators. |
Other Factors |
· The location is very close to TM-CLKT portal,
resulting in insufficient separation distance to allow for traffic weaving. · There is no access between the Project and the
existing bus stop. · The
furthest away from the tunnel portal and increase the ventilation adit
length, which results in larger fan pressure loss and more energy
consumption. |
· The scheme does not provide improvement in
connectivity to TM-CLKT and accessibility to the existing bus stop. · Further
away to the tunnel portal and increases the ventilation adit length, which
results in larger fan pressure loss and more energy consumption. |
· This
scheme is located further in the north, allowing sufficient distance between
the Project portal and TM-CLKT portal for a better connectivity, avoiding
traffic weaving. · The
scheme is located further in the north, and it improves the connectivity with
the existing Lung Mun Road and especially the accessibility from and to the
existing bus stop. · Closer
to the tunnel portal and minimize ventilation adit length, which results in
smaller fan pressure loss and less energy consumption as long ventilation
adit is omitted. |
Table
2.9 Evaluation
for Options of NVB
Consideration |
Preliminary Scheme |
Alternative Scheme 1 |
Alternative Scheme 2 |
Engineering Factors |
·
Extensive cut
slope area required. |
·
Reduce the need to undergo significant rock cut. |
·
Reduce the need to undergo
significant rock cut. ·
Potential space proofing
and interface problems with the gantry and foundation all lying within the
footprint of the building. |
Environmental Factors |
· More C&D materials are expected to generate
from the extensive rock cut and slope. · Direct disturbance of habitat the NVB area, as it
is located on the natural slope. |
·
Less
C&D
materials are expected as
the need to undergo significant rock cut is reduced. ·
Furthest away from the Tai Lam
Country Park boundary,
avoid disturbance of habitat
at the NVB, and it is located at the existing cut at Lam Tei Quarry. |
· Less
C&D materials are expected as the need to undergo significant rock cut is
reduced. ·
Direct disturbance of habitat the
NVB area, as it is partially located on the natural slope. |
Other Factors |
·
Slope interface
with Route 11. · No Additional land requirement would result in
disturbances near to Lam Tei Irrigation Reservoir and Lam Tei Quarry. |
·
Additional land
requirement would result in disturbances near Lam Tei Irrigation Reservoir
and Lam Tei Quarry. |
· Slope interface with Route 11. · No
Additional land requirement would result in disturbances near Lam Tei
Irrigation Reservoir and Lam Tei Quarry. |
Table 2.10 Summary of Adopted Design Option
TMB |
Recommended Option |
|
Preliminary Alignment Option |
Preliminary
Alignment Option 1 |
|
Sub-area of Preliminary Alignment |
Near Wu Shan Road |
Option A2 |
At Sam Shing Estate |
Option B2 |
|
Near Lam Tei Irrigation
Reservoir |
Option C3 |
|
Southern
Interchange and Portal |
Option S3 |
|
Northern
Portal |
Option N3 |
|
Middle
Ventilation Building (MVB) |
MVB
Alternative Scheme 2 |
|
South
Ventilation Building (SVB) |
SVB
Alternative Scheme 2 |
|
North
Ventilation Building (NVB) |
NVB
Alternative Scheme 1 |
Table 2.11 Consideration for
Magazine Sites
Consideration |
Three Selected Locations |
Engineering
Factors |
·
The
proposed magazine site at Siu Lam utilise the historical magazine for
Express Rail Link project. ·
Utilised
the location at Pillar Point has been carried out of the previous study. ·
Utilised disturbed/ development area to
avoid further site formation works. |
Environmental
Factors |
· Locations selected are generally
disturbed/ developed area, minimised loss of natural habitat during
construction of the magazine. ·
The
locations of the three proposed magazine sites are generally located in the
remote area with low density of receptors, the selected locations ensure
that the magazines serve the work faces closest to the magazine to reduce
the risk to public safety as low as reasonably practicable. |
Other
Factors |
· Located
in government lands. |
Table 2.12 Comparison
of Construction Methods for Tunnel Sections
Construction
Method |
Advantages |
Disadvantages |
Drill-and-Blast /Drill-and-Break |
·
Avoids
aboveground works at Tai Lam Country Park. ·
Avoids direct
environmental impact to Tai Lam Country Park especially terrestrial ecology
aspect. ·
Efficient
excavation method in hard rock conditions (as expected in
Tai Lam Country Park). ·
Minimises impact
to the public during the construction stage. |
·
Potential higher
impulsive vibration impact but with the good practices and mitigation measures, adverse impacts
from impulsive vibration would be insignificant. ·
Potential risk
due to the use of explosives, which has been considered in Section 8. ·
Groundwater
infiltration, lead to potential drawdown of surface water bodies and
groundwater at Tai Lam Country
Park. Impact can be managed by good practices and water control strategies. |
Tunnel Boring Machine (Preferred option for
underneath Tuen Mun Typhoon Shelter to Pillar
Point) |
·
Avoid marine
works such as temporary reclamation and dredging works, also avoid major
environmental impacts on water quality, fisheries, and marine ecology,
disposal of marine sediment at Tuen Mun Typhoon Shelter. ·
Shorten
construction time ·
Minimises
environmental impact associated with aboveground works. ·
Minimises impact
to the public during the construction stage. ·
Able to provide
confinement to prevent surface collapse or water ingress to tunnelling (in
