TABLE OF CONTENTS
2.1 Project Site Location and Site History
2.3 Appreciation of Existing Environment
2.4 Development Opportunities for Project Development
2.5 Development Constraints for Project Development
2.6 Description of the Project
2.10 Major Amendments from PODP to RODP
2.11 Consideration of Alternatives and Development of the Preferred Option
2.12 Proposed Construction Methodologies
2.13 Consideration of Alternatives for Construction Methodologies
2.14 Consideration of Alternatives for Reclamation Sequencing at TKO 132
2.15 Key Environmental Problems
2.16 Development Programme for the Project
List of Tables
Table 2.1 Needs for Public Facilities in PODP Stage
Table 2.2 Planning Requirements for Public Facilities in PODP stage
Table 2.3 Land Use Budget of the RODP (TKO 137)
Table 2.4 Land Use Budget of the RODP (TKO 132)
Table 2.5 Summary of Key Concerns to Environment
Table 2.8 Benefits and Dis-benefits of the Land use Option
Table 2.9 Benefits and Dis-benefits of the Layout of TKO 132
Table 2.10 Benefit and Dis-benefits of Alternative Configuration of TKO 132
Table 2.11 Benefit and Dis-benefits of Alternative Road Connecting to TKO 132
Table 2.12 Comparison of Benefits and Dis-benefits for Sewerage System Options
Table 2.13 Environmental Benefits and Dis-benefits of Effluent Outfall Options
Table 2.14 Environmental Benefits and Disbenefits of the Preferred Option
Table 2.15 Benefit and Dis-benefit of Locating Public Facilities in Caverns
Table 2.16 Benefits and Dis-benefits of Eco-shoreline
Table 2.17 Comparison of Seawall Design Options
Table 2.18 Comparison of Reclamation Options
Table 2.19 Comparison of Marine Viaduct Construction Options
Table 2.20 Summary of Key Environmental Problems Avoided and Environmental Options
Table 2.21 Preliminary Construction and Population Intake Schedule
Table 2.22 Summary of Potential Cumulative Impacts
List of Figures
Current Outline Zoning Plan of TKO 137 |
|
Preliminary Land Use of Land to be Created off TKO 132 |
|
Land Requirement Plan for TKO 132 |
|
Recommended Outline Development Plan of TKO 137 |
|
Recommended Outline Development Plan of TKO 132 |
|
Preliminary Outline Development Plan - TKO Area 137 |
|
Preliminary Outline Development Plan – Reclaimed land off TKO Area 132 |
|
Reclamation Extent at TKO 137 |
|
Reclamation Extent at TKO 132 |
|
Location Plan of TKO 137 Effluent Polishing Plant |
|
Schematic Layout of TKO 137 Effluent Polishing Plant |
|
General Layout – Works at TKO 137 |
|
General Layout – Works at TKO 132 |
|
Locations of Concurrent Projects |
List of Appendices
Tentative Preliminary Development Schedule |
|
Tentative Construction Programme |
|
Site Phasing Plan |
|
Proposed Construction Traffic Routing |
Land to be created off Tseung Kwan O Area 132 (TKO 132)
Table 2.1 Needs for Public Facilities in PODP Stage
Public Facility |
Need of the facilities/ site selection consideration |
Marine Frontage Requirement |
PFTF |
Public fill generated in the territory east is currently received and stockpiled at the TKO 137 temporary fill bank pending transfer to appropriate projects for reuse. With the plan to develop TKO 137, and while the upcoming reclamation projects in Hong Kong would reduce significantly the need for stockpiling public fill, there is still a need to retain a smaller-scale facility to receive and transfer public fill generated in the territory east (including TKO), at a location with marine frontage.
|
Marine frontage is required for transferring public fill received to appropriate projects through marine transport.
|
CBP |
The temporary CBP at TKO 137 is planned to be decommissioned by 2029. A permanent site for re-provisioning the CBP in the vicinity is required to serve construction sites in East Kowloon and New Territories East (including TKO), as freshly mixed concrete must be delivered within a reasonably short time to construction sites to maintain the quality of concrete.
|
To facilitate the operation of the CBP, a waterfront site to allow transportation of raw materials by sea for concrete production could avoid increasing loading on road traffic.
|
EFs, comprising power receiving and conversion facilities, are important strategic infrastructure for enhancing Hong Kong’s capability to import zero-carbon energy through regional cooperation and meeting the decarbonisation target of reducing Hong Kong’s carbon emissions by 50% before 2035 as compared to the 2005 level, with a view to achieving carbon neutrality before 2050.
TKO 132 is considered as the optimal location as it is situated near the potential connection points at TKO and Island East of the two power companies’ existing power grids, and their power systems can be interconnected through submarine cables with a shorter distance.
|
Marine frontage is necessary for the landing of submarine cables.
|
|
CWHF |
There is a need to set up a CWHF to receive, handle and bulk transfer construction waste primarily generated from the territory east (including TKO) to other waste handling facilities (e.g. landfill) upon closure of SENTX prior to population intake at TKO 137.
|
Bulk transfer of mixed construction waste to other waste handling facilities would require marine frontage.
|
RTS |
There is currently no dedicated RTS in the territory east area (including TKO). Temporary arrangement is put in place to transfer municipal solid waste (MSW) generated in this area to RTSs in Island East, West Kowloon and Shatin for handling. As these three RTSs have reached their capacity limits, there is a need to set up a RTS for serving existing and future developments in the territory east area (including TKO).
|
Marine frontage is necessary as MSW would be compacted and containerised in purposely built containers for onward shipment to waste management facilities via marine traffic.
|
MRCP |
As the Cha Kwo Ling site is to be developed into part of a waterfront promenade, the MRCP thereat is proposed to be reprovisioned at a location in the territory east to serve the eastern waters. Proximity to the Refuse Transfer Station also allows operational synergy.
|
Marine frontage is necessary for unloading collected refuse from the vessels.
|
TKO 137
TKO 132
TKO 137
Ř Housing and Job Opportunities
TKO 132
TKO 137
Ř Limited Development Area in TKO 137
Ř Tathong Channel Traffic Separation Scheme (Tathong Channel TSS)
Ř Avoidance and Minimisation of Industrial and Residential Interface Problems
Ř Consideration of Permitted Burial Ground during planning
Ř Existing Ecological, Natural and Landscape Features
Ř Declared Monument/ Site of Archaeological Interest
TKO 132
Ř Existing Government Land Licences
Ř Junk Bay Chinese Permanent Cemetery
Ř Junk Bay Dangerous Goods Anchorage (JBDGA)
Diagram 2.1 – Location of JBDGA[4]
Ř Requirements for Public Facilities
Table 2.2 Planning Requirements for Public Facilities in PODP stage
Public Facilities |
Required Footprint |
Maximum Building Height |
Minimum Marine Frontage Required |
EFs |
5.9 ha |
60 m |
200m for sloping seawall for cable landing |
RTS |
3.0 ha
|
40 m (50 m for on-shore crane) |
170 m |
CWHF |
4.5 ha |
20 m |
18 0 m |
PFTF |
4.0 ha |
25 m |
230 m |
CBP |
0.6 ha |
28 m |
80 m |
MRCP |
0.18 ha |
14 m |
30 m |
Ř Existing Ecological, Natural and Landscape Features
Ř Graded Historic Buildings
TKO 137
TKO 132
TKO 137
2.6.2.2 To put land resources into optimal use, higher development parameters[5] have been adopted, including a domestic plot ratio (PR) of 6.5 to 7.5 for public housing sites and a domestic PR of 4.0 to 6.0 for private housing sites. Non-domestic PR of 0.5 is adopted within the residential sites to create vibrancy and maintain vitality at street level.
Table 2.3 Land Use Budget of the RODP (TKO 137)
Approx. Area (ha) (% of total) |
|
Residential - Public - Private |
51.9 (50.8%) 25.9 26.0 |
Government, Institution and Community Facilities - Primary Schools - Secondary Schools - Sports Centre and Government Reserve - Divisional Police Station - Sub-divisional Fire Station cum Ambulance Depot - Government Complex (includes Swimming Pool Complex, Sports Centre, Public Market, Community Hall, Health Centre, Recycling Store, Refuse Collection Point) |
7.3 (7.2%) 2.0 1.6 0.8 0.4 0.5 2.0
|
Open Space |
18.8 (18.4%) |
Other Specified Uses – - Effluent Polishing Plant - Green Fuel Station - Electricity Substation - Fresh Water Service Reservoir/ Salt Water Service Reservoir |
6.9 (6.8%) 4.5 0.4 1.0 1.0 |
Roads |
17.2 (16.9%) |
TOTAL (about) |
102.2 (round to 103) (100%) |
Remarks: The above Land Use Budget is based on the RODP version dated 2024.07.10. Due to rounding, the figures presented may not add up precisely to the totals provided and percentages may not precisely reflect the absolute figures.
