|
|
|
|||||
|
|
|
|||||
|
|
|
|||||
|
|
AUES Project No.: TCS/00684/13 |
|
|
|
||
|
|
|
|
|
|
||
|
|
WSD Contract No. 1/WSD/13 - Improvement of
Fresh Water Supply to Cheung Chau |
|
|
|
||
|
|
|
|
|
|
||
|
|
Monthly
Environmental Monitoring and Audit (EM&A) Report (No.40) ¡V July 2017 |
|
|
|
||
|
|
Prepared For China Road- China Pipeline Joint Venture |
|
|
|
||
|
|
|
|
|
|
||
Quality Index |
|||
Date |
Reference No. |
Prepared By |
Approved By |
11 August 2017 |
TCS00684/13/600/emar201707 |
|
|
Martin Li Assistant Environmental
Consultant |
T.W. Tam Environmental
Team Leader |
Version |
Date |
Description |
1 |
9 August 2017 |
First Submission |
2 |
11 August 2017 |
Amended against IEC¡¦s comments |
|
|
|
executive summary
ES.01 Water Supplies Department
(hereafter referred as ¡§WSD¡¨) is the Project Proponent and the Permit
Holder of Improvement
of Fresh Water Supply to Cheung Chau (hereinafter referred as ¡§the
Project¡¨), which is a Designated Project to be implemented under Environmental
Permit number EP-392/2010/B (hereinafter referred as ¡§the EP-392/2010/B¡¨ or ¡§the EP¡¨). The Works is predicted to take about 36 months.
ES.02 In the Project, China Road - China Pipeline
Joint Venture (hereinafter ¡§CRCPJV¡¨) is the Main Contractor, SMEC Asia Limited
as an Independent Environmental Checker (IEC), Black & Veatch Hong Kong
Limited is the representative engineer on site to manage the Project and Action-United Environmental
Services and Consulting (AUES) has been appointed as the independent
Environmental Team (ET) to implement the relevant EM&A programme.
ES.03 According
to the construction information provided by the Contractor, Section 1 of works
of the captioned project has been substantially completed and Certification of
Completion for Section 1 of the works was issued on 29 May 2017. As agreed by
the RE, IEC, Contractor and ET, the construction phase EM&A programme was terminated on 23 July 2017 and the 4-week post project marine
water quality monitoring was immediately commenced on 24 July 2017 as required
in Section 2.7.3 of the EM&A Manual. In this regards, an associated letter ref. TCS005684/13/300/L0343
date 21 July 2017 has been issued to EPD for approval and no adverse comment
was received.
ES.04 This is the last (40th) monthly
Environmental Monitoring and Audit Report for July 2017 covering the period from
1st
to 31st July 2017 (the Reporting Month).
Environmental
Monitoring and Audit Activities
ES.05 Environmental monitoring activities under
the EM&A program in this Reporting Month are summarized in the following
table.
Table ES-1 Environmental
Monitoring Activities in Reporting Month
Issues |
Environmental Monitoring Parameters /
Inspection |
Occasions |
Construction
Noise |
Leq(30min)
Daytime |
3 |
Water Quality |
Marine
Water Sampling |
9 |
Total
Residual Chlorine of In Situ Measurement |
NA |
|
Inspection / Audit |
ET
Regular Environmental Site Inspection |
3 |
IEC
Monthly Environmental Site Audit |
1 |
Breach of Action and Limit
(A/L) Levels
ES.06 No exceedance of construction noise and
marine water monitoring were recorded in this Reporting Month. The statistics
of environmental exceedance, NOE issued and investigation of exceedance
are summarized in the following table.
Table ES-2 Summary
NOE issued and investigation of exceedance in Reporting Month
Environmental Issues |
Monitoring Parameters |
Action Level |
Limit
Level |
Event & Action |
||
NOE Issued |
Investigation |
Corrective Actions |
||||
Construction Noise |
Leq(30min) Daytime |
0 |
0 |
0 |
-- |
-- |
Water Quality |
DO |
0 |
0 |
0 |
-- |
-- |
Turbidity |
0 |
0 |
0 |
-- |
-- |
|
SS |
0 |
0 |
0 |
-- |
-- |
Note: NOE
¡V Notification of Exceedance
ES.07 No environmental complaint was
recorded or received in this Reporting Month.
Notification of
Summons and Successful Prosecutions
ES.08 No environmental summons or
successful prosecutions were recorded in this Reporting Month.
ES.09 No reporting
changes were made in this Reporting Month.
Site Inspection by External Parties
ES.10 No
joint site inspection
with AFCD and EPD was carried out in the Reporting Period
Table of Contents
1. Introduction 1
Project Background 1
Report Structure 2
2. Project Organization and Construction progress 3
Project Organization and Management Structure 3
Construction Progress 3
Summary of Environmental Submissions 3
3. Summary of Monitoring Requirements 4
General 4
Monitoring Parameters 4
Monitoring Location 4
Monitoring Frequency and Period 5
Monitoring Equipment 5
Monitoring Methodology 7
Equipment Calibration 8
Meteorological Information 8
Data Management and Data QA/QC Control 8
Determination of Action/Limit (A/L) Levels 8
4. Impact monitoring Results 10
Results of Water Quality Monitoring 10
Results of In Situ Total Residual Chlorine
Measurement 12
Results of Construction Noise Monitoring 13
5. Waste Management 14
Records of Waste Quantities 14
6. Site Inspection 15
7. Environmental Complaint and Non-Compliance 16
Environmental Complaint, Summons and Prosecution 16
8. Implementation Status of Mitigation Measures 17
General Requirements 17
9. Conclusions 18
Conclusions 18
List of TABLES
Table 2-1 Construction
activities and potential environmental impacts in Reporting Month
Table 2-2 Status
of Environmental Licenses and Permits
Table 3-1 Summary
of the monitoring parameters of EM&A Requirements
Table 3-2 Location
of Marine Water Quality Monitoring Station
Table 3-3 Location
of Construction Noise Monitoring Station
Table 3-4 Monitoring
Equipment Used in EM&A Program
Table 3-5 Action
and Limit Levels for Water Quality
Table 3-6 Action
and Limit Levels for Construction Noise
Table 4-1 Results
Summary of Depth Average (Surface & Middle Layer) of DO (mg/L)
Table 4-2 Results
Summary of Bottom Depth of DO (mg/L)
Table 4-3 Results
Summary of Depth Average of Turbidity (NTU)
Table 4-4 Results
Summary of Depth Average of Suspended Solids (mg/L)
Table 4-5 Summary
of Water Quality Exceedance
Table 4-6 Summary
of Construction Noise Monitoring Results ¡V N1
Table 5-1 Summary
of Quantities of Inert C&D Materials
Table 5-2 Summary
of Quantities of C&D Wastes
Table 6-1 Site
Observations
Table 7-1 Statistical
Summary of Environmental Complaints
Table 7-2 Statistical
Summary of Environmental Summons
Table 7-3 Statistical
Summary of Environmental Prosecution
Table 8-1 Environmental
Mitigation Measures
List of Appendices
Appendix A Project
Site Layout Plan
Appendix B Organization
Structure and Contact Details of Relevant Parties
Appendix C Master
and Three Months Rolling Construction Programs
Appendix D Monitoring
Locations Designated in the EM&A Manual
Appendix E Monitoring
Equipment Calibrated Certificates and Laboratory Certificates
Appendix F Event
and Action Plan
Appendix G Impact
Monitoring Schedule
Appendix H Database
of Monitoring Results
Appendix I Graphical
Plots of Impact Monitoring
Appendix J Meteorological
Data
Appendix K Monthly
Summary Waste Flow Table
Appendix L Implementation
Schedule for Environmental Mitigation Measures (ISEMM)
1.1
Water Supplies Department (hereafter referred as ¡§WSD¡¨) is the
Project Proponent and the Permit Holder of Improvement of Fresh Water Supply to Cheung
Chau (hereinafter referred as ¡§the Project¡¨),
which is a Designated Project to be implemented under Environmental Permit
number EP-392/2010/B (hereinafter referred as ¡§the EP-392/2010/B¡¨ or ¡§the EP¡¨).
