4.
Noise Impact
4.1
Legislation, Standards and Guidelines
4.1.1
General
4.1.1.1
The relevant legislation and
associated guidance applicable to present the study for the assessment of noise
impacts include:
·
Noise
Control Ordinance (NCO) (Cap.400);
·
Technical
Memorandum (TM) on Noise from Construction Work other than Percussive Piling
(GW–TM);
·
TM on Noise
from Percussive Piling (PP–TM);
·
TM on Noise
from Construction Work in Designated Areas (DA–TM);
·
TM for the
Assessment of Noise from Places other than Domestic Premises, Public Places or
Construction Sites (IND–TM); and
·
Environmental
Impact Assessment Ordinance (EIAO) (Cap. 499) and EIAO–TM.
4.1.2
Construction Noise
Airborne
Construction Noise During Non-restricted Hours
4.1.2.1
The NCO provides the statutory
framework for noise control in Hong Kong. Assessment procedures and standards
are set out in the respective TM promulgated under NCO.
4.1.2.2
For general construction works
other than percussive piling works using Powered Mechanical Equipment (PME),
there is no statutory limit on construction noise during non-restricted hours (i.e 07:00 – 19:00 on any day not being a Sunday or general
holiday), under the NCO and related TMs. There is statutory control on
construction noise between the hours 1900 and 0700 from Monday to Saturday and
at any time on general holidays (including Sundays), i.e.
restricted hours, under the NCO. To ensure a better environment, the EIAO–TM
promulgated under the EIAO has imposed more stringent criteria. Daytime general
construction works (excluding percussive piling) between the hours 0700 and
1900 on weekdays, i.e. non–restricted hours, is
controlled under the EIAO. The EIAO–TM stipulates criteria of 65 – 75dB(A) for
daytime construction activities, as shown in Table 4.1.
Table 4.1 Noise standards for daytime
construction activities
Uses
|
Noise
Standards[1], [2], Leq(30min) dB(A)
|
0700
– 1900 hours on any day not being a Sunday or general holiday
|
· All domestic premises;
· Temporary housing accommodation;
· Hostels
· Convalescent homes; and
· Homes
for the aged
|
75
|
· Places of public worship;
· Courts of law; and
· Hospitals
and medical clinics
|
70
|
Educational institutions
(including kindergartens and nurseries)
|
70
65 (During examination)
|
Notes:
[1] The
above standards apply to uses that rely on opened windows for ventilation and
are assessed at 1m from the external facade.
[2] A Construction Noise Permit (CNP)
shall be required for the carrying out of the construction work during
restricted hours under the Noise Control Ordinance (NCO). In case the applicant
would like to evaluate whether construction works in restricted hours as
defined under the NCO is feasible or not in the context of programming
construction works, reference should be made to relevant technical memoranda
issued under the NCO.
4.1.2.3
In addition, reference has been
made to EIAO Guidance Note No. 09/2010 on “Preparation of Construction Noise
Impact Assessment under the Environmental Impact Assessment Ordinance”.
Airborne
Construction Noise during Restricted Hours
4.1.2.4
The NCO also provides statutory
control on general construction works during restricted hours (i.e. 1900 to 0700 hours (of the next day) from Monday to
Saturday and at any time on Sundays or public holidays). The use of PME for
construction works during restricted hours would require a Construction Noise
Permit (CNP). The GW–TM details the procedures adopted by the Noise Control
Authority for assessing such application. The granting of a CNP is subject to
conditions stated in the CNP and it may be revoked at any time for failure to
comply with the permit conditions.
4.1.2.5
In addition to the general
controls on the use of PME during restricted hours, the use of Specified
Powered Mechanical Equipment (SPME) and the undertaking of Prescribed Construction
Work (PCW) during the restricted hours in a designated area are also controlled
by the DA–TM. Construction plant or equipment classified as SPME under the
DA–TM includes hand–held breakers, bulldozers, concrete lorry mixers, dump
trucks and vibratory pokers. The PCW includes the erection or dismantling of
formwork or scaffolding, hammering, loading, unloading
or handling of rubble, wooden boards, steel bars, wood or scaffolding material.
4.1.2.6
The DA–TM details the
procedures that are adopted by the Noise Control Authority for assessing the
use of SPME during restricted hours and for determining whether a CNP would be
issued.
4.1.2.7
Noise
from construction activities during restricted hours at affected Noise
Sensitive Receivers (NSRs) are controlled under the TMs and shall not generally
exceed the specified Acceptable Noise Levels (ANLs). These ANLs are obtained
with corrections for the duration of the CNP and multiple permit situations, if
applicable, to the Basic Noise Levels (BNLs). The BNLs are stipulated in accordance
with the Area Sensitivity Ratings established for the NSRs. The BNLs for
construction works in Designated Areas are more stringent than those given in
the GW–TM and summarised in Table 4.2.
Table 4.2 BNLs for construction during restricted hours
Time Period
|
BNLs for Area Sensitive Ratings
[1], dB(A)
|
A
|
B
|
C
|
All weekdays during the evening
(1900 to 2300 hours), and general holidays (including Sundays) during the day
and evening (0700 to 2300 hours)
|
60 (45)
|
65 (50)
|
70 (55)
|
All days during the night–time (2300 to 0700 hours)
|
45 (30)
|
50 (35)
|
55 (40)
|
Note:
[1] Figures in brackets are BNLs for
SPME construction work in designated areas.
4.1.2.8
As
defined in the Noise Control (Construction Work Designated Areas) Notice Plan
No. EPD/AN/NT–01 & EPD/AN/NT–03, Lam Tei areas such as Tsoi Yuen Tsuen, Fuk
Hang Tsuen; Tuen Mun area such as Kam Fai Garden, Sam Shing Hui, Siu Shan
Court, Wu King Estate, etc; are within the Designated Area (DA).
4.1.2.9
Despite
any description made in this report, there is no guarantee that a CNP will be
issued for the project construction. The Noise Control Authority will consider
a well–justified CNP application, once filed, for construction works within
restricted hours as guided by the relevant TMs issued under the NCO. The Noise
Control Authority will take into account contemporary
conditions / situations of adjoining land uses and any previous complaints
against construction activities at the site before making a decision in
granting a CNP. Nothing in the report shall bind the Noise Control Authority in
making a decision. If a CNP is to be issued, the Noise
Control Authority shall include in it any conditions as
appropriate. Failure
to comply with any such conditions will lead to cancellation of the CNP and
prosecution under the NCO.
Blasting
4.1.2.10
The
administrative and procedural control of all blasting operations in Hong Kong
is vested in the Mines Division of the Civil Engineering and Development
Department (CEDD). The Mining Ordinance (Cap. 285) / Dangerous Goods Ordinance
(Cap. 295) also stipulates that no person shall carry out blasting unless he
possesses a valid mine blasting certificate to be issued by the Mines Division
of CEDD. The Superintendent of Mines will review the application on a
case–by–case basis before issuing the Mine Blasting Certificate. Although there
is no statutory noise level for blasting, the noise associated with the removal
of debris and rocks are controlled under the EIAO–TM.
Groundborne Construction Noise during
Non-restricted Hours
4.1.2.11
Noise
arising from general construction works that may generate groundborne
noise during normal hours is governed by the EIAO–TM under the EIAO and summarized in Table 4.1. The IND–TM under the NCO stipulates that noise transmitted
primarily through the structural elements of building, or buildings, shall be
10 dB(A) less than the relevant ANLs.
4.1.2.12
Based
on the same principle for the groundborne noise
criteria (i.e. ANL–10 dB(A) under the IND–TM), the groundborne construction noise levels inside domestic
premises and schools shall be limited to 65 dB(A) and 60 dB(A) respectively
when compared to the EIAO–TM. A summary of groundborne
construction noise criteria during normal working days is given in Table 4.3.
Table 4.3 Groundborne construction noise criteria
Uses
|
Noise
Criteria, dB(A)
|
0700
to 1900 hours
on
any day not being a Sunday or general holiday
|
· All
domestic premises;
· Temporary
housing accommodation;
· Hostels;
· Convalescent
homes; and
· Homes
for the aged
|
65
|
· Places
of public worship;
·
Courts
of law; and
·
Hospitals
and medical clinics
|
60
|
Educational institutions (including
kindergartens and nurseries)
|
60
55 (During examination)
|
Groundborne Construction Noise
During Restricted Hours
4.1.2.13
Similar
to airborne construction noise during restricted hours, NCO also provides
statutory control of construction work for goundborne
noise during restricted hours. As discussed in the above section, same
principle for groundborne noise criteria (i.e. ANL–10dB(A) under the IND–TM) shall be adopted.
Therefore, table below summarizes the groundborne
construction noise criteria during restricted hours.
Table 4.4 Construction groundborne noise criteria during
restricted hours
Time Period
|
Noise Criteria, dB(A) for Area
Sensitivity Ratings, dB(A)
|
A
|
B
|
C
|
All weekdays during the evening
(1900 to 2300 hours), and general holidays (including Sundays) during the day
and evening (0700 to 2300 hours)
|
50
|
55
|
60
|
All days during the night–time (2300 to 0700 hours)
|
35
|
40
|
45
|
4.1.3
Operational Noise
4.1.3.1
The
EIAO–TM (Annex 5 of TM) has stipulated the noise standards for various noise
sources as shown in the following Table 4.5. It should, however, be noted
that the following noise criteria are only applicable to uses that rely on
opened windows for ventilation.
Table 4.5 Noise standards for
operational phase
Common
Uses
|
Noise
Standards [1]
|
Road
Traffic Noise L10 (1hour) dB(A)
|
Fixed
Noise Sources
|
· All domestic premises;
· Temporary housing accommodation;
· Hostels;
· Convalescent homes; and
· Homes for the aged
|
70
|
(a) 5dB(A) below the appropriate ANLs shown in the
Technical Memorandum for the Assessment of Noise from Places Other than
Domestic Premises, Public Places or Construction Sites, or
(b) the prevailing background noise levels (For
quiet areas with noise level 5 dB(A) below the ANL)
|
· Educational institutions
(including kindergartens and nurseries)
· Places of public worship;
· Courts of law
|
65
|
Hospitals
and medical clinics
|
55
|
Notes:
[1] The above standards, or equivalent,
apply to uses which rely on opened windows for ventilation and are assessed at
1m from the external facade.
Road Traffic Noise
4.1.3.2
The
criteria for assessing road traffic noise are given in the EIAO–TM and
tabulated in Table 4.5. For domestic premises, temporary housing accommodation, hostels, convalescent
homes and homes for the aged, the criterion is 70dB(A). For educational
institutes, places of worship and courts of law, the
criterion is 65dB(A). For hospitals and medical clinics, a more stringent criterion of 55dB(A) is
stipulated. It should be noted that all these criteria only apply to NSRs that
rely on opened windows for ventilation. In addition, reference has been made on
EIAO Guidance Note No. 12/2010 on “Road Traffic Noise Impact Assessment under
the Environmental Impact Assessment Ordinance”.
Fixed Noise Sources
4.1.3.3
Operational
noise from fixed noise sources is controlled under the IND–TM. To plan for a
better environment, the EIAO–TM has specified the following requirements for
the planned fixed noise sources, whichever is more stringent.
·
5dB(A) below
the appropriate ANLs in the IND–TM; or
·
the
prevailing background noise levels.
4.1.3.4
The
ANLs for different Area Sensitivity Ratings during different periods are
summarised in the Table 4.6.
Table 4.6 ANLs for fixed noise sources
Time
Period
|
ANL,
dB(A)
|
Area
Sensitivity Rating A
|
Area
Sensitivity Rating B
|
Area
Sensitivity Rating C
|
Day (0700 to 1900 hours)
|
60
|
65
|
70
|
Evening (1900 to 2300 hours)
|
60
|
65
|
70
|
Night (2300 to 0700 hours)
|
50
|
55
|
60
|
4.1.3.5
For
assessing fixed noise sources, the Area Sensitivity Ratings at the NSRs are
defined in accordance with the IND-TM.