areas under the Tuen Mun Typhoon Shelter). ·
Pre-cast
internals and tunnel segments increase quality control and reduce risk. |
·
Large site
installation required in the temporary condition under construction. ·
Power and other
utility/ supply to the tunnel portal in temporary condition. ·
TBM is
suitable for fractured rock / mixed ground condition. The use of TBM in Tai
Lam Country Park was duly explored but considered not suitable from the
engineering perspective. |
Table 2.13 Key Elements of the Project
Key Element |
Locations |
Description
|
Drill-and-Blast
/ Drill-and-Break Tunnelling |
·
Between Tai Lam Country Park and Tuen Mun Typhoon Shelter
|
·
Tunnel section
underneath Tai Lam Country
Park would be in granite. The depth of this tunnel section would vary between
43 – 465m below local ground (Refer to Section 2.5 and Section 2.6 for details). ·
The longitudinal
profile of the Project is given in Figure 2.10. |
Tunnel
Boring Machine Tunnelling |
·
Between Tuen Mun
Typhoon Shelter and Pillar Point |
·
The section
within Tuen Mun Typhoon Shelter would be approximately 10 – 60m underneath
seabed. ·
The section from
Tuen Mun Area 44 to Pillar Point would be land based and would be
approximately 10 – 60m below local ground (Refer to Section 2.5 and Section 2.6 for details). ·
The longitudinal
profile of the Project presents in Figure 2.10. |
Portal
and Interchange |
·
Northern Portal
at Lam Tei Quarry ·
Southern
Interchange and Portal at TM-CLKT and Lung Mun Road |
·
Aboveground road
structure and link road (Refer to Section 2.5 and Section 2.6 for details). |
Ventilation
Buildings [1] |
·
NVB: at Lam Tei
Quarry |
·
A building
structure with main roof level at approximately 21m above ground level. Other
structures, such as E&M plant, lift shaft structure, ancillary features,
water tanks, etc. are located above the main roof. Exhaust discharge from louver of the
E&M plant room above the roof. |
·
MVB: at Wah Fat
Playground |
·
A building
structure with the main roof level at approximately 19m above ground level.
Exhaust discharge from wall louver of the E&M plant room at the top
floor. Other structures, such as
E&M plant, lift shaft structure, ancillary features, water tanks, etc.
are located above the main roof. |
|
·
SVB: at hillside
of TM-CLKT northbound. |
·
A building structure
with the main roof level at approximately 24m above ground level. Exhaust
discharge from wall louver of the E&M plant room at the top floor. Other structures, such as E&M plant,
lift shaft structure, ancillary features, water tanks, etc. are located above
the main roof. |
|
Highway/Tunnel
Operation Area (including satellite control building, administration
building, maintenance compound, recovery/ supporting area and other highway /
tunnel operation areas in Lam Tei) |
·
Satellite control
building at the northern portal |
·
An aboveground
building structure. |
·
Administration
building and maintenance compound at the southern interchange |
·
An aboveground
building structure. |
|
·
Recovery area, training
ground and other supporting area for highway / tunnel operation at the
southern interchange. |
·
At-grade area for
tunnel operation. |
|
·
Highway / tunnel
operation area at the northern portal in Lam Tei |
·
At-grade area for
tunnel operation. |
|
Proposed
Works Area for Reprovision of affected facilities |
·
Temporary
re-provisioning of basketball court and public toilet at the carpark near Sam
Shing Hui (KW carpark) |
·
The Wah Fat
Playground would be used at construction works area for MVB construction. ·
The affected
basketball court and public toilet at Wah Fat Playground would be temporary
re-provided. ·
After the
completion of construction works, the Wah Fat Playground will be re-instated
with more spacious area. ·
The temporary
basketball court and public toilet will be demolished. |
·
Temporary
re-provisioning of carparking area at the existing parking lots and open area
with planters in Fung On Street. |
·
Proposed works area
for re-provisioning of temporary carparking area. ·
After the
reinstatement of KW carpark, the works area at Fung On Street will be
reinstated. |
|
·
Temporary
re-provisioning of EMSD vehicle servicing centre at the former TM-CKLT Site
Office. |
·
The southern
interchange will encroach into the existing EMSD Tuen Mun Vehicle Servicing
Station and temporary re-provisioning will be required. |
|
·
Wah Fat
Playground Works Area. |
·
Construction site
of MVB and site for TBM retrieval points and storage spoils and construction
material. |
|
·
Area at the
former Girl Guide Association (GGA) Campsite for site office or other project
uses. |
·
The site was
established in late 1950s. Some restoration and repair of building will be
carried for site office and other project uses. ·
No demolition and
removal of structures at the area. |
|
·
Temporary works
area at Tuen Mun West (near Mong Fat Street). |
·
Storage of construction
material and equipment, spoil storage area, slurry treatment plant and site
office. |
|
Barging Point |
·
East side TM-CLKT
northern landfall vertical seawall. |
·
4 berths for
delivery of construction waste/ material. ·
Barging point
facilities s for marine delivery, storage construction material, spoil storage area and plants laydown area
and site office |
Three
magazines (for shared use with Route 11) |
·
At Lam Tei Quarry
(underground), Pillar Point and Siu Lam. |
·
Storage of
explosives. |
Note:
[1] Roof level
refers to the approximate main roof finish floor level, excluding any E&M
plant, lift shaft structure, ancillary features, water tanks, etc. above the
main roof.