1.2
The scope of the works comprises primarily the laying of a new
submarine fresh water main across the Adamasta
Channel from Lantau Island to Cheung Chau by horizontal directional drilling
method to enhance the reliability of fresh water supply to Cheung Chau. The Works is commenced on 28 March 2014
and predicted to be undertaken about 24 months. The layout plan of project is shown in Appendix
A.
1.3
Action-United
Environmental Services and Consulting (AUES) has been appointed as the
independent environmental team (ET) to implement the relevant EM&A programme of Water Supplies
Department (WSD) Contract No. 1/WSD/13 ¡V Improvement of Fresh Water Supply to Cheung Chau. In the Project, China Road - China Pipeline
Joint Venture
(hereinafter ¡§CRCPJV¡¨) is a
main-contractor, SMEC Asia Limited as an Independent Environmental Checker (IEC), and Black
& Veatch Hong Kong Limited is the representative engineer on site to manage
the Project.
1.4
According
to the Particular Specification (PS) Section 25 and the EP-392/2010/B, overall scope of environmental monitoring including construction
noise and water quality, and site environmental audit should be undertaken in
accordance with the provided Environmental Monitoring and Audit Manual by an
independent Environmental Team (ET).
1.5
The
baseline monitoring program was carried out during the period between 4 January and 31
January 2014 at the
designated monitoring locations by the ET according to the EM&A
Manual. The ¡§Baseline Monitoring
Report (R0014 Version 3)¡¨ had submitted to EPD before commencement of major
construction works and approved by the IEC on 21 February 2014. Further to CRCPJV¡¦s instructions, the EM&A program was commenced on 1 April 2014
and
the monitoring schedule had
been issued to relevant parties on 28 March 2014.
1.6
According
to the construction information provided by the Contractor, Section 1 of works
of the captioned project has been substantially completed and Certification of
Completion for Section 1 of the works was issued on 29 May 2017. As agreed by
the RE, IEC, Contractor and ET, the construction phase EM&A programme was terminated on 23 July 2017 and the 4-week
post project marine water quality monitoring was immediately commenced on
24 July 2017 as required in Section 2.7.3 of the EM&A Manual. In this regards, an associated letter ref.
TCS005684/13/300/L0343 date 21 July 2017 has been issued to EPD for approval
and no adverse comment was received. The
result of 4-week post project marine water
quality monitoring will be provided separately and is not included in this
EM&A report.
1.7
This
is the last (40th)
monthly Environmental Monitoring and Audit Report for July 2017 covering the period from
1st to 31st July 2017 (the
Reporting Month).
1.8
The
Monthly Environmental Monitoring and Audit (EM&A) Report is structured into
the following sections:-
Section 1 Introduction
Section 2 Project
Organization and Construction Progress
Section
3 Summary of Monitoring
Requirements
Section 4 Impact
Monitoring Results
Section 5 Waste Management
Section 6 Site
Inspections
Section 7 Environmental
Complaints and Non-Compliance
Section 8 Implementation
Statues of Mitigation Measures
Section 9 Conclusions
2.1
Organization
structure and contact details of relevant parties with respect to on-site
environmental management are shown in Appendix B.
2.2
The layout
plans with location of construction activities carried out are enclosed in Appendix A, the master and three month rolling
construction programs are enclosed in Appendix C,
and the major construction activities undertaken in this Reporting Month and
their potential environmental impacts are listed below:-
Table 2-1 Construction
activities and potential environmental impacts in Reporting Month
Construction Activities |
Potential Environmental Impact(s) |
Environmental protection/mitigation
measures |
No Construction
Work |
NA |
NA |
2.3
Summary of
the relevant permits, licences, and/or notifications
on environmental protection for this Project in this Reporting Month is
presented in Table 2-2.
Table 2-2 Status of Environmental Licenses and Permits
Item |
Description |
License/Permit Status |
1 |
Air pollution
Control (Construction Dust) |
Notified EPD on 28/10/2013 Ref. no. 366253 |
2 |
Chemical waste
Producer Registration |
Application
date: 20/12/2013 Date approved:
30/01/2014 WPN:
8334-920-C3839-01 |
3 |
Water Pollution
Control Ordinance (Discharge License) |
Application
date: 03/01/2014 License no.
WT00018191-2014 Valid to
28/02/2019 |
4 |
Billing Account
for Disposal of Construction Waste |
Application no.
:RS01134 Date approved:
1/11/2013 Account Number: 7018602 |
2.4
Baseline
Monitoring Report (TCS00684/13/600/R0014Ver.3) for the Project was issued by
the ETL and verified by the IEC on 24 March 2014. The report was also submitted to the EPD
for endorsement.
2.5
According
to Clause 3.9 EP-392/2010/B stipulation, the detailed proposal of the HDD technique and the
management of the drilling fluid for construction of the Project were submitted
on 9 July 2014.
2.6
According
to Clause 4.3 EP-392/2010/B stipulation, the detailed proposal of the cleaning
and sterilization process of the Project were submitted on 19 October
2016.
