5.1 Legislations,
Standards, Guidelines and Criteria
5.3 Representative
Water Sensitive Receivers
5.4 Approaches
to Avoid and Minimise Hydrodynamic and Water Quality ectioImpacts
5.5 Identification
and Evaluation of Water Quality Impacts for Construction Phase – Land Based
Works
5.7 Identification
and Evaluation of Water Quality Impacts for Operational Phase
5.8 Cumulative
Impacts from Concurrent Projects
5.9 Recommended
Mitigation Measures – Construction Phase (Marine Based Works)
5.10 Recommended
Enhancement Measures – Construction Phase (Marine Works)
5.11 Recommended
Mitigation Measures – Construction Phase (Land Based Works)
5.12 Recommended
Mitigation Measures – Operational Phase
5.14 Environmental
Monitoring and Audit (EM&A)
Tables
Table
5.1 WQOs
for North Western, Western Buffer and Deep Bay WCZs
Table 5.2 Potential Polluting Sources and Water Sensitive Uses
Table 5.3 WSD's Target values of Sea Water Quality at Intake Point of Salt
Water Pumping Stations
Table 5.4 Proposed Assessment Criteria for Heavy Metal and Trace Organics at WSRs
Table 5.5 Summary of EPD's Routine Marine Water Quality Data for North Western
and Western Buffer WCZs in 2021
Table 5.6 Summary of EPD's Routine Marine Water Quality data for Tuen Mun Typhoon Shelter in 2021
Table 5.7 Summary of EPD's Routine Marine Sediment Quality Data for Pearl Island in 2021
Table 5.8 Pore Water Test Results
Table 5.9 Elutriate Test Results
Table 5.10 Summary of EPD's Routine River Water Quality Data for Tuen Mun River and Pai Min Kok Stream in 2021
Table 5.11 Wet Season Water Quality Sampling Results for Stream at So Kwun Wat
Village, Streat at Siu Lam and Tai Lam Chung River
Table 5.12 Dry Season Water Quality Sampling Results for Stream at So Kwun Wat
Village, Stream at Siu Lam and Tai Lam Chung River
Table 5.13 Annual geometric mean E. coli levels for Beaches of Tuen Mun District (Years 2012 to 2022)
Table 5.14 Annual geometric mean E. coli levels for Beaches of Tsuen Wan District (Years 2012 to 2022)
Table 5.15 Summary of Identified Representative WSRs
Table 5.16 Summary of Construction Methods for Different Alignment Sections
Table 5.17 Construction Elements Required for Construction Works
Table 5.18 Water Quality Model Observation Points
Table 5.19 Ambient SS levels from EPD Monitoring Station (1986-2021)
Table 5.20 Observation Points and Adopted Suspended Solids Criteria
Table 5.21 Ambient DO Levels from EPD Monitoring Stations (1986-2021)
Table 5.22 Criteria for DO Depletion
Table 5.23 SS Criteria for Observation Points
Table 5.24 Maximum SS Elevation for Scenario WQ01a
Table 5.25 Maximum SS Elevation for Scenario WQ01b
Table 5.26 Maximum SS Elevation for Scenario WQ02a
Table 5.27 Maximum SS Elevation for Scenario WQ02b
Table 5.28 Sedimentation Rate at Coral Habitats (g/m2/day)
Table 5.29 Maximum DO Depletion for Scenario WQ01a
Table 5.30 Maximum DO Depletion for Scenario WQ01b
Table 5.31 Maximum DO Depletion for Scenario WQ02a
Table 5.32 Maximum DO Depletion for Scenario WQ02b
Table 5.33 Estimated Contaminant Concentration at Observation Points in Western
Buffer WCZ from Elutriate Tests
Table 5.34 Estimated Contaminant Concentration at Observation Points in North
Western WCZ from Elutriate Tests
Table 5.35 Estimated Contaminant Concentration at Observation Points in Western Buffer WCZ from Pore Water Tests
Table 5.36 Estimated Contaminant Concentration at Observation Points in North Western WCZ from Pore Water Tests
Table 5.37 Comparison of Instantaneous Discharge Results at Concerned Channels
Table 5.38 Comparison of Ebb/Flood Tidal Flow Volume at Concerned Channels
Table 5.39 Comparison of Cumulative Discharge Results at Concerned Channels
Table 5.40 Comparison of Depth Averaged Velocity at Concerned Channels
Figures
Figure 5.1 Locations of Water Sensitive Receivers
Appendices
Appendix 5.1 Pore Water / Elutriate Results
Appendix 5.2 River Monitoring Results
Appendix 5.3 Reclamation Construction Sequences
Appendix 5.4 Hydrodynamic Modelling Methodology
Appendix 5.5 Hydrodynamic Validation Methodology and Results
Appendix 5.6 Water Quality Modelling Methodology
Appendix 5.7 Construction Phase Water Quality Modelling Results
Appendix 5.8 Hydrodynamic Modelling Results
Appendix 5.9 Concurrent Projects and Potential Cumulative Water Quality Impacts
Appendix 5.10 Conditions for Working within Water Gathering Grounds
5.1 Legislations, Standards, Guidelines and Criteria
5.1.1.1 The relevant legislations, standards, guidelines and criteria applicable to this Study for the assessment of water quality impacts include:
· Environmental Impact Assessment Ordinance (EIAO) (Cap. 499);
· Water Pollution Control Ordinance (WPCO) (Cap. 358);
· Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS);
· Hong Kong Planning Standards and Guidelines (HKPSG);
· ProPECC PN 1/94 “Construction Site Drainage”;
· ProPECC PN 5/93 “Drainage Plans Subject to Comment by the Environmental Protection Department”;
· Environment, Transport and Works Bureau (ETWB) Technical Circular (Works) No. 5/2005: Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction Works;
· Water Supplies Department’s (WSD) Target Values of Sea Water Quality for Flushing Supply at Intake Point of Salt Water Pumping Station; and
· Assessment Criteria for Heavy Metals and Trace Organics.
5.1.2 Environmental Impact Assessment Ordinance (EIAO) (Cap. 499)
5.1.2.1 EIAO (Cap. 499) provides the major statutory framework for the Environmental Impact Assessment (EIA) in Hong Kong. Under Section 16 of the EIAO, EPD issued the Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM) which specifies the assessment methods and criteria for EIA process. Annexes 6 and 14 of the EIAO-TM stipulate the “Criteria for Evaluating Water Pollution” and “Guidelines for Assessment of Water Pollution” respectively.
5.1.3 Water Pollution Control Ordinance (WPCO) (Cap. 358)
5.1.3.1 WPCO (Cap. 358) provides the major statutory framework for the protection and control of water quality in Hong Kong. According to the Ordinance and its subsidiary legislation, the entire Hong Kong waters are divided into ten Water Control Zones (WCZs) and four supplementary WCZs. Each WCZ has a designated set of statutory Water Quality Objectives (WQOs). The WQOs set limits for different parameters that should be achieved in order to protect specific beneficial uses and conservation goals of each of the zones.
5.1.3.2 The Project is situated within North Western, Western Buffer, and Deep Bay WCZs, the water quality objectives for both WCZs are summarized in Table 5.1.
