· Air Quality Impact
· Noise Impact
· Water Quality Impact
· Waste Management Implication
· Land Contamination
· Ecological Impact
· Cultural Heritage
· Landscape and Visual Impact
· Hazard to Life
Avoidance of substantial portal slope and site formation works at natural habitat for the new middle third tunnel tube of LRT at both Kowloon and Shatin Portals
Minimization of encroachment from tunnel ancillary facilities upon Lion Rock Country Park
Minimization of encroachment from the proposed LRTR widening works upon Lion Rock Country Park and woodland area
Minimization of environmental impacts due to the proposed natural terrain hazard mitigation measures (NTHMM)
· Adoption of environmentally friendly construction method;
· Adoption of engineering design which mitigates environmental impacts;
· Phased Construction Programme;
· Implementation of trip-ticket system; and
· Implementation of environmental monitoring and auditing system.
Adoption of Environmentally Friendly Construction Method
Adoption of Engineering Design which Mitigates Environmental Impacts
Phased Construction Programme
Implementation of Trip-Ticket System
Implementation of Environmental Monitoring and Auditing System
Table 14.1 Summary of Key Environmental Problems Avoided and Sensitive Areas Protected
Design Approach |
Environmental Problems Avoided and Sensitive Areas Protected |
Optimisation of Project footprint (Section 2) |
· When formulating the design and layout of the proposed works, avoid and minimize encroachment / direct impacts to sites of conservation importance such as LRCP and Beacon Hill SSSI to the maximum practicable extent · Avoided habitat loss for the area of stockpiling |
Adoption of environmental friendly construction method (Section 2) |
· Adoption of pre-cast construction elements as far as practical replacing traditional cast in-situ construction to reduce the adverse impacts to the sensitive receivers · Adoption of prefabricated steel formwork replacing conventional timber formwork to lessen the C&D materials generated |
Appropriate design of NTHMM (Section 2) |
· Adoption of flexible barriers instead of rigid barriers as NTHMMs to minimize the impacts from construction work outside LRCP · Construction of rigid barriers at the developed/paved area rather than proposing large-scale soil nailing works at the uphill slope located within LRCP to minimize the impacts from construction work within LRCP |
Phased Construction Programme for road widening of LRTR (Section 2) |
· Minimize the cumulative construction phase environmental impact on the nearby sensitive receivers by staggered construction programme |
Impacts of noise mitigation measures on ardeid flight path avoided (Section 8) |
· Avoid disturbance on ardeid flight path |
Implementation of EM&A System (Section 12) |
· Ensure all the recommended measures are properly in place and their effectiveness |
Air Quality Impact
Noise Impact
Construction Noise
Road Traffic Noise
Tunnel Portal Noise Impact
Fixed Noise Source
Water Quality Impact
Waste Management Implication
Land Contamination
Ecology Impact
Cultural Heritage Impact
Landscape and Visual Impact
Hazard to Life
Table 14.2 Summary of Mitigation Measures and Associated Environmental Benefit
Environmental Aspect |
Mitigation Measures and any Associated Benefit |
Air Quality Impact |
· Watering once every 2 hours on work areas, exposed surface and unpaved road to reduce dust emission. · Sealed door and dust collector with dust removal efficiency of at least 80% at the opening of tunnel mined by drill and break. · Implementation of dust suppression measures as required in the Air Pollution Control (Construction Dust) Regulation to minimize construction dust impact. · With implementation of the above measures, potential air quality would be minimised/avoided. No adverse air quality impact would be anticipated |
Noise Impact |
Construction Phase: · NSRs are protected with implementation of the proposed noise mitigation measures, including the use of QPME, deployment of construction noise barriers, sequencing operation of construction activates at critical area, reduction of PME at critical works area and avoiding to carry out particular noisy construction activities during examination periods. The predicted mitigated construction noise levels arising from the Project at all NSRs selected for the construction noise impact assessment would comply with the EIAO-TM construction noise criteria during non-restricted hours and restricted hours. Operation Phase: · Provision of low-noise road surfacing polymer modified friction course (PMFC) (i.e. a type of low noise road surfacing) as standard surfacing material · Provision of a total of 170m long vertical noise barrier, 240m long cantilever noise barriers, and 1300m long semi- enclosure on Project Road sections (refer to Table 4.22, 60604728/R42b/Figure 4.4, 60604728/R42b/Figure 4.4.2, 60604728/R42b/Figure 4.4.3 and 60604728/R42b/Figure 4.4.4) can protect 1,239 dwellings. |