Table 2.14 Summary of the
Key Construction Works for the Project
Description |
Tentative
Construction Programme |
Re-provisioning works of affected facilities (at
KW Carpark and Fung On Street). |
2025 Q2 to 2025 Q4 |
Site formation works, construction northern and
southern portals, and underground magazine site, setting up of the slurry
treatment plant. |
2025 Q2 to 2027 Q2 |
TBM and drill-and-blast / drill-and-break
tunnelling works, building works, highway/tunnel operation area, road
connecting to TM-CLKT. |
2026 Q2 to 2031 Q3 |
Route-wide tunnel E&M works, thermal barrier,
tunnel cladding, route-wide TCSS works and testing and commissioning for TMB. |
2027 Q3 to 2033 Q3 |
Table 2.15 Summary of Potential Concurrent Projects
Description |
Tentative Programme |
Potential Cumulative Impacts |
||||
Start |
Complete |
Reference for
Programme |
Construction
Stage |
Operation
Stage |
||
Route 11 (Section between Yuen Long and North
Lantau) |
A new highway with an approximate length of 20km
between NWNT and North Lantau. |
2025 |
2033 |
LC Paper No. CB(4)1046/2022(01) |
Cumulative dust
and noise impacts were evaluated in Section 3 and Section 4 of this EIA Report respectively. Potential risk
due to transportation of explosives was evaluated in Section
8 |
Cumulative air
quality and noise impacts were evaluated in Section 3 and Section 4 of this EIA Report respectively. Traffic
noise and vehicular emission caused by induced traffic is anticipated. |
Traffic Improvement Scheme in Tuen Mun- Widening
and Addition of Slip Roads at Lung Fu Road/ Tuen Mun Road/ Wong Chu Road/ Hoi
Wing Road |
Road improvement works to increase road capacity |
2024 |
2031 |
Approved EIA the Concurrent Project [AEIAR-251/2023] |
Cumulative dust
impacts were evaluated in Section 3 of this EIA Report |
Cumulative air
quality impacts were evaluated in Section 3 of this EIA Report. Vehicular
emission caused by induced traffic is anticipated. |
Underground Quarrying at Lam Tei, Tuen Mun |
Development of an underground quarry |
2024/25 |
2025/27 |
Project Profile of the Concurrent
Project [PP-643/2022] |
Cumulative dust and noise impacts were
evaluated in Section 3 and
Section
4 of
this EIA report respectively. Potential risk
due to transportation of explosives was evaluated in Section 8 |
There may be potential cumulative air
quality and noise impact. However, details of the development (including its
emission sources) are not available during the preparation of this EIA study
for detailed impact assessment. |
Cycle Track
between Tsuen Wan and Tuen Mun (Tuen Mun to So Kwun Wat Section) |
Development of a new cycling track |
2023 |
2026 |
Approved EIA the Concurrent Project [AEIAR-239/2022] |
Cumulative dust and noise impacts were
evaluated in Section 3 and
Section
4 of
this EIA report respectively. |
Not anticipated in view of the nature of
the concurrent project. |
Cycle
Track between Bayview Garden and So Kwun Wat [1] |
Development
of a new cycling track |
Under
Planning [2] [3] |
Under
Planning [2] [3] |
CEDD
Project Page on Cycle Track between Bayview Garden and So Kwun
Wat |
There
may be potential cumulative dust and noise impact. However, details of
construction programme and plant inventory is not available during the
preparation of this EIA study for detailed impact assessment. |
Not
anticipated in view of the nature of the concurrent project. |
Reprovision
of Tuen Mun Swimming Pool and Tuen Mun centre Golf Centre Practice Green |
Reprovision
of recreation facilities |
Commenced |
2026 |
Approved EIA of Tuen Mun South Extension (AEIAR-246/2022) |
Potential risk due to transportation of
explosives was evaluated in Section 8. |
Not anticipated in view of the nature of the
concurrent project. |
Railway
line extension of Tuen Ma Line |
2023 |
2030 |
As confirmed with the respective Project
Proponent |
The concurrent project is located within 500m area
from the underground alignment of TMB, no adverse cumulative impact is
anticipated. |
Not anticipated in view of the nature of the
concurrent project. |
|
Planned Property Development at Area 16, Tuen Mun
|
Potential
residential development |
Under
planning [2] |
Under
planning [2] |
Approved EIA of Tuen Mun South Extension
(AEIAR-246/2022) |
The underground alignment of TMB is located within
500m from the concurrent project, no adverse cumulative impact is
anticipated. |
The underground alignment of TMB is located
within 500m from the concurrent project, no adverse cumulative impact is
anticipated. Vehicular emission caused by induced traffic is anticipated. |
Sports Ground and Open Space with Public Vehicle
Park in Area 16, Tuen Mun |
Proposed
Ground and Open Space |
2024-25 |
2028-29 |
AchSD
Project Page on Sports Ground and Open Space with Public Vehicle
Park in Area 16, Tuen Mun
[4] |
The underground alignment of TMB is located
within 500m from the concurrent project, no adverse cumulative impact is
anticipated. |
The underground alignment of TMB is located
within 500m from the concurrent project, no adverse cumulative impact is
anticipated. Vehicular emission caused by induced traffic is anticipated. |
Public
Housing Developments at Tuen Mun Central- Wu Shan Road |
Development
of public housing sites to alleviate territorial housing needs |
Commenced |
2027 |
N/A |
The underground alignment of TMB is located within
500m from the concurrent project, no adverse cumulative impact is
anticipated. |
The underground alignment of TMB is located within
500m from the concurrent project, no adverse cumulative impact is
anticipated. Vehicular emission caused by induced traffic is anticipated. |
Widening of
Yuen Long Highway (Section between Lam Tei Quarry and Tong Yan San Tsuen
Interchange) |
