TABLE OF CONTENTS

 

4        Airborne noise impact. 4-1

4.1        Introduction. 4-1

4.2        Environmental Legislation, Standards, and Guidelines. 4-1

4.3        Description of Existing Environment 4-4

4.4        Noise Sensitive Receivers. 4-6

4.5        Construction Phase. 4-17

4.6        Operational Phase - Fixed Plant Noise Impact Assessment 4-30

4.7        Operational Phase - Rail Noise Impact Assessment 4-55

4.8        Environmental Monitoring and Audit Requirement 4-56

4.9        Conclusion. 4-56

 

 

List of Tables

 

Table 4.1     Noise Criteria for Daytime Construction Noise. 4-2

Table 4.2     Construction Noise Criteria during Restricted Hours. 4-3

Table 4.3     Acceptable Noise Levels for Airborne Rail Noise. 4-3

Table 4.4     Acceptable Noise Levels for Fixed Noise Source. 4-4

Table 4.5     Representative NAPs for Construction Noise Impact Assessment 4-6

Table 4.6    Representative NAPs for Operational Noise - Fixed Plant Noise Impact Assessment 4-10

Table 4.7     Summary of Unmitigated Construction Noise Levels. 4-20

Table 4.8     Summary of Mitigation Measures adopted for PMEs. 4-25

Table 4.9     Summary of Mitigated Construction Noise Levels. 4-27

Table 4.10  Predicted Maximum Allowable SWL for Planned Noise Source. 4-33

 

 

List of Figures

 

C1603/C/NOL/ACM/M52/301

Locations of Prevailing Background Noise Measurement

C1603/C/NOL/ACM/M52/302

Location of Prevailing Background Noise Measurement (Tin Shui Wai, near Wetland Seasons Park Phase 1)

C1603/C/NOL/ACM/M52/310 to C1603/C/NOL/ACM/M52/323

Locations of Noise Sensitive Receivers (Existing)

C1603/C/NOL/ACM/M52/330 to C1603/C/NOL/ACM/M52/339

Locations of Noise Sensitive Receivers (Planned)

C1603/C/NOL/ACM/M52/351 to C1603/C/NOL/ACM/M52/362

Locations of Representative Noise Assessment Points (Construction Noise)

C1603/C/NOL/ACM/M52/390 to C1603/C/NOL/ACM/M52/402

Locations of Representative Noise Assessment Points (Fixed Plant Noise)

 

 

List of Appendices

 

Appendix 4.1

Prevailing Background Noise Measurement

Appendix 4.2

Proposed Fixed Plant Noise Criteria for NSRs

Appendix 4.3

Existing NSRs to be Removed or Resumed

Appendix 4.4

Photographs of Selected Representative Noise Sensitive Receivers

Appendix 4.5

SWLs of PMEs

Appendix 4.6

Detailed PME Inventory

Appendix 4.7

Locations of Workfronts for Construction

Appendix 4.8

Unmitigated Construction Noise Calculation

Appendix 4.9

Sketch of Typical Temporary Noise Barrier & Enclosure

Appendix 4.10

Mitigated Construction Noise Calculation

Appendix 4.11

Fixed Plant Noise Calculation

Appendix 4.12

Fixed Plant Noise Measurement at Existing KSR Station

Appendix 4.13

Predicted Fixed Plant Noise Levels at the NSRs at Representative Floor Levels

Appendix 4.14

Locations of Noise Canopy and Elevation of NTD

 

 


4                  Airborne noise impact

4.1              Introduction

4.1.1         Potential airborne noise impacts likely arising from both the construction and operational phases of the Project were evaluated in this section.   Recommendations on noise mitigation measures were also made where necessary and appropriate.

4.2              Environmental Legislation, Standards, and Guidelines

General

4.2.1         Noise impacts were assessed in accordance with Annexes 5 and 13 of the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) and the Project Study Brief (i.e. ESB-346/2021).

4.2.2         The Noise Control Ordinance, Cap. 400 (NCO) and Environmental Impact Assessment Ordinance, Cap. 499 (EIAO) provide the statutory framework for noise control. Assessment procedures and standards are set out in the following Technical Memoranda (TMs):

·         Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM);

·         Technical Memorandum for the Assessment of Noise from Places other than Domestic Premises, Public Places or Construction Sites (IND-TM);

·         Technical Memorandum on Noise from Construction Work in Designated Areas (DA-TM);

·         Technical Memorandum on Noise from Construction Work other than Percussive Piling (GW-TM); and

·         Technical Memorandum on Noise from Percussive Piling (PP-TM).

4.2.3         Percussive piling is governed under the PP-TM and a construction noise permit (CNP) is required in order to carry out such work.  As the issuance of a CNP by the Noise Control Authority (NCA) would depend on the compliance of percussive piling noise impact with the limits set out within the PP-TM, in addition to no percussive piling works required during the construction of the Project, the assessment of this type of noise was not covered in the EIA Report.

Construction Noise Criteria during Non-restricted Hours

4.2.4         There is no statutory limit on construction noise during non-restricted hours (i.e. 0700 – 1900 hours of any day not being a Sunday or general holiday) under NCO and related TMs.  Nevertheless, the EIAO-TM promulgated under the EIAO imposes noise criteria to ensure a better environment.   Daytime general construction works (excluding percussive piling) between the 0700 – 1900 hours on weekdays, is controlled under the EIAO-TM.  Annex 5 of the EIAO-TM sets out the construction noise assessment limits, which are Leq(30 min) 75 dB(A) for domestic premises, hotels and hostels; and Leq(30 min) 70 dB(A) for schools during normal hours (Leq(30 min) 65 dB(A) during examination periods) and all other places where unaided voice communication is required. The noise criteria are summarised in Table 4.1.

Table 4.1   Noise Criteria for Daytime Construction Noise

Uses(1)

Daytime (0700 to1900 hours on any day not being a Sunday or general holiday)

(Leq, 30min, dB(A))

All domestic premises including temporary housing accommodation

75

Hotels and hostels

75

Educational institutions (including kindergartens, nurseries and all others where unaided voice communication is required

70

65 (During examinations)

Notes:

(1)    The above standards apply to uses which rely on opened windows for ventilation.

(2)    The above standards shall be viewed as the maximum allowable noise levels assessed at 1m from the external façade.

 

Construction Noise Criteria during Restricted Hours

4.2.5         The NCO provides statutory control on general construction works during restricted hours (i.e. 1900 to 0700 hours (of the next day) from Monday to Saturday and at any time on Sundays or public holidays).  The use of Powered Mechanical Equipment (PME) for construction works during restricted hours would require a Construction Noise Permit (CNP).  The GW-TM details the procedures adopted by EPD for assessing such application.  The granting of a CNP is subject to conditions stated in the CNP, and it may be revoked at any time for failure to comply with the permit conditions. 

4.2.6         In addition to the general controls on the use of PME during restricted hours, the use of Specified Powered Mechanical Equipment (SPME) and the undertaking of Prescribed Construction Work (PCW) within a designated area during the restricted hours would require a CNP and are controlled by the DA-TM.  The SPME defined under the DA-TM includes hand-held breaker, bulldozer, concrete lorry mixer, dump truck and hand-held vibratory poker, while the PCW includes the erection or dismantling of formwork or scaffolding; hammering; and loading, unloading or handling of rubble, wooden boards, steel bars, wood or scaffolding material.  The DA-TM details the procedures adopted by EPD for assessing the use of SPME and/or the undertaking of PCW within a designated area during restricted hours and for determining whether a CNP would be issued. As defined in the Noise Control Designated Area Plan No. EPD/AN/NT-01, some construction area of the Project would fall within the Designated Area (DA).

4.2.7         A CNP may be granted in cases where the noise can be contained within the Acceptable Noise Level (ANL) at the noise sensitive receivers (NSRs).  ANLs are assigned depending upon the Area Sensitivity Rating (ASR).  The corresponding basic noise levels (BNLs) for the evening and night-time periods are given in Table 4.2.

Table 4.2   Construction Noise Criteria during Restricted Hours

Time Period

BNL During Restricted Hours 
(Leq, 5min, dB(A)) (1)

ASR ‘A’

ASR ‘B’

ASR ‘C’

All days during the evening (1900 to 2300 hours), and general holidays (including Sundays) during the daytime and evening (0700 to 2300 hours)

60 (45)

65 (50)

70 (55)

All days during the night-time (2300 to 0700 hours)

45 (30)

50 (35)

55 (40)

Note:

(1)        Figures in brackets are BNLs for SPME within the designated area.

 

4.2.8         As defined in the Noise Control Designated Area Plan No. EPD/AN/NT-01, the works sites at Shui Mei Road, Pok Wai, Long Ha, Yau Tam Mei Tsuen and Shek Wu Wai San Tsuen, etc. are within the DA.

4.2.9         Despite any description or assessment made in this EIA Report on construction noise aspects, there is no guarantee that a CNP will be issued for the Project construction. The Noise Control Authority will consider a well-justified CNP application, once filed, for construction works within restricted hours as guided by the relevant TMs issued under the NCO.  It will also take into account contemporary conditions/ situations of adjoining land uses and any previous complaints against construction activities at the site before deciding whether to grant a CNP.  Nothing in the EIA Report should bind the Noise Control Authority in making its decision.  If a CNP is to be issued, the Noise Control Authority should include in the permit any condition it thinks fit.  Failure to comply with any such conditions will lead to cancellation of the CNP and prosecution under the NCO.

Operational Noise – Airborne Rail Noise

4.2.10       The EIAO-TM and IND-TM stipulate the appropriate ANL for airborne rail noise.  The ANLs are dependent on ASR of the NSR and are shown in Table 4.3.  The EIAO-TM also specifies the maximum rail noise limit of Lmax 85 dB(A) between 2300 and 0700 hours.

Table 4.3      Acceptable Noise Levels for Airborne Rail Noise

Time Period

Noise Criteria (Leq, 30min, dB(A))

ASR ‘A’

ASR ‘B’

ASR ‘C’

Daytime and Evening (0700 to 2300 hours) 

60

65

70

Night-time (2300 to 0700 hours)

50

55

60

 

4.2.11       The NOL alignment would be located underground except a short trough section at the tunnel portal connecting to Ngau Tam Mei Depot (NTD).  The NTD has been designed with concrete deck and vertical walls to avoid noise nuisance to the NSRs nearby from train operation within NTD.  The depot openings have been minimized as far as practicable. In addition, the internal surfaces of NTD would be lined with noise absorption materials with due consideration of engineering and operation constraints to further minimise the noise nuisance. The short trough section has also been minimised as far as practicable and would also be covered by noise canopies with natural ventilation feature. With such design, there would be no direct line of sight from any NSRs to the airborne railway noise sources.

4.2.12       For maintenance trains depart and return to the NTD between 2300 and 0700 hours, these will be used to support maintenance operations in the transporting of personnel and plant for inspection and remedial works. The night-time train noise from maintenance trains would be governed by CNP under NCO and hence would not be quantified in this EIA study.

Operational Noise – Fixed Plant Noise

4.2.13       Fixed noise sources associated with the Project are controlled by the NCO and IND-TM.  The ANL is a function of the type of area within which the NSRs are located, and the degree of the effect on the NSRs of influencing factors such as major roads and industrial areas.

4.2.14       More stringent criteria for planned fixed plant noise impact stipulated in the EIAO-TM for planning purposes are as follows.

·         5 dB(A) below the appropriate ANL set out in the IND-TM; or

·         prevailing background noise level where the prevailing background noise level is 5 dB(A) below the appropriate ANL (i.e. ANL – 5 dB(A)).

4.2.15       The ANLs for different time periods are given in Table 4.4.  In any event, the Area Sensitivity Rating assumed in the EIA Report is for indicative assessment only.  Therefore, the Noise Control Authority shall determine noise impact from concerned fixed noise sources on the basis of prevailing legislation and practices being in force, and taking account of contemporary conditions/situations of adjoining land uses.  Nothing in the EIA study shall bind the Noise Control Authority in the context of law enforcement against any of the fixed noise sources being assessed. 

Table 4.4      Acceptable Noise Levels for Fixed Noise Source

Time Period

 ANL, dB(A)

ANL-5, dB(A)

ASR ‘A’

ASR ‘B’

ASR ‘C’

ASR ‘A’

ASR ‘B’

ASR ‘C’

Daytime and Evening (0700 to 2300 hours)

60

65

70

55

60

65

Night (2300 to 0700 hours)

50

55

60

45

50

55

 

4.3              Description of Existing Environment

4.3.1         The Project is located in the northern part of the New Territories where majority of the area is predominantly in rural nature.  The underground alignment would pass through a large area of wetlands, agricultural lands, private lots, brown field sites, village developments and low-density residential developments.  There are also numerous planned housing developments located within and in the vicinity of the assessment area such as public housing developments at Kam Tin South, public housing development near Sha Po Tsuen, as well as the new development areas at Kwu Tung, San Tin and Ngau Tam Mei.

4.3.2         The existing noise climate in the vicinity of the Project area is dominated by the road traffic noise from Tsing Long Highway, San Tin Highway and Fanling Highway, as well as the rail noise from TML at Kam Tin area.  In addition, isolated industrial operations scattered throughout the Project area also contribute to the overall ambient noise levels.  These operations include open storage facilities, warehouse, container back-up areas and car stripping/repair workshops. 

Prevailing Background Noise Measurement

4.3.3         According to the latest information provided by MTR Corporation, the fixed plant noise sources of the Project would be located at stations, ancillary buildings (ABs), and NTD.  Background noise measurements were conducted at various locations in the vicinity of the Project to obtain prevailing background noise levels during weekday and weekend.

4.3.4         In accordance with IND-TM, sound level meter in compliance with International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications were used for carrying out the noise measurement.  Immediately prior to and following each noise measurement, the accuracy of sound level meter was checked using an acoustic calibrator generating 94dB at 1000 Hz.  Measurement was considered to be valid with the calibration level from before and after the noise measurement within 1.0 dB(A).