3.1
The Environmental Monitoring and Audit requirements are set out in
the Approved EM&A manual.
Environmental aspects such as the construction noise and marine water
quality were identified as the key issues during the construction phase of the
Project. The detailed requirements
are presented in the sub-sections below.
3.2
The EM&A baseline and impact monitoring program covers the
following environmental issues:
• Construction noise; and
• Marine Water quality
3.3
A summary of the monitoring parameters is presented in Table
3-1:
Table 3-1 Summary
of the monitoring parameters of EM&A Requirements
Environmental Issue |
Parameters |
Marine Water Quality |
In-situ Measurements •
Dissolved Oxygen Concentration (mg/L); •
Dissolved Oxygen Saturation (% ); •
Turbidity (NTU); •
pH value; •
Salinity (ppt); •
Water depth (m); •
Temperature (ºC); and •
# Total residual chlorine (TRC) (mg/L) |
Laboratory
Analysis •
Suspended Solids (mg/L) |
|
Noise |
•
Leq(30min) during normal working hours;
and •
Leq(5min) during Restricted Hours. |
Water
Quality
3.4
Two control stations (W8 and W9) and seven impact stations (W1-W7)
were recommended in the EM&A Manual Section 2.5. Detailed and co-ordinance of water
quality monitoring stations is described in Table 3-2 and the
graphical is shown in Appendix D.
Table 3-2 Location
of Marine Water Quality Monitoring Station
Station |
Description |
Co-ordinance |
|
Easting |
Northing |
||
W1 |
Impact Station ¡V Marine waters
near the proposed launching site at Cheung Chau |
820 704 |
808 688 |
W2 |
Impact Station ¡V Marine waters
near the proposed launching site at Cheung Chau |
820 656 |
808 631 |
W3 |
Impact Station ¡V Marine waters
along the proposed water main alignment |
820 445 |
809 036 |
W4 |
Impact Station ¡V Marine waters
along the proposed water main alignment |
820 072 |
809 297 |
W5 |
Impact Station ¡V Marine waters near the proposed
reception site at Lantau |
819 875 |
809 700 |
W6 |
Impact Station ¡V
Marine waters near the Cheung Sha Wan Fish Culture Zone |
819 174 |
810 917 |
W7 |
Impact Station ¡V Marine
waters between the works and the Cheung Sha Wan Fish Culture Zone |
820 055 |
810 523 |
W8 |
Control station ¡V
Marine waters of Adamasta Channel |
821 328 |
810 240 |
W9 |
Control station ¡V
Marine waters of Adamasta Channel |
819 045 |
807 953 |
Construction Noise
3.5
According to EM&A Manual Section 6.4, only one noise sensitive
receiver (NSR) is designated for the construction noise monitoring. The detailed construction noise
monitoring station to under the Project is described in Table 3-3 and graphical
is shown in Appendix D.
Table 3-3 Location
of Construction Noise Monitoring Station
Noise Monitoring Station |
NSR ID |
Location |
N1 |
NSR2 |
Village house at No. 1A Tai Kwan Wan San Tsuen |
3.6
The requirements of impact monitoring
are stipulated in Sections 2.6 and 2.7 of the EM&A Manual and
listed as follows.
Parameters : One set of Leq(30min) as 6 consecutive Leq(5min) between 0700-1900 hours on normal weekdays
Frequency : Once every week
Duration : Throughout the construction
period
Water Quality (Marine) Monitoring
Parameters |
: |
In-situ measurements
including water depth, temperature, DO, pH, turbidity and salinity; and
Suspended Solids is analyzed by HOKLAS-accredited laboratory. |
Frequency |
: |
Three days a week, at mid ebb
and mid flood tides. The interval between 2 sets of monitoring
will be more than 36 hours. |
Sampling Depth |
: |
(i.)
Three depths: 1m below water surface, 1m
above sea bottom and at mid-depth when the water depth exceeds 6m. (ii.)
If the water depth is between 3m and 6m,
two depths: 1m below water surface and 1m above sea bottom. (iii.) If the
water depth is less than 3m, 1 sample at mid-depth is taken |
Duration |
: |
Throughout the
construction period |
Water Quality Monitoring
i.
Dissolved Oxygen and
Temperature Measuring Equipment ¡V
The
instrument should be a portable and weatherproof dissolved oxygen (DO)
measuring instrument complete with cable and sensor, and use a DC power source.
The equipment should be capable of measuring as included a DO level in the
range of 0 ¡V 20 mgL-1 and 0 ¡V 200% saturation; and a temperature of 0 ¡V 45 degree Celsius.
ii.
pH Meter ¡V The instrument
shall consist of a potentiometer, a glass electrode, a reference electrode and
a temperature-compensating device.
It shall be readable to 0.1 pH in arrange of 0 to 14.
iii.
Turbidity (NTU) Measuring
Equipment ¡V The instrument should
be a portable and weatherproof turbidity measuring instrument using a DC power
source. It should have a photoelectric sensor capable of measuring turbidity
between 0 - 1000 NTU.
iv.
Water Sampling Equipment ¡V A water sampler should comprise a transparent PVC
cylinder, with a capacity of not less than 2 litres,
which can be effectively sealed with latex cups at both ends. The sampler
should have a positive latching system to keep it open and prevent premature
closure until released by a messenger when the sampler is at the selected water
depth.
v.
Water Depth Detector ¡V A portable, battery-operated echo sounder should
be used for the determination of water depth at each designated monitoring
station. This unit can either be hand held or affixed to the bottom of the work
boat.
vi.
Salinity Measuring Equipment ¡V A portable salinometer
capable of measuring salinity in the range of 0 - 40 parts per thousand (ppt) should be provided for measuring salinity of the water
at each monitoring location.
vii. Sample Containers and Storage ¡V Water samples for SS should be stored in high density
polythene bottles with no preservative added, packed in ice (cooled to 4¢XC
without being frozen).
viii. Monitoring Position Equipment - A hand-held or boat-fixed type digital Differential
Global Positioning System (DGPS) with way point bearing indication and Radio
Technical Commission for maritime (RTCM) Type 16 error message ¡¥screen pop-up¡¦
facilities (for real-time auto-display of error messages and DGPS corrections
from the Hong Kong Hydrographic Office), or other equipment instrument of
similar accuracy, should be provided and used during marine water monitoring to
ensure the monitoring vessel is at the correct location before taking
measurements.
ix.
Suspended Solids Analysis ¡V Analysis of suspended solids shall be carried out
in a HOKLAS or other international accredited laboratory.
