4.2 Environmental Legislation, Standards, and
Guidelines
4.3 Description of Existing Environment
4.6 Operational Phase - Fixed Plant Noise Impact
Assessment
4.7 Operational Phase - Rail Noise Impact
Assessment
4.8 Environmental Monitoring and Audit
Requirement
List of Tables
Table
4.1 Noise
Criteria for Daytime Construction Noise
Table
4.2 Construction
Noise Criteria during Restricted Hours
Table
4.3 Acceptable
Noise Levels for Airborne Rail Noise
Table
4.4 Acceptable
Noise Levels for Fixed Noise Source
Table
4.5 Representative
NAPs for Construction Noise Impact Assessment
Table
4.6 Representative
NAPs for Operational Noise - Fixed Plant Noise Impact Assessment
Table
4.7 Summary
of Unmitigated Construction Noise Levels
Table
4.8 Summary
of Mitigation Measures adopted for PMEs
Table
4.9 Summary
of Mitigated Construction Noise Levels
Table
4.10 Predicted
Maximum Allowable SWL for Planned Noise Source
List of Figures
Locations of Prevailing Background Noise Measurement |
|
Location of Prevailing Background Noise Measurement (Tin Shui
Wai, near Wetland Seasons Park Phase 1) |
|
Locations of Noise Sensitive Receivers (Existing) |
|
Locations of Noise Sensitive Receivers (Planned) |
|
Locations of Representative Noise
Assessment Points (Construction Noise) |
|
Locations of
Representative Noise Assessment Points (Fixed Plant Noise) |
List of Appendices
Prevailing Background Noise Measurement |
|
Proposed Fixed Plant Noise Criteria for NSRs |
|
Existing NSRs to be Removed or Resumed |
|
Photographs of Selected Representative Noise Sensitive Receivers |
|
SWLs of PMEs |
|
Detailed PME Inventory |
|
Locations of Workfronts for Construction |
|
Unmitigated Construction Noise Calculation |
|
Sketch of Typical Temporary Noise Barrier & Enclosure |
|
Fixed Plant Noise Calculation |
|
Fixed Plant Noise Measurement at Existing KSR Station |
|
Predicted Fixed Plant Noise Levels at the NSRs at Representative
Floor Levels |
|
Locations of Noise Canopy and Elevation
of NTD |
General
·
Technical
Memorandum on Environmental Impact Assessment Process (EIAO-TM);
·
Technical
Memorandum for the Assessment of Noise from Places other than Domestic
Premises, Public Places or Construction Sites (IND-TM);
·
Technical
Memorandum on Noise from Construction Work in Designated Areas (DA-TM);
·
Technical
Memorandum on Noise from Construction Work other than Percussive Piling
(GW-TM); and
·
Technical
Memorandum on Noise from Percussive Piling (PP-TM).
Construction Noise
Criteria during Non-restricted Hours
Table 4.1 Noise Criteria
for Daytime Construction Noise
Uses(1) |
Daytime
(0700 to1900 hours on any day not being a Sunday or general holiday) (Leq,
30min, dB(A)) |
All domestic premises
including temporary housing accommodation |
75 |
Hotels and hostels |
75 |
Educational
institutions (including kindergartens, nurseries and all others where unaided
voice communication is required |
70 65 (During
examinations) |
Notes:
(1) The above standards apply to uses which rely on opened windows for ventilation.
(2) The above standards shall be viewed as the maximum allowable noise levels assessed at 1m from the external façade.
Construction Noise
Criteria during Restricted Hours
Table
4.2 Construction
Noise Criteria during Restricted Hours
Time Period |
BNL During
Restricted Hours |
||
ASR ‘A’ |
ASR ‘B’ |
ASR ‘C’ |
|
All days during the evening (1900 to 2300 hours), and general holidays
(including Sundays) during the daytime and evening (0700 to 2300 hours) |
60 (45) |
65 (50) |
70 (55) |
All days during the night-time (2300 to 0700 hours) |
45 (30) |
50 (35) |
55 (40) |
Note:
(1)
Figures in brackets are BNLs for SPME
within the designated area.
Operational Noise –
Airborne Rail Noise
Table 4.3 Acceptable Noise Levels for Airborne Rail Noise
Time Period |
Noise
Criteria (Leq, 30min, dB(A)) |
||
ASR ‘A’ |
ASR ‘B’ |
ASR ‘C’ |
|
Daytime and Evening (0700 to 2300 hours) |
60 |
65 |
70 |
Night-time (2300 to 0700 hours) |
50 |
55 |
60 |
Operational Noise –
Fixed Plant Noise
·
5
dB(A) below the appropriate ANL set out in the IND-TM; or
·
prevailing
background noise level where the prevailing background noise level
is 5 dB(A) below the appropriate ANL (i.e. ANL – 5 dB(A)).
Table 4.4 Acceptable Noise Levels for Fixed
Noise
Source
Time Period |
ANL, dB(A) |
ANL-5, dB(A) |
||||
ASR ‘A’ |
ASR ‘B’ |
ASR ‘C’ |
ASR ‘A’ |
ASR ‘B’ |
ASR ‘C’ |
|
Daytime and Evening (0700
to 2300 hours) |
60 |
65 |
70 |
55 |
60 |
65 |
Night (2300 to 0700 hours) |
50 |
55 |
60 |
45 |
50 |
55 |
Prevailing Background
Noise Measurement
·
Parameters
such as frequency weighting, the time weighting and the duration of measurement
were set as follows:
-
Frequency
weighting: A
-
Time
weighting: Fast
- Duration of measurement: at least 24
hours continuously to cover both daytime and night-time periods (with data
being logged at every one second)
·
Noise
measurements were conducted in accordance with standard acoustic principles
and practices in the relation to weather conditions.
4.3.6
For the measurement conducted under free-field condition, a façade
correction of +3dB(A) was added to the measurement result to account the façade
reflection effect.
4.4.2
Some of the existing NSRs, that are close to the Project, would be
removed / resumed by the Project or other concurrent projects according to the
respective construction programme provided by the project proponent, and thus
these NSRs, as listed in Appendix 4.3, would not be considered in the noise impact assessment.
Table 4.5 Representative NAPs for
Construction Noise Impact Assessment
NAP ID |
Description |
Land Use (1) |
Existing / Planned |
No. of Storey |
PHD-E1 |
11D Shek Wu Tong |
R |
Existing |
2 |
PHDKSR-E1 |
2 Shek Wu Tong |
R |
Existing |
2 |
PHDKSR-P1 |
Planned Residential Block at Kam
Tin South Housing Development |
R |
Planned |
N/A (2) |
PHDKSR-P2 |
Planned Residential Block at Kam
Tin South Housing Development |
R |
Planned |
N/A (2) |
PHDKSR-P3 |
Planned Residential Block at Kam
Tin South Housing Development |
R |
Planned |
N/A (2) |
KSR-P1 |
Planned Residential Block at Kam
Tin South Housing Development |
R |
Planned |
N/A (2) |
KSR-P2 |
Planned G/IC Site at Kam Tin
South Housing Development(3) |
G/IC |
Planned |
N/A (2) |
KSR-P3 |
Planned G/IC Site at Kam Tin
South Housing Development |
G/IC |
Planned |
N/A (2) |
KSR-P4 |
Planned Residential Block at Kam
Tin South Housing Development |
R |
Planned |
N/A (2) |
KSR-P5 |
Grand Mayfair |
R |
Planned |
16 |
KSR-P6 |
Grand Mayfair |
R |
Planned |
16 |
KSR-P7 |
Grand Mayfair |
R |
Planned |
16 |
KSR-P8 |
Planned School Site at Kam Tin
South Housing Development |
E |
Planned |
N/A (2) |
KSR-E1 |
230 Kat Hing Wai |
R |
Existing |
3 |
SMR-E1 |
Tower 8B, Park Yoho |
R |
Exiting |
14 |
SMR-E2 |
Tower 1A, Park Yoho |
R |
Existing |
14 |
AUT-E1 |
Shum Residence |
R |
Existing |
2 |
AUT-E2 |
26 Mo Fan Heung |
R |
Existing |
1 |
AUT-P1 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
Planned |
N/A (2) |
AUT-P2 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
Planned |
N/A (2) |
AUT-P3 |
Planned Residential Block at Sha
Po Public Housing Development |
R |
Planned |
N/A (2) |
POW-E1 |
166 Pok Wai |
R |
Existing |
2 |
POW-E2 |
171A Pok Wai |
R |
Existing |
1 |
POW-E3 |
169 Pok Wai |
R |
Existing |
2 |
POW-E4 |
170 Pok Wai |
R |
Existing |
3 |
LHT-E1 |
Village House in Long Ha |
R |
Existing |
1 |
NTM-E1 |
Hongtai Home for the Aged Limited |
HA |
Existing |
3 |
NTM-E2 |
Village House in Yau Tam Mei
Tsuen |
R |
Existing |
2 |
NTM-E3 |
Temporary Structure near Chun
Shin Road |
R |
Existing |
1 |
NTM-E4 |
Village House near Chuk Yau Road |
R |
Existing |
2 |
NTM-E5 |
Temporary Structure near Chuk Yau
Road |
R |
Existing |
2 |
NTM-E6 |
Village House near Wang Ping Shan
South Road |
R |
Existing |
2 |
NTM-E7 |
House A, Greenacres Villa |
R |
Existing |
3 |
NTM-E8 |
Temporary Structure near Ching
Yau Road |
R |
Existing |
1 |
SAT-E1 |
Temporary Structure near Shek Wu
Wai San Tsuen |
R |
Existing |
1 |
SAT-E2 |
Temporary Structure near Shek Wu
Wai San Tsuen |
R |
Existing |
1 |
SAT-E3 |
Temporary Structure near Shek Wu
Wai |
R |
Existing |
1 |
SAT-E4 |
89 Shek Wu Wai |
R |
Existing |
3 |
SAT-E5 |
Temporary Structure near Shek Wu
Wai |
R |
Existing |
2 |
SAT-E6 |
Christian New Life Association |
R |
Existing |
1 |
KLR-E1 |
616 Siu Hum Tsuen |
R |
Existing |
3 |
KTR-E1 |
Village House near Kwu Tung Road |
R |
Existing |
1 |
KTR-E2 |
Village House near Kwu Tung Road |
R |
Existing |
2 |
KTR-E3 |
271 Chau Tau Tsuen |
R |
Existing |
3 |
PSA-E1 |
Village House near Pak Shek Au |
R |
Existing |
1 |
KTU-P1 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P2 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P3 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P4 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P5 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P6 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P7 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
KTU-P8 |
Planned Housing Development at
Kwu Tung North NDA |
R |
Planned |
N/A (2) |
TSH-E1 |
Village House near Tai Shu Ha
Road West |
R |
Existing |
1 |
Notes:
(1)
E – Educational
Institution; G/IC – Government, Institution or Community; HA – Home for the
Aged; R – Residential.