4.3.5         Prevailing background noise was measured in L90 (1hr). During the noise measurement, the following procedures were followed:

·         Parameters such as frequency weighting, the time weighting and the duration of measurement were set as follows:

-       Frequency weighting: A

-       Time weighting: Fast

-       Duration of measurement: at least 24 hours continuously to cover both daytime and night-time periods (with data being logged at every one second)

·         Noise measurements were conducted in accordance with standard acoustic principles and practices in the relation to weather conditions.

4.3.6         For the measurement conducted under free-field condition, a façade correction of +3dB(A) was added to the measurement result to account the façade reflection effect.

4.3.7         For the prevailing background noise within future KTN NDA, reference was made to Table 4.15 of the approved EIA report for North East New Territories New Development Areas (NENT NDA) (Register No.: AEIAR-175/2013).

4.3.8         For simulation of the future conditions at SAT and NTM NDAs, background noise measurement was conducted at Tin Shui Wai (near Wetland Seasons Park Phase 1), where are located in the same type of area “Area other than those above” with prevailing background dominated by road traffic on Wetland Park Road, for determination of comparable background noise at these NDAs.  Noise climate of future San Tin / Lok Ma Chau Development Node (STLMC DN) with SAT Station will be dominated by planned District Distributor roads (i.e. Road D1), similar to the condition at Wetland Season Park of which the noise climate is dominated by Wetland Park Road.  As both planned Road D1 and Wetland Park Road are classified as District Distributor Road, the prevailing background noise measured near Wetland Season Park is considered representative to that of future SAT Station area.  Similarly, it is anticipated that the noise climate at the area to the south of NTD would be dominated by future road network within the area under Land Use Review Study for Ngau Tam Mei Area (NTM LUR). Although the road category of the planned road is not available in this stage, the scale of the road is expected to be similar to Wetland Park Road.  Hence, the prevailing background noise within NTM LUR area is expected to be similar to Wetland Season Park, and the prevailing background noise measured near Wetland Season Park is considered also representative to that of area to the south of NTD. 

4.3.9         Locations of the prevailing background noise measurement are shown in Figure Nos. C1603/C/NOL/ACM/M52/301 to 302.  The prevailing noise measurement results and measurement details is presented in Appendix 4.1.

4.3.10       Based on the measurement results in Appendix 4.1, appropriate noise criteria for planned fixed noise sources were determined by comparing the prevailing background noise levels and the appropriate ANL-5 dB(A).   The proposed fixed plant noise criteria for different NSRs are summarised in Appendix 4.2.

4.4              Noise Sensitive Receivers

4.4.1         The assessment area for the noise impact assessment was set as 300m from the boundary of the Project and the works areas/works sites.  With reference to the criteria set out in Annex 13 of EIAO-TM, observations from site visits and review of relevant land use plans including the Outline Zoning Plans (OZP), Development Permission Area Plans, Outline Development Plans, Layout Plans and other relevant published land use plans, including plans and drawings published by the Lands Department and any land use and development applications approved by the Town Planning Board, representative existing and planned NSRs, within 300m assessment area of the Project boundary were identified.  All NSRs within the assessment area are shown in Figure Nos. C1603/C/NOL/ACM/M52/310 – 323 and C1603/C/NOL/ACM/M52/330 – 339.

4.4.2         Some of the existing NSRs, that are close to the Project, would be removed / resumed by the Project or other concurrent projects according to the respective construction programme provided by the project proponent, and thus these NSRs, as listed in Appendix 4.3, would not be considered in the noise impact assessment. 

4.4.3         Representative NSRs located closest to the subject noise sources, i.e. first layer of NSRs, are considered the most affected locations.  Furthermore, the first layer of NSRs would provide acoustic shielding to those receivers at further distance behind.  The first layer of NSRs represents the worst-case scenario and are selected as representative Noise Assessment Point (NAPs) for noise assessment.   A summary of representative NAPs, including the planned/committed and existing NSRs, for different noise impact assessments is presented in Table 4.5 and Table 4.6 respectively with their locations shown in Figure Nos. C1603/C/NOL/ACM/M52/351 – 362 and C1603/C/NOL/ACM/M52/390 – 402.  Photographs of representative NSRs are shown in Appendix 4.4.

Table 4.5     Representative NAPs for Construction Noise Impact Assessment

NAP ID

Description

Land Use (1)

Existing / Planned

No. of Storey

PHD-E1

11D Shek Wu Tong

R

Existing

2

PHDKSR-E1

2 Shek Wu Tong

R

Existing

2

PHDKSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

Planned

N/A (2)

PHDKSR-P2

Planned Residential Block at Kam Tin South Housing Development

R

Planned

N/A (2)

PHDKSR-P3

Planned Residential Block at Kam Tin South Housing Development

R

Planned

N/A (2)

KSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

Planned

N/A (2)

KSR-P2

Planned G/IC Site at Kam Tin South Housing Development(3)

G/IC

Planned

N/A (2)

KSR-P3

Planned G/IC Site at Kam Tin South Housing Development

G/IC

Planned

N/A (2)

KSR-P4

Planned Residential Block at Kam Tin South Housing Development

R

Planned

N/A (2)

KSR-P5

Grand Mayfair

R

Planned

16

KSR-P6

Grand Mayfair

R

Planned

16

KSR-P7

Grand Mayfair

R

Planned

16

KSR-P8

Planned School Site at Kam Tin South Housing Development

E

Planned

N/A (2)

KSR-E1

230 Kat Hing Wai

R

Existing

3

SMR-E1

Tower 8B, Park Yoho

R

Exiting

14

SMR-E2

Tower 1A, Park Yoho

R

Existing

14

AUT-E1

Shum Residence

R

Existing

2

AUT-E2

26 Mo Fan Heung

R

Existing

1

AUT-P1

Planned Residential Block at Sha Po Public Housing Development

R

Planned

N/A (2)

AUT-P2

Planned Residential Block at Sha Po Public Housing Development

R

Planned

N/A (2)

AUT-P3

Planned Residential Block at Sha Po Public Housing Development

R

Planned

N/A (2)

POW-E1

166 Pok Wai

R

Existing

2

POW-E2

171A Pok Wai

R

Existing

1

POW-E3

169 Pok Wai

R

Existing

2

POW-E4

170 Pok Wai

R

Existing

3

LHT-E1

Village House in Long Ha

R

Existing

1

NTM-E1

Hongtai Home for the Aged Limited

HA

Existing

3

NTM-E2

Village House in Yau Tam Mei Tsuen

R

Existing

2

NTM-E3

Temporary Structure near Chun Shin Road

R

Existing

1

NTM-E4

Village House near Chuk Yau Road

R

Existing

2

NTM-E5

Temporary Structure near Chuk Yau Road

R

Existing

2

NTM-E6

Village House near Wang Ping Shan South Road

R

Existing

2

NTM-E7

House A, Greenacres Villa

R

Existing

3

NTM-E8

Temporary Structure near Ching Yau Road

R

Existing

1

SAT-E1

Temporary Structure near Shek Wu Wai San Tsuen

R

Existing

1

SAT-E2

Temporary Structure near Shek Wu Wai San Tsuen

R

Existing

1

SAT-E3

Temporary Structure near Shek Wu Wai

R

Existing

1

SAT-E4

89 Shek Wu Wai

R

Existing

3

SAT-E5

Temporary Structure near Shek Wu Wai

R

Existing

2

SAT-E6

Christian New Life Association

R

Existing

1

KLR-E1

616 Siu Hum Tsuen

R

Existing

3

KTR-E1

Village House near Kwu Tung Road

R

Existing

1

KTR-E2

Village House near Kwu Tung Road

R

Existing

2

KTR-E3

271 Chau Tau Tsuen

R

Existing

3

PSA-E1

Village House near Pak Shek Au

R

Existing

1

KTU-P1

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P2

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P3

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P4

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P5

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P6

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P7

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

KTU-P8

Planned Housing Development at Kwu Tung North NDA

R

Planned

N/A (2)

TSH-E1

Village House near Tai Shu Ha Road West

R

Existing

1

Notes:

(1)         E – Educational Institution; G/IC – Government, Institution or Community; HA – Home for the Aged; R – Residential.

(2)         Information regarding number of storeys for the planned/ committed developments is unavailable at the time of preparing this EIA Report.

(3)         Based on the best available information provided by CLP Power Hong Kong Limited, there will be a cable reserve zone along the southwest boundary of the G/IC site and a planned substation to be located at southern part of the GI/C site. Information subject to the design of the planned development. The NAP was assumed at a location outside the cable reserve zone and the planned substation

 


Table 4.6      Representative NAPs for Operational Noise - Fixed Plant Noise Impact Assessment

NAP ID(1),(21)

Description

Land Use(2)

Existing / Planned

No. of

Storey

Type of Area

Influencing Factor

Degree to which NSR is affected

Area Sensitive Rating (3),(4)

KSR-PF01a

Future Kam Sheung Road Package 2 Property Development

R

Planned

-(6)

Area other than those above(7)

-

-

B

KSR-PF01b

Future Kam Sheung Road Package 2 Property Development

R

Planned

-(6)

Area other than those above(7)

-

-

B

KSR-PF01c

Future Kam Sheung Road Package 2 Property Development

R

Planned

-(6)

Area other than those above(7)

-

-

B

KSR-PF02a

Grand Mayfair

R

Planned

16

Area other than those above(8)

-

-

B

KSR-PF02b

Grand Mayfair

R

Planned

16

Area other than those above(8)

-

-

B

KSR-PF02c

Grand Mayfair

R

Planned

16

Area other than those above(8)

-

-

B

KSR-PF02d

Grand Mayfair

R

Planned

16

Area other than those above(8)

-

-

B

KSR-PF03a

Planned G/IC Site at Kam Tin South Housing Development

G

Planned

-(6)

Area other than those above(9)

-

-

B

KSR-PF03b

Planned G/IC Site at Kam Tin South Housing Development

G

Planned

-(6)

Area other than those above(9)

-

-

B

KSR-PF04

Planned Residential Block at Kam Tin South Housing Development

R

Planned

-(6)

Area other than those above(9)

-

-

B

KSR-PF05

Planned G/IC Site at Kam Tin South Housing Development

G

Planned

-(6)

Area other than those above(9)

-

-

B

KSR-PF06

Planned School Site at Kam Tin South Housing Development

E

Planned

-(6)

Area other than those above(9)

-

-

B

KSR-PF08

Planned School in Park Yoho Phase 3

E

Planned

-(6)

Area other than those above(10)

-

-

B

KSR-PF08a

Planned School in Park Yoho Phase 3

E

Planned

-(6)

Area other than those above(10)

-

-

B

AUT-F01

Tower 8B, Park Yoho

R

Existing

14

Area other than those above(11)

-

-

B

AUT-F01a

Tower 5B, Park Yoho

R

Existing

13

Area other than those above(11)

-

-

B

AUT-PF01

Planned Residential Block at Sha Po Public Housing Development

R

Planned

-(6)

Area other than those above(13)

San Tin Highway

Not Affected

B

AUT-PF02

Planned Residential Block at Sha Po Public Housing Development

R

Planned

-(6)

Area other than those above(13)

San Tin Highway

Not Affected

B

AUT-PF03

Planned Residential Block at Sha Po Public Housing Development

R

Planned

-(6)

Area other than those above(13)

San Tin Highway

Not Affected

B

AUT-PF04

Planned Residential Block at Sha Po Public Housing Development

R

Planned

-(6)

Area other than those above(13)

San Tin Highway

Not Affected

B

AUT-F06

26 Mo Fan Heung

R

Existing

2

Area other than those above

Industrial Zone

Within 100m of Industrial Zone

B (12)

AUT-F02

Shum Residence

R

Existing

2

Area other than those above

Industrial Zone

Within 100m of Industrial Zone

B (12)

AUT-F05a

166 Pok Wai

R

Existing

2

Low density residential area

San Tin Highway

Indirectly Affected

B

AUT-F05b

170 Pok Wai

R

Existing

3

Low density residential area

San Tin Highway

Indirectly Affected

B

AUT-F05c

169 Pok Wai

R

Existing

2

Low density residential area

San Tin Highway

Indirectly Affected

B

NTM-F01

Village House in Long Ha

R

Existing

1

Area other than those above(14)

San Tin Highway

Not Affected

B

NTM-F02

Village House in Long Ha

R

Existing

1

Low density residential area

-

-

A

NTM-F04

Hongtai Home for the Aged Limited

HA

Existing

3

Area other than those above(16)

-

-

B

NTM-F04a

Temporary Structure near Ching Yau Road

R

Existing

1

Area other than those above(16)

-

-

B

NTM-F05

The Dhamma Garden

R/W

Existing

3

Area other than those above(18)

-

-

B

NTM-F05a

Temporary Structure near Chuk Yau Road

R

Existing

2

Area other than those above(16)

-

-

B

NTM-F06

Village House near Wang Ping Shan South Road

R

Existing

2

Area other than those above(16)

-

-

B

NTM-F07

Temporary Structure near Chun Shin Road

R

Existing

1

Low density residential area

-

-

A

NTM-F08

Village House near Chuk Yau Road

R

Existing

2

Area other than those above(16)

-

-

B

NTM-PF01(17)

Potential Development at Land Use Review Study for Ngau Tam Mei Area (NTM LUR)

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF01a(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF01b(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF02(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF04(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07a (17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07b(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07c(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07d(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07e(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07f(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07g(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07h(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07q(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07r(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

NTM-PF07s(17)

Potential Development at NTM LUR

-(6)

Planned

-(6)

Area other than those above(16)

-

-

B

SAT-F02

Temporary Structure near Shek Wu Wai

R

Existing

1

Low density residential area

-

-

A

SAT-PF01a

Potential Housing Development in San Tin / Lok Ma Chau Development Node (STLMC DN)

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01b

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01c

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01d

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01e

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01f

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF01h

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF02d

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF03

Potential School in STLMC DN

E

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF03a

Potential Housing Development in STLMC DN

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-PF05a

Potential FSD Staff Quarter in San Tin / Lok Ma Chau Development Node

R

Planned

-(6)

Area other than those above(19)

-

-

B

SAT-F04

271 Chau Tau Tsuen

R

Existing

3

Low density residential area

-

-

A

KTU-F01

Village House near Pak Shek Au

R

Existing

1

Area other than those above(14)

-

-

B

KTU-F01a

Village House near Pak Shek Au

R

Existing

1

Area other than those above(14)

-

-

B

KTU-PF01a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF01b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF01c

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF02a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF02b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF03a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF03b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF04a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF04b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF05a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF05b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF06a

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF06b

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF06c

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

KTU-PF07

Planned Housing Development at Kwu Tung North NDA

R

Planned

-(6)

Area other than those above(20)

-

-

B

Notes:

(1)        For planned/committed development, the locations of NAP were identified based on the best available information provided from the relevant parties.

