TABLE OF CONTENTS

3.        Air quality  3-1

3.1        Introduction. 3-1

3.2        Environmental Legislations, Standards and Guidelines. 3-1

3.3        Description of Environment 3-3

3.4        Identification of Air Sensitive Receivers. 3-9

3.5        Identification of Environmental Impacts. 3-20

3.6        Assessment Methodology. 3-29

3.7        Prediction and Evaluation of Environmental Impacts. 3-40

3.8        Mitigation of Adverse Environmental Impacts. 3-75

3.9        Evaluation of Residual Impacts. 3-76

3.10      Environmental Monitoring and Audit 3-77

3.11      Environmental Acceptability of Schedule 2 Designated Projects. 3-78

3.12      Conclusion. 3-79

List of Tables

Table 3.1        Air Quality Objectives for Hong Kong

Table 3.2        Air Quality Standards for Non-AQO Criteria Pollutants

Table 3.3        Average Concentrations of Pollutants in the Recent Five Years (Year 2018 – 2022) at Yuen Long EPD Air Quality Monitoring Station

Table 3.4        Background Air Pollutants in Year 2030 Extracted from PATH Model (PATHv2.1)

Table 3.5        Background Air Pollutants in Year 2035 Extracted from PATH Model (PATHv2.1)

Table 3.6        Representative Air Sensitive Receivers in the vicinity of STLMC DN

Table 3.7        Vehicular Emission Burden in the Study Area

Table 3.8        Summary of Assessment Scenarios and Contributing Sources

Table 3.9        Conversion Factors from 1-hour to 30-minute Averaging Time

Table 3.10     Summary of Measured Odour Emission for the Pig Farm 18/19/P43

Table 3.11     Estimated Odour Emission for the Retained Pig Farm 18/19/Y10

Table 3.12     Aerial Photo of the San Tin Barracks Sewage Treatment Works

Table 3.13     Estimated Odour Emission for the San Tin Barracks STW

Table 3.14     Conversion Factors to 5-second Mean Concentration

Table 3.15     Construction of DPs Involved in Development Stages

Table 3.16     Construction Activities with Major Dust Emission in Each Development Stage

Table 3.17     Estimated Cut and Fill Volumes for the Development by Year

Table 3.18     Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2031

Table 3.19     Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2031

Table 3.20     Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2034

Table 3.21     Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2034

Table 3.22     Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2039

Table 3.23     Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2039

Table 3.24     Worst Predicted Cumulative Odour Concentrations at Representative Air Sensitive Receivers

Table 3.25... Comparison of Odour Impact between Existing and Future Scenarios

 


 

List of Figures

Figure 3.1

Locations of Representative Sensitive Receivers

Figure 3.2

Contour of Predicted 10th Highest Cumulative Daily RSP Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.3

Contour of Predicted Cumulative Annual RSP Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.4

Contour of Predicted 19th Highest Cumulative Daily FSP Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.5

Contour of Predicted Cumulative Annual FSP Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.6

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.7

Contour of Predicted Cumulative Annual NO2 Concentration at 1.5 mAG (µg/m3) (Year 2031)

Figure 3.8

Contour of Predicted 10th Highest Cumulative Daily RSP Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.9

Contour of Predicted Cumulative Annual RSP Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.10

Contour of Predicted 19th Highest Cumulative Daily FSP Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.11

Contour of Predicted Cumulative Annual FSP Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.12

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.13

Contour of Predicted Cumulative Annual NO2 Concentration at 1.5 mAG (µg/m3) (Year 2034)

Figure 3.14

Contour of Predicted 4th Highest Cumulative 10-Min SO2 Concentration at 1.5 mAG (µg/m3) (Year 2031 and 2034)

Figure 3.15

Contour of Predicted 4th Highest Cumulative Daily SO2 Concentration at 1.5 mAG (µg/m3) (Year 2031 and 2034)

Figure 3.16

Contour of Predicted 10th Highest Cumulative Daily RSP Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.17

Contour of Predicted Cumulative Annual RSP Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.18

Contour of Predicted 19th Highest Cumulative Daily FSP Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.19

Contour of Predicted Cumulative Annual FSP Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.20

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.21

Contour of Predicted Cumulative Annual NO2 Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.22

Contour of Predicted 4th Highest Cumulative 10-Min SO2 Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.23

Contour of Predicted 4th Highest Cumulative Daily SO2 Concentration at 1.5 mAG (µg/m3) (Year 2039)

Figure 3.24

Contour of Predicted 5-Second Average Odour Concentration at 1.5 mAG (OU/m3)

Figure 3.25

Contour of Predicted 5-Second Average Odour Concentration at 5 mAG (OU/m3)

Figure 3.26

Contour of Predicted 5-Second Average Odour Concentration at 10 mAG (OU/m3)

Figure 3.27

Contour of Predicted 5-Second Average Odour Concentration at 15 mAG (OU/m3)

Figure 3.28

Contour of Predicted 5-Second Average Odour Concentration at 20 mAG (OU/m3)

Figure 3.29

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 5 mAG (µg/m3) (Year 2031)

Figure 3.30

Contour of Predicted Cumulative Annual NO2 Concentration at 5 mAG (µg/m3) (Year 2031)

Figure 3.31

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 5 mAG (µg/m3) (Year 2034)

Figure 3.32

Contour of Predicted Cumulative Annual NO2 Concentration at 5 mAG (µg/m3) (Year 2034)

Figure 3.33

Contour of Predicted 19th Highest Cumulative Hourly NO2 Concentration at 5 mAG (µg/m3) (Year 2039)

Figure 3.34

Contour of Predicted Cumulative Annual NO2 Concentration at 5 mAG (µg/m3) (Year 2039)

 

 

 

List of Appendices

 

Appendix 3.1         (Not Used)

Appendix 3.2         (Not Used)

Appendix 3.3         Calculation of EPP Emission Source

Appendix 3.4         Traffic Data

Appendix 3.5         Calculation of Vehicular Emission Source

Appendix 3.6         Calculation of Emissions Associated with Transport Interchange Hub

Appendix 3.7         Calculation of Emissions from Portal

Appendix 3.8         (Not Used)

Appendix 3.9         Emission Inventory of Major Stack in 4km Boundary

Appendix 3.10       Calculation of Odour Emission Source at EPP, FWPF and SPS

Appendix 3.11       Calculation of Odour Emission Source at Retained Pig Farm and RTS

Appendix 3.12       Calculation of Odour Emission Source at San Tin Barracks STW

Appendix 3.13       Determination of Surface Characteristics

Appendix 3.14       Detailed Prediction Results (Operation Phase, Year 2031)

Appendix 3.15       Detailed Prediction Results (Operation Phase, Year 2034)

Appendix 3.16       Detailed Prediction Results (Operation Phase, Year 2039)

Appendix 3.17       Detailed Prediction Results (Odour Impact)

Appendix 3.18       Frequency and Magnitude of Odour Exceedance for ASRs within Exceedance Zone

Appendix 3.19       Derivation of Cumulative Annual Average NOX-to-NO2 Conversion Equation using Jenkin Method

Appendix 3.20       Comparison of Odour Impact between Existing and Future Scenarios

 


3.                    Air quality

3.1                  Introduction

3.1.1.1           This section presents an assessment of potential air quality impacts arising from the construction and operation of the Project.  The air quality impact assessment has been conducted in accordance with the requirement in Annexes 4 and 12 of the EIAO-TM and the requirements in Section 3.4.3 and Appendix B and B-1 of the EIA Study Brief (ESB-340/2021).

3.1.1.2           An application for an Environmental Permit (EP) would be submitted for the following Schedule 2 Designated Projects (DPs) and the potential air quality impact due to these DPs during construction and operation phases are addressed in this assessment. These DPs include:

·          New primary distributor and new district distributor roads (DP1);

·          New San Tin Lok Ma Chau Effluent Polishing Plant (STLMC EPP) (DP2);

·          New Water Reclamation Plant (DP3);

·          Revitalisation of San Tin Eastern Main Drainage Channel (DP6);

·          Recreational Development within Deep Bay Buffer Zone 2 (DP7).

3.1.1.3           The following DPs would apply the EP through separate EIA studies but their potential impacts during construction and operation phases are also addressed in this assessment. These DPs include:

·          Refuse Transfer Station (RTS) (DP4);

·          400kV Electricity Substation (DP5).

3.2                  Environmental Legislations, Standards and Guidelines

3.2.1.1           The criteria for evaluating air quality impacts and the guidelines for air quality assessment are laid out in Annex 4 and Annex 12 of the EIAO-TM.

3.2.2              Air Quality Objectives & Technical Memorandum on EIA Process

3.2.2.1           Air Pollution Control Ordinance provides the statutory authority for controlling air pollutants from a variety of sources.  Hong Kong Air Quality Objectives (AQOs), which stipulate the maximum allowable concentrations over specific periods for typical pollutants, should be met.  The prevailing AQOs are summarized in Table 3.1.

Table 3.1     Air Quality Objectives for Hong Kong

Pollutants

Averaging Time

Concentration Limit (µg/m3) [1]

Number of Exceedance Allowed per Year

Respirable Suspended Particulates (RSP or PM10)[2]

24-hour

100

9

Annual [4]

50

N/A

Fine Suspended Particulates (FSP or PM2.5)[3]

24-hour

50

18 [5]

Annual [4]

25

N/A

Nitrogen Dioxide (NO2)

1-hour

200

18

Annual [4]

40

N/A

Sulphur Dioxide (SO2)

10-min

500

3

24-hour

50

3

Carbon Monoxide (CO)

1-hour

30,000

0

8-hour

10,000

0

Ozone (O3)

8-hour

160

9

Lead (Pb)

Annual[4]

0.5

NA

Note:

[1] Gaseous pollutants measured at 293K and 101.325kPa

[2] Suspended particulates in air with a nominal aerodynamic diameter of 10µm or smaller.

[3] Suspended particulates in air with a nominal aerodynamic diameter of 2.5µm or smaller.

[4] Arithmetic mean

[5] For government projects, the number of exceedance allowed per year for daily FSP is 18 times only.

3.2.2.2           In accordance with Annex 4 of EIAO-TM, the limit of 5 odour units based on an averaging time of 5 seconds for odour prediction assessment should not be exceeded at any air sensitive receiver (ASR).

3.2.3              Air Quality Standards for Non-AQO Criteria Pollutants

3.2.3.1           Aside from the AQO criteria pollutants mentioned in Section 3.2.2, Methane (CH4), Hydrogen Chloride (HCl), Hydrogen Fluoride (HF) and Formaldehyde (CH2O) would also be emitted from the combustion of biogas at the proposed biogas engine and boilers.  In accordance with Annex 4 of EIAO-TM, for air pollutants with no established criteria under the Air Pollution Control Ordinance nor in the EIAO-TM, standards or criteria should be adopted by recognized international organizations.  The air quality standards for these pollutants are therefore employed by making reference to standards by recognized international organizations and are detailed in Table 3.2.

Table 3.2     Air Quality Standards for Non-AQO Criteria Pollutants

Pollutants

Averaging Time

Air Quality Standard (µg/m3)

Reference

Methane

 

1-hour

600,000

TEEL-0 (the threshold concentration below which most people will experience no adverse health effects)  from

https://edms.energy.gov/pac/Docs/Revision_26_Table4.pdf

HCl

1-hour

2100

https://oehha.ca.gov/air/general-info/oehha-acute-8-hour-and-chronic-reference-exposure-level-rel-summary

Annual

20

Integrated Risk Information System, USEPA

HF

1-hour

240

https://oehha.ca.gov/air/general-info/oehha-acute-8-hour-and-chronic-reference-exposure-level-rel-summary

Annual

14

https://oehha.ca.gov/air/general-info/oehha-acute-8-hour-and-chronic-reference-exposure-level-rel-summary

Formaldehyde

30-min

100

World Health Organization Air Quality Guidelines for Europe (https://www.euro.who.int/__data/assets/pdf_file/0005/74732/E71922.pdf)

Annual

9

Office of Environmental Health Hazard Assessment (OEHHA) Toxicity Criteria Database, California, USA (http://www.oehha.ca.gov/tcdb/index.asp).

3.2.4              Air Pollution Control (Construction Dust) Regulation

3.2.4.1           Notifiable and regulatory works are under the control of Air Pollution Control (Construction Dust) Regulation.  This Project is expected to include notifiable works (foundation and superstructure construction and demolition) and regulatory works (dusty material handling and excavation).  Contractors and site agents are required to inform Environmental Protection Department (EPD) and adopt dust reduction measures to minimize dust emission, while carrying out construction works, to the acceptable level.

3.2.5              Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation

3.2.5.1           Air Pollution Control (Non-road Mobile Machinery) (Emission) Regulation comes into effect on 1 June 2015.  Under the Regulation, Non-road mobile machinery (NRMMs), except those exempted, are required to comply with the prescribed emission standards.  From 1 September 2015, all regulated machines sold or leased for use in Hong Kong must be approved or exempted with a proper label in a prescribed format issued by EPD.  Starting from 1 December 2015, only approved or exempted NRMMs with a proper label are allowed to be used in specified activities and locations including construction sites.  The Contractor is required to ensure the adopted machines or non-road vehicle under the Project could meet the prescribed emission standards and requirement.

3.2.6              Air Pollution Control (Fuel Restriction) Regulation

3.2.6.1           Air Pollution Control (Fuel Restriction) Regulation was enacted in 1990 to impose legal control on the types of fuel allowed for use and their sulphur contents in commercial and industrial processes to reduce sulphur dioxide (SO2) emissions. Since 1 October 2008, liquid fuel with a sulphur content not exceeding 0.005% by weight such as Ultra Low Sulphur Diesel (ULSD) shall be used, unless a valid certificate of compliance with emission limits issued by a competent examiner.

3.2.7              Development Bureau Technical Circular (Works)

3.2.7.1           Development Bureau Technical Circular (Works) No. 13/2020 is one of the environmental guidelines on timely application of temporary electricity and wider use of electric vehicles in public works contract.  The project team should timely apply for the temporary electricity and water supply with a target that the necessary cables/water mains laying works could be completed before the commencement of works contract. The project times should also specify the use of EV(s) and installation of a designated medium-speed charger for each EV in each public contract.

3.2.7.2           Development Bureau Technical Circular (Works) No. 1/2015 also requires that no exempted generators, air compressors, excavators and crawler cranes shall be allowed in the new capital works contracts of public works (including design and build contracts) with an estimated contract value exceeding $200 million, unless is at the discretion of the Architect/Engineer considering no feasible alternative.

3.3                  Description of Environment

3.3.1              Project Site Location

3.3.1.1           The site area of STLMC DN is about 610 hectares and locates to the west of Kwu Tung North and Fanling North New Development Areas (NDAs), Fanling and Sheung Shui New Towns and to the northeast of Yuen Long and Tin Shui Wai New Towns.  It is bound to the North by San Tin Highway and the Lok Ma Chau Boundary Control Point and to the South by San Tin Barracks and its neighbouring hills. 

3.3.1.2           The Project site currently has a mixed urban-rural character.  The predominant uses to the north are wetland as well as brownfield sites including open storage yards with some village developments. Land in the south is mainly occupied by low-density residential and village developments with some scattered brownfield operations (mainly open storage, warehouse and workshop uses).

3.3.1.3           No chimney emission source is found within the Project area.  However, there are nine existing livestock farms (seven pig farms and two chicken farms) located within the Project area, and two livestock farms (one pig farm and one chicken farm) located in the vicinity of the Project boundary.  These livestock farms are existing odour emission sources within the study area.   

3.3.2              Background Concentration by Observation

3.3.2.1           The nearest EPD Air Quality Monitoring Station to the Project Site is the North Air Quality Monitoring Station (AQMS) situated at Po Wing Road Sport Centre which has been operating since July 2020 and is under the land use type “New Town: Residential”.  Owing to insufficient data for time before Year 2020 and in Year 2020, the background observation refers to the next closest station with the same land use type instead, i.e. Yuen Long AQMS at Yuen Long District Office Building as published in Air Quality in Hong Kong. The annual average monitoring data recorded at EPD’s Yuen Long Air Quality Monitoring Station has shown an overall decreasing trend of pollutants’ concentration in the past five years. The recent five years (2018 – 2022) average concentrations of air pollutants relevant to the Project are summarized in Table 3.3.

Table 3.3     Average Concentrations of Pollutants in the Recent Five Years (Year 2018 – 2022) at Yuen Long EPD Air Quality Monitoring Station

Pollutant

Averaging Time

AQO

Pollutant Concentration (µg/m3)

2018

2019

2020

2021

2022

Respirable Suspended Particulates (RSP)

 

10th Highest 24-hour

100 (9)

75

83

77

73

56

Annual

50

37

37

30

30

25

Fine Suspended Particulates (FSP)

 

19th Highest 24-hour

50 (18)

41

38

33

36

38

Annual

25

20

20

16

17

16

Nitrogen Dioxide (NO2)

 

19th Highest

200 (18)

150

161

135

148

122

Annual

40

43

44

32

40

37

Sulphur Dioxide (SO2)

 

4th Highest 10-min

500 (3)

52

42

26

24

21

4th Highest 24-hour

50 (3)

16

11

10

14

7

3.3.2.2           Apart from the air quality monitoring data, EPD has released a set of background levels from “Pollutants in the Atmosphere and their Transport over Hong Kong”, PATH model (PATHv2.1).  The population intake is expected to take place in three major phases during Year 2031 and Year 2039. Relevant dataset of Year 2030 and Year 2035 in the assessment area extracted from PATHv2.1 model, and are presented in Table 3.4 and Table 3.5 respectively.


Table 3.4     Background Air Pollutants in Year 2030 Extracted from PATH Model (PATHv2.1)

Pollutant

Averaging Time

AQO [1]

Data Summary

PATH v2.1 Grid in Year 2030 [2]

28,51

28,52

28,53

29,50

29,51

29,52

29,53

29,54

29,55

30,50

30,51

30,52

30,53

Respirable Suspended Particulates (RSP) [3]

24-hr

100 (9)

Max.

91

91

91

91

88

93

91

91

93

92

88

94

91

10th Max.

68

70

70

69

68

70

69

70

70

69

68

69

68

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

Annual

50

-

27

28

27

28

27

28

27

27

28

27

27

28

27

Fine Suspended Particulates (FSP) [4]

24-hr

50 (18)

Max.

75

75

74

75

72

76

75

74

76

76

72

77

75

19th Max.

36

37

36

38

34

38

35

35

37

37

35

38

34

No. of Exceedance(s)

11

11

11

11

10

11

11

11

11

11

10

11

11

Annual

25

-

16

16

16

16

15

16

16

16

16

16

15

16

15

Nitrogen Dioxide (NO2)

1-hour

200 (18)

Max.

171

181

182

171

173

185

187

188

190

175

177

185

189

19th Max.

112

116

125

105

112

121

125

133

140

102

111

125

129

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

Annual

40

-

15

17

16

12

13

17

16

17

19

11

12

15

15

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

52

61

65

48

51

61

65

70

72

53

52

59

64

4th Max.

52

61

65

48

51

61

65

70

72

53

52

59

64

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

24-hr

50 (3)

Max.

16

17

18

15

16

17

18

20

23

15

16

16

18

4th Max.

12

13

14

11

12

12

13

15

16

11

11

12

13

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

 


Pollutant

Averaging Time

AQO [1]

Data Summary

PATH v2.1 Grid in Year 2030 [2]

30,54

30,55

31,50

31,51

31,52

31,53

31,54

31,55

32,51

32,52

32,53

32,54

Respirable Suspended Particulates (RSP) [3]

24-hr

100 (9)

Max.

91

94

91

90

93

92

91

92

92

94

95

92

10th Max.

69

71

69

69

68

68

69

70

69

69

69

68

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Annual

50

-

27

28

27

27

28

27

27

28

27

28

28

27

Fine Suspended Particulates (FSP) [4]

24-hr

50 (18)

Max.

74

76

74

73

77

76

75

75

76

78

79

75

19th Max.

35

37

37

37

37

36

35

36

38

38

39

35

No. of Exceedance(s)

11

11

11

11

11

11

11

11

11

11

11

10

Annual

25

-

15

16

15

15

16

16

16

16

16

16

16

15

Nitrogen Dioxide (NO2)

1-hour

200 (18)

Max.

194

195

176

179

183

188

195

199

179

182

185

190

19th Max.

134

142

91

101

113

129

134

141

96

103

116

132

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Annual

40

-

16

20

10

11

14

15

15

18

12

13

16

14

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

73

78

57

58

61

69

82

90

56

67

73

79

4th Max.

73

78

57

58

61

69

82

90

56

67

73

79

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

24-hr

50 (3)

Max.

21

24

15

16

16

18

22

24

16

16

17

20

4th Max.

14

16

11

11

12

13

14

17

11

12

12

13

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Notes:

[1] Values in ( ) mean the number of exceedances allowed per year.

[2] Bolded values mean exceedance of the AQO limit values.

[3] Annual FSP concentration is adjusted by adding 3.5 µg/m3 with reference to Guidelines on Choice of Models and Model Parameters.

[4] Daily and annual RSP concentration is adjusted by adding 11.0 µg/m3 and 10.3 µg/m3 respectively with reference to Guidelines on Choice of Models and Model Parameters.

[5] All concentration units are in microgram per cubic metre (µg/m3).