(2)
Information
regarding number of storeys for the planned/ committed developments is
unavailable at the time of preparing this EIA Report.
(3)
Based on the best
available information provided by CLP Power Hong Kong Limited, there will be a
cable reserve zone along the southwest boundary of the G/IC site and a planned
substation to be located at southern part of the GI/C site. Information subject
to the design of the planned development. The NAP was assumed at a location
outside the cable reserve zone and the planned substation
Table 4.6 Representative NAPs for Operational Noise - Fixed Plant Noise Impact
Assessment
NAP ID(1),(21) |
Description |
Land
Use(2) |
Existing / Planned |
No. of Storey |
Type of Area |
Influencing Factor |
Degree to which NSR is affected |
Area Sensitive Rating (3),(4) |
KSR-PF01a |
Future
Kam Sheung Road Package 2 Property Development |
R |
Planned |
-(6) |
Area other than those above(7) |
- |
- |
B |
KSR-PF01b |
Future
Kam Sheung Road Package 2 Property Development |
R |
Planned |
-(6) |
Area other than those above(7) |
- |
- |
B |
KSR-PF01c |
Future
Kam Sheung Road Package 2 Property Development |
R |
Planned |
-(6) |
Area other than those above(7) |
- |
- |
B |
KSR-PF02a |
Grand
Mayfair |
R |
Planned |
16 |
Area other than those above(8) |
- |
- |
B |
KSR-PF02b |
Grand
Mayfair |
R |
Planned |
16 |
Area other than those above(8) |
- |
- |
B |
KSR-PF02c |
Grand
Mayfair |
R |
Planned |
16 |
Area other than those above(8) |
- |
- |
B |
KSR-PF02d |
Grand
Mayfair |
R |
Planned |
16 |
Area other than those above(8) |
- |
- |
B |
KSR-PF03a |
Planned
G/IC Site at Kam Tin South Housing Development |
G |
Planned |
-(6) |
Area other than those above(9) |
- |
- |
B |
KSR-PF03b |
Planned
G/IC Site at Kam Tin South Housing Development |
G |
Planned |
-(6) |
Area other than those above(9) |
- |
- |
B |
KSR-PF04 |
Planned
Residential Block at Kam Tin South Housing Development |
R |
Planned |
-(6) |
Area other than those above(9) |
- |
- |
B |
KSR-PF05 |
Planned
G/IC Site at Kam Tin South Housing Development |
G |
Planned |
-(6) |
Area other than those above(9) |
- |
- |
B |
KSR-PF06 |
Planned
School Site at Kam Tin South Housing Development |
E |
Planned |
-(6) |
Area other than those above(9) |
- |
- |
B |
KSR-PF08 |
Planned
School in Park Yoho Phase 3 |
E |
Planned |
-(6) |
Area other than those above(10) |
- |
- |
B |
KSR-PF08a |
Planned
School in Park Yoho Phase 3 |
E |
Planned |
-(6) |
Area other than those above(10) |
- |
- |
B |
AUT-F01 |
Tower 8B,
Park Yoho |
R |
Existing |
14 |
Area other than those above(11) |
- |
- |
B |
AUT-F01a |
Tower 5B,
Park Yoho |
R |
Existing |
13 |
Area other than those above(11) |
- |
- |
B |
AUT-PF01 |
Planned
Residential Block at Sha Po Public Housing Development |
R |
Planned |
-(6) |
Area other than those above(13) |
San Tin
Highway |
Not
Affected |
B |
AUT-PF02 |
Planned
Residential Block at Sha Po Public Housing Development |
R |
Planned |
-(6) |
Area other than those above(13) |
San Tin
Highway |
Not
Affected |
B |
AUT-PF03 |
Planned
Residential Block at Sha Po Public Housing Development |
R |
Planned |
-(6) |
Area other than those above(13) |
San Tin
Highway |
Not
Affected |
B |
AUT-PF04 |
Planned Residential
Block at Sha Po Public Housing Development |
R |
Planned |
-(6) |
Area other than those above(13) |
San Tin
Highway |
Not
Affected |
B |
AUT-F06 |
26 Mo Fan
Heung |
R |
Existing |
2 |
Area other than those above |
Industrial
Zone |
Within 100m
of Industrial Zone |
B (12) |
AUT-F02 |
Shum
Residence |
R |
Existing |
2 |
Area other than those above |
Industrial
Zone |
Within
100m of Industrial Zone |
B (12) |
AUT-F05a |
166 Pok
Wai |
R |
Existing |
2 |
Low density residential area |
San Tin
Highway |
Indirectly
Affected |
B |
AUT-F05b |
170 Pok
Wai |
R |
Existing |
3 |
Low density residential area |
San Tin
Highway |
Indirectly
Affected |
B |
AUT-F05c |
169 Pok
Wai |
R |
Existing |
2 |
Low density residential area |
San Tin
Highway |
Indirectly
Affected |
B |
NTM-F01 |
Village House
in Long Ha |
R |
Existing |
1 |
Area other than those above(14) |
San Tin
Highway |
Not
Affected |
B |
NTM-F02 |
Village
House in Long Ha |
R |
Existing |
1 |
Low density residential area |
- |
- |
A |
NTM-F04 |
Hongtai
Home for the Aged Limited |
HA |
Existing |
3 |
Area other than those above(16) |
- |
- |
B |
NTM-F04a |
Temporary
Structure near Ching Yau Road |
R |
Existing |
1 |
Area other than those above(16) |
- |
- |
B |
NTM-F05 |
The
Dhamma Garden |
R/W |
Existing |
3 |
Area other than those above(18) |
- |
- |
B |
NTM-F05a |
Temporary
Structure near Chuk Yau Road |
R |
Existing |
2 |
Area other than those above(16) |
- |
- |
B |
NTM-F06 |
Village
House near Wang Ping Shan South Road |
R |
Existing |
2 |
Area other than those above(16) |
- |
- |
B |
NTM-F07 |
Temporary
Structure near Chun Shin Road |
R |
Existing |
1 |
Low density residential area |
- |
- |
A |
NTM-F08 |
Village
House near Chuk Yau Road |
R |
Existing |
2 |
Area other than those above(16) |
- |
- |
B |
NTM-PF01(17) |
Potential
Development at Land Use Review Study for Ngau Tam Mei
Area (NTM LUR) |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF01a(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF01b(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF02(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF04(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07a
(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07b(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07c(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07d(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07e(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07f(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07g(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07h(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07q(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07r(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
NTM-PF07s(17) |
Potential
Development at NTM LUR |
-(6) |
Planned |
-(6) |
Area other than those above(16) |
- |
- |
B |
SAT-F02 |
Temporary
Structure near Shek Wu Wai |
R |
Existing |
1 |
Low density residential area |
- |
- |
A |
SAT-PF01a |
Potential
Housing Development in San Tin / Lok Ma Chau Development Node (STLMC DN) |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01b |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01c |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01d |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01e |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01f |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF01h |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF02d |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF03 |
Potential
School in STLMC DN |
E |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF03a |
Potential
Housing Development in STLMC DN |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-PF05a |
Potential
FSD Staff Quarter in San Tin / Lok Ma Chau Development Node |
R |
Planned |
-(6) |
Area other than those above(19) |
- |
- |
B |
SAT-F04 |
271 Chau
Tau Tsuen |
R |
Existing |
3 |
Low density residential area |
- |
- |
A |
KTU-F01 |
Village
House near Pak Shek Au |
R |
Existing |
1 |
Area other than those above(14) |
- |
- |
B |
KTU-F01a |
Village
House near Pak Shek Au |
R |
Existing |
1 |
Area other than those above(14) |
- |
- |
B |
KTU-PF01a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF01b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF01c |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF02a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF02b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF03a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF03b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF04a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF04b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF05a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF05b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF06a |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF06b |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF06c |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
KTU-PF07 |
Planned
Housing Development at Kwu Tung North NDA |
R |
Planned |
-(6) |
Area other than those above(20) |
- |
- |
B |
Notes:
(1)
For
planned/committed development, the locations of NAP were identified based on
the best available information provided from the relevant parties.
(2)
E- Educational; HA
- Home for the Aged; R – Residential; W – Place of Public Worship; G – G/IC
(3)
The corresponding
ASR of the NSRs are determined based on the best available information and is
for indicative assessment only. The Noise Control Authority shall determine
noise impact from concerned noise sources on the basis of prevailing
legislation and practices being in force, and the ASR determined in this report
should not bind the Authority when enforcing the NCO based on the contemporary
conditions. The ASR would be reviewed as necessary based on the contemporary
conditions/situations such as adjoining land uses, influencing factors or the
latest new development areas.
(4)
The fixed plant
noise criteria are “ANL-5 dB(A)” of respective Area Sensitive Rating or
prevailing background noise level where the prevailing background noise level
is 5 dB(A) below the appropriate ANL.
(5)
Not used.
(6)
Information
subject to the design of planned development.
(7)
As the areas in the vicinity of the
Future Kam Sheung Road Package 2 Property Development (i.e. Grand Mayfair and
Kam Tin South Public Housing Development) will be developed to medium to
high-density residential area, type of area
was considered to be “Area other than those above”.
(8)
According to the information in
Sales Brochure of the development, Grand Mayfair will be developed to a medium
to high-density residential area, type of area was therefore considered to
be “Area other than those above”.
(9)
According to the building layout
plans provided by Housing Department, the Planned Kam Tin South Development
(Site 1 & 6) would be developed to medium to high-density residential area,
type
of area was therefore considered to be “Area other than those above”.
(10)
According to planning application
A/YL-KTN/604 and A/YL-KTN/663, Park Yoho Phase 2 and 3 will be developed to a
medium to high-density residential area, type of area was therefore considered to be “Area other than those above”.
(11)
NAP is located in a medium to high-density
residential area with some scattered industrial activities (e.g. garage), type
of area was therefore considered to be “Area other than those above”.
(12)
Considering the existing industrial
zone would be changed to other land uses for Sha Po Public Housing Development,
as conservative approach, the effect of industrial zone was not considered to
determine the appropriate noise criteria.
(13)
According to the block layout provided by
Housing Department, the Proposed Public Housing Development Near Sha Po Tsuen
would be developed to medium to high-density residential area, type of area was
therefore considered to be “Area other than those above”.