(2)        E- Educational; HA - Home for the Aged; R – Residential; W – Place of Public Worship; G – G/IC

(3)        The corresponding ASR of the NSRs are determined based on the best available information and is for indicative assessment only. The Noise Control Authority shall determine noise impact from concerned noise sources on the basis of prevailing legislation and practices being in force, and the ASR determined in this report should not bind the Authority when enforcing the NCO based on the contemporary conditions. The ASR would be reviewed as necessary based on the contemporary conditions/situations such as adjoining land uses, influencing factors or the latest new development areas.

(4)        The fixed plant noise criteria are “ANL-5 dB(A)” of respective Area Sensitive Rating or prevailing background noise level where the prevailing background noise level is 5 dB(A) below the appropriate ANL.

(5)        Not used.

(6)        Information subject to the design of planned development.

(7)        As the areas in the vicinity of the Future Kam Sheung Road Package 2 Property Development (i.e. Grand Mayfair and Kam Tin South Public Housing Development) will be developed to medium to high-density residential area, type of area was considered to be “Area other than those above”.

(8)        According to the information in Sales Brochure of the development, Grand Mayfair will be developed to a medium to high-density residential area, type of area was therefore considered to be “Area other than those above”.

(9)        According to the building layout plans provided by Housing Department, the Planned Kam Tin South Development (Site 1 & 6) would be developed to medium to high-density residential area, type of area was therefore considered to be “Area other than those above”. 

(10)      According to planning application A/YL-KTN/604 and A/YL-KTN/663, Park Yoho Phase 2 and 3 will be developed to a medium to high-density residential area, type of area was therefore considered to be “Area other than those above.

(11)      NAP is located in a medium to high-density residential area with some scattered industrial activities (e.g. garage), type of area was therefore considered to be “Area other than those above”.

(12)      Considering the existing industrial zone would be changed to other land uses for Sha Po Public Housing Development, as conservative approach, the effect of industrial zone was not considered to determine the appropriate noise criteria.

(13)      According to the block layout provided by Housing Department, the Proposed Public Housing Development Near Sha Po Tsuen would be developed to medium to high-density residential area, type of area was therefore considered to be “Area other than those above”. 

(14)      In view of open storages/industrial uses located in the vicinity of the NSRs, type of area was considered to be “Area other than those above”.

(15)      Not used.

(16)      According to Section 16 of LC Paper No. CB(1)756/20-21(01–) - Using Brownfield Clusters for Public Housing Development (Second Phase Review) and Other Developments, Ngau Tam Mei Area would be developed to provide a mix of over 6,000 public and private housing units. Based on this information, type of area was considered to be “Area other than those above”.

(17)      Reference was made to the draft Preliminary Outline Development Plan (PODP) of Land Use Review Study for Ngau Tam Mei Area provided by the relevant government department.

(18)      Not Used.

(19)      According to Section 14 of LC Paper No. CB(1)756/20-21(01) - Using Brownfield Clusters for Public Housing Development (Second Phase Review) and Other Developments, the San Tin Lok Ma Chau Development Node (STLMC DN) would be developed as a new development area supporting an estimated housing yield of 31 000 units together with economic and community facilities. Based on this information, type of area was considered to be “Area other than those above”. 

(20)      Based on the information provided in the approved NENT NDA EIA report (Register No.: AEIAR-175/2013), the area near KTU(NOL) Station will be developed to a medium to high-density residential area, type of area was therefore considered to be “Area other than those above”.

(21)      The identification of the planned NAPs is based on the following sources of best available information:

§  KSR-PF01a, KSR-PF1b & KSR-PF1c - No indicative layout plan was available during the course of EIA study and therefore the indicative location of NAP was set at the boundary of the Future Kam Sheung Road Package 2 Property Development.

§  KSR-PF02a, KSR-PF02b, KSR-PF02c and KSR-PF02d- Reference was made to the building layout provided in Sales Brochure of the development (See Note (8) above).

§  KSR-PF03a & KSR-PF3b - Based on the best available information provided by CLP Power Hong Kong Limited, there will be a cable reserve zone along the southwest boundary of the G/IC site and a planned substation to be located at southern part of the G/IC site. The NAP was assumed at a location outside the cable reserve zone and the planned substation.

§  KSR-PF05 & KSR-PF06 – Assessment points were assigned at the boundary of the respective zone for the conservative approach.

§  KSR-PF04 - Reference was made to building layout plans provided by Housing Department.

§  KSR-PF08 and KSR-PF08a - Reference was made to planning application A/YL-KTN/604 and A/YL-KTN/663, and the NAPs were identified based on the Indicative Master Layout Plan shown in these planning applications.

§  AUT-PF01, AUT-PF02, AUT-PF03 and AUT-PF04 - Reference was made to the building layout plans in Final Report (Sha Po) of Agreement No. CE 10/2020 (CE) Site Formation and Infrastructure Works for Proposed Public Housing Developments at Sha Po, Shap Pat Heung and Tai Kei Leng, Yuen Long – Feasibility Study, as provided by Housing Department.

§  NTM-PF01 to NTM-PF07s – Please refer to Note (17) above.

§  SAT-PF01a to SAT-PF05a – Reference was made to the Recommended Outline Development Plan (RODP) provided by the project proponent of STLMC DN.

§  KTU-PF01a to KTU-PF07 - Reference was made to the information provided by CEDD.

 


4.5              Construction Phase

Source of Impact

4.5.1         The potential sources of airborne noise impact during construction phase of the Project would mainly be the use of PME for various construction activities.  Key construction works that would contribute to airborne construction noise impacts are summarized below.

·         Construction of 5 stations including KSR(NOL), AUT, NTM, SAT and KTU(NOL) by cut-and-cover;

·         Construction of tunnel connecting KSR(NOL), AUT, NTM, SAT and KTU(NOL) Stations by Tunnel Boring Machine (TBM);

·         Construction of branching tunnel connecting to NTD by cut-and-cover, mined and drill-and-blast tunnelling method;

·         Construction of NTD;

·         Construction of overrun tunnel section at KSR and crossover box and bifurcation at SAT by cut-and-cover;

·         Demolition of EAP (an aboveground structure) under Existing EAL at Kwu Tung;

·         Construction of ABs for EAP/EEPs/VBs;

·         Site clearance, construction and reinstatement of temporary explosive magazine at Tai Shu Ha (Yuen Long) and reinstatement;

·         Works such as temporary traffic management (TTM), landscaping, minor reinstatement, material delivery, etc.; and

·         Construction, operation, and demolition of a concrete batching plant (CBP) at San Tin.

4.5.2         For the construction of branching tunnel connecting to NTD, drill-and-blast tunnelling method would be adopted.  There is no statutory procedure or criteria under the NCO and EIAO for assessing the blasting impacts. However, the administrative and procedural control of all blasting operations in Hong Kong is vested in the Mines Division of the CEDD. The Dangerous Goods (General) Regulations, Chapter 295B also stipulates that no person shall carry out blasting unless the possesses a valid mine blasting certificate to be issued by the Mines Division of CEDD. 

4.5.3         Major planned/ committed projects in the vicinity which may have potential interface with the Project were identified in Section 2.9 and recapped below.  Any cumulative airborne construction noise impacts from these concurrent projects would be considered and addressed in the EIA Study as appropriate.

·         Kam Tin South Public Housing Development;

·         Grand Mayfair (under construction);

·         Kam Sheung Road Package 2 Property Development;

·         Kam Tai Road Residential Development (under construction);

·         Park Yoho Phase 2 & 3 Development;

·         Sha Po Public Housing Development;

·         Land Use Review Study for Ngau Tam Mei Area;

·         Proposed watermains under Ngau Tam Mei Water Treatment Works Extension;

·         San Tin Lok Ma Chau Development Node – Investigation (also known as San Tin Technopole);

·         Kwu Tung North New Development Area – Advance Works;

·         Kwu Tung North New Development Area – Remaining Phase; and

·         Kwu Tung Station on Lok Ma Chau Spur Line.

4.5.4         The construction of the Project will tentatively commence in 2025 for completion in 2034. The plant inventory (Appendix 4.6 refers) was provided and confirmed by the construction professional for the construction noise impact assessment, while the construction programme is shown in Appendix 2.2. 

4.5.5         Practically, the PMEs will not be operating for all times within a work site. The utilization rates would depend on the construction sequences, work fronts scale and construction nature.  In this assessment, the utilization rates were reviewed by the construction professionals and were concluded to be practical for the purposed of this EIA.  Appendix 4.6 tabulates the adopted utilization rates, and Appendix 4.7 presents the currently envisaged locations of the workfronts and distances between the notional sources and the NAPs. 

4.5.6         The Project Proponent has formulated a reasonable construction programme to avoid noisy construction works, particularly the aboveground works,  to be carried out in restricted hours as far as practicable.  According to the proposed construction programme, most of the proposed construction works would be carried out during non-restricted hours.  However, certain construction works which would cause not only serious interruption or disruption to road or rail traffic but also the safety concern to pedestrians and drivers. Therefore, some works are unavoidably required to be carried out during restricted hours, so as to minimise inconvenience/ safety issue to the public.  In case of any construction activities are unavoidable to be conducted during restricted hours (i.e. 1900 – 0700 hours), it is the Contractor’s responsibility to ensure the compliance with the NCO and the relevant TMs. The Contractor should submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued.  According to best available information in this stage, the construction works that would be carried out during restricted hours have been identified as below:

·         Construction works in proximity to existing rail operation; and 

·         Construction of tunnels by TBM (Figure No. C1603/C/NOL/ACM/M50/305 refers).

4.5.7         In addition, TBM would be operated during restricted hours at some locations.  As the operation of TBM would be underground, the airborne construction noise impact is not anticipated.  However, if there would be any associated activities such as removal of debris and rocks during restricted hours, the Contractor should submit CNP application to the Noise Control Authority. 

Assessment Methodology

4.5.8         The airborne construction noise impact assessment was conducted based on the following procedures:

·         Determine 300m from the boundary of the Project and the works sites/areas;

·         Obtain the construction methods and work sequences for the construction period;

·         Obtain the construction plant inventory for each corresponding construction work sequence;

·         Determine the Sound Power Levels (SWLs) of the plant items according to the information stated in the GW-TM or other recognised sources of reference, where appropriate;

·         Calculate the correction factors based on the distance between the NSRs and the notional noise source positions of the work sites;

·         Apply corrections for façade, distance, barrier attenuation, acoustic reflection where applicable;

·         Predict construction noise levels at the NAPs;

·         Quantify the level of impact at the NAPs, in accordance with GW-TM;

·         Predict the cumulative noise impacts for any concurrent construction works in the vicinity of the proposed work;

·         For any exceedance of noise criteria, all practical mitigation measures such as alternative construction methodology, quiet plant, silencer for ventilation fan, full noise enclosure for TBM launching shafts/ retrieval shafts, etc., should be examined to alleviate the predicted noise impacts as much as practicable; and

·         Consideration of noise mitigation measures by following Annex 13 of EIAO-TM, EIAO Guidance Note “Preparation of Construction Noise Impact Assessment under the Environmental Impact Assessment Ordinance” [GN 9/2010] and Good Practices on Mitigation Construction Noise by EPD.

Cumulative Construction Noise Impact

4.5.9         Concurrent projects in the vicinity of the Project as listed out in Section 4.5.3 were reviewed.  Cumulative construction noise impacts arising from San Tin Lok Ma Chau Development Node and NENT NDA have been included in this quantitative impact assessment where appropriate.

4.5.10       In accordance with the approved Environmental Review Report (ERR) for the Variation of Environmental Permit (VEP) of Sheung Shui to Lok Ma Chau Spur Line (Application No.: VEP-604/2021), the construction of KTU(EAL) Station would tentatively commence in Q3 2023 for completion by 2027.  Major construction activities including site mobilization and excavation would be carried out from Q1 2024 to Q2 2025.  Only minor construction works, i.e. structural works, site reinstatements, and inspection and trial runs, that would not cause significant construction noise impacts, would remain afterwards.  Cumulative construction noise impacts are anticipated to be the most significant in Q2 2025 when the construction works for KTU(NOL) Station starts, yet they are considered to be relatively transient.  Any cumulative impacts due to construction of KTU(EAL) Station are expected to be minimal from Q3 2025 onwards.

4.5.11       For the concurrent projects with no details on the construction programme and plant inventory at the time of preparing this EIA, they are not included in this cumulative assessment.

Prediction and Evaluation of Environmental Impacts

 

Unmitigated Airborne Construction Noise Impact during Non-restricted Hours

4.5.12       For normal daytime working hours, according to the latest engineering design, construction would mainly comprise the activities as described in Section 4.5.1.  Appendix 4.5 presents the SWLs of each PME.  Appendix 4.6 presents the plant inventory adopted for each workfront while Appendix 4.7 shows the locations of workfronts adopted for this construction noise assessment.

4.5.13       Appendix 4.8 presents the unmitigated construction noise levels predicted at representative NAPs, while the summary of unmitigated construction noise levels at the NAPs under unmitigated scenario is provided in Table 4.7 below.