Water Quality Impact |
Construction Phase: · Implementation of mitigation measures and good site practices in ProPECC PN 1/94 “Construction Site Drainage”, and precaution measures in ETWB Technical Circular (Works) No. 5/2005 · Provision of temporary sanitary facilities, such as chemical toilets, for construction workforce · Implementation of groundwater infiltration minimisation strategies and post-grouting · Adoption of proper interception and treatment of contaminated site runoff and wastewater from land decontamination in compliance with the TM-DSS, and proper treatment or recharge of contaminated groundwater in compliance with the TM-DSS · With implementation of the above measures, potential water quality would be minimised/avoided. No adverse water quality impact during construction phase would be anticipated Operation Phase: · Adequate design in on-site STP adopted MBR with UV disinfection, an emergency storage tank with 2 hours of ADWF capacity and grease trap for sewage and wastewater generated from administration building which designed with reference to EPD’s “Guidelines for the Design of Small Sewage Treatment Plant”. · Provision of dual or standby power supply, standby sewage treatment units, flow sensors and alarm systems for the on-site STP. · Provision of spare parts such as electrical and mechanical components of the on-site STP in case of break down / emergency. · Adequate design in septic tank with soakaway system and active carbon filter for sewage and wastewater generated from ventilation buildings which take into account the guidelines in ProPECC PN 5/93. · Adequate design in on-site STP, petrol interceptor and sedimentation tank for wastewater generated from washing and maintenance operation. · Regular test, maintenances and replacement of membranes or equipment to maintain a good operation condition. · Regular maintenance to all wastewater treatment system, including the on-site STP, septic tank with soakaway system, grease traps, active carbon filter system, petrol interceptor, sedimentation tank, etc. · With implementation of the above measures, potential water quality would be minimised/avoided. No adverse water quality impact during operation phase would be anticipated |
Waste Management Implications |
· Implementation of good site practices, waste reduction measures and proper storage, collection and transport of waste to ensure no adverse environmental impact in relation to hazard, air/odour emissions, noise, wastewater discharge or public transport. |
Land Contamination |
· Subject to the finding of supplementary CAR(s) / site appraisal, if contamination is identified, the remediation measures for remediation works as stated in RR(s) should be implemented to ensure soil/groundwater contamination, if any, would be identified and properly treated prior to construction works. |
Ecological Impact (Terrestrial) |
· Avoidance of encroachment on recognised sites of conservation importance (i.e. LRCP (about 197 ha) and Beacon Hill SSSI (about 34 ha) within the assessment area as far as possible. · Carefully design of the detailed layout of the construction works to avoid/minimise direct impact on flora species of conservation importance recorded in the project footprint. If direct impact is unavoidable, mitigation measures to (e.g. transplant, compensate) the flora species of conservation importance should be conducted, where possible, according to Final Plant Preservation and Transplantation Proposal to be submitted at later stage. · Reinstatement of temporarily affected area within the Project footprint (about 1.48 ha), including those within LRCP (about 0.25 ha), by woodland mix planting upon completion of works according to the Final Reinstatement Plan to be submitted at later stage. · Direct impact on fauna species of conservation importance and their key habitats are avoided. Precautionary measure such as a pre-construction survey in natural habitats within and in the surrounding of the Project footprint is recommended (e.g. woodland, mixed woodlands and natural watercourse within and near the Project footprint) prior to the commencement of construction activities. In case any fauna species of conservation