Table 3.5     Background Air Pollutants in Year 2035 Extracted from PATH Model (PATHv2.1)

Pollutant

Averaging Time

AQO [1]

Data Summary

PATH v2.1 Grid in Year 2035 [2]

28,51

28,52

28,53

29,50

29,51

29,52

29,53

29,54

29,55

30,50

30,51

30,52

30,53

Respirable Suspended Particulates (RSP) [3]

24-hr

100 (9)

Max.

90

91

90

91

87

92

91

91

93

92

88

93

91

10th Max.

68

70

70

69

67

70

69

70

70

69

68

69

67

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

Annual

50

-

27

28

27

27

26

28

27

27

28

27

27

28

27

Fine Suspended Particulates (FSP) [4]

24-hr

50 (18)

Max.

74

74

74

75

71

75

74

74

75

76

71

77

74

19th Max.

35

36

35

38

34

37

34

35

37

37

35

38

34

No. of Exceedance(s)

10

11

11

11

10

11

11

11

11

11

10

11

10

Annual

25

-

15

16

15

16

15

16

15

15

16

15

15

16

15

Nitrogen Dioxide (NO2)

1-hour

200 (18)

Max.

170

180

182

170

172

184

186

188

189

174

176

185

188

19th Max.

107

115

125

103

110

117

124

132

140

100

108

121

127

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

Annual

40

-

13

15

14

11

12

15

14

16

18

10

11

13

14

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

52

61

65

48

51

61

65

70

72

53

52

59

64

4th Max.

52

61

65

48

51

61

65

70

72

53

52

59

64

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0

24-hr

50 (3)

Max.

16

17

18

15

16

17

18

20

23

15

16

16

18

4th Max.

12

13

14

11

12

12

13

15

16

11

11

12

13

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

0


Pollutant

Averaging Time

AQO [1]

Data Summary

PATH v2.1 Grid in Year 2035 [2]

30,54

30,55

31,50

31,51

31,52

31,53

31,54

31,55

32,51

32,52

32,53

32,54

Respirable Suspended Particulates (RSP) [3]

24-hr

100 (9)

Max.

90

93

90

89

92

91

91

92

91

94

94

91

10th Max.

69

71

68

69

68

68

69

70

69

69

69

68

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Annual

50

-

27

28

27

27

27

27

27

27

27

28

28

27

Fine Suspended Particulates (FSP) [4]

24-hr

50 (18)

Max.

73

76

74

73

76

75

74

75

75

77

78

75

19th Max.

35

37

37

37

36

35

35

36

38

38

38

35

No. of Exceedance(s)

11

11

11

11

11

11

11

11

11

11

11

10

Annual

25

-

15

16

15

15

16

15

15

16

15

16

16

15

Nitrogen Dioxide (NO2)

1-hour

200 (18)

Max.

193

195

176

178

183

187

195

199

178

181

184

190

19th Max.

134

141

88

98

110

127

134

141

94

103

111

131

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Annual

40

-

15

19

9

10

12

13

14

17

10

12

13

13

Sulphur Dioxide (SO2)

10-min

500 (3)

Max.

73

78

57

58

61

69

82

90

56

67

73

79

4th Max.

73

78

57

58

61

69

82

90

56

67

73

79

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

24-hr

50 (3)

Max.

21

24

15

16

16

18

22

24

16

16

17

20

4th Max.

14

16

11

11

12

13

14

17

11

12

12

13

No. of Exceedance(s)

0

0

0

0

0

0

0

0

0

0

0

0

Notes:

[1] Values in ( ) mean the number of exceedances allowed per year.

[2] Bolded values mean exceedance of the AQO limit values.

[3] Annual FSP concentration is adjusted by adding 3.5 µg/m3 with reference to Guidelines on Choice of Models and Model Parameters.

[4] Daily and annual RSP concentration is adjusted by adding 11.0 µg/m3 and 10.3 µg/m3 respectively with reference to Guidelines on Choice of Models and Model Parameters.

[5] All concentration units are in microgram per cubic metre (µg/m3).


3.4                  Identification of Air Sensitive Receivers

3.4.1.1           In accordance with Annex 12 of the EIAO-TM, any domestic premises, hotel, hostel, hospital, clinic, nursery, temporary housing accommodation, school, educational institution, office, factory, shop, shopping centre, place of public worship, library, court of law, sports stadium or performing arts centre are considered as ASRs.

3.4.1.2           In accordance with Clause 3.4.4.2 of the EIA Study Brief, the assessment area for air quality impact assessment should be defined by a distance of 500m from the boundary of the Project site and the works of the Project.  Illustration of the proposed assessment area is presented in Figure 3.1.  For identification of the representative ASRs within the assessment area that would likely be affected by the potential impacts from the construction and operation of STLMC DN, a review has been conducted based on Revised Recommended Outline Development Plan (RODP) for STLMC DN and relevant available information including topographic maps, Outline Zoning Plans (OZPs) (such as OZP Plan No. S/YL-NTM/12 – Ngau Tam Mei, S/YL-ST/8 – San Tin, S/YL-MP/6 – Mai Po & Fairview Park HSK/2, S/KTN/3 – Kwu Tung North) and other published plans in the vicinity of the Project site.  The representative ASRs within the assessment area are identified and presented in Table 3.6 below.  Their locations are illustrated in Figure 3.1.


Table 3.6     Representative Air Sensitive Receivers in the vicinity of STLMC DN

ASR ID

Description

Land Use

Site ID

Shortest Distance from Site Boundary (m)

Assessment Height (mAG)

Potentially Affected

By Construction

By Operation

A01

Shek Wu Wai

V

Existing

< 5

1.5, 5, 10

A02

Shek Wu Wai

V

Existing

< 5

1.5, 5, 10

A03

Shek Wu Wai

V

Existing

< 5

1.5, 5, 10

A04

Village house

V

Existing

10

1.5, 5, 10

A05

San Tin Village

V

Existing

15

1.5, 5, 10

A06

Site office

V

Existing

30

1.5, 5, 10

A07

Wing Ping Tsuen

V

Existing

20

1.5, 5, 10

A08

Tun Yu School

E

Existing

130

1.5, 5, 10

A09

Tsing Lung Tsuen

V

Existing

35

1.5, 5, 10

A10

San Lung Tsuen

V

Existing

195

1.5, 5, 10

A11

Fan Tin Tsuen

V

Existing

230

1.5, 5, 10

A12

Yan Shau Wai

V

Existing

65

1.5, 5, 10

A13

Chau Tau Tsuen

V

Existing

10

1.5, 5, 10, 15

A14

Pun Uk Tsuen

V

Existing

70

1.5, 5, 10, 15, 20, 30

A15

Ha Wan Fisherman San Tsuen

V

Existing

75

1.5, 5, 10

A16

Lok Ma Chau Village

V

Existing

45

1.5, 5, 10, 15

A17

Mai Po San Tsuen

V

Existing

80

1.5, 5, 10

A18

Mai Po San Tsuen

V

Existing

65

1.5, 5, 10

A19

Rolling Hills

R

Existing

10

1.5, 5, 10

A20

Rolling Hills

R

Existing

10

1.5, 5, 10

A21

Scenic Heights

R

Existing

< 5

1.5, 5, 10

A22

Scenic Heights

R

Existing

10

1.5, 5, 10

A23

Maple Garden

R

Existing

20

1.5, 5, 10

A24

Maple Garden

R

Existing

10

1.5, 5, 10

A25

San Tin Barracks

N/A

Existing

20

1.5, 5

A26

San Tin Barracks

N/A

Existing

5

1.5, 5, 10, 15

A27

San Tin Barracks

N/A

Existing

25

1.5, 5

A28

San Tin Barracks

N/A

Existing

< 5

1.5, 5, 10

A29

San Tin Barracks

N/A

Existing

10

1.5, 5, 10, 15

A30

San Tin Barracks

N/A

Existing

45

1.5, 5

A31

Ki Lun Tsuen

V

Existing

185

1.5

A32

Europa Garden

R

Existing

460

1.5, 5, 10, 20, 30, up to 50

A33

Village house

V

Existing

175

1.5, 5, 10, 15

P101

Planned Primary School

E

E.2.5

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P102

Planned Public Housing [1]

RSc

RSc.2.1

Within project boundary

14, 15, 20, 30, up to 150

 

P103

Planned Public Housing

RSc

RSc.2.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 160

 

P104

Planned Public Housing [1]

RSc

RSc.2.2

Within project boundary

14, 15, 20, 30, up to 150

 

P105

Planned Public Housing [1]

RSc

RSc.2.2

Within project boundary

14, 15, 20, 30, up to 150

 

P106

Planned Public Housing [1]

RSc

RSc.2.2

Within project boundary

19, 20, 30, up to 160

 

P107

Planned Private Housing [1]

R

R1.2.3

Within project boundary

5, 10, 15, 20, 30, up to 150

 

P108

Planned Private Housing [1]

R

R1.2.3

Within project boundary

13, 15, 20, 30, up to 150

 

P109

Planned Private Housing

R

R1.2.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P110

Planned Village Resite

V

V.3.1

Within project boundary

1.5, 5, 10

 

P111

Planned Village Resite

V

V.3.1

Within project boundary

1.5, 5, 10

 

P112

Planned Logistics, Storage and Warehouse

OU(LSW)

OU(LSW).1.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P113

Planned Information and Technology - Zone 2

OU(I&T)

OU(I&T)2.1.1

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P114

Planned Information and Technology - Zone 2

OU(I&T)

OU(I&T)2.1.1

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P115

Planned Information and Technology - Zone 2 [2]

OU(I&T)

OU(I&T)2.1.1

Within project boundary

5, 10, 20, 30, up to 90

 

P116

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.7

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 100

 

P117

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.7

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 100

 

P118

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.8

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P119

Planned Information and Technology - Zone 3 [3]

OU(I&T)

OU(I&T)3.1.8

Within project boundary

20, 30, up to 70

 

P120

Planned Information and Technology - Zone 3 [3]

OU(I&T)

OU(I&T)3.1.8

Within project boundary

20, 30, up to 70

 

P121

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.7

Within project boundary

1.5, 5, 10, 20, 30, up to 70

 

P122

Planned Information and Technology - Zone 3 [2]

OU(I&T)

OU(I&T)3.1.5

Within project boundary

5, 10, 15, 20, 30, up to 110

 

P123

Planned Information and Technology - Zone 3
(Government Data Centre)

OU(I&T)

OU(I&T)3.1.6

Within project boundary

1.5, 5, 10, 20, 30, up to 50

 

P124

Planned Information and Technology - Zone 3
(Government Data Centre)

OU(I&T)

OU(I&T)3.1.6

Within project boundary

1.5, 5, 10, 20, 30, up to 50

 

P125

Planned Information and Technology - Zone 3 [2]

OU(I&T)

OU(I&T)3.1.4

Within project boundary

5, 10, 20, 30, up to 70

 

P126

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.4

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P127

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.1

Within project boundary

1.5, 5, 10, 15, 20

 

P128

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.1

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P129

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.1

Within project boundary

1.5, 5, 10, 20, 30, up to 80

 

P130

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P131

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 120

 

P132

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 120

 

P133

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P134

Planned Information and Technology - Zone 3 (Data Centre) [2]

OU(I&T)

OU(I&T)3.1.2

Within project boundary

5, 10, 20, 30, up to 60

 

P135

Planned Information and Technology - Zone 3 (Data Centre)

OU(I&T)

OU(I&T)3.1.2

Within project boundary

1.5, 5, 10, 20, 30, up to 60

 

P136

Planned Information and Technology - Zone 3 (Data Centre)

OU(I&T)

OU(I&T)3.1.1

Within project boundary

1.5, 5, 10, 20, 30, up to 80

 

P137

Planned AFCD Fisheries Research Centre

OU(I&T)

OU(I&T)6.1.1

Within project boundary

1.5, 5, 10

 

P138

Planned Customs Dog Base

GIC

G.1.1

Within project boundary

1.5, 5, 10

 

P139

Planned Customs Dog Base

GIC

G.1.1

Within project boundary

1.5, 5, 10

 

P140

Planned Information and Technology - Zone 5

OU(I&T)

OU(I&T)5.1.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P141

Planned Information and Technology - Zone 5

OU(I&T)

OU(I&T)5.1.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P142

Planned Information and Technology - Zone 5

OU(I&T)

OU(I&T)5.1.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P143

Planned Information and Technology - Zone 5 [2]

OU(I&T)

OU(I&T)5.1.2

Within project boundary

5, 10, 15, 20, 30

 

P144

Planned Information and Technology - Zone 5

OU(I&T)

OU(I&T)5.1.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P145

Planned Open Space

O

O.1.2

Within project boundary

1.5

 

P146

Planned Open Space

O

O.1.2

Within project boundary

1.5

 

P147

Planned Open Space

O

O.1.2

Within project boundary

1.5

 

P148

Planned Open Space

O

O.1.2

Within project boundary

1.5

 

P149

Planned Open Space

O

O.1.3

Within project boundary

1.5

 

P150

Planned Open Space

O

O.1.3

Within project boundary

1.5

 

P151

Planned Open Space

O

O.1.3

Within project boundary

1.5

 

P152

Planned AFCD Fisheries Research Centre

OU(I&T)

OU(I&T)6.1.1

Within project boundary

1.5, 5, 10

 

P153

Planned Secondary School

E

E.2.4

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P201

Planned Reserve

GIC

G.5.4

Within project boundary

1.5, 5, 10, 15, 20, 30, 40

 

P202

Planned Fire Service NT Workshop, Uniform Store and General Store

GIC

G.5.3

Within project boundary

1.5, 5, 10

 

P203

Planned Sports Centre

GIC

G.5.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P204

Planned 2 Primary School

E

E.2.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P205

Planned 2 Primary School

E

E.2.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P206

Planned Reserve (Potential Education Facilities)

E

E.5.3

Within project boundary

1.5, 5, 10, 15, 20, 30, 40

 

P207

Planned Reserve

GIC

G.5.5

Within project boundary

1.5, 5, 10, 15, 20, 30, 40

 

P208

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.9

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 110

 

P209

Planned Information and Technology - Zone 3

OU(I&T)

OU(I&T)3.1.9

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 110

 

P210

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.3

Within project boundary

1.5, 5, 10, 20, 30, up to 80

 

P211

Planned Lok Ma Chau Police Station cum Operational Base, Petrol Station and Dangerous Goods Storage

GIC

G.1.5

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P213

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.3

Within project boundary

1.5, 5

 

P214

Planned Logistics, Storage and Warehouse

OU(LSW)

OU(LSW).1.2

Within project boundary

1.5, 5, 10, 20, 30, up to 50

 

P215

Planned Information and Technology - Zone 1 [1]

OU(I&T)

OU(I&T)1.1.2

Within project boundary

7, 10, 15, 20, 30, up to 60

 

P216

Planned Information and Technology - Zone 1 [1]

OU(I&T)

OU(I&T)1.1.2

Within project boundary

7, 10, 15, 20, 30, up to 60

 

P217

Planned Information and Technology - Zone 1

OU(I&T)

OU(I&T)1.1.2

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P219

Planned Information and Technology - Zone 2

OU(I&T)

OU(I&T)2.1.2

Within project boundary

1.5, 5, 10, 20, 30, up to 70

 

P220

Planned Information and Technology - Zone 2

OU(I&T)

OU(I&T)2.1.2

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 120

 

P221

Planned Information and Technology - Zone 2 [2]

OU(I&T)

OU(I&T)2.1.2

Within project boundary

5, 10, 15, 20, 30, up to 120

 

P222

Planned 3 Secondary School

E

E.2.3

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P223

Planned 3 Secondary School

E

E.2.3

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P224

Planned Public Housing [1]

RSc

RSc.2.6

Within project boundary

14, 15, 20, 30, up to 150

 

P225

Planned Public Housing [1]

RSc

RSc.2.6

Within project boundary

14, 15, 20, 30, up to 150

 

P226

Planned Public Housing [1]

RSc

RSc.2.4

Within project boundary

14.5, 15, 20, 30, up to 150

 

P227

Planned Public Housing [1]

RSc

RSc.2.4

Within project boundary

14.5, 15, 20, 30, up to 150

 

P228

Planned Private Housing [1]

R

R1.2.1

Within project boundary

5, 10, 15, 20, 30, up to 140

 

P229

Planned Private Housing [1]

R

R1.2.1

Within project boundary

10, 15, 20, 30, up to 140

 

P230

Planned Private Housing [1]

R

R1.2.2

Within project boundary

5, 10, 15, 20, 30, up to 140

 

P231

Planned Public Housing [1]

RSc

RSc.2.5

Within project boundary

9.5, 10, 15, 20, 30, up to 150

 

P232

Planned Open Space

O

O.5.3

Within project boundary

1.5, 5, 10

 

P233

Planned Primary School

E

E.2.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P234

Planned Reserve

GIC

G.5.12

Within project boundary

1.5, 5, 10, 15, 20, 30, 40

 

P235

Planned Primary School

E

E.5.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P236

Planned GIC Complex [3]

GIC

G.5.11

Within project boundary

20, 30, up to 50

 

P237

Planned Joint User Government Office [3]

GIC

G.5.10

Within project boundary

20, 30, up to 110

 

P238

Planned Potential Healthcare Facilities [3]

GIC

G.5.8

Within project boundary

20, 30, up to 80

 

P239

Planned Reserve [3]

GIC

G.5.9

Within project boundary

20, 30, 40

 

P240

Planned Primary School

E

E.5.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P241

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 15, 20

 

P242

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 15, 20

 

P243

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 20, 30, up to 50

 

P244

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 20, 30, up to 50

 

P245

Planned Secondary School

E

E.3.3

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P246

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 120

 

P247

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 120

 

P248

Planned Logistics, Storage and Warehouse

OU(LSW)

OU(LSW).4.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 150

 

P249

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P250

Planned Logistics, Storage and Warehouse

OU(LSW)

OU(LSW).4.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 150

 

P251

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.4

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 140

 

P252

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.4

Within project boundary

1.5, 5, 10, 20, 30, up to 90

 

P253

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.3

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 140

 

P254

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 130

 

P255

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.2

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 150

 

P256

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.5

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 150

 

P257

Planned Information and Technology - Zone 4

OU(I&T)

OU(I&T)4.4.5

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 160

 

P258

Planned Public Housing [1]

RSc

RSc.3.2

Within project boundary

14, 15, 20, 30, up to 150

 

P259

Planned Public Housing [1]

RSc

RSc.3.2

Within project boundary

14, 15, 20, 30, up to 150

 

P260

Planned Primary School

E

E.3.1

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P261

Planned Public Housing [1]

RSc

RSc.3.1

Within project boundary

14, 15, 20, 30, up to 150

 

P262

Planned Youth Facilities

GIC

G.3.2

Within project boundary

1.5, 5, 10, 20, 30, up to 80

 

P263

Planned FSD staff quarters, Divisional Fire Station-cum-Ambulance Depot, Operational Base for Tactical Support Unit and Community Emergency Preparedness Experiential Learning

GIC

G.3.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 190

 

P264

Planned Private Housing [1]

R

R1.3.2

Within project boundary

10, 15, 20, 30, up to 140

 

P265

Planned Private Housing [1]

R

R1.3.2

Within project boundary

5, 10, 15, 20, 30, up to 140

 

P266

Planned Private Housing [1]

R

R1.3.1

Within project boundary

10, 15, 20, 30, up to 140

 

P267

Planned Private Housing [1]

R

R1.3.1

Within project boundary

10, 15, 20, 30, up to 140

 

P268

Planned 1 Primary School + 1 Secondary School

E

E.3.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P269

Planned 1 Primary School + 1 Secondary School

E

E.3.2

Within project boundary

1.5, 5, 10, 15, 20, 30

 

P270

Planned Sport Centre [2]

GIC

G.5.14

Within project boundary

5, 10, 15, 20, 30

 

P271

Planned Open Space

O

O.1.1

Within project boundary

1.5

 

P272

Planned Open Space

O

O.1.1

Within project boundary

1.5

 

P301

Planned Public Housing [1]

RSc

RSc.2.3

Within project boundary

14, 15, 20, 30, up to 180

 

P302

Planned Public Housing [1]

RSc

RSc.2.3

Within project boundary

14, 15, 20, 30, up to 170

 

P303

Planned Public Housing [1]

RSc

RSc.2.3

Within project boundary

14, 15, 20, 30, up to 170

 

P304

Planned Mix use (San Tin Station) [1]

OU(MU)

OU(MU)1.2.1

Within project boundary

17, 20, 30, up to 170

 

P305

Planned Mix use (San Tin Station)

OU(MU)

OU(MU)1.2.1

Within project boundary

1.5, 5, 10, 15, 20, 30, up to 190

 

P306

Planned Mix use (San Tin Station) [1]

OU(MU)

OU(MU)1.2.1

Within project boundary

17, 20, 30, up to 160

 

P307

Planned Mix use (San Tin Station) [1]

OU(MU)

OU(MU)1.2.1

Within project boundary

17, 20, 30, up to 170

 

P308

Planned Public Housing [1]

RSc

RSc.2.7

Within project boundary

14, 15, 20, 30, up to 150

 

P309

Planned Public Housing [1]

RSc

RSc.2.7

Within project boundary

14, 15, 20, 30, up to 150

 

P310

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 15, 20

 

P311

Planned Cultural & Recreational Complex

GIC

G.5.7

Within project boundary

1.5, 5, 10, 15, 20

 

P312

Planned Reserve

GIC

G.3.3

Within project boundary

1.5, 5, 10, 15, 20, 30, 40

 

P313

Planned Reserve [2]

GIC

G.5.13

Within project boundary

5, 10, 15, 20, 30, 40

 

P314

Planned Mixed use (Station near Chau Tau) [1]

OU(MU)

OU(MU)2.1.1

Within project boundary

27, 30, 40, up to 140

 

P315

Planned Mixed use (Station near Chau Tau) [1]

OU(MU)

OU(MU)2.1.1

Within project boundary

22, 30, 40, up to 200

 

P316

Planned Mixed use (Station near Chau Tau) [1]

OU(MU)

OU(MU)2.1.1

Within project boundary

27, 30, 40, up to 160

 

P317

Planned Wetland Conservation Park Management Office

GIC

G.1.3

Within project boundary

1.5, 5, 10

 

Remarks:

RSc – Public Housing Site, R – Private Housing, OU(MU) – Other Specified Uses (Mixed Use), V – Village Type Development, E – Education, GIC – Government, Institution or Community, OU(I&T) – Other Specified Uses (I&T Park), OU(LSW) – Other Specified Uses (Logistics Storage and Warehouse), N/A – Unclassified.