Table 4.7      Summary of Unmitigated Construction Noise Levels

NAP ID

Description

Land Use(1)

Daytime Noise Criterion,

Leq (30min), dB(A) (2)

Max. Unmitigated Construction Noise Levels, Leq (30mins), dB(A) (3)

Max. Noise Exceedance, dB(A) (2)

PHD-E1

11D Shek Wu Tong

R

75

70

-

PHDKSR-E1

2 Shek Wu Tong

R

75

73

-

PHDKSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

75

82

7

PHDKSR-P2

Planned Residential Block at Kam Tin South Housing Development

R

75

84

9

PHDKSR-P3

Planned Residential Block at Kam Tin South Housing Development

R

75

83

8

KSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

75

78

3

KSR-P2

Planned G/IC Site at Kam Tin South Housing Development

G/IC

75

88

13

KSR-P3

Planned G/IC Site at Kam Tin South Housing Development

G/IC

75

79

4

KSR-P4

Planned Residential Block at Kam Tin South Housing Development

R

75

79

4

KSR-P5

Grand Mayfair

R

75

84

9

KSR-P6

Grand Mayfair

R

75

80

5

KSR-P7

Grand Mayfair

R

75

78

3

KSR-P8

Planned School Site at Kam Tin South Housing Development

E

70 (65)

87

17(22)

KSR-E1

230 Kat Hing Wai

R

75

75

-

SMR-E1

Tower 8B, Park Yoho

R

75

87

12

SMR-E2

Tower 1A, Park Yoho

R

75

70

-

AUT-E1

Shum Residence

R

75

80

5

AUT-E2

26 Mo Fan Heung

R

75

86

11

AUT-P1

Planned Residential Block at Sha Po Public Housing Development

R

75

66

-

AUT-P2

Planned Residential Block at Sha Po Public Housing Development

R

75

69

-

AUT-P3

Planned Residential Block at Sha Po Public Housing Development

R

75

63

-

POW-E1

166 Pok Wai

R

75

87

12

POW-E2

171A Pok Wai

R

75

86

11

POW-E3

169 Pok Wai

R

75

91

16

POW-E4

170 Pok Wai

R

75

84

9

LHT-E1

Village House in Long Ha

R

75

73

-

NTM-E1

Hongtai Home for the Aged

HA

75

85

10

NTM-E2

Village House in Yau Tam Mei Tsuen

R

75

85

10

NTM-E3

Temporary Structure near Chun Shin Road

R

75

78

3

NTM-E4

Village House near Chuk Yau Road

R

75

90

15

NTM-E5

Temporary Structure near Chuk Yau Road

R

75

86

11

NTM-E6

Village House near Wang Ping Shan South Road

R

75

82

7

NTM-E7

House A, Greenacres Villa

R

75

78

3

NTM-E8

Temporary Structure near Ching Yau Road

R

75

83

8

SAT-E1

Temporary Structure near Shek Wu Wai San Tsuen

R

75

80

5

SAT-E2

Temporary Structure near Shek Wu Wai San Tsuen

R

75

83

8

SAT-E3

Temporary Structure near Shek Wu Wai

R

75

80

5

SAT-E4

89 Shek Wu Wai

R

75

85

10

SAT-E5

Temporary Structure near Shek Wu Wai

R

75

81

6

SAT-E6

Christian New Life Association

R

75

84

9

KLR-E1

616 Siu Hum Tsuen

R

75

66

-

KTR-E1

Village House near Kwu Tung Road

R

75

79

4

KTR-E2

Village House near Kwu Tung Road

R

75

79

4

KTR-E3

271 Chau Tau Tsuen

R

75

69

-

PSA-E1

Village House near Pak Shek Au

R

75

83

8

KTU-P1

Planned Housing Development at Kwu Tung North NDA

R

75

75

-

KTU-P2

Planned Housing Development at Kwu Tung North NDA

R

75

83

8

KTU-P3

Planned Housing Development at Kwu Tung North NDA

R

75

76

1

KTU-P4

Planned Housing Development at Kwu Tung North NDA

R

75

71

-

KTU-P5

Planned Housing Development at Kwu Tung North NDA

R

75

70

-

KTU-P6

Planned Housing Development at Kwu Tung North NDA

R

75

88

13

KTU-P7

Planned Housing Development at Kwu Tung North NDA

R

75

86

11

KTU-P8

Planned Housing Development at Kwu Tung North NDA

R

75

86

11

TSH-E1

Village House near Tai Shu Ha Road West

R

75

60

-

Notes:

(1)   E – Educational Institution; G/IC – Government, Institution or Community; HA – Home for the Aged; R – Residential.

(2)   Values in parentheses are applicable to the examination period of education institution.

(3)   Bolded values indicate exceedance against the relevant noise criterion.

 

4.5.14       Based on the above table, without implementation of mitigation measures, the exceedances of noise criteria would range from 1 to 16 dB(A) for residential premises, and 17 dB(A) and 22 dB(A) during normal period and examination period for school respectively. It is estimated that approximately 160 dwellings (existing dwellings at the time of preparing this EIA Report) would be exposed to construction noise impacts exceeding the relevant criteria under unmitigated scenario.

Unmitigated Airborne Construction Noise Impact during Restricted Hours

 

4.5.15       The Project Proponent has formulated a reasonable construction programme to avoid works particularly the aboveground works,  to be carried out in restricted hours as far as practicable.  According to the proposed construction programme, most of the proposed construction works would be carried out during non-restricted hours.  However, certain construction works which would cause not only serious interruption or disruption to road or rail traffic but also the safety concern to pedestrians and drivers are required to be carried out during restricted hours, so as to minimise inconvenience to the public.  In case of any construction activities are unavoidable to be conducted during restricted hours (i.e. 1900 – 0700 hours), it is the Contractor’s responsibility to ensure the compliance with the NCO and the relevant TMs.  The Contractor should submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued. 

Mitigation Measures

 

4.5.16       Given that there would be construction noise exceedances predicted during daytime period, mitigation measures are therefore required with the following mitigation measures considered:

·         Adoption of quieter construction methods;

·         Good site practices to limit noise emissions at the source;

·         Use of quiet PMEs;

·         Use of temporary movable noise barriers, noise enclosure, noise insulating fabric, silencer, soundproof hammer bracket to screen noise from PMEs;

·         Installation of temporary noise barrier along PWA works site boundary to screen noise for the NSR at Pok Wai; and

·         Alternative use of plant items within one worksite, wherever practicable.

4.5.17       The above mitigation measures would be implemented at works sites as good practices where appropriate. 

Adoption of Quieter Construction Methods

4.5.18       The practicability of the following quieter construction methods has been reviewed by the construction professionals.

·         Use of TBM;

·         Use of large diameter bored piling;

·         Use of pre-casting and prefabrication technology;

·         Use of silent piling such as hydraulic press-in method; and

·         Use of rubber head poker vibrator.

 

4.5.19       Use of TBM and large diameter bored piling have been duly considered during the formulation of construction design.  They would be adopted where appropriate and practicable to substitute the noisier cut-and-cover method using excavator-mounted breaker for tunnelling and percussive piling for foundation works.

4.5.20       In addition, off-site prefabrication technologies including Modular Integrated Construction (MiC) and Design for Manufacture and Assembly (DfMA) would be used for the construction of the stations and ABs as far as practicable.  Both technologies involve the technique of having modular components (e.g. reinforced concrete beams, slabs and columns, etc.) manufactured off-site and would then be transported to site for assembly.  The adoption of MiC and DfMA could result in lesser on-site construction activity and shorter construction period, minimising any airborne construction noise impact to NSRs.

4.5.21       In view of the construction noise impacts associated with sheet piling/ H-beam piling, employment of silent piling by press-in method has been explored as well and considered practicable.  This alternative construction method would be adopted at the sites at which the construction activities would induce non-compliance, including KSR, SAT, Shui Mei Road Ancillary Building (SMA), Pak Shek Au Ancillary Building (PAA) and etc.

4.5.22       Use of rubber head poker vibrator will be adopted in place of conventional vibratory poker where appropriate and practicable.

4.5.23       For the use of hydraulic crusher and ripper, the Project Proponent will review the feasibility if further mitigation measures are required.

Good Site Practice

4.5.24       Good site practice and noise management techniques could considerably reduce the noise impact from construction site activities on nearby NSRs. The following measures should be practised during each phase of construction:

·         Only well-maintained plant should be operated on-site and plant should be serviced regularly during the construction programme;

·         Machines and plant (such as trucks) that may be in intermittent use should be shut down between work periods or should be throttled down to a minimum;

·         Plant known to emit noise strongly in one direction should, wherever possible, be orientated so that the noise is directed away from the nearby NSRs;

·         Silencers or mufflers which available on construction equipment should be properly fitted and maintained during the construction works;

·         Spoil transportation routes should be directed away from NSRs as far as practicable;

·         Mobile plant should be sited as far away from NSRs as possible and practicable;

·         Material stockpiles, site office and other structures should be effectively utilized, wherever practicable, to screen noise from on-site construction activities; and

·         Noise monitoring at selected NSRs should be conducted as far as practicable.

4.5.25       The benefits of these techniques can vary according to specific site conditions and operations. The environmental noise climate would certainly be improved with these control practices, although the improvement can only be quantified during implementation when specific site parameters are known.

Use of Quiet PMEs

4.5.26       Quiet PMEs would be adopted where appropriate, by making reference to the PME listed in the GW-TM, the Quality Powered Mechanical Equipment (QPME)/ other commonly used PME listed in EPD web pages or PME specification published by equipment manufacturer. It is generally known (supported by field measurement) that particular models of construction equipment are quieter than standard types given in the GW-TM.

4.5.27       The types of quiet PME adopted in this assessment are presented in Appendix 4.5 and is for reference only.  The Contractor may adopt alternative quiet PME which can be demonstrated that they would not result in construction noise impacts worse than those predicted in this assessment.

Use of Temporary Movable Noise Barrier, Noise Enclosure, Noise Insulating Fabric, Silencer and Soundproof Hammer Bracket

4.5.28       Temporary movable noise barriers that can be located close to noisy plant and be moved concurrently with the plant along a worksite can be very effective for screening noise from NSRs. A typical design which has been used locally is a wooden framed barrier with a small-cantilevered upper portion of superficial density no less than 7kg/m2 on a skid footing with 25mm thick internal sound absorptive lining. This measure is particularly effective for low level zone of NSRs. A cantilevered top cover would be required to achieve screening benefits at upper floors of NSRs.

4.5.29       Temporary movable noise barriers will be used for some PME (e.g. excavator). It is anticipated that suitably designed barriers could achieve at least 5dB(A) reduction for movable plant and 10dB(A) for stationary plant.

4.5.30       For the use of temporary movable noise barrier for at-grade construction works, working space would be considered for their manoeuvrability and placement. Generally, sufficient separation between major plants during at-grade construction works is envisaged to cater for the use of temporary movable noise barriers onsite. Temporary movable noise barrier can be placed close to noise source locally as far as practicable.

4.5.31       In addition, noise insulating fabric (acoustic mats) would be installed for PME such as piling rigs and drilling rigs and the fabric should be lapped such that there would be no opening or gaps on the joints.  With reference to MTRC Contract C4420 Tsim Sha Tsui Modification Noise Assessment Report for Variation of Environmental Permit (July 2003) and the technical data from manufacturer, a noise reduction of over 10dB(A) could be achieved with the use of the fabric.  Therefore, as a conservative approach, a noise reduction of 10dB(A) for the PME lapped with the fabric was assumed in this assessment.

4.5.32       The use of standard enclosure has been considered in this assessment to shelter relatively fixed plant including water pump, etc. These standard enclosures can provide at least 15dB(A) noise reduction.

4.5.33       To minimise the noise impact arising from excavator-mounted hydraulic breakers, soundproof hammer bracket will also be installed by Contractor.  According to the "Best Practice Guide for Environmental Protection on Construction Sites", page 6-10, published by Hong Kong Construction Association, May 2013, excavator-mounted breaker with soundproof hammer bracket can provide a noise reduction of up to 10 dB(A).  The bracket should be made of special alloy and the inside of it is lined with sound insulation material. For conservativeness, the soundproof hammer bracket should be used together with a temporary movable noise barrier or other equivalent mitigation measure(s) for achieving a noise reduction of 10 dB(A) noise reduction.

4.5.34       The feasibility, practicability, programming and effectiveness of the above mitigation measures have been reviewed.

4.5.35       A summary of the temporary movable noise barrier, noise enclosure, noise insulating fabric, etc., adopted for various PMEs is given in Appendix 4.5 and the associated noise reduction is summarised in Table 4.8. Indicative drawings for barrier and enclosure are shown in Appendix 4.9.

Table 4.8      Summary of Mitigation Measures adopted for PMEs

PME

Mitigation Measures

Attenuation, dB(A)

Air compressor, air flow > 30m3/min

Barrier

-10

Asphalt paver

Barrier

-5

Batching Plant

Barrier

-10

Hand-held breaker

Barrier

-10

Breaker, excavator mounted (hydraulic)

Barrier with Soundproof Hammer Bracket (or other equivalent mitigation measure(s))

-10

Bulldozer

Barrier

-5

Concrete corer

Enclosure

-15

Concrete lorry mixer

Barrier

-5

Concrete mixer

Barrier

-10

Concrete pump

Enclosure

-15

Mobile crane

Barrier

-5

Crane, tower (electric)

Barrier

-5

Compactor, vibratory

Barrier

-10

Drill/ grinder, percussive, hand-held (electric)

Barrier

-10

Excavator/ loader

Barrier

-5

Hoist

Barrier

-5

Piling, diaphragm wall, bentonite filtering plant/ slurry treatment plant

Barrier

-10

Piling, larger diameter bored, grab and chisel

Acoustic Mat

-10

Piling, larger diameter bored, oscillator

Acoustic Mat

-10

Piling, larger diameter bored, reverse circulation drill

Acoustic Mat

-10

Piling, earth auger

Acoustic Mat

-10

Power pack

Barrier

-10

Vibratory poker

Barrier

-10

Planer

Barrier

-10

Roller, vibratory

Barrier

-5

Saw

Barrier

-10

Ventilation fan

Silencer

-15

Drill rig

Acoustic Mat

-10

Grout pump

Barrier

-10

Portable generator

Barrier

-10

Vibrating hammer

Barrier

-10

Lorry

Barrier

-5

Dump truck

Barrier

-5

Installation of Temporary Noise Barrier along the PWA Works Site Boundary

4.5.36       In view of the close proximity between a village house (i.e. POW-E3) and construction works for PWA, a noise barrier, which would provide at least 8dB(A) noise reduction, is proposed along the site boundary adjacent to the concerned NSR.  The location and the section drawing of the proposed temporary noise barrier is shown in Appendix 4.10.  The design of the barrier should include the followings:

·         Gaps and openings at joints should be avoided;

·         The length of the barrier should be about 75m while the height should be about 2.3m; and

·         Surface density of the barrier should be no less than 7kg/m2.

