TABLE OF CONTENTS

EXECUTIVE SUMMARY

A) Introduction

B) Environmental Monitoring Works

C) Environmental Licensing and Permitting

D) Complaints and Prosecutions

E) Future Key Issues

1.   INTRODUCTION

Background

Project Organizations

Construction Programme

Summary of EM&A Requirements

2.   AIR QUALITY

Monitoring Requirements

Monitoring Locations

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedures

Results and Observations

3. NOISE

Monitoring Requirements

Monitoring Locations

Monitoring Equipment

Monitoring Parameters, Frequency and Duration

Monitoring Methodology and QA/QC Procedures

Maintenance and Calibration

Results and Observations

4. WATER QUALITY

Monitoring Requirements

Monitoring Equipment

Monitoring Parameters, Frequencies and Durations

Monitoring Locations

Monitoring Methodology, Calibration Details and QA/QC Procedures

Results and Observations

5.   ENVIRONMENTAL AUDIT

Site Audits

Review of Environmental Monitoring Procedures

Status of Environmental Licensing and Permitting

Status of Waste Management

Implementation Status of Weekly Site Audit and Mitigation Measures

Summary of Exceedances of the Environmental Quality Performance Limit

Implementation Status of Event Action Plans

Summary of Complaints and Prosecutions

Environmental Meeting

6.   FUTURE KEY ISSUES

Key Issues for the Coming Month

Monitoring Schedule for the Next Month

7.   CONCLUSIONS AND RECOMMENDATIONS

Conclusions

Recommendations

 

LIST OF TABLES

 

Table 1.1  Key Project Contacts

Table 2.1  Locations for Air Quality Monitoring Station

Table 2.2  Air Quality Monitoring Equipment

Table 2.3  Impact Dust Monitoring Parameters, Frequency and Duration

Table 3.1  Noise Monitoring Stations

Table 3.2  Noise Monitoring Equipment

Table 3.3  Noise Monitoring Parameters, Frequency and Duration

Table 4.1  Water Quality Monitoring Equipment

Table 4.2  Water Quality Monitoring Parameters and Frequency

Table 4.3  Location for Impact Water Quality Monitoring Stations

Table 5.1  Summary of Environmental Licensing and Permit Status

 

LIST OF FIGURES

 

Figure 1.1 Site Layout Plan

Figure 1.2 Project Organization Chart

Figure 2.1 Impact Air Quality Monitoring Locations

Figure 3.1 Impact Noise Monitoring Locations

Figure 4.1 Impact Water Quality Monitoring Locations

 

LIST OF APPENDICES

 

A             Action and Limit Levels for Air Quality and Noise and Compliance Levels for Water Quality

B              Copies of Renewed Calibration Certificates for the Reporting Month

C             Environmental Monitoring Schedules

D             1-hour TSP Monitoring Results and Graphical Presentations

E              24-hour TSP Monitoring Results and Graphical Presentations

F              Noise Monitoring Results and Graphical Presentations

G             Wind Data

H             Water Monitoring Results and Graphical Presentations

I               Site Audit Summary

J               Summary of Exceedances

K             Amount of Waste Generated

L              Not used

M             Complaint Log

N             Extracted Minutes for Environmental Meetings

 

ABBREVIATION AND ACRONYM

 

 

AL Levels Action and Limit Levels

DSD        Drainage Services Department

E / ER      Engineer/Engineer’s Representative

EIA          Environmental Impact Assessment

EM&A     Environmental Monitoring and Audit

EMIS       Environmental Mitigation Implementation Schedule

EP            Environmental Permit

FEP         Further Environmental Permit

EPD         Environmental Protection Department

ET            Environmental Team

HVS        High Volume Sampler

IEC          Independent Environmental Checker

RH           Relative Humidity

TSP         Total Suspended Particulates

QA/QC    Quality Assurance / Quality Control

SLM        Sound Level Meter

WMP       Waste Management Plan