Public Housing, Private Housing and Mixed Uses (“RSc”, “R1”, “R2” & “OU(MU)”)
Open Space
TKO 132
Table 2.4 Land Use Budget of the RODP (TKO 132)
Land Use |
Approx. Area (ha) (% of total) |
(A) EFs |
5.6 (28.3%) |
(B) RTS |
3.0 (15.2%) |
(C) CWHF |
4.5 (22.7%) |
(D) PFTF |
4.0 (20.2%) |
(E) CBP |
0.6 (3.0%) |
(F) Others* |
2.0 (10.1%) |
Total (about) |
19.8 (round to 20) (100%) |
Infrastructural Facilities
Amenity
TKO 137
Ř Waterworks
Ř Sewerage
Ř Drainage
Ř Utility Services
2.6.3.6 Utility services are the fundamental support to a new development area. Similar to other urban areas, the utility services to be provided at TKO 137 to support the project development and future operation, including but not limited to below:
· Power supply network;
· Gas supply network;
· Telephone and telecommunication services;
· Cable TV service; and
· Street lighting and traffic signals system
Ř Landscaping Works at Open Spaces and Slopes
Ř Natural Terrain Mitigation Works
TKO 132
Ř Road Works and Construction of Marine Viaduct
Ř Building Works
2.6.3.10 Building works of each public facility will be carried out by corresponding Project Proponent or Bureaux and Departments (B/Ds) or future developers after site formation works and site handover. Phased implementation of site formation works and building works will be carried out to minimise concurrent construction works, thus minimise the environmental impact and nuisance to the public throughout the course of construction.
Ř Waterworks
Ř Sewerage
Ř Drainage
Ř Utility Services
2.6.3.14 Utility services are the fundamental support to a new development area. Similar to other urban areas, the utility services to be provided at TKO 132 to support the project development and future operation, including but not limited to below:
· Power supply network;
· Telephone and telecommunication services; and
· Street lighting and traffic signals system
Ř Landscaping Works at Amenity Areas and Slopes
2.6.3.15 Landscaping works at amenity areas and slopes will be conducted after site formation works and slope works. As these will mainly involve planting and pedestrian facilities, environmental impact is not anticipated.
Ř Natural Terrain Mitigation Works
Ř Road Transport - External Connectivity
Ř Road Network
Ř Public Transport
Ř Pedestrian Walkway and Cycle Track Networks
2.7.1.1 Based on the RODP, the Project would comprise the following designated projects by virtue of items A.8, C1, C2, F1, F2, G.2, G5 and H.1 under Part I, of Schedule 2 of EIAO.
DP1 – Construction of Carriageway Bridge at TKO 132
2.7.1.2 A single-2-lane carriageway in the form of viaduct structure for motor vehicles with minimum length of about 700 m between abutments and supported by piers, over the sea, will be constructed near TKO-LTT to provide a direct and convenient connection to the proposed facilities at TKO 132.
2.7.1.3 The proposed carriageway bridge at TKO 132 will fall into the category of Item A.8, Part I, Schedule 2 of EIAO - A carriageway bridge for motor vehicles, or a railway bridge, the length between abutments for which is more than 100 m, with bridge piers over the sea supporting the bridge. The general layout of proposed carriageway bridge is presented in Figure 1.2.
DP2 – Reclamation works at TKO 137 and off TKO 132
2.7.1.4 In order to create more land for the development of TKO 137, around 20 ha of land will be formed by reclamation. The reclamation is located at the barging basin at the north of TKO 137 and area along the southwest shoreline of TKO 137. The location of the reclamation works of TKO 137 development is shown in Figure 2.8.
2.7.1.5 TKO 132 will be formed by reclamation (around 19 ha) and the remaining by slope-cutting/ site formation to house the Public Facilities. The location of the reclamation works of TKO 132 development is shown in Figure 2.9. The boundary of the reclamation works at TKO 132 is around 30 m from the nearest boundary of On Luen Village (location of existing government land licences).
DP3 – Construction and Operation of Effluent Polishing Plant
2.7.1.7 An effluent polishing plant will be built at TKO 137 to support the population of TKO 137. The treatment capacity of the EPP is proposed to be at 54,000 m3 per day. The EPP is around 100 m from the planned residential area and around 30 m from the planned educational institution at TKO 137.
DP4 – Construction and Operation of Refuse Transfer Station
2.7.1.9 A Refuse Transfer Station will be built at land to be created off TKO 132 for serving existing and future developments in the territory east area (including TKO).
DP5 – Construction and Operation of Construction Waste Handling Facility
2.7.1.11 A Construction Waste Handling Facility with handling capacity of approx. 3,000 tonnes per day will be built at land to be created off TKO 132 to receive, handle and bulk transfer construction waste primarily generated from the territory east (including TKO) to other waste handling facilities upon the closure of SENTX prior to population intake at TKO 137. The CWHF is around 140m from On Luen Village (location of existing government land licences).
DP6 – Construction and Operation of Electricity Facilities
2.7.1.13 Electricity Facilities comprising power receiving and conversion facilities will be built at land to be created off TKO 132 for enhancing Hong Kong’s capability to import zero-carbon energy through regional cooperation and meeting the decarbonisation target of reducing Hong Kong’s carbon emissions. EFs are planned to house equipment up to 400kV.
2.7.2.1 With reference to the Project scope as stated in Section 1.2, the EIA has provided an assessment of the potential environmental impacts associated with the construction and operation of the Project, based on the engineering design information available at this stage. For DP1, DP2 and DP3, application of environmental permit would be made based on the specific assessments with specific mitigation measures recommended within the individual chapters. Separate EIA studies would be prepared for application of the environmental permit for DP4, DP5 and DP6.
2.8.1.1 The Project make use of the formed land of TKO 137 which is currently used as a temporary fill bank into a new community primarily for housing purpose. The land to be created off TKO 132 which is at a relatively obscure area, is able to accommodate the Public Facilities. The development of the Project could result in the following benefits:
Direct Benefits
2.8.1.2 Diverse housing options to meet long-term housing needs of Hong Kong – Different housing types will be provided to meet long-term housing needs of Hong Kong, engendering a sense of belonging for people and ultimately enhancing their quality of life. The Project will provide about 50,000 new flats.
Environmental Benefit and Initiatives
2.8.1.4 Reduce heavy vehicles at Wan Po Road – Currently, vast majority of the existing traffic on Wan Po Road south of LOHAS Park is generated by TKOFB. The heavy vehicles, such as diesel fuel dump trucks, are driving through the existing road network of TKO to TKOFB which could cause disturbance to local residents. With TKOFB converting into a housing development, the traffic on Wan Po Road is expected to shift predominantly to electric and petroleum vehicles, which emit fewer pollutants. By locating the PFTF at TKO 132, those heavy vehicles generated could be diverted away from TKO New Town and access to Kowloon directly via Tseung Lam Highway. This would minimise any possible nuisance to local residents.
2.8.1.8 Walkability and cycling – Walkability and cycling are the key elements for the Project. A comprehensive and attractive pedestrian walkway and cycle track network is planned throughout the TKO 137. Key destinations, such as key public transport nodes, major employment nodes and residential communities, would be linked up by pedestrian walkways, cycle track and open spaces. This would allow a safe, convenient and comfortable movement within TKO 137 and create local communities with easily accessible daily necessities to promote an active and healthy lifestyle to reduce mechanised vehicular trips and hence carbon emissions.
· Comprehensive pedestrian network – Comprehensive pedestrian network of TKO 137 connects residential and employment nodes to provide continuous walkways for pedestrians. It could promote walking from homes to workplaces, retail and services for various purposes.
· Open space network / green linkages – A series of open space corridors branching off the main comprehensive pedestrian network, including the open spaces along drainage channel and linear parks along major road. They shall provide additional pedestrian connections to the surrounding residential communities and employment areas, and further to the green and natural areas.
· Robust cycling network – TKO 137 provides a robust cycling network which link effectively to the existing and planned cycling tracks within and outside TKO 137. The proposed cycling network would connect to the existing tracks from Wan Po Road to create a continuous cycling environment that extends to other destinations beyond TKO 137. Routes within TKO 137 would be provided parallel to the major roadways to serve commuting needs, as well as to provide some other routes within the proposed open space areas for leisure.
Promoting Biodiversity
2.8.1.10 Create liveable environment - The landscape framework should be formulated based on the findings of the ecological survey. Following principles applied in the landscape framework: (i) Optimise key existing ecological capital where possible. (ii) Maximise green space coverage for habitat creation and leisure activities; (iii) Diversify landscape typologies through a rich mix of landscape characters and activities for both people and wildlife; and (iv) Create a mutual respect culture between people and nature through design.