Alternative Use of Plant Items within One Works Site

4.5.37       In practice, some plant items will operate sequentially within the same worksite, and certain reduction of the predicted noise impacts could be achieved.  However, any additional control on the sequencing of plants will impose a restrictive constraint to the Contractor on the operation and planning of plant items, and the implementation of the requirement would be difficult to be monitored.  Hence, sequencing operation of PME has not been taken into consideration.

Mitigation Measures for Construction Works During Restricted Hours

4.5.38       The Contractor(s) should avoid conducting construction activities during restricted hours as far as practicable. If such construction activities are unavoidable, the Contractor(s) should adopt quieter construction methods such as use of QPME, quieter PME, quieter construction method (such as use of hydraulic crusher/wire saw/hand-held concrete crusher instead of hydraulic breaker for demolition works), purpose-built noise barrier and noise enclosure as far as practicable for construction activities during restricted hours to ensure compliance with the NCO and relevant TM.  The effectiveness and practicality of all these identified measures should be investigated and verified during the design, tendering and implementation stage of the construction works.

 

Mitigated Construction Noise Levels during Non-Restricted Hours

 

4.5.39       Appendix 4.10 presents the details of mitigated construction noise levels predicted at the representative NAPs.  A summary of the mitigated construction noise levels predicted at the NAPs is provided in Table 4.9 below.

Table 4.9      Summary of Mitigated Construction Noise Levels

NAP ID

Description

Land Use(1)

Daytime Noise Criterion,

Leq (30min), dB(A) (2)

Mitigated Construction Noise Levels, Leq (30mins), dB(A) (3)

Max. Noise Exceedance, dB(A) (2)

PHD-E1

11D Shek Wu Tong

R

75

55

-

PHDKSR-E1

2 Shek Wu Tong

R

75

57

-

PHDKSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

75

66

-

PHDKSR-P2

Planned Residential Block at Kam Tin South Housing Development

R

75

67

-

PHDKSR-P3

Planned Residential Block at Kam Tin South Housing Development

R

75

67

-

KSR-P1

Planned Residential Block at Kam Tin South Housing Development

R

75

65

-

KSR-P2

Planned G/IC Site at Kam Tin South Housing Development

G/IC

75

75

-

KSR-P3

Planned G/IC Site at Kam Tin South Housing Development

G/IC

75

66

-

KSR-P4

Planned Residential Block at Kam Tin South Housing Development

R

75

68

-

KSR-P5

Grand Mayfair

R

75

73

-

KSR-P6

Grand Mayfair

R

75

68

-

KSR-P7

Grand Mayfair

R

75

67

-

KSR-P8

Planned School Site at Kam Tin South Housing Development

E

70 (65)

70

(5)

KSR-E1

230 Kat Hing Wai

R

75

63

 

SMR-E1

Tower 8B, Park Yoho

R

75

75

-

SMR-E2

Tower 1A, Park Yoho

R

75

55

-

AUT-E1

Shum Residence

R

75

69

-

AUT-E2

26 Mo Fan Heung

R

75

75

-

AUT-P1

Planned Residential Block at Sha Po Public Housing Development

R

75

53

-

AUT-P2

Planned Residential Block at Sha Po Public Housing Development

R

75

57

-

AUT-P3

Planned Residential Block at Sha Po Public Housing Development

R

75

51

-

POW-E1

166 Pok Wai

R

75

72

-

POW-E2

171A Pok Wai

R

75

71

-

POW-E3

169 Pok Wai

R

75

75

-

POW-E4

170 Pok Wai

R

75

70

-

LHT-E1

Village House in Long Ha

R

75

- (6)

-

NTM-E1

Hongtai Home for the Aged

HA

75

74

-

NTM-E2

Village House in Yau Tam Mei Tsuen

R

75

73

-

NTM-E3

Temporary Structure near Chun Shin Road

R

75

64

-

NTM-E4

Village House near Chuk Yau Road

R

75

74

-

NTM-E5

Temporary Structure near Chuk Yau Road

R

75

70

-

NTM-E6

Village House near Wang Ping Shan South Road

R

75

71

-

NTM-E7

House A, Greenacres Villa

R

75

64

-

NTM-E8

Temporary Structure near Ching Yau Road

R

75

71

-

SAT-E1

Temporary Structure near Shek Wu Wai San Tsuen

R

75

70

-

SAT-E2

Temporary Structure near Shek Wu Wai San Tsuen

R

75

72

-

SAT-E3

Temporary Structure near Shek Wu Wai

R

75

69

-

SAT-E4

89 Shek Wu Wai

R

75

74 (5)

-

SAT-E5

Temporary Structure near Shek Wu Wai

R

75

71

-

SAT-E6

Christian New Life Association

R

75

71

-

KLR-E1

616 Siu Hum Tsuen

R

75

71 (4)

-

KTR-E1

Village House near Kwu Tung Road

R

75

67

-

KTR-E2

Village House near Kwu Tung Road

R

75

67

-

KTR-E3

271 Chau Tau Tsuen

R

75

59

-

PSA-E1

Village House near Pak Shek Au

R

75

70

-

KTU-P1

Planned Housing Development at Kwu Tung North NDA

R

75

64 (5)

-

KTU-P2

Planned Housing Development at Kwu Tung North NDA

R

75

72 (5)

-

KTU-P3

Planned Housing Development at Kwu Tung North NDA

R

75

65 (5)

-

KTU-P4

Planned Housing Development at Kwu Tung North NDA

R

75

60 (5)

-

KTU-P5

Planned Housing Development at Kwu Tung North NDA

R

75

59 (5)

-

KTU-P6

Planned Housing Development at Kwu Tung North NDA

R

75

75 (5)

-

KTU-P7

Planned Housing Development at Kwu Tung North NDA

R

75

74 (5)

-

KTU-P8

Planned Housing Development at Kwu Tung North NDA

R

75

74 (5)

-

TSH-E1

Village House near Tai Shu Ha Road West

R

75

52

-

Notes:

(1)   E – Educational Institution; G/IC – Government, Institution or Community; HA – Home for the Aged; R – Residential.

(2)   Values in parentheses are applicable to the examination period of education institution.

(3)   Bolded values indicate exceedance against the relevant noise criterion.

(4)   No mitigation measures are considered necessary and proposed, given that compliance with noise criterion under unmitigated scenario. Cumulative airborne construction noise impacts from San Tin Lok Ma Chau Development Node were incorporated.

(5)   Cumulative airborne construction noise impacts from San Tin Lok Ma Chau Development Node and NENT NDA were incorporated.

(6)   No mitigation measures are considered necessary and proposed, given that compliance with noise criterion under unmitigated scenario.

 

4.5.40       With the adoption of the above mitigation measures, the predicted construction noise levels at the identified NAPs would be largely reduced, complying with the corresponding noise criterion, except at the planned school site at Kam Tin South Housing Development (i.e. KSR P-8) where exceedance of 5dB(A) are still anticipated during examination period. The Contractor should liaise with the representative of concerned school and/or the Examination Authority to ascertain the exact dates and times of all examination periods during the construction period and should avoid conducting noisy activities during the examination periods if the school is relied on opened windows for ventilation.  With the avoidance of particular noisy construction activities during the examination periods, the mitigated construction noise impact at the concerned school would comply with the stipulated noise criterion.

4.5.41       It is recommended that Construction Noise Management Plan(s) (CNMP(s)) should be prepared based on the best available information before the issue of tender and the commencement of construction works, subject to the contract arrangement of the Project and agreement with EPD.  The plan should include a quantitative construction noise impact assessment with details on the construction method, plant inventory and recommended noise mitigation measures for the future contractors’ further update on CNMP before commencement of construction works and implementation in order to minimise the construction noise impact and comply with the EIAO-TM. In addition, further review on the cumulative construction noise impact should be conducted as necessary in the later CNMP when the information of the concurrent project is available. The CNMP(s) should be certified by Certified Noise Modelling Professional of Hong Kong Institute of Qualified Environmental Professionals (HKIQEP) or equivalent.

Evaluation of Residual Construction Noise Impacts

4.5.42       With the implementation of the recommended noise mitigation measures, including quieter construction methods, good site practices, the use of QPME, temporary movable noise barriers, proper scheduling and arrangement of concerned construct activities and avoidance of using particular noisy PMEs during examination period, the predicted construction noise levels at the NSRs during non-restricted hours would comply with the noise criteria set out in EIAO-TM.

Construction Noise Impact during Restricted Hours

4.5.43       The Contractor should avoid works to be carried out within restricted hours as far as practicable. However, it is envisaged that some construction works which are listed in Section 4.5.6 would cause not only serious interruption or disruption to road or rail traffic, but also the safety concern to pedestrians and drivers. Therefore, some works are unavoidably required to be conducted during restricted hours. In addition, removal of debris and rocks for operation of TBM would be carried out in restricted hours. Nevertheless, it is the Contractor’s responsibility to ensure the compliance of noise generated from any construction activities that are unavoidable to be conducted during restricted hours (i.e. 1900 – 0700 hours) with the NCO and the relevant TMs. The Contractor should submit CNP application to the Noise Control Authority and abide by any conditions stated in the CNP, should one be issued. 

4.6              Operational Phase - Fixed Plant Noise Impact Assessment

Assessment Methodology – Fixed Plant Noise

4.6.1         Given that the noise specifications of the proposed fixed plant items are not available during the EIA Study, the maximum allowable sound power levels were therefore determined for future detailed design of the fixed plant.  For the assessment of noise from the fixed plant, the Max. SWLs of the identified fixed noise sources were determined by adopting standard acoustics principles.  The following formula was used for calculating the Max. SWLs of the fixed plant:

SPL = Max SWL – DC + FC + BC

where

SPL

Sound Pressure Level, in dB(A)

Max SWL

Maximum Allowable Sound Power Level , in dB(A)

DC

Distance Attenuation, in dB(A) (i.e. 20 log D + 8 [where D is the distance in metres])

FC

Facade Correction, in dB(A) (i.e. 3 dB(A))

BC

Barrier Correction, in dB(A)

4.6.2         It is assumed that all fixed plant within the same location would be operated at the same time as the worst-case operation mode / scenario.  Screening correction offered by buildings or other structures such as proposed stations, ABs and residential buildings was taken into account in calculating the predicted noise levels.  Barrier correction of -10 dB(A) was applied if the direct line of sight between the noise source and NSR is blocked by buildings or natural terrains, while a barrier correction of -5 dB(A) was applied for NSR do not have direct line of sight to the fixed plant.  A positive 3 dB(A) was added to predicted noise levels at the NSRs due to the façade effect.

4.6.3         Corrections of tonality, intermittency or impulsiveness were not included owing to the lack of design/supplier information at the time of preparing the EIA study.  If the noise exhibits any of these characteristics during detailed design or operation of the plant, the noise limit of the plants should be reduced in accordance with the recommendation given in IND-TM.

4.6.4         Other than the potential fixed plant noise impact arising from the Project, cumulative fixed plant noise may also contribute from the existing and planned fixed plant noise sources of other railway projects.  Existing/Planned fixed plant sources of other railway projects may include:

·         Existing fixed plant sources at PHD;

·         Existing ventilation louvers at KSR Station on TML; and

·         Fixed plant sources on the Lok Ma Chau Spur Line (LMCSL) of EAL.

4.6.5         Cumulative fixed plant noise impacts from other railway projects were assessed quantitatively.

Source of Impact – Fixed Plant Noise

 

4.6.6         The major fixed plant noise sources would be the new electrical and mechanical (E&M) equipment to be installed in the proposed stations, NTD and ABs.  It is expected that most of the fixed noise sources would be housed within plant rooms, which would be effective in most cases for minimising fixed plant noise impact.  In NTD, fixed noise sources would comprise ventilation fans, traction substation and plants associated with building and maintenance services including a train wash, running maintenance track, lifting track, workshop, a loco shed, plantrooms to support the operation of NOL.  Loco shed, train wash, running maintenance track, lifting track and workshop will be located under the concrete deck of the NTD and away from the depot's ingress/outgress/openings, such that noise impact from these facilities to surroundings are considered minimal. Other fixed noise sources such as traction substation, a ventilation building, louvres and cooling towers which will be located outside the concrete deck were included in the fixed plant noise assessment.  The operational modes of the fixed plants have been confirmed by railway operation professionals.

4.6.7         It should be noted that the locations and the number of the fixed plant sources would be subject to change during the design evolvement of the Project in the later stage (e.g. detailed design stage).  In addition, the blocking layouts of planned developments in the vicinity of the Project were yet to be available during the EIA stage.  Nevertheless, a preliminary fixed plant noise assessment was conducted, following the assessment methodology stated in Section 4.6.1, to estimate the maximum allowable SWLs of the fixed plant noise sources.  The design of fixed noise sources should be further reviewed by Engineer/Contractor to ensure the compliance of NCO and EIAO-TM criteria in the detailed design stage or fitting-out stage and after the development layouts of planned development in the vicinity of the Project being finalized. Due considerations should be given to locate major plants and noisy activities far away from depot's ingress/outgress/openings, and quieter plants and quieter designs should also be adopted during detailed design stage.

4.6.8         Locations of fixed noise sources and the relevant concerned NSRs are shown in Figure Nos. C1603/C/NOL/ACM/M52/390 to 402.  The validity of the inventory and locations of the fixed noise sources was confirmed with the Project Engineer.

4.6.9         The maximum SWLs of the fixed plant noise sources of the Project are presented in Table 4.10.  Detailed noise calculations for daytime and evening (i.e. 0700 – 2300 hours) and night-time (i.e. 2300 – 0700 hours) operations are shown in Appendix 4.11.  The predicted noise impacts at different NAPs with various representative floor levels are presented in Appendix 4.13.