Noise Monitoring
3.7
Sound level meter in compliance with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications
shall be used for carrying out the noise monitoring. The sound level meter shall be checked
using an acoustic calibrator. The
wind speed shall be checked with a portable wind speed meter capable of measuring
the wind speed in ms-1.
3.8
The
monitoring equipment using for the EM&A program were proposed by the ET and
verified by the IEC prior to the commencement of the monitoring. Details of the equipment used for impact
monitoring are listed in Table 3-4 below.
Table 3-4 Monitoring
Equipment Used in EM&A Program
Model |
|
Construction Noise |
|
Integrating Sound
Level Meter |
B&K Type 2238 |
Calibrator |
Rion
NC - 74 |
Portable Wind Speed
Indicator |
Testo
Anemometer |
Water quality |
|
A Digital Global Positioning System |
GPS12 Garmin |
Water
Depth Detector |
Eagle Sonar |
Water
Sampler |
A
2-litre transparent PVC cylinder with latex cups at both ends |
YSI
Professional Plus Digital Sampling System Water Quality Meter |
|
pH
meter |
|
Salinometer |
|
Turbidimeter |
Hach 2100Q Portable Turbidimeter |
Sample
Container |
High
density polythene bottles (provided by laboratory) |
Storage
Container |
¡¥Willow¡¦
33-litter plastic cool box with Ice pad |
Suspended
Solids |
HOKLAS-accredited
laboratory (ALS Technichem (HK) Pty Ltd) |
Total residual chlorine |
HANNA HI96724C Free & Total Chlorine ISM |
Water Quality
3.9
Water
quality monitoring is conducted at the designated locations. The sampling
produce with the in-situ monitoring are presented as below:
Sampling
Procedures
3.10
A Digital Global Positioning System (GPS) is
used to identify the designated monitoring stations prior to water
sampling. A portable,
battery-operated echo sounder is used for the determination of water depth at
each station. At each station,
marine water sample is collected at three depths: 1m below water surface, 1m
above sea bottom and at mid-depth when the water depth exceeds 6m. Samples at 1m below water surface and 1m
above sea bottom are collected when the water depth is between 3m and 6m. Only 1 sample at mid-depth is taken when
the water depth is below 3m.
3.11
The marine water sampler is lowered into the water body at the
predetermined depth. The trigger
system of the sampler should been activated with a messenger. The opening ends of the sampler then is
closed accordingly and water sample is collected.
3.12
The sample container is rinsed with a portion of the water
sample. The water sample then is
transferred to the high-density polythene
bottles as provided by the laboratory, labeled with a unique sample
number and sealed with a screw cap.
3.13
Before commencement of the sampling, general information such as
the date and time of sampling, weather condition and tidal condition as well as
the personnel responsible for the monitoring are to be recorded on the
monitoring field data sheet.
3.14
A
¡¥Willow¡¦ 33-litter plastic cool box packed with ice is used to preserve the
collected water samples prior to arrival at the laboratory for chemical
determination. The water
temperature of the cool box is maintained at a temperature as close to 40C
as possible without being frozen.
Samples collected are delivered to the laboratory upon collection
In-situ
Measurement
Positioning of Monitoring Locations
3.15
A digital Global Positioning System (GPS) is used during marine
water monitoring to ensure the monitoring vessel is at the correct location
when taking measurement and samples.
Depth, Dissolved Oxygen (DO), Temperature, Turbidity,
Salinity and pH value
3.16
The YSI ProDSS Digital Sampling
System Water Quality Meter are
used for marine water in-situ measures, which automates the measurements
and data logging of depth, temperature, dissolved oxygen, dissolved oxygen
saturation, turbidity, pH and salinity simultaneously. Before
each round of monitoring, the dissolved oxygen probe is calibrated by the wet
bulb method and the turbidity and salinity probes checked with distilled water.
Total Residual
Chlorine
3.17
Total residual chlorine is measured
in-situ using approved test kit HANNA HI96724C Free & Total
Chlorine ISM at the effluent discharge point. When de-chlorinated
water is being discharged, Total Residual Chlorine measurement is
conducted continuous hourly.
Laboratory Analysis
3.18
All water samples are analyzed with Suspended Solids (SS) as
specified in the EM&A Manual by a local HOKLAS-accredited testing laboratory (ALS Technichem (HK) Pty Ltd HOKLAS registration no. 66). SS analysis is determined by the laboratory upon receipt
of the water samples using HOKLAS accredited analytical methods namely ALS
Method EA-025.
The HOKLAS accredited certificate of laboratory is provided in Appendix E.
Construction Noise
3.19
Noise
measurements were taken in terms of the A-weighted equivalent sound pressure
level (Leq) measured in decibels (dB(A)). Supplementary statistical results (L10
and L90) were also obtained for reference.
3.20
Sound
level meters listed in Table 3-4 are complied with the International Electrotechnical
Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type 1) specifications,
as recommended in Technical Memorandum (TM) issued under the Noise Control Ordinance (NCO).
3.21
During
the monitoring, all noise measurements were performed with the meter set to
FAST response and on the A-weighted equivalent continuous sound pressure level
(Leq). Leq(30min)
in six consecutive Leq(5min) measurements
were used as the monitoring parameter for the time period between 0700-1900
hours on weekdays; and also Leq(15min) in
three consecutive Leq(5min) measurements
is used as monitoring parameter for other time periods (e.g. during restricted
hours), if necessary.
3.22
During the measurement, the sound level meter is
mounted on a tripod with a height of 1.2m above ground and placed at the
assessment point and oriented such that the microphone is pointed to the site
with the microphone facing perpendicular to the line of sight. The windshield
is fitted for all measurements. The assessment
point is normally set as free-field situation for the measurement.
3.23
Prior
of noise measurement, the accuracy of the sound level meter is checked using an
acoustic calibrator generating a known sound pressure level at a known
frequency. The checking was
performed before and after the noise measurement.
3.24
The sound level meter and calibrator are
calibrated and certified by a laboratory accredited under HOKLAS or any other
international accreditation scheme at yearly basis.
3.25
The
Multi-parameter Water Quality Monitoring System is calibrated by HOKLAS
accredited laboratory of three month intervals.
3.26
All updated calibration certificates of
the monitoring equipment used for the impact monitoring program in this
Reporting Month are attached in Appendix E.
3.27
The meteorological information during
the construction phase is obtained from Cheung Chau Station of
the Hong Kong Observatory (HKO).
3.28
The
impact monitoring data are handled by the ET¡¦s systematic data recording and
management, which complies with in-house Quality Management System. Standard
Field Data Sheets (FDS) are used in the impact monitoring program.
