CONTENTS

 

5             WATER QUALITY. 5-1

5.1         Introduction. 5-1

5.2         Relevant Legislation and Guidelines. 5-1

5.3         Baseline Conditions. 5-4

5.4         Assessment Criteria. 5-12

5.5         Assessment Methodology. 5-22

5.6         Potential Sources of Impact 5-22

5.7         Impact Assessment - Construction Phase. 5-23

5.8         Impact Assessment - Operational Phase. 5-30

5.9         Mitigation Measures. 5-67

5.10       Cumulative Impacts. 5-69

5.11       Residual Impacts. 5-72

5.12       Environmental Monitoring and Audit 5-73

5.13       Conclusion. 5-73

 

TABLES

Table 5.1            Summary of Water Quality Objectives for NWWCZ  5-1

Table 5.2            Summary of EPD Routine Water Quality Monitoring Data from Selected Stations within the Assessment Area (2017 – 2021) 5-5

Table 5.3            Summary of 3RS Water Quality Monitoring Data from 2016-2022  5-6

Table 5.4            Summary of EPD Routine Sediment Quality Monitoring Data from Selected Stations within the Assessment Area (2017– 2021) 5-7

Table 5.5            Summary of Elutriate Test Results for Sediment Collected under this EIA  5-9

Table 5.6            Water Sensitive Receivers  5-10

Table 5.7            Allowable Increase in SS (mg L-1) Levels for Water Sensitive Receivers and Observation Points  5-14

Table 5.8            WSD’s Water Quality Criteria for Water at Seawater Intakes  5-17

Table 5.9            Allowable DO Depletion (mg L-1) for Water Sensitive Receivers and Observation Points  5-18

Table 5.10          Summary of Assessment Criteria for Dissolved Metals and Organic Contaminants  5-21

Table 5.11          Predicted Tidal Discharge across Major Cross Sections  5-34

Table 5.12          Predicted Percentile Distribution of Tidal Discharge across Major Cross Sections (Black: Scenario O1; Blue: Scenario O2) 5-35

Table 5.13          Predicted Instantaneous Tidal Discharge across Major Cross Section (Black: Scenario O1; Blue: Scenario O2) 5-39

Table 5.14          Current Magnitude at Observation Points outside the Embayment in Dry Season and Wet Season  5-45

Table 5.15          Current Direction at Additional Observation Points outside the Embayment in Dry Season and Wet Season  5-48

Table 5.16          Predicted Level of SS Elevation (mg L-1) from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with a Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source) 5-53

Table 5.17          Predicted Level of Sedimentation (g/m2/day) at Coral and Artificial Reef from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with One Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source) 5-58

Table 5.18          Predicted Level of DO Depletion (mg L-1) (Dredging Rate of 40 m3 hr-1 with One Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source) 5-60

Table 5.19          Predicted Level of Conservative Tracer (mg L-1) and Corresponding Level of TIN and UIA at WSR C14 from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with One Close Grab Dredger close to WSR C14, and with Cage Type Silt Curtain at Source) 5-65

Table 5.20          Estimation of Contaminant Levels Elevation at the Most Impacted WSRs from Maintenance Dredging  5-65

Table 5.21          Concurrent Projects Considered in this Water Quality Impact Assessment 5-70

 

FIGURES

Figure 5.1        Water Sensitive Receivers and EPD Marine Water / Sediment Quality Monitoring Stations in the North Western Water Control Zone

 

APPENDICES

Appendix 5.1   Working Paper on Water Quality Modelling Plan

Appendix 5.2   Contour Plots for SS Elevation and Sedimentation Flux from Maintenance Dredging

Appendix 5.3   Grid Convergence Test

Appendix 5.4   Contour Plot of Depth-Averaged Tracer Concentration in Dry and Wet Seasons

Appendix 5.5   Details of Proposed Project Element and Existing Piers and Box Culvert Considered in Hydrodynamic Assessment

Appendix 5.6   General Layout Plan for Marine Viaduct

Appendix 5.7   Sediment Elutriate Test Results

 

EXHIBITS

Exhibit 5.1       Steel Casing Installation with Silt Curtain

Exhibit 5.2       Design of Wave Attenuator

Exhibit 5.3       Indicative Pile Locations for SkyPier (Option MF-B)

Exhibit 5.4       Indicative Pile Locations for Berthing Area (Option MF-B)

Exhibit 5.5       Threshold Seabed Level for Triggering Maintenance Dredging

Exhibit 5.6       Indicative Locations for the Major Cross Section shown in Black Line, Green Dots indicates Project Elements that could Affect Flow Regime

Exhibit 5.7       Predicted Water Temperature (°C) at Seawater Intake C9

Exhibit 5.8       Selected Representative Locations for Nearby WSRs outside the Embayment


5                         WATER QUALITY

5.1                   Introduction

5.1.1.1       This Section presents an evaluation and assessment of the potential water quality impacts from the construction and operation of the Project in accordance with Clause 3.4.6 of the EIA Study Brief, and the results were assessed with reference to the relevant environmental legislation, standards and criteria.

5.2                   Relevant Legislation and Guidelines

5.2.1             General

5.2.1.1       The following legislation and relevant guidance or non-statutory guidelines are applicable to the evaluation of water quality impacts associated with the construction and operation of the Project.

5.2.2             Water Pollution Control Ordinance (WPCO) (Cap 358)

5.2.2.1       The Water Pollution Control Ordinance (WPCO) (Cap 358) is the primary legislation for the control of water pollution and water quality in Hong Kong.  Under the WPCO, Hong Kong waters are divided into 10 Water Control Zones (WCZs).  Each WCZ has a designated set of statutory Water Quality Objectives (WQOs).

5.2.2.2       The proposed Project elements span from Tung Chung to the east side of the Airport Island and the west side of the Hong Kong Port (HKP).  According to Clause 3.4.6.2 of the EIA Study Brief, the Assessment Area shall include areas within 500 m from the boundary of the Project and shall cover the North Western Water Control Zone (NWWCZ) under the WPCO.  The applicable WQOs for NWWCZ are presented in Table 5.1.  

Table 5.1         Summary of Water Quality Objectives for NWWCZ

 

Water Quality Objectives

Sub-Zone

A

AESTHETIC APPEARANCE

 

a)

Waste discharges shall cause no objectionable odours or discolouration of the water.

Whole zone

b)

Tarry residues, floating wood, articles made of glass, plastic, rubber or of any other substances should be absent.

Whole zone

c)

Mineral oil should not be visible on the surface.  Surfactants should not give rise to a lasting foam.

Whole zone

d)

There should be no recognisable sewage derived debris.

Whole zone

e)

Floating, submerged and semi-submerged objects of a size likely to interfere with the free movement of vessels, or cause damage to vessels, should be absent.

Whole zone

f)

Waste discharges shall not cause the water to contain substances which settle to form objectionable deposits.

Whole zone

B

BACTERIA

 

a)

The level of Escherichia coli should not exceed 610 per 100 mL, calculated as the geometric mean of all samples collected in a calendar year.

Secondary Contact Recreation Subzones

b)

The level of Escherichia coli should be less than 1 per 100mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

c)

The level of Escherichia coli should not exceed 1 000 per 100 mL, calculated as the running median of the most recent 5 consecutive samples taken at intervals of between 7 and 21 days.

Tuen Mun (C) Subzone and other inland waters

d)

The level of Escherichia coli should not exceed 180 per 100 mL, calculated as the geometric mean of all samples collected from March to October inclusive.  Samples should be taken at least 3 times in one calendar month at intervals of between 3 and 14 days.

Bathing Beach Subzones

C

COLOUR

 

a)

Waste discharges shall not cause the colour of water to exceed 30 Hazen units.

Tuen Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones

b)

Waste discharges shall not cause the colour of water to exceed 50 Hazen units.

Tuen Mun (C) Subzone and other inland waters

D

DISSOLVED OXYGEN

 

a)

Waste discharges shall not cause the level of dissolved oxygen to fall below 4 mg per litre for 90% of the sampling occasions during the whole year; values should be calculated as water column average (arithmetic mean of at least 3 measurements at 1 m below surface, mid-depth and 1 m above seabed).  In addition, the concentration of dissolved oxygen should not be less than 2 mg per litre within 2 m of the seabed for 90% of the sampling occasions during the whole year.

Marine waters

b)

Waste discharges shall not cause the level of dissolved oxygen to be less than 4 mg per litre.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones and other inland waters

E

pH

 

a)

The pH of the water should be within the range of 6.5-8.5 units.  In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.2 unit. 

Marine waters excepting Bathing Beach Subzones

b)

Waste discharges shall not cause the pH of the water to exceed the range of 6.5-8.5 units.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

c)

The pH of the water should be within the range of 6.0-9.0 units.

Other inland waters

d)

The pH of the water should be within the range of 6.0-9.0 units for 95% of samples collected during the whole year.  In addition, waste discharges shall not cause the natural pH range to be extended by more than 0.5 unit.

Bathing Beach Subzones

F

TEMPERATURE

 

a)

Waste discharges shall not cause the natural daily temperature range to change by more than 2.0°C.

Whole zone

G

SALINITY

 

a)

Waste discharges shall not cause the natural ambient salinity level to change by more than 10%.

Whole zone

H

SUSPENDED SOLIDS

 

a)

Waste discharges shall neither cause the natural ambient level to be raised by more than 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities.

Marine waters

b)

Waste discharges shall not cause the annual median of suspended solids to exceed 20 mg per litre.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

c)

Waste discharges shall not cause the annual median of suspended solids to exceed 25 mg per litre.

Other inland waters

I

AMMONIA

 

a)

The unionized ammoniacal nitrogen level should not be more than 0.021 mg per litre, calculated as the annual average (arithmetic mean).

Whole zone

J

NUTRIENTS

 

a)

Nutrients shall not be present in quantities sufficient to cause excessive or nuisance growth of algae or other aquatic plants. 

Marine waters

b)

Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.3 mg per litre, expressed as annual water column average (arithmetic mean of at least 3 measurements at 1 m below surface, mid-depth and 1 m above seabed).

Castle Peak Bay Subzone

c)

Without limiting the generality of objective (a) above, the level of inorganic nitrogen should not exceed 0.5 mg per litre, expressed as annual water column average (arithmetic mean of at least 3 measurements at 1 m below surface, mid-depth and 1 m above seabed).

Marine waters excepting Castle Peak Bay Subzone

K

5-DAY BIOCHEMICAL OXYGEN DEMAND

 

a)

Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 3 mg per litre.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

b)

Waste discharges shall not cause the 5-day biochemical oxygen demand to exceed 5 mg per litre.

Other inland waters

L

CHEMICAL OXYGEN DEMAND

 

a)

Waste discharges shall not cause the chemical oxygen demand to exceed 15 mg per litre.

Tuen Mun (A), Tuen Mun (B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones

b)

Waste discharges shall not cause the chemical oxygen demand to exceed 30 mg per litre.

Other inland waters

M

TOXINS

 

a)

Waste discharges shall not cause the toxins in water to attain such levels as to produce significant toxic, carcinogenic, mutagenic or teratogenic effects in humans, fish or any other aquatic organisms, with due regard to biologically cumulative effects in food chains and to toxicant interactions with each other.

Whole zone

b)

Waste discharges shall not cause a risk to any beneficial use of the aquatic environment.

Whole zone

N

PHENOL

 

a)

Phenols shall not be present in such quantities as to produce a specific odour, or in concentration greater than 0.05 mg per litre as C6H5OH.

Bathing Beach Subzones

O

TURBIDITY

 

a)

Waste discharges shall not reduce light transmission substantially from the normal level.

Bathing Beach Subzones

 

5.2.3             Technical Memorandum for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-ICW)

5.2.3.1       All discharges from the construction and operational phases of the proposed Project are required to comply with the Technical Memorandum Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-ICW) issued under Section 21 of the WPCO.

5.2.3.2       The TM-ICW defines acceptable discharge limits to different types of receiving waters.  Under the TM-ICW, effluents discharged into the drainage and sewerage systems, inshore and coastal waters of the WCZs are subject to pollutant concentration standards for specified discharge volumes.  These are defined by the Environmental Protection Department (EPD) and are specified in licence conditions for any new discharge(s) within a WCZ.

5.2.4             Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM)

5.2.4.1       Annexes 6 and 14 of the EIAO-TM provide general guidelines and criteria to be used in assessing water quality impacts.

5.2.4.2       The EIAO-TM recognizes that, in the application of the above water quality criteria, it may not be possible to achieve the WQO at the point of discharge as there are areas which are subjected to greater impacts (which are termed by the EPD as the mixing zones), where the initial dilution of the discharge takes place.  The definition of this area is determined on a case-by-case basis.  In general, the criteria for acceptance of the mixing zones are that it must not impair the integrity of the water body as a whole and must not damage the ecosystem.

5.2.5             Practice Note for Professional Persons, Construction Site Drainage

5.2.5.1       Apart from the above statutory requirements, the Practice Note for Professional Persons, Construction Site Drainage (ProPECC PN 1/94), issued by EPD in 1994, also provide useful guidelines on the prevention of water pollution associated with construction activities.

5.3                   Baseline Conditions

5.3.1             Assessment Area

5.3.1.1       According to Clause 3.4.6.2 of the EIA Study Brief, the Assessment Area shall include areas within 500 m from the boundary of the Project and shall cover the NWWCZ as designated under the WPCO and the water sensitive receivers in the vicinity of the Project.

 

 

5.3.2             Marine Water Quality

5.3.2.1       Baseline marine water quality of the Assessment Area has been determined through a review of EPD routine water quality monitoring data collected between 2017 and 2021.  This dataset provides Hong Kong’s most comprehensive long-term water quality monitoring data and allows an indication of temporal and spatial change in marine water quality in Hong Kong.  Water quality monitoring data from EPD monitoring stations that are located within or close to the Assessment Area were used to provide the baseline water quality conditions of the Assessment Area.  The monitoring results from 2017 to 2021 at the selected monitoring stations are summarized in Table 5.2.  Locations of the selected marine water quality monitoring stations are presented in Figure 5.1.