[1] Podium design has been adopted in the block layout. There is no air sensitive uses, including openable window, fresh air intake of central air conditioning, and recreational uses in open space below the first assessment height.

[2] The lobby at 1.5mAG is central air conditioned. There is no air sensitive uses, including openable window, fresh air intake of central air conditioning, and recreational uses in open space below 5mAG.

[3] The lobby at 1.5mAG is central air conditioned. There is no air sensitive uses, including openable window, fresh air intake of central air conditioning, and recreational uses in open space below 20mAG.

 

 

 

 

                                                                                                                                                                                                                                

                                                                                                                                                                                                                                


3.5                  Identification of Environmental Impacts

3.5.1              Construction Phase

3.5.1.1           Major construction works for the Project would include the site development in the RODP and construction of the 7 DPs which include:

·          Construction of New primary distributor and district distributor roads (DP1);

·          Construction of New San Tin Lok Ma Chau Effluent Polishing Plant (STLMC EPP) (DP2);

·          Construction of New Water Reclamation Plant (DP3);

·          Construction of Refuse Transfer Station (RTS) (DP4);

·          Construction of 400kV Electricity Substation (DP5).

·          Revitalization of San Tin Eastern Main Drainage Channel (STEMDC) (DP6);

·          Recreational Development within Deep Bay Buffer Zone 2 (DP7).

3.5.1.2           Based on the tentative construction programme, the Project will be developed in three stages, namely Initial Phase, Main Phase and Remaining Phase. The construction works of Initial Phase will commence in Q4 2024 and the population intake is expected in Year 2031 – 2033. Main Phase will commence in Year 2027 and its population intake is expected in Year 2034 – 2038. Remaining Phase will commence in 2032 and population intake is expected in Year 2039. The tentative typical working hours would be 7:00am to 7:00pm on weekdays. A summary of the key construction activities is given below and the locations of the Project Areas are shown in Appendix 2.1.  Details of the tentative construction programme is presented in Appendix 2.2. 

 

(A)  Initial Phase

·          North of the Project Area

-       Site Formation and development for drainage pumping station, sewerage pumping station, G/IC, I&T, Open Space and Amenity areas;

-       Construction of Primary Distributor Road P1, District Distributor Roads D4 and D6, and local roads;

·          Northeast of the Project Area

-       Site Formation and development for drainage pumping station, G/IC, I&T and Amenity areas, 400kV ESS, Refuse Transfer Station cum Resource Recovery Facilities, Logistic, Storage and Warehouse;

-       Construction of Primary Distributor Road P1, District Distributor Road D6, and local roads;

·          Northwest of the Project Area

-       Site Formation and development for G/IC, I&T, LSW, Amenity areas and Open Space;

-       Construction of district Distributor Road D3 and local roads;

·          Southwest of the Project Area

-       Site Formation and development for Effluent Polishing Plant, Sewage Pumping Station, Water Reclamation Plant, G/IC, Residential Development and Amenity areas;

-       Construction of District Distributor Roads D1 and D2, and local roads;

·          South of San Tin Interchange

-       Site Formation and development for Sewerage Pumping Station, G/IC and Amenity areas;

-       Construction of District Distributor Road D1 and local roads;

·          South of the Project Area

-       Site Formation and development for Water Service Reservoirs;

-       Widening of sections of San Tin Highway and construction of local roads.

 

(B)  Main Phase

·          North of the Project Area

-       Site Formation and development for I&T areas;

·          Northeast of the Project Area

-       Site Formation and development for I&T areas;

·          Northwest of the Project Area

-       Site Formation and development for G/IC, I&T and Open Space areas;

·          Southwest of the Project Area

-       Site Formation and development for G/IC and Amenity areas;

·          South of San Tin Interchange

-       Site Formation and development for G/IC, Residential Development, Open Space and Amenity areas;

-       Construction of District Distributor Road D1, and local roads

·          South of the Project Area

-       Site Formation and development for G/IC, Residential Development, Open Space and Amenity areas;

-       Construction of District Distributor Roads D1 and D2, and local roads;

·          Southeast of the Project Area

-       Site Formation and development for G/IC, I&T, LSW, Open Space and Amenity areas, and 400kV ESS;

-       Construction of District Distributor Road D5 and local roads.

 

(C)  Remaining Phase

·          Northeast of the Project Area

-       Site Formation and development for Commercial Development areas;

·          Northwest of the Project Area

-       Site Formation and development for Wetland Conservation Park Management Office;

·          South of San Tin Interchange

-       Site Formation and development for G/IC areas;

·          South of the Project Area

-       Site Formation and development for G/IC, Residential and Commercial Development and Open Space areas;

-       Construction of District Distributor Road D1.

Identification of Key Air Pollutants of Emission from Construction Activities

3.5.1.3           Most of the above construction activities would involve excavation, spoiling handling, backfilling of different scale. These dusty construction activities and wind erosion of exposed sandfill areas would cause potential fugitive emission in particulates. Regular water on exposed construction sandfill areas, good site practices and dust suppression measures as stipulated in the Air Pollution Control (Construction Dust) Regulation will be implemented to minimize the potential dust impact.

3.5.1.4           On-site use of diesel-powered engines is also the potential source for other gaseous pollutants, such as NO2, SO2, CO and smoke. The emissions from the NRMM are regulated under the Air Pollution Control (Non-Road Mobile Machinery) (Emission) Regulation.  Fuel with sulphur content not exceeding 0.005% by weight will be used to minimize SO2 emission in accordance with the Air Pollution Control (Fuel Restriction) Regulation. In addition, the use of NRMMs with exempted label under the Air Pollution Control (NRMM) Regulation will be avoided as far as practicable. The equipment would also be properly maintained to minimize any emissions. Furthermore, the use of electrified NRMMs is unlikely to cause significant smoke and gaseous emissions. On-site power supply will be provided and the use of diesel generators and machinery will be avoided during the construction stage, as far as practicable. In view of the minor impact by NRMMs, particulates from construction activities would be the major air pollutant during construction phase. 

Concurrent Project

3.5.1.5           Northern Link (NOL) Phase 2 by MTR Corporate Limited is one of the concurrent project which includes a railway of about 10.7 kilometres between the Kam Sheung Road Station and KTU Station, with three intermediate stations at San Tin, Ngau Tam Mei and Au Tau. The location of NOL is illustrated in Figure 2.15. The construction will commence in Year 2025 for completion by Year 2034. San Tin Station and associated ventilation shafts and ancillary facilities which lie inside STLMC DN is expected be constructed at the same time as the construction works for the Project according to the latest construction programme.

3.5.1.6           Kwu Tung North New Development Area (KTN NDA) – Advance Works and Remaining Phase are the concurrent projects in the east of STLMC DN. The location of KTN NDA is illustrated in Figure 2.15. The construction works of Advance Works commenced in Year 2019 for completion by Year 2026, while the one for Remaining Phase will commence in Year 2024 for completion in Year 2031.  Referring to the latest construction programme, most of the site formation work under Advance Works were completed and would likely be completed by end 2024. 

3.5.1.7           Development of Lok Ma Chau Loop – Main Works Package 1 is to develop the Loop with higher education as the leading land use, complemented by high-tech R&D and C&C industries. The location of the Loop is illustrated in Figure 2.12. The project comprises the development and supporting infrastructure which includes road within the Loop, external connection roads such as Western Connection Road, Eastern Connection Road and the Direct Link to MTR LMC Station, sewage treatment works, flushing water service reservoir, district cooling systems (provisional), fire station cum ambulance depot, electricity substations, drainage and sewage systems, water supply network and public utilities. The construction works has commenced in July 2021 for operation commencement in Year 2026. In accordance with the construction programme, site clearance and site formation works have been completed.  It is anticipated that the coming construction activities would major involve in superstructural works and would not be dusty activities.  With the implementation of the dust suppression measures as recommended in the EIA Report for Development of Lok Ma Chau Loop, the potential cumulative dust impact is anticipated to be minimal. 

Review of Dust Monitoring Data of Past Project

3.5.1.8           A review of dust monitoring data during construction phase of similar infrastructure projects including North East New Territories New Development Areas (NENT) and Hong Kong Express Rail Link (XRL) has been conducted.  The NENT is a large-scale development project and the project site area is about 614 ha which is similar to that of this Project (610 ha).  The XRL is also a large scope infrastructural project and its length is approximately 26 km long which is longer than that of NOL.  XRL involves the operation of concrete batching plant during construction while NOL also requires concrete batching plant of similar scale to support its construction. The work sites of both projects were located in close vicinity of ASRs.  Good site practices and dust suppression measures as recommended in the EIA Report were adopted.  Some existing ASRs were located in close vicinity of construction works and concrete batching plant, and selected as dust monitoring stations for impact monitoring during construction phase of the projects.  In view of the above, the data of these monitoring stations of both projects were selected for review.    

3.5.1.9           For NENT Project, the measured 1-hr TSP and 24-hr TSP levels at all monitoring stations were below the action levels of 300 µg/m3 and 150 µg/m3 respectively and limit levels of 500 µg/m3 and 260 µg/m3 respectively during site clearance and site formation with the monitoring locations located from the work site boundary from 1m to 169 m.  No exceedance of action level and limit level was recorded.

3.5.1.10        For XRL Project, during 2010 – 2018, the measured 24-hr TSP levels at all monitoring stations located from 11m – 153m from the work site boundary complied with limit level of 260 µg/m3 except two measurement events of exceedance recorded.  After investigation, the exceedance was not related to the construction of the project.  In fact, over 99% of the measured 24-hr TSP levels at all monitoring stations were below the action level (i.e. 146 - 217 µg/m3) during the whole construction period.  

3.5.1.11        In view of the insignificant dust impact caused by these past similar scale projects, the potential construction dust impact by the Project is evaluated qualitatively.

3.5.2              Operation Phase

Vehicular Emission from Proposed Primary Distributor and District Distributor Roads (DP1) and Other Roads

3.5.2.1           Primary Distributor Road P1, District Distributors Road D1, D2, D3, D4, D5 and D6, collectively as DP1, and associated connecting local roads are proposed under the Project to support the population of the Project. The locations of these roads are illustrated in Figure 2.1. Potential vehicular emission would arise from these proposed roads and affect both existing and planned ASRs.

3.5.2.2           Vehicular emission from existing roads within 500m assessment area also contributes to the ambient air quality.  Major roads within 500m assessment area include San Tin Highway, Fanling Highway, Castle Peak Road – Mai Po and Castle Peak Road – San Tin, etc. These open road emissions were also considered in the modelling assessment.

Vehicular Emission associated with Concerned Facilities

3.5.2.3           Facilities with frequent operation associated with vehicles also contribute to ambient air quality by vehicular running, idling and start emission within the facilities of concerned. The facilities of concern within assessment area, such as PTI, logistics facilities, parking sites, were identified and their locations are illustrated in Appendix 3.6. There are existing and planned PTIs within 500m assessment area. Two Transport Interchange Hub (TIH) are proposed under RODP to provide for a convenient and pleasant setting for multi-modal transport interchange activities.

3.5.2.4           Eight existing HGV / Coach parking sites identified within 500m assessment area are generally small, with less than 20 HGV / Coach parking lots. Location ID8 will be removed before the operation phase of the Project in Year 2031 and Location ID 6 & 7 are occupied by vehicle dealer with very limited access of vehicle. 24-hour site surveys were conducted at the five existing HGV/Coach parking sites (ID1 – 5) with infrequent access of HGV and coach observed throughout the day, hence limited vehicular emission from these parking sites is expected. Trip frequencies of the parking sites (ID1 – 5) can be found in Appendix 3.6. Start emissions of all vehicle types (except FBSD and FBDD) from these parking sites (ID1 – 5) are considered by broad-brush approach in which the emissions are allocated along the concerned roads around these HGV/Coach parking lots.

3.5.2.5           In summary, the concerned facilities considered in the modelling assessment by precise approach include:

·         Existing Lok Ma Chau Station PTI;

·         Planned Lok Ma Chau Loop PTI;

·         Planned TIH at proposed station near Chau Tau;

·         Planned San Tin Station TIH; 

·         Planned PTI in Pang Loon Tei; and

·         Three existing logistics facilities.

Proposed Effluent Polishing Plant (EPP) (DP2)

3.5.2.6           A new sewage treatment works, namely tertiary effluent polishing plant, is proposed at Site OU(EPP)5.3 to support the population of the Project. The treatment capacity of the EPP is proposed to be at 125,000 m3/day. Apart from the sewage treatment works, the proposed EPP will also offer the conversion of sewage gas into electricity to support the plant’s operation or for export. Its location is illustrated in Appendix 3.3.

3.5.2.7           Biogas is expected to be generated as a by-product from the anaerobic digestion process in the co-digestion of sludge and food wastes.  Biogas generated will be fed to the sulphur absorption vessels to remove the hydrogen sulphide (H2S) before storage in the biogas holders.  The stored biogas will be pretreated and fed to the combined heat and power (CHP) units and steam boiler as fuel.  The combustion of biogas in the CHP generator produces electricity and heat for sludge digester, while heat produced from the combustion of biogas in the steam boiler serves the heating demands in the sludge treatment process use.  Continuous heating is required in the anaerobic co-digestion process for the biomass feeding to the digesters and heat loss compensation from the digesters.  Heat produced by the CHP units will supply heat for the digestion process.  Duty plus sufficient standby CHP units are expected to ensure uninterrupted power and heat generation.  Meanwhile, steam from the steam boiler will be utilized to provide the needed thermal energy for the sludge dryer to achieve the required dryness in the digested sludge for disposal.  Both flue gas emission from the CHP units and boiler were considered in the modelling assessment.

3.5.2.8           Waste gas burners are to be connected to the biogas holders and combust any waste gas in case of emergency.  Duty plus sufficient standby CHP units are to ensure uninterrupted biogas consumption. In view of the high operation reliability of CHPs and provision of standby units, biogas flaring by waste gas burner would be rare and only be carried out during emergency. 

Proposed FWPF and RTS

3.5.2.9           The proposed FWPF and RTS involve no anerobic digestion, biogas generation nor biogas combustion. No air pollutant emission is expected from these two proposed facilities, except odour emission. The processes in details and associated odour emissions are addressed in Section 3.5.3.

Revitalisation of STEMDC (DP6) and Recreational Development within Deep Bay Buffer Zone 2 (DP7)

3.5.2.10        The revitalisation of STEMDC involves naturalism of channel banks and planting with native vegetation to enhance ecological and landscape value, and flood attenuation measures to improve flood resilience. Recreational development within Deep Bay Buffer Zone 2 would propose open space with tree and water features for enjoy of public, which would not cause any air emission. No air and odour emission is anticipated during the operation of DP6 and DP7.

Proposed Innovation and Technology Uses

3.5.2.11        The proposed Innovative and Technology (I&T) uses in STNLMC DN involve developments including R&D facilities, research and production labs, data centres, offices, convention premises, potential advance manufacturing uses, and other general uses such as talent accommodation, retails and food & beverages, open space, recreation and entertainment facilities, etc. No air and odour emission is expected from these uses. Should there be any noxious emission in the future use, separate air quality impact assessment shall be conducted to show acceptable air quality impact on the nearby uses based on the prevailing AQOs. Relevant regulations such as APCO shall also be followed. 

Proposed Healthcare Facilities

3.5.2.12        Potential healthcare facilities are proposed at Site G.5.8 under the RODP. To support its daily operation, it will be equipped with electric boiler. Therefore, no air quality impact due to the healthcare facilities is anticipated.

Concurrent Project

3.5.2.13        NOL will operate to provide a mass transit for the population in STLMC DN. NOL will be electric-powered, and air-emission free during the normal operation.  Exhaust for general ventilation and smoke extraction facilities will be carefully positioned to avoid causing any nuisance to the ambient. The potential air quality impact during operation phase was thus considered limited and was not assessed.

3.5.2.14        Planned roads under KTN NDA lie within 500m assessment area of STLMC DN. Furthermore, the traffic induced by population in KTN NDA would travel along Fanling Highway and San Tin Highway, which run through the STLMC DN and would cause indirect air quality impact on the existing and planned ASRs under the RODP. The potential air quality impact due to planned roads and induced traffic was considered in the modelling assessment. Their locations are illustrated in Appendix 3.5.

3.5.2.15        Planned roads under Lok Ma Chau Loop also lies within 500m assessment area of STLMC DN. Similarly, the traffic induced by population in Lok Ma Chau Loop would travel along Ha Wan Tsuen East Road and Lok Ma Chau Road which run through the STLMC DN and would cause indirect air quality impact on the existing and planned ASRs under the RODP.  Some of planned roads under Strategic Study on Major Roads beyond 2030 would also lie within 500m assessment area of STLMC DN. The potential air quality impact due to planned roads and induced traffic was considered in the modelling assessment. Their locations are illustrated in Appendix 3.5.

Major Point Source within 4 km from the Project Boundary

3.5.2.16        The asphalt plant (Tar and Bitumen Works) at Man Kam To Road operated by K. Wah Asphalt Limited under SP Licence No. L-15-035(2) is identified as a major point source within 4 km from the Project boundary. The location of the asphalt plant is illustrated in Appendix 3.9.  The terrain in Northern Hong Kong is generally flat.  The plume from the stack would transport long distance encountering no physical obstruction and cause direct impact on area on the Project site.  Therefore, the stack sources of this asphalt plant were considered in the modelling assessment.

Identification of Key Air Pollutants of Emission during Operation Phase

3.5.2.17        Vehicular emission is the dominant source of air pollutants within the development plan. The key air pollutants associated with vehicular emission during operation phase include NOX, RSP and FSP.

3.5.2.18        The combustion during the operation of CHPs and boilers of the proposed EPP also cause air pollutant emissions.  The key air pollutants associated with biogas combustion include NOX, RSP, FSP and SO2. Trace amount of carbon monoxide, methane, formaldehyde, HCl and HF are also expected from the combustion of biogas.

3.5.3              Operation Phase (Odour Impact)

Proposed Effluent Polishing Plant (EPP) (DP2)

3.5.3.1           A new sewage treatment works, namely tertiary effluent polishing plant, is proposed at Site OU(EPP)5.3 to support the population of the Project. The treatment capacity of the EPP is proposed to be at 125,000 m3/day. The proposed EPP will offer tertiary treatment to the sewage with food waste/sewage sludge co-digestion.  The EPP would include inlet works (screen, inlet pump, conveyor, compactor, grit classifier, equalization tank, and skip), sewage treatment units (sedimentation tanks, and biological treatment unit), sludge treatment units (sludge blend tank, centrifuge, sludge holding tank, dryer, sidestream treatment facilities and skip) and food waste reception facilities (food waste bunker and preparation tank), etc.  All these treatment units/facilities with potential odour emission will be covered and the exhausted air will be conveyed to deodourizers for treatment before exhausting to the environment.  The potential odour source during the operation phase of the proposed EPP would therefore be the exhaust of the deodourizing units.  The preliminary layout plan of the EPP is shown in Appendix 3.10. The emission from deodorizing units of proposed EPP was considered in the modelling assessment. As discussed in Section 3.5.2.7, biogas generated by the co-digestion process will have H2S removed by sulphur absorption vessels before combustion.  The generated biogas will undergo treatment in sulphur absorption vessels to remove H2S by the filter, the H2S will be bound and the resulting solid precipitate is disposed of as solid waste, which is not expected to emit any odourous gases. In addition, the Anammox process will also be adopted for sewage treatment. Anammox technology utilizes a lower energy ammonification process to convert ammonia (NH3) in the sewage to nitrogen gas to reduce the overall NH3 emission from the plant. The locations of the deodourizing units are illustrated in Appendix 3.10.

3.5.3.2           The odour impact from sludge transfer tanks, if any, could be controlled by proper design and good cleaning practices of sludge transfer tanks.  The opening of sludge transfer tank is the potential odour source during the transportation when there are gaps between the tank opening and its cover.  Sludge tanks with its air-tightness proved by DSD should be deployed for transporting sludge.  With thorough cleaning practice and regular condition test of the sludge tanks, odour emission and leachate leakage during storage and transportation are not anticipated.