Table 2.5 Summary of Key Concerns to Environment
Key Issue |
Key Comments |
Responses |
Reclamation |
· Straightening of the coastline and narrowing the bay of Tseung Kwan O may increase the risk of flooding when a typhoon strikes and cause damage to the Tseung Kwan O Waterfront Promenade and Heng Fa Chuen
|
· Computer wave model analysis with and without the reclamation of TKO 132 and TKO 137 have been conducted under separate study of the Project. The simulation results indicates that the direction of incident ocean waves is governed by the local geometry of Tathong Channel and focused on the south-east direction. It also verifies that the proposed reclamation will have no adverse impact to Tseung Kwan O Waterfront Promenade and Heng Fa Chuen in terms of exposure to extreme waves and corresponding risks. |
· Reclamation of 25 ha for TKO 132 is too large and suggested using slope-cutting method or relocation to caverns to create land |
· Reclamation has been reduced to approximately 19 ha by optimising land use layout and making use of slope-cutting for land creation. Total length of the marine frontage has been reduced from around 1270 m to 1190 m by shared use of marine access. · Feasibility to accommodate the Public Facilities to cavern have been considered. As all public facilities require marine frontage for the normal operation, only part of the public facilities could have potential to be relocated into caverns. Cavern options induce higher design and construction risks, longer construction period and increases capital and recurrent costs compared with land reclamation option. The benefit and dis-benefits are discussed in detail in Section 2.11.8. |
|
· Adopting offshore reclamation to reduce the impact to the natural shoreline of great geodiversity value |
· Direct land access is required by the Public Facilities, especially for Electricity Facilities where cable wayleave to inland is necessary. · Off-shore reclamation, particularly when extending towards the existing shoreline for EFs cables, presents several disbenefits. It significantly reduces tidal flushing and water circulation, leading to decreased current velocities that enhance sediment deposition and increase the need for maintenance dredging, which can compromise water quality at coral recipient sites. The capability for self-cleansing and water quality recovery diminishes, resulting in depleted dissolved oxygen levels. Additionally, vessel operations become closer to noise-sensitive areas, raising concerns about marine traffic noise. The reclamation further extends into the sea which exacerbates visual and landscape impacts on nearby residential developments. Finally, this approach entails longer construction times and higher costs due to increased seawall requirements and the volume of Deep Cement Mixing needed. Details are discussed in Section 2.11.3. |
|
· Public Facilities at TKO 132 should be incorporated into the reclamation area at TKO 137. |
· Accommodating the Public Facilities at TKO 137 will occupy a large section of the waterfront and require a certain buffer distance from the residential area. This will not make good use of the land and will not be conducive to the creation of a new livable community in the future. In addition, vehicles using the facilities, such as dump trucks, concrete lorry, will drive through the existing road network of TKO New Town to reach TKO-LTT, putting pressure on the road network of TKO. |
|
Traffic and Transportation |
· Development in TKO 137 would aggravate traffic pressure in TKO district with new population
|
· Traffic and traffic impact assessment shows the traffic conditions on roads in TKO are acceptable. |
· Concern about traffic arrangements and mitigation measures during construction period. Suggested future residents to move in after establishing transportation infrastructure. Utilisation of environmental-friendly vehicles is also suggested.
|
· Traffic noise impact has been assessed under this EIA. With the implementation of the proposed mitigation measures for construction phases, no adverse environmental impacts on the sensitive receivers would be anticipated. · Green fuel station is proposed at TKO 137 to encourage residents to use environmental- friendly vehicles. |
|
· Increased number of heavy vehicles in TKO will increase traffic pressure and cause traffic noise |
· The heavy vehicle generated from existing TKO 137 Fill Bank via Wan Po Road would be diverted to TKO 132 after relocation. · Heavy vehicles generated from the Public Facilities at TKO 132 would be diverted away from TKO and access to Kowloon directly via TKO-LTT to minimise disturbance to local residents. |
|
Ecology and Fisheries |
· Potential ecological impact on fish of conservation importance (Philippine Neon Goby (Stiphodon atropurpureus)) and coral communities |
· Extent of reclamation has been reduced to 19 ha to minimise direct impact on fish of conservation importance and coral communities. The footprint of reclamation has avoided the coral recipient site. Coral translocation is also recommended, as to minimise the ecological impact on coral colonies to be affected by the Project. · The associated foundation and pier of the marine viaduct would locate away from the downstream section to avoid direct impact and blockage of natural watercourse S2 which the concerned fish species was recorded, and works including natural terrain mitigation works and construction of marine viaduct would be also conducted at least 20m away from natural watercourse S2. |
· The extent of the reclamation has been reduced to minimise the direct impact on the marine habitats at TKO 132. · Enhancement measures such as ecological enhanced seawall have been proposed to enhance the marine habitats during the operation of TKO 132 and provide opportunity to marine organisms. · For impact on fisheries, there would be around 22 ha loss of fishing ground and fisheries habitats due to reclamation and the marine viaduct piles. However, the loss only constitutes an insignificant proportion of fishing ground and fisheries habitats in Hong Kong, which the fisheries operations primarily consist of small, flexible sampans, and the low to moderate fisheries production consisting mainly of non-commercial or low valued species, the direct impacts on fisheries are considered to be minor. |
||
Public Facilities |
· Cumulative impact of proposed Public Facilities |
· Cumulative impact from the construction and operation of the Public Facilities at TKO 132 have been assessed under this EIA. With the implementation of the proposed mitigation measures for construction and operation phases, no adverse cumulative environmental impacts on the sensitive receivers would be anticipated. · The operation of the Public Facilities is regulated by relevant legislation or contract. |
· Potential environmental impact (e.g. noise quality, air quality, water quality, landscape and visual, hazard to life etc.) to sensitive receivers in close proximity to TKO 132 |
· EIA has been conducted according to the requirement as stipulated in the EIA Study Brief. Based on the assessment results, the Project would be environmentally acceptable with the implementation of the proposed mitigation measures for construction and operation phases. Details of the assessment under different aspect are presented in S.2 to S.17 of this EIA Report. |
TKO 137
Ř Road, Pedestrian, Cycling Connectivity and Public Transport Interchange
2.10.1.2 Some refinements on the road alignment, including footpaths and cycle tracks have been made as appropriate for better design and connectivity. Cycle track arrangement has also been reviewed and refined to promote better connectivity and proximity to developments. Footpath have also been reserved to accommodate potential laybys. Road L1 has shifted eastward.
2.10.1.3 Development boundaries have been reviewed to suit the latest planning after the PODP. The plot ratio have been reviewed and adjusted with the stepped down development intensity towards the waterfront maintained.
Ř Government Facilities
2.10.1.4 Based on departmental requests, a fire station cum ambulance depot has been reserved. A swimming pool, a public market and a refuse collection point are also to be accommodated in the Government Complex together with the planned community hall, health centre and sports centre.
A recycling store is proposed to be co-located with the refuse collection point within the Government Complex at Site.
Ř Interface with TKLSE
2.10.1.5 In terms of the land use, re-alignment of the lot boundaries of several public housing sites has been made to avoid encroaching on the works areas and potential station facilities of TKLSE such that the implementation of the public housing development will not be affected.
Ř Infrastructures
2.10.1.6 As coordinated with CLP, a 400kV Electricity Substation (ESS) is no longer required while two 132kV ESS should still be reserved. Two sites are reserved for provision of a 132kV Bulk ESS and a 132kV Primary ESS.
2.10.1.7 In view of the Government’s initiatives in promoting greener fuels, annotation of the petrol & LPG station has been updated as Green Fuel Station.
2.10.1.8 In reviewing infrastructural demand arising from development of TKO 137, fresh and salt water service reservoirs have been reserved at Fat Tong Chau.
2.10.1.9 In order to minimise the water quality impacts, the use of a submarine effluent outfall from the EPP proposed during the PODP stage is not recommended. Instead, both storm drains and effluent from the EPP will be directed to the seawall via an underground pipe or box culvert, ensuring that the outfall remains submerged below the marine water surface. Therefore, DP Item F.6-A submarine sewage outfall, as stated in the EIA Study Brief, is removed from this EIA study.
Ř Natural Terrain Mitigation Works
2.10.1.10 The proposed natural terrain mitigation works (i.e. flexible barrier) has been re-located to be within the EPP site to avoid any works encroaching into Clear Water Bay Country Park (CWBCP). Therefore, DP Item Q.1- Earthworks partly or wholly in an existing country park, as stated in the EIA Study Brief, is removed from this EIA study.
Ř Development Parameters
2.10.1.11 Residential - Comparing to PODP, the layout has been re-juggled such that all the private housing land parcels are now located along the waterfront, in order to minimise the impact of the construction of TKLSE on the handover of public housing sites. To create a stepped building height profile from northeast to the southwest, the domestic plot ratio (PR) of private housing sites along waterfront has been updated to a range of 4.0 to 6.0, whilst the domestic PR of public housing sites is updated to a range of 7.0 to 7.5. With the adjustment on layout and plot ratio, the building height restrictions (BHR) of the residential sites has been updated in RODP, ranging 120 mPD to 200 mPD for private housing and 175 mPD to 200 mPD for public housing. The non-domestic PR of two private housing sites PR1 and PR2 have been lowered from 0.5 in PODP stage to 0.3 in RODP stage to achieve a ratio similar to the current retail provision to population status in TKO District.