5.3.2.2       Compliance with the WQOs is generally observed in most parameters at the selected monitoring stations, except for total inorganic nitrogen (TIN) levels at NM3, NM5 and NM6.  According to EPD's Marine Water Quality in Hong Kong in 2021, the overall WQO compliance rate of the North Western WCZ was 89%, with the DO and unionized ammonia nitrogen WQOs fully met.  Under the influence of high background level in the Pearl River Estuary, the compliance rate for TIN WQO was 67%.

Table 5.2         Summary of EPD Routine Water Quality Monitoring Data from Selected Stations within the Assessment Area (2017 – 2021)

Parameter

NM1

NM2

NM3

NM5

NM6

NM8

Temperature (°C)

24.3

24.6

24.3

24.6

24.9

24.7

(16.6-30.8)

(16.7-31.7)

(16.9-31.5)

(16.9-31.5)

(16.6-32.1)

(16.4-32.2)

Salinity (psu)

29.7

28.0

28.0

27.0

25.2

27.2

(22.1-33.5)

(18.1-33.4)

(19.5-33.4)

(19.6-33.3)

(9.8-33.2)

(11.4-33.7)

Dissolved Oxygen

(mg L-1)

5.5

5.6

5.7

5.6

6.0

6.1

(3.5-7.9)

(4.1-7.9)

(4.0-8.3)

(3.5-8.0)

(4.2-8.5)

(4.2-8.8)

Dissolved Oxygen

(mg L-1) - Bottom

5.1

5.5

5.4

5.3

6.0

5.8

(1.8-7.7)

(2.5-7.7)

(2.2-8.2)

(1.8-7.9)

(3.9-8.8)

(2.8-8.6)

Suspended Solids (mg L-1)

9.4

8.6

9.5

11.5

11.1

14.4

(1.6-38.7)

(1.6-35.7)

(1.5-37.3)

(2.2-42.3)

(2.3-45.3)

(2.2-48.7)

5-day Biochemical

Oxygen Demand (mg L-1)

0.7

0.8

0.7

0.7

0.9

0.8

(0.1-2.8)

(0.1-4.9)

(0.2-2.8)

(0.2-2.6)

(0.2-6.4)

(0.2-2.7)

Unionized Ammonia Nitrogen

(mg L-1)

0.003

0.003

0.003

0.003

0.004

0.002

(0.001-0.013)

(0.000-0.009)

(0.000-0.013)

(0.000-0.012)

(0.000-0.043)

(0.000-0.008)

Total Inorganic Nitrogen

(mg L-1)

0.41

0.49

0.52

0.62

0.69

0.48

(0.15-0.80)

(0.13-1.33)

(0.14-1.02)

(0.17-1.22)

(0.12-1.82)

(0.08-1.63)

Orthophosphate

Phosphorus (mg L-1)

0.019

0.019

0.019

0.022

0.021

0.014

(0.007-0.033)

(0.003-0.040)

(0.003-0.039)

(0.003-0.041)

(0.003-0.042)

(0.003-0.039)

Total Phosphorus (mg L-1)

0.05

0.05

0.05

0.06

0.05

0.05

(0.03-0.15)

(0.02-0.24)

(0.03-0.14)

(0.02-0.17)

(0.02-0.12)

(0.02-0.22)

Chlorophyll-a (µg L-1)

3.1

3.6

3.3

3.1

4.5

4.5

(0.5-16.3)

(0.4-22.3)

(0.4-17.7)

(0.4-14.6)

(0.5-26.7)

(0.7-19.2)

Escherichia coli

(cfu/100ml)

142

55

97

225

39

5

(6-2433)

(3-1225)

(5-4367)

(6-4320)

(1-637)

(1-300)

Notes:

1.                Data presented are depth-averaged values calculated by taking the means of three depths, i.e. surface (S), mid-depth (M) and bottom (B), except as specified.

2.                Data presented are annual arithmetic means except for E.  coli, which are geometric means.

3.                Shaded cells indicate non-compliance with the WQOs.

5.3.2.3       In addition, review of water quality impact monitoring data from Three-Runway System (AEIAR-185/2014) (referred as 3RS hereafter) between 2016 and 2022 was undertaken.  With reference to 3RS’s project webpage ([1]), water quality monitoring data at three control stations C1, C2 and C3 as shown in Figure 5.1 were selected to compare the nearest EPD routine water quality monitoring stations NM8, NM5 and NM2, respectively.  Parameters available on 3RS project webpage for comparison include salinity, temperature, pH, DO, turbidity and SS.  3RS impact water quality monitoring data is summarized in Table 5.3. 

Table 5.3         Summary of 3RS Water Quality Monitoring Data from 2016-2022

Parameter

C3

C2

C1

Temperature (°C)

23.9

24.1

23.9

(12.4-31)

(14-31.5)

(13.3-30.8)

Salinity (psu)

28.2

25.9

28

(6.4-34.9)

(1.1-34.5)

(3.4-35.8)

pH

8.03

8.00

8.06

(3.80-8.50)

(3.83-10.90)

(3.00-8.00)

Dissolved Oxygen

(mg L-1)

6.4

6.4

6.7

(2.3-12.8)

(2.3-12.8)

(1.7-13.1)

Dissolved Oxygen

(mg L-1) - Bottom

6.2

6.2

6.4

(2.3-10)

(2.3-10.1)

(1.7-10.8)

Suspended Solids (mg L-1)

6.2

6.9

8.5

(2-49)

(2-60)

(2-922)

Turbidity (NTU)

5.9

8.2

9.4

(3.8-8.5)

(3.8-10.9)

(3.0-8.0)

Notes:

1.                Data presented are depth-averaged values calculated by taking the means of three depths, i.e. surface (S), mid-depth (M) and bottom (B), except as specified.

5.3.3             Marine Sediment Quality

5.3.3.1       Baseline marine sediment quality in the Assessment Area has been determined through a review of EPD routine sediment quality monitoring data collected between 2017 and 2021.  Sediment monitoring data from relevant EPD monitoring stations were used to represent the sediment quality adjacent to the Project (Table 5.4).  Locations of selected sediment quality monitoring stations are presented in Figure 5.1.

5.3.3.2       Sediment quality monitoring data from the EPD monitoring stations were compared with the relevant sediment quality criteria specified in ADV-21 Management Framework for Disposal of Dredged/Excavated Sediment.  The EPD routine sediment quality monitoring data indicate that the contaminant levels in the sediments within the NWWCZ are below Lower Chemical Exceedance Level (LCEL) except for arsenic.  Minor exceedance in LCEL for arsenic was recorded at NS3 and NS6. 

Table 5.4         Summary of EPD Routine Sediment Quality Monitoring Data from Selected Stations within the Assessment Area (2017– 2021)

Parameter

ADV-21 Guideline

NS2

NS3

NS4

NS6

LCEL

UCEL

Arsenic (mg kg-1)

12

42

12.0

12.8

11.1

16.1

(7.7-23.0)

(9.7-15.0)

(8.3-15.0)

(13.0-22.0)

Cadmium (mg kg-1)

1.5

4

<0.1

<0.1

<0.1

<0.1

(<0.1-0.1)

(<0.1-<0.1)

(<0.1-<0.1)

(<0.1-0.1)

Chromium (mg kg-1)

80

160

34.3

31.4

25.0

34.2

(21.0-53.0)

(22.0-47.0)

(17.0-44.0)

(22.0-49.0)

Copper (mg kg-1)

65

110

32.5

28.3

25.6

27.7

(17.0-48.0)

(17.0-37.0)

(16.0-44.0)

(15.0-39.0)

Lead (mg kg-1)

75

110

45.5

39.3

33.9

43.2

(29.0-90.0)

(33.0-48.0)

(25.0-41.0)

(34.0-52.0)

Mercury (mg kg-1)

0.5

1

0.10

0.10

0.12

0.11

(0.06-0.14)

(0.06-0.12)

(0.06-0.54)

(0.06-0.17)

Nickel (mg kg-1)

40

40

20.4

19.0

15.9

21.5

(13.0-31.0)

(13.0-27.0)

(10.0-26.0)

(15.0-27.0)

Silver (mg kg-1)

1

2

<0.2

<0.2

<0.2

<0.2

(<0.2-<0.2)

(<0.2-<0.2)

(<0.2-<0.2)

(<0.2-<0.2)

Zinc (mg kg-1)

200

270

152.9

117.2

116.7

117.2

(79.0-220.0)

(92.0-160.0)

(78.0-200.0)

(82.0-180.0)

Total Polychlorinated Biphenyls (PCBs) (μg kg-1)

23

180

18

18

18

18

(18-18)

(18-18)

(18-18)

(18-18)

Low Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs) (μg kg-1)

550

3,160

<180

<180

<180

<180

(<180-<180)

(<180-224)

(<180-<180)

(<180-200)

High Molecular Weight Polycyclic Aromatic Hydrocarbons (PAHs) (μg kg-1)z

1,700

9,600

69

96

73

50

(41-110)

(<32-200)

(<32-225)

(<32-92)

Chemical Oxygen Demand (mg kg-1)

--

--

11520

13570

13080

11780

(9200-13000)

(6700-17000)

(8800-17000)

(9800-15000)

Total Kjeldahl Nitrogen (mg kg-1)

--

--

442.5

450.0

448.8

433.8

(280.0-540.0)

(380.0-530.0)

(330.0-740.0)

(340.0-570.0)

Notes:

1.                Data presented are arithmetic means average the years.

2.                Underlined values are above the LCEL.  Bold values are above the UCEL.

 

5.3.4             Sediment Quality in Project Area

5.3.4.1       Sediment sampling was collected at five sampling locations in vicinity of the project area where marine works is needed between 1 June 2022 and 21 June 2022 to determine the levels of contaminants in the sediment.  The collected sediment samples were delivered to a laboratory and sediment elutriate test was undertaken to determine the potential of release of sediment-bounded contaminants into the water column upon agitation during maintenance dredging.  For each collected sediment sample, in-situ marine waters were mixed in a sediment-to-water ratio of 1:4 on a volume basis.  The sediment quality results are detailed in Appendix 5.7.  A summary of sediment contaminant levels under elutriate test is provided in Table 5.5.  Results indicated the release of contaminants from sediment was below levels of reporting for all metals and organic pollutants except for arsenic and nickel.


Table 5.5         Summary of Elutriate Test Results for Sediment Collected under this EIA

Boreholes

BHE1

BHE2

BHE3

BHE4

BHD4

 

Parameters

(Unit µg L-1 unless otherwise specified)

Concentration
 in Seawater Blank

Concentration  in Elutriate

Concentration Increase from Elutriation

Concentration
in Seawater Blank

Concentration in Elutriate

Concentration Increase from Elutriation

Concentration
in Seawater Blank

Concentration in Elutriate

Concentration Increase from Elutriation

Concentration
in Seawater Blank

Concentration in Elutriate

Concentration Increase from Elutriation

Concentration
in Seawater Blank

Concentration in Elutriate

Concentration Increase from Elutriation

Max.  Concentration Increase from Elutriation

(a)

(b)

(b)-(a)

(c)

(d)

(d)-(c)

(e)

(f)

(f)-(e)

(g)

(h)

(h)-(g)

(i)

(j)

(j)-(i)

Mercury

<0.05

<0.05

<0.01

<0.05

<0.05

<0.01

<0.05

<0.05

<0.01

<0.05

<0.05

<0.01

<0.05

<0.05

<0.01

<0.01

Arsenic

2

36

34

2

25

23

2

31

29

2

52

50

2

7

5

50

Cadmium

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

<0.1

Chromium

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<0.1

Copper

1.2

<1.0

<0.1

3.0

<1.0

<0.1

1.3

1.3

<0.1

2.0

<1.0

<0.1

1.3

<1.0

<0.1

<0.1

Lead

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<0.1

Nickel

1.1

<1.0

<0.1

1.4

1.1

<0.1

1.0

1.2

0.2

1.2

<1.0

<0.1

1.3

<1.0

<0.1

0.2

Silver

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<1.0

<1.0

<0.1

<0.1

Zinc

<10

<10

<1

<10

<10

<1

<10

<10

<1

<10

<10

<1

<10

<10

<1

<1

Total PCB

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

<0.01

PAHs

<1.60

<1.60

<0.01

<1.60

<1.60

<0.01

<1.60

<1.60

<0.01

<1.60

<1.60

<0.01

<1.60

<1.60

<0.01

<0.01

TBT

<0.015

<0.015

<0.001

<0.015

<0.015

<0.001

<0.015

<0.015

<0.001

<0.015

<0.015

<0.001

<0.015

<0.015

<0.001

<0.001

Ammonia-N (mg/L)

0.06

9.05

8.99

0.03

9.17

9.14

0.05

7.76

7.71

0.07

6.63

6.56

<0.01

0.64

0.64

9.14

Nitrite-N (mg/L)

0.08

0.07

N/A

0.02

0.03

0.01

0.05

0.05

0.00

0.01

0.02

0.01

0.09

0.08

N/A

0.01

Total Kjeldahl Nitrogen (mg/L)

0.4

10.3

9.9

0.3

9.8

9.5

0.4

16.1

15.7

0.3

13.2

12.9

0.4

1.2

0.8

15.7

Note: Please refer to Figure 6.1 of Chapter 6 for the locations of sediment sampling and Appendix 5.7 for the detailed results of the elutriate test.

 


5.3.5             Water Sensitive Receivers

5.3.5.1       The sensitive receivers that may be affected by changes in water quality arising from the Project are identified in accordance with the EIAO-TM and with reference to current land uses and relevant published plans (e.g. relevant Outline Zoning Plans, Development Permission Area Plans, Outline Development Plans and Layout Plans).  For each of the sensitive receivers, established threshold criteria or guidelines have been utilized for establishing the significance of impacts to water quality. 