Proposed Food Waste Pre-treatment Facilities (FWPF)

3.5.3.3           Potential odour source of the typical FWPF would be the food waste reception hall, and pre-treatment of food waste and transportation of the raw food waste to the FWPF.  The incoming food waste would be transported by fully enclosed trucks to avoid odour nuisance.  The surface of the enclosed trucks shall be washed upon exit and kept clean to avoid any food waste residue which would cause odour nuisance during transport. The food waste reception hall and other treatment facilities will be enclosed and the odorous air in these facilities will be vented to the deodourizing unit for odour treatment prior to discharge to the environment. The food waste pretreatment facilities will adopt mechanical treatment for impurities removal and size reduction, turning food waste into a consistent semi-fluid product for subsequent food waste/sewage sludge anaerobic co-digestion conducted off-site in the proposed EPP. Thus, only odour emission is expected in the proposed FWPF, i.e. no other air pollutant emission is involved. The pretreated food waste will be transported by fully enclosed pipes to the proposed EPP to avoid odour nuisance. 

3.5.3.4           There is no detailed design of the FWPF at this stage, however, the FWPF will be enclosed with negative pressure to prevent untreated odourous air from discharging to the atmosphere.  Instead, the odorous air in this facility will be vented to the deodourizing unit for odour treatment prior to discharge to the environment.  The ventilation exhaust location of the FWPF has not been confirmed at this moment but the exhaust outlet of the proposed FWPF should be located away from all nearby ASRs as far as possible for minimization of the odour impact. The odour emission from proposed FWPF was considered in the modelling assessment. The locations of the deodourizing units are illustrated in Appendix 3.10.

Proposed Sewage Pumping Stations (SPSs)

3.5.3.5           Three SPSs are proposed at Site OU.1.2, OU.3.2 and OU.5.7 with design capacities of 30,176 m3/day, 52,317 m3/day and 96,484 m3/day respectively. Their locations are illustrated in Appendix 3.10.  All potential odour sources of SPSs are to be fully enclosed by reinforced concrete structure.  Negative pressure would be maintained to prevent foul air from escaping the buildings. The odourous gas inside the SPSs would be conveyed to the provided deodourisers with odour removal efficiency of at least 95% before discharging to the atmosphere. The odour emission from these three SPSs was assessed quantitatively, together with other odour emission sources such as the proposed EPP and RTS. The locations of the DO exhaust are illustrated in Appendix 3.10.  Screening wastes would also be stored in covered containers, packed and handled carefully inside the screen houses within reinforced concrete structure before disposal at landfill site.  As such, the chance of on-site and off-site odour nuisance from the removal/handling of screening wastes would be further minimised.

Proposed Refuse Transfer Station (RTS) (DP4)

3.5.3.6           The new RTS is proposed at the Site OU.1.9, northeastern part of STLMC DN and have a design capacity of 3,000 tonnes per day (tpd). The RTS handles MSW only and there is no grease trap waste treatment facility in the site.  A wastewater treatment plant will be provided on-site to partially treat the leachate before discharging to public sewer as appropriate. No anerobic digestion, biogas production nor combustion would be involved in the proposed RTS. Potential odour would arise from the handling of municipal solid waste (MSW) at the tipping hall and the compactor hall, and the Wastewater Treatment Plant (WWTP) inside the proposed RTS. The WWTP will be electric powered such that there is no gaseous emission expected from the RTS.

3.5.3.7           Appropriate mitigation measures commonly adopted in other existing RTSs in Hong Kong would be considered in the design such as enclosing the odourous facilities, maintaining negative pressure to prevent foul air from escaping the building, and provision of odour removal system at the ventilation exhaust to control odour emission, potential odour impact from the proposed RTS on nearby ASRs would be assessed. The odour at the exhaust of the deodourizing system shall be continuously monitored.

3.5.3.8           The design of the RTS and a separate Schedule 2 EIA for the proposed RTS will be conducted by another party, therefore, the design of the RTS is not available at this stage.  The ventilation exhaust location of the RTS has not been confirmed at this moment but the exhaust outlet of the proposed RTS should be located away from all nearby ASRs as far as possible for minimization of the odour impact. The proposed RTS was considered in the modelling assessment. Its location is illustrated in Appendix 3.10.

Proposed Refuse Collection Point (RCP)

3.5.3.9           The proposed RCPs will be provided with proper ventilation, deodourizing and exhaust system with high odour removal efficiency to minimise the potential odour nuisance on nearby ASRs.  Commercially available odour control device[1] could achieve at least 95% and 80% removal on H2S and NH3 respectively, where H2S and NH3 are the primary odourous gas from municipal solid waste. The RCPs would be fully enclosed with ventilation system to ensure negative pressure.  Good site practices will be also adopted to enhance the hygiene of the RCPs by frequent washing, proper covering of refuse bins, closing of roller shutters and proper maintenance of the ventilation, deodourizing and exhaust systems.  A monitoring and sanction mechanism would be observed by Food and Environmental Hygiene Department (FEHD) to ensure satisfactory service by waste collection contractors such that the potential odour nuisance due to RCPs would be very limited.

3.5.3.10        During transportation of MSW, refuse collection vehicle (RCV) would be of fully-enclosed type to avoid odour spread.  In addition, the route for the RCV between RCP and RTS would be designed so as to minimise the potential odour impact from these vehicles to the ASRs in the vicinity of the routing.  The drivers of RCV should follow the procedures for cleaning of the RCV in accordance with Code of Practice on the Operation of Refuse Collection Vehicles issued by EPD and Transport Department so as to keep the RCV in a clean and hygienic condition.  Therefore, no adverse odour nuisance would be expected from the operation of RCVs.

Retained Existing Livestock Farm

3.5.3.11        All existing livestock farms within the Project boundary would be removed under the Project, except an existing pig farm (EPD Farm Code: 18/19/Y10; AFCD LKL No. LK871), which would be retained[2].  The retained pig farm would be a potential odour source in the assessment area and was considered in the modelling assessment. Its location is illustrated in Appendix 3.11.

Existing Sewage Treatment Works at San Tin Barracks (San Tin Barracks STW)

3.5.3.12        San Tin Barracks lies in the southeast of STLMC DN and is adjacent to the proposed site development under the RODP. A sewage treatment works is identified in the western barracks and is visible outside the fence at the perimeter. The barracks is restricted area, thus site visit is not possible. Referring to the aerial photo as shown in Table 3.12, the sewage treatment works (STW) at San Tin Barracks consists of two circular shaped tanks, two smaller rectangular tanks and one rectangular tank.  Site visits at the perimeter were conducted in mid September 2022 and end December 2023. The concerned STW was confirmed to be in operation but no odour from the STW was perceived during the site visit.  Since the STW is still in operation, its potential odour impact shall be assessed. The emission from this existing STW was therefore considered in the modelling assessment. Its location is illustrated in Appendix 3.12.

Proposed Water Reclamation Plant (WRP) (DP3)

3.5.3.13        A Water Reclamation Plant (WRP) is also proposed at Site G.3.13, located next to the EPP. Owing to the high effluent standard of the EPP, the tertiary treated effluent is odourless and is subject for water reclamation. According to DSD’s definition on the reclaimed water[3], it is highly treated effluent water which is clear in appearance, odourless and is safe for use.  The reclamation process involves disinfection process which is also odourless.  Hence, potential odour emission from the WRP is not anticipated.

3.6                  Assessment Methodology

3.6.1              Construction Phase

3.6.1.1           With reference to past air quality monitoring data, the construction of similar scale projects did not pose adverse dust impacts.  It is anticipated that the Project would not cause adverse dust impacts during construction phase with the implementation of appropriate dust suppression measures. Therefore, qualitative assessment approach was adopted for construction dust impact assessment. A comprehensive EM&A programme with RSP and FSP real-time monitoring would be conducted to ensure the proper implementation of measures and the compliance of AQOs during the construction of STLMC DN in the area.

3.6.2              Operation Phase

Vehicular Emission and Start Emission from Proposed Primary Distributor and District Distributor Roads (DP1) and Other Roads  

3.6.2.1           The key air pollutant associated with vehicular emission during the operation phase are NO2, RSP and FSP.  Major open road emission sources include proposed DP roads under the ROPD including Road P1, D1, D2, D3, D4, D5 and D6, and existing open roads within 500m assessment area such as San Tin Highway and Fanling Highway.

3.6.2.2           EMFAC-HK v4.3 was adopted to estimate the vehicular emission factors in NO2, NO, RSP and FSP in various travelling speeds and ambient conditions, i.e. the lowest temperature and relative humidity in each season with reference to the observation in Year 2021 by HKO meteorological stations at Beas River in Sheung Shui, Shek Kong and Sheung Shui. The resulting emission factors were applied for both short-term and long-term impacts.

3.6.2.3           According to the Hong Kong Roadmap on Popularization of Electric Vehicles released by the Environmental Bureau, long-term policy and plans have been formulated to promote the goal of zero vehicle emission before the 2050s. Gradual changeover to electric-private cars (E-PC) is expected during the Project, which results in less PC with tailpipe emission in the future. The trend of newly registered E-PC in future years was assumed in linear growth from the recent percentage in first registered vehicle list in TD, to the target 100% newly registered E-PC by Year 2035.  The population of PC in EMFAC, which are the fleet accounted for tailpipe emission, was then adjusted accordingly to reflect the changeover of E-PC. Detailed assumptions and calculations are presented in Appendix 3.5.

3.6.2.4           The traffic data for each road in 500m study area comprises 24-hour traffic flow with vehicle percentage, travelling speed in 18 vehicle classes and is presented in Appendix 3.4. Transport Department (TD) agreement on the adopted traffic data is also presented in the appendix.  The induced traffic due to the Project including population intake, other specified uses, etc. has been taken into account in the traffic data. With reference to the traffic data, hourly emission factor of each open road was determined by summation of emission by each vehicle class which is product of traffic flow and emission factor at specific speed and ambient condition.  The hourly emissions factors of NO, NO2, RSP and FSP were further divided by the hourly flow to obtain a composite emission rate in gram per miles per vehicle, ready for input to the dispersion model. The detailed calculation of vehicular emission source is presented in Appendix 3.5.

3.6.2.5           Start emission refers to the air pollutants generated due to the ignition of the vehicle engines which is released at vehicle tailpipes.  Start emission generally occurs on the local road where there is potential trip start, while no start emission along district distributor or expressway is anticipated.  For the assessment purpose, broad-brush approach was adopted which assumed start emission at all local roads irrelevant to the actual location of engine start.  Also, all vehicle classes were assumed to have potential trip start on local road, except franchised bus (FBSD and FBDD) which usually starts its engine at its termini throughout its service route. Start emission from the 5 existing parking sites (ID1 – 5) were also calculated by broad-brush approach along their access roads.

3.6.2.6           Start emission factors of 18 vehicle classes at various soak times were extracted from EMFAC-HK v4.3, among which the highest factor is adopted for a vehicle class.  Frequency of start emission of a vehicle type on a road is estimated by its forecasted VKT and Trips/VKT ratio extracted from Traffic Census.  Detailed estimation of start emission is presented in Appendix 3.5.

Vehicular Emission Associated with Concerned Facilities

3.6.2.7           Running, idling and start emissions within the existing Lok Ma Chau Station PTI, planned Lok Ma Chau Loop PTI, three existing logistics facilities, one planned PTI in Pang Loon Tei and the two planned TIHs were assessed with precise approach. Open-air design was considered for each facility. Data concerning engine start at these concerned locations, such as the frequency and soak time, were collected in 24-hour site survey on a normal working day and are presented in Appendix 3.6. The start emissions calculation was conducted according to the “Technical Note on the Calculation of Start Emissions in Air Quality Impact Assessment”. Start emission factors of vehicle types at various soak times were extracted from EMFAC-HK v4.3.  The detailed calculation of start emission is presented in Appendix 3.6.

Determination of Assessment Year for Vehicular Emission

3.6.2.8           The population intake is expected to take place in three phases, namely Initial Phase (Year 2031 – 2033), Main Phase (Year 2034 – 2038) and Remaining Phase (Year 2039). The assessment year for open road vehicular emission of each phase was determined by the year with the highest vehicular emission burden within the assessment area within the next 15 years after the first population intake year, i.e. Year 2031 – 2046. The vehicular emission burdens in NOX, RSP and FSP for Initial Phase (Year 2031, 2032 and 2033), Main Phase (Year 2034, 2036 and 2038) and Remaining Phase (Year 2039, 2042, and 2046) were estimated with EMFAC-HK v4.3 and are presented in Table 3.7.  Owing to the nearby development which also induces traffic to the connecting highways such as Fanling Highway and San Tin Highway, an ultimate scenario denoted as Year 2046+, which takes account of these bypassing traffic, is also considered.  The traffic data is presented in Appendix 3.4 and the assumptions adopted in EMFAC-HK is presented in Appendix 3.5. Based on the burden results, vehicular emission of Year 2031 was selected for Initial Phase, Year 2034 for Main Phase and Year 2039 for Remaining Phase and Post-2046.

Table 3.7     Vehicular Emission Burden in the Study Area

Development Stage

Year

Vehicular Emission Burden (kg per day)

NOX

RSP

FSP

Initial Phase

2031

374.1

16.3

15.0

2032

341.8

14.6

13.5

2033

337.1

12.8

11.8

Main Phase

2034

396.9

13.7

12.6

2036

345.2

8.8

8.1

2038

378.7

9.0

8.3

Remaining Phase

2039

464.7

10.2

9.3

2042

392.4

9.2

8.5

2046

404.2

9.1

8.4

Post-2046

2048

397.3

8.9

8.2

Remark:

Emission burden of wintertime is presented, which is the highest among the four seasons.

Underlined value indicates the highest among the period.

Proposed Effluent Polishing Plant (EPP) (DP2)

3.6.2.9           Biogas is produced as a by-product from the co-digestion process.  Biogas will be stored in the gas holders and then be utilized by CHP units to produce heat and electricity. Flue gas emission from the operation of Project would be expected from the combustion of biogas by CHP units and boiler.  The exhaust gas from CHPs and boiler will be vented to the ambient via a stack.

3.6.2.10        The design of the proposed EPP was referenced to Yuen Long South Effluent Polishing Plant (YLSEPP) as presented in its approved EIA Report (AEIA-237/2022) and modified the plant design by engineers with the need of STLMC DN. Based on the preliminary design of the proposed EPP, there would be 3 CHP units and a boiler. Therefore, 3 CHP units identical to the design of YLSEPP and 1 boiler with adjusted biogas consumption were adopted in the calculation. The details of the CHP and boiler emission are presented in Appendix 3.3.

3.6.2.11        RSP, FSP, NO2 and SO2 concentrations were predicted at each identified ASRs at respective assessment heights. Carbon monoxide, methane, formaldehyde, HCl and HF were also predicted.

Concurrent Project

3.6.2.12        Concurrent projects, namely Strategic Study on Major Roads beyond 2030, KTN NDA and Lok Ma Chau Loop, would also induce traffic within the development plan. This induced traffic has been accounted in the traffic data and presented in Appendix 3.4. Vehicular emission from proposed roads was estimated with the same approach as discussed in Section 3.6.2.1 and 3.6.2.6. The detailed calculation of vehicular emission source is presented in Appendix 3.5.

Major Point Source

3.6.2.13        The stack emission of the identified asphalt plant was considered in the cumulative air quality assessment. The information including valid emission strength, corresponding air pollutant control measures of emission sources and their emission duration which is applicable is extracted from the SP Licence Registry and taken into account in the assessment. The corresponding emission details and spatial location are presented in Appendix 3.9.

Summary of Assessment Scenarios and Contributing Sources

3.6.2.14        Table 3.8 summarizes the assessment scenarios and sources considered in the assessments.

Table 3.8     Summary of Assessment Scenarios and Contributing Sources

Assessment Scenario

Vehicular Emission

PATH Background

DP under RODP

Other Sources

Initial Phase
(Year 2031 – 2033)

Year 2031

Year 2030

·     Road P1 D1 (part), D2, D3, D4, D6

·     EPP

·     LMC Station PTI

·     LMC Loop PTI

·     Existing Logistics Facilities

Main Phase
(Year 2034 – 2038)

Year 2034

Year 2030

·     All DP Roads (except section of D1 at RSc.2.7)

·     EPP

·     LMC Station PTI

·     LMC Loop PTI

·     PTI in Pang Loon Tei

·     Existing Logistics Facilities

Remaining Phase + 2046+
(Year 2039 – 2048)

Year 2039

Year 2035

·     All DP Roads

·     STLMC EPP

·     LMC Station PTI

·     LMC Loop PTI

·     PTI in Pang Loon Tei

·     San Tin TIH

·     TIH at Proposed Station near Chau Tau

·     Existing Logistics Facilities

Remark:

1.     All open roads within the assessment area are also included in each scenario.

Dispersion Modelling and Modelling Approach for Proposed EPP and Major Point Source

3.6.2.15        According to Guidelines on Assessing the ‘TOTAL’ Air Quality Impacts by EPD, an integrated modelling system PATHv2.1 which is developed and maintained by EPD was applied to provide background pollutant concentrations in assessing the total impact in the study area.  In addition, Weather Research and Forecast (WRF) meteorological data were adopted for modelling.

3.6.2.16        American Meteorological Society (AMS) and U.S. Environmental Protection Agency (EPA) Regulatory Model (AERMOD), the HKEPD approved air dispersion model, was applied to predict the air quality impacts at the representative ASRs due to the emission of chimneys of Proposed EPP and the asphalt plant.  Hourly and annual averages of NO2, daily and annual averages of RSP and FSP concentrations were predicted at each identified ASRs at various assessment height, ranging from 1.5 metres above ground to the roof level of ASR with intervals of every 10 metres.

3.6.2.17        Hourly meteorological conditions including wind data, temperature, relative humidity, pressure, cloud cover and mixing height of Year 2015 were extracted from the WRF meteorological data adopted in the PATHv2.1 system.  The dataset by WRF should be intact and consistent among parameters. In order to avoid any hours misidentified as missing data by AERMOD and its associated components, the WRF met data were handled manually to set wind direction between 0° – 0.1° to be 360°.  The height of the input data was assumed to be 9 metres above ground for the first layer of the WRF data as input.

3.6.2.18        The wind speed and mixing heights in the WRF data were further adjusted before meteorological pre-processing by AERMET.  The minimum wind speed was capped at 1 metre per second.  The mixing height was capped between 131 metres and 1941 metres according to the observation in Year 2015 by HKO.  After pre-processed by AERMET, the mixing height was verified once again and adjusted to the capped range if necessary.

3.6.2.19        Surface characteristic parameters such as albedo, Bowen ratio and surface roughness are required in the AERMET.  The parameters are determined according to land use classified for the surrounding and the latest AERMOD Implementation Guide.  The determination of the surface characteristics parameter is presented in Appendix 3.13.  Flat terrain was applied in AERMOD.

Dispersion Modelling and Modelling Approach for Open Road

3.6.2.20        CALINE4, the USEPA approved line source air dispersion model developed by the California Department of Transport was used to assess the secondary contribution due to vehicular emission from road networks within 500 m assessment area.

3.6.2.21        The surface roughness is dependent on the land use characteristics, which is estimated to be 10% of average height of physical structure within 1 km radius of the Project Site.  Typically, the value is assumed to be 370 cm and 100 cm for urban and new development respectively.  The assessment area comprises low-rise buildings and highways, and thus surface roughness of 100 cm was assumed.

3.6.2.22        The hourly meteorological data including wind speed, wind direction, air temperature and Pasquill-Gifford stability class of the relevant grids from the WRF Meteorological data (same basis for PATH model), were employed for the model run. 

Dispersion Modelling and Modelling Approach for Portal Emission

3.6.2.23        There is planned full enclosure along Fanling Highway outside Europa Garden in Kwu Tung, which is under KTN NDA. AERMOD was applied for the prediction of air pollutant contributions due to portal emissions. Details of model parameters refer to Section 3.6.2.163.6.2.19.

3.6.2.24        The portal emission was modelled as adjacent volume sources in accordance with the recommendations in the Permanent International Association of Road Congress Report (PIARC, 1991).  The pollutants were assumed to eject from the portal as a portal jet such that 2/3 of the total emissions is dispersed within the first 50m of the portal and the other 1/3 of the total emissions within the second 50m.  The emission inventory of portals is presented in Appendix 3.7.

Cumulative impact of Criteria Air Pollutants

3.6.2.25        Cumulative air pollutant concentration at ASR was derived by the sum of contributions by various sources, and background contribution from PATHv2.1 system on hour-by-hour basis.  Averaging results, namely daily and annual, were derived from the cumulative hour-by-hour results in accordance with Title 40, Code of Federal Regulations, US Environmental Protection Agency (USEPA 40 CFR) Part 51 “Revision to the Guideline on Air Quality Models, January 2017”.  If the total number of valid hours is less than 18 for 24-hour average, the total concentration should be divided by 18 for the 24-hour average.  For annual average, the sum of all valid hourly concentrations was divided by the number of valid hours during the year.  For daily average, cumulative results at each ASR amongst 365 days were ranked by highest concentration and compared with the maximum allowable concentration to determine the number of exceedance throughout a year.  The air quality impact on ASRs was then evaluated by number of exceedance per annum against the criteria of EIAO-TM and AQOs.

3.6.2.26        Ozone Limiting Method (OLM) has been adopted for the conversion of short-term NOX to NO2 based on the ozone background concentration from PATHv2.1. Regarding vehicular emission, NO2 and NO were predicted separately in CALINE4.  Following the principle of OLM, the total predicted vehicular NO2 is estimated as below:

[NO2]vehicular = [NO2]predicted + MIN {[NO]predicted, or (46/48) ´ [O3]PATH}

where

[NO2]vehicular   is the total predicted vehicular NO2 concentration

[NO2]predicted  is the predicted NO2 concentration

[NO]predicted    is the predicted NO concentration

MIN              means the minimum of the two values within the bracket

[O3]PATH        is the representative O3 PATH concentration (from other contribution)

(46/48)          is the molecular weight of NO2 divided by the molecular weight of O3

3.6.2.27        Similarly, NO2-to-NOX ratio of 10% was adopted for the emission from CHP/boiler, with reference to Air Quality Studies for Heathrow: Base Case, Segregated Mode, Mixed Mode and Third Runway Scenario modelling using ADMS-Airport, Cambridge Environmental Research Consultants, 2007. Same NO2-to-NOX ratio was adopted for the emission from diesel burning of the asphalt plant.