4.2
Baseline Conditions
4.2.1
Description of Noise
Environment
4.2.1.1
The
Project is an approximately 10km connection roads with open roads, tunnel and viaducts to enhance the connectivity between Lam
Tei, Tuen Mun Area 40 and Pillar Point. The Project covers Lam Tei, Tai Lam
Country Park, Tuen Mun Area 40 and Pillar Point.
4.2.1.2
An
interchange and tunnel will be constructed at Lam Tei. The areas are mainly
villages and greenbelts. The noise climate at Lam Tei is dictated by the road
traffic noise from Yuen Long Highway (YLH), Kong Sham Western Highway (KSWH)
and noise from the existing Lam Tei Quarry.
4.2.1.3
A
tunnel will be constructed from Lam Tei to Tuen Mun Area 40, which will pass
through Tai Lam Country Park. The areas which tunnel passed through are mainly
country park, Government Institution or Community (GIC), residential area and greenbelt. The noise climate at these area is dictated by Tuen Mun Road (TMR) and local
roads.
4.2.1.4
An
open road section will be constructed at Tuen Mun Area 40. The areas are mainly
industrial area “I”, GIC, Other Specified Uses” (OU) and greenbelt. The noise
climate at Tuen Mun Area 40 is dictated by Lung Mun Road and the industrial
operations nearby.
4.2.2
Prevailing Noise Measurements
4.2.2.1
Prevailing
noise measurements have been conducted at Lam Tei and Tuen Mun in order to
capture the existing noise environment near ventilation shaft for tunnel. The
prevailing noise measurements were conducted in October 2022 and the measurements locations are shown in Figure 4.1.
L90(1hr) was used as the parameter to establish the corresponding
noise criteria according to HKPSG. A summary of the results is given in Table 4.7. These prevailing noise measurement results are adopted to identify
the fixed noise sources impact assessment criteria for conservative assessment.
Appendix 4.1 shows the detailed prevailing noise
measurement results.
Table 4.7 Prevailing Noise Level Measurements
Measurement
Points
|
Prevailing
Noise Levels (L90(1hr)) [1], dB(A)
|
ID
|
Location
|
Day
[2]
|
Evening
[2]
|
Night
[2]
|
PNM–LT
|
Fu Tei Ha Tsuen, Lam Tei
|
52 – 58
|
50 – 55
|
45 – 53
|
PNM–TMC
|
Wah Fat
Street, Tuen Mun Centre
|
53 –59
|
53 – 54
|
49 – 52
|
Notes:
[1] Noise level with 3dB(A) façade
correction
[2] Day: 0700 – 1900 hours, Evening:
1900 – 2300 hours, Night: 2300 – 0700 hours.
4.2.3
Noise Sensitive Receivers
Identification of Noise Sensitive Receivers
4.2.3.1
With
reference to Annex 13 of the EIAO–TM, Noise Sensitive Receivers (NSRs) include
residential uses (all domestic premises including temporary housing
accommodation), hostels, convalescent homes, homes for the aged,
educational institutional uses (including kindergarten and nurseries),
hospitals, medical clinics, places of public worship, court of law; and any
other premises or places that are considered by the Director to have similar
sensitivity to noise as the above.
4.2.3.2
Noise
sensitive areas are identified and hatched in Figure 4.2.
Representative NSRs within the assessment area have been then selected with the
most affected layer of NSRs selected as Noise Assessment Points (NAPs) for
assessment. These NSRs cover all existing sensitive developments, committed and
planned NSRs during construction and operational phases of the Project.
4.2.3.3
The
existing NSRs are identified by means of topographic maps, aerial photos, land
status plans and site inspections. Planned / committed NSRs within the
Assessment Area are identified by making reference to
relevant documents as listed:
·
Lam Tei and Yick Yuen Outline
Zoning Plan (OZP) (No. S/TM–LTYY/12 dated on 18 November 2022;
·
Tuen Mun OZP (No. S/TM/37 dated
12 May 2023);
·
So Kwun Wat OZP (No.
S/TM-SKW/14 dated 30 September 2022);
·
Planning Applications under
S.16 / S.12a Town Planning Ordinance;
·
Development Permission Area
Plans and Outline Development Plans by the Planning Department (PlanD);
·
Land Sale Programme published
by the Lands Department (LandsD); and
·
Other relevant published plans,
including plans, drawings and applications by the
correspondent project proponents.
4.2.3.4
Assessment
area and locations of NSRs are shown in Figure 4.2.
Identified representative NSRs within 300m assessment area for construction
noise, road traffic noise and fixed noise sources impact are listed in Table
4.8 below. Discussion on the assessment area for construction noise, road
traffic noise, and fixed noise sources impact is given in Section 4.3, Section 4.4
and Section 4.5
respectively. Photos of the representative existing NSRs are presented in Appendix 4.2.
4.2.3.5
For those
noise sensitive areas with future potential developments without any planning
information or committed site layout or intention at the time of this Study,
the requirements of noise mitigation measures for addressing the potential
noise issues raised by the Project should be considered under the land
administration regime and where appropriate, the planning approval mechanism.
Therefore, these areas are not reflected in Table 4.8.
Table 4.8 NSRs
within 300m Assessment Area for Construction Noise, Road Traffic Noise and
Fixed Noise Sources Impact
NSR ID
|
Description
|
Uses [1]
|
Number of Storeys
|
Construction Noise
|
Road Traffic Noise
|
Fixed Noise Sources
|
Existing
NSR
|
a.
Lam Tei
|
LT01
|
Area
at/near Lo Fu Hang
|
R
|
1–3
|
✓
|
✓
|
☓
|
LT02
|
Area at/near Fu Tei Ha Tsuen
|
R
|
1–3
|
✓
|
✓
|
✓
|
Temples at Fu Tei Ha Tsuen
|
W
|
1
|
✓
|
✓
|
✓
|
LT03
|
Village
Houses near Fuk Hang Tsuen Road
|
R
|
1–3
|
✓
|
☓
|
☓
|
b.
Tuen Mun West
|
TMS01
|
Harvest
Garden
|
R
|
17
|
✓
|
☓
|
✓
|
TMS02
|
Kam
Fai Garden
|
R
|
15
|
✓
|
☓
|
✓
|
TMS03
|
Saint
Temple at Sam Shing Hui
|
W
|
1
|
✓
|
☓
|
☓
|
TMS04
|
Hanford
Garden
|
R
|
26
– 27
|
✓
|
☓
|
☓
|
TMS05
|
Sam
Shing Estate
|
R
/ C / E [4]
|
16
– 27
|
✓
|
☓
|
☓
|
TMS06
|
Palm
Cove
|
R
|
13
– 14
|
✓
|
☓
|
☓
|
TMS07
|
Tsui
Ning Garden
|
R
|
35
|
✓
|
☓
|
☓
|
TMS08
|
Goodview
Garden
|
R
|
32
|
✓
|
☓
|
☓
|
TMS09
|
Tuen
Mun Wu Hong Clinic
|
C
|
3
|
✓
|
☓
|
☓
|
TMS10
|
Siu
Shan Court
|
R
|
20
|
✓
|
☓
|
☓
|
Buddhist
Leung Chik Wai College
|
E
|
6
|
✓
|
☓
|
☓
|
TMS11
|
Caritas
Li Ka Shing Care and Attention Home
|
C
|
4
|
✓
|
☓
|
☓
|
TMS12
|
Castle
Peak Sam Chau Ma Temple
|
W
|
1
|
✓
|
☓
|
☓
|
TMS13
|
Yan
Chai Hospital Ho Sik Nam Primary School
|
E
|
7
|
✓
|
☓
|
☓
|
c.
Siu Lam
|
SL01
|
Grandview
Terrace
|
R
|
3
|
✓
|
☓
|
☓
|
d.
Pillar Point
|
– [2]
|
Area near
Tuen Mun West No. 2 Fresh Water Service Reservoir
|
NA [3]
|
NA [3]
|
☓
|
☓
|
☓
|
Planned NSR
|
a. Lam Tei
|
– [6]
|
Lam Tei
North East Development (population intake is not yet
available)
|
[6]
|
[6]
|
☓
|
☓
|
☓
|
b. Tuen Mun West
|
P01
|
Social welfare
/ Education facilities for Public Housing Development at Wu Shan Road
|
C / E [5]
|
2 – 3
|
✓
|
☓
|
☓
|
Notes:
[1] R – Residential, E – Educational Institutions,
W – Place of Public Worship; C – Clinic.
[2] No sensitive use buildings that rely on opened
window/door for ventilation within 300m assessment area.
[3] NA – Not Applicable
[4] As there are social welfare facilities,
such as kindergarten, elderly centre, etc., located at the lower floors of the
Sam Shing Estate, the uses and the relevant noise criteria are subject to the
type of social welfare facilities.
[5] Social welfare facilities, such as
Residential Care Home for the Elderly (RCHE), Special Child Care Centre (SCCC)
etc., are provided in the non-domestic facilities of the Public Housing
Development at Wu Shan Road, the uses and the relevant noise criteria are
subject to the type of social welfare facilities.
[6] Lam Tei North East
Development is still under Early Feasibility Study Stage, details of the
Development are not yet available. As communicated with CEDD, assessments on
Planned Lam Tei North East Development will be covered
in its separate study.
4.3
Construction Noise Impact Assessment
4.3.1
Construction Noise Impact Assessment Methodology
4.3.1.1
As set out in
Appendix C Clause 2.1.2 of the EIA SB, a qualitative assessment is required to
identify the major noise sources / activities, and
propose corresponding quieter construction method and equipment adopted to
demonstrate that no adverse construction noise impact will be associated with
the Project. A summary of key steps for this qualitative construction noise
assessment that has been conducted is:
·
Determine 300m from the
boundary of the Project Site and associated works and temporary work site /
works area;
·
Identify NSRs and locate
representative assessment points that may be affected by the works;
·
Summarize the construction
method for the key construction work;
·
Collate the construction plant
inventory for the key construction work;
·
Evaluate the potential impact
on the NSRs qualitatively;
·
Examine and recommend all
practical mitigation measures such as alternative construction methodology,
quiet plant, silencer, enclosure, etc, to alleviate any potential noise impacts
as much as practicable; and
·
Consideration of noise
mitigation measures will follow Annex 13 of EIAO–TM and EIAO Guidance Note
“Preparation of Construction Noise Impact Assessment under the Environmental
Impact Assessment Ordinance” [GN 9/2010].
4.3.2
Identification of Construction Noise Impact
Identification of Assessment Area and Noise Sensitive Receiver
4.3.2.1
The
assessment area for construction noise includes an area within 300m from the gazette boundary of the Project and the
work site / work areas of the Project. Representative
NSRs and Noise Assessment Points (NAPs) that
would be affected by the construction activities have been identified and
presented in Table 4.8 and are
summarised in Table 4.9
below. Locations of Representative NSRs and NAPs
for construction noise impact assessment are shown in Figure 4.3.
Table 4.9 Identified NSRs and
NAPs within 300m of Construction Noise Assessment Area
NSR ID
|
Description
|
Uses [1]
|
Number of Storeys
|
NAP ID
|
Existing NSR
|
a.
Lam Tei
|
LT01
|
Area at/near Lo Fu Hang
|
R
|
1–3
|
LFH–01
|
LT02
|
Area at/near Fu Tei Ha
Tsuen
|
R
|
1–3
|
FTT–01 – FTT–03
|
Temples at Fu Tei Ha Tsuen
|
W
|
1
|
Te–06
|
LT03
|
Village Houses near Fuk Hang Tsuen Road
|
R
|
1–3
|
VH–13
|
b.