Highway improvement
works to increase road capacity |
Under
planning [2] |
2036 |
Project Profile of the Concurrent
Project [PP-647/2022] |
Located more than 500m from the Project, no
adverse cumulative impacts are anticipated. |
Traffic noise and vehicular emission caused by
induced traffic is anticipated. |
Widening
of Castle Peak Road - Castle Peak Bay |
Road
improvement works to increase road capacity |
Commenced |
2024 |
HyD
Project Page on Widening of Castle Peak Road - Castle Peak Bay [5] |
There
is no overlap of construction period. Therefore, cumulative impact during
construction phase is not anticipated. |
Traffic noise and vehicular emission caused by
induced traffic is anticipated. |
Widening
of Fuk Hang Tsuen Road (Between Castle Peak Road – Lam Tei and Fuk Hang Tsuen
Lane) |
Road
improvement works to increase road capacity |
Commenced |
2025 |
HyD Project Page on Widening of Fuk Hang Tsuen
Road (Between Castle Peak Road – Lam Tei and Fuk Hang Tsuen Lane) [6] |
There is no overlap of construction period.
Therefore, cumulative impact during construction phase is not anticipated. |
Traffic noise and vehicular emission caused by
induced traffic is anticipated. |
Land
development for housing and economic purposes |
Under
planning [2] |
Under
planning [2] |
As confirmed with the respective Project
Proponent |
Details of construction programme and plant
inventory is not available during the preparation of this EIA study for
detailed impact assessment. |
Vehicular emission caused by induced traffic
is anticipated. |
|
Relocation of Tuen Mun
Water Treatment Works to Caverns |
Relocation of a water
treatment works to cavern |
Under
planning [2] |
Under
planning [2] |
N.A. |
There
may be potential cumulative dust and noise impact. However, details of
construction programme and plant inventory is not available during the
preparation of this EIA study for detailed impact assessment. |
Not
anticipated in view of the nature of the concurrent project. |
Lung Kwu Tan Reclamation and the Re-planning of Tuen Mun West Area |
Land
development for economic purposes and residential-oriented community |
Under
planning [2] |
Under
planning [2] |
N/A |
Details of construction programme and plant
inventory is not available during the preparation of this EIA study for
detailed impact assessment. |
Details of implementation programme is not
available during the preparation of this EIA study for detailed assessment. |
Notes:
[1] The Project
location is yet to be confirmed at this stage. Location of the Project is
therefore not shown in Figure 2.11.
[2] For
concurrent project which is still under study and under planning, any potential
cumulative impact would be addressed in its respective EIA study.
[3] https://www.twtm-cycletrack.hk/en/
[4] https://www.archsd.gov.hk/en/projects/capital-projects-under-detail/278RS.html
[5] https://www.hyd.gov.hk/en/our_projects/road_projects/6853th/index.html
[6] https://www.hyd.gov.hk/en/our_projects/road_projects/6852th/index.html
Table 2.16 Summary
of Key Concerns from Public Consultation and Follow Up Actions
Key Concerns / Issues |
Follow
Up Actions to be Taken |
Road traffic noise impact due to the additional
traffic generated from the Project |
·
Operation phase noise
impact assessment and associated cumulative impacts have been conducted to
comply with the requirements set out in the EIAO-TM. Suitable mitigation
measures will be implemented during operation stages as necessary. ·
Please refer to Section 4 for
road traffic noise impact assessment. |
Adverse air quality impact from traffic and
ventilation building during operation phase |
·
Operation phase
air quality impact assessment and associated cumulative impacts have been
conducted to comply with the requirements set out in the EIAO-TM. Suitable
mitigation measures will be implemented during construction and operation
stages as necessary. ·
Please refer to Section 3 for
operational air quality impact assessment. |
Tunnel construction method at the typhoon shelter
to minimize environmental impact |
·
TBM tunnelling
will be adopted to construct the tunnel section within Tuen Mun Typhoon
Shelter instead of cut-and-cover/immersed tube to minimize the environmental
impact and social impact to the stakeholders of the typhoon shelter. |
Adverse environmental impact on reclamation |
·
The deletion of
the reclamation scheme and the relocation of MVB to for the Project have
totally avoided the reclamation and the associated dredging works within Tuen
Mun Typhoon Shelter. ·
The use of TBM
for the construction of tunnel section within Tuen Mun Typhoon Shelter has
avoided reclamation. |
Hazard to associated with onsite magazine and
explosive transportation |
·
The potential
impacts of hazard-to-life have been evaluated in compliance with the
requirements set out in the EIAO-TM. Suitable mitigation measures will be
implemented during construction stage. ·
Please refer to Section 8 for
hazard-to-life assessment. |
Generation and disposal of a large amount of
construction and demolition (C&D) materials |
·
The waste
management implications and quantity of C&D materials have been evaluated
in compliance with the requirements set out in the EIAO-TM. Suitable
mitigation measures such as on-sorting, re-use, trip-ticket system will be
implemented during construction stage. ·
Please refer for
Section
6 for waste implication management. |
Landfill gas hazard from nearby restored Pillar
Point Valley Landfill |
·
During the
detailed design stage, a review of this preliminary qualitative risk
assessment will be carried out and a detailed Qualitative Landfill Gas Hazard
Assessment (QLFGHA) will be prepared. The detailed QLFGHA Report together