importance recorded would be directly impacted, a Protection and Translocation Proposal should be prepared to recommend suitable mitigation measures at later stage. · Permanent (0.16 ha) and temporary (0.09 ha) loss of woodlands within LRCP would be unavoidable. While the temporarily affected woodlands would be reinstated by woodland mix planting upon completion of works, provision of compensation woodland in ratio not less than 1:1 in terms of area (i.e. at least 0.25 ha) in accordance with the Woodland Compensation Plan is recommended as mitigation and enhancement measures. · Implementation of good site practices (e.g. provision of screening, control of glare / lighting, groundwater infiltration minimization measures, etc), regular site inspection and monitoring requirement. · Implementation of groundwater infiltration minimization measures (e.g. groundwater control strategies, post-grouting) as stated in the Water Quality Section above and Section 5 of the EIA Report. · Adoption of NTHMMs with smaller footprint (rigid barriers and flexible barriers) to avoid and minimize the potential impacts to LRCP, natural habitats and associated vegetation. Operation Phase: · Implementation of good site practices and mitigation measures (e.g. planting of peripheral screening plants/vertical green, control of glare / lighting) measures to minimize potential indirect impacts including dust, noise, site runoff, groundwater infiltration and glare) to natural habitats and wildlife in the vicinity · Carefully design of the noise barrier (e.g. location, use of tinted materials and superimposing dark patterns or strips on the noise barrier) to avoid and minimize bird mortality from collision. |
Impact on Cultural Heritage |
Avoidance of impact on Ex-Kowloon-Canton Railway Beacon Hill Tunnel and non-graded buildings and structures including Lion Rock Valve House, Lion Rock High Level No.1 Primary Service Reservoir, Lion Rock Low Level Primary Service Reservoir, Radio Television Hong Kong Broadcasting House during construction phase: · Monitoring of vibration, settlement and tilting incorporated with a set of Alert, Alarm and Action (AAA) system Maintenance of the original sentiment of Lion Rock Tunnel and associated buildings with following measures: · Fonts on both sides of the portals of the two tunnels should be kept or replicated and placed on similar position as the current setting · The colour scheme of associated buildings could be adopted to the new administrative buildings in order to maintain the original sentiment. · The two commemorative plaques marking the opening ceremony of the tunnel should be kept at prominent position at the new administrative buildings visible to all guests. · Detailed photographic recording on the Lion Rock Tunnel and its associated buildings (both exterior and interior) should be conducted before any works to commence. A copy of the photographic documentation should be provided to AMO for record.
|
Landscape and Visual Impacts |
Construction Phase: · Preservation of Existing Vegetation · Control of Night-time Lighting Glare · Erection of Decorative Screen Hoarding · Management of Construction Activities and Facilities · Reinstatement of Temporarily Disturbed Landscape Areas · Minimize the Direct Conflict with Lion Rock Country Park · Minimize Disturbance on Watercourses Operation Phase: · Compensatory Tree Planting (min. 145 heavy standard trees) for Loss of approximate 2,925 nos. of Existing Trees · Compensatory Woodland Mix Planting (7,720m.sq.) within site (about 2,070 tree whips) and provision of off-site compensation woodland (about 0.3 ha or 1,200 native seedlings/whip trees) · Aesthetically pleasing design of Aboveground Structures · Aesthetically pleasing design of Highways Structures and Slope Associated Structures · Aesthetically pleasing design of footbridges, noise barriers and noise enclosures · Provision of Green Roof · Provision of Buffer Planting / Roadside Planting · Greening Works on Slopes and associated structures With the implementation of proposed mitigation measures, the residual landscape and visual impacts would be further minimized throughout the operation phase when the proposed compensatory planting, buffer planting and woodland mix planting become mature in year 10 of operation to blend in with the adjacent landscape and visual setting of the area. |
Hazard to Life |
· Establishment of emergency response plans. · Safety/emergency response training and drills for all personnel. · Maintain the number of construction workers onsite to a minimum to minimise any potential risk. |