2.10.1.12 G/IC/OU – To address the departmental request of having a swimming pool of minimum 2 ha according to Hong Kong Planning Standards and Guidelines (HKPSG), the site G4 has been increased in site area from 1 ha to 2 ha to accommodate various G/IC facilities, including Swimming Pool, sports centre, public markets, community hall, health centre, refuse collection point and recycling store. A set of more appropriate BHR has been reflected on RODP for the G/IC or OU facilities. For utilities, the proposed Electricity Substations (ESS) (OU1 and OU2) are subject to maximum building height of 3 storey. The proposed Green Fuel Station (GFS) (OU3) is subject to maximum building height of 1 storey. The proposed Effluent Polishing Plant (EPP) (OU4) subject to maximum building height of 30 mPD. The proposed Fresh Water Service Reservoir (FWSR) (OU5) and Salt Water Service Reservoir (SWSR) (OU6) are subject to maximum building height of 80 mPD. As for Government Reserve and Sport Centre (G3) and the Divisional Police Station (OU1), both BHRs are revised as 110mPD, in response to the operational needs of Hong Kong Police Force (HKPF) and referencing existing similar G/IC facilities.
TKO 132
Ř Road
2.10.1.13 Other than the slip roads to/from TKO-LTT, one further pair of slip roads to/from Tseung Lam Highway would be provided. Road layout have been reviewed.
Ř Public Facilities
2.10.1.14 With regards to optimising land use layout in order to reduce the reclamation area, the following changes were made for the site configuration of each facility.
· EFs – Previous proposed L-shaped land parcel for EFs is revised to rectangular shape. Site area is reduced from 5.9ha (under PODP) to 5.6ha.
· CWHF – CWHF is relocated adjacent to EFs and configuration of the land parcel is revised to make use of the 190m frontage of EFs.
· PFTF – PFTF is relocated adjacent to CWHF and configuration of the land parcel for PFTF is revised.
· RTS – RTS is relocated further away from the nearest residential development adjacent to PFTF and configuration of the land parcel for RTS is revised.
· CBP - Configuration of the land parcel for CBP is revised to minimise the reclamation area.
· MRCP – In view of the public aspiration to reduce the number of Public Facilities, the MRCP will not be relocated to TKO 132.
Ř Breakwater
2.10.1.15 In accordance with the computer wave simulation, the significant wave height at the proposed TKO 132 under tropical cyclone warning signal no.3 is approximately 1 to 2 m. Common vessels to be used at TKO 132 such as working barges and material transport vessels are relatively resilience to wave impacts and are capable to operate under the 1 to 2m wave conditions.
2.10.1.16 After liaison with the future operators of the Public Facilities, it is noted that the breakwater is not necessary for their operations and is therefore removed from the RODP. It reduces the reclamation extent. Therefore, the DP Item C.4- A breakwater more than 1km in length or a breakwater extending into a tidal flushing channel by more than 30% of the channel width, stated in the EIA Study Brief, is removed in this EIA study.
Table 2.6 Comparison of Key Development Parameters and Land Use Budget between PODP and RODP for TKO 137
|
PODP |
RODP |
Area (ha) |
~101 |
~102.2 |
Population |
~135,010 |
|
Estimated Employment |
~21,300 |
~22,100 |
No. of flats |
~50,000 (with ~70% public housing) |
Table 2.7 Comparison of Key Development Parameters and Land Use Budget between PODP and RODP for TKO 132
|
PODP |
RODP |
Area* (ha) |
~25 |
~20 |
Estimated Employment |
~219 |
~389 |
Remarks: * Marine Viaduct is not included.
2.11.1.4 The environmental benefits and dis-benefits were also considered in formulating the preferred option as summarised in Table 2.8 below.
Table 2.8 Benefits and Dis-benefits of the Land use Option
Options |
Benefits |
Dis-benefits |
Accommodate Public Facilities at barging basin of TKO 137 |
· Reclamation off TKO 132 would not be required |
· As the existing marine frontage at the barging basin TKO 137 is not sufficient, this option will occupy a large section of the waterfront at TKO 137 · As the Public Facilities might require a certain buffer distance from the residential area, thus TKO 137 could not be developed into a predominantly residential community for a population of around 135,000 · Pollution source from the Public Facilities is close to sensitive receivers (i.e. future residential of TKO 137) · Potential noise, air and landscape and visual impact to future residents of TKO 137
|
Accommodate Public Facilities at reclamation off TKO 132 (Preferred Option) |
· Distant the potential pollution source from the Public Facilities away from sensitive receivers (around 1km away from Ocean Shores) · Avoid directing traffic arisen from proposed Public Facilities along heavily populated areas · Reduce visual impact to nearby residents with the Public Facilities located away around 1km away from Ocean Shores |
· Reclamation off TKO 132 would be required |
2.11.2.1 In the PODP for TKO 132, the original layout for the development could optimise the use of the local terrain to alleviate the visual impact of the reclaimed site on the residents of Tiu Keng Leng, the layout and road alignment takes up around 790m of the natural shoreline which causes direct impact to the coral recipient site. The layout in the PODP also requires more extensive reclamation. Therefore, the layout option in PODP was no longer recommended. The following table (Table 2.9) summarises the benefits and dis-benefits identified.
Table 2.9 Benefits and Dis-benefits of the Layout of TKO 132
Options |
Benefits |
Dis-benefits |
Alternative Option – PODP scheme
|
· Optimise the use of the local terrain to alleviate the visual impact of the reclaimed site on the residents of Tiu Keng Leng |
· Direct impact to coral recipient site · Impact to the natural shoreline (only around 1000m out of total length of 1600m of natural shoreline can be maintained) · Large area of permanent loss for subtidal hard substrata is anticipated. · More potential direct ecological impact on coral communities |
Preferred Option (Current RODP of TKO 132) |
· Avoid direct impact to coral recipient site · Reduced reclamation extent and shortened road alignment minimise the impact to the natural shoreline. Approximately 1km of natural shoreline can be maintained · Area of permanent loss for subtidal hard substrata is considered smaller than the alternative option · Minimise potential direct ecological impact on coral communities by avoiding reclamation at area with higher coral coverage |
· Less use of the local terrain to alleviate the visual impact of the reclaimed site on the residents of Tiu Keng Leng |
Diagram 2.2 Alternative Configuration of TKO 132 (L-shaped Layout)
Table 2.10 Benefit and Dis-benefits of Alternative Configuration of TKO 132
Options |
Benefits |
Dis-benefits |
Alternative Configuration – L-shaped Layout
|
· Maintain majority of the natural shoreline. |
· Significantly diminish the tidal flushing capacity and water circulation around TKO 132 as compared to the proposed layout. · Footprint of the reclaimed land encroach into the shallow water region so more sediment would need to be dredged to ensure marine safety for vessel operation at inner basin. · Velocity of the current inside the water surrounded by the reclamation will be reduced which increase the sediment deposition rate and increase the frequency of maintenance dredging. · Self-cleansing and water quality recovery capability would reduce, and cause DO depletion. · Vessel operations are closer to the Nosie Sensitive Receivers at TKO 132. Higher marine traffic noise level is anticipated. · The reclaimed land is situated further out to the sea which increases the landscape and visual impact to the nearby residents. · Longer construction time and greater cost are required due to increase in seawalls and Deep Cement Mixing (DCM) volumes. · Longer construction noise period is anticipated to the Noise Sensitive Receivers at TKO 132. · There will be a bottle-neck at the EFs that the access to all other facilities would be totally relied on the public road where the buffer area would not be available due to facing the open water. · Security concerns on the exposed EFs’ cables where the cables trough would be subject to damages. |
Preferred Option (Current RODP of TKO 132) |
· Use of the local terrain to alleviate the visual impact of the reclaimed site on the residents of Tiu Keng Leng. · Reduce reclamation extent by slope-cutting. · No embayment area is created, hence tidal flow and water circulation can be maintained. Frequent routine dredging for vessel operation is not necessary. |
· Less use of the local terrain to alleviate the visual impact of the reclaimed site on the residents of Tiu Keng Leng. · Direct impact to the natural shoreline. |
Table 2.11 Benefit and Dis-benefits of Alternative Road Connecting to TKO 132
Options |
Benefits |
Dis-benefits |
Alternative Option - Dual-2-lane carriageway with slip roads connecting TKO 132 to/from TKO-LTT, to/from Tseung Kwan O Town Centre and to/from Cross Bay Link |
· Provide connection between TKO 132 and TKO East. |
· The construction involves foundation and superstructure of the marine viaduct. Hence, longer construction noise period will be anticipated to the Noise Sensitive Receivers at TKO 132. · Higher construction cost and longer construction time with the additional slip road to/from Cross Bay Link. · Larger extent of the slip roads, hence, more affected areas on landscape resources and larger visual obstruction to the public viewers will be anticipated. |
Preferred Option - Single-2- lane carriageway with slip roads to/from TKO-LTT and to/from Tseung Kwan O Town Centre |
· Shorter construction time which minimise the environmental impact to the nearby sensitive receivers. · Smaller affected areas on landscape resources and reduce visual impact to the public viewers in Tiu Keng Leng. · Lower construction cost. |
· No connection between TKO 132 and Lohas Park. |
Table 2.12 Comparison of Benefits and Dis-benefits for Sewerage System Options
Options |
Benefits |
Dis-benefits |
Provision of a local sewage treatment works |
· Minimise the impact to existing sewerage network in TKO. |
· Larger footprint is required for the treatment works which may require additional reclamation and cause greater disturbance to the seabed. · Require disposal of residual sludge and other waste materials; therefore, it increases traffic emissions. · Larger visual impact is anticipated. · Longer construction period is anticipated. |
Provision of gravity sewer pipeline |
· Simple to operate and maintain if no intermediate / downstream SPS is required. |
· Long gravity sewer would result in very deep sewer pipe and manholes at the downstream end, being costly to construct, and possibly requiring an intermediate SPS to lift sewage to a shallower depth to improve sewerage pipeline construction practicality, and to lift flows into the existing downstream sewerage network. · Longer construction period is anticipated. |
Provision of a sewage pumping station (Preferred Option) |
· Less land required for pumping station than local Sewage Treatment Works, to reducing the need of marine dredging works due to reclamation. · Smaller footprint and building size such that to having less visual impact. |
· Increase in traffic emissions anticipated due to waste disposal. |
2.11.6.1 Outfall discharge options have been evaluated for both storm drains and effluent from the EPP at TKO 137. The proposed system will utilise a seawall outfall only, with no submarine intakes or outfalls included in the Project. Model results indicate that the marine water quality effects from the EPP's seawall discharges are insignificant, and these discharges will not lead to any water quality non-compliance during normal or emergency operations. Therefore, the seawall discharge location is deemed the most effective option for minimising water quality impacts, and the use of a submarine effluent outfall is not recommended. Both storm drains and effluent from the EPP will be directed to the seawall via an underground pipe or box culvert, ensuring that the outfall remains submerged below the marine water surface. The following table (Table 2.13) summarises the benefits and dis-benefits identified.