3.29
The
monitoring data recorded in the equipment e.g. noise meter and Multi-parameter Water Quality
Monitoring System are downloaded directly from the equipment at the end
of each monitoring day. The
downloaded monitoring data are input into a computerized database properly
maintained by the ET. The
laboratory results are input directly into the computerized database and QA/QC
checked by personnel other than those who input the data. For monitoring activities require
laboratory analysis, the local laboratory follows the QA/QC requirements as set
out under the HOKLAS scheme for all laboratory testing.
3.30
According
to the approved Environmental Monitoring and Audit Manual, the construction
noise and water quality criteria were set up, namely Action and Limit levels
are listed in Tables 3-5 and 3-6 as below.
Table
3-5 Action
and Limit Levels for Water Quality
Impact Station |
Dissolved Oxygen (mg/L) |
Depth Average of Turbidity (NTU) |
Depth Average of SS (mg/L) |
|||||
Depth Average of Surface & Middle |
Bottom |
|||||||
Action Level |
Limit Level |
Action Level |
Limit Level |
Action Level |
Limit Level |
Action Level |
Limit Level |
|
W1 |
5.64 |
4.54 |
NA |
NA |
5.87 |
8.81 |
7.00 |
8.00 |
W2 |
5.16 |
5.02 |
NA |
NA |
5.50 |
5.66 |
7.00 |
8.00 |
W3 |
6.18 |
5.66 |
5.36 |
5.05 |
6.94 |
7.29 |
8.00 |
8.00 |
W4 |
5.94 |
4.95 |
5.71 |
5.54 |
7.50 |
8.03 |
7.85 |
11.57 |
W5 |
5.14 |
5.00 |
5.79 |
5.79 |
5.44 |
7.43 |
6.00 |
6.43 |
W6 |
5.92 |
4.26 |
6.04 |
4.49 |
6.82 |
7.10 |
8.00 |
9.59 |
W7 |
6.08 |
5.78 |
6.08 |
5.60 |
5.71 |
6.26 |
7.85 |
10.00 |
Table 3-6 Action
and Limit Levels for Construction Noise
Monitoring Location |
Action Level |
Limit Level in dB(A) |
Time Period: 0700-1900 hours
on normal weekdays |
||
N1 |
When one or more documented
complaints are received |
75 dB(A) |
If works
are to be carried out during restricted hours, the conditions stipulated in the construction noise
permit issued by the NCA have to be followed.
3.31
Furthermore,
Action/Limit Levels of Total residual chlorine is 0.2mg/L as
stipulated by EM&A Manual. Discharge of dechlorinated water must be suspended
if the total residual chlorine exceeds 0.2 mg/L and the water should be
circulated to a standby tank for further dechlorination
and testing.
3.32
Should
non-compliance of the environmental quality criteria occurs, remedial actions
will be triggered according to the Event and Action Plan enclosed in Appendix F.
4.1
The monitoring schedule of July 2017
had been issued to relevant parties on 29 June 2017 and listed in Appendix
G. The works
undertaken during the report month has been illustrated in Appendix
C. The monitoring
results are presented in the following sub-sections.
4.2
In
this Reporting Month, a total of 9 sampling
days perform marine water monitoring at the nine designated locations. Monitoring
results of 3 key parameters: dissolved oxygen (DO), turbidity and suspended
solids in this Reporting Month, are summarized in Tables 4-1 and 4-4.
Table 4-1 Results
Summary of Depth Average (Surface & Middle Layer)
of DO (mg/L)
Tidal |
Sampling date |
W1 |
W2 |
W3 |
W4 |
W5 |
W6 |
W7 |
W8 |
W9 |
Mid-Ebb |
4-Jul-17 |
7.85 |
7.88 |
7.01 |
7.43 |
7.98 |
7.95 |
8.26 |
7.64 |
7.48 |
6-Jul-17 |
8.33 |
8.51 |
7.78 |
7.72 |
8.32 |
8.55 |
8.54 |
7.86 |
7.86 |
|
8-Jul-17 |
5.89 |
5.91 |
6.22 |
6.13 |
6.24 |
6.26 |
6.18 |
6.22 |
5.53 |
|
10-Jul-17 |
6.87 |
7.01 |
6.42 |
6.34 |
6.71 |
7.06 |
6.56 |
6.36 |
6.71 |
|
12-Jul-17 |
14.68 |
14.78 |
11.61 |
11.59 |
15.14 |
11.07 |
12.02 |
11.54 |
12.29 |
|
14-Jul-17 |
6.67 |
6.53 |
6.61 |
6.62 |
6.50 |
6.64 |
6.68 |
6.66 |
6.67 |
|
18-Jul-17 |
7.21 |
7.30 |
6.79 |
6.84 |
6.93 |
7.74 |
7.24 |
6.68 |
6.94 |
|
20-Jul-17 |
8.73 |
8.85 |
7.97 |
8.43 |
8.55 |
8.24 |
8.33 |
8.14 |
8.00 |
|
22-Jul-17 |
8.58 |
8.29 |
8.13 |
7.85 |
7.79 |
7.77 |
8.02 |
8.12 |
7.81 |
|
Mid-Flood |
4-Jul-17 |
8.51 |
8.33 |
7.84 |
7.90 |
8.32 |
8.55 |
8.54 |
7.86 |
7.86 |
6-Jul-17 |
7.85 |
7.88 |
6.93 |
7.98 |
7.98 |
8.10 |
8.26 |
7.64 |
7.48 |
|
8-Jul-17 |
6.02 |
6.06 |
6.32 |
6.31 |
6.01 |
6.01 |
6.18 |
6.19 |
5.87 |
|
10-Jul-17 |
6.47 |
6.36 |
6.67 |
6.70 |
6.32 |
6.65 |
6.64 |
6.61 |
6.67 |
|
12-Jul-17 |