with the detailed design of landfill gas protection measures will be
submitted to EPD for vetting. ·
Mitigation
measures as recommended in the EIA and detailed QLFGHA will be
implemented. As such, the potential risk of landfill gas migration
to the respective targets would be minimal. ·
Please refer to Section 9 for
the mitigation measures for minimizing landfill gas hazard. |
Potential hydrological impacts on the natural
streams and reservoirs |
·
Appropriate
water control strategies will be implemented to minimize the groundwater
infiltration during the tunnel construction. ·
Please refer to Section 5 for
details of mitigation measures for minimizing groundwater infiltration. ·
As an additional
precautionary measure, surface water level monitoring at natural watercourses
within Tai Lam Country Park, Lam Tei Irrigation Reservoir, and in the
vicinity of the tunnelling works would be conducted during the construction
and operation stages. ·
Please refer to Section
10 for the details of monitoring on surface water level of
natural watercourses. |
Loss of natural habitats |
·
Drill-and-blast/drill-and-break
method will be adopted to construct tunnel section and the temporary
underground adit underneath Tai Lam Country Park. No aboveground works within Tai Lam Country Park will be conducted.
Consideration has been taken to maximize the distance in between the
project’s works and the Tai Lam Country Park to further avoid and minimise
indirect impacts on the Country Park. ·
Please refer to Section
10 for details ecological impact assessment. |
The potential vibration of the land due to
construction might have an impact to wildlife and plants |
·
Drill-and-blast/drill-and-break
tunnel section would be in granite and with sufficient depth below ground,
together with the good practices and mitigation measures, adverse impacts
from impulsive vibration would be insignificant. |
Interfacing issues with Route 11 and other
concurrent projects |
·
The cumulative
impacts have been assessed in the EIA study (except for the concurrent projects under planning where potential
cumulative impacts would be addressed in their respective EIA studies). |
Table
2.17 Key Recommended Mitigation Measures/ Good Site
Practices/ Enhancement Measure and their Associated Benefit
Environmental Aspect |
Key
Recommended Mitigation Measures / Good Site Practices/ Enhancement Measure |
Associated
Benefits |
Air Quality
Impact |
· Adopt
dedicated spoil transportation routes away from the identified Air Sensitive
Receivers (ASRs) as practicable. · Install
3-sided screen with top cover and provide water sprays at the unloading point
to barges at the barging facility. · Avoid
using exempted NRMM as much as practicable and when alternatives are
available from the local market at the time of construction. ·
Site
hoardings of not less than 2.4m high should be provided as far as practicable
along the site boundary with provision for public crossing. Taller site hoardings may be considered for ASRs in close vicinity to
the site boundary, subject to actual site constrains and detailed design.
Good site practice shall also be adopted by the Contractor to ensure the
conditions of the hoardings are properly maintained throughout the
construction period. · Adopt
water spraying system for areas with heavy construction activities. · Connect
construction plant and equipment to mains electricity supply, and avoid use
of diesel generators and diesel-powered equipment as far as practicable to
minimize air quality impact arising from construction machinery. · Close
the impermeable blast covers at tunnel portals prior to blasting works in
order to ensure blasting works in a fully enclosed environment. · Water
spray before open blasting and on blasted material prior to transportation. · Provide
vehicle washing facilities at the exit of the barging facility and exit of
works sites. · The
engine of the barge shall be switched-off during berthing as far as
practicable. Provision of on-shore power supply shall also be considered
wherever possible to minimize air quality impact from the marine vessels, with
consideration of actual site constraints or circumstances to be further
reviewed during detail design stage. · Close
liaison between the contractors of other concurrent projects and the Project
would be maintained to minimise dusty activities to be conducted concurrently
as far as practicable. ·
During the subsequent design stage and the
operational stage, the ventilation engineer should conduct reviews on the
ventilation scheme covering different periods of a day, taking into account
the contemporary circumstance such as latest traffic forecast, traffic
composition, update on the ambient air quality, etc., and then review and
update the air quality assessment as necessary to demonstrate full compliance
of the AQO. These reviews would allow
the designer and operator to optimize the operation of the ventilation system
without compromising the compliance of AQO. · The planned
air sensitive uses within the highway / tunnel operation and maintenance
facilities of the TMB shall be properly designed such that any openings,
openable windows, and/or fresh air intakes will be located and avoided from
the predicted exceedance zone at 1.5mAG. Further review of the layout and
design of operation area will be conducted in Detailed Design Stage to ensure
compliance of the AQOs. |
·
Protect air
sensitive receivers (ASRs) by reducing fugitive dust emissions; and ·
Ensure compliance with the requirements in
Annex 4 of the EIAO-TM at the ASRs. |
Noise Impact |
· Follow
good site practices to limit construction noise emissions at the sources. · Use
of quality powered mechanical equipments and quieter construction methods. · Use