[NO2]stack = f ´ [NOX]predicted + MIN {(1 – f) ´ [NOX]predicted, or (46/48) ´ [O3]PATH}

where

f                   is the NO2-to-NOX ratio

[NO2]stack      is the total predicted NO2 concentration

[NOX]predicted  is the predicted NOX concentration

MIN              means the minimum of the two values within the bracket

[O3]PATH        is the representative O3 PATH concentration (from other contribution)

(46/48)          is the molecular weight of NO2 divided by the molecular weight of O3

3.6.2.28        With reference to the Guidance on Choice of Models and Model Parameters, Jenkin method was adopted for the conversion of cumulative annual average NOX to NO2 by using the empirical relationship in observed annual mean of NOX and NO2 concentrations. The empirical relationship is derived from the annual mean observed data by relevant EPD’s air quality monitoring stations (AQMS) including Yuen Long (the closest station), Tap Mun Station (background station with no vehicular emission), and three roadside stations (stations dominated by vehicular emission). The resulting curve was adopted for the cumulative annual average NOx to NO2 conversion. Detailed derivation of NOX-to-NO2 conversion equation using Jenkin method is presented in Appendix 3.19.

3.6.2.29        According to “Guidelines on the Estimation of 10-min average SO2 Concentration for Air Quality Assessment in Hong Kong”, SO2 concentration in 10-min average due to the stack emissions is estimated by applying stability-dependent multiplicative factor to 1-hour average model prediction by AERMOD.

3.6.2.30        For the estimation of formaldehyde, 1-hour to 30-minute conversion factors were calculated via a power law relationship with reference to Duffee et al., 1991[4] as shown below, such that the 1-hour average concentrations predicted by the AERMOD model were converted to 30-minute average concentrations.  The conversion factors for different Pasquill stability classes are listed in Table 3.9. As a conservative approach, the AERMOD predicted maximum 1-hour average formaldehyde concentration at each ASRs was converted to 30-minute average using the highest conversion factor of 1.41.

Cl = Cs(ts/tl)p

where

Cl = concentration for the longer time-averaging period;

Cs = concentration for the shorter time-averaging period;

ts = shorter averaging time;

tl = longer averaging time; and

p = power law exponent in Table 3.9

 

Table 3.9     Conversion Factors from 1-hour to 30-minute Averaging Time

Pasquill Stability Class

Power Law Exponent

1-hour to 30-minute Conversion Factor

A

0.5

1.41

B

0.5

1.41

C

0.333

1.26

D

0.2

1.15

E

0.167

1.12

F

0.167

1.12

 

3.6.3              Operation Phase (Odour Impact)

Proposed Effluent Polishing Plant (EPP) (DP2)

3.6.3.1           The proposed EPP will serve the catchment of the proposed STLMC DN, which will mainly consist of residential, commercial uses, as well as Innovation and Technology (I&T) uses.  Therefore, the characteristics of the sewage to be received by the proposed EPP would be mainly domestic and commercial sewage.  To estimate the potential odour impact from the proposed EPP, specific odour emission rate (SOER) from other effluent polishing plants (EPPs) in Hong Kong are referenced, such as Yuen Long South EPP (YLSEPP) and Shek Wu Hui EPP (SWHEPP) which both treat domestic sewage without seawater flushing. The proposed EPP is also a tertiary treatment plant receiving similar nature of sewage without seawater flushing and adopts the same sewage treatment processes as the one adopted in SWHEPP and YLSEPP, i.e. MBBR. The SOERs or odour emission rates of YLSEPP and SWHEPP were referenced to its approved EIA studies, e.g. YLSEPP (AEIAR-237/2022) and SWHEPP (AEIAR-175/2013), and the resulting odour emission rates were modified with the design of the proposed EPP.

3.6.3.2           All treatment units of the proposed EPP with potential odour emission will be covered and the exhausted air will be conveyed to the deodourizer(s) for treatment before discharge to the environment.  Two-stage deodourization system with overall practical odour removal efficiency of 97%, namely bio-filters and dry scrubbing (carbon or impregnated media), will be implemented to treat the odourous exhaust. With reference to the “Code of Practice on Assessment and Control of Odour Nuisance from Waste Water Treatment Works, April 2005” published by the Scottish Executive, bio-filters and dry scrubbing (carbon or impregnated media) are the two common odour abatement technology, which can achieve at least 95% alone. The exhaust gas after deodourization may cause potential odour impact during the operation phase.  With reference to the odour emission rate of each type of sewage treatment facilities adopted in YLSEPP, the potential odour emission rates generated from the operation of the proposed EPP were estimated according to the treatment process design as well as the performance of deodorization treatment. The odour emission in details is presented in Appendix 3.10.

Proposed Food Waste Pre-Treatment Facilities (FWPF)

3.6.3.3           The odour emission inventory of the proposed FWPF will be subject to its planning and engineering design.  Based on the latest design information, the FWPF will have a capacity of 100 tpd.  For the assessment purpose, the respective odour emission strength would be referenced to the H2S and NH3 monitoring record at the food waste pre-treatment facilities of the Food Waste / Sludge Anaerobic Co-Digestion Tai Po Pilot Plant which is at a capacity of 50 tpd. Two units of similar configuration were assumed in the calculation, which accounts for the capacity of 100 tpd in total.  Similar to the reference plant, activated carbon filter will be applied to treat the odourous exhaust. The odour emission in details is presented in Appendix 3.10.

Proposed SPSs at Site OU.1.2, OU.3.2 and OU.5.7

3.6.3.4           The wet well of the proposed SPS with potential odour emission will be covered and the exhausted air will be conveyed to the deodourizer with 95% odour removal efficiency (>99.5% removal for H2S) for treatment before discharge to the environment.  The odour emission in details is presented in Appendix 3.10.

Proposed Refuse Transfer Station (RTS) (DP4)

3.6.3.5           The new RTS is proposed at Site OU.1.9, western part of the STLMC DN. The design capacity would be around 3,000 tpd based on the latest design information and it is similar to the throughput of West Kowloon Transfer Station (WKTS), currently operating at 2,700 tpd and up to 3,182 tpd in 2034 based on Agreement No. CE43/2018(EP) Refurbishment and Upgrading Studies for (A) West Kowloon Transfer Station and (B) Island West and Island East Transfer Stations – Investigation, Design and Construction.  Similar configuration of waste transfer building is anticipated, which consists of tipping hall, compactor hall, WWTP but no grease trap waste treatment facility, anaerobic digestor, nor biogas production and combustion.  Hence, the respective odour emission strength and corresponding air pollutant control measures of proposed RTS are generally referenced to WKTS.

3.6.3.6           6-stack configuration is assumed for the proposed RTS, similar to expanded WKTS with 3,182 tpd. The uncontrolled odour emission referred to the highest total H2S and NH3 concentrations monitored at all DO inlets of current WKTS from Jan 2021 to May 2022 and was adjusted accordingly, from its 2,700 tpd to 3,000 tpd of the proposed RTS. The monitored data was also contributed by the odour emission from the grease trap treatment facility at WKTS. It is considered as a worst-case assumption for the proposed RTS though it has no grease trap treatment involved. A wet chemical scrubber (with H2S and NH3 removal efficiencies of 99.9% and 90% respectively) is generally implemented at existing RTS as advised by EPD, thus it is adopted in the calculation. The odour emission in details is presented in Appendix 3.11.

Retained Existing Livestock Farm

3.6.3.7           Under Agreement No. CE 28/2019(CE) Study on Phase One Development of New Territories North – San Tin / Lok Ma Chau Development Note – Feasibility Study, the owner of the retained pig farm was approached for obtaining consent for odour sampling at the pig farm.  However, the owner refused to grant access for site inspection and odour sampling.  A written request for site inspection and odour sampling to the contact of the owner of the retained pig farm has been issued in July 2022 but no response has been received so far.  Alternative odour assessment would be employed as presented below.

3.6.3.8           For the purpose of odour impact assessment of the Project, the odour emission parameters of the retained pig farm would be estimated with reference to the findings of odour sampling at an existing pig farm (Farm Code: 18/19/P43) documented in a Working Paper on Odour Sampling Results and Odour Emission Inventory – Pig Farm LK801[5] (the WP) conducted under the CE 28/2019(CE) Study.  In view of the similarities of the retained pig farm and the sampled pig farm (18/19/P43) in terms of nature (both are open-form pig farms), and rearing capacity (1,500 for sampled pig farm; 1,200 for the retained pig farm), reference would be made to odour sampling result reported in the WP for estimating the odour emission parameters of the retained pig farm.  The odour emission strength of the odour sources in the sampled pig farm with reference to the WP are listed in below Table 3.10.

Table 3.10  Summary of Measured Odour Emission for the Pig Farm 18/19/P43

ID

Description

Odour Emission Area, m2

Specific Odour Emission Rate (SOER), OU/m2·s [2]

1-5

Pig House

524.63

2.89[3]

6-9

Pig House

1234.93

2.89[3]

A

Collection Tank

17.02

51.34

B

Waste segregation facility

6.42

14.04

C

Sludge Storage Tank

13.20

44.96

D-F

Anaerobic Digestion Tank

25.20

12.35

L-O and Q

Aeration Tank

84.00

0.77

P

Sedimentation Tank

5.20

0.12

R

Sedimentation Tank

25.80

0.12

S

Sludge Storage Tank – Basin for solid residues

10.23

0.28

Sludge Storage Tank -

10.23

44.96

RB

Rubbish Bin Holding Area

6.00

0.07

Remarks:

[1] SOER refers to the values reported in Working Paper on Odour Sampling Results and Odour Emission Inventory – Pig Farm LK801 (Revision 2) dated 31 January 2022 which has been approved by EPD.

[2] In the referenced odour survey, SOER was determined with the sampling flow rate and area covered with flux hood or wind tunnel.

[3] According to the referenced odour survey, two SOERs were determined for the excrement on the floor of the same pig house, which were 1.86 OU/m2·s and 3.91 OU/m2·s respectively. It showed that odour emission varied over the floor of the pig house. As an estimate, an average value of 2.89 OU/m2·s is therefore adopted for the overall SOER of a pig house.

3.6.3.9           Since the retained pig farm (capacity of 1,200) and the sampled pig farm (capacity of 1,500) would have similar capacity, the specific odour emission rate (SOER) in the retained pig farm would be estimated the same as that in the sampled pig farm 18/19/P43.  The estimated odour emission rates for the retained pig farm are listed in Table 3.11. The locations of these odour emission sources in the retained pig farm would be referenced from the farm layout plan provided by AFCD, as shown in Appendix 3.11.  

Table 3.11  Estimated Odour Emission for the Retained Pig Farm 18/19/Y10

ID

Use

Dimension, m [2]

Area, m2

Assumed SOER, OU/m2·s [1]

SOER Reference from Pig Farm 18/19/P43 [1]

PF01

Pig House

3.78

x

5.76

21.8

2.89

Pig House

PF02

Pig House

6.03

x

2.92

17.6

2.89

Pig House

PF03

Pig House

10

x

23.6

236

2.89

Pig House

PF04

Pig House

3.6

x

7.6

27.4

2.89

Pig House

PF05

Pig House

4.7

x

30.98

145.6

2.89

Pig House

PF06

Pig House

2

x

5.88

11.8

2.89

Pig House

PF07

Pig House

5.7

x

6

34.2

2.89

Pig House

PF08

Pig House

4.9

x

15.44

75.7

2.89

Pig House

PF09

Pig House

4.8

x

3.5

16.8

2.89

Pig House

PF10

Pig House

3.3

x

8.8

29.0

2.89

Pig House

PF11

Pig House

4.45

x

6.02

26.8

2.89

Pig House

12

Feed Store

9.4

x

5.92

55.6

[3]

[3]

13

Store Room

2.75

x

3.25

8.9

[3]

[3]

PF14

Pig House

3

x

8.96

26.8

2.89

Pig House

PF15

Pig House

7.26

x

5.99

43.5

2.89

Pig House

PF16

Pig House

9.95

x

2.94

29.3

2.89

Pig House

PF17

Pig House

12.11

x

10.95

132.6

2.89

Pig House

PF18

Pig House

15.25

x

5.08

77.5

2.89

Pig House

PF19

Pig House

10.15

x

7.98

81.0

2.89

Pig House

PF20

Pig House

4.2

x

9.86

41.4

2.89

Pig House

PF21

Pig House

6.36

x

6.15

39.1

2.89

Pig House

PF22

Pig House

-

 

-

88.5

2.89

Pig House

PF23

Pig House

12

x

9

108

2.89

Pig House

PFA

Collection Tank

2

x

2

4

51.34

Collection Tank

PFB

Collection Tank

2

x

2

4

51.34

Collection Tank

PFC

Collection Tank

2

x

2

4

51.34

Collection Tank

PFD

Waste segregation facility

-

1 [4]

14.04

Waste segregation facility

PFE

Sludge Storage Tank

11

x

1.7

18.7

44.96

Sludge Storage Tank

PFF

Sludge Storage Tank

2

x

12.3

24.6

44.96

Sludge Storage Tank

PFG

Filtration Tank[5]

9

x

3.5

31.5

12.35

Anaerobic Digestion Tank

PFH

Filtration Tank[5]

9

x

3.5

31.5

12.35

Anaerobic Digestion Tank

PFI

Filtration Tank[5]

9

x

3.5

31.5

12.35

Anaerobic Digestion Tank

PFJ

Filtration Tank[5]

9

x

3.5

31.5

12.35

Anaerobic Digestion Tank

PFK

Aeration Tank

4.2

x

3.4

14.28

0.77

Aeration Tank

PFL

Aeration Tank

5.2

x

3.4

17.68

0.77

Aeration Tank

PFM

Aeration Tank

5.2

x

3.4

17.68

0.77

Aeration Tank

PFN

Aeration Tank

5.2

x

7

36.4

0.77

Aeration Tank

PFO

Sedimentation Tank

2.8

x

6.4

17.92

0.12

Sedimentation Tank

Remarks:

[1] SOER refers to the value reported in Working Paper on Odour Sampling Results and Odour Emission Inventory – Pig Farm LK801 (Revision 2) dated 31 January 2022 which has been approved by EPD.

[2] Dimension of the odour sources referenced to the farm layout plan provided by AFCD and is presented in Appendix 3.11.

[3] The area was not identified odourous for odour sampling for Pig Farm 18/19/P43.

[4] It is a stand-alone machine identified from the farm layout plan. 1 m2 is assumed for the purpose of calculation.

[5] The area was not identified odourous for odour sampling for Pig Farm 18/19/P43. SOER of anaerobic digestion tank as a necessary wastewater treatment process is adopted for assessment purpose to avoid underestimation of odour impact.

Existing Sewage Treatment Works at San Tin Barracks (San Tin Barracks STW)

3.6.3.10        While the engineering information of San Tin Barracks STW is not available, the potential odour sources of sewage treatment facilities would be identified by aerial photo as shown in Table 3.12.  It is expected that the sewage would be mainly domestic sewage. With reference to our STW design experience, the facilities at San Tin Barracks STW is of a secondary treatment level which comprises inlet works, sedimentation, bioreactor and a sludge thickening process.

Table 3.12          Aerial Photo of the San Tin Barracks Sewage Treatment Works

3.6.3.11        Given that the type of sewage received and the expected process conducted at these tanks, odour emission rates of inlet works, sedimentation tank and bioreactors in the San Tin Barracks STW therefore generally make reference to the odour emission rates of tanks with similar type of treatment units in Shek Wu Hui STW which also receive major domestic sewage without seawater flushing.  The Shek Wu Hui STW emission rates are presented in the approved EIA Report for NENT (AEIAR-175/2013).  For the sludge treatment tank, as the sludge is not digested, the odour strength would be higher.  Its emission strength is proposed to adopt the sludge mixing tank of YLEPP as presented in its approved EIA Report (AEIAR-220/2019).  The estimated odour emission rates are presented in Table 3.13. The odour emission in details is presented in Appendix 3.12.

Table 3.13  Estimated Odour Emission for the San Tin Barracks STW

ID

Use

Dimension, m [1]

Area, m2

Assumed SOER, OU/m2·s

SOER Reference [2] [3]

STBSTW_01

Inlet works

5.6

x

10.6

59.4

3.26

S1 Inlet pumping station of SWHSTW

STBSTW_02

Sedimentation Tank

5.6

x

10.6

59.4

4.03

S6 Primary Sedimentation Tank of SWHSTW

STBSTW_03

Bioreactor

Diameter = 11m

95

1.65

S7 Bioreactor of SWHSTW

STBSTW_04

Bioreactor

Diameter = 11m

95

1.65

S7 Bioreactor of SWHSTW

STBSTW_05

Sludge Treatment Tank

9.4

x

11.6

109

26.42

Sludge Mixing Tank of YLEPP

Remarks:

[1] Determined with GeoInfo Map Hong Kong.

[2] SOERs of SWHSTW refer to Appendix 3.8 of NENT Development EIA (AEIAR-175/2013)

[3] SOERs of YLEPP refer to Appendix 3.9 of YLEPP EIA (AEIAR-220/2019)

Dispersion Modelling & Modelling Approach for Odour Source

3.6.3.12        With reference to Clause 3.4.3 and Appendices B and B-1 of the EIA Study Brief ESB-340/2021 and EPD’s Guidelines for Local-Scale Air Quality Assessment Using Models, American Meteorological Society (AMS) and U.S. Environmental Protection Agency (EPA) Regulatory Model (AERMOD), the HKEPD approved air dispersion model, was employed to predict the odour impact at representative ASRs.

3.6.3.13        Cumulative odour impact within 500m from these odour sources, namely the proposed EPP, RTS and FWPF, proposed SPSs, Retained Pig Farm and San Tin Barracks STW, were assessed.  It is assumed that the proposed deodorizing units/system of the proposed EPP and the proposed RTS operate continuously on a 24-hour-per-day basis with steady state ventilation rate and exhaust gas velocity in the assessment, unless otherwise specified. Odour emission from the exhaust outlet of the deodorizers was modelled as point source, while odour emission from the retained pig farm was modelled as volume and area sources for pig houses and tank surfaces respectively.

3.6.3.14        The assessment heights would be at predetermined heights above ground level according to the height of the ASRs.  The contour plots of the predicted odour levels at the worst affected heights of the ASRs would also be produced.

3.6.3.15        The handling of meteorology input and determination of surface characteristics refer to Section 3.6.2.173.6.2.19.

3.6.3.16        If the odour emission sources are found to be wake-affected point sources, the 1-hour to 1-second conversion factors from Approved Methods for the Modelling and Assessment of Air Pollutants in New South Wales (NSW Approved Method) for wake-affected point sources would then be adopted.  The conversion factors for wake-affected point sources converting 1-hour average to 1-second average concentration stipulated in NSW Approved Method would be adopted directly to convert the 1-hour concentration predicted by the AERMOD model to 5-second concentration as a conservative approach.  The conversion factors for different types of source and stability classes are listed in Table 3.14 below.  Pasquill-Gifford stability refers to the dataset based on the WRF meteorological data.

Table 3.14     Conversion Factors to 5-second Mean Concentration

Pasquill Stability Class

Conversion Factor

Wake Affected Point Source / Volume Source

Area

A

2.3

2.5

B

2.3

2.5

C

2.3

2.5

D

2.3

2.5

E

2.3

2.3

F

2.3

2.3

 

3.7                  Prediction and Evaluation of Environmental Impacts

3.7.1              Construction Phase

3.7.1.1           Based on the RODP, the Project will be developed in three stages, namely Initial Phase, Main Phase and Remaining Phase. The development sites involved in each development stage are shown in Appendix 2.1.  Apart from the general development sites, constructions of DPs are also involved in each development phase, as summarized in Table 3.15.

Table 3.15   Construction of DPs Involved in Development Stages

Development Stage

DP-related Construction Works

Initial Phase

DP1 – Construction of Road P1, D1 (part), D2, D3, D4, D6

DP2 – Construction of EPP

DP3 – Construction of WRP

DP4 – Construction of RTS

DP6 – Revitalisation of STEMDC

DP7 – Recreational Development within Deep Bay Zone 2 (O.1.2, O.1.3)

Main Phase

DP1 – Construction of Road D1 (part), D5

DP5 – Construction of 400kv Electricity Substation

DP6 – Revitalisation of STEMDC

DP7 – Recreational Development within Deep Bay Zone 2 (O.1.1)

Remaining Phase

DP1 – Construction of Road D1 (section at RSc.2.7)

3.7.1.2           Construction works of general sites generally involves site formation works and construction of superstructures.  New primary distributor and district distributor roads are to be laid within STLMC DN, while the existing road system is to be largely demolished, realigned or upgraded.  A new sewage treatment works with treatment capacity of 125,000 m3/day , namely tertiary effluent polishing plant, is to be built at Site OU(EPP).5.3.  A new water reclamation plant with capacity of 112,500 m3/day is to built at Site OU(WRP).5.2.  A new refuse transfer station with capacity 3,000 tpd is to be built at Site OU.1.9.  Two 400kV electricity substations are to be built at Site OU.1.7 and OU.4.2. The revitalisation of STEMDC involves provision of flood attenuation measures such as underground storage tanks, integrated ponds and retention ponds at the upstream and provision of green embarkment and open space with floodable landscape along the revitalised channels.  Open space at O.1.1, O.1.2 and O.1.3 are to be developed to recreational purpose for the enjoyment of general public.