15.08 |
14.89 |
11.48 |
11.84 |
14.42 |
11.15 |
11.56 |
11.69 |
11.58 |
|
14-Jul-17 |
6.23 |
6.23 |
6.55 |
6.56 |
6.23 |
6.34 |
6.33 |
6.04 |
6.25 |
|
18-Jul-17 |
7.49 |
7.52 |
6.97 |
6.90 |
7.00 |
6.68 |
6.94 |
7.12 |
7.22 |
|
20-Jul-17 |
9.00 |
9.11 |
8.41 |
8.56 |
8.94 |
8.27 |
8.19 |
8.09 |
8.08 |
|
22-Jul-17 |
8.20 |
7.99 |
8.10 |
7.63 |
7.93 |
8.07 |
8.02 |
8.04 |
7.96 |
Table 4-2 Results
Summary of Bottom Depth of DO (mg/L)
Tidal |
Sampling date |
W1 |
W2 |
W3 |
W4 |
W5 |
W6 |
W7 |
W8 |
W9 |
Mid-Ebb |
4-Jul-17 |
NA |
NA |
6.05 |
6.15 |
7.17 |
6.86 |
7.42 |
6.48 |
6.22 |
6-Jul-17 |
NA |
NA |
6.16 |
6.65 |
8.13 |
6.59 |
7.58 |
6.60 |
6.90 |
|
8-Jul-17 |
NA |
NA |
6.06 |
5.94 |
6.09 |
6.09 |
6.09 |
6.09 |
4.99 |
|
10-Jul-17 |
NA |
NA |
6.09 |
5.80 |
6.39 |
6.32 |
6.41 |
5.36 |
5.76 |
|
12-Jul-17 |
NA |
NA |
6.65 |
6.59 |
6.97 |
6.78 |
6.95 |
7.01 |
6.95 |
|
14-Jul-17 |
NA |
NA |
6.66 |
6.66 |
6.62 |
6.66 |
6.65 |
6.67 |
6.65 |
|
18-Jul-17 |
NA |
NA |
6.41 |
6.49 |
6.93 |
7.15 |
6.64 |
6.60 |
6.36 |
|
20-Jul-17 |
NA |
NA |
5.79 |
5.85 |
7.12 |
6.90 |
6.68 |
6.65 |
5.55 |
|
22-Jul-17 |
NA |
NA |
6.40 |
7.27 |
6.39 |
6.11 |
6.57 |
6.92 |
6.13 |
|
Mid-Flood |
4-Jul-17 |
NA |
NA |
6.80 |
6.88 |
8.13 |
6.54 |
7.58 |
6.60 |
6.83 |
6-Jul-17 |
NA |
NA |
6.02 |
6.84 |
7.17 |
6.82 |
7.42 |
6.89 |
6.94 |
|
8-Jul-17 |
NA |
NA |
6.04 |
6.03 |
6.06 |
6.07 |
6.12 |
6.12 |
5.69 |
|
10-Jul-17 |
NA |
NA |
6.40 |
6.40 |
6.23 |
6.42 |
6.49 |
6.51 |
6.40 |
|
12-Jul-17 |
NA |
NA |
6.57 |
6.02 |
7.27 |
6.66 |
6.43 |
6.43 |
6.23 |
|
14-Jul-17 |
NA |
NA |
6.49 |
6.51 |
6.33 |
6.30 |
6.29 |
6.00 |
6.17 |
|
18-Jul-17 |
NA |
NA |
6.50 |
6.49 |
6.78 |
6.60 |
6.36 |
6.55 |
6.53 |
|
20-Jul-17 |
NA |
NA |
6.89 |
6.25 |
7.86 |
6.97 |
7.12 |
5.46 |
5.67 |
|
22-Jul-17 |
NA |
NA |
6.83 |
7.40 |
7.31 |
7.18 |
7.43 |
7.30 |
6.64 |
Table 4-3 Results
Summary of Depth Average of Turbidity (NTU)
Tidal |
Sampling date |
W1 |
W2 |
W3 |
W4 |
W5 |
W6 |
W7 |
W8 |
W9 |
Mid-Ebb |
4-Jul-17 |
2.80 |
2.67 |
3.03 |
3.14 |
2.62 |
3.22 |
2.48 |
2.72 |
2.79 |
6-Jul-17 |
2.78 |
2.32 |
2.60 |
2.81 |
2.81 |
2.48 |
2.49 |
2.63 |
2.69 |
|
8-Jul-17 |
3.45 |
4.36 |
5.88 |
5.54 |
4.33 |
3.73 |
5.05 |
5.06 |
4.56 |
|
10-Jul-17 |
3.95 |
3.99 |
4.26 |
4.29 |
4.02 |
4.08 |
4.22 |
4.36 |
4.50 |
|
12-Jul-17 |
3.59 |
3.75 |
3.13 |
2.98 |
3.74 |
3.02 |
3.73 |
2.55 |
3.22 |
|
14-Jul-17 |
2.34 |
2.02 |
3.25 |
3.41 |
2.19 |
3.30 |
3.33 |
3.20 |
3.42 |
|
18-Jul-17 |
0.16 |
0.12 |
0.09 |
0.12 |
0.90 |
0.11 |
0.16 |
0.36 |
0.13 |
|
20-Jul-17 |
1.46 |
0.52 |
0.39 |
1.00 |
0.41 |
1.18 |
3.69 |
4.57 |
0.73 |
|
22-Jul-17 |
0.51 |
0.54 |
1.27 |
0.45 |
0.55 |
0.59 |
0.58 |
0.51 |
0.61 |
|
Mid-Flood |
4-Jul-17 |
2.32 |
2.78 |
2.63 |
2.76 |
2.81 |
2.48 |
2.49 |
2.63 |
2.69 |
6-Jul-17 |
2.80 |
2.67 |
3.03 |
3.14 |
2.62 |
3.05 |
2.48 |
2.72 |
2.79 |
|
8-Jul-17 |
4.43 |
4.30 |
4.66 |
4.77 |
4.25 |
4.68 |
4.11 |
4.35 |
4.42 |
|
10-Jul-17 |
4.59 |
5.17 |
4.66 |
5.37 |
5.39 |
2.03 |
2.95 |
2.74 |
4.68 |
|
12-Jul-17 |
4.58 |
3.67 |
3.13 |
3.15 |
3.94 |
2.96 |
3.04 |
3.03 |
3.39 |
|
14-Jul-17 |
2.25 |
4.13 |
2.79 |
2.88 |
2.77 |
1.27 |
1.20 |
0.91 |
3.28 |
|
18-Jul-17 |
0.14 |
0.15 |
0.14 |
0.14 |
0.51 |
0.88 |
0.88 |
0.88 |
0.03 |
|
20-Jul-17 |
3.62 |
5.32 |
1.16 |
1.39 |
0.45 |
0.39 |
2.42 |
2.73 |
0.45 |
|
22-Jul-17 |
0.63 |
0.62 |
0.56 |
0.59 |
0.59 |
0.56 |
0.58 |
0.56 |
0.79 |
Table 4-4 Results
Summary of Depth Average of Suspended Solids (mg/L)
Tidal |
Sampling date |
W1 |
W2 |
W3 |
W4 |
W5 |
W6 |
W7 |
W8 |
W9 |
Mid-Ebb |
4-Jul-17 |
3.00 |
3.00 |
3.33 |
3.50 |
3.50 |
3.67 |
4.17 |
4.33 |
4.00 |
6-Jul-17 |
3.00 |
4.50 |
3.83 |
2.83 |
3.50 |
3.33 |
3.17 |
3.33 |
3.17 |
|
8-Jul-17 |
4.00 |
3.00 |
3.00 |
3.33 |
4.50 |
5.00 |
4.50 |
5.00 |
5.50 |
|
10-Jul-17 |
6.00 |
7.00 |
7.33 |
6.00 |
5.50 |
7.00 |
7.67 |
7.33 |
8.67 |
|
12-Jul-17 |
6.50 |
7.00 |
5.50 |
5.50 |
5.50 |
5.67 |
7.17 |
10.00 |
9.17 |
|
14-Jul-17 |
3.00 |
2.50 |
3.50 |
2.67 |
5.75 |
3.83 |
3.33 |
3.83 |
3.50 |
|
18-Jul-17 |
4.00 |
6.50 |
6.83 |
4.50 |
2.75 |
3.33 |
3.00 |
4.33 |
4.67 |
|
20-Jul-17 |
5.50 |
4.00 |
4.83 |
4.67 |
3.25 |
4.67 |
5.17 |
4.83 |
3.17 |
|
22-Jul-17 |
4.00 |
3.50 |
3.50 |
4.33 |
5.75 |
4.50 |
5.00 |