Table 5.1 WQOs for North Western, Western Buffer and Deep Bay WCZs
Water Quality Objectives (WQO) |
North Western WCZ |
Western Buffer WCZ |
Deep Bay WCZ |
Aesthetic Appearance |
|||
·
Tarry residues, floating
wood, articles made of glass, plastic, rubber or any other substances should
be absent. ·
Mineral oil should not be
visible on the surface. Surfactants should not give rise to a lasting foam. ·
There should be no
recognisable sewage-derived debris. ·
Floating, submerged and
semi-submerged objects of a size likely to interfere with the free movement
of vessels, or cause damage to vessels, should be absent. |
Whole
Zone |
Whole
Zone |
Whole
Zone |
·
Waste discharges shall
cause no objectionable odours or discolouration of the water. ·
Waste discharges shall
not cause the water to contain substances which settle to form objectionable
deposits. |
Whole
Zone |
N/A |
Whole
Zone |
·
There should be no
objectionable odours or discoloration of the water. ·
The water should not
contain substances which settle to form objectionable deposits. |
N/A |
Whole
Zone |
N/A |
Bacteria |
|||
·
The level of Escherichia
coli should not exceed 610 per 100mL, calculated as the geometric mean of
all samples collected in a calendar year. |
Secondary
Contact Recreation Subzones |
Secondary
Contact Recreation Subzone & Fish Culture Zones |
Secondary
Contact Recreation Subzone and Mariculture Subzone (L.N. 455 of 1991) |
·
The level of Escherichia
coli should not exceed 180 per 100 mL, calculated as the geometric mean
of all samples collected from March to October inclusive. Samples should be
taken at least 3 times in one calendar month at intervals of between 3 and 14
days. |
Bathing
Beach Subzones |
Recreation
Subzone |
Yung
Long Bathing beach Subzone (L.N. 455 of 1991) |
·
The level of Escherichia
coli should be less than 1 per 100 mL, calculated as the geometric mean
of the most recent 5 consecutive samples taken at intervals of between 7 and
21 days. |
N/A |
Water
Gathering Ground Subzones |
N/A |
·
The level of Escherichia
coli should be less than 1 per 100 mL, calculated as the running median
of the most recent 5 consecutive samples taken at intervals of between 7 and
21 days. |
Tuen
Mun (A) and Tuen Mun (B) Subzones and Water Gathering Ground Subzones |
N/A |
N/A |
·
The level of Escherichia coli should not exceed
1,000 per 100 mL, calculated as the running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days. |
Tuen Mun (C) Subzone and
other inland waters |
Other Inland Waters |
Yuen Long & Kam Tin
(Lower) Subzone and other inland waters |
·
The level of Escherichia coli should be
zero per 100 mL, calculated as the running median of the most recent 5
consecutive samples taken at intervals of between 7 and 21 days. |
N/A |
N/A |
Yuen Long & Kam Tin
(Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water
Gathering Ground Subzones |
Colour |
|||
·
Waste discharges shall not cause the colour of
water to exceed 30 Hazen units. |
Tuen Mun (A) and Tuen Mun
(B) Subzones and Water Gathering Ground Subzones |
N/A |
Yuen
Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone, Ganges
Subzone and Water Gathering Ground |
·
Waste discharges shall not cause the colour of
water to exceed 50 Hazen units. |
Tuen Mun (C) Subzone and
other inland waters |
N/A |
Yuen
Long & Kam Tin (Lower) Subzone and other inland waters |
·
Human activity should not cause the colour of
water to exceed 30 Hazen units. |
N/A |
Water Gathering Ground
Subzones |
N/A |
·
Human activity should not cause the colour of
water to exceed 50 Hazen units. |
N/A |
Other Inland Waters |
N/A |
Dissolved Oxygen |
|||
·
Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 mg/L for 90% of the sampling occasions
during the year; values should be calculated as the water column average
(arithmetic mean of at least 3 measurements at 1 metre below surface,
mid-depth, and 1 metre above seabed). In addition, the concentration of
dissolved oxygen should not be less than 2 mg/L within 2 metres of the seabed
for 90% of the sampling occasions during the year. |
Marine Waters |
N/A |
N/A |
·
Waste discharges shall not cause the level of dissolved
oxygen to fall below 4 mg/L for 90% of the sampling occasions during the
year; values should be calculated as the water column average (arithmetic
mean of at least 2 measurements at 1 metre below surface and 1 metre above
seabed). In addition, the concentration of dissolved oxygen should not be
less than 2 milligrams per litre within 2 metres of the seabed for 90% of the
sampling occasions during the year. |
N/A |
N/A |
Outer
Marine Subzone excepting Mariculture Subzone |
·
Waste discharges shall not cause the level of
dissolved oxygen to be less than 4 mg/L. |
Tuen Mun (A), Tuen Mun
(B) and Tuen Mun (C) Subzones, Water Gathering Ground Subzones and other
inland waters |
N/A |
Yuen
Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone,
Ganges Subzone, Water Gathering Ground Subzones and other inland waters of
the Zone |
·
The dissolved oxygen level should not be less
than 5 mg/L for 90% of the sampling occasions during the year; values should
be calculated as water column average (arithmetic mean of at least 3
measurements at 1 metre below surface, mid-depth and 1 metre above seabed).
In addition, the concentration of dissolved oxygen should not be less than 2
mg/L within 2 metres of the seabed for 90% of the sampling occasions during
the year. |
N/A |
Fish Culture Subzones |
N/A |
·
The level of dissolved oxygen should not fall
below 4 mg/L for 90% of the sampling occasions during the whole year; values should
be calculated as the annual water column average (arithmetic mean of at least
3 measurements at 1 metre below surface, mid-depth and 1 metre above seaed).
In addition, the concentration of dissolved oxygen should not be less than 2
mg/L within 2 metres of the seabed for 90% of the sampling occasions during
the whole year. |
N/A |
Marine
Waters Except Fish Culture Subzones |
N/A |
·
The level of dissolved oxygen should not be less
than 4 mg/L. |
N/A |
Water
Gathering Ground Subzones and Other Inland Waters |
N/A |
·
Waste discharges shall not cause the level of
dissolved oxygen to fall below 4 mg/L for 90% of the sampling occasions
during the year; values should be taken at 1 metre below surface. |
N/A |
N/A |
Inner
Marine Subzone excepting Mariculture Subzone |
·
The dissolved oxygen level should not be less
than 5 mg/L for 90% of the sampling occasions during the year; values should
be taken at 1 metre below surface. |
N/A |
N/A |
Mariculture
Subzone |
pH |
|||
·
The pH of the water should be within the range of
6.5-8.5 units. In addition, waste discharges shall not cause the natural pH
range to be extended by more than 0.2 units. |
Marine Waters excepting
Bathing Beach Subzones |
N/A |
Marine
waters excepting Yung Long Bathing Beach Subzone |
·
The pH of the water should be within the range of
6.0-9.0 units. |
Other Inland Waters |
N/A |
Other Inland Waters |
·
The pH of the water should be within the range of
6.0-9.0 units for 95% of samples. In addition, waste discharges shall not
cause the natural pH range to be extended by more than 0.5 units. |
Bathing Beach Subzones |
N/A |
Yung
Long Bathing Beach Subzone |
·
Waste discharges shall not cause the pH of the
water to exceed the range of 6.5–8.5 units. |
Tuen Mun (A), Tuen Mun
(B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones |
N/A |
Yuen
Long & Kam Tin (Upper and Lower) Subzones, Beas Subzone, Indus Subzone,
Ganges Subzone, Water Gathering Ground Subzones |
·
The pH of the water should be within the range of
6.5-8.5 units. In addition, human activity should not cause the natural pH
range to be extended by more than 0.2 unit. |
N/A |
Marine Waters |
N/A |
·
Human activity should not cause the pH of the water
to exceed the range of 6.0-9.0 units. |
N/A |
Other inland waters |
N/A |
·
Human activity should not cause the pH of the
water to exceed the range of 6.5-8.5 units. |
N/A |
Water Gathering Ground
Subzones |
N/A |
Temperatures |
|||
·
Waste discharges shall not cause the natural
daily temperature range to change by more than 2.0°C. |
Whole Zone |
N/A |
Whole Zone |
·
Human activity should not cause the natural daily
temperature range to change by more than 2.0ºC. |
N/A |
Whole Zone |
N/A |
Salinity |
|||
·
Waste Discharges shall not cause the natural
ambient salinity level to change by more than 10%. |
Whole Zone |
N/A |
Whole Zone |
·
Human activity shall not cause the natural
ambient salinity level to change by more than 10%. |
N/A |
Whole
Zone |
N/A |
Suspended Solids |
|||
·
Waste discharges shall neither cause the natural
ambient level to be raised by 30% nor give rise to accumulation of suspended
solids which may adversely affect aquatic communities. |
Marine Waters |
N/A |
Marine Waters |
·
Waste discharges shall not cause the annual
median of suspended solids to exceed 20 mg/L. |
Tuen Mun (A), Tuen Mun
(B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones |
N/A |
Yuen Long & Kam Tin
(Upper and Lower) Subzones, Beas Subzone, Indus Subzone, Ganges Subzone,
Water Gathering Ground Subzones and other inland waters |