Table 4.10    Predicted Maximum Allowable SWL for Planned Noise Source

Location

Fixed Plant Source ID

Fixed Plant Source

Maximum Allowable SWL during Daytime/Evening Period, dB(A)

Maximum Allowable SWL during
Night-time Period, dB(A)

Kam Sheung Road Station

K01a

Ventilation Louvre

72

61

K01b

Ventilation Louvre

73

62

K01c

Ventilation Louvre

73

62

K02

Ventilation Louvre at Transformer (Tx) Room

83

72

K03

Ventilation Louvre at Transformer (Tx) Room

71

60

K04

Ventilation Louvre at Transformer (Tx) Room

83

72

K05

Ventilation Louvre at Transformer (Tx) Room

71

60

K06

Ventilation Louvre at Transformer (Tx) Room

83

72

K07

Ventilation Louvre at Transformer (Tx) Room

71

60

K08

Ventilation Louvre at Transformer (Tx) Room

83

72

K09

Ventilation Louvre at Transformer (Tx) Room

76

65

K09a

Ventilation Louvre

73

62

K09b

Ventilation Louvre

73

62

K09c

Ventilation Louvre

74

63

K09d

Chiller Plantroom Fresh Air Intake

74

63

K10

Ventilation Louvre

81

70

K10a

Ventilation Louvre

69

58

K10b

Ventilation Louvre

71

60

K10c

Ventilation Louvre

71

60

K10d

Ventilation Louvre

71

60

K11

Ventilation Louvre at Transformer (Tx) Room

71

60

K12

Ventilation Louvre at Transformer (Tx) Room

71

60

K13

Ventilation Louvre at Transformer (Tx) Room

71

60

K14

Ventilation Louvre at Transformer (Tx) Room

71

60

K15

Ventilation Louvre at Transformer (Tx) Room

71

60

K16

Ventilation Louvre at Transformer (Tx) Room

71

60

K17

Ventilation Louvre at Transformer (Tx) Room

71

60

K18

Ventilation Louvre at Transformer (Tx) Room

71

60

K19

Ventilation Louvre

86

75

K20

Ventilation Louvre

88

77

K20a

Ventilation Louvre

79

68

K21

Ventilation Louvre

79

68

K22

Ventilation Louvre

86

75

K22a

Ventilation Louvre

81

70

K22b

Ventilation Louvre

81

70

K22c

Ventilation Louvre

83

72

K23

Ventilation Louvre

86

75

K24

Ventilation Louvre

86

75

K25

Ventilation Louvre

86

75

K26

Ventilation Louvre

86

75

K27

Ventilation Louvre

85

74

K27a

Ventilation Louvre

83

72

K28

Ventilation Louvre

88

77

K29

Ventilation Louvre

88

77

K30

Ventilation Louvre

85

74

K30a

Ventilation Louvre

69

58

K31

Ventilation Louvre

85

74

K31a

Ventilation Louvre

66

55

K31b

Ventilation Louvre

66

55

K31c

Ventilation Louvre

81

70

K31d

Ventilation Louvre

83

72

K32

Cooling Tower (Discharge Louvre)

88

77

K33

Cooling Tower (Discharge Louvre)

88

77

K34

Cooling Tower (Discharge Louvre)

88

77

K35

Cooling Tower (Intake Louvre)

87

76

K35a

Ventilation Louvre

83

72

K35b

Ventilation Louvre

81

70

K37

Ventilation Louvre

88

77

K38

Ventilation Louvre

88

77

K39

Ventilation Louvre

88

77

K40

Ventilation Louvre

88

77

K41

Ventilation Louvre

86

75

K41a

Ventilation Louvre

77

66

K42

Ventilation Louvre

86

75

K42a

Ventilation Louvre

71

60

K43

Ventilation Louvre

86

75

K44

AC Outdoor Unit

77

66

K45

AC Outdoor Unit

77

66

K45a

Ventilation Louvre

83

72

K46

AC Outdoor Unit

77

66

K47

AC Outdoor Unit

76

65

K48

Ventilation Louvre

86

75

K48a

Ventilation Louvre

81

70

K48b

Ventilation Louvre

81

70

K49

Ventilation Louvre

88

77

K50

Ventilation Louvre

88

77

K51

Ventilation Louvre

88

77

K51a

Ventilation Louvre

81

70

K51b

Ventilation Louvre

81

70

K52

Ventilation Louvre

88

77

K53

Ventilation Louvre

85

74

K54

Ventilation Louvre

85

74

K55

Ventilation Louvre

85

74

K56

Ventilation Louvre

85

74

K57

AC Outdoor Unit

85

74

Au Tau Station

A01

Ventilation Louvre

90

80

A02

Ventilation Louvre

90

80

A03

Ventilation Louvre

90

80

A03a

Ventilation Louvre

80

70

A04

Ventilation Louvre

84

74

A04a

Ventilation Louvre

80

70

A05

Ventilation Louvre

80

70

A05a

Ventilation Louvre

80

70

A05b

Ventilation Louvre

85

75

A05c

Ventilation Louvre

85

75

A06

Ventilation Louvre

89

79

A07

Ventilation Louvre

89

79

A08

Cooling Tower (Intake Louvre)

86

76

A09

Cooling Tower (Discharge Louvre)

95

85

A10

Cooling Tower (Discharge Louvre)

95

85

A11

Cooling Tower (Discharge Louvre)

95

85

A12

Ventilation Louvre

90

80

A12a

Ventilation Louvre

85

75

A13

Ventilation Louvre

90

80

A13a

Ventilation Louvre

90

80

A14

Ventilation Louvre

85

75

A14a

Ventilation Louvre

90

80

A15

Ventilation Louvre

85

75

A15a

Ventilation Louvre

90

80

A15b

Ventilation Louvre

90

80

A15c

Ventilation Louvre

85

75

A15d

Ventilation Louvre

85

75

A16

AC Outdoor Unit

90

80

A16a

Ventilation Louvre

85

75

A16b

Ventilation Louvre

85

75

A17

AC Outdoor Unit

85

75

A17a

Ventilation Louvre

85

75

A19

Ventilation Louvre at Transformer (Tx) Room

82

72

A20

Ventilation Louvre at Tx Room

82

72

A21

Ventilation Louvre at Tx Room

82

72

A22

Ventilation Louvre at Tx Room

80

70

A23

Ventilation Louvre at Tx Room

80

70

A24

Ventilation Louvre at Tx Room

82

72

A25

Ventilation Louvre at Tx Room

80

70

A26

Ventilation Louvre at Tx Room

82

72

A26a

Ventilation Louvre

85

75

A27

Ventilation Louvre

89

79

A28

Ventilation Louvre

87

77

A28a

Ventilation Louvre

80

70

A28b

Ventilation Louvre

80

70

A29

Ventilation Louvre

87

77

A30

Ventilation Louvre at Tx Room

77

67

A31

Ventilation Louvre at Tx Room

80

70

A32

Ventilation Louvre at Tx Room

78

68

A33

Ventilation Louvre at Tx Room

80

70

A34

Ventilation Louvre at Tx Room

78

68

A35

Ventilation Louvre at Tx Room

80

70

A36

Ventilation Louvre at Tx Room

78

68

A37

Ventilation Louvre at Tx Room

80

70

A37a

Ventilation Louvre

80

70

A37b

Ventilation Louvre

80

70

A37c

Ventilation Louvre

80

70

A37d

Ventilation Louvre

82

72

A37e

Ventilation Louvre

82

72

A38

AC Outdoor Unit

87

77

A39

Ventilation Louvre

86

76

A40

Ventilation Louvre

86

76

A41

Ventilation Louvre

87

77

Ngau Tam Mei Station

N01

Ventilation Louvre

79

74

N02

Ventilation Louvre

79

74

N03

Ventilation Louvre

79

74

N04

Ventilation Louvre at Transformer (Tx) Room

77

72

N05

Ventilation Louvre at Transformer (Tx) Room

77

72

N06

Ventilation Louvre at Transformer (Tx) Room

77

72

N07

Ventilation Louvre at Transformer (Tx) Room

77

72

N08

Ventilation Louvre

80

75

N09

Ventilation Louvre at Transformer (Tx) Room

77

72

N10

Ventilation Louvre at Transformer (Tx) Room

77

72

N11

Ventilation Louvre at Transformer (Tx) Room

77

72

N12

Ventilation Louvre at Transformer (Tx) Room

82

77

N12a

Ventilation Louvre

78

73

N12b

Ventilation Louvre

78

73

N12c

Ventilation Louvre

78

73

N12d

Ventilation Louvre

80

75

N13

AC Outdoor Unit

80

75

N14

AC Outdoor Unit

80

75

N15

Ventilation Louvre at Transformer (Tx) Room

77

72

N15a

Ventilation Louvre

78

73

N16

Ventilation Louvre at Transformer (Tx) Room

77

72

N17

Ventilation Louvre

80

75

N18

Ventilation Louvre at Transformer (Tx) Room

77

72

N19

Ventilation Louvre at Transformer (Tx) Room

77

72

N20

Ventilation Louvre

80

75

N20a

Ventilation Louvre

78

73

N21

Ventilation Louvre at Transformer (Tx) Room

77

72

N21a

Ventilation Louvre

78

73

N22

Ventilation Louvre at Transformer (Tx) Room

77

72

N23

Ventilation Louvre at Transformer (Tx) Room

77

72

N24

Ventilation Louvre at Transformer (Tx) Room

77

72

N25

Ventilation Louvre

79

74

N26

Ventilation Louvre

80

75

N27

Ventilation Louvre

77

72

N28

Ventilation Louvre

79

74

N29

Ventilation Louvre

79

74

N30

Ventilation Louvre

77

72

N30a

Ventilation Louvre

78

73

N31

Ventilation Louvre

79

74

N31a

Ventilation Louvre

82

77

N31b

Ventilation Louvre

82

77

N31c

Ventilation Louvre

82

77

N31d

Ventilation Louvre

82

77

N32

Ventilation Louvre

80

75

N32a

Ventilation Louvre

78

73

N32b

Ventilation Louvre

78

73

N33

Ventilation Louvre

80

75

N34

Ventilation Louvre

80

75

N34a

Ventilation Louvre

73

68

N35

Ventilation Louvre

82

77

N36

Ventilation Louvre

80

75

N37

Ventilation Louvre

80

75

N38

Ventilation Louvre

68

63

N39

Ventilation Louvre

80

75

N39a

Ventilation Louvre

75

70

N40

Ventilation Louvre

78

73

N40a

Ventilation Louvre

78

73

N40b

Ventilation Louvre

82

77

N41

Ventilation Louvre

75

70

N41a

Ventilation Louvre

72

67

N43

Ventilation Louvre

72

67

N44

Ventilation Louvre

76

71

N45

Ventilation Louvre

72

67

N45a

Ventilation Louvre

68

63

N45b

Ventilation Louvre

68

63

N46

Ventilation Louvre

76

71

N46a

Ventilation Louvre

75

70

N47

Ventilation Louvre

76

71

N47a

Ventilation Louvre

75

70

N47b

Ventilation Louvre

75

70

N47c

Ventilation Louvre

75

70

N48

Ventilation Louvre

79

74

N49

Ventilation Louvre

76

71

N50

Cooling Tower (Intake Louvre)

81

76

N50a

Cooling Tower (Discharge Louvre)

81

76

N51

Cooling Tower (Intake Louvre)