Tuen Mun West
|
TMS01
|
Harvest Garden
|
R
|
17
|
HAR–01
|
TMS02
|
Kam Fai Garden
|
R
|
15
|
KAM–01 – KAM–02
|
TMS03
|
Saint Temple at Sam Shing Hui
|
W
|
1
|
Te–101
|
TMS04
|
Hanford Garden
|
R
|
26 – 27
|
HAN–01 – HAN–02
|
TMS05
|
Sam Shing Estate
|
R / C / E [2]
|
16 – 27
|
SSE–01
|
TMS06
|
Palm Cove
|
R
|
13 – 14
|
PAC–01
|
TMS07
|
Tsui Ning Garden
|
R
|
35
|
TNG–01
|
TMS08
|
Goodview Garden
|
R
|
32
|
GOG–01
|
TMS09
|
Tuen Mun Wu Hong Clinic
|
C
|
3
|
cTMW–01
|
TMS10
|
Siu Shan Court
|
R
|
20
|
SSC–01
|
Buddhist Leung Chik Wai College
|
E
|
6
|
eLCW–01
|
TMS11
|
Caritas Li Ka Shing Care and Attention Home
|
C
|
4
|
CLKS-01
|
TMS12
|
Castle Peak Sam Chau Ma Temple
|
W
|
1
|
Te-201
|
TMS13
|
Yan Chai Hospital Ho Sik Nam Primary School
|
E
|
7
|
eYCH-01
|
c.
Siu Lam
|
SL01
|
Grandview Terrace
|
R
|
3
|
GRT–03
|
Planned NSR
|
b. Tuen
Mun West
|
P01
|
Social welfare / Education facilities
for Public Housing Development at Wu Shan Road
|
C / E [3]
|
2 – 3
|
PTMW-01
|
Note:
[1] R – Residential, E – Educational Institutions,
W – Place of Public Worship; C – Clinic.
[2] As there are social welfare
facilities, such as kindergarten, elderly centre, etc., located at the lower
floors of the Sam Shing Estate, the uses and the relevant noise criteria are
subject to the type of social welfare facilities.
[3] Social welfare facilities, such as
Residential Care Home for the Elderly (RCHE), Special Child Care Centre (SCCC)
etc., are provided in the non-domestic facilities of the Public Housing
Development at Wu Shan Road.
Inventory of Noise
Sources
4.3.2.2
Section 2 has described the key project elements and the associated
construction methodology. The potential sources of noise impact during the
construction of the Project would be the use of PME for various construction
activities. The key construction works would include the following:
·
Construction of road tunnels at
Lam Tei and Tuen Mun West;
·
Construction of open roads,
interchanges, flyovers and slip roads at Lam Tei and Tuen Mun West;
·
Site formation, construction
and decommission of explosive magazines;
·
Ancillary works including slope
works/formation, administration buildings, ventilation buildings, other tunnel operation area, adits and associated connection with existing roads, barging
facilities, reprovision of existing facilities, landscaping works, road
lighting, etc.; and
·
Ground Investigation (GI)
works.
4.3.2.3
The currently envisaged
construction programme would not require percussive piling works. Review on the
application of typical quieter construction methods have been conducted and
summarized in Appendix
4.3. With
due consideration of the EPD’s list of good practices and state-of-the-art
technologies with the industry, the followings are examples of quieter
construction methods / equipment that are found applicable to this Project.
·
Quieter type saw and hydraulic
crusher can be adopted for concrete removal for site clearance and road
realignment works;
·
Press-in piling method for the
building works; and
·
Prefabricated segments can be
widely used in viaduct construction to replace in-situ construction.
4.3.2.4
Using Tunnel Boring Machine
(TBM) has also been considered for construction of tunnels as a quieter
construction method.
4.3.2.5
According to the construction
methodology envisaged at this stage, the construction activities and its
associated tentative PMEs has been identified in the following Table 4.10.
The plant inventory adopted for the assessment have been confirmed by Project
Engineer. It is noted that the Contractor would consider the engineering data
available at that time and review and update this tentative construction plant
inventory.
Table 4.10 Tentative Plant inventory for key construction activities
Activities
|
Possible PMEs Required [1]
|
Site clearance and formation
|
· Backhoe
· Breaker
· Compactor
· Crane
· Drilling plant
|
· Dump truck
· Excavator
· Generator
· Hand–held breaker
|
· Hydraulic crusher
· Mechanical breaker
· Piling machine
· Saw
|
Construction of the temporary noise enclosure
|
· Crane
|
· Generator
|
· Hydraulic crusher
|
Construction of administration building / satellite
control building
|
· Air compressor
· Bar bender and cutter
· Concrete lorry mixer
· Concrete pump
· Crane
|
· Dump truck
· Excavator
· Generator
· Grout mixer
· Grout pump
|
· Lorry
· Piling machine
· Vibrating hammer
· Vibratory poker
· Water pump
|
Construction of ventilation buildings
|
· Air compressor
· Bar bender and cutter
· Concrete lorry mixer
· Concrete pump
· Crane
· Dump truck
|
· Excavator
· Generator
· Grout mixer
· Grout pump
· Lorry
|
· Piling machine
· Raised boring machine
· Vibrating hammer
· Vibratory poker
· Water pump
|
Construction of the Slurry Treatment Plant
|
· Crane
· Conveyor Belt
|
· Generator
· Lorry
|
· Hydraulic crusher
· Bar bender and cutter
|
Tunnel Construction by TBM
|
· Air compressor
· Batching plant
· Breaker
· Compactor
· Conveyor belt
· Dump truck
|
· Dumper
· Excavator
· Generator
· Grader
· Lorry
|
· Mobile crane
· TBM
· Ventilation fan
· Water pump
· Water treatment plant
|
Tunnel Construction by drill-and-blast /
drill-and-break
|
· Batching plant
· Breaker
· Concrete lorry mixer
· Concrete mixer
· Concrete pump
· Conveyor belt
· Crane
|
· Drill
· Drill Rig
· Dump truck
· Dumper
· Excavator
· Generator
· Grader
|
· Grinder
· Lorry
· Rock drill
· Ventilation fan
· Shotcrete machine
· Tunnelling Jumbo
|
Construction of portal structure
|
· Air compressor
· Asphalt paver
· Bar bender and cutter
· Compactor
· Concrete lorry mixer
|
· Concrete pump
· Crane
· Dump truck
· Excavator
|
· Generator
· Roller
· Vibratory poker
· Water Pump
|
Road works [2]
|
· Air compressor
· Asphalt paver
· Bar bender and cutter
· Compactor
· Concrete lorry mixer
· Concrete pump
|
· Crane
· Dump truck
· Excavator
· Generator
· Launching girder
· Paint liner marker
|
· Piling machine
· Roller
· Trailer truck
· Vibratory poker
· Water Pump
|
Construction work for explosive magazines
|
· Breaker
· Crane
· Drill
· Dump truck
· Dumper
|
· Excavator
· Generator
· Grader
· Grinder
· Lorry
|
· Road miller
· Road roller
· Roller
· Ventilation fan
|
Demolition work for explosive magazines
|
· Air compressor
· Bulldozer
· Breaker
· Concrete crusher
|
· Crane
· Dump truck
· Excavator
|
· Generator
· Lorry
· Saw
|
Construction of Barging facility
|
· Conveyor belt
· Derrick Barge
|
· Crane
· Excavator
|
· Tug boat
· Welding set
|
Construction of conveyor belt
|
· Concrete lorry mixer
· Crane
|
· Excavator
· Generator
|
· Loader
|
Construction of temporary adit
at Wah Fat Playground
|
· Breaker
· Concrete lorry mixer
· Concrete mixer
· Concrete pump
· Conveyor belt
· Drill
|
· Dump truck
· Dumper
· Excavator
· Generator
· Grader
|
· Grinder
· Lorry
· Crane
· Rock drill
· Ventilation fan
|
Reprovisioning & Reinstatement Works
|
· Air compressor
· Asphalt paver
· Bar bender and cutter
· Compactor
· Concrete lorry mixer
· Concrete pump
· Crane
|
· Dump truck
· Excavator
· Generator
· Grout mixer
· Grout pump
· Paint liner marker
|
· Piling machine
· Roller
· Trailer truck
· Vibrating hammer
· Vibratory poker
· Water Pump
|
Ancillary works (such
as training ground and tunnel operation area)
|
·
Air compressor
·
Asphalt paver
·
Bar bender and cutter
·
Compactor
·
Concrete lorry mixer
|
·
Concrete pump
·
Crane
·
Dump truck
·
Excavator
·
Generator
|
·
Roller
·
Trailer truck
·
Vibratory poker
·
Water Pump
|
Slope works
|
· Breaker
· Concrete lorry mixer
· Compactor
· Drill
· Drill rig
|
· Dump truck
· Excavator
· Generator
· Grout mixer
· Grout pump
|
· Hydraulic crusher
· Lorry
· Saw
· Vibratory poker
· Water pump
|
GI works
|
· Crane
|
· Drilling rig
|
· Generator
|
Landscape works
|
· Breaker
· Crane
· Dump Truck
|
· Excavator
· Generator
|
· Lorry
· Saw
|
Notes:
[1] Quiet
equipment or QPME would be adopted where appliable and practicable.
[2] Includes
pavement, lighting, signage, drainage.
4.3.3
Evaluation of Construction
Noise Impact
Lam Tei Area
4.3.3.1
Key construction work sites in Lam Tei area include those within Lam Tei
Quarry area. Key construction activities
include site formation, slope cutting, construction of portals and tunnel
section, construction of columns and deck for viaduct sections, construction of
at–grade roads, construction of ventilation building and construction of an
underground magazine site. Existing NSRs in the vicinity include Lo Fu Hang, Fu
Tei Ha Tsuen, and village houses along Fuk Hang Tsuen Road. All these NSRs are
village houses or temples with 1–3 storeys. Their ranges of separation
distances are approximately ≤20m from the nearest gazette
boundary and approximately 125m – 480m from underground magazine site. Based on the PME anticipated
at this stage (see Section 4.3.2), it is considered that the
mitigation measures and good site practices including use of QPME, quieter
construction methods, noise barriers, noise enclosures and locating mobile
plant as far away from NSRs as possible and practicable etc as discussed in Section 4.3.4 would be required to control the
associated construction noise impacts. However, as the NSRs near Lo Fu Hang and
Fu Tei Ha Tsuen would be relatively closer to the site formation work (i.e. approximately ≤20m) and noise exceedance maybe
anticipated without the adoption of noise mitigation measures, there would be a
need for a site hoarding with higher surface density and height to provide
extra noise attenuation for the PME as mitigation measures.
4.3.3.2
Construction
vehicles would also be required to transport various materials to and from the
construction sites as necessary. In
order to minimise the loading on existing roads (e.g.
Fuk Hang Tsuen Road and Castle Peak Road, etc.), the Contractor will implement
measures to ensure construction traffic would avoid the peak hours where
practicable. This would largely help to
minimise the nuisance from both traffic and environmental perspectives. It is also noted that the traffic induced by
various construction works in Lam Tei Area including tunnelling, stockpiling, slope
works, satellite control building and
ventilation buildings, etc would vary as the construction progresses. For
example, the construction traffic generated during the initial and later stages
would likely be less than those during the peak construction period which would
constitute a relatively shorter period. The Detailed Designer and the
Contractor shall review all the contemporary issues (e.g.
constructability, site constraints, detailed GI information, etc.) to optimise
the construction methodology and the generation of construction vehicles. For
Lam Tei Area in particular, the latest available information at this stage
suggests that the construction traffic generated along Fuk Hang Tsuen Road and
Castle Peak Road would be typically in the order of 12 construction vehicles
per hour per direction during advance works / site formation activities. During
the drill–and–blast /
drill-and-break excavation activities, the construction traffic
generated may increase to 24 construction vehicles per hour
per direction. As explained above, there will be proper traffic control for
construction vehicle and careful coordination with the concurrent projects to
avoid concurrent uses of the same travelling routes and to minimize the number
of induced traffic, noise nuisance from construction vehicle movement outside
construction sites is unlikely to be significant.
Construction of
Underground Tunnel from
Lam Tei to Sam Shing Hui
4.3.3.3
As discussed in Section 2, the
underground tunnel section from Lam Tei to Sham Shing Hui would be constructed
by drill–and–blast or drill-and-break.