Table 2.13 Environmental Benefits and Dis-benefits of Effluent Outfall Options
Options |
Benefits |
Dis-benefits |
Alternative Submarine Outfall Option |
· Submarine outfall with multiport diffusers on seabed would potentially provide better effluent dispersion during the operational phase. |
· Need of dredging for construction of new outfall diffusers with waste / sediment management issue. · Release of sediments and sediment-bound contaminants during construction of new outfall diffusers, causing indirect marine water quality, fisheries and marine ecological impacts. · Temporary loss of fishing ground and marine habitat during the construction of new outfall diffuser. · Permanent loss of fishing ground and marine habitat due to operation of new outfall diffuser. |
Preferred Seawall Outfall Option |
· No loss of fishing ground / marine habitat during construction and operational phases. · No disturbance to seabed sediment and no release of sediment and sediment-bound contaminants. |
· Potentially inducing greater water quality impact to nearby water sensitive receivers but the impact is predicted to be insignificant and acceptable, in view that the seawall outfall is located at Tathong Channel with deep water depth and high flushing capacity. |
2.11.7.1 Strategy on building height and built-form are applied to form a pleasant vertical image of the waterfront neighbourhood. A diminution in development height from the hinterland to the waterfront area has been adopted to enhance variety in building height and massing of development. A stepped building height profile descending from the northeast to the southwest and towards the waterfront is proposed with respect to the mountain backdrop. As compared to options of having more uniform building height, the current option of having stepped building height would avoid “wall effect” development along the coastal area as far as possible. In terms of built-form, monotonous and continuous built-form has been avoided with the introduction of open space corridor, in order to reduce visual obstruction and enhance the landscape character. The following table (Table 2.14) summarises the benefits and dis-benefits identified.
Table 2.14 Environmental Benefits and Disbenefits of the Preferred Option
Options |
Benefits |
Dis-benefits |
More uniform building height and built-form across different land lots |
· Nil. |
· Create “wall effect” developments along the coastline. · Resultant building mass and built-form would be stereotype or monotonous. · Substantial visual obstruction to the public viewers would be anticipated. |
Stepped building height from inland towards the waterfront together with varied built-form (Preferred Option) |
· Reduce visual impact to the residents of Siu Sai Wan by having stepped building height profile descending from the northeast to the southwest and towards the waterfront. · Avoid “wall effect” from continuous built-form improve air ventilation. · Encourage diversity and variety in building mass and built-form. · Enhance the landscape character with introduction of open space corridor. |
· Nil. |
Table 2.15 Benefit and Dis-benefit of Locating Public Facilities in Caverns
Options |
Benefits |
Dis-benefits |
Locating part of the Public Facilities to Cavern |
· Reduce reclamation area. |
· Increase in construction and operation cost due to additional need of ventilation system and E&M facilities. · Longer construction time led to programme mismatch for site handover site for CBP and PFTF. This affects the closure of temporary CBP and decanting of PFTF at TKO 137 and therefore affect the population intake schedule. · The cavern portal is away from the berthing area, double handling of the materials for most of the Public Facilities is inevitable. |
Locating Public Facilities to Reclaimed Land (Preferred Option) |
· Lower construction cost and operation cost compared to cavern option. · Construction is relatively faster compared to cavern option. |
· More reclamation area |
Table 2.16 Benefits and Dis-benefits of Eco-shoreline
Options |
Benefits |
Dis-benefits |
Adopt Eco-shoreline |
· Welcome intertidal species back to coastlines by increasing microhabitats within the shoreline by grooves or holes. · Encourage the attachment of marine flora and fauna and enhance water filtration. |
· Increase in construction cost. |
No Eco-shoreline |
· Lower construction cost in compared with seawall with eco-shoreline features |
· Diminish the ecological values/systems along coastline. |
TKO 137
Stage 1: Installation of Silt Curtain
Commencement of installation of silt curtain for the whole site to prevent muddy water from flowing out of the site boundary.
Stage 2: Removal of Rock Armour of Existing Seawall
Commencement of removal of rock armour of existing seawall to facilitate the installation of geotextile.
Stage 3: Installation of Sand Blanket
Commencement of placement of sand blanket (around 2 m thick) to facilitate future ground treatment works. Deposition of the sand blanket would be carried out in layers not exceeding 0.5 m thick with a leading edge between consecutive layers to prevent mud wave formation.
Stage 4: Construction of DCM for Proposed Seawall
Commencement of marine DCM works for the non-dredged seawall region.
Stage 5: Construction of Proposed Seawall
Staged construction of proposed seawall after completion of DCM works. Reusing some of the existing rock armour.
Stage 6: Construction of DCM for Main Reclamation
Commencement of DCM works for the non-dredged main reclamation region.
Stage 7: Reclamation Filling to +3.0mPD (Above Water)
Carry out earth filling works to +3.0mPD above water to facilitate future ground treatment works.
Stage 8: Jet Grouting on Land
Carry out jet grouting for the dredged trench region.
Stage 9: Construction of Temporary Seawall
Temporary seawall to enclose the area
Stage 10: Filling to Formation Level / Surcharge
Continue earth filling up to the future formation level and establish surcharge filling where necessary.
TKO 132
Stage 1: Installation of Silt Curtain
Commencement of installation of silt curtain for the whole site to prevent muddy water from flowing out of the site boundary.
Stage 2: Removal of Obstruction/ Dumped Material
Commencement of removal of obstruction to facilitate the construction of DCM.
Stage 3: Installation of Sand Blanket
Commencement of placement of sand blanket (around 2 m thick) to facilitate future ground treatment works. Deposition of the sand blanket would be carried out in layers not exceeding 0.5 m thick with a leading edge between consecutive layers to prevent mud wave formation.
Stage 4: Construction of DCM for Proposed Seawall
Commencement of marine DCM works for the non-dredged seawall region.
Stage 5: Construction of Proposed Seawall
Staged construction of proposed seawall after completion of DCM works.
Stage 6: Construction of DCM for Main Reclamation
Commencement of DCM works for the non-dredged main reclamation region.
Stage 7 Reclamation Filling to +3.0mPD (Above Water)
Carry out earth filling works to +3.0mPD above water to facilitate future ground treatment works.
Stage 8: Jet Grouting
Carry out jet grouting for regions with thick layer of dumped materials.
Stage 9: Filling to Formation Level / Surcharge
Continue earth filling up to the future formation level and establish surcharge filling where necessary. Reusing some of the excavated dumped materials.
Precast segmental method: With the bridge deck constructed as precast segments (each a few metres long) which are lifted into position and then stitched & prestressed together.