81

76

N52

Ventilation Louvre

78

73

N53

Ventilation Louvre

79

74

N54

Ventilation Louvre

79

74

N55

Ventilation Louvre

79

74

N56

Ventilation Louvre

79

74

Ngau Tam Mei Depot

NTD01

Ventilation Louvre

78

73

NTD02

Ventilation Louvre

76

71

NTD03

Ventilation Louvre

75

70

NTD04

Ventilation Louvre

75

70

NTD05

Ventilation Louvre

75

70

NTD06

Ventilation Louvre

76

71

NTD07

Ventilation Louvre

75

70

NTD08

Ventilation Louvre

75

70

NTD09

Ventilation Louvre

70

65

NTD10

Ventilation Louvre

70

65

NTD11

Ventilation Louvre

70

65

NTD12

Ventilation Louvre

75

70

NTD13

Ventilation Louvre

79

74

NTD14

Ventilation Louvre

77

72

NTD15

Ventilation Louvre

77

72

NTD15a

Transformer

80

75

NTD16

Ventilation Louvre

80

75

NTD16a

Transformer

80

75

NTD17

Ventilation Louvre

77

72

NTD18

Ventilation Louvre

73

68

NTD19

Ventilation Louvre

73

68

NTD20

Ventilation Louvre

73

68

NTD21

Ventilation Louvre

78

73

NTD22

Ventilation Louvre

80

75

NTD23

Ventilation Louvre

80

75

NTD24

Ventilation Louvre

76

71

NTD25

Ventilation Louvre

80

75

NTD26

Ventilation Louvre

70

65

NTD27

Ventilation Louvre

70

65

NTD28

Ventilation Louvre

75

70

NTD29

Ventilation Louvre

75

70

NTD30

Ventilation Louvre

83

78

NTD31

Ventilation Louvre

80

75

NTD32

Ventilation Louvre

82

77

NTD33

Ventilation Louvre

81

76

NTD34

Ventilation Louvre

80

75

NTD35

Ventilation Louvre

85

80

NTD36

Ventilation Louvre

85

80

NTD37

Ventilation Louvre

85

80

NTD38

Ventilation Louvre

85

80

NTD39

Ventilation Louvre

85

80

NTD40

Ventilation Louvre

80

75

NTD41

Ventilation Louvre

75

70

NTD42

Ventilation Louvre

75

70

NTD43

Ventilation Louvre

75

70

NTD44

Ventilation Louvre

75

70

NTD45

Ventilation Louvre

75

70

NTD46

Ventilation Louvre

75

70

NTD47

Ventilation Louvre

75

70

NTD48

Ventilation Louvre

70

65

NTD49

Ventilation Louvre

70

65

NTD50

Ventilation Louvre

70

65

NTD51

Ventilation Louvre

80

75

NTD52

Ventilation Louvre

73

68

NTD53

Ventilation Louvre

68

63

NTD54

Ventilation Louvre

73

68

NTD55

Ventilation Louvre

85

80

NTD56

Ventilation Louvre

72

67

NTD57

Ventilation Louvre

78

73

NTD58

Ventilation Louvre

73

68

NTD59

Ventilation Louvre

70

65

NTD60

Ventilation Louvre

69

64

NTD61

Ventilation Louvre

71

66

NTD62

Ventilation Louvre

80

75

NTD63

Ventilation Louvre

78

73

NTD64

Ventilation Louvre

72

67

NTD65

Ventilation Louvre

72

67

NTD66

Ventilation Louvre

74

69

NTD67

Ventilation Louvre

73

68

NTD68

Ventilation Louvre

75

70

NTD69

Ventilation Louvre

70

65

NTD70

Ventilation Louvre

75

70

NTD71

Ventilation Louvre

75

70

NTD72

Ventilation Louvre

78

73

NTD73

Ventilation Louvre

75

70

NTD74

Ventilation Louvre

75

70

NTD75

Ventilation Louvre

75

70

NTD76

Ventilation Louvre

75

70

NTD77

Ventilation Louvre

77

72

NTD78

Ventilation Louvre

75

70

NTD79

Ventilation Louvre

76

71

NTD80

Ventilation Louvre

75

70

NTD81

Ventilation Louvre

75

70

NTD82

Ventilation Louvre

75

70

NTD83

Ventilation Louvre

75

70

NTD84

Ventilation Louvre

75

70

NTD85

Ventilation Louvre

75

70

NTD86

Ventilation Louvre

77

72

NTD87

Ventilation Louvre

75

70

NTD88

Ventilation Louvre

74

69

NTD89

Ventilation Louvre

73

68

NTD90

Ventilation Louvre

72

67

NTD91

Ventilation Louvre

75

70

NTD92

Ventilation Louvre

74

69

NTD93

Ventilation Louvre

78

73

NTD94

Ventilation Louvre

73

68

NTD94a

Ventilation Louvre

73

68

NTD95

Ventilation Louvre

73

68

NTD96

Ventilation Louvre

74

69

NTD97

Cooling Tower

80

75

NTD98

Cooling Tower

80

75

NTD99

Cooling Tower

80

75

NTD100

Ventilation Louvre

80

75

NTD101

Ventilation Louvre

80

75

NTD102

Ventilation Louvre

75

70

NTD103

Ventilation Louvre

75

70

NTD104

Ventilation Louvre

83

78

NTD105

Ventilation Louvre

73

68

NTD106

Ventilation Louvre

75

70

NTD107

Ventilation Louvre

72

67

NTD108

Ventilation Louvre

82

77

NTD109

Ventilation Louvre

82

77

NTD110

Ventilation Louvre

85

80

NTD111

Ventilation Louvre

77

72

NTD112

Ventilation Louvre

77

72

NTD113

Ventilation Louvre

77

72

NTD114

Ventilation Louvre

85

80

NTD115

Ventilation Louvre

85

80

San Tin Station

S01

Ventilation Louvre

88

80

S02

Ventilation Louvre

88

80

S03

Ventilation Louvre at Transformer (Tx) Room

88

80

S04

Ventilation Louvre at Transformer (Tx) Room

88

80

S05

Ventilation Louvre at Transformer (Tx) Room

88

80

S06

Ventilation Louvre

88

80

S07

Ventilation Louvre at Transformer (Tx) Room

88

80

S08

Ventilation Louvre at Transformer (Tx) Room

88

80

S09

Ventilation Louvre at Transformer (Tx) Room

88

80

S09a

Ventilation Louvre

88

80

S09b

Ventilation Louvre

93

85

S10

Ventilation Louvre

89

81

S10a

Ventilation Louvre

88

80

S11

Ventilation Louvre

96

88

S12

Ventilation Louvre

86

78

S13

Ventilation Louvre

85

77

S14

Ventilation Louvre

85

77

S14a

Ventilation Louvre

83

75

S14b

Ventilation Louvre

81

73

S14c

Ventilation Louvre

81

73

S15

Ventilation Louvre

87

79

S15a

Ventilation Louvre

80

72

S15b

Ventilation Louvre

80

72

S16

Ventilation Louvre

88

80

S16a

Ventilation Louvre

78

70

S17

Ventilation Louvre

85

77

S18

Ventilation Louvre

85

77

S19

Ventilation Louvre

84

76

S20

Ventilation Louvre

86

78

S20a

AC Outdoor Unit

88

77

Kwu Tung Station on NOL

KT1

Ventilation Louvre

82

70

KT2

Ventilation Louvre

82

70

KT3

Ventilation Louvre

82

70

KT4

Ventilation Louvre

82

70

KT5

Ventilation Louvre

82

70

KT6

Ventilation Louvre

82

70

KT7

Ventilation Louvre

82

70

KT8

Ventilation Louvre

82

70

KT9

Ventilation Louvre

82

70

KT10

Ventilation Louvre

82

70

KT11

Ventilation Louvre

85

75

KT12

Ventilation Louvre

85

75

KT13

Ventilation Louvre

80

70

KT14

Ventilation Louvre

80

70

KT15

Ventilation Louvre

80

70

KT16

Ventilation Louvre

81

72

KT17

Ventilation Louvre

81

72

KT18

Ventilation Louvre

80

71

KT19

Ventilation Louvre

80

71

KT20

Ventilation Louvre

80

70

KT21

Ventilation Louvre

80

68

KT22

Ventilation Louvre

80

68

KT23

Ventilation Louvre

80

68

KT24

Ventilation Louvre

80

68

KT25

Ventilation Louvre

80

68

KT26

Ventilation Louvre

80

70

KT27

Ventilation Louvre

85

75

KT28

Ventilation Louvre

85

76

KT29

Ventilation Louvre

85

76

KT30

Ventilation Louvre

85

76

KT31

Ventilation Louvre

85

75

KT32

Ventilation Louvre

85

75

KT33

Ventilation Louvre

80

72

KT34

Ventilation Louvre

80

72

KT35

Ventilation Louvre

80

72

KT36

Ventilation Louvre

80

72

KT37

Ventilation Louvre

80

72

KT38

Ventilation Louvre

80

72

KT39

Ventilation Louvre

80

71

KT40

Ventilation Louvre

80

71

KT41

Ventilation Louvre

80

69

KT42

Ventilation Louvre

80

69

KT43

Ventilation Louvre

80

69

KT44

Ventilation Louvre

80

68

KT45

Ventilation Louvre

80

68

KT46

Ventilation Louvre

80

68

KT47

Ventilation Louvre

80

68

KT48

Ventilation Louvre

80

74

KT49

Ventilation Louvre

85

75

KT50

Ventilation Louvre

85

75

KT51

Ventilation Louvre

85

75

KT52

Ventilation Louvre

85

75

KT53

Ventilation Louvre

80

70

KT54

Ventilation Louvre

83

73

KT55

Ventilation Louvre

85

75

KT56

Ventilation Louvre

85

75

KT57

Ventilation Louvre

85

75

KT58

Ventilation Louvre

85

75

KT59

Ventilation Louvre

85

75

KT60

Ventilation Louvre

81

71

KT61

Ventilation Louvre

81

71

KT62

Ventilation Louvre

81

71

KT63

Ventilation Louvre

80

70

KT64

Ventilation Louvre

80

70

KT65

Ventilation Louvre

80

70

KT66

Ventilation Louvre

80

70

KT67

Ventilation Louvre

80

70

KT68

Ventilation Louvre

82

72

KT69

Ventilation Louvre

81

71

KT70

Ventilation Louvre

81

71

KT71

Ventilation Louvre

81

70

KT72

Ventilation Louvre

81

70

KT73

Ventilation Louvre

81

71

KT74

Ventilation Louvre

81

71

Shui Mei Road Ancillary Building

SMA-1

Ventilation Louvre

68

60

SMA-1a

Ventilation Louvre

68

64

SMA-2

Ventilation Louvre

67

65

SMA-3

Ventilation Louvre at Tx Room

72

72

SMA-4

Ventilation Louvre at Tx Room

72

72

SMA-5

Ventilation Louvre at Tx Room

68

68

SMA-6

Ventilation Louvre at Tx Room

68

68

SMA-7

Ventilation Louvre at Tx Room

72

72

SMA-8

Ventilation Louvre at Tx Room

72

72

SMA-9

Ventilation Louvre at Tx Room

72

72

SMA-10

Ventilation Louvre at Tx Room

72

72

SMA-10a

Ventilation Louvre

79

79

SMA-11

Ventilation Louvre

79

79

SMA-11a

Ventilation Louvre

79

79

SMA-11b

Ventilation Louvre

79

79

SMA-11c

Ventilation Louvre

79

79

SMA-11d

Ventilation Louvre

70

62

SMA-11e

Ventilation Louvre

70

62

SMA-11f

Ventilation Louvre

70

65

SMA-11g

Ventilation Louvre

70

66

SMA-12

Ventilation Louvre

71

70

SMA-13

AC Outdoor Unit

72

70

Pok Wai Ancillary Building

PWA-1

Ventilation Louvre

89

79

PWA-2

Ventilation Louvre

89

79

PWA-3

Ventilation Louvre

89

79

PWA-4

Ventilation Louvre at Tx Room

82

72

PWA-5

Ventilation Louvre at Tx Room

82

72

PWA-6

Ventilation Louvre at Tx Room

82

72

PWA-7

Ventilation Louvre at Tx Room

82

72

PWA-8

Ventilation Louvre at Tx Room

82

72

PWA-9

Ventilation Louvre at Tx Room

82

72

PWA-10

Ventilation Louvre at Tx Room

82

72

PWA-11

Ventilation Louvre at Tx Room

82

72

PWA-11a

Ventilation Louvre

85

75

PWA-12

Ventilation Louvre

75

65

PWA-13

Ventilation Louvre

84

74

PWA-14

Ventilation Louvre

81

71

PWA-15

Ventilation Louvre

81

71

PWA-16

Ventilation Louvre

71

61

PWA-16a

Ventilation Louvre

70

60

PWA-16b

Ventilation Louvre

80

70

PWA-17

AC Outdoor Unit

85

75

Long Ha Tsuen Ancillary Building

LHA-1

Ventilation Louvre at Tx Room

87

82

LHA-2

Ventilation Louvre at Tx Room

87

82

LHA-3

Ventilation Louvre at Tx Room

87

82

LHA-4

Ventilation Louvre at Tx Room

87

82

LHA-4a

Ventilation Louvre

82

77

LHA-4b

Ventilation Louvre

82

77

LHA-5

Ventilation Louvre

82

77

LHA-5a

Ventilation Louvre

82

77

LHA-5b

Ventilation Louvre

82

77

LHA-6

Ventilation Louvre

82

77

LHA-6a

Ventilation Louvre

82

77

LHA-6b

Ventilation Louvre

82

77

LHA-6c

Ventilation Louvre

82

77

LHA-7

AC Outdoor Unit

91

86

San Tin Ancillary Building

SNA-1

Ventilation Louvre

88

80

SNA-1a

Ventilation Louvre

88

80

SNA-2

Ventilation Louvre

88

80

SNA-3

Ventilation Louvre

88

80

SNA-4

Ventilation Louvre at Tx Room

82

74

SNA-5

Ventilation Louvre at Tx Room

82

74

SNA-6

Ventilation Louvre at Tx Room

82

74

SNA-7

Ventilation Louvre at Tx Room

82

74

SNA-8

Ventilation Louvre at Tx Room

82

74

SNA-9

Ventilation Louvre at Tx Room

82

74

SNA-10

Ventilation Louvre at Tx Room

82

74

SNA-11

Ventilation Louvre at Tx Room

82

74

SNA-11a

Ventilation Louvre

82

74

SNA-12

Ventilation Louvre

88

80

SNA-12a

Ventilation Louvre

83

75

SNA-12b

Ventilation Louvre

83

75

SNA-13

AC Outdoor Unit

94

86

SNA-13a

Ventilation Louvre

83

75

SNA-13b

Ventilation Louvre

82

74

SNA-13c

Ventilation Louvre

82

74

SNA-13d

Ventilation Louvre

82

74

SNA-14

Ventilation Louvre

82

74

Ka Lung Road Ancillary Building

KLA-1

Ventilation Louvre at Tx Room

96

88

KLA-2

Ventilation Louvre at Tx Room

96

88

KLA-3

Ventilation Louvre at Tx Room

96

88

KLA-4

Ventilation Louvre at Tx Room

96

88

KLA-4a

Ventilation Louvre

93

85

KLA-4b

Ventilation Louvre

93

85

KLA-4c

Ventilation Louvre

93

85

KLA-4d

Ventilation Louvre

93

85

KLA-4e

Ventilation Louvre

93

85

KLA-4f

Ventilation Louvre

93

85

KLA-4g

Ventilation Louvre

93

85

KLA-4h

Ventilation Louvre

93

85

KLA-4i

Ventilation Louvre

93

85

KLA-4j

Ventilation Louvre

96

88

KLA-4k

Ventilation Louvre

96

88

KLA-5

AC Outdoor Unit

97

88

Kwu Tung Road Ancillary Building

KTA-1

Ventilation Louvre

95

88

KTA-1a

Ventilation Louvre

93

86

KTA-1b

Ventilation Louvre

93

86

KTA-2

Ventilation Louvre at Tx Room

95

85

KTA-3

Ventilation Louvre at Tx Room

95

85

KTA-4

Ventilation Louvre

95

85

KTA-5

Ventilation Louvre at Tx Room

95

85

KTA-5a

Ventilation Louvre

95

88

KTA-6

Ventilation Louvre at Tx Room

95

85

KTA-7

Ventilation Louvre at Tx Room

95

85

KTA-7a

Ventilation Louvre

95

88

KTA-7b

Ventilation Louvre

95

88

KTA-8

Ventilation Louvre at Tx Room

95

85

KTA-9

Ventilation Louvre at Tx Room

95

85

KTA-9a

Ventilation Louvre

95

88

KTA-9b

Ventilation Louvre

95

88

KTA-10

Ventilation Louvre

95

88

KTA-10a

Ventilation Louvre

95

88

KTA-10b

Ventilation Louvre

95

88

KTA-11

AC Outdoor Unit

97

90

Pak Shek Au Ancillary Building

PAA-1

Ventilation Louvre at Tx Room

87

81

PAA-2

Ventilation Louvre at Tx Room

87

81

PAA-3

Ventilation Louvre at Tx Room

87

81

PAA-4

Ventilation Louvre at Tx Room

87

81

PAA-4a

Ventilation Louvre

87

81

PAA-4b

Ventilation Louvre

87

81

PAA-4c

Ventilation Louvre

87

81

PAA-4d

Ventilation Louvre

87

81

PAA-4e

Ventilation Louvre

87

81

PAA-4f

Ventilation Louvre

87

81

PAA-4g

Ventilation Louvre

87

81

PAA-4h

Ventilation Louvre

87

81

PAA-4i

Ventilation Louvre

89

83

PAA-5

AC Outdoor Unit

91

85

PAA-6

Ventilation Louvre at Tx Room

93

87

PAA-7

Ventilation Louvre

87

81

PAA-8

Ventilation Louvre

87

81

PAA-9

Ventilation Louvre

87

81

PAA-10

Ventilation Louvre

87

81

PAA-11

Ventilation Louvre

87

81

PAA-12

Ventilation Louvre

87

81

PAA-12a

Ventilation Louvre

87

81

PAA-13

Ventilation Louvre at Tx Room

93

87

PAA-14

Ventilation Louvre

87

81

PAA-15

Ventilation Louvre

87

81

PAA-16

Ventilation Louvre

87

81

PAA-17

Ventilation Louvre

87

81

PAA-18

Ventilation Louvre

87

81

PAA-19

Ventilation Louvre

87

81

PAA-20

Ventilation Louvre

93

87

PAA-21

Ventilation Louvre

93

87

PAA-22

Ventilation Louvre

87

81

PAA-23

Ventilation Louvre

87

81

PAA-24

Ventilation Louvre

93

87

PAA-25

Ventilation Louvre

93

87

PAA-26

Ventilation Louvre

87

81

PAA-27

Ventilation Louvre

93

87

PAA-28

Ventilation Louvre

93

87

PAA-29

Ventilation Louvre

87

81

PAA-30

AC Outdoor Unit

87

81

 

Mitigation Measure