·
Waste discharges shall not cause the annual
median of suspended solids to exceed 25 mg/L. |
Other Inland Waters |
N/A |
N/A |
·
Human activity should neither cause the natural
ambient level to be raised by more than 30% nor give rise to accumulation of
suspended solids which may adversely affect aquatic communities. |
N/A |
Marine Waters |
N/A |
·
Human activity should not cause the annual median
of suspended solids to exceed 20 mg/L. |
N/A |
Water Gathering Ground
Subzones |
N/A |
·
Human activity should not cause the annual median
of suspended solids to exceed 25 mg/L. |
N/A |
Other Inland Waters |
N/A |
Ammonia |
|||
·
The un-ionised ammoniacal nitrogen level should
not be more than 0.021 mg/L calculated as the annual average (arithmetic
mean). |
Whole Zone |
Whole Zone |
Whole Zone |
Nutrients |
|||
·
Nutrients shall not be present in quantities
sufficient to cause excessive or nuisance growth of algae or other aquatic
plants. |
Marine Waters |
Marine Waters |
Inner and Outer marine
Subzones |
·
Without limiting the generality of objective (a) above,
the level of inorganic nitrogen should not exceed 0.3 mg/L, expressed as
annual water column average (arithmetic mean of at least 3 measurements at 1
metre below surface, mid-depth and 1 metre above seabed). |
Castle Peak Bay Subzone |
N/A |
N/A |
·
Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 mg/L, expressed
as annual water column average (arithmetic mean of at least 3 measurements at
1 metre below surface, mid-depth and 1 metre above seabed). |
Marine Waters excepting
Castle Peak Bay Subzone |
N/A |
N/A |
·
Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.5 mg/L, expressed
as annual water column average (arithmetic mean of at least 2 measurements at
1 metre below surface and 1 metre above seabed). |
N/A |
N/A |
Outer Marine Subzone |
·
Without limiting the generality of objective (a) above,
the level of inorganic nitrogen should not exceed 0.4 mg/L, expressed as
annual water column average (arithmetic mean of at least 3 measurements at 1
metre below surface, mid-depth and 1 metre above seabed). |
N/A |
Marine Waters |
N/A |
·
Without limiting the generality of objective (a)
above, the level of inorganic nitrogen should not exceed 0.7 mg/L, expressed
as annual mean. |
N/A |
N/A |
Inner Marine Subzone |
5-Day Biochemical Oxygen Demand |
|||
·
Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 3 mg/L. |
Tuen Mun (A), Tuen Mun
(B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones |
N/A |
Yuen Long & Kam Tin (Upper) Subzone, Beas Subzone, Indus Subzone,
Ganges Subzone and Water Gathering Ground |
·
Waste discharges shall not cause the 5-day
biochemical oxygen demand to exceed 5 mg/L. |
Other Inland Waters |
N/A |
Yuen Long & Kam Tin
(Lower) Subzone and other inland waters |
·
The 5-day biochemical oxygen demand should not exceed
3 mg/L. |
N/A |
Water Gathering Ground
Subzones |
N/A |
·
The 5-day biochemical oxygen demand should not
exceed 5 mg/L. |
N/A |
Other Inland Waters |
N/A |
Chemical Oxygen Demand |
|||
·
Waste discharges shall not cause the chemical
oxygen demand to exceed 15 mg/L. |
Tuen Mun (A), Tuen Mun
(B) and Tuen Mun (C) Subzones and Water Gathering Ground Subzones |
N/A |
Yuen Long & Kam Tin
(Upper) Subzone, Beas Subzone, Indus Subzone, Ganges Subzone and Water
Gathering Ground Subzones |
·
Waste discharges shall not cause the chemical
oxygen demand to exceed 30 mg/L. |
Other Inland Waters |
N/A |
Yuen Long & Kam Tin
(Lower) Subzone and other inland waters |
·
The chemical oxygen demand should not exceed 15
mg/L. |
N/A |
Water Gathering Ground Subzones |
N/A |
·
The chemical oxygen demand should not exceed 30
mg/L. |
N/A |
Other Inland Waters |
N/A |
Toxins |
|||
·
Waste discharges shall not cause the toxins in water
to attain such levels as to produce significant toxic carcinogenic, mutagenic
or teratogenic effects in humans, fish or any other aquatic organisms, with
due regard to biologically cumulative effects in food chains and to toxicant
interactions with each other. ·
Waste discharges shall not cause a risk to any
beneficial use of the aquatic environment. |
Whole Zone |
N/A |
Whole Zone |
·
Toxic substances in the water should not attain
such levels as to produce significant toxic, carcinogenic, mutagenic or
teratogenic effects in humans, fish or any other aquatic organisms, with due
regard to biologically cumulative effects in food chains and to interactions
of toxic substances with each other. ·
Human activity should not cause a risk to any
beneficial use of the aquatic environment. |
N/A |
Whole Zone |
N/A |
Phenol |
|||
·
Phenols shall not be present in such quantities
as to produce a specific odour, or in concentration greater than 0.05 mg/L as
C6H5OH. |
Bathing Beach Subzones |
N/A |
Yung Long Bathing Beach
Subzone |
Turbidity / Light Penetration |
|||
·
Waste discharges shall not reduce light
transmission substantially from the normal level. |
Bathing Beach Subzones |
Bathing Beach Subzones |
Yung Long Bathing Beach
Subzone |
5.1.4 Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters (TM-DSS)
5.1.4.1 Under Section 21 of the WPCO (Cap. 358), TM-DSS was issued to control the physical, chemical, and microbial quality of effluent discharges into foul sewers, stormwater drains, inland and coastal waters. Specific limits apply for different areas and are different between surface waters and sewers, and the limits vary with the rate of effluent flow. Under the TM-DSS, any effluents discharged from the Project must comply with pollutant concentration standards defined by EPD and are specified in license conditions for any new discharge.
5.1.5 Hong Kong Planning Standards and Guidelines (HKPSG)
5.1.5.1 Chapter 9 of HKPSG outlines the environmental requirements that need to be considered in land use planning. The recommended guidelines, standards and guidance cover the selection of suitable locations for the developments and provision of environmental facilities, design, layout, phasing, and operational controls to minimise adverse environmental impact. It lists out environmental factors influencing land use planning and recommends buffer distances for land uses.
5.1.5.2 Section 5 under Chapter 9 of HKPSG provides broad guidelines on water quality which includes the principal framework for planning against water pollution. The overall objectives for planning against water pollution are:
· Achieving and maintaining the quality of inland waters, coastal waters, marine waters and groundwaters so that they can be used for their legitimate purposes;
· Providing adequate public sewerage, wastewater treatment and disposal facilities for all wastewaters; and
· Putting in place and enforce water pollution control legislation aimed at safeguarding the health and welfare of the community.
5.1.5.3 With reference to the aforementioned part of HKPSG, a list of potentially polluting and sensitive uses is summarized below in Table 5.2.
Table 5.2 Potential Polluting Sources and Water Sensitive Uses
Potential Polluting Sources |
Water Sensitive Uses |
· Industry and agriculture (including livestock
keeping and slaughterhouses); · Sewage disposal (including sewage from private
residential developments); · Civil engineering works (including all building
works, well boring, ground investigation, dredging, reclamation, excavation
of fill, man-made lagoons etc.); and · Transport facilities. |
· Bathing beaches; · Aquaculture and fisheries; · Agriculture; · Residential and recreational development; · Typhoon shelters, marinas and boat parks; · Water gathering grounds; · Nature reserves; · Sites of Special scientific Interest; · Marine parks/marine reserves; · Coastal protection areas; · Conservation areas; and · Fish spawning grounds. |
5.1.6 ProPECC PN 1/94: “Construction Site Drainage”
5.1.6.1 Professional Persons Environmental Consultative Committee Practice Note (ProPECC PN) 1/94 on construction site drainage provides guidelines for the handling and disposal of construction discharges. This note is applicable for the control of site run-off and wastewater generated during the construction phase of the Project.
5.1.6.2 The types of discharges from construction sites outlined in the ProPECC PN 1/94 include:
· Surface run-off;
· Groundwater;
· Boring and drilling water;
· Wastewater from concrete batching and precast concrete casting;
· Wheel washing water;
· Water for testing and sterilisation of water retaining structures and water pipes;
· Wastewater from building construction;
· Acid cleaning, etching, and pickling wastewater; and
· Wastewater from site facilities.
5.1.7 ProPECC PN 5/93: “Drainage Plans subject to Comment by the Environmental Protection Department”
5.1.7.1 ProPECC PN 5/93 issued by EPD provides guidelines on the environmental design and pollution control in drainage plans submitted under Building (standards of Sanitary Fitments, Plumbing, Drainage Work and Latrines) Regulations 40(1), 40(2), 41(1), and 90. Any submitted drainage plans submitted shall be referred to EPD for comment on whether there may be concerns regarding pollution control.