5.3.5.2       Water Sensitive Receivers (WSRs) in the vicinity of the project elements are identified as below, including coral communities, gazetted and non-gazetted bathing beaches, seawater intakes, typhoon shelter, fish spawning grounds, dolphin habitats, corals / artificial reef, sites of special scientific interest (SSSIs), horseshoe crab habitats, mangrove stands and existing / planned / potential marine park.  For consistencies, all WSRs within the NWWCZ identified in the approved EIA of the Expansion of Hong Kong International Airport into a Three-Runway System (AEIAR-185/2014) (referred as 3RS hereafter) are taken into account in this EIA.  In addition, a number of artificial reefs locations north to the embayment area are also identified as WSRs for this EIA.  The locations of the identified WSRs are listed in Table 5.6 and shown in Figure 5.1.

Table 5.6         Water Sensitive Receivers

Description

Location

Model Output Location

Geodesic Distance from  the Area of Marine Facilities (km)

Geodesic Distance from  the Area of Marine Viaduct (km)

Fisheries Sensitive Receivers

Spawning Grounds for commercial fisheries resources

North Lantau

F1

0.6

3.1

Marine Ecological Sensitive Receivers

Marine Park

Sha Chau and Lung Kwu Chau Marine Park

E1

7.9

9.2

Marine Park

The Brothers Marine Park

E2

3.9

6.4

SSSI

Tai Ho Bay and Tai Ho Stream SSSI

E4

3.8

4.2

SSSI

Tung Chung Bay and San Tau Beach SSSI

E5

3.6

1.2

Horseshoe Crab Habitat

Hau Hok Wan

E6

4.1

2.7

Horseshoe Crab Habitat

Sha Lo Wan

E7

5.0

3.7

Horseshoe Crab Habitat, Mangrove Stand

Sham Wat Wan

E8

7.5

5.7

Horseshoe Crab Habitat, Mangrove Stand

Yam O Wan

E9

7.7

9.3

Artificial Reef and coral communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

7.1

8.0

Coral communities

The Brothers Islands (West Brother)

CR2

2.3

5.0

Coral communities

North of Sheung Sha Chau

CR3

7.4

8.6

Coral communities

Sham Shui Kok (2)

CR4

3.7

5.0

Artificial Reef

HKIA Approach Area

CLK1

1.5

4.1

Artificial Reef

HKIA Approach Area

CLK2

1.2

3.9

Artificial Reef

HKIA Approach Area

CLK3

1.0

3.6

Artificial Reef

HKIA Approach Area

CLK4

1.0

3.6

Artificial Reef

HKIA Approach Area

CLK5

1.2

3.9

Water Sensitive Receivers

Non-gazetted beach

Lung Kwu Sheung Tan

B1

9.9

12.3

Non-gazetted beach

Lung Tsai / Lung Kwu Tan

B2

8.1

10.5

Gazetted Beach

Butterfly Beach

B3

6.4

9.1

Gazetted Beach

Cafeteria New Beach

B4

7.5

10.2

Gazetted Beach

Golden Beach

B5

7.4

10.1

Gazetted Beach

Castle Peak Beach

B6

7.8

10.5

Gazetted Beach

Kadoorie Beach

B7

7.6

10.3

Gazetted Beach

Cafeteria Old Beach

B8

7.6

10.3

Seawater Intake

Castle Peak Power Station Cooling Water Intake

C1

6.8

9.1

Seawater Intake

Cooling Water Intake for Shiu Wing Steel Mills

C2

5.8

8.1

Seawater Intake

WSD Seawater Intake at Tuen Mun

C3

6.5

9.2

Seawater Intake

Proposed Lok On Pai Intake (Pumping Station)

C4

7.3

9.9

Seawater Intake

Future Seawater Intake Point for Sunny Bay

C5

8.7

10.6

Seawater Intake

Proposed Ta Pang Po Intake (Pumping Station)

C6

6.4

8.1

Seawater Intake

Future Seawater Intake Point for Tung Chung East

C8

1.5

2.0

Seawater Intake

Hong Kong Port (HKP) Intake

C9

0.5

3.2

Seawater Intake

Cooling Water Intake at Hong Kong International Airport (HKIA) North

C10

1.0

3.2

Seawater Intake

Future Seawater Intake at HKIA East

C11

2.4

4.1

Seawater Intake

Seawater Intake at Tung Chung

C12

2.4

0.1

Seawater Intake

Cooling Water Intake at HKIA South

C13

3.3

2.0

Seawater Intake

  Cooling Seawater Intake Point for SKYCITY

C14

0.0

2.7

Seawater Intake

Light Rail Transit (LRT) Tuen Mun Ferry Pier Terminus

C15

6.5

9.2

Seawater Intake

Tuen Mun Hospital

C16

7.2

9.9

Seawater Intake

Sam Shing Estate

C17

7.7

10.4

Seawater Intake

China Cement Plant

C18

6.3

8.6

Typhoon Shelter

Tuen Mun

T1

7.0

9.7

Typhoon Shelter

Gold Coast Marina

B5

7.4

10.1

Observation Points

Boundary of Marine Park

The Brothers Marine Park

M9

2.6

4.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10a

11.0

12.6

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10b

10.1

12.0

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10c

7.5

7.8

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10d

6.3

7.0

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10e

5.3

6.4

Boundary of Marine Park

Proposed North Lantau Marine Park

M11a

6.7

5.7

Boundary of Marine Park

Proposed North Lantau Marine Park

M11b

5.7

5.0

Boundary of Marine Park

Proposed North Lantau Marine Park

M11c

0.9

3.6

Notes:

1.                        Sham Shui Kok was included as a dolphin habitat WSRs due to high Chinese White Dolphin (CWD) activities in the past.  According to more recent Marine Mammal Monitoring Reports by AFCD (Available at: https://www.afcd.gov.hk/english/conservation/con_mar/con_mar_chi/con_mar_chi_chi/con_mar_chi_chi.html), Sham Shui Kok is no longer a hotspot for CWD activities since 2012.  Thus, Sham Shui Kok is not included as CWD WSR under this EIA.

2.                        The entire coastline of North Lantau is covered with scattered coral communities.  For this EIA, CR4 at Sham Shui Kok is selected as representative locations for the coral along the coastline of North Lantau.

 

5.3.5.3       Note that there are some other WSRs, such as secondary contact recreation subzones and Chinese White Dolphin habitat cover large swath of marine waters in HK.  No separate observation points would be set for these WSRs.  Instead, these WSRs are represented by observation points of other WSRs within their area.  Secondary contact recreation subzones near the Project site are represented by observation points B1 to B7 and CR1 while Chinese White Dolphin are represented by observation points E1 and E2.

5.4                   Assessment Criteria

5.4.1             General

5.4.1.1       The following sections explain the derivation of relevant assessment criteria for suspended solids, dissolved oxygen, total inorganic nitrogen, unionized ammonia nitrogen, heavy metals and trace organic contaminants, which are all parameters that can be directly affected by the operational phase maintenance dredging operation and typically assessed in past EIA modelling exercise for marine works such as AEIAR-241/2022 New Contaminated Sediment Disposal Facility to the West of Lamma Island.  Other less relevant water quality parameters which were not assessed are therefore not included in the following sections.

5.4.2             Suspended Solids

5.4.2.1       Elevation in suspended solids (SS) concentrations resulting from the Project’s construction and operational activities will be assessed against the WQO.  The WQO for SS is defined as not to raise the natural ambient level by 30%, nor cause the accumulation of SS which may adversely affect aquatic communities.  The assessment criterion is hence defined as the WQO allowable increase in SS concentrations within the corresponding WCZs.

5.4.2.2       SS data from EPD’s routine water quality monitoring programme from 2017 to 2021 have been analysed to determine the WQO allowable SS increase at the WSRs.  This is calculated as 30% of the ambient level (90th percentile value) from the 2017 to 2021 baseline marine water quality data.  For each WSR, ambient level was derived from the closest EPD water quality monitoring station.  The assessment criterion for SS at each WSR is summarized in Table 5.7.

5.4.2.3       Coral communities have been identified within the Assessment Area.  There is no established legislative criteria for water quality for corals.  For this Study, SS elevation at these coral WSRs, their corresponding WQO standards of SS (30% increase) is derived (Table 5.7) and adopted in this EIA, following criterion of previously approved EIA reports for assessing SS impacts on corals, including Expansion of Hong Kong International Airport into a Three-Runway System (Register No. AEIAR-185/2014) and New Contaminated Sediment Disposal Facility to the West of Lamma Island (Register No. AEIAR-241/2022).


 

Table 5.7         Allowable Increase in SS (mg L-1) Levels for Water Sensitive Receivers and Observation Points

Description

Location

Model Output Location

EPD Station

Relevant Depth

Dry Season

Wet Season

(Ambient Level) (1)

(WQO Allowable Change)

(Ambient Level) (1)

(WQO Allowable Change)

Fisheries Sensitive Receivers

Spawning Grounds for commercial fisheries resources

Spawning Grounds for commercial fisheries resources in North Lantau

F1

NM6

Depth-averaged

28.7

8.6

17.2

5.2

Marine Ecological Sensitive Receivers

Marine Park

Sha Chau and Lung Kwu Chau Marine Park

E1

NM6

Depth-averaged

28.7

8.6

17.2

5.2

Marine Park

The Brothers Marine Park

E2

NM2

Depth-averaged

19.7

5.9

13.3

4.0

SSSI

Tai Ho Bay and Tai Ho Stream SSSI

E4

NM2

Depth-averaged

19.7

5.9

13.3

4.0

SSSI

Tung Chung Bay and San Tau Beach SSSI

E5

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Horseshoe Crab Habitat

Hau Hok Wan

E6

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Horseshoe Crab Habitat

Sha Lo Wan

E7

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Horseshoe Crab Habitat, Mangrove Stand

Sham Wat Wan

E8

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Horseshoe Crab Habitat, Mangrove Stand

Yam O Wan

E9

NM1

Depth-averaged

17.3

5.2

14.9

4.5

Artificial Reef and Coral Communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

NM6

Bottom

30.0

9.0

17.7

5.3

Coral Communities

The Brothers Islands (West Brother)

CR2

NM3

Bottom

22.8

6.8

19.6

5.9

Coral Communities

North of Sheung Sha Chau

CR3

NM6

Bottom

30.0

9.0

17.7

5.3

Coral Communities

Sham Shui Kok

CR4

NM2

Bottom

28.0

8.4

19.1

5.7

Artificial Reef

HKIA Approach Area

CLK1

NM3

Bottom

22.8

6.8

19.6

5.9

Artificial Reef

HKIA Approach Area

CLK2

NM3

Bottom

22.8

6.8

19.6

5.9

Artificial Reef

HKIA Approach Area

CLK3

NM3

Bottom

22.8

6.8

19.6

5.9

Artificial Reef

HKIA Approach Area

CLK4

NM3

Bottom

22.8

6.8

19.6

5.9

Artificial Reef

HKIA Approach Area

CLK5

NM3

Bottom

22.8

6.8

19.6

5.9

Water Sensitive Receivers

Non-gazetted beach

Lung Kwu Sheung Tan

B1

NM5

Depth-averaged

22.3

6.7

19.6

5.9

Non-gazetted beach

Lung Tsai / Lung Kwu Tan

B2

NM5

Depth-averaged

22.3

6.7

19.6

5.9

Gazetted Beach

Butterfly Beach

B3

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Gazetted Beach

Cafeteria New Beach

B4

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Gazetted Beach

Gold Coast Marina / Golden Beach

B5

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Gazetted Beach

Castle Peak Beach

B6

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Gazetted Beach

Kadoorie Beach

B7

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Gazetted Beach

Cafeteria Old Beach

B8

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Seawater Intake

Castle Peak Power Station Cooling Water Intake

C1

NM5

Depth-averaged

22.3

6.7

19.6

5.9

Seawater Intake

Cooling Water Intake for Shiu Wing Steel Mills

C2

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

WSD Seawater Intake at Tuen Mun (2)

C3

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Seawater Intake

Proposed Lok On Pai Intake (Pumping Station)

C4

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Seawater Intake

Future Seawater Intake Point for Sunny Bay

C5

NM1

Depth-averaged

17.3

5.2

14.9

4.5

Seawater Intake

Proposed Ta Pang Po Intake (Pumping Station)

C6

NM1

Depth-averaged

17.3

5.2

14.9

4.5

Seawater Intake

Future Seawater Intake Point for Tung Chung East

C8

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

HKP Intake

C9

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

Cooling Water Intake at HKIA North

C10

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

Future Seawater Intake at HKIA East

C11

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

Seawater Intake at Tung Chung

C12

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

Cooling water Intake at HKIA South

C13

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Seawater Intake

Cooling Seawater Intake Point for SKYCITY 

C14

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Seawater Intake

LRT Tuen Mun Ferry Pier Terminus

C15

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Seawater Intake

Tuen Mun Hospital

C16

NM2

Depth-averaged

28.0

8.4

19.1

5.7

Seawater Intake

Sam Shing Estate

C17

NM2

Depth-averaged

28.0

8.4

19.1

5.7

Seawater Intake

China Cement Plant

C18

NM5

Depth-averaged

22.0

6.6

36.1

10.8

Typhoon Shelter

Tuen Mun

T1

NM2

Depth-averaged

19.7

5.9

13.3

4.0

Observation Points

Boundary of Marine Park

The Brothers Marine Park

M9

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10a

NM5

Depth-averaged

22.3

6.7

19.6

5.9

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10b

NM5

Depth-averaged

22.3

6.7

19.6

5.9

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10c

NM6

Depth-averaged

28.7

8.6

17.2

5.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10d

NM6

Depth-averaged

28.7

8.6

17.2

5.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10e

NM6

Depth-averaged

28.7

8.6

17.2

5.2

Boundary of Marine Park

Proposed North Lantau Marine Park

M11a

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Boundary of Marine Park

Proposed North Lantau Marine Park

M11b

NM8

Depth-averaged

42.0

12.6

23.8

7.1

Boundary of Marine Park

Proposed North Lantau Marine Park

M11c

NM3

Depth-averaged

20.0

6.0

15.7

4.7

Notes:

1.             Ambient level is calculated as 90th percentile of the EPD routine water quality monitoring data (2017-2021) at respective EPD station close to the WSRs.