of temporary noise barriers and noise enclosures to screen noise from
relatively static PMEs. · Install
acoustic tunnel door or enclosure at the tunnel portal opening for tunnelling
activities. · Install
temporary noise enclosures for the construction sites near Wah Fat
Playground. · Alternative
use of plant items within one worksite, wherever practicable. · Provide
mitigation measures for fixed noise sources (e.g. quieter equipment,
silencer, barrier and enclosure) with reference to EPD’s “Good Practices on
Ventilation System Noise Control”. · Orientate
louvres away from adjacent NSRs, preferably onto main roads which are less
noise sensitive. ·
Select façade for ventilation shafts with
adequate sound insulation properties. |
·
Protect noise
sensitive receivers (NSRs) by reducing construction and operational noise. ·
Ensure compliance
with the respective road traffic noise requirements at neighbouring NSRs. ·
Ensure compliance
with the respective fixed noise requirements at neighbouring NSRs. |
Water Quality Impact |
· Follow Best Management Practices (BMPs) of
mitigation measures in controlling water pollution and good site management
as specified in the Professional Persons Environmental Consultative Committee
(ProPECC) Practice Note (PN) 1/94 “Construction Site Drainage” and
Environment, Transport and Works Bureau (ETWB) Technical Circular (Works)
(TC(W)) No. 5/2005. · Adopt
suitable water control strategies as far as practicable, including probing
ahead, pre-grouting and post-grouting, during tunnelling works. · Control
impact on groundwater through adopting toe grouting and installation of
recharge well during temporary dewatering for excavation works. · Provide
adequate and sufficient portable chemical toilets for construction workforce
and temporary storage tank for collection of wastewater. · Carry
out construction works close to inland waters in dry season as far as
practicable. · Conduct
watercourse removal and flow diversion in dry season as far as practicable. ·
Size all vessels
to maintain adequate clearance between vessels and the seabed in all tide
levels. ·
Control loading
of barges and hoppers to prevent splashing of materials into the surrounding
water. ·
Install and
maintain roadside gullies and oil / grease interceptors for removal of
pollutants from storm water as necessary. ·
Collect and treat wastewater generated by
washing and maintenance activities, and discharge to public sewerage system
properly. |
·
Protect the
neighbouring Water Sensitive Receivers (WSRs) during construction phase. |
Waste Management Implications |
·
During design
phase, a Construction and Demolition (C&D) Material Management Plan
(C&DMMP) will be prepared in accordance with Section 4.1.3 “Construction
and Demolition Materials” of the Project Administration Handbook for Civil
Engineering Works and will be submitted together with the EIA Report to the
department Vetting Committee for endorsement and then to Public Fill
Committee (PFC) for approval. ·
Carry out on-site
sorting, re-use and recycled C&D materials, implement a trip-ticket
system for each works contract to in
accordance with Development Bureau TC(W) No. 6/2010 ensure
that the disposal/handling of C&D materials is properly documented and
verified, so as to avoid the illegal dumping and landfilling of C&D materials. ·
All dump trucks
and vessels engaged on site should be equipped with Global Positioning System
(GPS) or equivalent automatic system for real time tracking and monitoring of
their travel routings and parking locations. ·
Chemical wastes
(e.g. spent lubricant oil) should be recycled at an appropriate facility as
far as possible, while the chemical waste that cannot be recycled should be
disposed of at either the CWTC, or another licensed facility, in accordance
with the Waste Disposal (Chemical Waste) (General) Regulation. ·
Standard formwork
should also be used as far as practicable in order to minimise the arising of
non-inert C&D materials. The use of more durable formwork (e.g. metal
hoarding) or plastic facing should be encouraged in order to enhance the
possibility of recycling. The purchasing of construction materials should be
carefully planned in order to avoid over ordering and wastage. ·
Implement an
education programme for workforce relating to avoiding, reducing, reusing and
recycling general waste. Participation in a local collection scheme should be
considered by the Contractor to facilitate waste reduction. ·
Measures and good
site practices to be implemented at the works area during construction
(Details to refer to Section 6). |
·
Minimise waste
generation ·
Ensure proper
handling of chemical waste ·
Ensure the
C&D materials are disposed to the designated outlets |
Land Contamination |
·
Prior to the
commencement of the site investigation (SI) works, review the Contamination
Assessment Plan (CAP) provided in Appendix 7.1 and conduct site re-appraisal to confirm whether
the proposed SI works (e.g. sampling locations, testing parameters etc.) are
still valid, and to confirm the appropriate RBRGs land use scenario for the
development. ·
Should any
changes in operation which lead to any new or the relocation of contamination
hotspots or occurrence of spillage or accident be found in the review,
supplementary CAP(s), presenting the findings of the review, the latest site
conditions and updated sampling strategy and testing protocol, should be
submitted to EPD for approval. ·
The SI works
should be carried out according to EPD’s approved CAP(s). ·
Contamination
Assessment Report(s) (CAR(s)) should be prepared to present the findings of
the SI works and to discuss the presence, nature and extent of contamination.