(14)
In view of open storages/industrial uses
located in the vicinity of the NSRs, type of area was considered to be “Area
other than those above”.
(15)
Not used.
(16)
According to
Section 16 of LC Paper No. CB(1)756/20-21(01–) - Using Brownfield Clusters for
Public Housing Development (Second Phase Review) and Other Developments, Ngau
Tam Mei Area would be developed to provide a mix of over 6,000 public and
private housing units. Based on this information, type of area was considered
to be “Area other than those above”.
(19)
According to Section 14 of LC Paper
No. CB(1)756/20-21(01) - Using Brownfield Clusters for Public Housing
Development (Second Phase Review) and Other Developments, the San Tin Lok Ma
Chau Development Node (STLMC DN) would be developed as a new development area
supporting an estimated housing yield of 31 000 units together with economic
and community facilities. Based on this information, type of area was
considered to be “Area other than those above”.
(20)
Based on the information provided
in the approved NENT NDA EIA report (Register No.: AEIAR-175/2013), the area
near KTU(NOL) Station will be developed to a medium to high-density residential
area, type of area was therefore considered
to be “Area other than those above”.
(21)
The identification
of the planned NAPs is based on the following sources of best available
information:
§ KSR-PF01a, KSR-PF1b & KSR-PF1c - No indicative layout plan was
available during the course of EIA study and therefore the indicative location
of NAP was set at the boundary of the Future Kam Sheung Road Package 2 Property
Development.
§ KSR-PF02a, KSR-PF02b, KSR-PF02c and KSR-PF02d- Reference was made to the
building layout provided in Sales Brochure of the development (See Note (8)
above).
§ KSR-PF03a & KSR-PF3b - Based on the best available information
provided by CLP Power Hong Kong Limited, there will be a cable reserve zone
along the southwest boundary of the G/IC site and a planned substation to be
located at southern part of the G/IC site. The NAP was assumed at a location
outside the cable reserve zone and the planned substation.
§ KSR-PF05 & KSR-PF06 – Assessment points were assigned at the boundary
of the respective zone for the conservative approach.
§ KSR-PF04 - Reference was made to building layout plans provided by
Housing Department.
§ KSR-PF08 and KSR-PF08a - Reference was made to planning application
A/YL-KTN/604 and A/YL-KTN/663, and the NAPs were identified based on the
Indicative Master Layout Plan shown in these planning applications.
§ AUT-PF01, AUT-PF02, AUT-PF03 and AUT-PF04 - Reference was made to the building layout plans in Final Report (Sha Po)
of Agreement No. CE 10/2020 (CE) Site Formation and Infrastructure Works for
Proposed Public Housing Developments at Sha Po, Shap Pat Heung and Tai Kei
Leng, Yuen Long – Feasibility Study, as provided by Housing Department.
§ NTM-PF01 to NTM-PF07s – Please refer to Note (17) above.
§ SAT-PF01a to SAT-PF05a – Reference was made to
the Recommended Outline Development Plan (RODP) provided by the project
proponent of STLMC DN.
§ KTU-PF01a to KTU-PF07 - Reference was made to the information provided by
CEDD.
·
Construction of 5
stations including KSR(NOL), AUT, NTM, SAT and KTU(NOL) by cut-and-cover;
·
Construction of
tunnel connecting KSR(NOL), AUT, NTM, SAT and KTU(NOL) Stations by Tunnel Boring Machine (TBM);
·
Construction of
branching tunnel connecting to NTD by cut-and-cover, mined and drill-and-blast
tunnelling method;
·
Construction of NTD;
·
Construction of
overrun tunnel section at KSR and crossover box and bifurcation at SAT by
cut-and-cover;
·
Demolition of EAP (an
aboveground structure) under Existing EAL at Kwu Tung;
·
Construction of ABs
for EAP/EEPs/VBs;
·
Site clearance,
construction and reinstatement of temporary explosive magazine at Tai Shu Ha
(Yuen Long) and reinstatement;
·
Works such as
temporary traffic management (TTM), landscaping, minor reinstatement, material
delivery, etc.; and
·
Construction,
operation, and demolition of a concrete batching plant (CBP) at San Tin.
4.5.2
For the construction of branching tunnel connecting to NTD,
drill-and-blast tunnelling method would be adopted. There is no statutory procedure or criteria
under the NCO and EIAO for assessing the blasting impacts. However, the
administrative and procedural control of all blasting operations in Hong Kong
is vested in the Mines Division of the CEDD. The Dangerous Goods (General)
Regulations, Chapter 295B also stipulates that no person shall carry out
blasting unless the possesses a valid mine blasting certificate to be issued by the Mines
Division of CEDD.
·
Kam Tin South Public Housing Development;
·
Grand Mayfair (under construction);
·
Kam Sheung Road Package 2 Property Development;
·
Kam Tai Road Residential Development (under
construction);
·
Park Yoho Phase 2 & 3 Development;
·
Sha Po Public Housing Development;
·
Land Use Review Study for Ngau Tam Mei Area;
·
Proposed watermains under Ngau Tam Mei Water
Treatment Works Extension;
·
San Tin Lok Ma Chau Development Node –
Investigation (also known as San Tin Technopole);
·
Kwu Tung North New Development Area – Advance
Works;
·
Kwu Tung North New Development Area – Remaining
Phase; and
·
Kwu Tung Station on Lok Ma Chau Spur Line.
·
Construction works in proximity to existing rail
operation; and
·
Construction of tunnels by TBM (Figure No. C1603/C/NOL/ACM/M50/305 refers).
Assessment
Methodology
4.5.8
The airborne construction
noise impact assessment was conducted based on the following procedures:
·
Determine 300m from the boundary of the Project and
the works sites/areas;
·
Obtain the construction methods and work sequences
for the construction period;
·
Obtain the construction plant inventory for each
corresponding construction work sequence;
·
Determine the Sound Power Levels (SWLs) of the
plant items according to the information stated in the GW-TM or other
recognised sources of reference, where appropriate;
·
Calculate the correction factors based on the
distance between the NSRs and the notional noise source positions of the work
sites;
·
Apply corrections for façade, distance, barrier
attenuation, acoustic reflection where applicable;
·
Predict construction noise levels at the NAPs;
·
Quantify the level of impact at the NAPs, in
accordance with GW-TM;
·
Predict the cumulative noise impacts for any
concurrent construction works in the vicinity of the proposed work;
·
For any exceedance of noise criteria, all practical
mitigation measures such as alternative construction methodology, quiet plant,
silencer for ventilation fan, full noise enclosure for TBM launching shafts/
retrieval shafts, etc., should be examined to alleviate the predicted noise
impacts as much as practicable; and
·
Consideration of noise mitigation measures by
following Annex 13 of EIAO-TM, EIAO Guidance Note “Preparation of Construction
Noise Impact Assessment under the Environmental Impact Assessment Ordinance”
[GN 9/2010] and Good Practices on Mitigation Construction Noise by EPD.
Prediction
and Evaluation of Environmental Impacts
Unmitigated
Airborne Construction Noise Impact during Non-restricted Hours
Table 4.7 Summary of Unmitigated Construction Noise
Levels
NAP ID |
Description |
Land Use(1) |
Daytime Noise Criterion, Leq (30min), dB(A) (2) |
Max. Unmitigated Construction
Noise Levels, Leq (30mins), dB(A) (3) |
Max. Noise Exceedance, dB(A) (2) |
PHD-E1 |
11D Shek Wu Tong |
R |
75 |
70 |
- |
PHDKSR-E1 |
2 Shek Wu Tong |
R |
75 |
73 |
- |
PHDKSR-P1 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
82 |
7 |
PHDKSR-P2 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
84 |
9 |
PHDKSR-P3 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
83 |
8 |
KSR-P1 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
78 |
3 |
KSR-P2 |
Planned G/IC Site at Kam Tin South Housing Development |
G/IC |
75 |
88 |
13 |
KSR-P3 |
Planned G/IC Site at Kam Tin South Housing Development |
G/IC |
75 |
79 |
4 |
KSR-P4 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
79 |
4 |
KSR-P5 |
Grand Mayfair |
R |
75 |
84 |
9 |
KSR-P6 |
Grand Mayfair |
R |
75 |
80 |
5 |
KSR-P7 |
Grand Mayfair |
R |
75 |
78 |
3 |
KSR-P8 |
Planned School Site at Kam Tin South Housing Development |
E |
70 (65) |
87 |
17(22) |
KSR-E1 |
230 Kat Hing Wai |
R |
75 |
75 |
- |
SMR-E1 |
Tower 8B, Park Yoho |
R |
75 |
87 |
12 |
SMR-E2 |
Tower 1A, Park Yoho |
R |
75 |
70 |
- |
AUT-E1 |
Shum Residence |
R |
75 |
80 |
5 |
AUT-E2 |
26 Mo Fan Heung |
R |
75 |
86 |
11 |
AUT-P1 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
66 |
- |
AUT-P2 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
69 |
- |
AUT-P3 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
63 |
- |
POW-E1 |
166 Pok Wai |
R |
75 |
87 |
12 |
POW-E2 |
171A Pok Wai |
R |
75 |
86 |
11 |
POW-E3 |
169 Pok Wai |
R |
75 |
91 |
16 |
POW-E4 |
170 Pok Wai |
R |
75 |
84 |
9 |
LHT-E1 |
Village House in Long Ha |
R |
75 |
73 |
- |
NTM-E1 |
Hongtai Home for the Aged |
HA |
75 |
85 |
10 |
NTM-E2 |
Village House in Yau Tam Mei Tsuen |
R |
75 |
85 |
10 |
NTM-E3 |
Temporary Structure near Chun Shin Road |
R |
75 |
78 |
3 |
NTM-E4 |
Village House near Chuk Yau Road |
R |
75 |
90 |
15 |
NTM-E5 |
Temporary Structure near Chuk Yau Road |
R |
75 |
86 |
11 |
NTM-E6 |
Village House near Wang Ping Shan South Road |
R |
75 |
82 |
7 |
NTM-E7 |
House A, Greenacres Villa |
R |
75 |
78 |
3 |
NTM-E8 |
Temporary Structure near Ching Yau Road |
R |
75 |
83 |
8 |
SAT-E1 |
Temporary Structure near Shek Wu Wai San Tsuen |
R |
75 |
80 |
5 |
SAT-E2 |
Temporary Structure near Shek Wu Wai San Tsuen |
R |
75 |
83 |
8 |
SAT-E3 |
Temporary Structure near Shek Wu Wai |
R |
75 |
80 |
5 |
SAT-E4 |
89 Shek Wu Wai |
R |
75 |
85 |
10 |
SAT-E5 |
Temporary Structure near Shek Wu Wai |
R |
75 |
81 |
6 |
SAT-E6 |
Christian New Life Association |
R |
75 |
84 |
9 |
KLR-E1 |
616 Siu Hum Tsuen |
R |
75 |
66 |
- |
KTR-E1 |
Village House near Kwu Tung Road |
R |
75 |
79 |
4 |
KTR-E2 |
Village House near Kwu Tung Road |
R |
75 |
79 |
4 |
KTR-E3 |
271 Chau Tau Tsuen |
R |
75 |
69 |
- |
PSA-E1 |
Village House near Pak Shek Au |
R |
75 |
83 |
8 |
KTU-P1 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
75 |
- |
KTU-P2 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
83 |
8 |
KTU-P3 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
76 |
1 |
KTU-P4 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
71 |
- |
KTU-P5 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
70 |
- |
KTU-P6 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
88 |
13 |
KTU-P7 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
86 |
11 |
KTU-P8 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
86 |
11 |
TSH-E1 |
Village House near Tai Shu Ha Road West |
R |
75 |
60 |
- |
Notes:
(1)
E – Educational Institution; G/IC – Government,
Institution or Community; HA – Home for the Aged; R – Residential.