2.             It should be noted that the background level SS concentrations recorded at NM2 already exceeds the WSD’s SS criterion of 10 mg L-1.  For WSD intake WSRs where baseline SS levels exceed 10 mg L-1, WQO criterion of elevation not exceeding 30% of the ambient level would be adopted.

5.4.2.4       For seawater intake WSRs, the Water Supplies Department (WSD) has a set of standards for the quality of abstracted seawater.  The corresponding water quality criteria for WSD seawater intakes are presented in Table 5.8.  

5.4.2.5       The two nearest seawater intakes located within the embayment between the Airport Island and the HKP Island (C9 and C14) are both seawater intakes for cooling water (i.e. not WSD intakes) and are not known to be very sensitive to SS elevation.  For this EIA, water quality impact assessment would be based on the corresponding WQO criterion of elevation not exceeding 30% of the ambient level, following the similar approach adopted in the nearby approved EIA of 3RS.

Table 5.8         WSD’s Water Quality Criteria for Water at Seawater Intakes

Parameter

Criterion

Colour (HU)

< 20

Turbidity (NTU)

< 10

Threshold Odour No.

< 100

Ammoniacal Nitrogen (mg L-1)

< 1

Suspended Solids (mg L-1)

< 10

Dissolved Oxygen (mg L-1)

> 2

5-day Biochemical Oxygen Demand (mg L-1)

< 10

Synthetic Detergents (mg L-1)

< 5

E.  coli (cfu/100mL)

< 20,000

 

5.4.3             Dissolved Oxygen

5.4.3.1       Dissolved oxygen (DO) depletion resulting from the Project’s construction and operational activities will be assessed against the WQO.  The assessment criterion is defined as the WQO allowable changes in dissolved oxygen (DO) levels at the WSRs.  The depletion of DO in the water column is not expected to affect the operation of seawater intakes; therefore, no assessment criteria for seawater intake WSRs are identified, except for WSD intakes where the WSD DO criterion is adopted (i.e. C3).  For the purpose of assessment under this EIA Study, the WQO criterion for DO is applied for these non-WSD seawater intakes (i.e. C1, C2, C4 to C18).

5.4.3.2       DO data from EPD’s routine water quality monitoring programme from 2017 to 2021 have been analyzed to determine WQO allowable changes in DO levels at the WSRs.  Allowable DO change is calculated as the ambient DO level minus the WQO, i.e. 4 mg L-1 for depth-averaged, surface and middle layers, and 2 mg L-1 for bottom layer.  Ambient level is calculated as the 10th percentile value from the 2017 to 2021 marine water quality data.  For each WSR, ambient level was derived from the closest EPD water quality monitoring station.  The assessment criterion for DO at each WSR is summarized in Table 5.9.  Note that the WQO criterion for DO is specifically based on “90% of the sampling occasions during the whole year”, therefore, the assessment criterion adopted under this Study was also based on the annual 10th-percentile.

Table 5.9         Allowable DO Depletion (mg L-1) for Water Sensitive Receivers and Observation Points

Description

Location

Model Output Location

EPD Station

Relevant Depth

Annual Ambient Level (1)

Annual WQO Allowable Change

Spawning Grounds  for commercial fisheries resources

Spawning Grounds  for commercial fisheries resources in North Lantau

F1

NM6

Depth-averaged

4.70

0.7

Marine Park

Sha Chau and Lung Kwu Chau Marine Park

E1

NM6

Depth-averaged

4.70

0.7

Marine Park

The Brothers Marine Park

E2

NM2

Depth-averaged

4.45

0.5

SSSI

Tai Ho Bay and Tai Ho Stream SSSI

E4

NM2

Depth-averaged

4.45

0.5

SSSI

Tung Chung Bay and San Tau Beach SSSI

E5

NM8

Depth-averaged

4.59

0.6

Horseshoe Crab Habitat

Hau Hok Wan

E6

NM8

Depth-averaged

4.59

0.6

Horseshoe Crab Habitat

Sha Lo Wan

E7

NM8

Depth-averaged

4.59

0.6

Horseshoe Crab Habitat, Mangrove Stand

Sham Wat Wan

E8

NM8

Depth-averaged

4.59

0.6

Horseshoe Crab Habitat, Mangrove Stand

Yam O Wan

E9

NM1

Depth-averaged

4.17

0.2

Artificial Reef and Coral Communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

NM6

Bottom

4.50

2.5

Coral Communities

The Brothers Islands (West Brother)

CR2

NM3

Bottom

3.50

1.5

Coral Communities

North of Sheung Sha Chau

CR3

NM6

Bottom

4.50

2.5

Coral Communities

Sham Shui Kok

CR4

NM2

Bottom

3.66

1.7

Artificial Reef

HKIA Approach Area

CLK1

NM3

Bottom

3.50

1.5

Artificial Reef

HKIA Approach Area

CLK2

NM3

Bottom

3.50

1.5

Artificial Reef

HKIA Approach Area

CLK3

NM3

Bottom

3.50

1.5

Artificial Reef

HKIA Approach Area

CLK4

NM3

Bottom

3.50

1.5

Artificial Reef

HKIA Approach Area

CLK5

NM3

Bottom

3.50

1.5

Non-gazetted beach

Lung Kwu Sheung Tan

B1

NM5

Depth-averaged

4.23

0.2

Non-gazetted beach

Lung Tsai / Lung Kwu Tan

B2

NM5

Depth-averaged

4.23

0.2

Gazetted Beach

Butterfly Beach

B3

NM2

Depth-averaged

4.45

0.5

Gazetted Beach

Cafeteria New Beach

B4

NM2

Depth-averaged

4.45

0.5

Gazetted Beach

Gold Coast Marina / Golden Beach

B5

NM2

Depth-averaged

4.45

0.5

Gazetted Beach

Castle Peak Beach

B6

NM2

Depth-averaged

4.45

0.5

Gazetted Beach

Kadoorie Beach

B7

NM2

Depth-averaged

4.45

0.5

Gazetted Beach

Cafeteria Old Beach

B8

NM2

Depth-averaged

4.45

0.5

Seawater Intake

Castle Peak Power Station Cooling Water Intake

C1

NM5

Depth-averaged

4.23

0.2

Seawater Intake

Cooling Water Intake for Shiu Wing Steel Mills

C2

NM3

Depth-averaged

4.32

0.3

Seawater Intake

WSD Seawater Intake at Tuen Mun

C3

NM2

Depth-averaged

4.45

2.5

Seawater Intake

Proposed Lok On Pai Intake (Pumping Station)

C4

NM2

Depth-averaged

4.45

0.5

Seawater Intake

Future seawater Intake Point for Sunny Bay

C5

NM1

Depth-averaged

4.17

0.2

Seawater Intake

Proposed Ta Pang Po Intake (Pumping Station)

C6

NM1

Depth-averaged

4.17

0.2

Seawater Intake

Future seawater Intake Point for Tung Chung East

C8

NM3

Depth-averaged

4.32

0.3

Seawater Intake

HKP Intake

C9

NM3

Depth-averaged

4.32

0.3

Seawater Intake

Cooling Water Intake at HKIA North

C10

NM3

Depth-averaged

4.32

0.3

Seawater Intake

Future Seawater Intake at HKIA East

C11

NM3

Depth-averaged

4.32

0.3

Seawater Intake

Seawater Intake at Tung Chung

C12

NM3

Depth-averaged

4.32

0.3

Seawater Intake

Cooling Water Intake at HKIA South

C13

NM8

Depth-averaged

4.59

0.6

Seawater Intake

Cooling Seawater Intake Point for SKYCITY 

C14

NM3

Depth-averaged

4.32

0.3

Seawater Intake

LRT Tuen Mun Ferry Pier Terminus

C15

NM2

Depth-averaged

4.45

0.5

Seawater Intake

Tuen Mun Hospital

C16

NM2

Depth-averaged

4.45

0.5

Seawater Intake

Sam Shing Estate

C17

NM2

Depth-averaged

4.45

0.5

Seawater Intake

China Cement Plant

C18

NM5

Depth-averaged

4.23

0.2

Typhoon Shelter

Tuen Mun

T1

NM2

Depth-averaged

4.45

0.5

Boundary of Marine Park

The Brothers Marine Park

M9

NM3

Depth-averaged

4.32

0.3

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10a

NM5

Depth-averaged

4.23

0.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10b

NM5

Depth-averaged

4.23

0.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10c

NM6

Depth-averaged

4.70

0.7

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10d

NM6

Depth-averaged

4.70

0.7

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10e

NM6

Depth-averaged

4.70

0.7

Boundary of Marine Park

Proposed North Lantau Marine Park

M11a

NM8

Depth-averaged

4.59

0.6

Boundary of Marine Park

Proposed North Lantau Marine Park

M11b

NM8

Depth-averaged

4.59

0.6

Boundary of Marine Park

Proposed North Lantau Marine Park

M11c

NM3

Depth-averaged

4.32

0.3

Notes:

1.                    Ambient level is calculated as 10th percentile of the EPD routine water quality monitoring data (2017-2021) at respective EPD station close to the WSRs.

 

 

5.4.4             Sediment Deposition

5.4.4.1       Impacts to artificial reefs and corals will be assessed with regards to sediment deposition.  The assessment criterion of 200 g m-2 day-1, which represents an indicative level above which could result in moderate to severe impact on corals, has been used in approved EIA Reports ([2])([3]) and has been adopted here.

5.4.5             Nutrients

5.4.5.1       Elevation in the levels of nutrients as a result of the Project’s construction activities, if any, will be compared against the respective WQOs (Table 5.1 refers).

5.4.6             Dissolved Metals and Organics Contaminants

5.4.6.1       Assessment of dissolved metals and organics contaminants will be conducted based on the assessment criteria presented in Table 5.10.  These criteria are applicable to all WSRs except for seawater intakes which are not deemed sensitive to change in these contaminants levels.

Table 5.10       Summary of Assessment Criteria for Dissolved Metals and Organic Contaminants

Parameter

Unit

Assessment Criteria Adopted

Metals

 

 

Cadmium (Cd)

mg L-1

5.5 (1)

Chromium (Cr)

mg L-1

4.4 (1)

Copper (Cu)

mg L-1

1.3 (1)

Nickel (Ni)

mg L-1

70 (1)

Lead (Pb)

mg L-1

4.4 (1)

Zinc (Zn)

mg L-1

8 (1)

Mercury (Hg)

mg L-1

0.4 (1)

Arsenic (As)

mg L-1

13 (1)

Silver (Ag)

mg L-1

1.4 (1)

PAHs

Total PAHs

mg L-1

0.2 (2)

PCBs

 

 

Total PCBs

mg L-1

0.03 (2)

Organotins

 

 

Tributyltin (TBT)

mg L-1

0.006 (2)

Notes:

(1)        Australian and New Zealand Guidelines for Fresh and Marine Water Quality.  Default guideline value for protection for 95% Species in Marine water.  Available at: https://www.waterquality.gov.au/anz-guidelines/guideline-values/default/water-quality-toxicants/search
For chromium, the more stringent standard for Cr(VI) is adopted.  For arsenic, there is no standard for marine water, standard for freshwater for As(V) was thus adopted which is more conservative than that for As(III).

(2)       U.S.  Environmental Protection Agency, National Recommended Water Quality Criteria, 2009.  (https://www.epa.gov/wqc/national-recommended-water-quality-criteria-aquatic-life-criteria-table).  The Criteria Continuous Concentration (CCC) is an estimate of the highest concentration of a material in surface water (ie saltwater) to which an aquatic community can be exposed indefinitely without resulting in an unacceptable effect.  CCC is used as the criterion of the respective compounds in this study.

5.5                   Assessment Methodology

5.5.1.1       The methodology employed to assess potential water quality impacts associated with the construction and operation of the Project is presented in the Working Paper on Water Quality Modelling Plan (Appendix 5.1) and has been based on the information presented in the Project Description (Section 2).  Full details of the scenarios examined in the modelling works and the uncertainties in various aspects of the modelling assessment are provided in Working Paper on Water Quality Modelling Plan (Appendix 5.1).  Verification of hydrodynamic model has been provided in Appendix 5.1.  The WSRs assessed are presented in Figure 5.1.

5.6                   Potential Sources of Impact

5.6.1.1       The key construction and operation activities of the Project are discussed in Sections 2.7 and 2.8.  Potential sources of impacts to water quality arising from the Project may occur during both construction and operation activities, including:

5.6.2             Construction Phase:

·          Marine construction works including piling for marine facilities and marine viaduct;

·          Construction site runoff and wastewater generated from land-based activities; and

·          Generation of wastewater and sewage from workforce

5.6.3             Operational Phase:

·        Change in flow regime due to presence of floating structure and bridge piles which may affect the water quality in the bay area;

·        Change in water quality due to maintenance dredging (SS elevation and increased sedimentation, dissolved oxygen depletion and release of sediment-bounded nutrients);

·        Generation of wastewater, sewage from staff, visitors etc.;

·        Potential oil spillage associated with the operation of the vessels; and

·        Generation of road runoff

5.7                   Impact Assessment - Construction Phase

5.7.1             Sediment Disturbance and Wastewater generated from Marine-Based Construction Activities

5.7.1.1       As discussed in Section 2.7, there will not be any open sea dredging for construction phase.  The construction of marine viaduct section would involve the installation of 4 set of piers (3 piles for each set, totalled 12 piles, each with diameter of about 1.8 m) across the Tung Chung Navigation Channel (Appendix 5.6 referred).  After installation of silt curtain(s) to surround the active marine works area for the marine viaduct, a temporary working platform that sits on support casings (with or without reinforcing by mini-piles) would be installed.  The support casings will be positioned to the seabed by vibratory hammer from a barge.  Such operation is expected to result in limited level of localized disturbance to bottom sediment, particularly when controlled by the surrounding silt curtain.  In case mini-piles support is needed, the temporary support casings will be lowered until reaching the rock head until rock socket is formed.  After securing the support casings, a temporary working platform would be installed on top of the casings and all subsequent piling works would be conducted by piling plants on top of the temporary working platform.  Bored piling for the marine viaduct crossing the Tung Chung Navigation Channel would be conducted with the silt curtain remains in place.  At most two marine piles will be installed/ constructed concurrently at the viaduct works area across Tung Chung Navigation Channel during the construction phase.  Bored piling would be undertaken inside steel casing within silt curtain, which effectively contains sediment loss from the process.  Illustrative diagram of steel casing with silt curtain is shown in Exhibit 5.1.  Figure 2.5(a) shows the detailed work arrangements for marine works marine viaduct as well as the associated use of silt curtain.  After the installation bored piles, the rest of the pile installation would be conducted in dry environment within precast pier shell, and thus would not result in any direct water quality impact.  The locations and configurations of marine piles under this Project are show in Exhibit 5.2, Exhibit 5.3, Exhibit 5.4and Appendix 5.6.  Given the small scale of works (no open dredging, maximum two concurrent pile installation) and the use of silt curtain for sediment control, the potential disturbance of bottom sediment is expected to be limited and thus no unacceptable water quality impact from the proposed marine construction works for the marine viaduct would be expected.