5.1.8 Environment, Transp ort and Works Bureau (ETWB) Technical Circular (Works) No. 5/2005: “Protection of Natural Streams/Rivers from Adverse Impacts Arising from Construction Works”
5.1.8.1 The ETWB TC (W) No. 5/2005 provides a framework to better protect all natural streams/rivers from the adverse impacts of construction works. The procedures promulgated under the Circular aims to clarify and strengthen existing measures for protection of natural streams/rivers from both government and private projects/developments. The guidelines and precautionary mitigation measures given in the Circular should be followed to the best of abilities to protect inland watercourses at or near the Project area during the construction phase.
5.1.9 Water Supplies Department’s (WSD) Target Values of Sea Water Quality for Flushing Supply at Intake Point of Salt Water Pumping Station
5.1.9.1 The criteria for assessing the water quality impact on the WSD’s seawater intakes are based on the Target Values of Sea Water Quality for Flushing Supply at Intake Point of Salt Water Pumping Station (at intake point) issued by the WSD and are summarized under Table 5.3.
Table 5.3 WSD's Target values of Sea Water Quality at Intake Point of Salt Water Pumping Stations
Target Value |
|
Colour |
< 20 Hazen Unit |
Turbidity |
< 10 Nephelometric Turbidity unit (N.T.U.) |
Threshold Odour No. |
< 100 odour unit |
Ammoniacal Nitrogen |
< 1 mg/l |
Suspended Solids |
< 10 mg/l |
Dissolved Oxygen |
> 2 mg/l |
Biochemical Oxygen Demand |
< 10 mg/l |
Synthetic Detergents |
< 5 mg/l |
E. coli |
< 20,000 cfu/100 ml |
5.1.10 Assessment Criteria for Heavy Metals and Trace Organics
5.1.10.1 There are no existing legislations or guidelines for heavy metals, metalloids, trace organics (i.e. polycyclic aromatic hydrocarbons (PAH) and polychlorinated biphenyls (PCB)), and organotin (i.e. tributyltin (TBT) at water sensitive receivers (WSRs) in Hong Kong waters. According to the common practices in previous EIA studies, conservative criteria were set out by comparing different countries standards such as USA, Australia, and New Zealand. The lowest values from various international standards have been adopted as the assessment criteria. The adopted criteria for heavy metals and trace organics are presented in Table 5.4.
Table 5.4 Proposed Assessment Criteria for Heavy Metal and Trace Organics at WSRs
Heavy Metal/Metalloids/Trace
Organics |
Proposed
Criteria (µg/L) |
Reference |
Arsenic |
13 |
1 |
Cadmium |
5.5 |
1 |
Chromium |
4.4 |
1 |
Copper |
1.3 |
1 |
Lead |
4.4 |
1 |
Mercury |
0.4 |
1 |
Nickel |
70 |
1 |
Silver |
1.4 |
1 |
Zinc |
8 |
1 |
Total PAHs |
0.2 |
2 |
PCBs |
0.03 |
2 |
TBT |
0.006 |
2 |
References:
[1] Australian Department of
Agriculture, Water and the Environment, Australian and New Zealand Guidelines
for Fresh and Marine Water Quality (2019). For chromium, the more stringent
standard (i.e. chromium(VI)) was adopted.
For arsenic, since there was no standard for marine water, the more
stringent standard for freshwater (i.e. arsenic(V)) was adopted.
[2] U.S. Environmental Protection Agency,
National Recommended Water Quality Criteria (2009). The Criteria Continuous
Concentration (CCC) is an estimate of the highest concentration of a material
in surface marine water to which an aquatic community can be exposed
indefinitely without resulting in an unacceptable effect, and was hence adopted
as the criteria.
5.2.1.1 The marine water within the assessment area (see Section 5.3) of the Project includes North Western and Western Buffer WCZs. The marine water of Deep Bay WCZ is not at the vicinity of the Project’s alignment and work sites.
5.2.1.2 North Western WCZ is located at the western side of Hong Kong and covers the waters around the North and Western side of Lantau Island, Tuen Mun, Sha Chau, and Lung Kwu Chau. According to EPD’s Marine Water Quality of Hong Kong 2021 report, the overall WQO compliance rate of the North Western WCZ was 89% in year 2021. The Dissolved Oxygen (DO) and ammonia-nitrogen (NH3-N) WQOs were fully met. However, for Total Inorganic Nitrogen (TIN), the WQO was 67% under the influence of high background levels in the Pearl River Estuary. For the past 5 years, the WQO compliance rate has fluctuated, and there was an increase from 72% in Years 2017, to 89% in Years 2018 and 2019, before declining to 67% in 2020, and eventually rising back to 89% in 2021.
5.2.1.3 Western Buffer WCZ is located at the central areas of Hong Kong, and covers the waters around Tsing Lung Tau (TLT), Tsing Yi towards the north, and Ap Lei Chau towards the south. The Western Buffer WCZ fully achieved the WQOs in 2021, since the commissioning of the Harbour Area Treatment Scheme Advance Disinfection Facilities (HATS ADF) in 2021, the E. coli levels in the WCZ decreased substantially by about 90%.
5.2.1.4 The water quality monitoring data from monitoring stations NM1, NM2 of North Western WCZ, and WM4 of Western Buffer WCZ in 2021 is presented in Table 5.5 below.
Table 5.5 Summary of EPD's Routine Marine Water Quality Data for North Western and Western Buffer WCZs in 2021
North
Western WCZ1,2,3,4,5,6 |
Western
Buffer WCZ1,2,3,4,5,6 |
|||
NM1 |
NM2 |
WM4 |
||
Temperature (°C) |
24.5 |
24.8 |
24.4 |
|
(19.3 - 26.8) |
(19.5 - 27.9) |
(19.8 - 28.4) |
||
Salinity (ppt) |
30.6 |
29.3 |
31.5 |
|
(27.1 - 33.5) |
(22.9 - 33.5) |
(29.1 - 33.5) |
||
Dissolved Oxygen (mg/L) |
Depth Averaged |
4.8 |
4.9 |
4.6 |
(3.5 - 6.3) |
(4.1 - 5.7) |
(3.6 - 5.6) |
||
Bottom |
4.2 |
4.9 |
4.2 |
|
(2.2 - 6.3) |
(3.3 - 6.7) |
(2.4 - 6.0) |
||
Dissolved Oxygen (% Saturation) |
Depth Averaged |
67 |
70 |
65 |
(51 - 83) |
(59 - 82) |
(52 - 81) |
||
Bottom |
59 |
69 |
60 |
|
(31 - 85) |
(47 - 90) |
(35 - 84) |
||
pH |
7.5 |
7.5 |
7.5 |
|
(7.2 - 7.9) |
(7.2 - 7.9) |
(7.2 - 7.9) |
||
Secchi Disc Depth (m) |
2.8 |
2.3 |
2.5 |
|
(1.5 - 5.2) |
(1.7 - 3.5) |
(1.6 - 4.4) |
||
Turbidity (NTU) |
6.5 |
6.0 |
6.5 |
|
(3.0 - 11.5) |
(2.9 - 11.5) |
(3.7 - 11.3) |
||
Suspended Solids (mg/L) |
6.1 |
4.9 |
6.5 |
|
(1.6 - 12.8) |
(1.6 - 9.4) |
(1.9 - 11.4) |
||
5-day Biochemical Oxygen Demand (mg/L) |
1 |
1.3 |
0.8 |
|
(0.2 - 2.8) |
(0.2 - 4.9) |
(0.3 - 1.5) |
||
Ammonia Nitrogen (mg/L) |
0.100 |
0.090 |
0.122 |
|
(0.041 -
0.173) |
(0.038 -
0.167) |
(0.056 -
0.210) |
||
Unionised Ammonia (mg/L) |
0.001 |
0.001 |
0.002 |
|
(<0.001 -
0.003) |
(<0.001 -
0.003) |
(<0.001 -
0.007) |
||
Nitrite Nitrogen (mg/L) |
0.053 |
0.063 |
0.043 |
|
(0.003 -
0.108) |
(0.004 -
0.117) |
(0.006 -
0.084) |
||
Nitrate Nitrogen (mg/L) |
0.216 |
0.280 |
0.177 |
|
(0.051 -
0.477) |
(0.047 -
0.617) |
(0.073 -
0.393) |
||
Total Inorganic Nitrogen (mg/L) |
0.37 |
0.43 |
0.34 |
|
(0.20 - 0.64) |
(0.21 - 0.76) |
(0.23 - 0.53) |
||
Total Kjeldahl Nitrogen (mg/L) |
0.69 |
0.61 |
0.60 |
|
(0.43 - 0.96) |
(0.35 - 0.95) |
(0.34 - 0.89) |
||
Total Nitrogen (mg/L) |
0.83 |
0.78 |
0.75 |
|
(0.63 - 1.09) |
(0.59 - 1.11) |
(0.46 - 1.16) |
||
Orthophosphate Phosphorous (mg/L) |
0.014 |
0.014 |
0.016 |
|
(0.007 -
0.026) |
(0.003 -
0.027) |
(0.003 -
0.027) |
||
Total Phosphorous (mg/L) |
0.05 |
0.06 |
0.09 |
|
(0.04 - 0.08) |
(0.04 - 0.09) |
(0.05 - 0.14) |
||
Silica (as SiO2) (mg/L) |
1.07 |
1.29 |
1.05 |
|
(0.34 - 1.80) |
(0.34 - 2.10) |
(0.40 - 2.13) |
||
Chlorophyll-a (µg/L) |
4.2 |
4.8 |
3.9 |
|
(0.4 - 12.5) |
(0.8 - 15.5) |
(0.8 - 13.3) |
||
E. coli (count/100mL) |
95 |
31 |
230 |
|
(8 - 590) |
(6 - 350) |
(16 – 7,800) |
||
Faecal Coliforms (count/100mL) |
170 |
59 |
450 |
|
(18 - 910) |
(14 - 610) |
(31 – 17,000) |
[1] Data presented are annual arithmetic means
of the depth-averaged results except for E. coli and faecal coliforms which are
annual geometric means.