(2)
Values in parentheses are applicable to the
examination period of education institution.
(3)
Bolded values indicate exceedance against the
relevant noise criterion.
Unmitigated Airborne Construction Noise Impact during Restricted Hours
Mitigation Measures
·
Adoption of
quieter construction methods;
·
Good site
practices to limit noise emissions at the source;
·
Use of quiet
PMEs;
·
Use of temporary movable
noise barriers, noise enclosure, noise insulating fabric, silencer, soundproof
hammer bracket to screen noise from PMEs;
·
Installation of
temporary noise barrier along PWA works site boundary to screen noise for the
NSR at Pok Wai; and
·
Alternative use
of plant items within one worksite, wherever practicable.
Adoption of Quieter
Construction Methods
·
Use of TBM;
·
Use of large
diameter bored piling;
·
Use of
pre-casting and prefabrication technology;
·
Use of silent
piling such as hydraulic press-in method; and
·
Use of rubber
head poker vibrator.
Good Site Practice
·
Only
well-maintained plant should be operated on-site and plant should be serviced
regularly during the construction programme;
·
Machines and
plant (such as trucks) that may be in intermittent use should be shut down
between work periods or should be throttled down to a minimum;
·
Plant known to
emit noise strongly in one direction should, wherever possible, be orientated
so that the noise is directed away from the nearby NSRs;
·
Silencers or
mufflers which available on construction equipment should be properly fitted
and maintained during the construction works;
·
Spoil
transportation routes should be directed away from NSRs as far as practicable;
·
Mobile plant
should be sited as far away from NSRs as possible and practicable;
·
Material
stockpiles, site office and other structures should be effectively utilized,
wherever practicable, to screen noise from on-site construction activities; and
·
Noise monitoring
at selected NSRs should be conducted as far as practicable.
Use of Quiet PMEs
Use of Temporary Movable
Noise Barrier, Noise Enclosure, Noise Insulating Fabric, Silencer and
Soundproof Hammer Bracket
Table 4.8 Summary of Mitigation
Measures adopted for PMEs
PME |
Mitigation Measures |
Attenuation, dB(A) |
Air
compressor, air flow > 30m3/min |
Barrier |
-10 |
Asphalt paver |
Barrier |
-5 |
Batching Plant |
Barrier |
-10 |
Hand-held breaker |
Barrier |
-10 |
Breaker, excavator mounted (hydraulic) |
Barrier with Soundproof Hammer Bracket
(or other equivalent mitigation measure(s)) |
-10 |
Bulldozer |
Barrier |
-5 |
Concrete corer |
Enclosure |
-15 |
Concrete lorry mixer |
Barrier |
-5 |
Concrete mixer |
Barrier |
-10 |
Concrete pump |
Enclosure |
-15 |
Mobile crane |
Barrier |
-5 |
Crane, tower (electric) |
Barrier |
-5 |
Compactor, vibratory |
Barrier |
-10 |
Drill/ grinder, percussive, hand-held
(electric) |
Barrier |
-10 |
Excavator/ loader |
Barrier |
-5 |
Hoist |
Barrier |
-5 |
Piling, diaphragm wall, bentonite
filtering plant/ slurry treatment plant |
Barrier |
-10 |
Piling, larger diameter bored, grab
and chisel |
Acoustic Mat |
-10 |
Piling, larger diameter bored,
oscillator |
Acoustic Mat |
-10 |
Piling, larger diameter bored, reverse
circulation drill |
Acoustic Mat |
-10 |
Piling, earth auger |
Acoustic Mat |
-10 |
Power pack |
Barrier |
-10 |
Vibratory poker |
Barrier |
-10 |
Planer |
Barrier |
-10 |
Roller, vibratory |
Barrier |
-5 |
Saw |
Barrier |
-10 |
Ventilation fan |
Silencer |
-15 |
Drill rig |
Acoustic Mat |
-10 |
Grout pump |
Barrier |
-10 |
Portable generator |
Barrier |
-10 |
Vibrating hammer |
Barrier |
-10 |
Lorry |
Barrier |
-5 |
Dump truck |
Barrier |
-5 |
Installation of Temporary
Noise Barrier along the PWA Works Site Boundary
·
Gaps and openings
at joints should be avoided;
·
The length of the
barrier should be about 75m while the height should be about 2.3m; and
·
Surface density of the
barrier should be no less than 7kg/m2.
Alternative Use of Plant
Items within One Works Site
Mitigation Measures for
Construction Works During Restricted Hours
Mitigated
Construction Noise Levels during Non-Restricted Hours
Table 4.9 Summary of Mitigated Construction Noise Levels
NAP ID |
Description |
Land Use(1) |
Daytime Noise Criterion, Leq (30min), dB(A) (2) |
Mitigated Construction Noise
Levels, Leq (30mins), dB(A) (3) |
Max. Noise Exceedance, dB(A) (2) |
PHD-E1 |
11D Shek Wu Tong |
R |
75 |
55 |
- |
PHDKSR-E1 |
2 Shek Wu Tong |
R |
75 |
57 |
- |
PHDKSR-P1 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
66 |
- |
PHDKSR-P2 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
67 |
- |
PHDKSR-P3 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
67 |
- |
KSR-P1 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
65 |
- |
KSR-P2 |
Planned G/IC Site at Kam Tin South Housing Development |
G/IC |
75 |
75 |
- |
KSR-P3 |
Planned G/IC Site at Kam Tin South Housing Development |
G/IC |
75 |
66 |
- |
KSR-P4 |
Planned Residential Block at Kam Tin South Housing Development |
R |
75 |
68 |
- |
KSR-P5 |
Grand Mayfair |
R |
75 |
73 |
- |
KSR-P6 |
Grand Mayfair |
R |
75 |
68 |
- |
KSR-P7 |
Grand Mayfair |
R |
75 |
67 |
- |
KSR-P8 |
Planned School Site at Kam Tin South Housing Development |
E |
70 (65) |
70 |
(5) |
KSR-E1 |
230 Kat Hing Wai |
R |
75 |
63 |
|
SMR-E1 |
Tower 8B, Park Yoho |
R |
75 |
75 |
- |
SMR-E2 |
Tower 1A, Park Yoho |
R |
75 |
55 |
- |
AUT-E1 |
Shum Residence |
R |
75 |
69 |
- |
AUT-E2 |
26 Mo Fan Heung |
R |
75 |
75 |
- |
AUT-P1 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
53 |
- |
AUT-P2 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
57 |
- |
AUT-P3 |
Planned Residential Block at Sha Po Public Housing Development |
R |
75 |
51 |
- |
POW-E1 |
166 Pok Wai |
R |
75 |
72 |
- |
POW-E2 |
171A Pok Wai |
R |
75 |
71 |
- |
POW-E3 |
169 Pok Wai |
R |
75 |
75 |
- |
POW-E4 |
170 Pok Wai |
R |
75 |
70 |
- |
LHT-E1 |
Village House in Long Ha |
R |
75 |
- (6) |
- |
NTM-E1 |
Hongtai Home for the Aged |
HA |
75 |
74 |
- |
NTM-E2 |
Village House in Yau Tam Mei Tsuen |
R |
75 |
73 |
- |
NTM-E3 |
Temporary Structure near Chun Shin Road |
R |
75 |
64 |
- |
NTM-E4 |
Village House near Chuk Yau Road |
R |
75 |
74 |
- |
NTM-E5 |
Temporary Structure near Chuk Yau Road |
R |
75 |
70 |
- |
NTM-E6 |
Village House near Wang Ping Shan South Road |
R |
75 |
71 |
- |
NTM-E7 |
House A, Greenacres Villa |
R |
75 |
64 |
- |
NTM-E8 |
Temporary Structure near Ching Yau Road |
R |
75 |
71 |
- |
SAT-E1 |
Temporary Structure near Shek Wu Wai San Tsuen |
R |
75 |
70 |
- |
SAT-E2 |
Temporary Structure near Shek Wu Wai San Tsuen |
R |
75 |
72 |
- |
SAT-E3 |
Temporary Structure near Shek Wu Wai |
R |
75 |
69 |
- |
SAT-E4 |
89 Shek Wu Wai |
R |
75 |
74 (5) |
- |
SAT-E5 |
Temporary Structure near Shek Wu Wai |
R |
75 |
71 |
- |
SAT-E6 |
Christian New Life Association |
R |
75 |
71 |
- |
KLR-E1 |
616 Siu Hum Tsuen |
R |
75 |
71 (4) |
- |
KTR-E1 |
Village House near Kwu Tung Road |
R |
75 |
67 |
- |
KTR-E2 |
Village House near Kwu Tung Road |
R |
75 |
67 |
- |
KTR-E3 |
271 Chau Tau Tsuen |
R |
75 |
59 |
- |
PSA-E1 |
Village House near Pak Shek Au |
R |
75 |
70 |
- |
KTU-P1 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
64 (5) |
- |
KTU-P2 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
72 (5) |
- |
KTU-P3 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
65 (5) |
- |
KTU-P4 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
60 (5) |
- |
KTU-P5 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
59 (5) |
- |
KTU-P6 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
75 (5) |
- |
KTU-P7 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
74 (5) |
- |
KTU-P8 |
Planned Housing Development at Kwu Tung North NDA |
R |
75 |
74 (5) |
- |
TSH-E1 |
Village House near Tai Shu Ha Road West |
R |
75 |
52 |
- |
Notes:
(1)
E – Educational Institution; G/IC – Government,
Institution or Community; HA – Home for the Aged; R – Residential.