3.7.1.3           Potential construction dust impact would arise from the abovementioned construction works which involve site formation, excavation, backfilling, stockpiling, spoil handling, vehicle movement on haul roads, wind erosion of the exposed site area.  Among which, dominant dust emission would be associated with excavation and backfilling. The dust emission arising from the construction of superstructures is expected to be minor. Table 3.16 summarizes the duration of dusty construction activities of each development stage. Location of each development stage is illustrated in Appendix 2.1 and the tentative construction programme refers to Appendix 2.2.  According to the tentative construction programme, site formation works of Initial Phase would start in December 2024 and be completed by Year 2028. Site formation works of Main Phase would start in Year 2027 and be completed by Year 2029, however some of them such as I&T sites in the northwest would be as early as Year 2026, which are concurrent with Initial Phase. Site formation works of Remaining Phase would start in Year 2032 and be completed by Year 2034. Nevertheless, the construction programme is subject to land resumption schedule in the future. The exact locations of excavation and backfilling works at a specific time are not available at this stage.

3.7.1.4           According to the construction design by the engineer, cut and fill volumes to be handing in each construction years are summarized in Table 3.17 which is also presented in Chapter 7 of this Report. The major excavation and backfilling works will commence in Year 2025 and peak in Year 2027 – 2028.  The intensity of excavation and backing filling works will decrease significantly after Year 2028, when the site formation works of Initial Phase is completed. The transport of these excavated spoils would require 5 trucks per hectare per day starting from Year 2025, which is equivalent to 1021 trucks per day for the area of Initial Phase. In Year 2026, larger active work area is expected because of some site formation works of Main Phase, however 4 trucks is required per hectare per day, 1 truck less than the one in Year 2025. Site formation works will peak in Year 2027 and 2028, though it remains 5 trucks per hectare per day. The demand of dump trucks is expected to significantly decline to 1 – 2 trucks per hectare per day from Year 2029 to Year 2031. For Remaining Phase during Year 2032 - 3024, maximum of 8 trucks is required per hectare per day, which is equivalent to less than 300 trucks per day owing to smaller size of active work sites.

Table 3.16    Construction Activities with Major Dust Emission in Each Development Stage

Development Stage

Construction Activities

Duration

Initial Phase

Site Clearance, Site Formation Works, Excavation and Backfilling

December 2024 – 2028

Main Phase

Site Clearance, Site Formation Works, Excavation and Backfilling

2026 – 2029

Remaining Phase

Site Clearance, Site Formation Works, Excavation and Backfilling

2032 – 2034

Table 3.17    Estimated Cut and Fill Volumes for the Development by Year

Year [1]

Cut Volume (m3)

Fill Volume (m3)

No. of Trucks Required
(Vehicle per day)

No. of Trucks Required
(Vehicle per hectare per day)

2025

2,059,200

596,000

1021

5

2026

2,606,200

1,290,800

1293

4

2027

1,069,200

3,664,000

1817

5

2028

1,050,400

3,493,900

1733

5

2029

675,900

835,200

414

2

2030

233,400

382,400

190

1

2031

439,500

204,000

218

1

2032

566,100

172,100

281

8

2033

430,300

110,000

213

6

2034

218,400

69,900

108

4

Note:

[1] The site clearance and site formation works shall commence in Dec 2024.  It is therefore assumed that no cut and fill volumes is anticipated in 2024.

[2] The data is extracted from Chapter 7, Waste Management Implication of this EIA Report.

3.7.1.5           The excess spoil from the excavation works would be transported with dump trucks out of the construction works sites to disposal outlet. The induced traffic would cause vehicle emission along the routes. Dump trucks would collect spoils from the construction works sites and transport via San Tin Highway, Yuen Long Highway, Tuen Mun Road to Tuen Mun Area 38 Fill Bank. Transportation routes in detailed refers to Table 7.7. Maximum of 200 vehicles per day is expected for transporting waste during construction phase. The routings should avoid the use of local roads and the truck traffic should avoid peak hours, as far as practicable. Dump truck is equipped with water-tight container and mechanical cover, which would not cause fugitive dust emission on the open road. With the implementation of these mitigation measures, it is anticipated that no adverse air quality impact would be caused by the transportation of spoils along the routes.

3.7.1.6           Dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation would be implemented as far as practicable to abate the fugitive dust emission from the construction sites.  Regular watering is to be provided at the excavation and backfilling works, spoil handing and exposed areas.  Stockpile area should be covered with impervious sheets, as far as practicable.  Haul roads should be paved and regularly wetted to suppress the fugitive dust emission caused by the travelling construction vehicles. Vehicles transporting dusty spoil should be properly covered with mechanical cover or tarpaulin sheets to avoid any dust pickup by gust during travel.  Wheel washing facility would also be provided at each exit of construction sites such that no residue on the body of construction vehicle would cause dust emission on public roads.  With the implementation of appropriate dust suppression measures and good site practices, the fugitive dust emission from the construction works would be reduced to minimum.

3.7.1.7           In order to avoid any intensive works at a location close to ASR, site formation works will be conducted individually at each site, subject to the land resumption schedule.  Several worksfronts would be implemented if a development site is large in size.  Careful scheduling of nearby construction works will be managed with coordination or collaboration among development sites.  With the implementation of individual construction works site by site and careful scheduling of works, construction works are managed to reduce in scale such that the associated fugitive dust emission is reduced.

3.7.1.8           Nevertheless, some ASRs would exist close to the project boundary at 10 metres or less, such as Shek Wui Wai (A01 – A03) enclosed by the Project, Chau Tau Tsuen (A13) in the northeast, Rolling Hill (A19) and Scenic Heights (A21) in the northwest. Dusty activities should be located away from these nearby ASRs as far as practicable. In addition to regular watering, hoarding of not less than 3.5m high should be provided to shield off ASRs from these dusty works. Dust monitoring at these locations shall be considered to ensure the potential dust impact complying with AQOs during the construction phase.

3.7.1.9           San Tin Station of NOL and three ancillary buildings, namely San Tin Ancillary Building, Kwu Tung Ancillary Building, Pak Shek Au Ancillary Building are to be built within STLMC DN.  Kwu Tung Ancillary Building and Pak Shek Au Ancillary Building lie within the area of Initial Phase, while San Tin Station and San Tin Ancillary Building lie within the area of Main Phase.  Major construction works of station box and ancillary buildings including excavation and backfilling works would be carried out concurrently with Initial Phase or Main Phase, subject to their location.  Kwu Tung Ancillary Building and Pak Shek Au Ancillary Building are to be completed by the population intake of Initial Phase, such that no planned ASR of Initial Phase is affected by the NOL construction works.  Owing to the larger footprint of San Tin Station, its construction works are expected to be conducted in several workfronts. San Tin Station and San Tin Ancillary Building are to be completed by the population intake of Main Phase, such that no planned ASR of Main Phase is affected. It is anticipated that appropriate dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation, such as regularly watering and paved haul road, would also be implemented by the contractors of NOL, resulting in minimum fugitive dust emission from their construction activities. Close liaison with the contractor of NOL will be taken place to minimize any construction activities to be taken place in the proximity at the same time.

3.7.1.10        Major construction works of KTN NDA within the assessment area would include the modification of the road interchange and the site formation works for amenity sites and district cooling system.  The associated construction works have commenced in Year 2019 and to be completed in Year 2031, which would be concurrent with Initial Phase and Main Phase of STLMC DN.  It is anticipated that appropriate dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation, such as regularly watering and paved haul road, would also be implemented by the contractors of KTN NDA, resulting in minimum fugitive dust emission from their construction activities. Close liaison with the contractor of KTN NDA will be taken place to minimize any construction activities to be taken place in the proximity at the same time.

3.7.1.11        Major construction works of the Loop within the assessment area are mostly site formation works and construction of superstructure.  The associated construction works have commenced in Year 2021 for operation commencement in Year 2026, which would be concurrent with Initial Phase of STLMC DN.  It is anticipated that appropriate dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation, such as regularly watering and paved haul road, would also be implemented by the contractors of the Loop, resulting in minimum fugitive dust emission from their construction activities. Close liaison with the contractor of the Loop will be taken place to minimize any construction activities to be taken place in the proximity at the same time.

3.7.1.12        With the implementation of workfronts for each development sites, careful scheduling of works, the effective dust suppression measures, good site practices and close liaison with contractors of concurrent works, no adverse dust impact on nearby ASRs in the assessment area due to the construction of STLMC DN, and other concurrent projects is anticipated.  A comprehensive EM&A programme with RSP and FSP real-time monitoring would be conducted to ensure the proper implementation of measures and the compliance of AQOs during the construction of STLMC DN in the area.

Potential Odour Impact from Revitalisation of STEMDC (DP6) during Construction Phase

3.7.1.13        The total volume of the excavated materials from the revitalisation works of STEMDC would be about 57 m3. Assuming works are to be carried out 6 days per week in 48 weeks,  the daily excavated materials would be about 0.20 m3/day. Hence, only minor excavation of the nullah bed material would be required for the revitalisation works of STEMDC.  Potential odour nuisance would be expected during excavation and handling of the nullah bed material. Odour mitigation measures such as covering the stockpiles of the excavated odour materials with tarpaulin and locating it away from air sensitive receivers (ASRs) as far as possible, and removing off site as soon as possible within 24 hours, are to be implemented when appropriate. No adverse odour nuisance is anticipated.

3.7.2              Operation Phase

Cumulative Air Quality Impact

3.7.2.1           The cumulative air quality impact due to proposed DP roads and EPP under the RODP, existing and planned open roads, planned portal within 500m assessment area, 4-km major point source and background concentration at representative ASRs in Year 2031, 2034 and 2039 have been evaluated.  Noise mitigation measures are proposed along San Tin Highways, and the assessment has incorporated such measures.  The details of proposed noise mitigation measures refer to Figure 4.13.  The predicted cumulative air quality impact on the representative ASRs in Year 2031, 2034 and 2039 are summarized in Table 3.18Table 3.23 respectively.  The predictions showed that daily and annual averages of RSP and FSP, 10-min and daily averages of SO2, and hourly and annual averages of NO2 at representative ASRs would comply with the AQOs.  The predicted CO concentration was well below the relevant AQOs. The detailed predictions with breakdown of contribution by sources in Year 2031, 2034 and 2039 are presented in Appendix 3.14, Appendix 3.15 and Appendix 3.16 respectively. 

3.7.2.2           According to the discrete results, the worst affected level would be 1.5 metres above ground (mAG) for those locations as their first level of air sensitive use.  The contour plots of RSP, FSP, SO2 and NO2 at 1.5mAG are illustrated in Figure 3.2Figure 3.7 and Figure 3.143.15 for Year 2031, Figure 3.8Figure 3.15 for Year 2034 and Figure 3.16Figure 3.23 for Year 2039.  No exceedance in RSP, FSP, and SO2 was predicted in the assessment area except that:

·         exceedance in annual NO2 was predicted in Year 2031 along the San Tin Highway, Fanling Highway, Lok Ma Chau Road, the proposed local road L5 and the proposed local road L13 north of the retained villages,

·         exceedance in hourly NO2 was predicted in Year 2034 along the San Tin Highway and Lok Ma Chau Road, and exceedance in annual NO2 was predicted in Year 2034 along San Tin Highway, Ha Wan Tsuen East Road, Lok Ma Chau Road, and the proposed local road L13 north of the retained villages,

·         exceedance in hourly NO2 was predicted in Year 2039 along the San Tin Highway, Ha Wan Tsuen East Road and Lok Ma Chau Road, and exceedance in annual NO2 was predicted in Year 2039 along San Tin Highway, Ha Wan Tsuen East Road, and Lok Ma Chau Road, and the proposed local road L13 north of the retained villages.

Yet there is no existing air sensitive use in the area, such as openable window, fresh air intakes of ventilation system or recreational uses in open space. No planned air sensitive use should be located within the exceedance zones at 5mAG or below. The contour plots of hourly and annual average NO2 contour plots at 5mAG illustrated in Figure 3.29 – Figure 3.34 which show the exceedance zones would be limited within the road alignment areas. No adverse air quality impact is anticipated during the operation phase of the development plan.

Non-AQO Criteria Pollutants by the Proposed EPP

3.7.2.3           The predicted methane, HCl, HF and formaldehyde concentrations at representative ASRs in Year 2031, 2034 and 2039 would be well below the respective standards as stated in Section 3.2.3. The detailed prediction results are presented in Appendix 3.15 for Year 2031 and 2034, and Appendix 3.16 for Year 2039 respectively.

Table 3.18  Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2031

ASRID

10th Highest Daily Average RSP Conc. (µg/m3)

(AQO: 100 µg/m3)

Annual RSP Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Daily Average FSP Conc. (µg/m3)

(AQO: 50 µg/m3)

Annual FSP Conc. (µg/m3)

(AQO: 25 µg/m3)

A01

70

28

38

17

A02

70

28

38

17

A03

70

28

38

16

A04

70

29

39

17

A05

69

28

36

16

A06

69

28

37

17

A07

69

28

35

16

A08

68

28

35

16

A09

70

29

38

17

A10

68

27

35

16

A11

68

27

35

16

A12

68

27

35

16

A13

69

28

36

16

A14

69

28

35

16

A15

69

27

35

16

A16

69

27

35

16

A17

71

29

38

17

A18

71

29

39

17

A19

68

27

35

15

A20

68

27

35

15

A21

71

29

38

17

A22

71

29

38

17

A23

71

29

38

17

A24

68

27

35

15

A25

69

27

37

15

A26

69

28

38

16

A27

69

28

37

16

A28

69

28

37

16

A29

69

28

37

16

A30

69

28

37

16

A31

69

28

38

16

A32

70

29

39

17

A33

68

27

35

16

P101

71

29

39

17

P102

68

27

35

15

P103

71

29

38

17

P104

71

29

38

17

P105

71

29

38

17

P106

71

29

38

17

P107

68

27

35

15

P108

68

27

35

15

P109

70

29

38

17

P110

70

28

38

17

P111

70

28

38

16

P112

69

28

36

16

P113

68

28

36

16

P114

69

28

37

17

P115

69

28

36

16

P116

68

28

36

16

P117

68

28

36

16

P118

68

28

36

16

P119

69

28

35

16

P120

69

28

35

16

P121

69

28

36

16

P122

69

28

36

16

P123

69

28

36

16

P124

69

28

36

16

P125

69

28

36

16

P126

70

28

35

16

P127

70

28

35

16

P128

70

28

35

16

P129

70

28

36

16

P130

69

28

35

16

P131

70

28

36

16

P132

69

28

35

16

P133

70

28

35

16

P134

69

27

35

16

P135

69

27

35

16

P136

69

27

35

16

P137

69

27

35

16

P138

70

27

35

16

P139

70

27

35

16

P140

72

28

37

16

P141

72

28

37

16

P142

72

28

37

16

P143

72

29

37

16

P144

72

28

37

16

P145

68

28

35

16

P146

68

28

35

16

P147

70

29

39

17

P148

70

29

39

17

P149

71

29

39

17

P150

71

29

39

17

P151

71

29

38

17

P152

70

28

35

16

P153

69

27

35

16

Remark:

Bolded value indicates exceedance in relevant criterion.

Table 3.19  Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2031

ASRID

4th Highest 10-min Average SO2 Conc. (µg/m3)

(AQO: 500 µg/m3)

4th Highest Daily Average SO2 Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Hourly Average NO2 Conc. (µg/m3)

(AQO: 200 µg/m3)

Annual Average NO2 Conc. (µg/m3)

(AQO: 40 µg/m3)

A01

60

12

131

17

A02

60

12

134

18

A03

60

12

130

16

A04

60

12

135

28

A05

66

14

143

31

A06

69

14

145

29

A07

65

14

144

26

A08

66

14

141

25

A09

60

12

133

21

A10

65

14

139

19

A11

65

14

141

19

A12

65

14

139

22

A13

82

16

139

24

A14

82

16

136

20

A15

73

16

137

20

A16

73

15

136

18

A17

63

13

142

24

A18

64

13

139

27

A19

52

13

122

16

A20

52

13

129

15

A21

62

13

137

21

A22

62

13

136

21

A23

62

13

134

20

A24

52

12

125

16

A25

59

12

105

11

A26

62

12

129

14

A27

61

13

115

13

A28

62

13

115

13

A29

61

13

115

13

A30

61

13

115

14

A31

67

13

108

13

A32

74

14

141

23

A33

80

15

133

17

P101

62

13

141

26

P102

52

13

127

16

P103

62

13

140

23

P104

62

13

133

19

P105

62

13

136

20

P106

62

14

135

20

P107

52

13

126

17

P108

52

13

118

15

P109

62

13

130

19

P110

60

12

134

18

P111

60

12

131

17

P112

69

15

140

24

P113

69

14

143

28

P114

69

14

148

31

P115

69

14

138

26

P116

69

14

136

28

P117

69

14

137

27

P118

69

14

137

27

P119

82

16

136

19

P120

82

16

136

18

P121

82

16

145

28

P122

69

14

144

29

P123

82

16

140

28

P124

82

16

142

25

P125

82

16

152

24

P126

73

16

147

25

P127

73

16

146

24

P128

73

16

144

24

P129

73

16

147

26

P130

73

16

143

23

P131

73

16

148

28

P132

73

16

140

21

P133

73

16

144

24

P134

73

15

140

21

P135

73

15

140

20

P136

73

15

137

21

P137

73

15

139

20

P138

73

15

142

21

P139

73

15

140

20

P140

78

18

149

24

P141

78

18

151

25

P142

78

18

147

23

P143

78

18

154

26

P144

78

18

146

23

P145

65

14

141

25

P146

65

14

139

24

P147

60

12

139

27

P148

60

12

139

28

P149

60

12

144

31

P150

62

13

150

33

P151

62

13

141

25

P152

73

15

144

22

P153

52

13

135

21

 

Table 3.20   Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2034

ASRID

10th Highest Daily Average RSP Conc. (µg/m3)

(AQO: 100 µg/m3)

Annual RSP Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Daily Average FSP Conc. (µg/m3)

(AQO: 50 µg/m3)

Annual FSP Conc. (µg/m3)

(AQO: 25 µg/m3)

A01

70

28

38

17

A02

70

28

38

17

A03

70

28

38

17

A04

70

29

39

17

A05

69

28

35

16

A06

69

28

36

16

A07

68

28

35

16

A08

68

28

35

16

A09

70

29

38

17

A10

68

27

35

16

A11

68

27

35

16

A12

68

27

35

16

A13

69

28

35

16

A14

69

28

35

16

A15

69

27

35

16

A16

69

27

35

16

A17

71

29

38

17

A18

71

29

39

17

A19

68

27

35

15

A20

68

27

35

15

A21

71

29

38

17

A22

71

29

38

17

A23

71

29

38

17

A24

68

27

35

15

A25

69

27

37

15

A26

70

28

38

16

A27

69

28

37

16

A28

69

28

37

16

A29

69

28

37

16

A30

69

28

37

16

A31

69

28

38

16

A32

70

29

39

17

A33

68

27

35

16

P101

71

29

38

17

P102

68

27

35

15

P103

71

29

38

17

P104

71

29

38

17

P105

71

29

38

17

P106

71

29

38

17

P107

68

27

35

15

P108

68

27

35

15

P109

70

29

38

17

P110

70

28

38

17

P111

70

28

38

17

P112

69

28

36

16

P113

68

28

36

16

P114

68

28

36

16

P115

68

28

36

16

P116

68

28

36

16

P117

68

28

36

16

P118

68

28

36

16

P119

69

28

35

16

P120

69

28

35

16

P121

69

28

36

16

P122

68

28

36

16

P123

69

28

36

16

P124

69

28

35

16

P125

69

28

36

16

P126

70

28

35

16

P127

70

28

35

16

P128

70

28

35

16

P129

70

28

35

16

P130

69

27

35

16

P131

70

28

36

16

P132

69

27

35

16

P133

70

28

35

16

P134

69

27

35

16

P135

69

27

35

16

P136

69

27

35

16

P137

69

28

35

16

P138

70

28

35

16

P139

70

27

35

16

P140

72

28

37

16

P141

72

28

37

16

P142

72

28

37

16

P143

72

29

37

16

P144

72

28

37

16

P145

68

27

35

16

P146

68

27

35

16

P147

70

29

38

17

P148

70

29

38

17

P149

70

29

39

17

P150

71

29

39

17

P151

71

29

38

17

P152

70

28

35

16

P153

68

27

35

15

P201

71

29

38

17

P202

71

29

38

17

P203

71

29

38

17

P204

70

28

38

17

P205

70

28

38

17

P206

70

28

38

17

P207

70

29

38

17

P208

70

29

38

17

P209

71

29

38

17

P210

70

29

38

17

P211

70

29

38

17

P213

70

29

38

17

P214

70

29

38

17

P215

68

27

35

16

P216

68

27

35

16

P217

68

28

35

16

P219

68

28

36

16

P220

69

28

36

16

P221

68

28

36

16

P222

68

27

35

15

P223

68

27

35

15

P224

68

27

35

15

P225

68

27

35

15

P226

68

27

35

15

P227

68

27

35

15

P228

68

27

35

15

P229

70

28

38

16

P230

70

28

38

17

P231

68

27

35

15

P232

68

27

35

15

P233

68

27

35

15

P234

68

27

35

15

P235

70

28

38

16

P236

70

28

38

16

P237

70

28

38

16

P238

70

28

38

16

P239

69

28

37

16

P240

69

28

37

16

P241

70

29

38

17

P242

70

29

38

17

P243

70

28

38

17

P244

70

28

38

17

P245

68

27

35

16

P246

69

28

38

16

P247

69

28

37

16

P248

69

28

37

16

P249

69

28

37

16

P250

69

28

37

16

P251

69

28

37

16

P252

69

28

37

16

P253

69

28

37

16

P254

69

28

37

16

P255

69

28

37

16

P256

69

28

37

16

P257

69

28

37

16

P258

69

28

37

16

P259

69

28

37

16

P260

68

28

36

16

P261

68

28

36

16

P262

68

28

36

16

P263

68

28

36

16

P264

68

28

36

16

P265

68

28

36

16

P266

69

28

37

16

P267

68

28

36

16

P268

68

28

36

16

P269

68

28

36

16

P270

69

28

36

16

P271

68

28

35

16

P272

68

28

35

16

 