The drill–and–blast / drill-and-break method is adopted for the section
underneath Tai Lam Country Park as it is a more efficient underground
tunnelling method in hard rock conditions as expected in Tai Lam Country Park.
TBM method is suitable for fractured rock / mixed ground condition, therefore,
it is not recommended for tunnelling in hard rock granite at Tai Lam Country
Park. The initial excavation of the tunnel sections will be conducted by
mechanical methods. Drill–and–blast / drill-and-break excavation will then be
adopted for the section approximately 50m behind the portal. The
drill–and–blast / drill-and-break would possibly be conducted throughout a
24–hour cycle on a daily basis to avoid programme delay and as the worst case scenario. For safety reason, an acoustic tunnel
door would be installed at the portal and this door would be closed during the
blasting. For the blasting activities, it will further be restricted to be
conducted from 0700 to 1900 on weekdays other than general holidays only to
minimize the construction impact.
4.3.3.4
As discussed in Section 4.1, a
CNP would be required for constructions works during restricted hours. In case
the Contractor considers there is a need for work within restricted hours, they
will submit an application for CNP to demonstrate the
compliance of relevant criteria.
4.3.3.5
While most of this tunnel
section would pass underneath the Tai Lam Country Park in which there are no NSRs,
the south end of this underground tunnel section would terminate at Sam Shing
Hui. At this section, the horizontal
separation distances from the tunnel center to the
nearest existing NSRs would be approximately 10m from Kam Fai Garden.
4.3.3.6
According to the latest
construction methodology, the blasting will only be conducted once per day and
the blasting will be subject to Mines Division’s agreement. As the blasting
will last for very short duration and be infrequent, it will not cause adverse groundborne construction noise impacts to NSRs in the
vicinity.
4.3.3.7
Besides, the Contractor will be
required to post highly visible warning notices/signs at suitable locations to
warn the public that blasting will take place. These warning signs will be
posted near the intended blasting location, even though all blasts will be
conducted underground. The Contractor is required to state the blasting date
and time on the notice.
4.3.3.8
For drill-and-blast /
drill-and-break tunnelling, only breaker and excavator would be adopted for the
initial excavation above-ground at Lam Tei while other PMEs would be operated
underground. Given the limited PME used underground, it will not cause adverse groundborne construction noise impacts to NSRs in the
vicinity.
4.3.3.9
According to current design as
stated in Section 2.6.1.8, site formation or rock excavation by means of non-percussive quieter
construction method such as chemical expansion agent or pulse plasma rock
fragmentation would be considered as far as practicable, and the use of
excavator-mounted breakers and blasting with explosives have been minimized.
All of the nosier works will only be conducted within the normal working hours,
i.e. non-restricted hours. On-surface blasting works
will also only be done in Lam Tei Quarry. Other than Lam Tei Quarry, all the
blasting works with explosives will only be conducted underground.
Construction of Underground Tunnel from Sam Shing Hui to Pillar
Point
4.3.3.10
As discussed in Section 2, the
underground tunnel section from Sam Shing Hui to Pillar Point would be
constructed by TBM methodology, and would possibly be conducted throughout a
24–hour cycle on a daily basis to avoid settlement issue and as the worst case
scenario. As discussed in Section 4.1, a
CNP would be required for constructions works during restricted hours. In case
the Contractor considers there is a need for work within restricted hours, they
will submit an application for CNP to demonstrate the
compliance of relevant criteria.
4.3.3.11
The TBM at Southern Portal will perform its break–in through a
vertical surface (25m (H) x 50m (W)) prepared beforehand as part of the
Southern Portal site formation. The TBM will be
dismantled at the underground dismantling chamber (16m (H) x 16m (W) x 25m(L))
at east of Sam Shing Estate excavated by drill–and–blast
/ drill-and-break method. The dismantled parts will be
transported through the interfacing tunnel section of approximately 250m long,
formed by drill–and–break or reduced drill–and–blast, and then to ground level
through temporary adit of approximately 570m long.
The portal of temporary adit (10m (H) x 10m (W)) is
located within Wah Fat Playground worksite. For
the temporary adit portal, the temporary full noise
enclosure would be installed prior to the construction of the adit. The entrance of this temporary full noise
enclosure would be designed with acoustic seals or the equivalent and should be
normally closed closed unless for lorries entering or
leaving this temporary noise enclosure for mucking out (conveying
spoil/transporting machinery) during daytime period.
4.3.3.12
For the NSR near Sam Shing Hui,
the nearest existing NSR are Castle Peak Sam Chau Ma Temple (TMS12) and Sam
Shing Estate (TMS05) which are directly located on the tunnel. The groundborne construction noise impact on these receivers
especially during restricted hours would require special attention. However, as the type and design of the TBM to
be deployed would be contractor specific, it is recommended that the Contractor
shall review the groundborne noise impacts that would
be caused by their TBM and recommend specific mitigation measures to ensure
compliance with the legislative requirements.
4.3.3.13
It is noted that a large portion
of the TBM tunnelling section would be underneath the seabed within the Tuen
Mun Typhoon Shelter in which there are no NSRs.
Hence, this portion of the TBM tunnelling would not cause any adverse
noise impacts.
4.3.3.14
Having said
that, there are some NSRs along the landbased section near Tuen Mun West. These NSRs include Tuen Mun Wu Hong Clinic,
Siu Shan Court and the planned Public Housing Development and its associated
social welfare and education facilities at Wu Shan Road. At this section, the tunnel alignment would
be approximately 25m below local ground and the slant separation distances from
the tunnel center to the nearest NSRs would be
approximately 30m from Siu Shan Court and Buddhist
Leung Chik Wai College, approximately 45m from Tuen Mun Wu Hong Clinic and approximately less than 25m from planned Public
Housing Development facilities at Wu Shan Road. According to the geological profile in this area, the
strata which the TBM drives through is bedrock. These NSRs in the vicinity are buildings on piles which would have
high attenuation due to building coupling factors. Nonetheless, the groundborne construction noise impact on these receivers
especially during restricted hours would require special attention. However, as the type and design of the TBM to
be deployed would be contractor specific, it is recommended that the Contractor
shall review the groundborne noise impacts that would
be caused by their TBM and recommend specific mitigation measures to ensure
compliance with the legislative requirements.
4.3.3.15
To further reduce the impact on
the NSRs, e.g Sam Shing Estate, Castle Peak Sam Chau
Ma Temple, Siu Shan Court and Buddhist Leung Chik Wai
College, etc., TBM maintenance will be planned for night-time shift and full
day maintenance on Sunday for these areas if the TBM is running 7days a week.
Contingency measures, such as reducing TBM thrust force and cutterhead rotation
speed for these area, would be considered to further
reduce the groundborne noise impact if it reached
statutory limits.
4.3.3.16
For the TBM launching portal
located at Southern Portal, there are no existing NSRs in the vicinity and
hence the construction and operation of this launching portal would not cause
adverse construction noise impacts.
4.3.3.17
Construction vehicles would be
required to transport various materials to and from the construction sites as
necessary. In order to minimise the loading on existing roads (e.g. Lung Mun Road etc), the Contractor will implement
measures to ensure construction traffic would avoid the peak hours where practicable. This would largely help to minimise the
nuisance from both traffic and environmental perspectives. It is also noted
that the traffic induced by various construction works in Pillar Point Area
tunnelling, slope works and ventilation building, etc. would vary as the
construction progresses. For example,
the construction traffic generated during the initial and later stages would
likely be less than those during the peak construction period which would
constitute a relatively shorter period.
The Detailed Designer and the Contractor shall review all the
contemporary issues (e.g. constructability, site
constraints, detailed GI information, etc.) to optimise the construction
methodology and the generation of construction vehicles. For Pillar Point in particular, the latest
available information at this stage suggests that the construction traffic
generated along Lung Mun Road would be typically in the order of 14
construction vehicles per hour per direction during advance works / site
formation activities. During the
excavation activities by tunnel boring machine, the construction traffic
generated may increase to 62 construction vehicles per hour per direction. As
explained above, there will be proper traffic control for construction vehicle
and careful coordination with the concurrent projects to avoid concurrent uses
of the same travelling routes and to minimize the number of induced traffic,
noise nuisance from construction vehicle movement outside construction sites is
unlikely to be significant.
Construction of Middle Ventilation Building
and Southern Ventilation Building
4.3.3.18
As discussed in Section 2, a
Middle Ventilation Building (MVB) is required for tunnel ventilation and the
location of this MVB is located at Wah Fat Playground. NSRs in the vicinity include Harvest Garden
(TMS01), Kam Fai Garden (TMS02) and Caritas Li Ka Shing Care and Attention Home
(TMS11). The horizontal separation distances from the gazette boundary are approximately <20m for Kam Fai Garden,
approximately 45m for Harvest Garden and <20m from Caritas Li Ka Shing Care
and Attention Home.
4.3.3.19
The construction site of the ventilation building will
generate excavated materials and the temporary adit
at Wah Fat Playground works area would also be adopted as the mucking out for
the underground tunnel sections connecting to Lam Tei and Sam Shing Estate.
In order to reduce the dispersion of construction noise, the current design
has allowed for 2 temporary noise enclosures, with one covering the temporary adit portal and spoil storage area, and with the other one
covering the excavation area for the ventilation building. For the
temporary adit portal and the spoil storage area, the
temporary full noise enclosure would be installed prior to the construction of
the adit and spoil storage area. The entrance
of this temporary full noise enclosure would be designed with acoustic seals or
the equivalent and should be normally closed unless for lorries entering or
leaving this temporary noise enclosure for mucking out (conveying
spoil/transporting machinery) during daytime period.
4.3.3.20
For the
construction of the ventilation building, another temporary full noise
enclosure is proposed to be installed prior to the bulk excavation of the
basement, which would help alleviating the construction noise impact from the
excavation activities. This temporary full noise enclosure should be
decommissioned only when most of the back filling works are completed. In
case mucking outs are required for conveying spoil / transporting machinery etc
during daytime period, the openings of these mucking outs should be facing
towards existing terrain instead of the existing NSRs. The mucking outs should
also be closed during evening, night–time and
restricted hours to minimise noise emanating out.
4.3.3.21
The subsequent detailed design should also explore the
practicability of locating the community liaison centre between the
construction site and Kam Fai Garden, which would provide a buffer between the
construction site and Kam Fai Garden, and hence further alleviate the
construction noise nuisance.
4.3.3.22
The Contractor shall plan to
commence the construction of these full noise enclosures for the temporary adit portal, spoil storage area and excavation area for the
MVB as early as possible. It is
recommended to complete the installation of the temporary full noise enclosure
for the MVB prior to the bulk excavation of the ventilation building so that
most of the noise generated by the bulk excavation would be well
contained. This temporary noise
enclosure should be decommissioned only when most of the back filling works are
completed. Nevertheless, based on the
PME anticipated at this stage (see Section 4.3.2), it is considered that the mitigation measures and good practices
including use of QPME, quieter constriction methods, noise barrier, noise
enclosure and mobile plant should be sited as far away from NSRs as possible
and practicable, etc as discussed in Section 4.3.4 would be required to control the associated construction noise
impacts.
4.3.3.23
After the decommissioning of
this temporary full noise enclosure, the superstructure works for the MVB could
commence. The mitigation measures and
good practices including use of QPME, quieter constriction methods, noise
barrier, noise enclosure and mobile plant should be sited as far away from NSRs
as possible and practicable, etc as discussed in Section 4.3.4 would be required to control the associated construction noise
impacts.