(2)
Values in parentheses are applicable to the
examination period of education institution.
(3)
Bolded values indicate exceedance against the
relevant noise criterion.
(4)
No mitigation measures are considered necessary and
proposed, given that compliance with noise criterion under unmitigated
scenario. Cumulative airborne construction noise impacts from San Tin Lok Ma
Chau Development Node were incorporated.
(5)
Cumulative airborne construction noise impacts from
San Tin Lok Ma Chau Development Node and NENT NDA were incorporated.
(6)
No mitigation measures are considered necessary and
proposed, given that compliance with noise criterion under unmitigated
scenario.
Evaluation of Residual Construction Noise
Impacts
Construction
Noise Impact during Restricted Hours
Assessment Methodology
– Fixed Plant Noise
SPL = Max
SWL – DC + FC + BC
where
SPL |
Sound Pressure Level, in dB(A) |
Max SWL |
Maximum Allowable Sound Power Level , in dB(A) |
DC |
Distance Attenuation, in dB(A) (i.e. 20 log D + 8 [where D is the
distance in metres]) |
FC |
Facade Correction, in dB(A) (i.e. 3 dB(A)) |
BC |
Barrier Correction, in dB(A) |
Source of Impact –
Fixed Plant Noise
Table 4.10 Predicted Maximum Allowable SWL for Planned
Noise Source
Location |
Fixed Plant Source ID |
Fixed Plant Source |
Maximum Allowable SWL
during Daytime/Evening Period, dB(A) |
Maximum Allowable SWL
during |
Kam Sheung
Road Station |
K01a |
Ventilation Louvre |
72 |
61 |
K01b |
Ventilation Louvre |
73 |
62 |
|
K01c |
Ventilation Louvre |
73 |
62 |
|
K02 |
Ventilation Louvre at
Transformer (Tx) Room |
83 |
72 |
|
K03 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K04 |
Ventilation Louvre at
Transformer (Tx) Room |
83 |
72 |
|
K05 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K06 |
Ventilation Louvre at
Transformer (Tx) Room |
83 |
72 |
|
K07 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K08 |
Ventilation Louvre at
Transformer (Tx) Room |
83 |
72 |
|
K09 |
Ventilation Louvre at
Transformer (Tx) Room |
76 |
65 |
|
K09a |
Ventilation Louvre |
73 |
62 |
|
K09b |
Ventilation Louvre |
73 |
62 |
|
K09c |
Ventilation Louvre |
74 |
63 |
|
K09d |
Chiller Plantroom Fresh
Air Intake |
74 |
63 |
|
K10 |
Ventilation Louvre |
81 |
70 |
|
K10a |
Ventilation Louvre |
69 |
58 |
|
K10b |
Ventilation Louvre |
71 |
60 |
|
K10c |
Ventilation Louvre |
71 |
60 |
|
K10d |
Ventilation Louvre |
71 |
60 |
|
K11 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K12 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K13 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K14 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K15 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K16 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K17 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K18 |
Ventilation Louvre at
Transformer (Tx) Room |
71 |
60 |
|
K19 |
Ventilation Louvre |
86 |
75 |
|
K20 |
Ventilation Louvre |
88 |
77 |
|
K20a |
Ventilation Louvre |
79 |
68 |
|
K21 |
Ventilation Louvre |
79 |
68 |
|
K22 |
Ventilation Louvre |
86 |
75 |
|
K22a |
Ventilation Louvre |
81 |
70 |
|
K22b |
Ventilation Louvre |
81 |
70 |
|
K22c |
Ventilation Louvre |
83 |
72 |
|
K23 |
Ventilation Louvre |
86 |
75 |
|
K24 |
Ventilation Louvre |
86 |
75 |
|
K25 |
Ventilation Louvre |
86 |
75 |
|
K26 |
Ventilation Louvre |
86 |
75 |
|
K27 |
Ventilation Louvre |
85 |
74 |
|
K27a |
Ventilation Louvre |
83 |
72 |
|
K28 |
Ventilation Louvre |
88 |
77 |
|
K29 |
Ventilation Louvre |
88 |
77 |
|
K30 |
Ventilation Louvre |
85 |
74 |
|
K30a |
Ventilation Louvre |
69 |
58 |
|
K31 |
Ventilation Louvre |
85 |
74 |
|
K31a |
Ventilation Louvre |
66 |
55 |
|
K31b |
Ventilation Louvre |
66 |
55 |
|
K31c |
Ventilation Louvre |
81 |
70 |
|
K31d |
Ventilation Louvre |
83 |
72 |
|
K32 |
Cooling Tower (Discharge
Louvre) |
88 |
77 |
|
K33 |
Cooling Tower (Discharge
Louvre) |
88 |
77 |
|
K34 |
Cooling Tower (Discharge
Louvre) |
88 |
77 |
|
K35 |
Cooling Tower (Intake
Louvre) |
87 |
76 |
|
K35a |
Ventilation Louvre |
83 |
72 |
|
K35b |
Ventilation Louvre |
81 |
70 |
|
K37 |
Ventilation Louvre |
88 |
77 |
|
K38 |
Ventilation Louvre |
88 |
77 |
|
K39 |
Ventilation Louvre |
88 |
77 |
|
K40 |
Ventilation Louvre |
88 |
77 |
|
K41 |
Ventilation Louvre |
86 |
75 |
|
K41a |
Ventilation Louvre |
77 |
66 |
|
K42 |
Ventilation Louvre |
86 |
75 |
|
K42a |
Ventilation Louvre |
71 |
60 |
|
K43 |
Ventilation Louvre |
86 |
75 |
|
K44 |
AC Outdoor Unit |
77 |
66 |
|
K45 |
AC Outdoor Unit |
77 |
66 |
|
K45a |
Ventilation Louvre |
83 |
72 |
|
K46 |
AC Outdoor Unit |
77 |
66 |
|
K47 |
AC Outdoor Unit |
76 |
65 |
|
K48 |
Ventilation Louvre |
86 |
75 |
|
K48a |
Ventilation Louvre |
81 |
70 |
|
K48b |
Ventilation Louvre |
81 |
70 |
|
K49 |
Ventilation Louvre |
88 |
77 |
|
K50 |
Ventilation Louvre |
88 |
77 |
|
K51 |
Ventilation Louvre |
88 |
77 |
|
K51a |
Ventilation Louvre |
81 |
70 |
|
K51b |
Ventilation Louvre |
81 |
70 |
|
K52 |
Ventilation Louvre |
88 |
77 |
|
K53 |
Ventilation Louvre |
85 |
74 |
|
K54 |
Ventilation Louvre |
85 |
74 |
|
K55 |
Ventilation Louvre |
85 |
74 |
|
K56 |
Ventilation Louvre |
85 |
74 |
|
K57 |
AC Outdoor Unit |
85 |
74 |
|
Au Tau
Station |
A01 |
Ventilation Louvre |
90 |
80 |
A02 |
Ventilation Louvre |
90 |
80 |
|
A03 |
Ventilation Louvre |
90 |
80 |
|
A03a |
Ventilation
Louvre |
80 |
70 |
|
A04 |
Ventilation Louvre |
84 |
74 |
|
A04a |
Ventilation
Louvre |
80 |
70 |
|
A05 |
Ventilation
Louvre |
80 |
70 |
|
A05a |
Ventilation
Louvre |
80 |
70 |
|
A05b |
Ventilation Louvre |
85 |
75 |
|
A05c |
Ventilation Louvre |
85 |
75 |
|
A06 |
Ventilation Louvre |
89 |
79 |
|
A07 |
Ventilation Louvre |
89 |
79 |
|
A08 |
Cooling Tower (Intake
Louvre) |
86 |
76 |
|
A09 |
Cooling Tower (Discharge
Louvre) |
95 |
85 |
|
A10 |
Cooling Tower (Discharge
Louvre) |
95 |
85 |
|
A11 |
Cooling Tower (Discharge
Louvre) |
95 |
85 |
|
A12 |
Ventilation Louvre |
90 |
80 |
|
A12a |
Ventilation
Louvre |
85 |
75 |
|
A13 |
Ventilation Louvre |
90 |
80 |
|
A13a |
Ventilation
Louvre |
90 |
80 |
|
A14 |
Ventilation Louvre |
85 |
75 |
|
A14a |
Ventilation Louvre |
90 |
80 |
|
A15 |
Ventilation Louvre |
85 |
75 |
|
A15a |
Ventilation Louvre |
90 |
80 |
|
A15b |
Ventilation Louvre |
90 |
80 |
|
A15c |
Ventilation Louvre |
85 |
75 |
|
A15d |
Ventilation Louvre |
85 |
75 |
|
A16 |
AC Outdoor Unit |
90 |
80 |
|
A16a |
Ventilation
Louvre |
85 |
75 |
|
A16b |
Ventilation
Louvre |
85 |
75 |
|
A17 |
AC Outdoor Unit |
85 |
75 |
|
A17a |
Ventilation
Louvre |
85 |
75 |
|
A19 |
Ventilation Louvre at
Transformer (Tx) Room |
82 |
72 |
|
A20 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
A21 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
A22 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A23 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A24 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
A25 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A26 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
A26a |
Ventilation
Louvre |
85 |
75 |
|
A27 |
Ventilation Louvre |
89 |
79 |
|
A28 |
Ventilation
Louvre |
87 |
77 |
|
A28a |
Ventilation
Louvre |
80 |
70 |
|
A28b |
Ventilation
Louvre |
80 |
70 |
|
A29 |
Ventilation Louvre |
87 |
77 |
|
A30 |
Ventilation Louvre at Tx
Room |
77 |
67 |
|
A31 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A32 |