 

Exhibit 5.1       Steel Casing Installation with Silt Curtain

Diagram

Description automatically generated

Note: This cross-sectional view has been simplified for clarity and is not to scale.


 

Exhibit 5.2       Design of Wave Attenuator

A picture containing diagram

Description automatically generated

 

Chart

Description automatically generated


Exhibit 5.3       Indicative Pile Locations for SkyPier (Option MF-B)

Diagram

Description automatically generated


Exhibit 5.4       Indicative Pile Locations for Berthing Area (Option MF-B)

Text Box: Wave AttenuatorDiagram

Description automatically generated


5.7.1.2       Similar to the case of marine construction at the marine viaduct, marine construction works for the marine facilities would only commence after the installation of silt curtain surrounding the corresponding works area.  For the marine facilities, there will be around 99 piles (about 0.6 m diameter) for the wave attenuator, around 8 piles (about 0.6 m diameter) for the SKYCITY Pier and about 118 piles for the berthing area (about 0.6 m diameter).  The floating pontoon (for both SKYCITY Pier and the floating platforms of the berthing facilities) as well as the wave attenuator would be installed using temporary working platform (illustrated in Figure 2.5(e)).  The temporary working platform will be erected and assembled at piling locations by deploying derrick lighter/ crane barge.  Foundation piles and guide piles for supporting or anchoring of the marine facilities will be driven into seabed/rockhead level by piling machine.  The pontoons for the floating platforms of the marine facilities and for the SKYCITY Pier will be constructed at an existing fabrication yard outside of Hong Kong, and will arrive at the project site via marine access, and then be lifted and secured by segment with guide piles by derrick lighter / crane barge.  For the SKYCITY PIER and wave attenuator, the pile casings will first be sunk down to the bed rock using drilling rig on the temporary working platform, then the socketed H-piles will be installed by crane barge, followed up the construction of the superstructure on top.  At most two marine piles will be installed/ constructed concurrently at the proposed marine facilities work area during the construction phase.  No open sea dredging will be involved in either case.  These works may result in minor disturbance to the bottom sediment and temporary localized elevation of turbidity which subside in a short period of time.  Figure 2.5(e) shows the detailed work arrangements for marine works for marine facilities as well as the associated use of silt curtain.  Given the small scale of works (no open sea dredging, maximum two concurrent pile installation) and the use of silt curtain for sediment control, the potential disturbance of bottom sediment is expected to be limited and thus no unacceptable water quality impact from the proposed marine construction works for the marine facilities would be expected.

5.7.1.3       Good site practices listed under Section 5.9.1 should be implemented to minimize risk of potential water quality impact from marine construction works.

5.7.2             Construction Site Runoff and Wastewater generated from Land-Based Construction Activities

5.7.2.1       Construction site runoff would be generated from runoff of earth working area and stockpiles, wastewater from dust suppression sprays and wheel washing facilities and wastewater from concrete washings and other grouting materials.  These surface runoff contains high concentration of suspended solids, which would cause potential blockage of drainage channels and increase in suspended solids and turbidity levels in the WSRs in vicinity of the project area.  Mitigation measures listed under Section 5.9 should be implemented to minimize the risk of potential water quality impact from construction site runoff and wastewater generated from land-based works.  No unacceptable impacts on water quality is anticipated with the implementation of appropriate measures.

5.7.3             Wastewater and Sewage generated from Workforce

5.7.3.1       Sewage will arise from the construction workforce and site office’s sanitary facilities.  Suitable sanitary facilities such as chemical toilets will be provided onsite.  These chemical toilets would be regularly maintained, cleaned and emptied by licensed contractor for off-site disposal to avoid any environmental nuisance.  No onsite discharge from these chemical toilets nor from construction work vessel would be allowed.  Therefore, no unacceptable water quality impacts to sensitive receivers are anticipated.

5.8                   Impact Assessment - Operational Phase

5.8.1             Change in Flow Regime due to Presence of Floating Structure and Viaduct Piers

5.8.1.1       The presence of viaduct piers across the Tung Chung Navigation Channel under this Project is expected to result in increased drag across the channel.  Similarly, the proposed development of berthing facilities within the embayment between the Airport Island and HKP Island requires the installation of piles as well as wave attenuator, which could slow down current to allow safe navigation and mooring.  These project elements would affect flow regime in the proximity and was required to be assessed in the EIA Study Brief for this Project.  For this EIA, a modelling exercise has been conducted to estimate the change in flow regime in the surrounding with the presence of project elements.

5.8.1.2       Fixed wave attenuator would be provided at the south-western corner of the embayment between the Airport Island and HKP Island.  Based on the latest design information, the fixed wave attenuator covers the water column approximately from about -2.7mPD up to +6mPD at the most shallow end close to the Airport Island, leaving about 0.9m of the water column near seabed unobstructed.  At the deepest end of the wave attenuator, it covers the water column approximately from about   -3.5mPD up to +6mPD, leaving about 1.5m of the water column near seabed unobstructed.  Horizontally, the fixed wave attenuator have a total length of approximately 290m.  Design of the wave attenuator is shown in Exhibit 5.2 below.  There are also other small piles for various facilities under this Project, including the SKYCITY Pier (indicative pile locations shown in Exhibit 5.3), berthing facilities (indicative pile locations shown in Exhibit 5.4) under this Project which would also affect the hydrodynamic within the embayment and have been taken into account in the modelling exercise.

5.8.1.3       Note that there is potential option of floating wave attenuator ([4]), where the wave-attenuating floats on the top layer of the water column to block off wave but not the majority of the circulation.  Preliminary design information indicated the floating wave attenuator would about 3 m thick vertically, and with 70 cm freeboard and 2.3 m of submerged part to block off wave energy.  This means the blocked off part of the water column is significantly less than that of the fixed wave attenuator option.  Comparison of blocked off part of the water column by fixed and floating wave attenuator is given in the lower part of Exhibit 5.2.  As shown, the fixed wave attenuator would block off more of the water column when compared with it floating counterpart.  Thus the adoption of fixed wave attenuator is the worst case scenario for conservative assessment under this Study. Note that while maintenance dredging would likely be required during operation in the proposed marine facilities, the scope of maintenance dredging would be to maintain the seabed level within the area of marine facilities at about the current level.  It is because the current seabed level provides enough depth for the designated type of marine vessels to operate.  Based on the latest design information, maintenance dredging would only be required if siltation within the area of marine facilities result in seabed level above the level shown in Exhibit 5.5 below and the maintenance dredging would only restore the seabed level to the current level.


Exhibit 5.5       Threshold Seabed Level for Triggering Maintenance Dredging

5.8.1.4       Two modelling scenarios have been conducted as described as scenarios O1 and O2 in the Working Paper (Appendix 5.1).  Scenario O1 represents the baseline scenario in the future horizon which takes into account major completed reclamation in the model domain (including the Third Runway development of the HKIA, Tung Chung New Town East development, Road P1, Sunny Bay and Lung Kwu Tan) as well as existing and future bridges near the Project (including the traffic bridges of the North Lantau Express Highway and Chek Lap Kok South Road, as well as the SkyPier Terminal Bonded Bridge and Airportcity Link).  In addition to the reclamation and bridges considered in scenario O1, scenario O2 takes into account project elements which have notable effect on the flow regime, including the bridge piers (consists of 4 sets of 3 piles of 1.8m in diameter, i.e. totalled 12) of the proposed marine viaduct at the Tung Chung Navigation Channel, the proposed fixed wave attenuator (and 99 no. of associated piles; fixed wave attenuator assessed for conservative reason) as well as other smaller piles for proposed SKYCITY Pier (8 piles each about 0.6 m in diameter), and berthing facilities (118 piles each about 0.6 m in diameter, including gangway).  Appendix 5.5 detailed the considerations for incorporation of existing and proposed piles, proposed wave attenuator and box culverts around the marine facilities and marine viaducts under this Project.  The predicted tidal discharge at a number of selected major cross sections under both scenarios are estimated and compared to demonstrate the potential change in flow regime as a result of the proposed marine viaduct across the Tung Chung Navigation Channel, and the embayment between the Airport Island and the HKP.  Exhibit 5.6 shows the locations of the selected major cross sections.  A summary of tidal discharge across these cross sections is provided in Table 5.11.  Percentile distribution plots for tidal discharge across major cross sections are presented in Table 5.12. Time series plot for instantaneous tidal discharges across these cross sections are presented in Table 5.13.  As shown, the change in tidal discharge between baseline scenario and project scenario at the west and south of Airport, Tung Chung and Urmston midway were small, except the east of Airport where it is located at the opening of the embayment.  This shows that the proposed ATCL marine viaduct across the Tung Chung Navigation Channel as well as the proposed berthing facilities would have limited impact on the flow regime at the farther regime of the western waters, including the Urmston Road to the north of the Project, as well as the Tung Chung Bay and the Tung Chung Navigation Channel.  The highest changes among these 4 cross sections is predicted under flood tide of dry season, where increase up to 1.2% was predicted.  The predicted changes at other cross sections under other season and tide condition are even lower.  Unacceptable change in flow regime from the Project during operation on these areas was not expected.  The change of tidal discharge across the cross section of Airport East is notable, particularly for the flooding tide.  It is because the cross section is relatively small and its tidal flow is not symmetric, i.e. water flow southward predominantly regardless of tide.  This means a substantially weaker and shorter time for northward flow (consistent with typical flooding current direction), thus resulting in a more notable percentage changes because of the smaller average tidal discharge.  As shown in Table 5.13, the model prediction shows that the Project does not materially alter the flow regime in terms of phase and direction of the tidal flow.  Given the embayment itself is highly developed and serves mostly navigational and industrial (i.e. cooling) purposes, such changes is not expected to be of unacceptable impact to these identified beneficial uses.  Exhibit 5.7 shows the predicted water temperature at the existing seawater intake at C9 (of the HKP) for HKP ([5]).  As shown, no notable deviation of water temperature at C9 was predicted under the baseline and project scenarios in both seasons.  The predicted changes in water temperature would be below 0.1°C, which is insignificant, well below the corresponding WQO criterion of 2°C and would not have any substantial impact on the corresponding beneficial use.


Exhibit 5.6       Indicative Locations for the Major Cross Section shown in Black Line, Green Dots indicates Project Elements that could Affect Flow Regime

Table 5.11       Predicted Tidal Discharge across Major Cross Sections

Cross Section

 Tide Condition

Dry Season

Wet Season

Scenario O1

Scenario O2

Scenario O1

Scenario O2

Average Discharge (m3 s-1)

Average Discharge (m3 s-1)

Change (m3 s-1)

% Change

Average Discharge (m3 s-1)

Average Discharge (m3 s-1)

Change (m3 s-1)

% Change

Airport South

Flood

220

218

-2

-0.9%

344

342

-2

-0.6%

Ebb

230

231

1

0.4%

294

294

0

0.0%

Airport West

Flood

19799

19800

1

0.0%

19759

19762

3

0.0%

Ebb

19903

19898

-5

0.0%

17152

17150

-2

0.0%

Tung Chung

Flood

490

484

-6

-1.2%

558

555

-3

-0.5%

Ebb

409

409

0

0.0%

389

390

1

0.3%

Urmston Midway

Flood

23225

23223

-2

0.0%

23645

23648

3

0.0%

Ebb

23307

23307

0

0.0%

20511

20509

-2

0.0%

Airport East

Flood

55

42

-13

-23.6%

28

35

7

25.0%

Ebb

98

88

-10

-10.2%

108

102

-6

-5.6%

 

 

Table 5.12       Predicted Percentile Distribution of Tidal Discharge across Major Cross Sections (Black: Scenario O1; Blue: Scenario O2)

Location

Season

Percentile Distribution of Tidal Discharges

Airport South

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

Airport West

(Positive: Ebbing; Negative: Flooding)

Dry

Wet

Tung Chung

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

Urmston Midway (Positive: Flooding; Negative: Ebbing)

Dry

Wet

Airport East

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

 


Table 5.13       Predicted Instantaneous Tidal Discharge across Major Cross Section (Black: Scenario O1; Blue: Scenario O2)

Location

Season

Predicted Instantaneous Tidal Discharges

Airport South

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

Airport West

(Positive: Ebbing; Negative: Flooding)

Dry

Wet

Tung Chung

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

Urmston Midway (Positive: Flooding; Negative: Ebbing)

Dry

Wet

Airport East

(Positive: Flooding; Negative: Ebbing)

Dry

Wet

 


Exhibit 5.7       Predicted Water Temperature (°C) at Seawater Intake C9

Text

Description automatically generated with medium confidence

5.8.1.5       To study the changes in the level of material exchange and tidal flushing of the embayment, an additional assessment has been conducted to investigate the tidal flushing of the embayment with and without the Project.  Water quality modelling scenarios were set up with initial tracer concentration of 1 mg L-1 within the embayment, and at 0 mg L-1 at the rest of the model domain at the start of the model.  Tracer would be set for baseline and project scenarios for a combination of high water / low water / flood tide / ebb tide under spring / neap tide in both dry / wet seasons (i.e. totalled 32 scenarios).