4.3.3.24
Construction vehicles would be
required to transport various materials to and from the construction sites as
necessary. In order to minimise the
loading on existing roads (e.g. Castle Peak Road -
Castle Peak Bay, etc.), the Contractor will implement measures to ensure
construction traffic would avoid the peak hours where practicable. This would largely help to minimise the
nuisance from both traffic and environmental perspectives. It is also noted that the traffic induced by
various construction works in area near Wah Fat Playground including slope
works, ventilation buildings, stockpiling etc. would vary as the construction
progresses. For example, the construction
traffic generated during the initial and later stages would likely be less than
those during the peak construction period which would constitute a relatively
shorter period. The Detailed Designer
and the Contractor shall review all the contemporary issues (e.g.
constructability, site constraints, detailed GI information, etc.) to optimise
the construction methodology and the generation of construction vehicles. For
area near Wah Fat Playground in particular, the latest available information at
this stage suggests that the construction traffic generated along Castle Peak
Road – Castle Peak Bay would be typically in the order of 23 construction
vehicles per hour per direction during advance works /
site formation activities. During
the drill–and–blast / drill-and-break excavation
activities, the construction traffic generated may increase to an average
of 47 construction vehicles per hour per direction. With the proper traffic
control for construction vehicle and careful coordination with the concurrent
projects to avoid concurrent uses of the same travelling routes and to minimize
the number of induced traffic, noise nuisance from construction vehicle
movement outside construction sites is unlikely to be significant.
4.3.3.25
A Southern Ventilation Building
(SVB) is also required at Pillar Point (right above the TM–CLKT). As there is no NSR identified within 300m
assessment area from SVB, adverse construction noise impact near SVB is not
anticipated.
Explosive Magazine Sites at Lam Tei Quarry, Siu Lam
and Pillar Point
4.3.3.26
The explosive magazine site at
Lam Tai Quarry would be an underground construction and would be constructed by
a combination of excavation and drill–and–break methodology. Key construction
activities include site formation and construction of the explosive storage.
The nearest NSRs in the vicinity of the explosive magazine site at Lam Tei is
the village houses near Fuk Hang Tsuen Road (LT03) which is located at
approximately 125m away. Based on the PME anticipated at this stage (see Section 4.3.2), it is considered that the mitigation measures and good practices
including use of QPME, quieter constriction methods, noise barriers, noise
enclosures and locating mobile plant as far away from NSRs as possible and
practicable etc as discussed in Section 4.3.4 would be required to control the associated construction noise
impacts.
4.3.3.27
For the surface explosive
magazine site at Siu Lam, the nearest NSR is Grandview Terrace (SL01) at
approximately 200m away. It is
considered that the mitigation measures and good practices including use of
QPME, quieter constriction methods, noise barriers, noise enclosures and
locating mobile plant as far away from NSRs as possible and practicable etc as
discussed in Section 4.3.4 would be required to control the associated construction noise
impacts.
4.3.3.28
For the surface explosive magazine
site at Pillar Point, there are no existing NSRs within 300m and hence adverse
construction noise impact is not anticipated to the nearby NSRs.
4.3.3.29
The construction work required
for the decommissioning of these explosive magazine sites is not anticipated to
be significant. Hence, the construction
noise is also not considered to be significant provided that suitable
mitigation measures are implemented.
Portal Opening and Open Road Near Pillar
Point
4.3.3.30
As there is no existing NSR
identified for Pillar Point within 300m assessment area, adverse construction
noise impact near Pillar Point is not anticipated.
Slurry Treatment Plant at Pillar Point
4.3.3.31
As there is no existing NSR
identified for Pillar Point within 300m assessment area, adverse construction
noise impact near Pillar Point is not anticipated. Also, Slurry Treatment Plant
(STP), its conveyor belts and slurry pipes will be fully enclosed with noise
enclosure, adverse construction noise impact is not anticipated.
The Ancillary Works at Pillar Point
4.3.3.32
As there is no existing NSR
identified for Pillar Point within 300m assessment area, adverse construction
noise impact from the Ancillary Works (e.g.
administrative building, training ground and supporting area, recovery area and
maintenance compound) is not anticipated.
Others
4.3.3.33
As discussed in Section 2,
there are barging points and facilities and delivery point at Pillar Point near
River Trade Terminal. As there is no existing NSRs identified within 300m
assessment area, adverse construction noise impact from the barging point is
not anticipated.
4.3.3.34
As there is no civil works or
demolition of at the former Girl Guide Association (GGA) Campsite and only
small scale of renovation for site office or other project uses is required.
Given the construction works are relatively minor and
hence the construction noise impacts would be relatively minor provided good
practices and standard mitigation measures are implemented.
Reprovision &
Reinstatement of Existing Facilities
4.3.3.35
As discussed in Section 2, reprovision is
required for some existing facilities at Tuen Mun West including reprovision of
basketball court and public toilet at the existing carpark near Sam Shing Hui
and reprovision of carpark at the existing parking lots and amenity area on
Fung On Street. These construction works are relatively minor and hence the
construction noise impacts would be relatively minor provided good practices
and standard mitigation measures are implemented.
4.3.3.36
For the reprovision works near
Sam Shing Hui (i.e. Temporary
reprovisioning of basketball court and public toilet and re-instatement at KW
carpark and re-instatement of Wah Fat Playground), NSRs
in the vicinity include Kam Fai Garden, Harvest Garden, Hanford Garden and
Saint Temple at Sam Shing Hui with horizontal separation distances between NSRs
and these works area in approximately 20m–70m. As for the reprovision works
near Fung On Street , NSRs in the vicinity include Tsui Ning Garden and
Goodview Garden near Fung On Street, with horizontal separation distances
between NSRs and the works area are 25m – 35m. Based on the PME anticipated at
this stage (see Section 4.3.2), it is considered that the mitigation measures and good practices
including use of QPME, quieter constriction methods, noise barrier, noise
enclosure and mobile plant should be sited as far away from NSRs as possible
and practicable, etc as discussed in Section 4.3.4 would be required to control the associated construction noise
impacts.
4.3.3.37
Besides, EMSD will relocate the existing Tuen Mun Vehicle Servicing
Station to a suitable location to be separately determined by EMSD. The site vacated will be used by the Project
as one of the construction sites. Where necessary, there would be a temporary
reprovision of this facility at the former TM–CLKT Site Office at Pillar
Point. In such a case, this temporary
reprovision would only last during the construction of the Project and the
permanent reprovision by EMSD would be completed before the commissioning year
for the operation of the Project. Nevertheless, since there is no existing NSR
in the vicinity of the temporary EMSD vehicle servicing centre, adverse
construction noise impact is not anticipated.
Consideration of
Cumulative Impacts
4.3.3.38
Section 2.10 has identified a list of concurrent projects that would have to be
considered in this EIA to address any significant cumulative impacts. The following sections discuss the cumulative
impacts for each area.
4.3.3.39
For Lam Tei Area, concurrent
projects include Route 11 (R11), Widening of Yuen Long Highway (Section between
Lam Tei Quarry and Tong Yan San Tsuen Interchange), Widening of Fuk Hang Tsuen
Road (Between Castle Peak Road – Lam Tei and Fuk Hang Tsuen Lane), Underground
Quarrying at Lam Tei, Relocation of Tuen Mun Water Treatment Works to Caverns,
Tuen Mun and Development at Lam Tei North East. For
R11, although the works area in Lam Tei Area would be larger than that
of the Project, the project proponent of R11 is the
same as the Project and would implement the equivalent set of construction
noise control measures as the Project.
Adverse cumulative construction noise impacts from R11 are therefore not
anticipated.
4.3.3.40
For Widening of Yuen Long
Highway (Section between Lam Tei Quarry and Tong Yan San Tsuen Interchange), it
is located more than 500m from the Project, adverse cumulative construction
noise impacts are therefore not anticipated.
4.3.3.41
For Widening of Fuk Hang Tsuen
Road (Between Castle Peak Road – Lam Tei and Fuk Hang Tsuen Lane), as there is
no overlap of construction period, the cumulative impact during construction
phase is not anticipated.
4.3.3.42
The Planning Study for the
Underground Quarrying at Lam Tei, Tuen Mun, Relocation of Tuen Mun Water
Treatment Works to Caverns and Development at Lam Tei North
East are still on–going and there are no definitive design information
at the time of preparing this EIA.
Nevertheless, it is anticipated that their studies would consider all
committed projects in the vicinity, including but not limited to Project during
their subsequent study. As any other
studies by government, it is anticipated that they will also implement all the
best practices to abate construction noise impacts where practicable. On this basis, adverse cumulative
construction noise impacts from these projects are therefore not anticipated.
4.3.3.43
For area near Wah Fat
Playground, the concurrent projects include the Cycle Track between Tsuen Wan
and Tuen Mun (Tuen Mun to So Kwun Wat Section), Cycle Track between Bayview
Garden and So Kwun Wat, Widening of Castle Peak Road – Castle Peak Bay, and
Traffic Improvement Scheme in Tuen Mun– Widening and Addition of Slip roads at
Lung Fu Road/ Tuen Mun Road/ Wong Chu Road/ Hoi Wing Road. For Cycle Track
between Tsuen Wan and Tuen Mun and Cycle Track between Bayview Garden and So
Kwun Wat, given the relatively small scale of the cycle track, together with
the good practices that they would implement, adverse cumulative construction
noise impacts are therefore not anticipated. For Traffic Improvement Scheme in
Tuen Mun –Widening and Addition of Slip roads at Lung Fu Road/ Tuen Mun Road/
Wong Chu Road/ Hoi Wing Road, the additional Tuen Mun Road/ Hoi Wing Road Slip
Road would be located in the vicinity. Nevertheless, the scale of road works is
anticipated to be small and the potential construction noise impacts are
anticipated to be limited. Adverse cumulative construction noise impacts are
not anticipated with the good site practices that they would implement.
4.3.3.44
For Widening of Castle Peak
Road – Castle Peak Bay, as there is no overlap of construction period, the
cumulative impact during construction phase is not anticipated.
4.3.3.45
The concurrent projects in Tuen
Mun, including Reprovision of Tuen Mun Swimming Pool and Tuen Mun centre Golf
Centre Practice Green, Tuen Mun, Sports Ground and Open Space with Public
Vehicle Park in Area 16, Tuen Mun and Site Formation and Infrastructure Works
for Public Housing Developments at Tuen Mun Central – Wu Shan Road, are located
outside 300m from the above ground construction area of the Project. As the
construction activities would be carried out underground by TBM and no
above-ground construction, no adverse cumulative construction noise impacts are
therefore anticipated. For concurrent projects in Tuen Mun South Extension and
Planned Property Development at Area 16, the nearest construction work area is reprovision works of carpak near
Fung On Street. Based on the PME for reprovision works of carpak
near Fung On Street anticipated at this stage (see Section 4.3.2) and construction works
are relatively minor, it is considered that with
adoption of mitigation measures and good practices, adverse cumulative
construction noise impact is not anticipated.
4.3.3.46
For Pillar Point Area, the
concurrent project includes Lung Kwu Tan Reclamation
and the Replanning of Tuen Mun West Area. The project is still undergoing its
respective studies and there is no definitive design information at the time of
preparing this EIA. Nevertheless, it is
anticipated that their study would consider all committed projects in the
vicinity, including but not limited to the
Project during their subsequent study and recommend
mitigation measures and all the best practices to abate construction noise
impacts where practicable. On this basis, adverse cumulative construction noise
impact from the concurrent project is therefore not anticipated.
4.3.4
Mitigation of Construction Noise Impact
4.3.4.1
Due to the short separation from
NSRs, noise exceedances are anticipated. The following mitigation measures have
been considered and confirmed the practicality by the Project Engineers:
·
Good site practices
to limit noise emissions at the source;
·
Use of
quality powered mechanical equipment (QPME) and quieter construction methods;
·
Use of site
hoarding with higher surface density and height at the site boundary where
adjacent to NSRs;
·
Use of
temporary noise barriers and noise enclosure to screen noise from relatively
static PMEs;
·
Noise
Enclosure Mucking out at the Portal Opening for Tunnelling Activities;
·
Install
Acoustic Tunnel Door or Enclosure at the Portal Opening for Tunnelling
Activities; and
·
Alternative
use of plant items within one worksite, wherever practicable.
4.3.4.2
The above mitigation measures
and the EPD’s “Recommended Pollution Control Clauses for Construction
Contracts” would need to be implemented in work sites as good practices where
appropriate. Detailed descriptions of these mitigation measures are given in
the following sections.