Ventilation Louvre at Tx
Room |
78 |
68 |
|
A33 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A34 |
Ventilation Louvre at Tx
Room |
78 |
68 |
|
A35 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A36 |
Ventilation Louvre at Tx
Room |
78 |
68 |
|
A37 |
Ventilation Louvre at Tx
Room |
80 |
70 |
|
A37a |
Ventilation
Louvre |
80 |
70 |
|
A37b |
Ventilation
Louvre |
80 |
70 |
|
A37c |
Ventilation
Louvre |
80 |
70 |
|
A37d |
Ventilation
Louvre |
82 |
72 |
|
A37e |
Ventilation
Louvre |
82 |
72 |
|
A38 |
AC Outdoor Unit |
87 |
77 |
|
A39 |
Ventilation
Louvre |
86 |
76 |
|
A40 |
Ventilation
Louvre |
86 |
76 |
|
A41 |
Ventilation
Louvre |
87 |
77 |
|
Ngau Tam Mei Station |
N01 |
Ventilation Louvre |
79 |
74 |
N02 |
Ventilation Louvre |
79 |
74 |
|
N03 |
Ventilation Louvre |
79 |
74 |
|
N04 |
Ventilation
Louvre at Transformer (Tx) Room |
77 |
72 |
|
N05 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N06 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N07 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N08 |
Ventilation Louvre |
80 |
75 |
|
N09 |
Ventilation Louvre at Transformer
(Tx) Room |
77 |
72 |
|
N10 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N11 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N12 |
Ventilation Louvre at
Transformer (Tx) Room |
82 |
77 |
|
N12a |
Ventilation Louvre |
78 |
73 |
|
N12b |
Ventilation Louvre |
78 |
73 |
|
N12c |
Ventilation Louvre |
78 |
73 |
|
N12d |
Ventilation Louvre |
80 |
75 |
|
N13 |
AC Outdoor Unit |
80 |
75 |
|
N14 |
AC Outdoor Unit |
80 |
75 |
|
N15 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N15a |
Ventilation Louvre |
78 |
73 |
|
N16 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N17 |
Ventilation Louvre |
80 |
75 |
|
N18 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N19 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N20 |
Ventilation Louvre |
80 |
75 |
|
N20a |
Ventilation Louvre |
78 |
73 |
|
N21 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N21a |
Ventilation Louvre |
78 |
73 |
|
N22 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N23 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N24 |
Ventilation Louvre at
Transformer (Tx) Room |
77 |
72 |
|
N25 |
Ventilation Louvre |
79 |
74 |
|
N26 |
Ventilation Louvre |
80 |
75 |
|
N27 |
Ventilation Louvre |
77 |
72 |
|
N28 |
Ventilation Louvre |
79 |
74 |
|
N29 |
Ventilation Louvre |
79 |
74 |
|
N30 |
Ventilation Louvre |
77 |
72 |
|
N30a |
Ventilation Louvre |
78 |
73 |
|
N31 |
Ventilation Louvre |
79 |
74 |
|
N31a |
Ventilation Louvre |
82 |
77 |
|
N31b |
Ventilation Louvre |
82 |
77 |
|
N31c |
Ventilation Louvre |
82 |
77 |
|
N31d |
Ventilation Louvre |
82 |
77 |
|
N32 |
Ventilation Louvre |
80 |
75 |
|
N32a |
Ventilation Louvre |
78 |
73 |
|
N32b |
Ventilation Louvre |
78 |
73 |
|
N33 |
Ventilation Louvre |
80 |
75 |
|
N34 |
Ventilation Louvre |
80 |
75 |
|
N34a |
Ventilation Louvre |
73 |
68 |
|
N35 |
Ventilation Louvre |
82 |
77 |
|
N36 |
Ventilation Louvre |
80 |
75 |
|
N37 |
Ventilation Louvre |
80 |
75 |
|
N38 |
Ventilation Louvre |
68 |
63 |
|
N39 |
Ventilation Louvre |
80 |
75 |
|
N39a |
Ventilation Louvre |
75 |
70 |
|
N40 |
Ventilation Louvre |
78 |
73 |
|
N40a |
Ventilation Louvre |
78 |
73 |
|
N40b |
Ventilation Louvre |
82 |
77 |
|
N41 |
Ventilation Louvre |
75 |
70 |
|
N41a |
Ventilation Louvre |
72 |
67 |
|
N43 |
Ventilation Louvre |
72 |
67 |
|
N44 |
Ventilation Louvre |
76 |
71 |
|
N45 |
Ventilation Louvre |
72 |
67 |
|
N45a |
Ventilation Louvre |
68 |
63 |
|
N45b |
Ventilation Louvre |
68 |
63 |
|
N46 |
Ventilation Louvre |
76 |
71 |
|
N46a |
Ventilation Louvre |
75 |
70 |
|
N47 |
Ventilation Louvre |
76 |
71 |
|
N47a |
Ventilation Louvre |
75 |
70 |
|
N47b |
Ventilation Louvre |
75 |
70 |
|
N47c |
Ventilation Louvre |
75 |
70 |
|
N48 |
Ventilation Louvre |
79 |
74 |
|
N49 |
Ventilation Louvre |
76 |
71 |
|
N50 |
Cooling Tower (Intake
Louvre) |
81 |
76 |
|
N50a |
Cooling Tower (Discharge
Louvre) |
81 |
76 |
|
N51 |
Cooling Tower (Intake
Louvre) |
81 |
76 |
|
N52 |
Ventilation Louvre |
78 |
73 |
|
N53 |
Ventilation Louvre |
79 |
74 |
|
N54 |
Ventilation Louvre |
79 |
74 |
|
N55 |
Ventilation Louvre |
79 |
74 |
|
N56 |
Ventilation Louvre |
79 |
74 |
|
Ngau Tam Mei Depot |
NTD01 |
Ventilation Louvre |
78 |
73 |
NTD02 |
Ventilation Louvre |
76 |
71 |
|
NTD03 |
Ventilation Louvre |
75 |
70 |
|
NTD04 |
Ventilation Louvre |
75 |
70 |
|
NTD05 |
Ventilation Louvre |
75 |
70 |
|
NTD06 |
Ventilation Louvre |
76 |
71 |
|
NTD07 |
Ventilation Louvre |
75 |
70 |
|
NTD08 |
Ventilation Louvre |
75 |
70 |
|
NTD09 |
Ventilation Louvre |
70 |
65 |
|
NTD10 |
Ventilation Louvre |
70 |
65 |
|
NTD11 |
Ventilation Louvre |
70 |
65 |
|
NTD12 |
Ventilation Louvre |
75 |
70 |
|
NTD13 |
Ventilation Louvre |
79 |
74 |
|
NTD14 |
Ventilation Louvre |
77 |
72 |
|
NTD15 |
Ventilation Louvre |
77 |
72 |
|
NTD15a |
Transformer |
80 |
75 |
|
NTD16 |
Ventilation Louvre |
80 |
75 |
|
NTD16a |
Transformer |
80 |
75 |
|
NTD17 |
Ventilation Louvre |
77 |
72 |
|
NTD18 |
Ventilation Louvre |
73 |
68 |
|
NTD19 |
Ventilation Louvre |
73 |
68 |
|
NTD20 |
Ventilation Louvre |
73 |
68 |
|
NTD21 |
Ventilation Louvre |
78 |
73 |
|
NTD22 |
Ventilation Louvre |
80 |
75 |
|
NTD23 |
Ventilation Louvre |
80 |
75 |
|
NTD24 |
Ventilation Louvre |
76 |
71 |
|
NTD25 |
Ventilation Louvre |
80 |
75 |
|
NTD26 |
Ventilation Louvre |
70 |
65 |
|
NTD27 |
Ventilation Louvre |
70 |
65 |
|
NTD28 |
Ventilation Louvre |
75 |
70 |
|
NTD29 |
Ventilation Louvre |
75 |
70 |
|
NTD30 |
Ventilation Louvre |
83 |
78 |
|
NTD31 |
Ventilation Louvre |
80 |
75 |
|
NTD32 |
Ventilation Louvre |
82 |
77 |
|
NTD33 |
Ventilation Louvre |
81 |
76 |
|
NTD34 |
Ventilation Louvre |
80 |
75 |
|
NTD35 |
Ventilation Louvre |
85 |
80 |
|
NTD36 |
Ventilation Louvre |
85 |
80 |
|
NTD37 |
Ventilation Louvre |
85 |
80 |
|
NTD38 |
Ventilation Louvre |
85 |
80 |
|
NTD39 |
Ventilation Louvre |
85 |
80 |
|
NTD40 |
Ventilation Louvre |
80 |
75 |
|
NTD41 |
Ventilation Louvre |
75 |
70 |
|
NTD42 |
Ventilation Louvre |
75 |
70 |
|
NTD43 |
Ventilation Louvre |
75 |
70 |
|
NTD44 |
Ventilation Louvre |
75 |
70 |
|
NTD45 |
Ventilation Louvre |
75 |
70 |
|
NTD46 |
Ventilation Louvre |
75 |
70 |
|
NTD47 |
Ventilation Louvre |
75 |
70 |
|
NTD48 |
Ventilation Louvre |
70 |
65 |
|
NTD49 |
Ventilation Louvre |
70 |
65 |
|
NTD50 |
Ventilation Louvre |
70 |
65 |
|
NTD51 |
Ventilation Louvre |
80 |
75 |
|
NTD52 |
Ventilation Louvre |
73 |
68 |
|
NTD53 |
Ventilation Louvre |
68 |
63 |
|
NTD54 |
Ventilation Louvre |
73 |
68 |
|
NTD55 |
Ventilation Louvre |
85 |
80 |
|
NTD56 |
Ventilation Louvre |
72 |
67 |
|
NTD57 |
Ventilation Louvre |
78 |
73 |
|
NTD58 |
Ventilation Louvre |
73 |
68 |
|
NTD59 |
Ventilation Louvre |
70 |
65 |
|
NTD60 |
Ventilation Louvre |
69 |
64 |
|
NTD61 |
Ventilation Louvre |
71 |
66 |
|
NTD62 |
Ventilation Louvre |
80 |
75 |
|
NTD63 |
Ventilation Louvre |
78 |
73 |
|
NTD64 |
Ventilation Louvre |
72 |
67 |
|
NTD65 |
Ventilation Louvre |
72 |
67 |
|
NTD66 |
Ventilation Louvre |
74 |
69 |
|
NTD67 |
Ventilation Louvre |
73 |
68 |
|
NTD68 |
Ventilation Louvre |
75 |
70 |
|
NTD69 |
Ventilation Louvre |
70 |
65 |
|
NTD70 |
Ventilation Louvre |
75 |
70 |
|
NTD71 |
Ventilation Louvre |
75 |
70 |
|
NTD72 |
Ventilation Louvre |
78 |
73 |
|
NTD73 |
Ventilation Louvre |