Table 3.21   Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2034

ASRID

4th Highest 10-min Average SO2 Conc. (µg/m3)

(AQO: 500 µg/m3)

4th Highest Daily Average SO2 Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Hourly Average NO2 Conc. (µg/m3)

(AQO: 200 µg/m3)

Annual Average NO2 Conc. (µg/m3)

(AQO: 40 µg/m3)

A01

60

12

135

18

A02

60

12

137

20

A03

60

12

136

18

A04

60

12

136

26

A05

66

14

143

28

A06

69

14

145

29

A07

65

14

144

25

A08

66

14

141

24

A09

60

12

132

21

A10

65

14

135

19

A11

65

14

137

19

A12

65

14

140

21

A13

82

16

138

22

A14

82

16

136

20

A15

73

16

137

20

A16

73

15

136

18

A17

63

13

145

25

A18

64

13

137

26

A19

52

13

122

16

A20

52

13

123

15

A21

62

13

135

20

A22

62

13

132

20

A23

62

13

131

19

A24

52

12

122

16

A25

59

12

108

11

A26

62

12

130

16

A27

61

13

119

14

A28

62

13

119

15

A29

61

13

125

16

A30

61

13

123

16

A31

67

13

108

13

A32

74

14

136

21

A33

80

15

132

17

P101

62

13

139

23

P102

52

13

125

15

P103

62

13

139

22

P104

62

13

131

19

P105

62

13

133

19

P106

62

14

134

20

P107

52

13

127

17

P108

52

13

124

15

P109

62

13

132

19

P110

60

12

137

20

P111

60

12

134

20

P112

69

15

140

24

P113

69

14

142

26

P114

69

14

144

28

P115

69

14

140

25

P116

69

14

136

24

P117

69

14

137

24

P118

69

14

135

24

P119

82

16

136

19

P120

82

16

136

18

P121

82

16

141

24

P122

69

14

150

28

P123

82

16

143

27

P124

82

16

137

23

P125

82

16

162

25

P126

73

16

148

25

P127

73

16

145

24

P128

73

16

147

24

P129

73

16

147

26

P130

73

16

143

23

P131

73

16

154

30

P132

73

16

140

22

P133

73

16

148

25

P134

73

15

143

22

P135

73

15

140

21

P136

73

15

138

22

P137

73

15

139

23

P138

73

15

145

26

P139

73

15

140

22

P140

78

18

149

24

P141

78

18

151

26

P142

78

18

147

24

P143

78

18

159

29

P144

78

18

146

23

P145

65

14

141

24

P146

65

14

141

23

P147

60

12

133

25

P148

60

12

134

26

P149

60

12

150

31

P150

62

13

151

32

P151

62

13

141

26

P152

73

15

145

26

P153

52

13

130

18

P201

67

14

139

23

P202

63

13

134

21

P203

62

15

138

23

P204

60

12

136

18

P205

60

12

134

18

P206

60

12

139

21

P207

60

12

141

23

P208

63

13

131

21

P209

62

13

136

22

P210

62

13

132

22

P211

60

12

135

23

P213

60

12

139

26

P214

60

12

138

24

P215

64

14

140

22

P216

64

14

139

24

P217

65

14

141

27

P219

69

14

141

26

P220

69

14

142

29

P221

69

14

141

27

P222

52

13

126

14

P223

53

13

122

14

P224

53

13

120

12

P225

53

13

121

12

P226

52

13

114

13

P227

52

13

117

13

P228

52

13

124

16

P229

60

12

134

17

P230

60

12

133

18

P231

53

13

119

14

P232

53

13

123

15

P233

53

13

123

14

P234

54

13

113

12

P235

61

12

134

17

P236

61

12

129

15

P237

61

12

129

15

P238

61

12

129

16

P239

61

13

119

14

P240

61

13

126

17

P241

61

12

133

21

P242

61

12

138

22

P243

60

12

136

19

P244

60

12

135

19

P245

66

14

142

20

P246

67

13

110

13

P247

63

13

114

14

P248

63

13

114

14

P249

63

13

114

14

P250

62

13

117

15

P251

62

13

123

17

P252

62

13

119

16

P253

62

13

114

14

P254

62

13

115

15

P255

61

13

123

16

P256

61

13

125

19

P257

61

13

125

18

P258

61

13

116

15

P259

61

13

116

15

P260

70

15

136

19

P261

69

15

133

17

P262

69

15

135

19

P263

69

15

136

21

P264

69

14

137

18

P265

69

15

139

21

P266

61

13

122

16

P267

69

14

138

18

P268

69

14

138

19

P269

69

14

139

20

P270

69

14

168

29

P271

65

14

143

27

P272

65

14

146

27

 

Table 3.22   Worst Predicted Cumulative RSP and FSP Concentrations at Representative ASRs in Year 2039

ASRID

10th Highest Daily Average RSP Conc. (µg/m3)

(AQO: 100 µg/m3)

Annual RSP Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Daily Average FSP Conc. (µg/m3)

(AQO: 50 µg/m3)

Annual FSP Conc. (µg/m3)

(AQO: 25 µg/m3)

A01

69

28

38

16

A02

70

28

38

16

A03

69

28

38

16

A04

70

28

38

17

A05

68

27

35

16

A06

68

28

36

16

A07

68

27

35

15

A08

68

27

35

16

A09

69

28

38

16

A10

68

27

34

15

A11

68

27

34

15

A12

68

27

34

15

A13

69

27

35

16

A14

69

27

35

16

A15

69

27

35

15

A16

69

27

35

15

A17

70

28

38

16

A18

70

29

38

17

A19

68

27

34

15

A20

68

27

34

15

A21

70

28

37

16

A22

70

28

38

16

A23

70

28

37

16

A24

68

27

34

15

A25

69

27

37

15

A26

69

28

38

16

A27

69

27

37

16

A28

69

27

37

16

A29

69

27

37

16

A30

69

27

37

16

A31

69

28

38

16

A32

70

28

38

16

A33

68

27

35

15

P101

70

28

37

16

P102

68

27

34

15

P103

71

28

37

16

P104

70

28

37

16

P105

71

28

37

16

P106

71

28

38

16

P107

68

27

34

15

P108

68

27

34

15

P109

70

28

37

16

P110

69

28

38

16

P111

69

28

38

16

P112

68

27

36

16

P113

68

27

36

16

P114

68

27

36

16

P115

68

27

36

16

P116

68

27

35

16

P117

68

27

35

16

P118

68

27

35

16

P119

69

27

35

16

P120

69

27

35

15

P121

69

27

35

16

P122

68

27

36

16

P123

69

28

35

16

P124

69

27

35

16

P125

69

28

35

16

P126

69

27

35

16

P127

69

27

35

15

P128

69

27

35

15

P129

69

27

35

16

P130

69

27

35

15

P131

70

27

35

16

P132

69

27

35

15

P133

69

27

35

16

P134

69

27

35

15

P135

69

27

35

15

P136

69

27

35

15

P137

69

27

35

15

P138

69

27

35

16

P139

69

27

35

15

P140

72

28

37

16

P141

72

28

37

16

P142

71

28

37

16

P143

72

28

37

16

P144

71

28

37

16

P145

68

27

34

15

P146

68

27

34

15

P147

69

28

38

16

P148

69

28

38

16

P149

70

28

38

16

P150

70

28

38

16

P151

70

28

38

16

P152

69

27

35

16

P153

68

27

34

15

P201

71

28

38

16

P202

70

28

38

16

P203

71

28

38

16

P204

69

28

38

16

P205

69

28

38

16

P206

70

28

38

16

P207

70

28

38

16

P208

70

28

38

16

P209

70

28

38

16

P210

70

28

38

16

P211

69

28

38

16

P213

69

28

38

16

P214

69

28

38

16

P215

68

27

34

15

P216

68

27

34

15

P217

68

27

34

15

P219

68

27

36

16

P220

68

28

36

16

P221

68

27

36

16

P222

68

27

35

15

P223

68

27

35

15

P224

68

27

35

15

P225

68

27

35

15

P226

68

27

35

15

P227

68

27

35

15

P228

68

27

35

15

P229

69

28

38

16

P230

69

28

38

16

P231

68

27

35

15

P232

68

27

35

15

P233

68

27

35

15

P234

68

27

35

15

P235

69

28

38

16

P236

69

28

38

16

P237

69

28

38

16

P238

69

28

38

16

P239

69

27

37

16

P240

69

27

37

16

P241

69

28

38

16

P242

69

28

38

16

P243

70

28

38

16

P244

69

28

38

16

P245

68

27

34

15

P246

69

28

38

16

P247

69

27

37

16

P248

69

27

37

16

P249

69

27

37

16

P250

69

27

37

16

P251

69

27

37

16

P252

69

27

37

16

P253

69

27

37

16

P254

69

27

37

16

P255

69

27

37

16

P256

69

27

37

16

P257

69

27

37

16

P258

69

27

37

16

P259

69

27

37

16

P260

68

27

35

16

P261

68

27

35

15

P262

68

27

35

16

P263

68

27

35

16

P264

68

27

35

16

P265

68

27

35

16

P266

69

27

37

16

P267

68

27

35

16

P268

68

27

35

16

P269

68

27

35

16

P270

69

28

36

16

P271

68

27

34

15

P272

68

27

34

15

P301

68

27

35

15

P302

68

27

34

15

P303

68

27

34

15

P304

68

27

35

15

P305

68

27

35

15

P306

69

28

38

16

P307

69

28

38

16

P308

69

28

38

16

P309

69

28

38

16

P310

69

28

38

16

P311

69

28

38

16

P312

69

27

37

16

P313

69

28

35

16

P314

67

27

34

15

P315

68

27

35

16

P316

67

27

34

15

P317

70

28

38

16

 

Table 3.23   Worst Predicted Cumulative NO2 and SO2 Concentrations at Representative ASRs in Year 2039

ASRID

4th Highest 10-min Average SO2 Conc. (µg/m3)

(AQO: 500 µg/m3)

4th Highest Daily Average SO2 Conc. (µg/m3)

(AQO: 50 µg/m3)

19th Highest Hourly Average NO2 Conc. (µg/m3)

(AQO: 200 µg/m3)

Annual Average NO2 Conc. (µg/m3)

(AQO: 40 µg/m3)

A01

60

12

135

18

A02

60

12

138

21

A03

60

12

137

19

A04

60

12

135

24

A05

66

14

142

27

A06

69

14

143

28

A07

65

14

143

24

A08

66

14

137

24

A09

60

12

130

20

A10

65

14

132

18

A11

65

14

136

18

A12

65

14

137

19

A13

82

16

138

20

A14

82

16

136

18

A15

73

16

136

19

A16

73

15

135

17

A17

63

13

147

26

A18

63

13

151

28

A19

52

13

120

15

A20

52

13

123

14

A21

62

13

132

19

A22

62

13

131

19

A23

62

13

129

18

A24

52

12

119

15

A25

59

12

107

10

A26

62

12

128

14

A27

61

13

118

13

A28

62

13

119

13

A29

61

13

123

14

A30

61

13

121

15

A31

67

13

107

12

A32

74

14

131

19

A33

80

15

132

16

P101

62

13

135

21

P102

52

13

122

14

P103

62

13

135

20

P104

62

13

130

17

P105

62

13

132

18

P106

62

14

129

18

P107

52

13

123

15

P108

52

13

122

14

P109

62

13

130

17

P110

60

12

135

20

P111

60

12

136

20

P112

69

15

138

23

P113

69

14

139

24

P114

69

14

139

25

P115

69

14

141

23

P116

69

14

132

21

P117

69

14

131

21

P118

69

14

133

21

P119

82

16

136

18

P120

82

16

136

17

P121

82

16

141

22

P122

69

14

151

26

P123

82

16

138

25

P124

82

16

137

21

P125

82

16

156

24

P126

73

16

144

23

P127

73

16

142

22

P128

73

16

145

22

P129

73

16

145

24

P130

73

16

140

21

P131

73

16

153

29

P132

73

16

140

20

P133

73

16

147

24

P134

73

15

140

20

P135

73

15

139

20

P136

73

15

137

21

P137

73

15

139

21

P138

73

15

145

24

P139

73

15

141

20

P140

78

18

149

23

P141

78

18

150

25

P142

78

18

148

22

P143

78

18

163

28

P144

78

18

146

22

P145

65

14

142

23

P146

65

14

142

23

P147

60

12

134

25

P148

60

12

135

25

P149

60

12

151

30

P150

62

13

148

29

P151

62

13

142

26

P152

73

15

144

24

P153

52

13

129

17

P201

67

14

166

25

P202

63

13

134

21

P203

62

15

136

21

P204

60

12

137

19

P205

60

12

134

18

P206

60

12

136

23

P207

60

12

141

23

P208

63

13

129

21

P209

62

13

134

22

P210

62

13

130

21

P211

60

12

134

22

P213

60

12

139

24

P214

60

12

138

23

P215

64

14

139

21

P216

64

14

138

22

P217

64

14

141

25

P219

69

14

138

24

P220

69

14

142

26

P221

69

14

139

24

P222

52

13

126

14

P223

53

13

122

13

P224

53

13

120

12

P225

53

13

120

11

P226

52

13

115

12

P227

52

13

115

12

P228

52

13

124

15

P229

60

12

134

16

P230

60

12

134

18

P231

53

13

119

13

P232

53

13

122

14

P233

53

13

122

13

P234

54

13

112

11

P235

61

12

133

16

P236

61

12

128

14

P237

61

12

126

14

P238

61

12

128

14

P239

61

13

119

13

P240

61

13

123

16

P241

61

12

133

19

P242

61

12

139

23

P243

60

12

134

18

P244

60

12

139

20

P245

66

14

143

20

P246

67

13

109

12

P247

63

13

111

13

P248

63

13

115

13

P249

63

13

111

13

P250

62

13

115

14

P251

62

13

118

15

P252

61

13

118

15

P253

62

13

112

13

P254

62

13

115

15

P255

61

13

122

15

P256

61

13

122

17

P257

61

13

123

17

P258

61

13

116

14

P259

61

13

116

14

P260

70

15

133

19

P261

69

14

132

16

P262

69

15

133

18

P263

69

15

133

20

P264

69

14

137

17

P265

69

15

139

21

P266

61

13

121

15

P267

69

14

136

17

P268

69

14

137

18

P269

69

14

136

19

P270

69

14

171

29

P271

65

14

140

25

P272

65

14

142

25

P301

52

13

122

12

P302

52

13

121

14

P303

52

13

120

14

P304

52

13

120

12

P305

52

13

123

14

P306

61

12

130

14

P307

61

12

130

15

P308

61

12

130

15

P309

61

12

129

15

P310

61

12

131

17

P311

60

12

136

19

P312

61

13

122

16

P313

69

14

172

28

P314

65

14

132

17

P315

69

14

136

19

P316

64

14

132

17

P317

62

13

133

22

3.7.3              Operational Phase (Odour Impact)

3.7.3.1           The cumulative odour impact due to the proposed EPP, FWPF, RTS, the three SPSs and the retained pig farm and the existing San Tin Barracks STW were predicted at the representative ASRs and are summarized in Table 3.24. Detailed prediction results are presented in Appendix 3.17. The prediction showed that the cumulative 5-second average odour concentrations would comply with the 5 OU/m3 of the EIAO-TM criterion among planned ASRs. However, the maximum predicted cumulative odour concentration at existing ASRs A26 and A33 would be 13.94 OU/m3 and 12.59 OU/m3 respectively, which results in non-compliance with the EIAO-TM criterion of 5 OU/m3.

Table 3.24   Worst Predicted Cumulative Odour Concentrations at Representative Air Sensitive Receivers

ASR ID

Maximum 5-second Average Odour Concentration (OU/m3) (EIAO-TM: 5 OU/m3)

A01

0.90

A02

1.52

A03

1.16

A04

0.90

A05

0.65

A06

0.86

A07

0.54

A08

0.58

A09

0.70

A10

0.52

A11

0.44

A12

0.35

A13

3.70

A14

1.70

A15

0.82

A16

0.57

A17

0.49

A18

1.16

A19

0.51

A20

0.49

A21

0.58

A22

0.63

A23

0.54

A24

0.55

A25

2.10

A26

13.94

A27

3.87

A28

2.51

A29

2.31

A30

2.04

A31

0.42

A32

1.78

A33

12.59

P101

0.56

P102

0.57

P103

0.54

P104

0.53

P105

0.52

P106

0.49

P107

0.79

P108

0.93

P109

0.92

P110

0.98

P111

1.06

P112

2.50

P113

1.30

P114

1.63

P115

1.50

P116

3.15

P117

3.20

P118

3.98

P119

3.00

P120

2.87

P121

1.91

P122

1.33

P123

1.60

P124

1.80

P125

1.45

P126

1.01

P127

0.83

P128

0.72

P129

0.65

P130

0.82

P131

0.93

P132

0.77

P133

0.80

P134

0.74

P135

0.64

P136

0.70

P137

0.39

P138

0.39

P139

0.59

P140

0.76

P141

0.78

P142

0.73

P143

0.82

P144

0.95

P145

0.49

P146

0.45

P147

0.75

P148

1.10

P149

0.96

P150

0.58

P151

0.79

P152

0.37

P153

0.63

P201

0.75

P202

0.78

P203

0.61

P204

0.93

P205

1.01

P206

0.95

P207

0.71

P208

1.17

P209

0.73

P210

0.73

P211

0.76

P213

0.81

P214

0.70

P215

0.46

P216

0.55

P217

0.60

P219

1.39

P220

1.63

P221

1.66

P222

0.92

P223

1.05

P224

1.31

P225

1.44

P226

1.13

P227

1.17

P228

1.24

P229

1.01

P230

1.23

P231

2.26

P232

2.57

P233

3.09

P234

4.44

P235

4.36

P236

2.43

P237

3.35

P238

2.37

P239

2.31

P240

4.05

P241

3.58

P242

2.25

P243

1.30

P244

1.45

P245

1.08

P246

0.72

P247

0.75

P248

0.81

P249

0.78

P250

0.91

P251

1.38

P252

1.78

P253

0.83

P254

0.98

P255

1.18

P256

1.39

P257

1.38

P258

1.01

P259

0.97

P260

0.97

P261

1.05

P262

1.19

P263

1.14

P264

0.96

P265

1.07

P266

0.99

P267

0.90

P268

0.92

P269

0.92

P270

0.96

P271

0.46

P272

0.44

P301

0.88

P302

0.90

P303

0.67

P304

1.32

P305

1.51

P306

1.35

P307

2.02

P308

2.75

P309

3.00

P310

2.30

P311

1.41

P312

1.76

P313

0.90

P314

0.69

P315

1.13

P316

0.63

P317

0.62

Remark:

Bolded value indicates exceedance in relevant criterion.

3.7.3.2           According to the predictions presented in the Appendix 3.17, the predicted maximum 5-second average cumulative odour concentration would occur at 1.5mAG, 5mAG, 10mAG, 15mAG and 20mAG, therefore contour plots of the cumulative odour concentrations at these levels are illustrated in Figures 3.243.28. Exceedance of odour impact was predicted at 1.5mAG, 5mAG, 10mAG and 15mAG in vicinity of the existing San Tin Barracks STW, over Site A.5.3, G.5.8, G.5.9, G.5.10, G.5.11, G.5.12, E.5.1, E.5.2, O.2.1, O.5.3, OU.5.8, OU.5.9 and OU.5.10. The government use buildings at Site G.5.8, G.5.9, G.5.10, G.5.11 and G.5.12 are to be air conditioned and their fresh air intakes are to be positioned at 20mAG or above. The school blocks at E.5.1 and E.5.2 are to be positioned away from the exceedance area. Site A.5.3 is a planned amenity site, while Site O.2.1 and O.5.3 are planned open space, and no air sensitive use exists. Site OU.5.8, OU.5.9 and OU.5.10 are District Cooling System Plant (DCS) and Electricity Substation (ESS), where no air sensitive use exists. With these building design considerations, no planned air sensitive use is expected at these altitudes in the exceedance area. However, the exceedance of odour impact would appear at the existing ASR A26, a building of the existing San Tin Barracks, at 1.5mAG, 5mAG and 10mAG.  