[2] Data in brackets indicate the ranges.
[3] NM indicates no measurement taken.
[4] Values at or below laboratory reporting
limits are presented as laboratory reporting limits.
[5] Equal values for annual medians (or
geometric means) and range indicates that all data are the same as or below
laboratory reporting limits.
[6] Unless specified otherwise, data presented
are depth-averaged value which are calculated by taking the means of three
depths (i.e. surface, mid-depth, and bottom).
5.2.2.1 Tuen Mun Typhoon Shelter is located at Tuen Mun South and at the mouth of Tuen Mun River, which is at the vicinity of the Project’s assessment area. There are no bacteriological WQOs for typhoon shelters as their beneficial use are primarily for vessel mooring, hence the concerned parameters for typhoon shelter water quality are mainly DO and NH3-N. All 2 parameters have met the WQO in 2021, in general the long-term trend shows an improvement of water quality in Tun Mun Typhoon Shelter.
5.2.2.2 The water quality monitoring data from monitoring stations NT1 of Tuen Mun Typhoon Shelter is presented in Table 5.6 below.
Table 5.6 Summary of EPD's Routine Marine Water Quality data for Tuen Mun Typhoon Shelter in 2021
Parameters |
Tuen Mun Typhoon Shelter1,2,3 |
|
NT1 |
||
Temperature (°C) |
26.2 |
|
(20.6 - 29.1) |
||
Salinity (ppt) |
26.1 |
|
(20.4 - 31.8) |
||
Dissolved Oxygen (mg/L) |
Depth Averaged |
4.8 |
(4.2 – 5.8) |
||
Bottom Layer |
4.7 |
|
(4.0 - 5.2) |
||
Dissolved Oxygen (%
Saturation) |
Depth Averaged |
69 |
(58 - 83) |
||
Bottom Layer |
67 |
|
(56 - 75) |
||
pH |
7.5 |
|
(7.1 - 7.6) |
||
Secchi Disc Depth (m) |
1.7 |
|
(1.4 - 2.4) |
||
Turbidity (NTU) |
6.9 |
|
(4.9 - 12.2) |
||
Suspended Solids (mg/L) |
7.1 |
|
(3.2 - 10.1) |
||
5-day Biochemical Oxygen
Demand (mg/L) |
0.9 |
|
(0.5 - 1.3) |
||
Ammonia Nitrogen (mg/L) |
0.098 |
|
(0.036 - 0.200) |
||
Unionised Ammonia (mg/L) |
0.001 |
|
(<0.001 - 0.003) |
||
Nitrite Nitrogen (mg/L) |
0.053 |
|
(0.019 - 0.073) |
||
Nitrate Nitrogen (mg/L) |
0.330 |
|
(0.143 - 0.635) |
||
Total Inorganic Nitrogen
(mg/L) |
0.48 |
|
(0.25 - 0.74) |
||
Total Kjeldahl Nitrogen
(mg/L) |
0.63 |
|
(0.58 - 0.68) |
||
Total Nitrogen (mg/L) |
0.83 |
|
(0.81 - 0.84) |
||
Orthophosphate
Phosphorous (mg/L) |
0.011 |
|
(0.005 - 0.021) |
||
Total Phosphorous (mg/L) |
0.08 |
|
(0.06 - 0.09) |
||
Silica (as SiO2)
(mg/L) |
1.25 |
|
(0.63 - 1.95) |
||
Chlorophyll-a (µg/L) |
7.0 |
|
(0.8 - 19.5) |
||
E. coli (count/100mL) |
33 |
|
(8 - 220) |
||
Faecal Coliforms
(count/100mL) |
210 |
|
(42 - 990) |
Notes:
[1] Data presented
are annual arithmetic means of the depth-averaged results except for E. coli
and faecal coliforms which are annual geometric means.
[2] Data in
brackets indicate the ranges.
[3] Unless
specified otherwise, data presented are depth-averaged value which are
calculated by taking the means of three depths (i.e. surface, mid-depth, and
bottom).
EPD Sediment Monitoring Stations
5.2.3.1 As discussed in Section 2, dredging/filling works associated with the reclamation would be required. The disturbed sediment during dredging / filling may release pollutants that may cause water quality impacts at WSRs. Hence, baseline sediment quality information was collated from EPD’s latest marine water quality report published in 2021, and additional pore water and elutriate tests were conducted on sediment samples collected near the reclamation area.
5.2.3.2 The sediment quality at the nearest EPD sediment quality monitoring station (i.e. Pearl Island (NS2) of North Western WCZ at 2021 is presented in Table 5.7. The sediment quality at NS2 is good as concentrations of all parameters did not exceed the Lower Chemical Exceedance Level (LCEL) presented under Appendix A of the Management Framework for Disposal of Dredged/Excavated Sediment (PNAP 252 ADV-21) published by Buildings Department.
Table 5.7 Summary of EPD's Routine
Marine Sediment Quality Data for Pearl Island in 2021
Parameters |
North Western WCZ1,2,3,4,5,6 |
NS2 |
|
Particle Size
Fractionation <63µm (%w/w) |
65 |
(20 – 97) |
|
Electrochemical Potential
(mV) |
-125 |
(-170 - -59) |
|
Total Solids (%w/w) |
51 |
(39 – 63) |
|
Total Volatile Solids
(%TS) |
6.5 |
(4.8 – 7.8) |
|
Chemical Oxygen Demand
(mg/kg) |
11,520 |
(9,200 – 13,000) |
|
Total Carbon (%w/w) |
0.6 |
(0.5 – 1.0) |
|
Ammonical Nitrogen
(mg/kg) |
5.27 |
(0.23 – 11.00) |
|
Total Kjeldahl Nitrogen
(mg/kg) |
440 |
(280 – 540) |
|
Total Phosphorous (mg/kg) |
220 |
(170 – 280) |
|
Total Sulphide (mg/kg) |
32.4 |
(2.5 – 77.0) |
|
Total Cyanide (mg/kg) |
0.1 |
(<0.1 – 0.2) |
|
Arsenic (mg/kg) |
12.0 |
(7.7 – 23.0) |
|
Cadmium (mg/kg) |
0.1 |
(<0.1 – 0.1) |
|
Chromium (mg/kg) |
34 |
(21 – 53) |
|
Copper (mg/kg) |
33 |
(17 – 48) |
|
Lead (mg/kg) |
46 |
(29 – 90) |
|
Mercury (mg/kg) |
0.10 |
(0.06 – 0.14) |
|
Nickel (mg/kg) |
20 |
(13 - 31) |
|
Silver (mg/kg) |
0.2 |
(<0.2 – 0.3) |
|
Zinc (mg/kg) |
150 |
(79 – 220) |
|
Total Polychlorinated Biphenyls
(PCBs) (µg/kg) |
18 |
(18 – 18) |
|
Low Molecular Weight
Polycyclic Aromatic Hydrocarbons (PAHs) (µg/kg) |
110 |
(90 – 150) |
|
High Molecular Weight
Polycyclic Aromatic Hydrocarbons (PAHs) (µg/kg) |
69 |
(40 – 110) |
Notes:
[1] Data presented
are arithmetic means; data in brackets indicate ranges.