If contamination is identified in the CAR(s), Remediation Action Plan(s)
(RAP(s)) which provides details of the remedial actions for the identified
contaminated soil and/or groundwater should be developed prior to
construction works at the concerned areas. Submission to EPD for approval of
the supplementary CAP(s), CAR(s) and, if required, RAP would be carried out
in stages according to the programme of TMB. ·
If required,
carry out soil/groundwater remediation works according to EPD approved RAP(s)
and submit Remediation Report(s) (RR(s)) afterwards for EPD approval prior to
the commencement of construction works at the contaminated areas. |
·
Land
contamination issues could be resolved before commencement of construction
works |
Hazard to Life |
· Reduce
the amount of combustibles in the cabin of truck. The fuel carried in the
fuel tank should also be minimized to reduce the duration of any fire. · Implement
defensive driving attitude and dedicate training programme for both driver
and his attendants. · Transport
the required quantity of explosive for a particular blast. · Combine
explosive deliveries for a given work area as far as practicable. · Maintain
a minimum headway between two consecutive truck convoys of 10 minutes
whenever practicable. · Implement
a better emergency response and training to ensure adequate fire
extinguishers are used and attempt is made to evacuate the area of the
incident or securing the explosive load if possible. · Equip
bigger capacity AFFF-type extinguishers on all explosive vehicles. · Implement
good practices as per Practice Note for Authorized Persons and Registered
Structural Engineers – Control of Blasting (APP-72), and Mines Division
Guidance Note Nos. GN 8 How to Apply for a Mode A Licence for Storage of
Schedule 1 Dangerous Goods (Blasting Explosives) and GN 3 Application and
Handling of a Conveyance Permit. ·
Formulate a Hazard Management Plan with a
view to aligning the understanding of the risk of the three projects (i.e.
Route 11, Tuen Mun Bypass (TMB) and Lam Tei Underground Quarrying (LTUQ)) so
that all the working populations at Lam Tei Quarry area, which includes the
workforce induced under the construction and operational stage of three
projects, could be considered as on-site populations in the QRA for all the
three projects. The measures
stipulated in the Hazard Management Plan may include, but not limited to, the
adjustment of the blasting schedules of the three projects to minimize the
potential cumulative impact, provision of common trainings and drills to the
workforce of all the three projects, etc. The Hazard Management Plan, which
would be agreed among the three projects, would be submitted to EPD for
agreement prior to the tender invitation of construction phases of Route 11,
TMB and LTUQ, whichever is earlier. |
·
Protect nearby
sensitive receivers from adverse impacts due to transportation, overnight
storage and use of explosive for blasting. |
Landfill Gas Hazard |
·
Implementation of
appropriate safety measures during construction works to minimise the risk of
fire and explosions and asphyxiation of works, especially in confined space. ·
Periodically
during ground-works construction, the works area should be monitored for
methane, carbon dioxide and oxygen using appropriately calibrated portable
gas detection equipment. ·
All access to
confined spaces should be restricted only to authorized personnel and should
be informed of the landfill gas hazard.
No general public should be permitted or allowed to access the service
voids, manholes, chambers or wells. ·
During operation,
regular monitoring of landfill gas should be conducted at buildings and
enclosures (e.g. proposed Administration Building, Maintenance Compound,
temporary re-provisioning of EMSD servicing centre, service manholes, etc.)
within the Consultation Zone to verify the effectiveness and to ensure the
continued performance of the implemented protection measures. |
·
Minimise the risk
of fire and explosions and asphyxiation of works |
Ecological Impact (Terrestrial) |
·
No aboveground
works at the recognized sites of conservation importance (including Lam Tei
and Yick Yuen Conservation Area and Tai Lam Country Park). A buffer clearance
between the site formation works at northern portal and Tai Lam Country Park has been considered.
Provision of screening (e.g. hoarding) during construction phase is
recommended to confine the proposed works within Project footprint and hence
outside Tai Lam Country Park to avoid disturbance to adjacent habitats from
the construction phase activities. ·
Shifting the link
roads and the mainline eastward away from the Lam Tei Irrigation Reservoir so
as to allow integrated site formation for tunnel portals of TMB and which can
also reduce environmental impact associated with site formation. ·
Shifting the
works area at Wah Fat Playground away from the perennial stream where two
freshwater crab species of conservation importance were recorded. ·
Upon the
completion of construction works, the proposed works area and magazine sites
would be decommissioned and reinstated to its original condition in
principle. ·
Detailed vegetation
survey should be conducted within mixed woodland and shrubland/grassland at
Pillar Point and near Wah Fat Playground prior to the commencement of
construction activities to confirm the presence of flora species of
conservation interest. Transplantation
and/or mitigation measures would be recommended as far as possible (Details
to refer to Section 10). ·
Prior to
commencement of the stream diversion and construction works near Wah Fat
Playground, an update Freshwater Crab survey should be conducted and cover
the stretch of the watercourse S2 and S2A.