5.00 |
4.67 |
|
Mid-Flood |
4-Jul-17 |
4.00 |
5.00 |
4.67 |
3.00 |
3.25 |
2.83 |
2.50 |
3.50 |
3.17 |
6-Jul-17 |
2.00 |
1.50 |
3.00 |
3.00 |
3.25 |
4.33 |
4.67 |
3.83 |
4.17 |
|
8-Jul-17 |
4.50 |
5.50 |
6.67 |
6.33 |
4.25 |
5.83 |
3.33 |
3.83 |
3.33 |
|
10-Jul-17 |
5.50 |
5.50 |
6.50 |
6.83 |
5.50 |
7.33 |
7.33 |
6.50 |
6.33 |
|
12-Jul-17 |
6.50 |
6.00 |
5.50 |
5.67 |
5.00 |
4.83 |
5.83 |
5.50 |
4.33 |
|
14-Jul-17 |
3.00 |
3.50 |
3.50 |
3.33 |
3.25 |
3.33 |
3.33 |
3.83 |
2.83 |
|
18-Jul-17 |
4.00 |
4.50 |
4.83 |
5.00 |
4.50 |
5.50 |
4.33 |
5.50 |
5.17 |
|
20-Jul-17 |
3.50 |
3.00 |
4.67 |
3.67 |
4.50 |
3.67 |
3.67 |
3.83 |
4.83 |
|
22-Jul-17 |
3.50 |
3.50 |
5.00 |
4.33 |
5.75 |
4.50 |
4.50 |
4.50 |
4.00 |
Remark: If the
monitoring result is less than 1, the average was calculated by assuming the measurement
value to be 1.
Italic and bold value
indicated Action Level exceedance
Underlined and
bold value indicated Limit Level exceedance
4.3
During the Reporting Period, field measurements showed that
temperatures of marine water were within 26.5¢XC to 29.4¢XC; the salinity concentrations within 18.12
to 31.44 ppt and pH values within 8.29 to 12.33
4.4
The
monitoring results including in-situ measurements and laboratory testing
results are provided in Appendix H. The
graphical plots are shown in Appendix I.
4.5
A
summary of exceedances for the three parameters: dissolved oxygen (DO),
turbidity and suspended solids is shown in Table
4-5.
Table 4-5 Summary
of Water Quality Exceedance
Station |
DO (Ave of Top & mid-depth) |
DO Bottom Depth |
Turbidity (Depth Ave.) |
SS (Depth Ave) |
Total Exceedance |
|||||
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
Action |
Limit |
|
W1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W3 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W4 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W5 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W6 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
W7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
No
of Exceedance |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
4.6
In
this Reporting Month, no Action and Limit Level exceedances recorded in water
quality recorded.
4.7
Since
cleaning and sterilization of watermain was carried
out and finished in January 2017, no de-chlorinated water was discharged in this reporting period and no in-situ
Total residual chlorine measurement was conducted.
4.8
Total 3 occasions
construction noise monitoring was undertaken in Reporting Period. The noise monitoring results at the
designated location (N1) are summarized in Table 4-6.
Table 4-6 Summary of Construction Noise Monitoring Results ¡V N1
Date |
Start
Time |
1st
Leq5min |
2nd
Leq5min |
3rd
Leq5min |
4th
Leq5min |
5th
Leq5min |
6th
Leq5min |
Leq30min |
Corrected* Leq30min |
4-Jul-17 |
13:16 |
55.4 |
55.7 |
53.2 |
54.9 |
54.5 |
54.6 |
54.8 |
58.0 |
14-Jul-17 |
13:47 |
54.9 |
52.3 |
52.7 |
51.9 |
52.7 |
51.5 |
52.8 |
56.0 |
22-Jul-17 |
14:11 |
52.3 |
53.4 |
52.9 |
53.4 |
55.7 |
54.2 |
53.8 |
57.0 |
Limit Level |
- |
> 75 dB(A) |
(*) A façade correction of +3 dB(A) has been added according to acoustical principles and
EPD guidelines.
4.9
As shown in the
results were well below 75dB(A), also no noise
complaint (which
is an Action Level exceedance) was received by
the RE, WSD, EPD and the Contractor.
Hence, no
Action or Limit Level exceedance was triggered during this month. The graphical plot is shown in Appendix
I.
4.10
The meteorological information during reporting
month extracted from Cheung Chau Station of the Hong Kong Observatory (HKO)
shows in Appendix J.
5.1
Waste management was carried out by an on-site Environmental
Officer or an Environmental Supervisor from time to time.
All types of waste arising from the construction work
are classified into the following:
l Construction & Demolition (C&D)
Material;
l Chemical Waste;
l General Refuse; and
l Excavated Soil.
5.2
The
quantities of waste for disposal in this Reporting Period are summarized in Table 5-1 and 5-2 and
the Monthly Summary Waste Flow Table is shown in
Appendix K. Whenever possible, materials were reused
on-site as far as practicable.