[2] All data are based on the analyses of bulk (unsieved sediment
and are reported on a dry weight basis unless stated otherwise.
[3] Total PCBs results are derived from the summation of 18 congeners.
If the concentration of a congener is below report limit (RL), the result will
be taken as 0.5xRL in the calculation.
[4] Low molecular weight polyaromatic hydrocarbons (PAHs) include 6
congeners of molecular weight below 200, namely: Acenaphthene, Acenaphthylene,
Anthracene, Flourene, Naphthalene and Phenanthrene.
[5] High molecular weight polyaromatic hydrocarbons (PAHs) include
10 congeners of molecular weight above 200, namely: Fluoranthene, Pyrene,
Benzo(a)anthracene, Chrysene, Benzo(b)fluoranthene, Benzo(k)fluoranthene,
Benzo(a)pyrene, Dibenzo(a,h)anthracene, Benzo(g,h,i)perylene and
Indeno(1,2,3-cd)pyrene.
[6] Low and high molecular weight PAHs results are derived from the summation of the corresponding congeners. If the concentration of a congener is below RL, the result will be taken as 0.5xRL in the calculation.
Pore Water and Elutriate Test
Results
5.2.3.3 Sediment samples were collected at 2 sampling locations at the proposed reclamation site at TLT on 26th and 27th September 2022. Pore water and elutriate tests were conducted for the following parameters:
· Heavy metals and metalloids including cadmium, chromium, copper, mercury, nickel, lead, zinc, silver, and arsenic;
· Organic micropollutants including PAHs and PCBs; and
· Inorganic non-metallic pollutants including nitrogen and phosphorous.
5.2.3.4 The maximum value of pore water and elutriate test results of each sampling location are summarised in Table 5.8 and Table 5.9 respectively, with detailed results and sampling locations presented in Appendix 5.1.
Table 5.8 Pore
Water Test Results
Parameter |
Proposed Criteria |
Units |
Sample ID[3] |
Criteria
Compliance |
|
TLB/VB1 |
TLB/VB3 |
||||
Heavy
Metals/Metalloids |
|||||
Arsenic |
13 |
µg/L |
6 |
7 |
✔ |
Cadmium |
5.5 |
µg/L |
<0.2 |
<0.2 |
✔ |
Chromium |
4.4 |
µg/L |
<1.0 |
<1.0 |
✔ |
Copper |
1.3 |
µg/L |
1.1 |
2.1 |
✔ |
Lead |
4.4 |
µg/L |
<1.0 |
<1.0 |
✔ |
Mercury |
0.4 |
µg/L |
<0.05 |
<0.05 |
✔ |
Nickel |
70 |
µg/L |
2 |
3 |
✔ |
Silver |
1.4 |
µg/L |
<1.0 |
<1.0 |
✔ |
Zinc |
8 |
µg/L |
1 |
2 |
✔ |
Inorganic
Non-Metallic Pollutants |
|||||
TKN |
- |
mg/L |
15 |
14 |
✔ |
NH3-N |
- |
mg/L |
13 |
10 |
✔ |
NO2-N |
- |
mg/L |
<0.01 |
<0.01 |
✔ |
NO3-N |
- |
mg/L |
0.2 |
0.1 |
✔ |
TIN[1] |
0.4 or 0.5 |
mg/L |
12.7 |
9.7 |
To be further
assessed[4] |
UIA[2] |
0.021 |
mg/L |
0.555 |
0.427 |
To be further
assessed[4] |
Reactive-P |
- |
mg/L |
<0.01 |
<0.01 |
✔ |
Ortho-P |
- |
mg/L |
0.3 |
0.4 |
✔ |
Total-P |
- |
mg/L |
0.3 |
0.4 |
✔ |
PCBs/PAHs/TBT |
|||||
Total
PAHs |
0.2 |
µg/L |
<9.0 |
<9.0 |
To be further
assessed[4] |
PCBs |
0.03 |
µg/L |
<0.18 |
<0.18 |
To be further
assessed[4] |
TBT |
0.006 |
µg/L |
<0.015 |
<0.015 |
To be further
assessed[4] |
Notes:
[1] TIN is
calculated by summation of NO2-N, NO3-N and NH3-N.
The proposed criteria for TIN is dependent on the location of the WSR (i.e.
0.4mg/L for Western Buffer WCZ and 0.5mg/L for North Western WCZ.)
[2] UIA is estimated by multiplying a conversion factor of 4.44% to
NH3-N. This factor is dependent on
water temperature and pH (i.e. 25.4°C and 7.9) at the nearest EPD
water quality monitoring station (i.e. NM1), the conversion factor referenced
“Aqueous Ammonia Equilibrium- Tabulation of Percent Unionized Ammonia”
(Thurston, 1979).
[3] Sampled values that are below the lowest detection limit are
presented as the lowest detection limit, bold values indicate an exceedance of
the criteria.
[4] For pore water test results that exceeded the criteria, the
parameter will be further assessed using quantitative water quality modelling
to determine the criteria compliances at the WSRs.
Table 5.9 Elutriate Test Results
Parameter |
Proposed Criteria [3] |
Units |
Sample ID[4] |
Criteria
Compliance |
|
TLB/VB1 |
TLB/VB3 |
||||
Heavy
Metals/Metalloids |
|||||
Arsenic |
13 |
µg/L |
15 |
6 |
To be further assessed[5] |
Cadmium |
5.5 |
µg/L |
<0.2 |
<0.2 |
✔ |
Chromium |
4.4 |
µg/L |
<1.0 |
<1.0 |
✔ |
Copper |
1.3 |
µg/L |
<1.0 |
1.1 |
✔ |
Lead |
4.4 |
µg/L |
1.0 |
<1.0 |
✔ |
Mercury |
0.4 |
µg/L |
<0.05 |
<0.05 |
✔ |
Nickel |
70 |
µg/L |
1.3 |
1.7 |
✔ |
Silver |
1.4 |
µg/L |
<1.0 |
<1.0 |
✔ |
Zinc |
8 |
µg/L |
131 |
1 |
To be further assessed[5] |
Inorganic
Non-Metallic Pollutants |
|||||
TKN |
- |
mg/L |
2.3 |
14.9 |
✔ |
NH3-N |
- |
mg/L |
1.39 |
12.5 |
✔ |
NO2-N |
- |
mg/L |
0.04 |
<0.01 |
✔ |
NO3-N |
- |
mg/L |
0.18 |
0.19 |
✔ |
TIN[1] |
0.4 or 0.5 |
mg/L |
1.6 |
12.7 |
To be further assessed[5] |
UIA[2] |
0.021 |
mg/L |
0.062 |
0.555 |
To be further assessed[5] |
Reactive-P |
- |
mg/L |
0.04 |
<0.01 |
✔ |
Ortho-P |
- |
mg/L |
0.09 |
0.33 |
✔ |
Total-P |
- |
mg/L |
0.13 |
0.34 |
✔ |
PCBs/PAHs/TBT |
|||||
Total
PAHs |
0.2 |
µg/L |
<9.0 |
<9.0 |
To be further assessed[5] |
PCBs |
0.03 |
µg/L |
<0.18 |
<0.18 |
To be further assessed[5] |
TBT |
0.006 |
µg/L |
<0.015 |
<0.015 |
To be further assessed[5] |
Notes:
[1] TIN is
calculated by summation of NO2-N, NO3-N and NH3-N.
The proposed criteria for TIN is dependent on the location of the WSR (i.e.
0.4mg/L for Western Buffer WCZ and 0.5mg/L for North Western WCZ.)
[2] UIA is estimated by multiplying a conversion factor of 4.44% to
NH3-N. This factor is dependent on
water temperature and pH (i.e. 25.4°C and 7.9) at the nearest EPD
water quality monitoring station (i.e. NM1), the conversion factor referenced
“Aqueous Ammonia Equilibrium- Tabulation of Percent Unionized Ammonia”
(Thurston, 1979).
[3] Reference
for proposed criteria can be referred to the footnotes of Table 5.4.