75 |
70 |
|
NTD74 |
Ventilation Louvre |
75 |
70 |
|
NTD75 |
Ventilation Louvre |
75 |
70 |
|
NTD76 |
Ventilation Louvre |
75 |
70 |
|
NTD77 |
Ventilation Louvre |
77 |
72 |
|
NTD78 |
Ventilation Louvre |
75 |
70 |
|
NTD79 |
Ventilation Louvre |
76 |
71 |
|
NTD80 |
Ventilation Louvre |
75 |
70 |
|
NTD81 |
Ventilation Louvre |
75 |
70 |
|
NTD82 |
Ventilation Louvre |
75 |
70 |
|
NTD83 |
Ventilation Louvre |
75 |
70 |
|
NTD84 |
Ventilation Louvre |
75 |
70 |
|
NTD85 |
Ventilation Louvre |
75 |
70 |
|
NTD86 |
Ventilation Louvre |
77 |
72 |
|
NTD87 |
Ventilation Louvre |
75 |
70 |
|
NTD88 |
Ventilation Louvre |
74 |
69 |
|
NTD89 |
Ventilation Louvre |
73 |
68 |
|
NTD90 |
Ventilation Louvre |
72 |
67 |
|
NTD91 |
Ventilation Louvre |
75 |
70 |
|
NTD92 |
Ventilation Louvre |
74 |
69 |
|
NTD93 |
Ventilation Louvre |
78 |
73 |
|
NTD94 |
Ventilation Louvre |
73 |
68 |
|
NTD94a |
Ventilation Louvre |
73 |
68 |
|
NTD95 |
Ventilation Louvre |
73 |
68 |
|
NTD96 |
Ventilation Louvre |
74 |
69 |
|
NTD97 |
Cooling Tower |
80 |
75 |
|
NTD98 |
Cooling Tower |
80 |
75 |
|
NTD99 |
Cooling Tower |
80 |
75 |
|
NTD100 |
Ventilation Louvre |
80 |
75 |
|
NTD101 |
Ventilation Louvre |
80 |
75 |
|
NTD102 |
Ventilation Louvre |
75 |
70 |
|
NTD103 |
Ventilation Louvre |
75 |
70 |
|
NTD104 |
Ventilation Louvre |
83 |
78 |
|
NTD105 |
Ventilation Louvre |
73 |
68 |
|
NTD106 |
Ventilation Louvre |
75 |
70 |
|
NTD107 |
Ventilation Louvre |
72 |
67 |
|
NTD108 |
Ventilation Louvre |
82 |
77 |
|
NTD109 |
Ventilation Louvre |
82 |
77 |
|
NTD110 |
Ventilation Louvre |
85 |
80 |
|
NTD111 |
Ventilation Louvre |
77 |
72 |
|
NTD112 |
Ventilation Louvre |
77 |
72 |
|
NTD113 |
Ventilation Louvre |
77 |
72 |
|
NTD114 |
Ventilation Louvre |
85 |
80 |
|
NTD115 |
Ventilation Louvre |
85 |
80 |
|
San Tin Station |
S01 |
Ventilation Louvre |
88 |
80 |
S02 |
Ventilation Louvre |
88 |
80 |
|
S03 |
Ventilation Louvre at
Transformer (Tx) Room |
88 |
80 |
|
S04 |
Ventilation Louvre at
Transformer (Tx) Room |
88 |
80 |
|
S05 |
Ventilation Louvre at
Transformer (Tx) Room |
88 |
80 |
|
S06 |
Ventilation Louvre |
88 |
80 |
|
S07 |
Ventilation Louvre at Transformer
(Tx) Room |
88 |
80 |
|
S08 |
Ventilation Louvre at
Transformer (Tx) Room |
88 |
80 |
|
S09 |
Ventilation Louvre at
Transformer (Tx) Room |
88 |
80 |
|
S09a |
Ventilation Louvre |
88 |
80 |
|
S09b |
Ventilation Louvre |
93 |
85 |
|
S10 |
Ventilation Louvre |
89 |
81 |
|
S10a |
Ventilation Louvre |
88 |
80 |
|
S11 |
Ventilation Louvre |
96 |
88 |
|
S12 |
Ventilation Louvre |
86 |
78 |
|
S13 |
Ventilation Louvre |
85 |
77 |
|
S14 |
Ventilation Louvre |
85 |
77 |
|
S14a |
Ventilation Louvre |
83 |
75 |
|
S14b |
Ventilation Louvre |
81 |
73 |
|
S14c |
Ventilation Louvre |
81 |
73 |
|
S15 |
Ventilation Louvre |
87 |
79 |
|
S15a |
Ventilation Louvre |
80 |
72 |
|
S15b |
Ventilation Louvre |
80 |
72 |
|
S16 |
Ventilation Louvre |
88 |
80 |
|
S16a |
Ventilation Louvre |
78 |
70 |
|
S17 |
Ventilation Louvre |
85 |
77 |
|
S18 |
Ventilation Louvre |
85 |
77 |
|
S19 |
Ventilation Louvre |
84 |
76 |
|
S20 |
Ventilation Louvre |
86 |
78 |
|
S20a |
AC Outdoor Unit |
88 |
77 |
|
Kwu Tung Station on NOL |
KT1 |
Ventilation Louvre |
82 |
70 |
KT2 |
Ventilation Louvre |
82 |
70 |
|
KT3 |
Ventilation Louvre |
82 |
70 |
|
KT4 |
Ventilation Louvre |
82 |
70 |
|
KT5 |
Ventilation Louvre |
82 |
70 |
|
KT6 |
Ventilation Louvre |
82 |
70 |
|
KT7 |
Ventilation Louvre |
82 |
70 |
|
KT8 |
Ventilation Louvre |
82 |
70 |
|
KT9 |
Ventilation Louvre |
82 |
70 |
|
KT10 |
Ventilation Louvre |
82 |
70 |
|
KT11 |
Ventilation Louvre |
85 |
75 |
|
KT12 |
Ventilation Louvre |
85 |
75 |
|
KT13 |
Ventilation Louvre |
80 |
70 |
|
KT14 |
Ventilation Louvre |
80 |
70 |
|
KT15 |
Ventilation Louvre |
80 |
70 |
|
KT16 |
Ventilation Louvre |
81 |
72 |
|
KT17 |
Ventilation Louvre |
81 |
72 |
|
KT18 |
Ventilation Louvre |
80 |
71 |
|
KT19 |
Ventilation Louvre |
80 |
71 |
|
KT20 |
Ventilation Louvre |
80 |
70 |
|
KT21 |
Ventilation Louvre |
80 |
68 |
|
KT22 |
Ventilation Louvre |
80 |
68 |
|
KT23 |
Ventilation Louvre |
80 |
68 |
|
KT24 |
Ventilation Louvre |
80 |
68 |
|
KT25 |
Ventilation Louvre |
80 |
68 |
|
KT26 |
Ventilation Louvre |
80 |
70 |
|
KT27 |
Ventilation Louvre |
85 |
75 |
|
KT28 |
Ventilation Louvre |
85 |
76 |
|
KT29 |
Ventilation Louvre |
85 |
76 |
|
KT30 |
Ventilation Louvre |
85 |
76 |
|
KT31 |
Ventilation Louvre |
85 |
75 |
|
KT32 |
Ventilation Louvre |
85 |
75 |
|
KT33 |
Ventilation Louvre |
80 |
72 |
|
KT34 |
Ventilation Louvre |
80 |
72 |
|
KT35 |
Ventilation Louvre |
80 |
72 |
|
KT36 |
Ventilation Louvre |
80 |
72 |
|
KT37 |
Ventilation Louvre |
80 |
72 |
|
KT38 |
Ventilation Louvre |
80 |
72 |
|
KT39 |
Ventilation Louvre |
80 |
71 |
|
KT40 |
Ventilation Louvre |
80 |
71 |
|
KT41 |
Ventilation Louvre |
80 |
69 |
|
KT42 |
Ventilation Louvre |
80 |
69 |
|
KT43 |
Ventilation Louvre |
80 |
69 |
|
KT44 |
Ventilation Louvre |
80 |
68 |
|
KT45 |
Ventilation Louvre |
80 |
68 |
|
KT46 |
Ventilation Louvre |
80 |
68 |
|
KT47 |
Ventilation Louvre |
80 |
68 |
|
KT48 |
Ventilation Louvre |
80 |
74 |
|
KT49 |
Ventilation Louvre |
85 |
75 |
|
KT50 |
Ventilation Louvre |
85 |
75 |
|
KT51 |
Ventilation Louvre |
85 |
75 |
|
KT52 |
Ventilation Louvre |
85 |
75 |
|
KT53 |
Ventilation Louvre |
80 |
70 |
|
KT54 |
Ventilation Louvre |
83 |
73 |
|
KT55 |
Ventilation Louvre |
85 |
75 |
|
KT56 |
Ventilation Louvre |
85 |
75 |
|
KT57 |
Ventilation Louvre |
85 |
75 |
|
KT58 |
Ventilation Louvre |
85 |
75 |
|
KT59 |
Ventilation Louvre |
85 |
75 |
|
KT60 |
Ventilation Louvre |
81 |
71 |
|
KT61 |
Ventilation Louvre |
81 |
71 |
|
KT62 |
Ventilation Louvre |
81 |
71 |
|
KT63 |
Ventilation Louvre |
80 |
70 |
|
KT64 |
Ventilation Louvre |
80 |
70 |
|
KT65 |
Ventilation Louvre |
80 |
70 |
|
KT66 |
Ventilation Louvre |
80 |
70 |
|
KT67 |
Ventilation Louvre |
80 |
70 |
|
KT68 |
Ventilation Louvre |
82 |
72 |
|
KT69 |
Ventilation Louvre |
81 |
71 |
|
KT70 |
Ventilation Louvre |
81 |
71 |
|
KT71 |
Ventilation Louvre |
81 |
70 |
|
KT72 |
Ventilation Louvre |
81 |
70 |
|
KT73 |
Ventilation Louvre |
81 |
71 |
|
KT74 |
Ventilation Louvre |
81 |
71 |
|
Shui Mei
Road Ancillary Building |
SMA-1 |
Ventilation Louvre |
68 |
60 |
SMA-1a |
Ventilation Louvre |
68 |
64 |
|
SMA-2 |
Ventilation Louvre |
67 |
65 |
|
SMA-3 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-4 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-5 |
Ventilation Louvre at Tx
Room |
68 |
68 |
|
SMA-6 |
Ventilation Louvre at Tx
Room |
68 |
68 |
|
SMA-7 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-8 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-9 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-10 |
Ventilation Louvre at Tx
Room |
72 |
72 |
|
SMA-10a |
Ventilation Louvre |
79 |
79 |
|
SMA-11 |
Ventilation Louvre |
79 |
79 |
|
SMA-11a |
Ventilation Louvre |
79 |
79 |
|
SMA-11b |
Ventilation Louvre |
79 |
79 |
|
SMA-11c |
Ventilation Louvre |
79 |
79 |
|
SMA-11d |
Ventilation Louvre |
70 |
62 |
|
SMA-11e |
Ventilation Louvre |
70 |
62 |
|
SMA-11f |
Ventilation Louvre |
70 |
65 |
|
SMA-11g |
Ventilation Louvre |
70 |
66 |
|
SMA-12 |
Ventilation Louvre |
71 |
70 |
|
SMA-13 |
AC Outdoor Unit |
72 |
70 |
|
Pok Wai
Ancillary Building |
PWA-1 |
Ventilation Louvre |
89 |
79 |
PWA-2 |
Ventilation Louvre |
89 |
79 |
|
PWA-3 |