Table 5-1 Summary
of Quantities of Inert C&D Materials
Type of Waste |
Quantity |
Disposal
Location |
C&D Materials (Inert) (¡¥000 m3) |
0 |
- |
Reused in this Contract (Inert) (¡¥000 m3) |
0 |
- |
Reused in other Projects (Inert) (¡¥000 m3) |
0 |
- |
Disposal as Public Fill (Inert) (¡¥000 m3) |
0 |
Outlaying Island Transfer facility
(Cheung Chau Station) |
Table 5-2 Summary
of Quantities of C&D Wastes
Type of Waste |
Quantity |
Disposal Location |
Recycled Metal (¡¥000kg) |
0 |
- |
Recycled Paper / Cardboard Packing (¡¥000kg) |
0 |
- |
Recycled Plastic (¡¥000kg) |
0 |
- |
Chemical Wastes (¡¥000kg) |
0 |
- |
General Refuses (¡¥000 m3) |
0.07 |
Outlaying Island Transfer
facility (Cheung Chau Station) |
5.3
The
estimated volume of surface runoff should be less than 50m3 in this
month period.
6.1
According to the Environmental Monitoring and Audit Manual, the
environmental site inspection should been formulation by ET Leader. Regular environmental site inspections
had been carried out by the ET to confirm the environmental performance. 3 weekly
site inspections were carried out on 7, 10 and 18 July
2017 with the Representatives of the Engineer and the Contractor to
evaluate the site environmental performance in this Reporting Month. Furthermore, joint site inspection with IEC also
undertaken on 7 July 2017. No
non-compliance was noted. However,
minor deficiencies were observed during weekly site inspection or joint site
inspection.
6.2
Observations
for the site inspections and monthly audit within this Reporting Month are
summarized in Table
6-1.
Date |
||
7 July 2017 |
No
environmental issue was observed during the site inspection. |
NA |
10 July 2017 |
No
environmental issue was observed during the site inspection. |
NA |
18 July 2017 |
No
environmental issue was observed during the site inspection. |
NA |
7.1
No
environmental complaint, summons and prosecution was received in this reporting
period. The statistical summary table of environmental complaint is presented
in Tables 7-1, 7-2 and 7-3.
Table 7-1 Statistical
Summary of Environmental Complaints
Reporting Period |
Environmental Complaint Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
28 Mar 14 ¡V 30 June 17 |
0 |
0 |
NA |
1 ¡V 23 July 17 |
0 |
0 |
NA |
Table 7-2 Statistical
Summary of Environmental Summons
Reporting Period |
Environmental Summons Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
28 Mar 14 ¡V 30 June 17 |
0 |
0 |
NA |
1 ¡V 23 July 17 |
0 |
0 |
NA |
Table 7-3 Statistical
Summary of Environmental Prosecution
Reporting Period |
Environmental Prosecution Statistics |
||
Frequency |
Cumulative |
Complaint Nature |
|
28 Mar 14 ¡V 30 June 17 |
0 |
0 |
NA |
1 ¡V 23 July 17 |
0 |
0 |
NA |
8.1
The environmental mitigation measures that recommended in the Implementation Schedule for
Environmental Mitigation Measures (ISEMM) in the approved EM&A Manual covered the issues of dust, noise, water and waste and they
are showed Appendix L.
8.2
CRCPJV had been implementing the required environmental mitigation
measures according to the
Environmental Monitoring and Audit Manual subject to
the site condition. Environmental
mitigation measures generally implemented by CRCPJV in this Reporting Month are
summarized in Table 8-1.
Table 8-1 Environmental
Mitigation Measures
Issues |
Environmental
Mitigation Measures |
Water
Quality |
¡P Wastewater were appropriately
treated by treatment facilities; ¡P Drainage channels were
provided to convey run-off into the treatment facilities; and ¡P Drainage systems were regularly and
adequately maintained. |
Air
Quality |
¡P
Regular watering to reduce
dust emissions from all exposed site surface, particularly during dry
weather; ¡P
Frequent watering for
particularly dusty construction areas and areas close to air sensitive
receivers; ¡P
Cover all excavated or
stockpile of dusty material by impervious sheeting or sprayed with water to
maintain the entire surface wet; ¡P
Public roads around the site entrance/exit had been kept clean
and free from dust; and ¡P
Tarpaulin
covering of any dusty materials on a vehicle leaving the site. |
Noise |
¡P
Good site practices to limit
noise emissions at the sources; ¡P
Use of quite plant and
working methods; ¡P
Use of site hoarding or
other mass materials as noise barrier to screen noise at ground level of
NSRs; ¡P
Use of shrouds/temporary
noise barriers to screen noise from relatively static PMEs; ¡P
Scheduling of construction
works outside school examination period in critical area; and ¡P
Alternative use of plant items within one worksite,
where practicable. |
Waste
and Chemical Management |
¡P
Excavated material should be
reused on site as far as possible to minimize off-site disposal. Scrap metals
or abandoned equipment should be recycled if possible; ¡P
Waste arising should be kept
to a minimum and be handled, transported and disposed of in a suitable
manner; ¡P
The Contractor should adopt
a trip ticket system for the disposal of C&D materials to any designed
public filling facility and/or landfill; and ¡P
Chemical waste shall be handled in accordance with the
Code of Practice on the Packaging, Handling and Storage of Chemical Wastes. |
General |
The
site was generally kept tidy and clean. |
9.1
This is last (40th) monthly EM&A report presenting the
monitoring results and inspection findings for the Reporting Period from 1st July
2017 to 31st July
2017.
9.2
No noise complaint (which is an Action Level exceedance) was
received and no construction noise measurement results that exceeded the Limit
Level were recorded in the Reporting Period. No NOEs or the associated corrective actions were therefore
issued.
9.3
In this Reporting Month, no
Action Limit Level exceedances recorded in water quality recorded.
9.4
Since
cleaning and sterilization of watermain was carried
out and finished in January 2017, no de-chlorinated water was discharged in this reporting period and no in-situ
Total residual chlorine measurement was conducted.
9.5
No documented complaint, notification of summons or successful prosecution
was received by the Project.
9.6
The ET had carried out site inspection on 7, 10 and 18 July 2017 with the
Representatives of the Engineer and the Contractor. Furthermore, joint site inspection with
IEC also undertaken on 7 July 2017.
9.7
As agreed by the RE, IEC,
Contractor and ET, the construction phase EM&A programme was terminated on
23 July 2017 and the 4-week post project marine water quality monitoring was immediately
commenced on 24 July 2017 as required in Section 2.7.3 of the EM&A Manual. The
result of 4-week post project marine water quality monitoring will be provided
separately and is not included in this EM&A report.