[4] Sampled values that are below the lowest detection limit are
presented as the lowest detection limit, bold values indicate an exceedance of
the criteria.
[5] For elutriate test results that exceeded the criteria, the
parameter will be further assessed using quantitative water quality modelling
to determine the criteria compliances at the WSRs.
5.2.3.5 As seen from the tables above, the results indicated that for most parameters, the criteria were met. However, for parameters that exceeded the criteria (i.e. arsenic, zinc, TIN, UIA, Total PAHs, PCBs, and TBT), further calculations will be conducted to assess whether their respective concentrations would comply with the criteria at WSRs after dispersion (see Section 5.6.4 for more discussion).
EPD River Monitoring Stations
5.2.4.1 Tuen Mun River is a major river located in the western New Territories, which passes through Lam Tei, San Hing Tsuen and Fu Tei in its upstream section, then through the densely populated Tuen Mun Town in its mid-stream before draining into the Tuen Mun Typhoon Shelter at its mouth. This river has experienced improvement in its water quality over the last three decades, with its WQO compliance rate has risen significantly from from 42% in 1991 to 85% in 2021. Four of the six monitoring stations (i.e. TN3 to TN6) are situated at the middle to lower sections of the river, and maintained a “Good” water quality index (WQI) grading. In 2021, the upstream monitoring station (i.e. TN2) received a “Fair” WQI grading, while another upstream monitoring station (TN1) was graded “Bad”, mainly due to discharges from unsewered rural areas.
5.2.4.2 Pai Min Kok Stream is located in western New Territories near Sham Tseng, and ultimately discharges into Anglers’ Beach. The stream achieved an overall WQO compliance rate of 98% in 2021, and both EPD monitoring stations (i.e. AN1 and AN2) of the stream maintained an “Excellent” water quality index (WQI) grading.
5.2.4.3 While a portion of the 500m assessment area is within the Deep Bay WCZ near Lam Tei, there are neither major rivers nor inland waterbodies within the assessment area.
5.2.4.4 The water quality monitoring data from monitoring stations TN1 and TN2 of Tuen Mun River, and AN1 and AN2 of Pai Min Kok Stream in 2021 is presented in Table 5.10 below.
Table 5.10 Summary of EPD's Routine River Water Quality Data for Tuen Mun River and Pai Min Kok Stream in 2021
Parameters |
Tuen Mun River1,2,3,4,5 |
Pai Min Kok Stream1,2,3,4,5 |
||
TN1 |
TN2 |
AN1 |
AN2 |
|
Dissolved Oxygen (mg/L) |
4.4 |
8.0 |
8.2 |
8.6 |
(2.0 - 5.9) |
(4.3 - 12.9) |
(7.6 - 9.4) |
(7.7 - 9.9) |
|
pH |
7.6 |
7.9 |
8.1 |
8.5 |
(7.4 - 8.2) |
(7.2 - 9.2) |
(7.8 - 8.6) |
(7.7 - 9.6) |
|
Suspended Solids (mg/L) |
11.0 |
7.6 |
2.4 |
5.8 |
(3.0 - 16.0) |
(3.3 – 6,600.0) |
(0.9 - 26.0) |
(1.2 - 83.0) |
|
5-Day Biochemical Oxygen
Demand (mg/L) |
24.0 |
3.9 |
1.4 |
0.6 |
(11.0 - 47.0) |
(2.4 - 66.0) |
(0.4 - 2.3) |
(0.2 - 2.2) |
|
Chemical Oxygen Demand
(mg/L) |
32 |
15 |
10 |
8 |
(20 - 54) |
(6 - 100) |
(4 - 20) |
(4 - 19) |
|
Oil & Grease (mg/L) |
0.6 |
<0.5 |
<0.5 |
<0.5 |
(<0.5 - 1.4) |
(<0.5 - 2.0) |
(<0.5 - <0.5) |
(<0.5 - <0.5) |
|
E. coli (counts/100mL) |
100,000 |
190,000 |
4,800 |
14,000 |
(44,000 – 230,000) |
(49,000 – 1,400,00) |
(1,200 – 34,000) |
(430 – 85,000) |
|
Faecal Coliforms
(counts/100mL) |
340,000 |
290,000 |
29,000 |
25,000 |
(130,000 – 990,000) |
(75,000 – 2,000,000) |
(13,000 – 120,000) |
(6,300 – 89,000) |
|
Ammonia Nitrogen (mg/L) |
6.900 |
2.100 |
0.057 |
0.026 |
(5.400 - 9.700) |
(1.200 - 7.800) |
(0.024 - 0.250) |
(0.015 - 0.062) |
|
Nitrate Nitrogen (mg/L) |
0.280 |
1.100 |
0.825 |
0.150 |
(<0.002 - 0.710) |
(0.011 - 7.000) |
(0.320 - 1.500) |
(0.008 - 0.390) |
|
Total Kjeldahl Nitrogen
(mg/L) |
11.50 |
9.00 |
0.76 |
0.46 |
(8.60 - 13.00) |
(3.50 - 11.00) |
(0.65 - 0.88) |
(0.34 - 0.78) |
|
Orthophosphate
Phosphorous (mg/L) |
0.520 |
0.260 |
0.043 |
0.029 |
(0.400 - 0.600) |
(0.140 - 0.780) |
(0.012 - 0.055) |
(0.015 - 0.290) |
|
Total Phosphorous (mg/L) |
0.94 |
0.86 |
0.08 |
0.08 |
(0.69 - 1.00) |
(0.39 - 0.96) |
(0.06 - 0.12) |
(0.03 - 0.12) |
|
Sulphide (mg/L) |
0.03 |
<0.02 |
<0.02 |
<0.02 |
(<0.02 - 0.05) |
(<0.02 - 0.03) |
(<0.02 - 0.02) |
(<0.02 - <0.02) |
|
Aluminium (µg/L) |
<50 |
<50 |
<50 |
54 |
(<50 - 442) |
(<50 - 140) |
(<50 - 155) |
(<50 - 158) |
|
Cadmium (µg/L) |
<0.1 |
<0.1 |
<0.1 |
<0.1 |
(<0.1 - <0.1) |
(<0.1 - <0.1) |
(<0.1 - <0.1) |
(<0.1 - <0.1) |
|
Chromium (µg/L) |
<1 |
<1 |
<1 |
<1 |
(<1 - 1) |
(<1 - 3) |
(<1 - <1) |
(<1 - <1) |
|
Copper (µg/L) |
1 |
2 |
3 |
2 |
(<1 - 2) |
(<1 - 7) |
(<1 - 5) |
(<1 - 4) |
|
Lead (µg/L) |
<1 |
<1 |
<1 |
<1 |
(<1 - <1) |
(<1 - 2) |
(<1 - <1) |
(<1 - 2) |
|
Zinc (µg/L) |
<10 |
<10 |
<10 |
<10 |
(<10 - 36) |
(<10 - 46) |
(<10 - 19) |
(<10 - 14) |
|
Flow (m³/s) |
0.138 |
0.017 |
NM[3] |
0.003 |
(0.072 - 0.328) |
(0.006 - 0.059) |
(0.000 - 0.023) |
Notes:
[1] Data
presented are annual arithmetic means of the depth-averaged results except for E.
coli and faecal coliforms which are annual geometric means.
[2] Data in
brackets indicate the ranges.
[3] NM
indicates no measurement taken.
[4] Values at
or below laboratory reporting limits are presented as laboratory reporting
limits.
[5] Equal
values for annual medians (or geometric means) and range indicates that all
data are the same as or below laboratory reporting limits.
Additional Inland Water Quality Sampling at So Kwun Wat, Siu Lam and
Tai Lam Chung
5.2.4.5 There are no EPD inland water quality monitoring stations at the vicinity of So Kwun Wat, Siu Lam, and Tai Lam Chung areas to establish the baseline conditions of the inland waters of these areas. Hence, additional water quality samplings were conducted under this EIA to supplement the inland water quality information for both wet season (i.e. between April 2022 and October 2022) and dry season (i.e. between November 2022 and March 2023). Samplings were conducted at a frequency of 3 sampling days per week over a 2 week period (i.e. 6 sampling days in total), at the locations as indicated in Appendix 5.2.