3.7.3.3           Exceedance of odour impact were also predicted at 1.5mAG, 5mAG, 10mAG and 15mAG in the vicinity of Retained Pig Farm, over Site A.1.7, A.1.8, A.1.15, OU(I&T)3.1.8, OU.1.7, OU.1.8 and OU.1.9. The exceedance was also predicted at 20mAG in the vicinity of Retained Pig Farm. The buildings at Site OU(I&T)3.1.8 are to be air conditioned and its fresh air intakes are to be positioned at 20mAG or above, thus no air sensitive use is expected within the exceedance zone. Its recreational use in the open air, if any, shall be positioned away from the exceedance area. Site A.1.7, A.1.8 and A.1.15 are planned amenity sites, where no air sensitive use exists. Site OU.1.7, OU.1.8 and OU.1.9 are Electricity Substation (ESS), RCP and RTS respectively, and have no air sensitive use. Should there be any on-site office, it should be located away from the exceedance area. With implementation of the abovementioned building design, no planned air sensitive use is expected at these altitudes in the exceedance area. However, the exceedance of odour impact would appear at 1.5mAG, 5mAG, 10mAG and 15mAG at the existing ASR A33, an existing village house uphill of the pig farm.

3.7.3.4           The exceedance of odour impact were also predicted at the proposed EPP and FWPF at 10mAG, 15mAG and 20mAG, at proposed SPS at Site OU.1.2 at 1.5mAG and at proposed SPSs at Site OU.3.2 and OU.5.7 at 1.5mAG and 5mAG. However, the exceedance area was confined within the site boundaries and there is no existing ASRs in these exceedance areas. Should there be any fresh air intake at the proposed EPP and FWPF, it would be located away from these exceedance areas, i.e. 5mAG or below. No adverse odour impact due to the operation of the proposed EPP, FPPF and SPSs on any planned ASR is anticipated.

Exceedance Magnitude, Frequency and Odour Contribution by the Project

3.7.3.5           Owing to the exceedance predicted at the existing ASRs A26 and A33, their prediction results were further analyzed. The exceedance magnitude, exceedance frequency and the corresponding odour contribution by the Project and existing odour sources are presented in Appendix 3.18. For ASR A26, the existing San Tin Barracks STW is the closest odour source which is around 70 metres away in the north, while the closest odour source by the Project, the proposed SPS at OU.5.7, is much further away, 910 metres away in the northwest. It is expected that the existing San Tin Barracks STW is the dominant odour source because of the close proximity to A26. The breakdown of the odour contributions showed that the existing San Tin Barracks STW has contributed the most, up to 13.92 OU/m3, during the time of exceedance. The frequency of exceedance in odour concentration at A26 is up to 0.89% of time in a year. While exceedance occurred, the Project would contribute less than 0.02 OU/m3 only, as shown in Table 1 of Appendix 3.18, which is less than 0.4% of the odour criterion.

3.7.3.6           Similarly for ASR A33, the Retained Pig Farm which is around 130 metres away in the southwest is the closest odour source, while the closest odour source by the Project, the proposed RTS, is further south, around 420 metres away. Given the close proximity to A33, it is expected that the Retained Pig Farm is the dominant odour source. The breakdown of the odour contribution showed that the Retained Pig Farm contributed the most, up to 12.55 OU/m3, during the time of exceedance. The frequency of exceedance in odour concentration at A33 is up to 6.00% of time in a year. The Project would contribute less than 0.07 OU/m3 only for exceedance at A33, as shown in Table 1 of Appendix 3.18, which is less than 1.4% of the odour criterion.

3.7.3.7           Regarding the odour sources by the Project, namely the proposed EPP, FWPF, RTS, and the three SPSs, optimal design against the potential odour impact has been considered. All odour sources in the EPP will be covered and with odourous gas conveyed for treatment at DOs with 2-stage deodourization system at overall practical odour removal efficiency of 97%. The proposed DOs would be two-stage biofilters and dry scrubbing (carbon or impregnated media). The exhaust of the DO is also designed to located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the ASRs. Further relocation of DO exhaust away from ASRs would be limited by engineering constraint, e.g. limitation of space and height restriction.

3.7.3.8           Although the detailed design of FWPF is not available at this stage, optimal design is recommended to minimize the potential odour impact. The FWPF will be enclosed with negative pressure to prevent untreated foul air escaping the structure.  The odorous air will be vented to the deodourizing unit with activated carbon filter for odour treatment prior to discharge. The exhaust of the DO is also designed to be located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the ASRs. Further relocation of DO exhaust away from ASRs would be limited by engineering constraint, e.g. limitation of space and height restriction.

3.7.3.9           Similar to other existing RTSs in Hong Kong, proven odour control measures would be implemented in the design of the proposed RTS, such as enclosing the odourous facilities, maintaining negative pressure to prevent foul air from escaping the building, and provision of odour removal system (i.e. wet chemical scrubber with H2S and NH3 removal efficiencies of 99.9% and 90% respectively) at the ventilation exhaust to control odour emission. The exhaust of the DO is also designed to be located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the ASRs. Nevertheless, the design of the proposed RTS will be conducted by another party and its potential odour impact will be further evaluated in a separate Schedule 2 EIA to ensure its environmental acceptability.

3.7.3.10        For the proposed SPSs, appropriate mitigation measures commonly adopted in other existing SPSs in Hong Kong would be implemented in the design, such as enclosing the odourous facility, maintaining negative pressure to prevent foul air from escaping the building, and provision of odour removal system with odour removal efficiency of at least 95% (>99.5% removal for H2S) at the ventilation exhaust to control the potential odour emission. The exhaust of the DO is also designed to be located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the ASRs. Given the abovementioned optimal design, it is therefore considered that the odour control measures for the Project have been exhausted.

3.7.3.11        With the implementation of the Project, 9 existing livestock farms within the Project area will be removed. A further quantitative assessment with dispersion model has been conducted to compare the change in odour impact between Existing (Without Project) and Future (With Project) Scenarios and it is presented in Appendix 3.20. Comparing with the odour emission inventory under the Future scenario (i.e. with proposed EPP, FWPF, RTS, and SPSs), the reduction in odour emission would be around 84%. The comparison showed that there would be improvement in odour impact on both A26 and A33 with the implementation of the Project as summarized in Table 3.25. The change in spatial odour concentration within the exceedance areas were also evaluated and is presented in Appendix 3.20. The spatial comparison showed that no existing and future air sensitive uses within the exceedance zone, including openable window / fresh air intakes of the ventilation system or recreational uses in open space, would suffer from odour impact due to the Project. It is concluded that the Project would induce an improvement in cumulative odour impact for all existing ASRs at all assessment heights and all planned ASRs in the Project area in general compared to that of existing condition without removal of the nine livestock farms.

Table 3.25 Comparison of Odour Impact between Existing and Future Scenarios

ASR ID

Height (mAG)

5-second Average Odour Concentration (OU/m3)

Change

Future Scenario

Existing Scenario

A26

1.5

13.94

15.47

-1.53

A26

5

13.39

14.92

-1.53

A26

10

12.23

14.04

-1.80

A26

15

4.74

6.68

-1.94

A33

1.5

12.59

12.68

-0.09

A33

5

11.28

11.41

-0.14

A33

10

10.97

11.04

-0.07

A33

15

5.11

5.14

-0.03

Remark:

Bold value indicates exceedance in odour criterion of 5 OU/m3 stipulated in EIAO-TM.

3.7.3.12        In summary, with the implementation of odour control measures in design as discussed in Section 3.5.3 and Section 3.7.3, the odour sources of the Project, namely the proposed EPP, FWPF, RTS, and the three SPSs, would contribute up to 0.16 OU/m3 as shown in Table 2 of Appendix 3.18, where contributions from the Project alone are presented. These odour control measures for the Project have been exhausted. Improvement in odour impact on the concerned locations has been predicted with the implementation of the Project, i.e. environmental benefit is anticipated. Therefore, no adverse residual odour impact is expected due to the odour sources of the Project.

3.8                  Mitigation of Adverse Environmental Impacts

3.8.1              Construction Phase

3.8.1.1           Dust suppression measures stipulated in Air Pollution Control (Construction Dust) Regulation and good site practices listed below should be carried out to further minimize construction dust impact.

·         Use of regular watering to reduce dust emissions from exposed site surfaces and unpaved roads, particularly during dry weather.

·         Use of frequent watering for particularly dusty construction areas and areas close to ASRs.

·         Side enclosure and covering of any aggregate or dusty material storage piles to reduce emissions.  Where this is not practicable owing to frequent usage, watering shall be applied to aggregate fines.

·         For the work sites close to the ASRs with a separation distance less than 10 m, provide hoardings of not less than 3.5 m high from ground level along the site boundary; for the other work sites in general, provide hoarding not less than 2.4m high from ground level along site boundary except for site entrance or exit.

·         Avoid position of material stockpiling areas, major haul roads and dusty works within the construction site close to concerned ASRs.

·         Avoid unnecessary exposed earth.

·         Locate all the dusty activities away from any nearby ASRs as far as practicable.

·         Open stockpiles shall be avoided or covered.  Where possible, prevent placing dusty material storage piles near ASRs.

·         Tarpaulin covering of all dusty vehicle loads transported to, from and between site locations.

·         Establishment and use of vehicle wheel and body washing facilities at the exit points of the site.

·         Where possible, routing of vehicles and positioning of construction plant should be at the maximum possible distance from ASRs.

·         Imposition of speed controls for vehicles on site haul roads.

·         Instigation of an environmental monitoring and auditing program to monitor the construction process in order to enforce controls and modify method of work if dusty conditions arise.

3.8.1.2           Guidelines stipulated in EPD’s Recommended Pollution Control Clauses for Construction Contracts should be incorporated in the contract document to abate dust impacts. These clauses include:

·         The Contractor shall observe and comply with APCO and its subsidiary regulation, particularly the Air Pollution Control (Construction Dust) Regulation.

·         The Contractor shall undertake at all times to prevent dust nuisance as a result of the construction activities.

·         The Contractor shall ensure that there will be adequate water supply /storage for dust suppression.

·         The Contractor shall devise and arrange methods of working and carrying out the works in such a manner so as to minimize dust impact on the surrounding environment, and shall provide experienced personnel with suitable training to ensure that these methods are implemented properly.

·         Before the commencement of any work, the Contractor may be required to submit the methods of working, plant, equipment and air pollution control system to be used on the site for the Engineer inspection and approval.

3.8.1.3           In order to help reduce carbon emission and pollution, timely application of temporary electricity and water supply would be made and electric vehicles would be adopted in accordance with DEVB TC(W) No. 13/2020 – Timely Application of Temporary Electricity and Water Supply for Public Works Contracts and Wider Use of Electric Vehicles in Public Works Contracts in the Project.

3.8.1.4           To minimize the exhaust emission from NRMMs during the construction phase, the following measures should be applied as far as practicable:

·         Connect construction plant and equipment to main electricity supply and avoid use of diesel generators and diesel-powered equipment;

·         Avoid exempted NRMMs as far as practicable; and

·         Deploy electrified NRMMS as far as practicable.

3.8.2              Operation Phase

3.8.2.1           No adverse air quality impact is anticipated during the operational phase of the Project, thus mitigation measure is deemed not necessary.

3.8.3              Operation Phase (Odour Impact)

3.8.3.1           With reference to Section 3.7.3, no adverse residual odour impact is anticipated due to the Project during the operational phase, with the implementation of odour control measures in design as mentioned in Section 3.5.3. No adverse residual odour impact is anticipated.

3.8.3.2           In view of the predicted exceedance of the odour impact at the existing ASRs as presented in Section 3.7.3, odour control measures of the Project have been reviewed. In general, all odour sources will be covered and the odourous gas will be conveyed to DOs for treatment, for example EPP with 2-stage deodourization system at overall practical odour removal efficiency of 97%, activated carbon filter for FWPF, and odour removal system with odour removal efficiency of at least 95% (>99.5% removal for H2S) for the SPSs. Odour removal system for RTS has been assumed, while the detailed design will be confirmed in later separate Schedule 2 EIA. The exhaust of the DO is also designed to located furthest away and pointing away from any ASRs as far as practicable to further minimize any odour impact on the ASRs. It is therefore considered that the odour control measures for the Project have been exhausted.

3.9                  Evaluation of Residual Impacts

3.9.1              Construction Phase

3.9.1.1           With the implementation measures specified in Air Pollution Control (Construction Dust) Regulation together with the recommended regular watering on the works areas, exposed surface and paved road, no residual impact would be expected from the construction of the Project.


 

3.9.2              Operation Phase

3.9.2.1           No residual impact is expected during the operation phase of the Project.

3.9.3              Operation Phase (Odour)

3.9.3.1           Within the Project area there are nine existing livestock farms which would be removed, including two chicken farms and seven pig farms located at the southern portion of the Project area. With the removal of these livestock farms and their odorous sources, it is anticipated the overall odour emission in the area would be improved.  Comparing with the odour emission inventory under the ‘with Project’ scenario (i.e. with proposed EPP, FWPF, RTS, and SPSs), the reduction in odour emission would be around 84%, which indicates a significant improvement to the Project area in general.  

3.9.3.2           With the implementation of odour control measures in design at the proposed EPP, FWPF, RTS and the three SPSs mentioned in Section 3.5.3 and Section 3.7.3, the odour control measures have been exhausted.

3.9.3.3           Considering the cumulative odour impact due to the Project, the Retained Pig Farm and existing San Tin Barracks STW, exceedance of odour impact was predicted at attitude below 20mAG within the development sites discussed in Section 3.7.3.2 and 3.7.3.3. The uses at these sites are to be air conditioned with their fresh air intake positioned at 20mAG or above. No adverse residual odour impact would be expected at these planned ASRs.

3.9.3.4           Potential odour exceedances were predicted at two existing ASRs A26 and A33 for a short duration of time (up to 0.89% and 6.00% of time in a year) during operation phase of the Project. The Project would only contribute less than 0.02 OU/m3 and less than 0.07 OU/m3 at A26 and A33 respectively, less than 0.1 OU/m3 during the non-compliance period.  As mentioned in Section 3.9.3.1, the odour emission from existing livestock farms at the Project area would be significantly decrease as all existing nine livestock farms within the Project area would be removed.  The Project would induce an improvement in odour impact for the Project area in general compared to that of existing condition without removal of the nine livestock farms as mentioned in Section 3.7.3.11.

3.10                Environmental Monitoring and Audit

3.10.1            Construction Phase

3.10.1.1        EM&A for potential dust impacts are recommended during the construction phase of the Project so as to check compliance with legislative requirements.  Details of the monitoring and audit programme are presented in a stand-alone EM&A Manual.

3.10.1.2        Close liaison with contractors of concurrent projects, including NENT, the Loop and NOL, will be carried out for the purpose of minimizing the cumulative dust impact and facilitating the investigation of observed exceedance by dust monitoring if any. Detailed mechanism for liaison is presented in the EM&A Manual.

3.10.2            Operation Phase (Air Pollutants)

3.10.2.1        No adverse impact would be generated during the operation phase of the Project.  No EM&A would be required during the operation of the Project.

3.10.3            Operation Phase (Odour)

3.10.3.1        For the proposed EPP, commissioning test should be conducted for the CHP units and the boiler to ensure proper operation of the facilities.  As H2S is the major odour source associated with the effluent polishing plant, it is recommended to conduct the odour monitoring in terms of hydrogen sulphide (H2S) at the deodorizers upon commissioning and in the first three years to determine whether it can meet the overall 97% odour removal performance requirement. Upon the third-year monitoring, the odour monitoring should be reviewed and agreed with EPD if the monitoring is required to be continued.  

3.10.3.2        For the proposed FWPF, continuous monitoring of H2S and NH3 concentrations and air flow at the exhaust outlet of the deodourization system are recommended after commissioning to ensure the actual odour emission rate not exceeding the emission limit adopted in the calculation shown in Appendix 3.10.

3.10.3.3        For both STLMC EPP and FWPF, an Odour Complaint Registration System is also proposed in the EM&A programme to check whether the deodorizing units can fulfill the recommended odour removal performance. In addition, odour patrol should be carried out after regular and ad hoc maintenance or cleaning of the deodourizers during operation of STLMC EPP / FWPF to ensure no adverse odour impact arisen from the operation. Details of the monitoring and audit programme are contained in a stand-alone EM&A Manual.

3.10.3.4        Similar EM&A requirements, including continuous monitoring of H2S and NH3 and air flow at DO exhaust, odour complaint registration system and odour patrol, are recommended for the proposed RTS. However, the RTS is subject to further study by another party. The EM&A programme are to be determined in its associated study.

3.11                Environmental Acceptability of Schedule 2 Designated Projects

3.11.1.1        An application for an EP would be submitted under this EIA for DP1, DP2, DP3, DP6 and DP7.

New Primary Distributor and District Distributor Road (DP1)

3.11.1.2        With the proper implementation of dust mitigation measures for construction activities (as detailed in Section 3.8), no unacceptable dust impact would be resulted from the proposed roads during the constructional stage. There is no adverse operational air quality impact of these DP roads as mentioned in Section 3.7.

New San Tin Lok Ma Chau Effluent Polishing Plant (STLMC EPP) (DP2)

3.11.1.3        With the proper implementation of dust mitigation measures for construction activities (as detailed in Section 3.8), and odour mitigation measures (as detailed in Section 3.8.3), no unacceptable dust impact during the constructional stage nor adverse air quality impact including odour impact during the operational stage would be resulted from the proposed EPP.

New Water Reclamation Plant (DP3), Revitalisation of San Tin Eastern Main Drainage Channel (DP6), Recreational Development within Deep Bay Buffer Zone 2 (DP7)

3.11.1.4        With the proper implementation of dust mitigation measures for construction activities (as detailed in Section 3.8), no unacceptable dust impact during the constructional stage would be resulted from these DPs. There is no emission source associated with these facilities, thus there is no adverse operational air quality impact from these facilities.

Other DPs

3.11.1.5        There will be separate EIA studies to assess the following Schedule 2 DPs.  The air quality impact of these Schedule 2 DPs during construction and operation phases will be further investigated in their own EIA studies under the EIAO.  The relevant EM&A requirements for these Schedule 2 DPs will also be provided under their own EIA studies.

·          Refuse Transfer Station (RTS) (DP4);

·          400kV Electricity Substation (DP5).

3.12                Conclusion

3.12.1            Construction Phase

3.12.1.1        Potential air quality impact from the construction works of the Project would mainly be related to construction dust from excavation, material handling, spoil removal and wind erosion.  Construction activities of the concurrent projects within 500m assessment area would also pose cumulative dust impact.  With the implementation of mitigation measures specified in the Air Pollution Control (Construction Dust) Regulation together with the recommended dust suppression measures including frequent watering on active works areas, exposed areas and unpaved haul roads and other site management measures such as good site practices, and EM&A programme, no adverse air quality impact on ASRs in the vicinity of the work sites would be anticipated during the construction stage.

3.12.2            Operation Phase

3.12.2.1        Cumulative air quality impact arising from the vehicular emission from existing and planned open roads within 500m assessment area, emission from biogas facilities of the planned EPP, and 4-km major point source has been evaluated.  The prediction results concluded that the cumulative NO2, RSP, FSP and SO2 concentrations at all existing and planned ASRs would comply with AQOs. The predicted methane, HCl, HF and formaldehyde concentrations would be well below the respective international standards. No adverse air quality impact on the existing and planned ASRs is anticipated.

3.12.2.2        Cumulative odour impact arising from proposed EPP, FWPF, RTS and the three SPSs, the Retained Pig Farm and Existing San Tin Barracks STW have been evaluated. The predicted odour impact on existing ASRs would comply with the criterion stipulated in EIAO-TM, except at ASR A26 and A33. Exceedance of odour impact was predicted at attitude of 15mAG or below within the development sites near the Retained Pig Farm and Existing San Tin Barracks STW. The uses at these sites are to be air conditioned with their fresh air intake positioned at 20mAG or above. Therefore, it is concluded that no adverse odour impact is anticipated at the existing and planned ASRs, except A26 and A33.

3.12.2.3        Potential odour exceedances were predicted at two existing ASRs A26 and A33 for a short duration of time (up to 0.89% and 6.00% of time in a year) during operation phase of the Project. The Project would only contribute less than 0.02 OU/m3 at A26 and less than 0.07 OU/m3 at A33 during non-compliance period, which is less than 0.1 OU/m3. The odour control measures for the Project have been exhausted. Improvement in odour impact on the concerned locations (all existing ASRs at all assessment heights within the exceedance zone and project sites within the exceedance zone) has been predicted with the implementation of the Project, i.e. environmental benefit is anticipated. It is therefore concluded that there is no adverse residual odour impact arising from the Project.



[1] Nano Confined Catalytic Oxidation (NCCO) could achieve H2S and NM3 removal efficiencies at more than 96.97% and 95.65% respectively. Nano Plasma-Driven Catalysis (PDCC) could achieve H2S and NM3 removal efficiencies at 95% and 80% - 85% respectively. The data is provided from the manufacturer.

[2] The number of livestock farms to be retained shall be subject to further discussion with departments.

[3] DSD’s website : http://www.dsd.gov.hk/EN/Sewerage/Environmental_Consideration/Reclaimed_Water/

[4] Richard A. Duffee, Martha A. O'Brien and Ned Ostojic, 'Odor Modeling - Why and How', Recent Developments and Current Practices in Odor Regulations, Controls and Technology, Air & Waste Management Association, 1991

[5] Working Paper on Odour Sampling Results and Odour Emission Inventory – Pig Farm LK801 (Revision 2) dated 31 January 2022 which has been approved by EPD.