5.8.1.6       Contour plots showing snapshots of instantaneous tracer concentration at 0 hr, 1 hr, 2 hr, 4 hr, 8 hr, 12 hr, 16 hr, 24 hr, 36 hr and 48 hr for all modelled scenarios are provided in Appendix 5.4.  As shown, it is quite typical the clearance of tracer at the outer part of the embayment (with respect to the proposed wave attenuator under this Project) is slightly faster under the Project Scenario than that of the Baseline Scenario.  It is because the presence of the proposed wave attenuator “cut off” the innermost part of the embayment, so the average distance for the conservative tracer to travel out of the embayment is effectively reduced and this allows a slightly shorter time of clearance.  On the other hand, the clearance of tracer behind the proposed wave attenuator is typically slower in the Project Scenario than that of Baseline Scenario which indicated a reduction of flushing capacity and material exchange behind the wave attenuator.  Given no discharge of sewage or other wastewater into the sea would be allowed within the area of the marine facilities ([6]), the accumulation of pollutants as a result of reduced flushing is not anticipated.  Regular cleaning and removal of floating refuses within the area of the marine facilities would be required to ensure no accumulation of floating refuse around the area of the marine facilities.  Overall, the tracer dispersion modelling exercise indicated the reduced flushing and material exchange behind the proposed wave attenuator but the potential risk is deemed manageable by provision of regular clean and removal of floating refuse, and thus deterioration of water quality within the embayment as a result of change in flow regime is not anticipated.

5.8.1.7       The tidal discharge analysis demonstrated the limited impact on flow regime for the entirety of the western waters, while the tracer dispersion assessment illustrated limited change in tidal flushing within the embayment where the berthing facilities will be located.  To further demonstrate the limited extent of change in flow regime outside of the embayment, additional time series plots of current directions and velocity at the nearest WSRs outside of the embayment under baseline and project scenarios are presented in Table 5.14 and Table 5.15.  Locations of these selected WSRs are shown in Exhibit 5.8.  As shown, the differences predicted under the two scenarios are minor.  Both the magnitude and direction of tidal current under both baseline and project scenarios matched well and showed no significant change.  This demonstrated the change in flow regime is highly localized and is not expected to be significant outside of the embayment and at the nearby WSRs.  Potential change at WSRs further away is expected to be even less significant.  Therefore, it is concluded that the change in flow regime beyond the Project would be limited and will not affect any nearby WSRs.


Exhibit 5.8       Selected Representative Locations for Nearby WSRs outside the Embayment

Table 5.14       Current Magnitude at Observation Points outside the Embayment in Dry Season and Wet Season

Location

Season

Current Magnitude in Baseline and Project Scenario

CLK4

Dry

Wet

CLK3

Dry

Wet

M11c

Dry

Wet

 

Table 5.15       Current Direction at Additional Observation Points outside the Embayment in Dry Season and Wet Season

Location

Season

Current Direction in Baseline and Project Scenario

CLK4

Dry

Wet

CLK3

Dry

Wet

M11c

Dry

Wet

5.8.2             SS Elevation and Increased Sedimentation due to Maintenance Dredging

5.8.2.1       Maintenance dredging within the area of the proposed marine facilities would be required regularly to maintain safe navigable water depth close to the existing seabed level.  Maintenance dredging will be carried out in every two years.  While the detailed design of such dredging works was still being investigated when this report was being prepared, the potential water quality impact from such maintenance dredging operation has been studied through the use of 3D computational modelling with Delft3D.  The selection of model, modelling assumptions, scenarios and other technical details were detailed in Appendix 5.1 for agreement with EPD.  Based on the latest available engineering information, a maintenance dredging scenario was conducted based on the work rate of 40 m3 hr-1 by a single dredger with closed grab working close to the nearest WSR C14 and with cage type silt curtain installed at the source.  This was modelled to determine the environmental acceptability of dredging at the prescribed rate.  A loss reduction factor of 80% was adopted for cage type silt curtain in the nearby approved EIA of the Hong Kong - Zhuhai - Macao Bridge Hong Kong Boundary Crossing Facilities (AEIAR-145/2009) and same factor was adopted for this Project.  Corresponding sediment loss rate was estimated below and adopted for the modelling analysis:

Sediment Loss Rate (kg s-1)

= Dredging Rate (m3 s-1) × Sediment Loss Rate (kg m-3) × Silt Curtain Efficiency

= 0.01111 m3 s-1 × 20 kg m-3 × (100% - 80%)

= 0.04444 kg s-1

5.8.2.2       Predicted SS elevation at identified WSRs were presented at Table 5.16.  Contour plot showing the instantaneous SS elevation for maintenance dredging under dry and wet seasons are provided in Appendix 5.2.

5.8.2.3       The predicted SS elevation was confined to WSRs close to the sediment source, with no notable elevation outside of the embayment between the HKP and the Airport Island.  Maximum SS elevation was predicted at the nearest WSR C14 and would be up to 5.31 mg L-1 in dry season and 4.60 mg L-1 in wet season, which are below the proposed assessment criteria based on WQO.  The second most impacted WSR was C9, which was also the second closest WSR.  The predicted level of SS elevation would be up to 0.15 mg L-1 in dry season and 0.22 mg L-1 in wet season.  SS elevation at WSRs beyond was limited and would be below 0.10 mg L-1 in general, which was much lower than the ambient level as well as the proposed assessment criterion.

5.8.2.4       The predicted levels of sedimentation at identified coral / artificial reef WSRs were expected to be limited.  Contour plot showing the maximum sedimentation flux for maintenance dredging under dry and wet seasons are provided in Appendix 5.2.  Model prediction for maximum sedimentation flux at identified coral / artificial reef WSRs are provided in Table 5.17.  Maximum sedimentation flux was predicted at CR2 and is only up to 0.05 g m-2 day-1, which is below the corresponding assessment criterion of 200 g m-2 day-1.  No additional mitigation measure is deemed necessary to further reduce sedimentation impact to the nearby WSRs.


Table 5.16       Predicted Level of SS Elevation (mg L-1) from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with a Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source)

Description

Location

Model Output Location

EPD Station

Relevant Depth

Dry Season

Wet Season

Ambient Level

WQO SS Allowable Change

Predicted Max Increase

Compliance Time %

Ambient Level

WQO SS Allowable Change

Predicted Max Increase

Compliance Time %

Fisheries Sensitive Receivers

Spawning Grounds  for commercial fisheries resources

Spawning Grounds  for commercial fisheries resources in North Lantau

F1

NM6

Depth-averaged

28.7

8.6

<0.01

100%

17.2

5.2

<0.01

100%

Marine Ecological Sensitive Receivers

Marine Park

Sha Chau and Lung Kwu Chau Marine Park

E1

NM6

Depth-averaged

28.7

8.6

<0.01

100%

17.2

5.2

<0.01

100%

Marine Park

The Brothers Marine Park

E2

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

SSSI

Tai Ho Bay and Tai Ho Stream SSSI

E4

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

SSSI

Tung Chung Bay and San Tau Beach SSSI

E5

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Horseshoe Crab Habitat

Hau Hok Wan

E6

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Horseshoe Crab Habitat

Sha Lo Wan

E7

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Horseshoe Crab Habitat, Mangrove Stand

Sham Wat Wan

E8

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Horseshoe Crab Habitat, Mangrove Stand

Yam O Wan

E9

NM1

Depth-averaged

17.3

5.2

<0.01

100%

14.9

4.5

<0.01

100%

Artificial Reef and Coral Communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

NM6

Bottom

30.0

9.0

<0.01

100%

17.7

5.3

<0.01

100%

Coral Communities

The Brothers Islands (West Brother)

CR2

NM3

Bottom

22.8

6.8

<0.01

100%

19.6

5.9

<0.01

100%

Coral Communities

North of Sheung Sha Chau

CR3

NM6

Bottom

30.0

9.0

<0.01

100%

17.7

5.3

<0.01

100%

Coral Communities

Sham Shui Kok

CR4

NM2

Bottom

28.0

8.4

<0.01

100%

19.1

5.7

<0.01

100%

Artificial Reef

HKIA Approach Area

CLK1

NM3

Bottom

22.8

6.8

<0.01

100%

19.6

5.9

<0.01

100%

Artificial Reef

HKIA Approach Area

CLK2

NM3

Bottom

22.8

6.8

<0.01

100%

19.6

5.9

<0.01

100%

Artificial Reef

HKIA Approach Area

CLK3

NM3

Bottom

22.8

6.8

0.01

100%

19.6

5.9

<0.01

100%

Artificial Reef

HKIA Approach Area

CLK4

NM3

Bottom

22.8

6.8

0.02

100%

19.6

5.9

<0.01

100%

Artificial Reef

HKIA Approach Area

CLK5

NM3

Bottom

22.8

6.8

<0.01

100%

19.6

5.9

<0.01

100%

Water Sensitive Receivers

Non-gazetted beach

Lung Kwu Sheung Tan

B1

NM5

Depth-averaged

22.3

6.7

<0.01

100%

19.6

5.9

<0.01

100%

Non-gazetted beach

Lung Tsai / Lung Kwu Tan

B2

NM5

Depth-averaged

22.3

6.7

<0.01

100%

19.6

5.9

<0.01

100%

Gazetted Beach

Butterfly Beach

B3

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Gazetted Beach

Cafeteria New Beach

B4

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Gazetted Beach

Gold Coast Marina / Golden Beach

B5

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Gazetted Beach

Castle Peak Beach

B6

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Gazetted Beach

Kadoorie Beach

B7

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Gazetted Beach

Cafeteria Old Beach

B8

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Seawater Intake

Castle Peak Power Station Cooling Water Intake

C1

NM5

Depth-averaged

22.3

6.7

<0.01

100%

19.6

5.9

<0.01

100%

Seawater Intake

Cooling Water Intake for Shiu Wing Steel Mills

C2

NM3

Depth-averaged

20.0

6.0

<0.01

100%

15.7

4.7

<0.01

100%

Seawater Intake

WSD Seawater Intake at Tuen Mun (b)

C3

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Seawater Intake

Proposed Lok On Pai Intake (Pumping Station)

C4

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Seawater Intake

Future Seawater Intake Point for Sunny Bay

C5

NM1

Depth-averaged

17.3

5.2

<0.01

100%

14.9

4.5

<0.01

100%

Seawater Intake

Proposed Ta Pang Po Intake (Pumping Station)

C6

NM1

Depth-averaged

17.3

5.2

<0.01

100%

14.9

4.5

<0.01

100%

Seawater Intake

Future Seawater Intake Point for Tung Chung East

C8

NM3

Depth-averaged

20.0

6.0

<0.01

100%

15.7

4.7

<0.01

100%

Seawater Intake

HKP Intake

C9

NM3

Depth-averaged

20.0

6.0

0.15

100%

15.7

4.7

0.22

100%

Seawater Intake

Cooling Water Intake at HKIA North

C10

NM3

Depth-averaged

20.0

6.0

0.01

100%

15.7

4.7

0.02

100%

Seawater Intake

Future Seawater Intake at HKIA East

C11

NM3

Depth-averaged

20.0

6.0

<0.01

100%

15.7

4.7

<0.01

100%

Seawater Intake

Seawater Intake at Tung Chung

C12

NM3

Depth-averaged

20.0

6.0

<0.01

100%

15.7

4.7

<0.01

100%

Seawater Intake

Cooling  Water Intake at HKIA South

C13

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Seawater Intake

Cooling Seawater Intake Point for SKYCITY 

C14

NM3

Depth-averaged

20.0

6.0

5.31

100%

15.7

4.7

4.60

100%

Seawater Intake

LRT Tuen Mun Ferry Pier Terminus

C15

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Seawater Intake

Tuen Mun Hospital

C16

NM2

Depth-averaged

28.0

8.4

<0.01

100%

19.1

5.7

<0.01

100%

Seawater Intake

Sam Shing Estate

C17

NM2

Depth-averaged

28.0

8.4

<0.01

100%

19.1

5.7

<0.01

100%

Seawater Intake

China Cement Plant

C18

NM5

Depth-averaged

22.0

6.6

<0.01

100%

36.1

10.8

<0.01

100%

Typhoon Shelter

Tuen Mun

T1

NM2

Depth-averaged

19.7

5.9

<0.01

100%

13.3

4.0

<0.01

100%

Observation Points

Boundary of Marine Park

The Brothers Marine Park

M9

NM3

Depth-averaged

20.0

6.0

<0.01

100%

15.7

4.7

<0.01

100%

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10a

NM5

Depth-averaged

22.3

6.7

<0.01

100%

19.6

5.9

<0.01

100%

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10b

NM5

Depth-averaged

22.3

6.7

<0.01

100%

19.6

5.9

<0.01

100%

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10c

NM6

Depth-averaged

28.7

8.6

<0.01

100%

17.2

5.2

<0.01

100%

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10d

NM6

Depth-averaged

28.7

8.6

<0.01

100%

17.2

5.2

<0.01

100%

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10e

NM6

Depth-averaged

28.7

8.6

<0.01

100%

17.2

5.2

<0.01

100%

Boundary of Marine Park

Proposed North Lantau Marine Park

M11a

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Boundary of Marine Park

Proposed North Lantau Marine Park

M11b

NM8

Depth-averaged

42.0

12.6

<0.01

100%

23.8

7.1

<0.01

100%

Boundary of Marine Park

Proposed North Lantau Marine Park

M11c

NM3

Depth-averaged

20.0

6.0

0.01

100%

15.7

4.7

0.02

100%

 

Table 5.17       Predicted Level of Sedimentation (g/m2/day) at Coral and Artificial Reef from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with One Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source)

Description

Location

Model Output Location

Assessment Criterion

Model Prediction

Dry Season

Wet Season

Artificial Reef and coral communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

200

<1

<1

Coral communities

The Brothers Islands (West Brother)

CR2

200

<1

<1

Coral communities

North of Sheung Sha Chau

CR3

200

<1

<1

Coral communities

Sham Shui Kok

CR4

200

<1

<1

 


5.8.3             Dissolved Oxygen (DO) Depletion due to Maintenance Dredging

5.8.3.1       The degree of DO depletion exerted by a sediment plume is a function of the sediment oxygen demand of the sediment, its concentration in the water column and the rate of oxygen replenishment.  The impact of the sediment oxygen demand on DO concentrations has been calculated based on the following equation:

DO (mg O2 L-1) = DO (g O2 m-3) = SS (g DW m-3) × sediment oxygen demand (g O2 g-1 DW)

5.8.3.2       Review of sediment quality data from the nearest EPD Sediment Quality Monitoring Station indicated maximum sediment oxygen demand of up to 17,000 mg kg-1.  Predicted DO depletion at identified WSRs were presented at Table 5.18.  Based on the predicted maximum SS elevation of 5.31 mg L-1 under the modelled scenario, the maximum level of DO depletion would be up to 0.09 mg L-1, which is below the corresponding allowable DO depletion levels of 0.4 mg L-1.  Other WSRs at further distance were predicted to have much lower SS elevation, and thus would experience proportionally lower DO depletion.  No unacceptable level of DO depletion is expected from the proposed maintenance dredging.