Option 1 – Fully Dredged Seawall
Option 2 – Partial Dredged Seawall
Option 3 – Non-dredged Seawall with Ground Improvement
Table 2.17 Comparison of Seawall Design Options
Options |
Benefits |
Dis-benefits |
Option 1 – Fully Dredged Seawall |
· Well proven technology in Hong Kong. · Relatively fast if dumping site for marine sediment is available and fill source is sufficient. · Familiar by most of the local contractors. · Better control of the stability and settlement as all the compressible soft sediment underneath the seawall are removed. |
· Large amount of dredged marine sediment to be disposed. · Large amount of the fill materials to be required to fill the dredged trench as the foundation to support the seawall on top. · Increase of marine vessels trips for the transportation of the relatively large amount of dredged marine sediment and fill materials. · More frequent marine vessel journeys will increase the noise and air impact. · Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent. |
Option 2 – Partial Dredged Seawall |
· Well proven technology in Hong Kong. · Relatively fast if dumping site for marine sediment is available and fill source is sufficient. · Familiar by most of the local contractors. · Relative less marine sediment to be disposal compared to fully dredged seawall. · Relative less fill materials to be required compared to fully dredged seawall. |
· Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent. · Relative higher risk of settlement and instability compared to fully dredged seawall. · Even though less than fully dredged seawall, relative large amount of dredged marine sediment is still required to be disposed. · Even though less than fully dredged seawall, large amount of the fill materials is still required to fill the dredged trench as the foundation to support the seawall on top. · Even though less than fully dredged seawall, increase of the marine vessels trips for the transportation of the relatively large amount of dredged marine sediment and fill materials. · Even though less than fully dredged seawall, more frequent marine vessel journeys will increase the noise and air impact. |
Option 3a and 3b – Non-dredged Seawall with Ground Improvement |
· Minimal or even no marine sediment are required to be disposed. · Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged seawall. · Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged seawall. · DCM methods is an environmentally friendly method which does not require dredging and disposal of dredged material · Largely reduce water quality impact associated with dredging works |
· Relative longer construction period (if PVD and surcharge method is adopted) may be required compared to fully dredged seawall. · Relative higher cost compared to fully dredged / partial dredged seawall. |
Option 1 – Fully Dredged Reclamation
Option 2 – Partially-dredged Reclamation
Option 3 – Non-dredged Reclamation (using Deep Cement Mixing)
Table 2.18 Comparison of Reclamation Options
Options |
Benefits |
Dis-benefits |
Option 1 – Fully Dredged Reclamation |
· Well proven technology in Hong Kong. · Relatively fast if dumping site for marine sediment is available and fill source is sufficient. · Familiar by most of the local contractors. · Better control of the stability and settlement as all the compressible soft sediment are removed. |
· Large amount of dredged marine sediment to be disposed. · Large amount of the fill materials to be required to fill the dredged trench. · Increase of marine vessels trips for the transportation of the relatively large amount of dredged marine sediment and fill materials. · More frequent marine vessel journeys will increase the noise and air impact. · Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent. |
Option 2 – Partial Dredged Reclamation |
· Well proven technology in Hong Kong. · Relatively fast if dumping site for marine sediment is available and fill source is sufficient. · Familiar by most of the local contractors. · Relative less marine sediment to be disposal compared to fully dredged reclamation. · Relative less fill materials to be required compared to fully dredged reclamation. |
· Dredging of the marine sediment will inevitably induce impact to the water quality to certain extent. · Relative higher risk of settlement and instability compared to fully dredged reclamation. · Even though less than fully dredged reclamation, relatively large amount of dredged marine sediment is still required to be disposed. · Even though less than fully dredged reclamation, large amount of the fill materials is still required to fill the dredged trench. · Even though less than fully dredged reclamation, increase of the marine vessels’ trips for the transportation of the relatively large amount of dredged marine sediment and fill materials. · Even though less than fully dredged reclamation, more frequent marine vessel journeys will increase the noise and air impact. |
Option 3 – Non-dredged Reclamation (using Deep Cement Mixing) |
· No marine sediment is required to be disposed. · Significantly reduced demand of fill materials for filling of the dredged trench compared to fully dredged / partial dredged reclamation. · Significantly reduced marine vessels trips are required for transportation of dredged marine sediment and fill materials compared to fully / partial dredged reclamation. · DCM methods is an environmentally friendly method which does not require dredging and disposal of dredged material. |
· Relative higher cost compared to fully dredged / partial dredged seawall reclamation. |
Table 2.19 Comparison of Marine Viaduct Construction Options
Options |
Benefits |
Dis-benefits |
Precast Segment (Preferred Option) |
· Minimise concrete mixing truck travelling in site area, thus minimise potential air and noise impact. · Shorten construction time, minimising on-site potential environmental impacts and cumulative environmental impacts with concurrent project. · Better control of quality and workmanship for works in fabrication yard. · Proven record for the construction of marine viaducts with no land access in the Tseung Lam Highway.
|
· Require another trade of skilled workers and additional construction equipment for erecting precast segments. |
Cast-situ |
· Conventional construction method and require relatively less special skilled labour when comparing with other construction methods. |
· Longer construction time to carry out the bridge deck construction, i.e. span by span. · Required concrete mixing truck and concrete pump truck travelling in site area, thus induce potential air and noise impact. · Require substantial temporary steel platform/ falsework for construction especially the bridge is to be constructed over water. · Use of timber formwork thus more C&D waste/ materials will be generated. |
2.15.1.1 Table 2.20 presents the key environmental problems that have been avoided and any sensitive areas protected by environmentally friendly options in the development of the Draft RODP.
Table 2.20 Summary of Key Environmental Problems Avoided and Environmental Options
Design Approaches |
Environmental Problems Avoided and Environmental Options |
Avoidance of encroachment into CWBCP |
· The proposed natural terrain mitigation works (i.e. flexible barrier) has been re-located to be within the EPP site to avoid any works encroaching into CWBCP |
Preservation of natural shoreline |
· Reclamation extent of TKO 132 has been optimised to minimise the impact to the natural shoreline. Approximately 1km out of 1.6km of natural shoreline can be maintained |
Minimise direct impact to hard and black corals colonies and coral recipient site at western Junk Bay |
· Reclamation extent of TKO 132 has been optimised to avoid encroachment into the coral recipient sites at Junk Bay and minimise direct impact to hard and black corals colonies and coral recipient site at western Junk Bay |
Minimise direct impact to subtidal habitats and associated coral colonies in Western Junk Bay |
· Reclamation extent of TKO 132 has been optimised to minimise direct impact to subtidal habitats and associated coral colonies in Western Junk Bay |
Avoidance of encroachment on the existing government land licences at On Luen Village |
· Site formation at TKO 132 has been designed to avoid encroachment into the existing government land licences at On Luen Village |
Avoidance of direct impacts on natural water course |
· Pier locations of the marine viaduct has been designed to avoid direct impact on the natural watercourse near TKO 132 |
Minimise impact to the terrestrial ecology at Devil’s Peak |
· The natural terrain mitigation works have been optimised to ensure that the works area is limited to the toe of Devil’s Peak as far as possible in order to minimise the terrestrial ecology impact |
Minimise potential odour impact |
· The EPP emission points are designed to be located away from the sensitive receivers to minimise the potential odour impact |
Providing sustainable transport infrastructure to promote low-carbon living |
· Pedestrian-friendly environment and robust cycling network are proposed to promote walkability and cycling for low-carbon living |
· With appropriate planning on building configuration and setback from roads, potential road traffic noise impact on future noise sensitive uses within the development would be minimised. The potential noise impacts could be alleviated by the use of low-noise road surfacing, acoustic windows and / enhanced acoustic balcony, blank wall, fixed window, architectural fin, etc., thereby avoiding the use of roadside noise barriers or enclosures. Without roadside noise barriers or enclosures, the associated visual impacts and bird collisions would also be avoided / minimised. |
|
Create buffer distance between TKOIP and sensitive receivers/uses in TKO 137 |
· To minimise the impact from the TKOIP to the sensitive receivers/uses in TKO 137, G/IC and open spaces have been positioned between TKOIP and residential sites to sufficient buffer distance |
Adoption of Non-dredged Reclamation |
· Non-dredged reclamation with in-situ ground treatment methods (including marine-based deep cement mixing and land-based jet grouting) would be adopted to minimise the associated water quality impacts from dredging and additional filling, the waste management implications from sediment disposal and the secondary environmental impacts from induced marine traffic. |
Adoption of Environmentally Friendly Construction Method |
· The precast method would be adopted for the construction of the proposed marine viaduct to reduce the overall C&D materials to be generated on-site, shorten construction duration and minimise on-site environmental impacts (e.g. dust and noise) on nearby sensitive receivers. |
2.16.1.1 To optimise the provision schedule of the proposed public facilities and supply of housing units, phased population intake would be necessary. Site formation, reclamation and key engineering infrastructure works will be implemented in stages while associated drainage, sewerage, water supply and utilities will process alongside road construction in respective development stages.
2.16.1.2 The Project would be commissioned in phases with the targeted first population intake in Year 2030. The tentative preliminary construction schedule under various phases is summarised in Table 2.21 with reference to Figure 2.8 for reclamation works and Appendix 2.1 for the tentative site development works. The tentative construction programme and site phasing plan are presented in Appendix 2.2 and Appendix 2.3, respectively.