4.6.10       Based on the preliminary assessment result, the predicted maximum allowable SWLs are in the range of 55 –97dB(A).  Relatively low SWLs were predicted for the fixed plant sources at the KSR(NOL) Station, NTM Station, NTD and SMA, due to the conservative assumptions on the NAP locations at the boundaries of the planned development.  It is recommended to update the maximum allowable SWLs in later stage of the Project when the detailed design of the fixed plant sources and the building layouts of the planned developments are available.

4.6.11       Nevertheless, the predicted maximum allowable SWLs are considered achievable by selection of proper plant and adoption of acoustic treatment based on the past experience of other similar railway projects.  Reference was made to the Fixed Plant Noise Audit Report for South Island Line (East)[1] for the typical SWLs of fixed plant sources.  For example, the measured SWLs of ventilation louvers at Ocean Park Station and its electrical room were in the range of 62 - 86 dB(A) and the measured SWLs of cooling tower at Lee Wing Street Plant Building (LWB) are in the range of 86 – 89 dB(A) without installation of mitigation measures acoustic louvers and noise enclosure.  For ventilation louvers, noise mitigation treatments could be provided in the form of acoustic louvers which are available in the market, fitted to the ventilation opening to ensure the compliance of noise levels at NSRs with the stipulated noise criteria.  Typical insertion losses of acoustic louvers are in the range of 5 dB(A) to 10 dB(A).  For cooling towers, a full noise enclosure with appropriate sound insulation material should be provided to alleviate the noise impact.  According to the Appendix IV of “Good Practices on Ventilation System Noise Control” published by EPD, a complete enclosure and a silenced ventilation system could provide more than 20 dB(A) noise reduction.  The Contractors should properly design the noise mitigation measures, if required, according to the “Good Practices on Ventilation System Noise Control”.

4.6.12       Fixed Noise Sources Management Plan(s) (FNMP(s)) should be prepared before the issue of tender and before commencement of the installation of fixed plant, subject to the contract arrangement of the Project and agreement with EPD. The FNMP should contain the quantitative fixed noise sources impact assessment based on the best available information, accounting all design measures including noise mitigation measures. The FNMP(s) should be certified by Certified Noise Modelling Professional of HKIQEP or equivalent.  In addition, Fixed Noise Audit Report(s) (FNAR) should be prepared before commencement of operation of the Project to demonstrate the compliance of the fixed plant noise sources of the Project with the maximum allowable SWLs determined in this EIA Report, or otherwise approved by the EPD in compliance with the requirements in EIAO-TM having due regard to the characteristics of tonality, impulsiveness and intermittency.

Cumulative Fixed Plant Noise Impact

4.6.13       The fixed plants at PHD, existing KSR(TML) Station, ventilation shafts and planned KTU(EAL) Station on LMCSL were identified as fixed plant noise sources that may pose cumulative fixed plant noise impact to the NSRs in the vicinity of these fixed plants.  The cumulative fixed plant noise impacts were evaluated and presented in Appendix 4.11.  Adverse cumulative fixed plant noise impact is not expected at the representative NAPs, with details discussed below.

PHD

4.6.14       According to the PHD ERR 2012, there is an existing train wash plant which is located near the Future School site in Kam Tin South Development (Site 1).  Cumulative fixed plant noise impact assessment was conducted based on the information of the fixed plant sources presented in the ERR.  In addition, other existing fixed plants that are located at more than 300m from the representative NAPs were excluded in the assessment.  The prediction results indicated that the cumulative fixed plant noise impacts at the representative NAPs comply with the relevant ANL.

KSR(TML) Station

4.6.15       Fixed noise sources at the existing KSR(TML) Station were identified and SWLs of the fixed noise sources were also determined by noise measurements. The SWL measurement results are presented in Appendix 4.12.  Cumulative fixed plant noise impacts were evaluated quantitatively, and the result indicated that the cumulative fixed plant noise impacts at the representative NAPs comply with the relevant ANL.

Ventilation Shafts on LMCSL near KTA and PAA

4.6.16       The KTA and PAA would be located near the ventilation shafts on LMCSL in Kwu Tung area, hence, cumulative fixed plant noise impact would be expected.  For the fixed plant noise from the existing ventilation shafts on LMCSL near KTA and PAA, reference was made to Table 7.16 of the approved EIA report for Sheung Shui to Lok Ma Chau Spur Line (LMCSL) (Register No.: AEIAR-052/2002) and Appendix 4.25 of the approved EIA report for NENT NDA (Register No.: AEIAR-175/2013) respectively.  Cumulative fixed plant noise impacts were evaluated quantitatively, and the results indicated that the cumulative fixed plant noise impacts at the representative NAPs comply with ANL.

KTU(EAL) Station and Existing EAPs on LMCSL

4.6.17       The KTU(NOL) Station would be located at the north of KTU Station (EAL) and existing EAPs on LMCSL.  There are two existing EAPs, namely EAP No. 3 and EAP No. 4, located at the east and the west of future KTU(EAL) Station respectively.  Based on the proposed construction arrangement, EAP No. 4 would be demolished before the operation of the Project.  Hence, no cumulative fixed plant noise impact would be expected from EAP No. 4.  For the fixed plant noise generated from the existing EAP No. 3, reference was made to the Appendix 4.25 of the approved EIA report for NENT NDA.   For the fixed plant noise generated from the future KTU(EAL) Station, reference was made to the LMCSL ERR 2021[2].   Cumulative fixed plant noise impact was evaluated quantitatively, and the results, which presented in Appendix 4.11, indicated that the cumulative fixed plant noise impacts at the representative NAPs comply with ANL.

4.7              Operational Phase - Rail Noise Impact Assessment

Source of Impact

4.7.1         The NOL alignment would be located underground except a short trough section at the tunnel portal connecting to NTD.  The trough section has been minimised as far as practicable to satisfy fire services requirement and tracks with turnouts at this trough section would also be covered by noise canopies and vertical louvre walls with natural ventilation feature. The locations of trough section, noise canopies and vertical louvre walls are shown in Appendix 4.14. 8-car type SP1900 or other train type with equivalent or better noise performance will be used in NOL and would shunt from tunnel portal to NTD at a speed of about 20kph and at a train frequency of 5 trains per 30mins per direction during both daytime and night-time periods. The nearest existing NSR (i.e. Village House near Wang Ping Shan South Road) would be located at about 80m from the trough section covered by noise canopies.  With provision of noise canopies, there would be no direct line of sight from any NSRs to the airborne railway noise sources at the trough section and in NTD.  Furthermore, the NTD has been designed with concrete deck and vertical walls, where the internal surfaces would be lined with noise absorption materials with due consideration of engineering and operation constraints, to avoid noise nuisance to the NSRs nearby from train operation within NTD.  Considering both the train speed and train frequency are relatively low and there would be no direct line of sight from any NSRs to the airborne railway noise sources, therefore, adverse airborne railway noise impact due to the operation of the Project is not anticipated.

4.7.2         Ancillary buildings would be constructed aboveground along the tunnel for emergency access and ventilation purpose. The ancillary buildings would be concrete structures and fitted with ventilation equipment, metal ducting and louvers at the ventilation openings. It is anticipated that there would be no direct air-borne noise transmission paths from the tunnel to outdoor via the ancillary buildings.  Any noise from louvres of the ancillary facilities, considered as noise from fixed plant sources, would be controlled under NCO through adoption of appropriate measures such as absorptive lining and splitter attenuator.  High performance attenuators could be installed in the ventilation air duct system to control ventilation fan noise and also substantially reduce train noise emission, if any, to the outside. 

4.8              Environmental Monitoring and Audit Requirement

Construction Noise

4.8.1         Noise monitoring is recommended as part of the environmental monitoring and audit (EM&A) programme for the construction phase of the Project to check the compliance of the daytime construction noise criteria.  The implementation of the recommended mitigation measures for daytime construction activities should also be audited as part of the EM&A programme.  Details of the EM&A requirements are provided in the EM&A Manual.

Fixed Plant Noise

4.8.2         Before commencement of the operation of fixed plant sources, FNAR(s) should be prepared, while verification of the noise performance of the fixed plants should be conducted during the testing and commissioning stage.  Details of the EM&A programme are provided in a stand-alone EM&A Manual.

Rail Noise

4.8.3         Compliance check on rail noise against NCO criteria should be conducted before the commissioning of the Project.  Details of the EM&A programme are provided in a stand-alone EM&A Manual.

4.9              Conclusion

Construction Phase

4.9.1         The construction noise impacts of the Project during normal daytime working hours were predicted according to the plant inventory and construction programme developed by the Project Engineer.  All practicable noise mitigation measures, including the use of QPME, deployment of construction noise barriers and enclosures, adoption of quieter construction methods (including use of TBM, large diameter bored piling, MiC, DfMA, silent piling, rubber head poker vibrator), as well as sequencing of construction activities at critical works areas, have been exhausted to minimise the potential construction noise impacts. The assessment results indicated that the mitigated noise levels at all NSRs would comply with the construction noise criteria as set out in EIAO-TM, except that exceedance is anticipated at the planned school site at Kam Tin South Housing Development during examination period. The Contractor should liaise with the representative of the concerned school and/or the Examination Authority to ascertain the exact dates and times of all examination periods during the construction period and should avoid conducting noisy activities during the examination periods if the school is relied on opened windows for ventilation.  With the avoidance of particular noisy construction activities during the examination periods, the mitigated construction noise impact at the concerned school would comply with the stipulated noise criterion.

4.9.2         It is recommended that CNMP(s) should be prepared based on the best available information before the issue of tender and the commencement of construction works, subject to the contract arrangement of the Project and agreement with EPD.  The plan should include a quantitative construction noise impact assessment with details on the construction method, plant inventory and recommended noise mitigation measures for the future Contractors’ further update on CNMP before commencement of construction works and implementation in order to minimise the construction noise impact and comply with the EIAO-TM. In addition, further review on the cumulative construction noise impact should be conducted as necessary in the later CNMP when the information of the concurrent project is available. The CNMP should be certified by Certified Noise Modelling Professional of HKIQEP or equivalent.

Operational Noise

4.9.3         With the proper selection of fixed plant and adoption of acoustic treatment to achieve the recommended maximum allowable SWLs for the proposed fixed plant, the fixed plant noise impact at the NSRs located in the vicinity of fixed plant sources would comply with the criteria set out in EIAO-TM.  If there is any change in engineering design information during detailed design stage or fitting-out stage, the fixed source noise design should be reviewed by Engineer/Contractor ensuring that the NCO and EIAO-TM criteria at NSRs can be met in the future.  FNMP should be prepared before the issue of tender and before commencement of the installation of fixed plant, subject to the contract arrangement of the Project and agreement with EPD. The FNMP should be certified by Certified Noise Modelling Professional of HKIQEP or equivalent. Fixed Noise Audit Report(s) (FNAR) should also be prepared before commencement of operation of the Project to demonstrate the compliance of the fixed plant noise sources of the Project.

4.9.4         The NOL alignment would be located underground except a short trough section at the tunnel portal connecting to NTD.  The trough section has been minimised and would be covered with noise canopies. Considering the train speed and train frequency are relatively low at the trough section and there would be no direct line of sight from any NSRs to the airborne railway noise sources at the trough section and NTD, adverse airborne railway noise impact due to the operation of the Project is therefore not anticipated.



[1] Fixed Plant Noise Audit Report for South Island Line (East), November 2016 (https://www.epd.gov.hk/eia/register/english/permit/vep5082016/documents/fpnar/pdf/fpnar.pdf)

[2] Environmental Review Report for supporting the Variation of Environmental Permit (VEP) of Sheung Shui to Lok Ma Chau Spur Line 2021 (Application No.: VEP-604/2021)