Table 5.18       Predicted Level of DO Depletion (mg L-1) (Dredging Rate of 40 m3 hr-1 with One Single Dredger with Closed Grab close to WSR C14, and with Cage Type Silt Curtain at Source)

Description

Location

Model Output Location

EPD Station

Relevant Depth

Predicted Max SS Increase

Predict Max DO Depletion

WQO DO Allowable Change

Dry Season

Wet Season

Dry Season

Wet Season

Fisheries Sensitive Receivers

Spawning Grounds for commercial fisheries resources

Spawning Grounds for commercial fisheries resources in North Lantau

F1

NM6

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.7

Marine Ecological Sensitive Receivers

Marine Park

Sha Chau and Lung Kwu Chau Marine Park

E1

NM6

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.7

Marine Park

The Brothers Marine Park

E2

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

SSSI

Tai Ho Bay and Tai Ho Stream SSSI

E4

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

SSSI

Tung Chung Bay and San Tau Beach SSSI

E5

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Horseshoe Crab Habitat

Hau Hok Wan

E6

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Horseshoe Crab Habitat

Sha Lo Wan

E7

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Horseshoe Crab Habitat, Mangrove Stand

Sham Wat Wan

E8

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Horseshoe Crab Habitat, Mangrove Stand

Yam O Wan

E9

NM1

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Artificial Reef and coral Communities

Sha Chau and Lung Kwu Chau Marine Park

CR1

NM6

Bottom

<0.01

<0.01

<0.01

<0.01

2.5

Coral Communities

The Brothers Islands (West Brother)

CR2

NM3

Bottom

<0.01

<0.01

<0.01

<0.01

1.5

Coral Communities

North of Sheung Sha Chau

CR3

NM6

Bottom

<0.01

<0.01

<0.01

<0.01

2.5

Coral Communities

Sham Shui Kok

CR4

NM2

Bottom

<0.01

<0.01

<0.01

<0.01

1.7

Artificial Reef

HKIA Approach Area

CLK1

NM3

Bottom

<0.01

<0.01

<0.01

<0.01

1.5

Artificial Reef

HKIA Approach Area

CLK2

NM3

Bottom

<0.01

<0.01

<0.01

<0.01

1.5

Artificial Reef

HKIA Approach Area

CLK3

NM3

Bottom

0.01

0.03

<0.01

<0.01

1.5

Artificial Reef

HKIA Approach Area

CLK4

NM3

Bottom

0.02

0.04

<0.01

<0.01

1.5

Artificial Reef

HKIA Approach Area

CLK5

NM3

Bottom

<0.01

<0.01

<0.01

<0.01

1.5

Water Sensitive Receivers

Non-gazetted Beach

Lung Kwu Sheung Tan

B1

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Non-gazetted Beach

Lung Tsai / Lung Kwu Tan

B2

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Gazetted Beach

Butterfly Beach

B3

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Gazetted Beach

Cafeteria New Beach

B4

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Gazetted Beach

Gold Coast Marina / Golden Beach

B5

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Gazetted Beach

Castle Peak Beach

B6

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Gazetted Beach

Kadoorie Beach

B7

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Gazetted Beach

Cafeteria Old Beach

B8

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Seawater Intake

Castle Peak Power Station Cooling Water Intake

C1

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Seawater Intake

Cooling Water Intake for Shiu Wing Steel Mills

C2

NM3

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.3

Seawater Intake

WSD Seawater Intake at Tuen Mun

C3

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

2.5

Seawater Intake

Proposed Lok On Pai Intake (Pumping Station)

C4

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Seawater Intake

Future Seawater Intake Point for Sunny Bay

C5

NM1

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Seawater Intake

Proposed Ta Pang Po Intake (Pumping Station)

C6

NM1

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Seawater Intake

Future Seawater Intake Point for Tung Chung East

C8

NM3

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.3

Seawater Intake

HKP Intake

C9

NM3

Depth-averaged

0.15

0.22

<0.01

<0.01

0.3

Seawater Intake

Cooling Water Intake at HKIA North

C10

NM3

Depth-averaged

0.01

0.02

<0.01

<0.01

0.3

Seawater Intake

Future Seawater Intake at HKIA East

C11

NM3

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.3

Seawater Intake

Seawater Intake at Tung Chung

C12

NM3

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.3

Seawater Intake

Cooling Water Intake at HKIA South

C13

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Seawater Intake

Cooling Seawater Intake Point for SKYCITY

C14

NM3

Depth-averaged

5.31

4.60

0.09

0.08

0.3

Seawater Intake

LRT Tuen Mun Ferry Pier Terminus

C15

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Seawater Intake

Tuen Mun Hospital

C16

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Seawater Intake

Sam Shing Estate

C17

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Seawater Intake

China Cement Plant

C18

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Typhoon Shelter

Tuen Mun

T1

NM2

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.5

Observation Points

Boundary of Marine Park

The Brothers Marine Park

M9

NM3

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.3

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10a

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10b

NM5

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.2

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10c

NM6

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.7

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10d

NM6

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.7

Boundary of Marine Park

Sha Chau and Lung Kwu Chau Marine Park

M10e

NM6

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.7

Boundary of Marine Park

Proposed North Lantau Marine Park

M11a

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Boundary of Marine Park

Proposed North Lantau Marine Park

M11b

NM8

Depth-averaged

<0.01

<0.01

<0.01

<0.01

0.6

Boundary of Marine Park

Proposed North Lantau Marine Park

M11c

NM3

Depth-averaged

0.01

0.02

<0.01

<0.01

0.3

 


5.8.4             Release of Sediment-bounded Nutrients due to Maintenance Dredging

5.8.4.1       Disturbance to sediment due to maintenance dredging could release sediment-bounded nutrients into the water column, causing an enrichment of nutrient levels in the receiving water.  The release of sediment-bounded nutrient was modelled as release of conservative tracer in Delft3D.  The modelled release rate was set to be the same as the sediment release rate.

5.8.4.2       Review of sediment quality results under the elutriate test (Appendix 5.7 referred; summary provided in Table 5.5) indicated some release on nitrogenous species would be expected from sediment disturbance from the proposed maintenance dredging.  Maximum release of Total Kjeldahl Nitrogen (TKN) from elutriate test among all survey locations was adopted for the assessment of potential elevation of total inorganic nitrogen (TIN) and unionized ammonia (UIA) nitrogen.  Note that oxidized nitrogen (nitrate and nitrite) tends to be low in sediment sample because of the reducing environment.  The elutriate test results for oxidized nitrogen are inconsistent and some elutriate has lower oxidized nitrogen level than that of sea water blank sample, indicating some oxidized nitrogen being removed (potentially through adsorption).  Therefore, the potential release of sediment-bounded oxidized nitrogen is not included in the assessment.  Among all stations, the maximum TKN release (elutriate level minus sea water blank level) was found to be 15.7 mg L-1.  Given these 15.7 mg L-1 of TKN was extracted from 1 kg of sediment using 4 L of seawater, this means about 62.8 mg of TKN could be released from 1 kg of disturbed sediment.  Assuming 100% of TKN would be converted into TIN immediately after release, this implies a release rate of 62.8 mg TIN per 1 kg of sediment disturbed, or a percentage of 0.00628%.  This 0.00628% ratio would then be applied to the predicted conservative tracer concentration at WSRs to estimate the predicted level of TIN elevation at WSRs (i.e. TIN elevation at WSR = conservative tracer concentration × 0.00628%).  Predicted level of conservative tracer and corresponding level of TIN and UIA nitrogen are presented in Table 5.19.  Based on the predicted maximum conservative tracer concentration in dry and wet seasons, the maximum TIN elevation at the most impacted WSR C14 was 0.0042 mg L-1 which was only about 0.6% of the ambient levels at the nearest EPD Marine Water Quality Monitoring Station (NM6, mean levels = 0.69 mg L-1).  Given the temporary nature of the impact and the small change in TIN levels relative to ambient concentrations, the expected level of TIN elevation at other WSRs were even lower and no unacceptable water quality impact from TIN elevation is anticipated. 

5.8.4.3       Similarly, the potential increase in UIA at C14 was calculated to be 0.00016 mg L-1, which was also less than 1% of the allowable elevation (0.017 mg L-1, based on baseline level of 0.004 mg L-1 as shown in Table 5.2).  It is expected that the UIA elevation at other farther WSRs were even lower and thus no unacceptable water quality impact from UIA elevation is anticipated.  Overall, no unacceptable change in water quality associated release of sediment-bounded nutrients from maintenance dredging is expected.

Table 5.19       Predicted Level of Conservative Tracer (mg L-1) and Corresponding Level of TIN and UIA at WSR C14 from Maintenance Dredging (Dredging Rate of 40 m3 hr-1 with One Close Grab Dredger close to WSR C14, and with Cage Type Silt Curtain at Source)

Description

Location

Model Output Location

EPD Station

Predicted Maximum Conservative Tracer Concentration

(mg L-1)

Predicted Maximum Elevation (mg L-1)

Dry Season

(a)

Wet Season

(b)

Total Inorganic Nitrogen

(c)=Max((a),(b))×0.00628%

Unionized Ammonia Nitrogen

(d)=(c)× 3.7%

Seawater Intake

Cooling Seawater Intake Point for SKYCITY 

C14

NM3

67.03100

39.42700

4.2E-03

1.6E-04

5.8.5             Release of Sediment-bounded Contaminants due to Maintenance Dredging

5.8.5.1       Review of the sediment quality results under elutriate test detailed in Section 5.3.4.1 suggested that there would not be observable release of contaminants from sediment to marine water for all heavy metals and organic contaminants of concern except for arsenic and nickel.  In view of this, arsenic and nickel level increase at the nearest WSRs due to the maintenance dredging were estimated.

5.8.5.2       Increase of arsenic and nickel levels at the nearest WSRs, WSR C14 (seawater intake) and the closest marine ecological sensitive receiver, WSR M11c (boundary of the proposed North Lantau Marine Park).  Note that WSR C14 is not known to be sensitive to heavy metals and organic contaminants but its data was presented as worst case scenario due to its proximity.  As shown in Table 5.20, the predicted maximum arsenic and nickel levels at both WSRs were below the assessment criteria and no exceedance on contaminants level would observe at other WSRs that farther away from the project area.  No unacceptable levels of sediment-bounded nutrients and contaminants from maintenance dredging is predicted.

Table 5.20       Estimation of Contaminant Levels Elevation at the Most Impacted WSRs from Maintenance Dredging

Parameters

Elutriate Elevation

Mass Release Rate

(a)

Maximum Tracer Conc.  (mg L-1) in Dry Season and Wet Season at C14

(b)

Contaminant Concentration (µg L-1)

(c)= (a)/1000x(b)/1000

Maximum Tracer Conc.  (mg L-1) in Dry Season and Wet Season at M11c

(d)

Contaminant Concentration (µg L-1)

(e)= (a)/1000x(d)/1000

Assessment Criteria (µg L-1)

Arsenic

50.00

200.00

67.03100

1.3E-02

0.00093

1.9E-07

13

Nickel

0.20

0.80

5.4E-05

7.5E-10

70

5.8.6             Generation of Wastewater, Sewage from Staff, Visitors etc.

5.8.6.1       Sewage effluent and wastewater would be generated from staff and visitors.  Local connections to the existing sewer within the Airport Island would be installed and no direct discharge of sewage and wastewater to the nearby drainage system and marine waters would be expected.  Review of existing sewerage system indicated capacity is sufficient in view of the limited sewage generation (0.0609 m3/s) from this Project.

5.8.6.2       Depot operation typically involve parking, charging and cleaning of zero emission vehicles.  Cleaning of zero emission vehicles generally involve only soap and water, which is typical safe for disposal to sewer.  The maintenance wastewater collection system will be separated from the public sewer.  Routine maintenance may involve release oil and grease residues.  Related wastewater will be properly collected, for treatment and disposal off-site by licensed contractor as well. 

5.8.6.3       Marine facilities which include a pier and berthing facilities would serve strictly for berthing purposes only and thus sewage discharge is not anticipated.  In addition, discharge from marine facilities were controlled under the Water Pollution Control Ordinance and discharge from vessels were controlled under both Water Pollution Control Ordinance and Merchant Shipping (Prevention and Control of Pollution) Ordinance. 

5.8.7             Potential Oil Spillage associated with the Operation of the Vessels

5.8.7.1       During the operational phase, the operation of the marine vessels would carry risk of spillage.  In general, marine vessel speed at or around the area of marine facilities would be low and therefore the risk of collision would be low as well.  Equipment for spillage clean-up such as floating booms would be stored on the marine facilities to facilitate quick response on clean-up effort.  The sheltered environment of the marine facilities also would limit the potential spread and allow containment and timely clean-up be conducted easily.  No unacceptable water quality impact from oil spillage from the operation of vessels within the marine facilities would be expected.