Ventilation Louvre |
89 |
79 |
|
PWA-4 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-5 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-6 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-7 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-8 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-9 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-10 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-11 |
Ventilation Louvre at Tx
Room |
82 |
72 |
|
PWA-11a |
Ventilation Louvre |
85 |
75 |
|
PWA-12 |
Ventilation Louvre |
75 |
65 |
|
PWA-13 |
Ventilation Louvre |
84 |
74 |
|
PWA-14 |
Ventilation Louvre |
81 |
71 |
|
PWA-15 |
Ventilation Louvre |
81 |
71 |
|
PWA-16 |
Ventilation Louvre |
71 |
61 |
|
PWA-16a |
Ventilation Louvre |
70 |
60 |
|
PWA-16b |
Ventilation Louvre |
80 |
70 |
|
PWA-17 |
AC Outdoor Unit |
85 |
75 |
|
Long Ha Tsuen
Ancillary Building |
LHA-1 |
Ventilation Louvre at Tx
Room |
87 |
82 |
LHA-2 |
Ventilation Louvre at Tx
Room |
87 |
82 |
|
LHA-3 |
Ventilation Louvre at Tx
Room |
87 |
82 |
|
LHA-4 |
Ventilation Louvre at Tx
Room |
87 |
82 |
|
LHA-4a |
Ventilation Louvre |
82 |
77 |
|
LHA-4b |
Ventilation Louvre |
82 |
77 |
|
LHA-5 |
Ventilation Louvre |
82 |
77 |
|
LHA-5a |
Ventilation Louvre |
82 |
77 |
|
LHA-5b |
Ventilation Louvre |
82 |
77 |
|
LHA-6 |
Ventilation Louvre |
82 |
77 |
|
LHA-6a |
Ventilation Louvre |
82 |
77 |
|
LHA-6b |
Ventilation Louvre |
82 |
77 |
|
LHA-6c |
Ventilation Louvre |
82 |
77 |
|
LHA-7 |
AC Outdoor Unit |
91 |
86 |
|
San Tin
Ancillary Building |
SNA-1 |
Ventilation Louvre |
88 |
80 |
SNA-1a |
Ventilation Louvre |
88 |
80 |
|
SNA-2 |
Ventilation Louvre |
88 |
80 |
|
SNA-3 |
Ventilation Louvre |
88 |
80 |
|
SNA-4 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-5 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-6 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-7 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-8 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-9 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-10 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-11 |
Ventilation Louvre at Tx
Room |
82 |
74 |
|
SNA-11a |
Ventilation Louvre |
82 |
74 |
|
SNA-12 |
Ventilation Louvre |
88 |
80 |
|
SNA-12a |
Ventilation Louvre |
83 |
75 |
|
SNA-12b |
Ventilation Louvre |
83 |
75 |
|
SNA-13 |
AC Outdoor Unit |
94 |
86 |
|
SNA-13a |
Ventilation Louvre |
83 |
75 |
|
SNA-13b |
Ventilation Louvre |
82 |
74 |
|
SNA-13c |
Ventilation Louvre |
82 |
74 |
|
SNA-13d |
Ventilation Louvre |
82 |
74 |
|
SNA-14 |
Ventilation Louvre |
82 |
74 |
|
Ka Lung Road
Ancillary Building |
KLA-1 |
Ventilation Louvre at Tx
Room |
96 |
88 |
KLA-2 |
Ventilation Louvre at Tx
Room |
96 |
88 |
|
KLA-3 |
Ventilation Louvre at Tx
Room |
96 |
88 |
|
KLA-4 |
Ventilation Louvre at Tx
Room |
96 |
88 |
|
KLA-4a |
Ventilation Louvre |
93 |
85 |
|
KLA-4b |
Ventilation Louvre |
93 |
85 |
|
KLA-4c |
Ventilation Louvre |
93 |
85 |
|
KLA-4d |
Ventilation Louvre |
93 |
85 |
|
KLA-4e |
Ventilation Louvre |
93 |
85 |
|
KLA-4f |
Ventilation Louvre |
93 |
85 |
|
KLA-4g |
Ventilation Louvre |
93 |
85 |
|
KLA-4h |
Ventilation Louvre |
93 |
85 |
|
KLA-4i |
Ventilation Louvre |
93 |
85 |
|
KLA-4j |
Ventilation Louvre |
96 |
88 |
|
KLA-4k |
Ventilation Louvre |
96 |
88 |
|
KLA-5 |
AC Outdoor Unit |
97 |
88 |
|
Kwu Tung
Road Ancillary Building |
KTA-1 |
Ventilation Louvre |
95 |
88 |
KTA-1a |
Ventilation Louvre |
93 |
86 |
|
KTA-1b |
Ventilation Louvre |
93 |
86 |
|
KTA-2 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-3 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-4 |
Ventilation Louvre |
95 |
85 |
|
KTA-5 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-5a |
Ventilation Louvre |
95 |
88 |
|
KTA-6 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-7 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-7a |
Ventilation Louvre |
95 |
88 |
|
KTA-7b |
Ventilation Louvre |
95 |
88 |
|
KTA-8 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-9 |
Ventilation Louvre at Tx
Room |
95 |
85 |
|
KTA-9a |
Ventilation Louvre |
95 |
88 |
|
KTA-9b |
Ventilation Louvre |
95 |
88 |
|
KTA-10 |
Ventilation Louvre |
95 |
88 |
|
KTA-10a |
Ventilation Louvre |
95 |
88 |
|
KTA-10b |
Ventilation Louvre |
95 |
88 |
|
KTA-11 |
AC Outdoor Unit |
97 |
90 |
|
Pak Shek Au
Ancillary Building |
PAA-1 |
Ventilation Louvre at Tx
Room |
87 |
81 |
PAA-2 |
Ventilation Louvre at Tx
Room |
87 |
81 |
|
PAA-3 |
Ventilation Louvre at Tx
Room |
87 |
81 |
|
PAA-4 |
Ventilation Louvre at Tx
Room |
87 |
81 |
|
PAA-4a |
Ventilation Louvre |
87 |
81 |
|
PAA-4b |
Ventilation Louvre |
87 |
81 |
|
PAA-4c |
Ventilation Louvre |
87 |
81 |
|
PAA-4d |
Ventilation Louvre |
87 |
81 |
|
PAA-4e |
Ventilation Louvre |
87 |
81 |
|
PAA-4f |
Ventilation Louvre |
87 |
81 |
|
PAA-4g |
Ventilation Louvre |
87 |
81 |
|
PAA-4h |
Ventilation Louvre |
87 |
81 |
|
PAA-4i |
Ventilation Louvre |
89 |
83 |
|
PAA-5 |
AC Outdoor Unit |
91 |
85 |
|
PAA-6 |
Ventilation Louvre at Tx
Room |
93 |
87 |
|
PAA-7 |
Ventilation Louvre |
87 |
81 |
|
PAA-8 |
Ventilation Louvre |
87 |
81 |
|
PAA-9 |
Ventilation Louvre |
87 |
81 |
|
PAA-10 |
Ventilation Louvre |
87 |
81 |
|
PAA-11 |
Ventilation Louvre |
87 |
81 |
|
PAA-12 |
Ventilation Louvre |
87 |
81 |
|
PAA-12a |
Ventilation Louvre |
87 |
81 |
|
PAA-13 |
Ventilation Louvre at Tx
Room |
93 |
87 |
|
PAA-14 |
Ventilation Louvre |
87 |
81 |
|
PAA-15 |
Ventilation Louvre |
87 |
81 |
|
PAA-16 |
Ventilation Louvre |
87 |
81 |
|
PAA-17 |
Ventilation Louvre |
87 |
81 |
|
PAA-18 |
Ventilation Louvre |
87 |
81 |
|
PAA-19 |
Ventilation Louvre |
87 |
81 |
|
PAA-20 |
Ventilation Louvre |
93 |
87 |
|
PAA-21 |
Ventilation Louvre |
93 |
87 |
|
PAA-22 |
Ventilation Louvre |
87 |
81 |
|
PAA-23 |
Ventilation Louvre |
87 |
81 |
|
PAA-24 |
Ventilation Louvre |
93 |
87 |
|
PAA-25 |
Ventilation Louvre |
93 |
87 |
|
PAA-26 |
Ventilation Louvre |
87 |
81 |
|
PAA-27 |
Ventilation Louvre |
93 |
87 |
|
PAA-28 |
Ventilation Louvre |
93 |
87 |
|
PAA-29 |
Ventilation Louvre |
87 |
81 |
|
PAA-30 |
AC Outdoor Unit |
87 |
81 |
Mitigation Measure
Cumulative Fixed Plant
Noise Impact
Source of Impact
4.7.2
Ancillary buildings
would be constructed aboveground along the tunnel for emergency access and
ventilation purpose. The ancillary buildings would be concrete structures and
fitted with ventilation equipment, metal ducting and louvers at the ventilation
openings. It is anticipated that there would be no direct air-borne noise
transmission paths from the tunnel to outdoor via the ancillary buildings. Any noise from louvres of the ancillary
facilities, considered as noise from fixed plant sources, would be controlled
under NCO through adoption of appropriate measures such as absorptive lining
and splitter attenuator. High
performance attenuators could be installed in the ventilation air duct system
to control ventilation fan noise and also substantially reduce train noise
emission, if any, to the outside.
Construction Phase
[1] Fixed Plant Noise Audit Report for
South Island Line (East), November 2016 (https://www.epd.gov.hk/eia/register/english/permit/vep5082016/documents/fpnar/pdf/fpnar.pdf)
[2] Environmental Review Report for supporting the Variation of
Environmental Permit (VEP) of Sheung Shui to Lok Ma Chau Spur Line 2021
(Application No.: VEP-604/2021)