Good Site Management Practices
4.3.4.3
Good site practice and noise
management techniques could considerably reduce the noise impact from
construction site activities on nearby NSRs. The following measures should be
practised during each phase of construction:
·
Only
well–maintained plant should be operated on–site and plant should be serviced
regularly during the construction programme;
·
Machines and
plant (such as trucks, cranes) that may be in intermittent use should be shut
down between work periods or should be throttled down to a minimum;
·
Plant known
to emit noise strongly in one direction, where possible, be orientated so that
the noise is directed away from nearby NSRs;
·
Silencers or
mufflers on construction equipment should be properly fitted and maintained
during the construction works;
·
Mobile plant
should be sited as far away from NSRs as possible and practicable; and
·
Material
stockpiles, site office and other structures should be effectively utilised,
where practicable, to screen noise from on–site construction activities.
4.3.4.4
Additional mitigation measures
such as rescheduling will be adopted. Mucking out and construction traffics
will only be operating from 0700 to 1900 within the normal working hours, i.e. non-restricted hours. Other noisier tasks such as
piling and mucking out works will also only be done within non-restricted
hours.
4.3.4.5
The benefits of these
techniques can vary according to specific site conditions and operations. The
environmental noise climate would certainly be improved with these control
practices, although the improvement can only be quantified during
implementation when specific site parameters are known.
Use of Quality Powered
Mechanical Equipment (QPME) and Quieter Construction Methods
4.3.4.6
The use of quiet plant
associated with the construction works is made reference to the QPME (e.g. air compressor, asphalt paver, bulldozer, compactor,
crane, excavator, generator, etc) / other commonly used PME listed in EPD web pages as far as possible which includes the SWLs
for specific quiet PME, and the quiet construction method and equipment listed in
EPD web page. It is generally known (supported by field measurement) that
particular models of construction equipment are quieter than standard types
given in the GW–TM. The quiet construction methods stated in Section 4.3.2.3 and Appendix 4.3 should be adopted where feasible.
Use of Site Hoarding
with Higher Surface Density and Height at the Site Boundary where Adjacent to
NSRs
4.3.4.7
Purpose-built temporary noise
barriers located on the site boundaries between noisy construction activities
and NSRs could generally reduce noise levels of NSRs at village houses through
partial screening. It would be possible for the Contractor to provide these in
the form of site hoardings to achieve this attenuation effect, provided that
the barriers have no openings or gaps and have a superficial surface density of
at least 14kg/m2. Good site practice shall also be adopted by the
Contractor to ensure the conditions of the hoardings are properly maintained
throughout the construction period.
Use of Movable Noise Barrier and Full Enclosure for Relatively Fixed
Plant Source
4.3.4.8
Movable temporary noise
barriers that can be located close to noisy plant and be moved concurrently
with the plant along a worksite can be very effective for screening noise from
NSRs. A typical design which has been used locally is a wooden framed barrier
with a small–cantilevered upper portion of surface mass density no less than
14kg/m2 on a skid footing with approximately 50mm thick internal
sound absorptive lining. The noise barrier should have no gaps/openings at
joints in the barrier material, and should have sufficient length (e.g., at
least five times greater than its height or be bent around the noise sources)
and height such that no part of the noise source will be visible from the NSR
being protected. The Contractor shall critically review the contemporary conditions
and develop the detailed design of the noise mitigation measures. This measure
is particularly effective for low level zone of NSRs. A cantilevered top cover
would be required to achieve screening benefits at upper floors of NSRs.
Schematic drawing for the noise barrier and full enclosure are given in Appendix
4.4.
4.3.4.9
Movable temporary noise
barriers will be used for some PME (e.g. excavator).
It is anticipated that suitably designed barriers could achieve at least 5dB(A)
reduction for movable plant and 10dB(A) for stationary plant.
4.3.4.10
For the use of movable noise
barrier for at–grade construction works, for example diaphragm wall
installation, working space would be considered for their manoeuvrability and
placement. Generally, sufficient separation between major plants during
at–grade construction works is envisaged to cater for the use of temporary
movable noise barriers onsite. Temporary movable noise barrier can be placed
close to noise source locally as far as practicable.
4.3.4.11
The use of standard enclosure
has been considered in this assessment to shelter relatively fixed plant
including air compressor, generator. These standard enclosures can provide at
least 15dB(A) noise reduction.
4.3.4.12
Full noise enclosures would be
required for the construction of temporary adit and
spoil storage area / excavation area for ventilation building. The temporary full noise enclosure shall
cover these adit portals, leaving only mucking outs
for conveying spoil / transporting machinery etc during daytime period. Where practicable, the openings of these
mucking outs should be facing towards existing terrain instead of the existing
NSRs. The mucking outs should also be
closed during evening, night–time and restricted hours
to minimise noise emanating out.
4.3.4.13
The Contractor shall plan to
commence the construction of this temporary full noise enclosure as early as
possible. The temporary full enclosure for the Adit
and spoil storage area should be installed prior to the construction of the adit and the spoil storage area. As for the full noise
enclosure for the excavation area of the MVB, it is recommended to complete the
installation of this full noise enclosure prior to the bulk excavation so that
most of the noise generated by the bulk excavation would be well
contained. This temporary noise
enclosure should be decommissioned only when most of the back filling works are
completed.
Install Acoustic Tunnel Door or Enclosure at
Construction Shafts for Tunnelling Activities
4.3.4.14
It is considered that
installation of acoustic tunnel door or enclosure at the tunnel portals is an
effective mitigation measure for construction works to be conducted inside the
tunnels during both the restricted hours and non-restricted hours. The acoustic
tunnel door or enclosure should be made of acoustic panels and the ventilation
openings of the tunnel door or enclosure should also be fitted with silencers.
The Contractor should select a proper type of acoustic panel and silencer which
can provide necessary noise reduction performance to achieve the full
compliance with the EIAO-TM's requirements or ANLs under CNP application.
Alternative use of plant
items within one worksite
4.3.4.15
In practice, some plant items
will operate sequentially within the same work site, and certain reduction of
the predicted noise impacts could be achieved. However, any additional control
on the sequencing of plant will impose a restrictive constraint to the
Contractor on the operation and planning of plant items, and the implementation
of the requirement would be difficult to be monitored. Hence, sequencing
operation of PME has not been taken into consideration.
4.3.5
Construction Noise
Management Plan
4.3.5.1
A Construction Noise Management
Plan (CNMP) containing a quantitative construction noise impact assessment, the
adopted quieter construction method(s) and equipment, noise mitigation measures
and the construction noise impact monitoring and audit programme will be
submitted to the EPD with reference to the updated and identified plant
inventories once available and in any case before tendering and commencement of
the project construction, and if there is any change to the construction noise
mitigation measures recommended in the CNMP, an updated CNMP shall be submitted
one month before the implementation of such change.
4.3.5.2
A summary of key steps for
quantitative construction noise assessment in a CNMP will be conducted:
·
Determine
300m from the boundary of the Project Site and associated works and temporary
work site / works area;
·
Identify
NSRs and locate representative assessment points that may be affected by the works;
·
Update the
construction method for the key construction;
·
Update the
construction plant inventory for the key construction work;
·
Determine
the SWLs of the plant items according to the information stated in the GW–TM or
other recognised sources of reference, where appropriate;
·
Calculate
the correction factors based on the distance between the NSRs and the notional
noise source positions of the work sites;
·
Apply
corrections for façade, distance, barrier attenuation, acoustic reflection
where applicable;
·
Predict
construction noise levels at the NSRs;
·
Quantify the
level of impact at the NSRs, in accordance with GW–TM;
·
Predict the
cumulative noise impacts for any concurrent construction works in the vicinity
of the proposed work;
·
For any
exceedance of noise criteria, all practical mitigation measures such as
alternative construction methodology, quiet plant, silencer, enclosure, etc,
shall be examined to alleviate the predicted noise impacts as much as
practicable; and
·
Consideration
of noise mitigation measures will follow Annex 13 of EIAO–TM and EIAO Guidance
Note “Preparation of Construction Noise Impact Assessment under the
Environmental Impact Assessment Ordinance” [GN 9/2010].
4.3.5.3
The CNMP will include an
implementation schedule to clearly list out the mitigation measures, the
implementation party, construction noise impact monitoring and audit programme,
locations, timing and environmental performance
required for implementation of the mitigation measures. Mitigation measures
recommended and requirement specified in the CNMP shall be fully implemented by
the Contactor.
4.3.6
Evaluation of Residual
Construction Noise Impact
4.3.6.1
Construction noise impact
arising from the Project will be within respective criteria. Adverse residual
noise impacts are thus not anticipated.
4.3.6.2
The number of dwellings,
classrooms and other sensitive elements that will be exposed to adverse
residual noise impact exceeding the criteria set in Annex 5 in the TM is nil.
4.4
Road Traffic Noise Impact
Assessment
4.4.1
Road Traffic Noise Impact
Assessment Methodology
4.4.1.1
Road traffic noise calculation
is based on the method of UK Department of Transport "Calculation of Road
Traffic Noise (CRTN)". The predicted noise levels at the sensitive
receivers include 2.5dB(A) facade reflection and correction factors of effects
due to gradient, distance, view angle, road surface and barriers.
4.4.1.2
The computer programme, RoadNoise 2000, has been used to model traffic noise from
road networks. It complies with the Calculation of Road Traffic Noise (CRTN)
developed by the UK Department of Transport. The road traffic noise will be
presented in terms of noise levels exceeded for 10% of the one–hour period
during peak traffic flow [i.e. L10(1hr) dB(A)].
4.4.1.3
Calculations of future road
traffic noise are based on the peak hourly flow for the maximum traffic
projected within a 15 years period upon full operation
of the roadworks. The traffic projection has adopted the latest Task Force
Planning Dataset of the Territorial Population and Employment Data Matrix
(TPEDM) issued in June 2022, which has taken into account
various committed projects.
4.4.1.4
As discussed in Section 2, the
commissioning year of the Project would be in Year 2033. The assessment year
with maximum traffic projections (morning peak hour traffic flows and vehicle
compositions, which is generally higher traffic flows than afternoon peak)
within 15 years upon operation of the Project would be Year 2048. Hence, Year
2048 was adopted as assessment year in road traffic noise assessment due to its
peak traffic prediction in Traffic Impact Assessment of the Project. The
traffic forecast for the prevailing year (i.e. 2025
without project) and the assessment year is presented in Appendix
4.5. The
traffic flow forecast has been confirmed with Transport Department.
4.4.1.5
The following concurrent road projects have been identified and
included in the traffic forecast and hence the road traffic noise assessment:
·
R11;
·
Widening of Fuk Hang Tsuen Road;
·
Widening of YLH (Section between
Lam Tei Quarry and Tong Yan San Tsuen Interchange);
·
Widening of Castle Peak
Road-Castle Peak Bay;
·
Road P1 (Tai Ho-Sunny Bay
Section);
·
TYLL; and
·
HKIW-NEL Link.
4.4.1.6
The following concurrent development projects have been identified
and the induced traffic from the concurrent projects has been included in the
traffic forecast, including but not limited to:
·
Hung Shui Kiu / Ha Tsuen New
Development Area;
·
Proposed Public Housing
Developments at Ping Shan South, Yuen Long, Lam Tei North and Nai Wai, Tuen Mun;
and
·
Public Housing Development near
Tan Kwai Tsuen, Yuen Long.
4.4.1.7
In accordance with the EIAO
Guidance Note “Road Traffic Noise Impact Assessment Under the Environmental
Impact Assessment Ordinance” (12/2010), direct mitigation measures should be
considered or proposed on the road project if there would be adverse
environmental impact. Where the predicted noise impacts with the project exceed
the noise criteria, direct mitigation measures shall be considered to reduce
the noise from the project road to a level that:
·
is not
higher than the standard; and
·
has no
significant contribution (i.e. less than 1.0dB(A)) to
the overall noise from other existing roads, if the cumulative noise level,
i.e. noise from the project road together with other existing roads exceeds the
standard.