5.8.8             Generation of Road Runoff

5.8.8.1       Road runoff discharge from viaducts and at-grade sections would be arise during operational phase.  The discharge would contain small amount of suspended solids and oil/grease that may cause water quality impacts to the nearby receiving marine water.  A proper drainage system will be provided to receive the surface runoff to the drainage system at the planning and design stages.  No new stormwater discharge outfall under this Project would be located within the marine facilities.  Unacceptable adverse water quality impact associated with the operation of marine facilities is not anticipated.  No unacceptable water quality impact from road runoff would be expected.

5.9                   Mitigation Measures

5.9.1             Construction Phase

5.9.1.1       The following standard measures and good site practices are recommended to be implemented to avoid/minimise the potential impacts from marine-based and land-based construction activities:

·        There will be at most 2 piles installed concurrently for the marine facilities.  Similarly, there will be at most 2 piles installed concurrently for the marine viaduct.

·        Silt curtain would be set up to enclose the entire active work area before commencement of piling works for marine facilities and marine viaduct to control sediment dispersion.

·        All vessels should be well maintained and inspected before use to limit any potential discharges to the marine environment.

·        All vessels must have a clean ballast system.

·        All vessels shall be sized such that adequate clearance is maintained between vessels and the sea bed at all states of the tide to ensure that undue turbidity is not generated by turbulence from vessel movement or propeller wash.

·        Marine works shall not cause foam, oil, grease, litter or other objectionable matter to be present in the water within and adjacent to the works site.  Wastewater from potentially contaminated area on working vessels should be minimized and collected.  These kinds of wastewater should be brought back to port and discharged at appropriate collection and treatment system.

·        No solid waste is allowed to be disposed overboard.

·        Best Management Practices (BMPs) of mitigation measures in controlling water pollution and good site management, as specified in the ProPECC PN 1/94Construction Site Drainage” are followed, where applicable, to prevent runoff with high level of SS from entering the surrounding waters.

·        At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works.  Channels, earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities.

·        Diversion of natural stormwater should be provided as far as possible.  The design of temporary on-site drainage should prevent runoff going through site surface, construction machinery and equipment in order to avoid or minimize polluted runoff.  Sedimentation tanks with sufficient capacity, constructed from pre-formed individual cells of approximately 6 to 8 m3 capacities, are recommended as a general mitigation measure which can be used for settling surface runoff prior to disposal.  The system capacity shall be flexible and able to handle multiple inputs from a variety of sources and suited to applications where the influent is pumped.

·        The dikes or embankments for flood protection should be implemented around the boundaries of earthwork areas.  Temporary ditches should be provided to facilitate the runoff discharge into an appropriate watercourse, through a silt/sediment trap.  The silt/sediment traps should be incorporated in the permanent drainage channels to enhance deposition rates.

·        The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94.  The detailed design of the sand/silt traps should be undertaken by the contractor prior to the commencement of construction.

·        All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms.  Deposited silt and grit should be removed regularly and disposed of by spreading evenly over stable, vegetated areas.

·        All open stockpiles of construction materials (for example, aggregates, sand and fill material) should be covered with tarpaulin or similar fabric during rainstorms.  Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system.

·        Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed so as to prevent silt, construction materials or debris being washed into the drainage system and storm runoff being directed into foul sewers.

·        The precautions to be taken at any time of year when rainstorms are likely together with the actions to be taken when a rainstorm is imminent or forecasted and actions to be taken during or after rainstorms are summarised in Appendix A2 of ProPECC PN 1/94.

·        All vehicles and plant should be cleaned before leaving a construction site to ensure no earth, mud, debris and the like is deposited by them on roads.  An adequately designed and sited wheel washing facilities should be provided at every construction site exit where practicable.  Wash-water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process.  The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient backfall toward the wheel-wash bay to prevent vehicle tracking of soil and silty water to public roads and drains.

·        Construction solid waste, debris and rubbish on site should be collected, handled and disposed of properly to avoid water quality impacts.

·        Appropriate numbers of chemical toilets will be provided by a licensed contractor to serve the construction workers over the construction sites to prevent direct disposal of sewage into the water environment.  No onsite discharge from these chemical toilets will be allowed.

·        All fuel tanks and chemical storage areas will be provided with locks and be sited on sealed areas.  The storage areas will be surrounded by bunds with a capacity equal to 110% of the storage capacity of the largest tank.

·        The contractors shall ensure that leakages or spillages are contained and cleaned up immediately.

5.9.2             Operational Phase

5.9.2.1       Maintenance dredging will be carried out to allow vessels to access the marine facilities at low tide and to enhance navigational safety.  Cage type silt curtain will be provided during maintenance dredging.  The maximum working rate for maintenance dredging is assumed to be 40 m3 per hour and only one closed grab dredger will be working in any time.  Other good site practices stipulated under Section 5.9.1 for marine construction works would be applicable for maintenance dredging during operational phase as well.

5.9.2.2       Local connections to the public sewer would be installed and no direct discharge of sewage and wastewater to the nearby drainage system and marine waters would be allowed.  Regular cleaning and removal of floating refuse should be conducted within the area of the marine facilities and coastal area around the Project to avoid excessive accumulation.  Also, any new drainage outfall(s) under this Project will be located outside of the marine facilities.

5.9.2.3       Spillage clean up equipment should be provided at the marine facilities to allow quick response in case of emergency.

5.9.2.4       A surface water drainage system should be provided to collect road runoff to the new drainage system with new stormwater outfall and adequate designed pollution removal devices such as silt trap and oil/grease trap, as necessary, which should be regularly cleaned and maintained to ensure proper functioning.

5.10               Cumulative Impacts

5.10.1.1   There are a few concurrent projects that could have significant effect on flow regime and sediment elevation within the NWWCZ.  They are listed in the Working Paper on Water Quality Modelling Plan (Appendix 5.1) and summarized in Table 5.21 below.

Table 5.21       Concurrent Projects Considered in this Water Quality Impact Assessment

 

Concurrent Projects

Marine Works Involved

Consideration in this Water Quality Impact Assessment

1

Expansion of Hong Kong International Airport into a Three-Runway System

Majority of reclamation works has been completed by mid-2021

Completed reclamation was taken into account in the hydrodynamic modelling in this EIA to account for its effect on flow regime.  Other discharges from 3RS operation and seawater intakes WSRs were also taken into account.

2

Tung Chung New Town Extension

Reclamation works was completed by 2022

Reclamation was taken into account for the operational phase assessment in this EIA for cumulative assessment.  Seawater intakes WSRs were considered as well.

3

Tung Chung Line Extension

No marine work under this project

No reclamation and proposed discharge of cooling water or other major effluent for this project.  No notable cumulative impact from this project is anticipated in terms of water quality.

4

SkyPier Terminal (SPT) Bonded Bridge (formerly known as Intermodal Transfer Terminal - Bonded Vehicular Bridge and Associated Roads)

Bridge piles installation has been completed on July 2022

Footprint of the piles and the effect of the presence of the bridge piles were taken into account in the operational phase hydrodynamic modelling for cumulative assessment.

5

Airportcity Link (formerly known as Airport City Link)

Bridge piles installation to be completed by 2024

6

SKYCITY

No marine work under this project

Sewage and wastewater will be discharged into local sewerage network and no direct discharge of sewage or wastewater is expected from this project.  No notable cumulative impact from this project is anticipated in terms of water quality.

7

East Coast Support Area

No marine work under this project

No notable cumulative impact from this project is anticipated in terms of water quality.

8

Potential Reclamation Site at Lung Kwu Tan

The proposed reclamation is currently being studied by CEDD and there is no clear implementation schedule

The reclamation area was taken into account in the operational phase modelling assessment for change in flow regime.  While these are Designated Projects under EIAO, the project proponents will need to carry out EIAs and carry out necessary measures to confine the sediment loss arising from the dredging/marine works.  It is anticipated that there will be limited level of cumulative SS elevation from the construction of this Project.  Therefore, sediment loss from this Project was not taken into account in the sediment dispersion modelling assessment for maintenance dredging.

Note that these projects are designated projects under the EIAO and separate assessment on cumulative impact arising project this Project would be conducted in the respective EIAs.

9

Potential Reclamation Site at Sunny Bay

The proposed reclamation is currently being studied by CEDD and there is no clear implementation schedule

10

Contaminated Mud Disposal Facilities at East of Sha Chau and South Brothers

It is expected the capacity of this facilities will be exhausted by 2027 and disposal will be stopped by then.  Capping of pits will be followed soon.  It is unlikely that there will be significant overlapping for the sediment disposal and capping under at the CMP and the maintenance dredging under this EIA given the completion of marine facilities under this Project would be by Q4 of 2027.

The final capped level at the East of Sha Chau and South Brothers Contaminated Mud Pit was taken into account in the hydrodynamic modelling to assess the change in flow regime.

 

11

Road P1 (Tai O – Sunny Bay Section)

Project is in its EIA stage and no detail project programme is available yet.  According to it project profile, project construction is targeted to be completed by 2030.  Marine reclamation is expected to create a thin stripe of land at Siu Ho Wan.

The reclamation area was taken into account in the operational phase modelling assessment for change in flow regime.  It is anticipated that there will be limited level of cumulative SS elevation from the construction of this Project given its separation (> 4 km plus HKP in between).  Therefore, sediment loss from this Project was not taken into account in the sediment dispersion modelling assessment for maintenance dredging.

5.11               Residual Impacts

5.11.1         Construction Phase

5.11.1.1   Marine construction works under this Project and the generation of wastewater and sewage from workforce have been assessed.  No unacceptable water quality impact from marine-based construction works is expected.

5.11.1.2   With the implementation of standard site practices and control measures specified under Section 5.9.1, no unacceptable water quality impact is expected from the proposed land-based construction works.

5.11.2         Operational Phase

5.11.2.1   Change in flow regime due to presence of both floating structure and berth piles at the embayment between Airport Island and HKP Island, as well as the marine viaduct piers at the Tung Chung Navigation Channel has been evaluated.  No unacceptable change in flow regime outside of the embayment is expected from the operation of the proposed marine facilities.

5.11.2.2   In addition, sediment dispersion modelling indicated there would be limited changes in water quality for maintenance dredging with controlled work rate of 40 m3 hr-1 and the use of cage type silt curtain around grab dredger, therefore no unacceptable water quality impact would be expected.

5.11.2.3   Other sources i.e. discharge of wastewater and sewage effluent from staff and visitors and potential oil spillage associated with the operation of the vessels have been evaluated.  No unacceptable water quality impact would be expected from these sources.

5.12               Environmental Monitoring and Audit

5.12.1.1   Marine water quality monitoring at representative locations is recommended for marine works for the marine viaduct and marine facilities during construction phase and maintenance dredging during operational phase.  Weekly site audits would also be conducted throughout the marine-based construction under this Project.  The specific monitoring requirements are detailed in the standalone Environmental Monitoring and Audit (EM&A) Manual.

5.13               Conclusion

5.13.1         Construction Phase

5.13.1.1   Potential water quality impact from marine and land-based construction works under the Project and the generation of wastewater and sewage from workforce have been assessed in this EIA.  Appropriate preventive and mitigation measures are recommended to minimise the potential water quality impact from these activities.  Unacceptable water quality impact from the construction works under the Project and sewage discharge is not expected.

5.13.2         Operational Phase

5.13.2.1   Computational modelling has been conducted to assess the potential change in flow regime due to the presence of piles and wave attenuator for marine facilities, as well as the marine viaduct at the Tung Chung Navigation Channel to be constructed under this Project.  No unacceptable change in flow regime would be expected from the Project.  In addition, various potential water quality impacts from the operational phase maintenance dredging, including SS elevation, sedimentation, DO depletion, release of sediment-bounded nutrient, heavy metal and organic contaminants have been assessed in this EIA.  Unacceptable water quality impact from maintenance dredging is not expected.

5.13.2.2   The potential water quality impact arising associated with the sewage and wastewater generated from workforce, depot operation and potential oil spillage from the operation of the marine vessels has been assessed.  Appropriate preventive and mitigation measures are recommended to minimise the potential water quality impact from these activities.  Unacceptable water quality impact from these activities is not expected.



([1])              Impact water quality monitoring data is available on 3RS’s project webpage.  (https://env.threerunwaysystem.com/en/data_search_WQ.php)

([2])     ERM (2016) EIA for Additional Gas-fired Generation Units Project (AEIAR-197/2016).  Final EIA Report.  For CLP Power Hong Kong Limited (CLP) and Castle Peak Power Company Limited (CAPCO).

([3])     ERM (2018) EIA for Hong Kong Offshore LNG Terminal (AEIAR-218/2018).  Final EIA Report.  For CLP Power Hong Kong Limited (CLP).

([4]) The technique for installing floating wave attenuator is patented and it has not yet been registered in Hong Kong.  As such, applying the floating wave attenuator may impose time/cost implication and some uncertainties to the project implementation.

([5]) The proposed seawater intake C14 represents the cooling water intake for the SKYCITY which is not currently in operation.  As such, the predicted temperature at C9 for HKP is adopted for assessment of the potential change in water temperature.

([6]) There is no known existing sewage outfall related to HKIA operation or HKP operation in the embayment, and there is no planned sewage outfall within the embayment under this Project.  Locations of outfalls by HKIA are shown in the following page: https://www.epd.gov.hk/eia/register/report/eiareport/eia_2232014/html/Drawing%208-008.pdf.  Location of outfall by HKP (formerly known as the HKBCF) are shown in the following page: https://www.epd.gov.hk/eia/register/report/eiareport/eia_1732009/html/Section%209%20(Water%20Quality)/Figure%209.4.pdf.  Note that there is one existing stormwater outfall discharging into the footprint of the marine facilities.  According to the drainage records, the catchment of the stormwater runoff covers mainly the existing and future commercial land use (59%), road (33%) and carpark (8%), which has low risk for contaminating the surface runoff in the future.