Table 2.21 Preliminary Construction and Population Intake Schedule
Development Stage |
Site |
Major construction activities and Areas |
Rationale of Phasing |
Earliest Date for Commencement of infrastructure Works |
Earliest Date for Availability of Land for Building Works |
Anticipated First Occupation/ Population Intake Date |
Initial Phase (End 2025 – End 2030)
|
TKO 137 |
Phase 1 Reclamation for TKO 137: reclamation, seawall works, site formation, box culvert(s) and seawall outfall(s) for the middle portion along the southwest shoreline and the existing barging basin at the north of the Project area of TKO 137 (1A, 1B and 1C referred to Figure 2.8)
Site development works mainly at north of the TKO 137, targeting to achieve the first population intake in 2030 (initial phase of development of TKO 137 referred to Appendix 2.1)
|
- Land resumption and availability for reclamation and site formation
- To commence infrastructure works for targeted population intake |
End 2025 |
End 2025 |
End 2030 |
TKO 132 |
Reclamation, seawall works, box culvert(s), seawall outfall(s), slope-cutting, site formation, marine viaducts, site development works to support TKO 132 (Preliminary Development of TKO 132 referred to Appendix 2.1) |
- The land to be created for relocation of Public Facilities to allow the site at TKO 137 to be vacated for residential development and accommodating other Public Facilities
- To commence infrastructure works for accommodating the location-specific Public Facilities |
End 2025 |
End 2028 |
- |
|
|
|
Marine viaducts and infrastructure works (including sewage pumping station) to support TKO 132 |
- To provide infrastructure to Public Facilities at TKO 132 |
End 2025 |
End 2030 |
End 2030 |
Main Phase (Feb 2027 – End 2035) |
TKO 137 |
Phase 2 Reclamation for TKO 137: reclamation, seawall works, site formation, box culvert(s) and seawall outfall(s) for the southern portion along the southwest shoreline of TKO 137 (2A and 2B referred to Figure 2.8)
Site development works mainly at east and north of the project area of TKO 137 (excluding the HyD/RDO reserved area) to support the targeted population intake (main phase of development of TKO 137 referred to Appendix 2.1)
|
- Land resumption and availability for reclamation and site formation works for targeted population intake
- Interim infrastructure for meeting 1st population intake
- Areas with road connection from existing road networks
- Key infrastructures
- To commence infrastructure works for targeted population intake
|
End 2028 |
End 2028 |
End 2033 |
TKO 132 |
Construction of Public Facilities (EFs, CWHF, RTS, PFTF and CBP) – by others |
- Upon completion of reclamation and site formation works, respective land will be handed over to the Public Facilities’ operators to construct EFs, CWHF, RTS, PFTF and CBP |
End 2028 (Building Works) |
End 2028 (Building Works) |
2030 (PFTF and CBP) 2031 (CWHF) 2032 (RTS) 2035 (EFs)
|
|
Remaining Phase (End 2033 – End 2041)
|
TKO 137 |
Site development works mainly for the HyD/RDO reserved area and the west of the Project area of TKO 137, and the remaining site development and interfacing works for TKO 137 to support the targeted population intake (remaining phase of development of TKO 137 referred to Appendix 2.1) |
- Land availability after releasing from HyD/RDO for commencing infrastructure works for targeted population intake
- Remaining works to suit the programme of other interfacing works |
End 2036 |
End 2036 |
End 2038 |
Remarks:
1. Phasing plan is subject to further liaison with LandsD and further review at Design & Construction stage.
2. Site formation works will have interface with the construction works of TKLSE (in services by 2036 subject to RDO’s later formulation of the railway construction works).
3. The lands under each phase will be available for building and infrastructure works with taking over of the sites in phases from LandsD.
2.16.2 Initial Phase Development
2.16.4 Remaining Phase Development
2.16.4.1 Remaining Phase Development is the last phase of the development for TKO 137, mainly including development works at the land area that was occupied by HyD/RDO for the TKLSE construction at initial phase (subject to HyD/RDO’s later formulation of the railway construction works), as well as any remaining infrastructure and interfacing works from the last development phase. The development works in this phase is to support the targeted population intake in Year 2038 and the targeted mass population intake in Year 2041 respectively at TKO 137.
2.16.4.2 The major development works in this development phase will include:
· Site development works for two ‘Private Housing” (“R1”) sites and two ‘Private Housing” (“R2”) sites at west of the Project area.
· Associated local roads, interchange/junction, pedestrian connectivity, drainage, waterworks, sewerage, UU, E&M, paving, road marking and street furniture.
· Interfacing works from the last development phase.
2.17.1.1 The EIA has assessed the potential cumulative impacts of the Project and associated works that may arise through interaction or in combination with other existing, committed and planned developments in the vicinity of the Project and associated works. In addition, interactions between different impacts (i.e. synergistic impacts) for key sensitive receptors have also been considered.
2.17.1.2 The following projects that are considered as concurrent project.
1. Tseung Kwan O Desalination Plant;
2. Large Scale Solar Farm at South East New Territories Landfill;
3. Existing SENTX;
4. SENT Landfill;
5. Construction of Relocated Berthing Facilities and Associated Structures within Tseung Kwan O Area 137 Fill Bank;
6. Cavern Development in Area around Tseung Kwan O;
7. Proposed Tseung Kwan O Line Southern Extension;
8. Existing explosives off-loading pier at Fat Tong O;
9. Fill bank at Tseung Kwan O Area 137 - Handling of Surplus Public Fill;
10. Tseung Kwan O – Lam Tin Tunnel and its associated works;
11. Cross Bay Link, Tseung Kwan O;
12. Water Sports Centre in Area 77, Tseung Kwan O;
13. Power cables connecting to the Electrical Facilities at TKO 132 and Electrical Substations at TKO 137;
14. Upgrading works for existing explosives off-loading pier at Fat Tong O;
15. Tiu Keng Leng Park;
16. Potential Hiking Trail at TKO 137; and
17. Potential Hiking Trail at TKO 132.
2.17.1.3 Several major projects are identified in 500 m assessment area as having the potential to run concurrently with the proposed Project and hence have the potential to result in cumulative impacts on the environment. The planned construction period and a brief description of the projects identified has been summarised in Table 2.22 Cumulative impacts from the concurrent projects have been assessed in the individual sections of this EIA Report and summarised in Table 2.22 and the locations of the concurrent projects are shown in Figure 2.13.
2.17.1.4 Cumulative impacts from projects that are outside of the 500 m assessment area such as housing development in TKO, are also not anticipated. Cumulative impact from TKO-YTT is not anticipated. Therefore, these projects are excluded in Table 2.22 and Figure 2.13.
Table 2.22 Summary of Potential Cumulative Impacts
Ref. no. |
Concurrent Project |
Project Proponent |
Construction Programme |
Brief Description |
Potential Cumulative Impact from the Concurrent projects |
||
Start |
Complete |
Construction |
Operation |
||||
1. |
Water Supplies Department |
The design and build period commenced at the end of December 2019 and started supplying portable water to public from 22 December 2023 |
- Construction of First Stage of Desalination Plant at Tseung Kwan O |
-
|
· Air Quality · Noise · Water Quality · Landscape and Visual · Hazard to Life
|
||
2. |
Second Stage of Desalination Plant at Tseung Kwan O – Investigation, Design and Construction under WSD Contract CE 92/2022 (WS) |
Water Supplies Department |
The Investigation, Design and Construction Consultancy commenced in Early June 2023 and the estimated works completion date is in January 2031. The construction works have not yet commenced. |
- Construction of Second Stage of Desalination Plant at Tseung Kwan O |
· Air Quality · Noise · Ecology
|
· Air Quality · Noise · Water Quality · Landscape and Visual · Hazard to Life · Ecology |
|
3. |
Implementation of a Large Scale Solar Farm at South East New Territories Landfill for Supplying Renewable Energy to the Tseung Kwan O Desalination Plant - Investigation, Design and Construction under WSD Agreement No. CE 39/2022 (EM) |
Water Supplies Department |
The Investigation, Design and Construction Consultancy commenced at the end of February 2023 and the estimated completion date is in October 2028. |
- The project comprises constructing a solar farm in South East New Territories Landfill for producing renewable energy with proposed approx. capacity of 10MW.
- The power generated from the solar farm would be used by the desalination plant exclusively.
|
· Ecology · Landscape and Visual |
· Ecology · Landscape and Visual |
|
4. |
Existing SENTX |
Environmental Protection Department |
Construction works of SENTX commenced in end 2018 and all works (incl. landfill restoration) to be completed prior to the population intake at TKO 137. |
- SENTX occupies 13 ha of the Tseung Kwan O Area 137 and 30 ha of the original SENT Landfill area to the north.
- It has a capacity of about 6.5 Mm3 and receives only construction waste for disposal.
- Landfill restoration works will be carried out in phases with the last phase to be completed prior to the population intake at TKO 137. |
· Air Quality · Noise · Ecology · Landscape and Visual · Landfill Gas Hazard
|
· Air Quality · Noise · Water Quality · Ecology · Landscape and Visual · Landfill Gas Hazard
|
|
5. |
SENT Landfill |
Environmental Protection Department |
SENT Landfill commenced operation in September 1994. It was exhausted and closed on 21 November 2021. At present, restoration works for the closed SENT Landfill are on-going for completion prior to the population intake at TKO 137. |
- SENT Landfill commenced operation in September 1994 and received domestic, commercial and industrial, construction and demolition, chemical and clinic wastes, dewater sewage sludge and stabilised incineration residues.
- Since January 2016, SENT landfill has been designated to receive only construction waste for disposal.
- SENT landfill was exhausted and closed on 21 November 2021. At present, restoration works for the closed SENT Landfill are on-going for completion prior to the population intake at TKO 137. |
· Landfill Gas Hazard
|
· Landfill Gas Hazard
|
|
6. |
Construction of Relocated Berthing Facilities and Associated Structures within Tseung Kwan O Area 137 Fill Bank |
Civil Engineering and Development Department |
The construction will commence in Q4 2025 and target to complete in Q4 2026. |
- The primary objective of the works is to facilitate the development of TKO 137, and the works involves construction of berthing facilities and associated structures within TKO 137 Fill Bank as a replacement for the berthing facilities at the barging basin in TKO 137.