4.4.1.8
In cases where direct noise mitigation measures alone are not
adequate in mitigating noise to a level in compliance with the EIAO–TM noise
criteria, indirect noise mitigation measures for existing NSRs may be adopted.
Eligibility of the affected premises for indirect noise mitigation measures is
determined with reference to EPD’s Guidance Note GN 12/2010, the following
three criteria, all of which must be satisfied:
·
The
predicted overall noise level exceeds the noise standard in accordance with
EIAO–TM;
·
The
predicted overall noise level is at least 1.0 dB(A) more than the prevailing
traffic noise level, i.e. the total traffic noise level
existing before the works to construct the road were commenced; and
·
The
contribution from the Project Road to the increase in the predicted overall
noise level is at least 1.0 dB(A).
4.4.2
Identification of Road
Traffic Noise Impact
Identification of Project
Road
4.4.2.1
The Project Road Extent
includes the following items and shown in Appendix
4.6 and summarized below:
·
Road tunnel
of about 7.5 km long running through Tuen Mun and Tai Lam Country Park, linking
the Tuen Mun – Chek Lap Kok Link (TM–CLKT) and the YLH and Kong Sham Western
Highway (KSWH);
·
Viaducts /
at–grade roads from the southern tunnel portal to the roads under planning near
Lung Mun Road/Mong Fat Street, and TM–CLKT at Tuen Mun Area 40; and
·
viaducts /
at–grade roads from the northern tunnel portal to YLH and KSWH at Lam Tei East
Interchange.
Noise Assessment Points for Road
Traffic Noise Impact Assessment
4.4.2.2
The assessment area for road
traffic noise includes an area within 300m from the Project Road and highway /
tunnel operation and maintenance facilities. Representative NSRs and NAPs that
would be affected road traffic noise have been identified and presented in Table
4.8 and are summarised in Table 4.11 below. Locations of
Representative NSRs and NAPs for road traffic noise impact assessment are shown
in Figure 4.4.
Table 4.11 Identified NSRs and NAPs within 300m of Road Traffic
Noise Assessment Area
NSR ID [1]
|
Description
|
Uses [2]
|
Number of Storeys
|
NAP ID
|
Lam Tei
|
LT01
|
Area at/near Lo Fu Hang
|
R
|
1–3
|
LFH–01 – LFH–08
|
LT02
|
Area at/near Fu Tei Ha
Tsuen
|
R
|
1–3
|
FTT–01 – FTT–04
|
Temples at Fu Tei Ha Tsuen
|
W
|
1
|
Te–06
|
Notes:
[1] The assessment will only include
NSRs which rely on opened windows for ventilation and within 300m assessment
area.
[2] R – Residential, W – Place of Public
Worship.
Inventory of Noise Sources
4.4.2.3
Road traffic noise will be
generated from vehicular traffic on existing road network and the proposed open
road network within the 300m assessment boundary from the Project Roads extent.
The key road traffic noise sources from existing roads include YLH, KSWH, etc.
4.4.2.4
The key road traffic noise sources
from planned roads are shown in Appendix
4.6. The
road segments are classified as “Project roads” and “Other roads”. Computer
plots of the traffic noise model are presented in Appendix
4.6. Agreement on the road sections to be included in the road
traffic noise assessment has been obtained from EPD in accordance with Appendix
C Clause 3.2.2(a) of the EIA Study Brief.
4.4.2.5
The characteristics of the road
network such as road width, surface type and traffic flow and the use of Low
Noise Road Surfacing (LNRS), the existing and committed noise mitigation
measures have been considered in the assessment.
4.4.2.6
The locations of existing and
committed noise mitigation measures (i.e. noise barrier proposed in the
Approved EIA for Deep Bay Link (AEIAR–064/2002)) and its Environmental Permit
No. EP–163/2003/H are presented in Appendix
4.7.
4.4.2.7
In accordance with Highways
Department (HyD) Guidance Notes on Road Surface Requirements for Expressways
and High Speed Roads (RD/GN/032A), Highly Modified
Friction Course (HMFC) is proposed as the standard surfacing material on the
high speed road sections of new road projects with design speed of 80km/hr or
above and expressway. From the RD/GN/032A, the noise reduction performance of
HMFC is comparable to traditional LNRS (i.e. PMFC),
hence, it is also served as LNRS. Locations of existing and committed LNRS
(including HMFC to be implemented at proposed project road with design speed of
80km/hr or above and expressway) are confirmed with HyD and presented in Appendix
4.8.
4.4.3
Prediction and Evaluation
of Road Traffic Noise Impact
Modelling Scenarios
4.4.3.1
Referring to the requirements
of the EIA SB, the following scenarios were assessed in the EIA study.
i.
Unmitigated
scenario at the assessment year with maximum traffic projection within 15 years
upon operation of the Project (i.e. Year 2048); and
ii.
Prevailing scenario
for indirect mitigated measures eligibility test (i.e.
Year 2025), if mitigation measures are required
4.4.4
Prediction Of Noise Impact of Unmitigated Scenario
4.4.4.1
The predicted road traffic
noise levels at each representative NAPs under unmitigated scenario are
presented in Table 4.12. Appendix
4.9 shows
the details of the noise impacts at different levels of the NAPs under
unmitigated scenario.
Table 4.12 Predicted Road
Traffic Noise Impact at NAPs Under Unmitigated Scenario
NSR
ID [1]
|
Description
|
NAP
ID
|
Use
[2]
|
Criterion,
L10 1hr dB(A)
|
Max.
Predicted Noise Level, L10 hr dB(A) [3]
|
Whether
Noise Mitigation Measures on “Project Roads” are required (Y/N)
|
Overall
|
Project
Roads
|
Other
Roads
|
Max.
“Project Roads” Contribution when Overall Noise Level Exceed Criterion [4]
[5]
|
Lam Tei
|
LT01
|
Area at/near Lo Fu Hang
|
LFH–01 – LFH–08
|
R
|
70
|
65–71
|
≤40–59
|
65–71
|
0.0
|
N
|
LT02
|
Area at/near Fu Tei Ha Tsuen
|
FTT–01 – FTT–04
|
R
|
70
|
54–66
|
≤40–56
|
54–65
|
–
|
N
|
Temples at Fu Tei Ha Tsuen
|
Te–06
|
W
|
65
|
46
|
≤40
|
46
|
–
|
N
|
Notes:
[1] The assessment will only include
NSRs which rely on opened windows for ventilation and within 300m assessment
area.
[2] R – Residential, W – Place of Public
Worship.
[3] Bold figure denotes the predicted
noise level is over the relevant EIAO–TM noise criteria.
[4] Bold figure denotes the noise
exceedance which is over the relevant EIAO–TM noise criteria and the
contribution from Project Roads to the overall noise level is equal to or
higher than 1.0 dB(A).
[5] Maximum Project Roads contribution
for NSRs with overall noise level exceeding relevant criteria.
Lam Tei Area
4.4.4.2
As
discussed in Section 4.4.2, the NSRs within the Assessment Area for
road traffic noise comprise of villages houses and temple of 1–3 storeys
high.
4.4.4.3
According
to the noise assessment results, the cumulative road traffic noise levels at
most of village houses and temple would comply with the noise criterion and
hence noise mitigation measures are not required.
4.4.4.4
However,
for Area at/near Lo Fu Hang (LT01), one of the NAPs would experience cumulative
noise impacts higher than the noise criterion.
However, the exceedance is caused by the noise generated from Chui Fuk
Road instead of the Project Road. The
respective Project Contribution is also less than 1dB(A). On this basis,
mitigation measures within the Project Road Extent would not be required.
Consideration of Tunnel Portal Noise
4.4.4.5
For portal openings at Lam Tei,
the existing NSRs within 300m from the portal openings are village houses,
which are located below the portal level. The portal opening would be screened
by the viaduct structure of new road sections or terrain. As there is also a proposed satellite control building and two ventilation
buildings of TMB and R11, these buildings will be 2-3 storeys in height which
can substantially screen the tunnel opening from the existing NSRs. Hence,
adverse noise impact from the portal is not anticipated.
4.4.4.6
For portal
openings near Tuen Mun Area 40, as there is no existing NSR identified within
300m from portal openings. Hence, adverse noise impact from the portal is not
anticipated.
4.4.5
Indirect Mitigation Measures
4.4.5.1
According
to Section 4.8 of EIAO Guidance
Note No. 12/2010, the testing criteria for consideration of Indirect Mitigation
Measures are set out as below:
(i)
the predicted overall noise level
from the road project together with other traffic noise in the vicinity must be
above a specified noise level;
(ii)
the predicted overall noise level
is at least 1.0 dB(A) more than the prevailing traffic noise level, i.e. the total traffic noise level existing before the works
to construct the road were commenced; and
(iii)
the contribution to the increase
in the predicted overall noise level from the road project must be at least 1.0
dB(A).
4.4.5.2
As
mentioned above, in the case where NSRs are still exposed to noise levels
exceeding the relevant noise criteria after the implementation of all direct
mitigation measures, the total number of existing dwellings, classrooms and
other noise sensitive elements which may qualify for indirect technical
remedies should be identified. However, for those NSRs with cumulative noise
level exceed the relevant noise criteria, the noise contribution from “Project
Road” would be lesser than 1.0 dB(A). The assessment result of the prevailing
scenario is shown in Appendix
4.10.
Hence, irrespective of the prevailing noise level, all the NSRs would not
satisfy the eligibility assessment criteria.
4.4.6
Evaluation of Residual Road Traffic Noise Impact
4.4.6.1
According to Section 4.4.4, adverse residual road traffic noise impact due to the Project is
not anticipated.
4.5
Fixed Noise Sources Impact
Assessment
4.5.1
Fixed Noise Sources Impact Assessment Methodology
4.5.1.1
As set out in Appendix C Clause
4.1.2 of the EIA SB, a qualitative assessment is required to identify the fixed
noise sources/ temporary industrial sources, and
proposing corresponding direct mitigation measures to be adopted during
operation phase to demonstrate that no adverse fixed noise sources impact will
be associated with the Project. A summary of key steps for this qualitative
fixed noise sources noise assessment that has conducted is:
· Determine the assessment area from Project Road and
highway / tunnel operation and maintenance facilities;
· Summarize the fixed noise sources;
· Identify and locate representative NSRs that may be
affected by the noise sources;
· Determine the noise criteria for both daytime and nighttime;
· Evaluate the potential qualitative impact at the
NSRs; and
· Examine and recommend all practical mitigation
measures such as quiet plant, silencer, enclosure, etc, to alleviate any
potential noise impacts as much as practicable.
4.5.2
Identification of Fixed Noise Sources Impact
Identification of
Assessment Area and Noise Sensitive Receiver
4.5.2.1
The assessment area for fixed
noise source impact includes an area within 300m from the Project Road and
highway / tunnel operation and maintenance facilities. Representative NSRs and
NAPs locations that would be affected by the fixed noise sources have been
identified and presented in Table 4.8
and are summarised in the Table 4.13 below. Locations of Representative
NSRs and NAPs for fixed noise sources impact assessment are shown in Figure 4.5.
Table 4.13 Representative NSRs for Fixed Noise Source
Impact Assessment
NSR ID [1]
|
Description
|
Use [2]
|
Number of Storeys
|
NAP ID
|
Area Sensitivity
Ratings [3]
|
ANL – 5, dB(A)
|
Prevailing
Background Noise Levels, dB(A)
|
Noise Criteria,
dB(A) [4,5]
|
Existing NSRs
|
a.
Lam Tei
|
LT02
|
Area at/near Fu Tei Ha Tsuen
|
R
|
1 – 3
|
FTT–01
|
A
|
55 / 55/ 45
|
52/ 50 / 45
|
52 / 50 / 45
|
Temples at Fu Tei Ha Tsuen
|
W
|
1
|
Te–06
|
A
|
55 / 55/ 45
|
52/ 50 / 45
|
52 / 50 / 45
|
b.