Should species of conservation importance be found within the affected
watercourse sections, a Freshwater Crab Translocation Plan should be
prepared. Freshwater crab translocation should be conducted to move the
affected individuals from the Project area to suitable recipient site(s)
(Details to refer to Section
10). ·
Measure and good
site practices to be implemented at the works area during construction
(Details to refer to Section
10). ·
Stream diversion
works with green channel design elements incorporated will be carried out to
divert any water flow from the upper sections of the watercourses within
Project Area (i.e. S1, S2 and S3) to the lower sections of the watercourses
with similar ecological features and/or hydrology setting outside the Project
Area so as to maintain the flow between unaffected sections of the stream and
to avoid excessive water flow entering the construction area. Detailed design
of any stream diversion should follow the guidelines in ETWB Technical
Circular (Works) No. 5/2005 (Protection of natural streams/rivers from
adverse impacts arising from construction works) and appropriate construction
methods should be used. ·
Adopt
suitable water control strategies, which are applicable to both TBM
tunnelling and drill-and-blast/drill-and-break tunnelling, as far as
practicable. (Details to refer to Section
5.7.2). ·
Compensatory
woodland planting is suggested to mitigate the loss of approximately ~2.2ha
of mixed woodland. (Details to refer
to Section 10) |
·
Minimise direct
and indirect impact to the habitat and species of conservation importance ·
Minimise physical
disturbance to the surrounding habitats |
Landscape and Visual Impacts |
·
Tree protection
works and tree transplantation to be undertaken in accordance with DEVB TC(W)
4/2020 on “Tree Preservation”. In accordance with DEVB TC(W) No. 4/2020, the
compensatory planting proposal should have the basic primary objective of
planting compensatory trees in a ratio not less than 1:1 in terms of quantity
as far as practicable. ·
Construction area
control, where possible, to ensure that the landscape and visual impacts
arising from the construction activities are minimized. ·
Advance
Implementation of Mitigation Planting. ·
Decorative screen
hoarding will be erected along areas of the construction works site boundary
where the works site borders publicly accessible routes and/or is close to
visually sensitive receivers (VSRs) to screen undesirable views of the works
site. ·
Control of
night-time lighting and Construction traffic (land and sea) reduced to
practical minimum. ·
The alignment and
structures associated with the new road should be integrated, as far as
technically feasible, with existing roadside structures and the landscape
context to reduce the potential cumulative impact of the proposed works. ·
Aesthetic
treatment and Design of the building and tunnel ventilation shaft should be
vetted and advised upon by ArchSD in accordance with ETWB TCW No. 8/2005 –
Aesthetic Design of Ancillary Buildings in Engineering Projects. ·
Greening Provision
in the early project planning stage and shall be in accordance with DEVB TCW
No. 2/2012- allocation of space for quality greening on Roads. ·
Post-planting
monitoring of the compensatory trees shall be undertaken (namely, duration of
the post-planting monitoring and monitoring methodology). The monitoring will
be aimed to assess the success and performance of the compensatory planting
trees, monitor the growth performance of the planted seedlings and whips, and
identify any need of vegetation and site maintenance work. ·
The design and
implementation of the aesthetic appearance of the retaining wall and slopes
will be undertaken in accordance with GEO Publication No. 1/2011 – Technical
Guidelines on Landscape Treatment for Slopes (2011), and WBTC No. 17/2000 on Improvement to the Appearance of
Slopes. |
·
Minimise
landscape and visual impact during construction and operational phases. |
Cultural Heritage |
· Three sites of Archaeological Interest,
namely Shek Kok Tsui, Fu Tei Ha and So Kwu Wat, will not be impacted. ·
Avoid direct
impact on the Built Heritage BH-03 at the GGA campsite, no excavation works
will be carried out and existing building structures will not be demolished
or removed but only require some necessary restoration/ refurbishment/
repair. Appropriate protective and mitigation measures are to be recommended
during detail design stage of the Project when the structural condition and
assessment of the Site and the historical buildings/ structures/ features are
verified during detailed design stage of the Project. The protective and
mitigation measures should be agreed by AMO, and to be implemented to the
satisfaction of AMO to safeguard against any potential adverse impact. ·
Any vibration and
building movement induced from the proposed works should be strictly
monitored to ensure no disturbance and physical damages made to the heritage
sites during the course of works. ·
Special
attention should be paid to avoid adverse physical impact arising from the
construction works to the heritage site. Design proposal, method of works and
choice of machinery should be targeted to minimize adverse impacts to the
heritage site. Any vibration and building movement induced from the
construction works should be strictly monitored to ensure no disturbance and
physical damages made to the heritage site during the course of works. ·
Excavation
works in close vicinity to the heritage site should not jeopardize stability
of the historic structures. It should not undermine or cause damage to
foundation of the historic structures. Foundation information of the historic
structures shall be verified on site if needed, sufficient lateral support
should be provided and de-watering (if required) should be carried out with
great cautions to control ground movement and change of ground water regime
at the heritage site. ·
Installation
of monitoring checkpoints shall be carried out in great care and adequate
protection shall be provided so as to avoid unnecessary disturbance / damage
to the historic fabrics. Photo records of monitoring checkpoints shall be
submitted upon installation for AMO's records. Monitoring records should be
submitted to AMO on regular basis and please alert AMO should the monitoring
reach Alert/ Alarm/ Action levels. ·
As a
precautionary measure, the project proponent and his/her contractor are
required to inform AMO immediately when any antiquities or supposed
antiquities under the Antiquities and Monuments Ordinance (Cap. 53) are
discovered during the course of works. |
·
Minimise adverse
impact on any Sites of Archaeological Interest and historical building building/structure/feature/site. ·
Ensure compliance
with all statutory requirements and those recommendations in the EIA report. |