- The concerned berthing facilities (with berthing length of around 500m) will be located near the southern end of TKO 137 Fill Bank.
- The berthing facilities will be in use from Q4 2026 to Q4 2031, subject to the availability of the re-provisioned PFTF in TKO 132. |
· Air Quality · Noise · Water Quality · Ecology · Landscape and Visual |
· Landscape and Visual |
|
7. |
Cavern Development in Area around Tseung Kwan O |
Civil Engineering and Development Department |
The project is under planning and expected to complete in 2032 and beyond. |
- The Government has been adopting a multi-pronged approach to enhance land supply, including cavern development. The project is under planning and subject to review. |
· Air Quality · Noise · Ecology · Landscape and Visual |
· Noise · Ecology · Landscape and Visual
|
|
8. |
Proposed Tseung Kwan O Line Southern Extension |
Transport and Logistics Bureau and Highways Department |
The project is under planning. Construction will commence in 2028 and expected to complete in 2038. |
- The TKO Line Southern Extension, aims to support the development of TKO 137 and provide a convenient and efficient mass transit system to the 135,000 new population. The Government recommends using the heavy rail system of the existing TKO Line as the basis and extending the railway from LOHAS Park Station southward to the underground station at TKO 137. |
· Air Quality[7] · Noise7 · Ecology7 · Fisheries7 · Water Quality7
|
· Noise · Water Quality7 · Ecology7 · Fisheries7
|
|
9. |
Existing explosives off-loading pier at Fat Tong O
|
Civil Engineering and Development Department |
The project is currently in operation and the tentatively end date of operation is end of 2029. |
- The Mines Division of CEDD operates a pier at TKO 137 (TGLA No. SK 567) for off-loading explosives from vessels.
- This pier is used for the explosives delivery operation from the Government Explosives Depot at Kau Shat Wan, Lantau, to projects throughout the HKSAR. |
· Hazard to Life · Landscape and Visual
|
- |
|
10. |
Fill bank at Tseung Kwan O Area 137 - Handling of Surplus Public Fill |
Civil Engineering and Development Department |
The fill bank has been in operation since 2002 through a series of construction contracts. The current contract is Contract No. CV/2023/10 - Handling of Surplus Public Fill (2024 - 2027) commenced in August 2024 for about 36 months. |
- The fill bank at TKO 137 (TKOFB) is for handling of public fill (including reception, temporary storage, etc.) generated from the local construction projects for subsequent beneficial reuse (including reclamation projects, delivery to the Mainland, etc.).
- To facilitate the development of Tseung Kwan O Area 137, there are plans to surrender the land parcels of TKOFB progressively in phases starting from end 2025. Subject to further discussions and deliberations, the facilities in the TKOFB may have to be relocated internally, such as combined reception and exit offices, berthing facilities, etc.
- The overall surrendering programme will also depend on the absorption programme of local reclamation projects under planning and the availability of facilities reprovisioning in TKO 132, such as Public Fill Transfer Facility. |
· Air Quality · Landscape and Visual
|
- |
|
11. |
Tseung Kwan O – Lam Tin Tunnel and its associated works |
Civil Engineering and Development Department |
Construction commenced in July 2016 and was substantially completed for road opening in December 2022. |
- The project is for the construction of a dual two-lane highway approximately 3.8 km long connecting Tseung Kwan O (TKO) at Po Shun Road in the east with proposed Trunk Road T2 in Kai Tak Development in the west.
- About 2.2 km of the highway is in the form of tunnel. TKO-LTT will meet the TKO external traffic demand as a result of continual development of TKO. TKO-LTT, together with the proposed Trunk Road T2 and Central Kowloon Route, will form the Route 6 which will provide an east-west express link between West Kowloon and TKO areas.
|
The project has been completed, therefore no potential cumulative impact under construction stage |
Air Quality |
|
12. |
Cross Bay Link, Tseung Kwan O |
Civil Engineering and Development Department |
Construction commenced in July 2018 and completed in December 2022. |
- Cross Bay Link (CBL) connects TKO–LTT to Wan Po Road in Area 86 of Tseung Kwan O (TKO).
- It provides an alternative access route to the south-eastern part of TKO, so as to cope with the anticipated traffic demand in TKO. With the completion of CBL, traffic from the south-eastern part of TKO can commute to and from the western part of TKO via CBL, as well as commute to and from Kowloon East via TKO–LTT, without travelling through Wan Po Road and TKO town centre.
- Hence, the traffic load to these roads during peak hours is relieved, and thereby minimising the traffic and environmental impacts on residents in the vicinity.
- The project includes an about 1.8 kilometres long dual -2-lane carriageway with cycle track and footpath across Junk Bay mainly on viaduct. The works include construction of connecting roads and implementation of associated traffic control and surveillance system, drainage, waterworks, marine, landscaping, electrical and mechanical and ancillary works. |
The project has been completed, therefore no potential cumulative impact under construction stage |
Air Quality |
|
13. |
Water Sports Centre in Area 77, Tseung Kwan O |
Leisure and Cultural Services Department |
To be confirmed (Note: As this project is at early planning stage, there is no concrete implementation schedule/construction programme.) |
- A Water Sports Centre in Area 77, Tseung Kwan O. Possible marine works include coastal facilities (including steps or levels on the seawall to serve as spectator stand for competitions) and construction of a pier with landing steps and mooring points for rescue boats. |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under operation stage cannot be assessed under this EIA and will be addressed in separate studies |
|
14. |
Power cables connecting to the Electrical Facilities at TKO 132 and Electrical Substations at TKO 137 |
To be determined |
The project(s) is under planning. Construction commencement is subject to separate study. Completion date is expected to be tally with the EFs and ESS. |
- Laying of power cables is expected to connect to the proposed EFs at TKO 132 and the proposed ESSs at TKO 137. The actual alignment and design are under planning. |
Design information on the cable alignment are unavailable, therefore, impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
· Electric and Magnetic Field
|
|
15. |
Upgrading works for existing explosives off-loading pier at Fat Tong O |
Civil Engineering and Development Department |
To be confirmed (Note: As this project is at feasibility stage, there is no concrete implementation schedule/construction programme.) |
- Upgrade of existing explosives off-loading pier for public use |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under operation stage cannot be assessed under this EIA and will be addressed in separate studies |
|
16. |
Tiu Keng Leng Park |
Leisure and Cultural Services Department |
To be confirmed (Note: As this project is at feasibility stage, there is no concrete implementation schedule/construction programme.) |
- Under the planning of the Tseung Kwan O Outline Zoning Plan, there is a district open space in Tseung Kwan O Area 72 for the proposed provision of the Tiu Keng Leng Park |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under operation stage cannot be assessed under this EIA and will be addressed in separate studies |
|
17. |
Potential Hiking Trail at TKO 137 |
Civil Engineering and Development Department |
To be confirmed (Note: As this project is at feasibility stage, there is no concrete implementation schedule/construction programme.) |
- Construction of hiking trail connecting existing hiking trails to TKO 137 |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under operation stage cannot be assessed under this EIA and will be addressed in separate studies |
|
18. |
Potential Hiking Trail at TKO 132 |
Civil Engineering and Development Department |
To be confirmed (Note: As this project is at feasibility stage, there is no concrete implementation schedule/construction programme.) |
- Construction of hiking trail/ boardwalk connecting existing hiking trails to TKO 132 |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under construction stage cannot be assessed under this EIA and will be addressed in separate studies |
Design information is unavailable at the time of preparation of this EIA. Therefore, potential impact under operation stage cannot be assessed under this EIA and will be addressed in separate studies |
|
Note: “—“ = Potential cumulative impact not anticipated.
[1] The CWHF to be provided in TKO 132 may also incorporate the function of the temporary construction waste sorting facility (temp. CWSF) currently located in TKO 137. Unlike the existing open air operation at the temp. CWSF, such future operation, if any, will be carried out in enclosed environment.
[2] The MRCP was proposed during the PODP stage and has been excluded from the RODP.
[3] The EFs are a strategic infrastructure that will account for about 30% of Hong Kong total fuel mix
for electricity generation for enhancing Hong Kong’s capability to import zero-carbon energy through
regional cooperation and meeting the decarbonisation target of reducing Hong Kong’s carbon emissions
by 50% before 2035 as compared to the 2005 level, with a view to achieving carbon neutrality before
2050.
[4] Location of JBDGA is extracted from Marine Chart by Marine Department’s “eSeaGo”
[5] The proposed development parameter for public and private residential is an assumption adopted for carrying out technical assessments which may be subject to change at implementation stage.
[6] Reclamation area is based on developable area.
[7] There is no confirmed details on the design/alignment and construction method of the TKLSE during this EIA study. Therefore, cumulative impact arising from TKLSE was evaluated based on the best available information (i.e. land area reserved for underground railway development). Nevertheless, since TKLSE is a designated project under Schedule 2 of the EIAO, the potential environmental impacts of TKLSE (including cumulative impact of concurrent project) will be assessed and addressed under a separate EIA study.