Tuen Mun West
|
TMS01
|
Harvest Garden
|
R
|
17
|
HAR–01
|
B
|
60 / 60 / 50
|
53 / 53 / 49
|
53 / 53 / 49
|
TMS02
|
Kam Fai Garden
|
R
|
15
|
KAM–01
|
B
|
60 / 60 / 50
|
53 / 53 / 49
|
53 / 53 / 49
|
Notes:
[1] The
assessment will only include NSRs which rely on opened windows for ventilation
and within 300m assessment area.
[2] R
– Residential; W – Place of Public Worship.
[3] Refer
to Appendix 4.11.
[4] Day
/ Evening / Nighttime criteria
[5] Fixed
noise criteria are stipulated in Annex 5 of EIAO–TM and summarized below:
(a) 5dB(A) below the appropriate ANLs shown
in Table 2 of the Technical Memorandum for the Assessment of Noise from Places
Other than Domestic Premises, Public Places or Construction Sites, or
(b) the prevailing background noise levels
(For quiet areas with noise level 5 dB(A) below the ANL).
Inventory of Noise Sources
4.5.2.2
According to current design, 3
ventilation buildings for the Project are proposed and summarized in Table
4.14 below. Potential fixed noise impacts arising from the ventilation
buildings would be caused by operation of the ventilation fans. The locations
of the potential fixed noise sources during operation phase as confirmed with
HyD are shown in Figure
4.5.
Table 4.14 Summary of Proposed Potential Fixed Noise Sources
Location
|
Ventilation building(s)
|
Other Potential Fixed Noise
Source
|
Lam Tei
|
Northern Ventilation Building
(NVB)
|
Satellite
Control Building
|
Wah Fat Playground
|
Middle Ventilation Building
(MVB)
|
-
|
Pillar Point (right above the
TM–CLKT)
|
Southern Ventilation Building
(SVB)
|
Administrative Building
Maintenance Compound
|
4.5.3
Evaluation of Fixed Noise
Sources Impact
4.5.3.1
As discussed in Section 2, the three Ventilation
Buildings (ie a total of 3 no. in Lam Tei, Wah Fat
Playground and Pillar Point) and Administration Building
(in Pillar Point) are the key fixed noise sources for the Project. Section 4.2.3 has also identified the NSRs in the vicinity of these
fixed noise sources. All the planned noise sources would be assumed to be
operated at the same time as worst-case scenario as confirmed with HyD.
4.5.3.2
For the Northern Ventilation Building, the nearest existing
NSR in the vicinity of are the village houses near Fu Tei Ha Tsuen (LT02). The
separation distance between Ventilation Building (i.e. the
nearest source) and this NSR is ~50m. It
is anticipated that, with a combination of the mitigation measures such as
selection of quieter plant, installation of suitable sound attenuators,
suitable orientation of the key louvers etc (see Section 2), adverse fixed noise
impact is not anticipated. The Detailed
Designer / Contractor of the Ventilation Building shall consider all the
contemporary circumstances including but not limited to the ventilation
building for R11 when designing the noise mitigation measures.
4.5.3.3
For Satellite
Control Building at Lam Tei, the major noise sources would be noise from ventilation
system. Comparing to NVB, they are located further away from nearest existing NSR (i.e. village houses near Fu Tei Ha Tsuen (LT02)). It is
anticipated that, with a combination of the mitigation measures such as
selection of quieter plant, installation of suitable sound attenuators,
suitable orientation of the key louvers etc (see Section 2), adverse fixed noise
impact is not anticipated.
4.5.3.4
For Highway/ Tunnel Operation
Area, it is reserved area for vehicle retention and other
tunnel operation. Since the uses, layout and design of the operation area are
not yet available at EIA stage, it is feasible that it could be planned and
designed with a combination of the mitigation measures such as selection of
quieter plant, installation of suitable sound attenuators, to avoid adverse
fixed noise impact.
4.5.3.5
For the Middle Ventilation Building, the nearest NSR in
the vicinity are Harvest Garden (TMS01) and Kam Fai Garden (TMS02), and noise exceedance maybe
anticipated without the adoption of noise mitigation measures. The separation distances
from these NSRs are approximately 150m from Harvest Garden
(TMS01) and approximately 95m from Kam Fai Garden
(TMS02). All the mitigation measures as
discussed for the Lam Tei area would also be applicable. Nevertheless, the Detailed Designer /
Contractor of the Ventilation Building shall orient the major louvres towards
the natural terrain and away from nearby NSRs as far as practicable.
4.5.3.6
For Southern Ventilation Building, Administrative
Building and Maintenance Compound at Pillar Point right above the TM–CLKT, as
there is no existing noise sensitive use identified within 300m assessment area
from these areas. Hence, adverse fixed noise impact due to Southern Ventilation
Building is not anticipated.
4.5.3.7
For the Recovery Area at Pillar Point, it is retention area for vehicle
that is not suitable for entering the tunnel, vehicle will leave this area
shortly and no fixed noise sources are identified. There
is no existing noise sensitive use identified within 300m assessment area from
the Recovery Area. Hence, adverse fixed
noise impact due to Recovery Area is not anticipated.
4.5.3.8
For the Training Ground and Supporting Area at Pillar Point, it is spare area for
supporting tunnel operation, there is no planned use currently and hence, no
fixed noise sources are identified. There is no
existing or planned noise sensitive use identified within 300m assessment area
from the Training Ground and Supporting Area. Hence, adverse fixed noise impact due to Training Ground and Supporting
Area is not anticipated.
4.5.3.9
The temporary re-provisioned
carpark will be operated by others, the future operator should ensure their
operation would comply with NCO and the relevant criteria. Adverse noise
impacts from carpark are therefore not anticipated.
4.5.3.10
As the temporary reprovision of EMSD vehicle servicing centre would only last
during the construction of the Project and the permanent reprovision by EMSD
would be completed before the commissioning year for the operation of the
Project. There is no existing NSR in the vicinity of the temporary EMSD vehicle
servicing centre, adverse noise impact from temporary reprovision of EMSD
vehicle servicing centre the is not anticipated.
Consideration of
Cumulative Impacts
4.5.3.11
The project proponent of R11 is
the same as the Project and would implement the equivalent set of noise
mitigation measures as the Project.
Adverse cumulative noise impacts from R11 are therefore not anticipated.
4.5.3.12
The planning studies for the
Underground Quarrying at Lam Tei, Tuen Mun and Development at Lam Tei North East are still on-going and there are no definitive
design information at the time of preparing this EIA. Nevertheless, it is anticipated that their
studies would consider all committed projects in the vicinity, including but
not limited to Project during their subsequent study. As any other studies by government, it is
anticipated that they will also implement all the best practices and
recommended mitigation measures to abate noise impacts where practicable. On this basis, adverse cumulative noise
impacts from these projects are therefore not anticipated.
4.5.4
Mitigation of Fixed Noise
Sources Impact
4.5.4.1
Possible mitigation measures
with reference to EPD’s “Good Practices on Ventilation System Noise Control”
could be considered the fixed noise sources and confirmed with the Engineer,
for examples:
· Quieter equipment;
· Silencer;
· Barrier; and
· Enclosure, etc.
4.5.4.2
The detailed design should
incorporate the following good practice in order to minimize the nuisance on
the neighboring NSRs. In case the Contractor would
change the design and locations of the vents, they would need to comply with
the legislative impacts at the receivers.
· Louvres should be orientated away from adjacent
NSRs, preferably onto main roads which are less sensitive.
· The façade for these ventilation shafts should have
adequate sound insulation properties to minimise the noise emanating through
the building fabric.
4.5.5
Fixed Noise Source Management Plan
4.5.5.1
As set out in Appendix C Clause
4.1.2 and 4.6 of the EIA SB, a Fixed Noise Source Management Plan (FNMP)
containing the quantitative fixed noise sources impact assessment, noise
mitigation measures and fixed noise sources impact monitoring and audit
programme will be submitted to the EPD with reference to the updated and
identified plant inventories and utilization schedule once available and in any
case before tendering and commencement of implementation of the Project. If
there is any change to the specifications of the planned fixed noise sources,
layout design, operation modes, mitigation measures, or any other factors that
would have implications on the fixed noise sources impact as concluded in the
FNMP, an updated FNMP shall be submitted to the EPD no later than one month
before the implementation of any such change.
4.5.5.2
A summary of key steps for
quantitative fixed noise sources noise assessment will be conducted is:
· Determine the assessment area from Project Road and
highway / tunnel operation and maintenance facilities;
· Update representative NSRs that may be affected by
the noise sources;
· Review and update the noise criteria for both
daytime and nighttime if necessary;
· Use standard acoustic principle for attenuation and
directivity;
· Adopt correction of tonality, impulsiveness and
intermittency as stipulated in IND–TM;
· Calculate the noise impacts using the latest or the
most updated plant inventories and utilisation schedule, if available; and
· Cumulative impacts shall be included.
4.5.5.3
The FNMP will include an
implementation schedule clearly listing out the mitigation measures, the
implementation party, location and timing of
implementation. Mitigation measures recommended and requirement specified in
the FNMP shall be fully implemented by the Contactor.
4.5.6
Evaluation of Residual Fixed
Noise Sources Impact
4.5.6.1
Fixed noise sources impact
arising from the Project will be within respective criteria. Adverse residual
noise impacts are thus not anticipated.
4.5.6.2
The number of dwellings,
classrooms and other sensitive elements that will be exposed to adverse
residual noise impact exceeding the criteria set in Annex 5 in the TM is nil.
4.6
Environmental Monitoring and Audit
4.6.1
Construction Noise
4.6.1.1
Noise monitoring should be
carried out as part of the Environmental Monitoring and Audit (EM&A)
programme for the construction phase of the Project to check compliance with
the construction noise criteria. A CNMP should evaluate the potential
construction noise impacts and to assess the effectiveness and practicality of
all proposed noise mitigation measures. The CNMP would be prepared with
reference to section 8 and Annex 21 of the EIAO-TM as well as this EIA report
and EM&A manual and submitted before tendering and commencement of
construction works. The implementation of the mitigation measures recommended
in CNMP should also be audited as part of the EM&A programme. Details of
the EM&A requirements are provided in the EM&A Manual.
4.6.2
Road Traffic Noise
4.6.2.1
As there is
no noise mitigation measures proposed under the Project, hence, no monitoring
is required for road traffic noise.
4.6.3
Fixed Noise Source Impact
4.6.3.1
A FNMP should evaluate the
potential fixed noise sources impacts and to assess the effectiveness and
practicality of all proposed noise mitigation measures. The FNMP would be
prepared with reference to section 8 and Annex 21 of the EIAO-TM as well as
this EIA report and EM&A manual and submitted before tendering and
commencement of implementation of the Project. Fixed noise audit should be
carried out for the proposed fixed noise sources during the testing and
commissioning stage to verify the compliance of the EIAO–TM criteria.
4.7
Conclusion
4.7.1
Construction Noise
4.7.1.1
An assessment on construction
noise has been conducted according to the requirements in the EIA SB. Results indicated that, with the adoption of
proposed noise mitigation measures, including the use of QPME, use of quieter
construction method, use of noise barrier / enclosure, etc, adverse noise
impact arising from construction works of the Project is not anticipated.
Nevertheless, a CNMP, which contains a quantitative construction noise impact
assessment, mitigation measures and monitoring and audit programme, should be
submitted before tendering and commencement of construction works.
4.7.2
Road Traffic Noise
4.7.2.1
A road traffic noise assessment
has been conducted according to the requirements in EIA SB. Mitigation measures
are not required within the Project Road extent to fulfill
the respective requirements.
4.7.3
Fixed Noise Source Impact
4.7.3.1
An assessment on fixed noise
sources has been conducted according to the requirements in EIA SB. With the
adoption of proposed noise mitigation measures, including the use of quieter
equipment, silencer, barrier, enclosure, etc, adverse noise impact arising from
fixed noise sources is not anticipated.
Nevertheless, a FNMP, which contains a quantitative fixed noise sources
impact assessment, mitigation measures and monitoring and audit programme,
should be submitted before tendering and commencement of implementation of the
Project.