5.2.4.6 The water quality parameters that were measured and sampled were the same as those used by EPD’s river monitoring stations. In addition, other relevant data (i.e. monitoring location, time, weather conditions, river conditions, etc.) were also recorded. The samples were then analysed at a Hong Kong Laboratory Accreditation Scheme (HOKLAS) accredited laboratory. The water quality sampling results for wet season and dry season at Stream at So Kwun Wat Village, Stream at Siu Lam, and Tai Lam Chung River are summarised in Table 5.11 and Table 5.12 respectively. In-situ monitoring records and laboratory analysis results are also presented in Appendix 5.2.
Table 5.11 Wet Season Water Quality Sampling Results for Stream at So Kwun Wat Village, Streat at Siu Lam and Tai Lam Chung River
Parameters |
Wet Season1,2,3,4,5 |
||
Stream at So Kwun Wat Village (R1) |
Stream at Siu Lam (R2) |
Tai Lam Chung River (R3) |
|
Dissolved Oxygen (mg/L) |
6.9 (5.6 - 7.5) |
7.5 (7.3 - 7.7) |
5.0 (4.8 - 5.6) |
pH |
9.2 (8.1 – 10.0) |
9.4 (7.9 - 10.4) |
8.3 (6.0 – 9.0) |
Suspended Solids (mg/L) |
18.7 (2.0 - 48.5) |
1.9 (0.6 - 5.1) |
5.2 (1.8 – 9.0) |
5-Day Biochemical Oxygen
Demand (mg/L) |
1.5 (<0.1 - 4.5) |
0.6 (<0.1 - 1.1) |
0.6 (<0.1 - 1.1) |
Chemical Oxygen Demand
(mg/L) |
10 (6 - 14) |
6 (<2 - 8) |
25 (20 - 40) |
Oil & Grease (mg/L) |
0.5 (<0.5 - 0.6) |
0.5 (<0.5 - 0.6) |
0.5 (<0.5 - 0.6) |
E. coli (counts/100mL) |
120,561 (330 – 510,000) |
396 (80 - 890) |
421 (80 – 1,000) |
Faecal Coliforms
(counts/100mL) |
274,875 (1,100 – 1,200,000) |
873 (190 – 1,300) |
720 (200 – 1,800) |
Ammonia Nitrogen (mg/L) |
0.660 (<0.005 - 2.580) |
0.010 (<0.005 - 0.016) |
0.150 (0.128 - 0.188) |
Nitrate Nitrogen (mg/L) |
0.137 (0.035 - 0.375) |
0.175 (0.074 - 0.231) |
0.356 (0.238 - 0.475) |
Total Kjeldahl Nitrogen
(mg/L) |
0.84 (0.10 - 3.06) |
0.10 (0.08 - 0.15) |
0.37 (0.31 - 0.49) |
Orthophosphate
Phosphorous (mg/L) |
0.024 (<0.001 - 0.044) |
0.013 (<0.001 - 0.021) |
0.066 (0.047 - 0.083) |
Total Phosphorous (mg/L) |
0.09 (0.04 - 0.28) |
0.03 (0.02 - 0.04) |
0.09 (0.06 - 0.11) |
Sulphide (mg/L) |
<0.05 (<0.05 - <0.05) |
<0.05 (<0.05 - <0.05) |
<0.05 (<0.05 - <0.05) |
Aluminium (µg/L) |
280 (75 - 656) |
93 (63 - 152) |
69 (23 - 165) |
Cadmium (µg/L) |
<0.1 (<0.1 - 0.1) |
<0.1 (<0.1 - 0.1) |
<0.1 (<0.1 -<0.1) |
Chromium (µg/L) |
<1.0 (<1.0 - <1.0) |
<1.0 (<1.0 - <1.0) |
<1.0 (<1.0 - <1.0) |
Copper (µg/L) |
1.3 (<1.0 - 2.3) |
1.7 (<1.0 - 5.9) |
2.0 (<1.0 – 6.0) |
Lead (µg/L) |
2.3 (<1.0 - 4.5) |
<1.0 (<1.0 - <1.0) |
<1.0 (<1.0 - <1.0) |
Zinc (µg/L) |
40 (13 - 150) |
12 (<10 - 15) |
31 (<10 - 119) |
Flow (m³/s) |
0.1 (0.1 - 0.1) |
0.2 (0.1 - 0.2) |
0.2 (0.1 - 0.3) |
Notes
[1] Data source:
Inland water sampling conducted in October 2022 for wet season.
[2] Data
presented are annual arithmetic means of the depth-averaged results except for
E. coli and faecal coliforms which are annual geometric means.
[3] Data in
brackets indicate the ranges.
[4] Values at
or below laboratory reporting limits are presented as laboratory reporting
limits.
[5] The
sampling period was conducted over 2 weeks, with 3 sampling days for each week,
hence, there are a total of 6 sampling days for each season.
Table 5.12 Dry Season Water Quality Sampling Results for Stream at So Kwun Wat Village, Stream at Siu Lam and Tai Lam Chung River
Parameters |
Dry Season1,2,3,4,5 |
||
Stream at So Kwun Wat Village (R1) |
Stream at Siu Lam (R2) |
Tai Lam Chung River (R3) |
|
Dissolved Oxygen (mg/L) |
7.8 (7.38 – 8.3) |
8.5 (8.0 – 9.2) |
6.7 (5.3 - 8.0) |
pH |
8.0 (7.38 - 8.42) |
8.5 (7.6 - 9.1) |
7.8 (7.4 - 8.3) |
Suspended Solids (mg/L) |
74.1 (33 - 126) |
20.7 (4.1 - 41.4) |
5.7 (4.5 - 8.0) |
5-Day Biochemical Oxygen
Demand (mg/L) |
1.8 (1.5 - 2.4) |
1.0 (0.7 - 1.3) |
1.3 (0.7 - 3.5) |
Chemical Oxygen Demand
(mg/L) |
27 (20 - 38) |
10 (9 - 14) |
20 (13 - 26) |
Oil & Grease (mg/L) |
0.5 (<0.5 - 0.6) |
0.6 (<0.5 - 0.8) |
0.5 (<0.5 - 0.7) |
E. coli (counts/100mL) |
1100 (0 - 4100) |
127 (8 - 590) |
267 (34 - 1600) |
Faecal Coliforms
(counts/100mL) |
1357 (0 - 4100) |
142 (14 - 590) |
700 (52 - 4600) |
Ammonia Nitrogen (mg/L) |
0.13 (0.01 - 0.24) |
0.05 (0.03 - 0.10) |
0.18 (0.14 - 0.34) |
Nitrate Nitrogen (mg/L) |
0.178 (0.128 - 0.264) |
0.252 (0.157 -
0.556) |
0.35 (0.20 - 0.47) |
Total Kjeldahl Nitrogen
(mg/L) |
0.56 (0.17 - 0.85) |
0.28 (0.07 - 0.53) |
0.49 (0.38 - 0.80) |
Orthophosphate
Phosphorous (mg/L) |
0.023 (0.016 - 0.030) |
0.019 (0.013 - 0.030) |
0.06 (0.036 - 0.118) |
Total Phosphorous (mg/L) |
0.26 (0.03 - 0.43) |
0.07 (0.02 - 0.13) |
0.10 (0.06 - 0.14) |
Sulphide (mg/L) |
<0.05 (<0.05 - <0.05) |
<0.05 (<0.05 -
<0.05) |
<0.05 (<0.05 - <0.05) |
Aluminium (µg/L) |
1063 (595 - 1630) |
446 (103 - 1040) |
74 (40 - 102) |
Cadmium (µg/L) |
0.1 (<0.1 - 0.2) |
0.1 (<0.1 -
0.4) |
<0.1 (<0.1 -<0.1) |
Chromium (µg/L) |
1.0 (<1.0 - 1.1) |
1.0 (<1.0 -
1.3) |
1.1 (<1.0 - 2.0) |
Copper (µg/L) |
2.6 (1.8 - 4.4) |
3.2 (<1.0 -
4.2) |
1.5 (1.0 – 3.0) |
Lead (µg/L) |
8.3 (4.2 - 12.5) |
2.3 (1.4 - 6) |
<1.0 (<1.0 - <1.0) |
Zinc (µg/L) |
57 (23 - 128) |
40 (18 - 89) |
104 (<10 - 273) |
Flow (m³/s) |
0.1 (0.1 - 0.1) |
0.1 (0.1 - 0.2) |
0.2 (0.1 - 0.3) |
Notes
[1] Data source:
Inland water sampling conducted in January 2023 for dry season.
[2] Data
presented are annual arithmetic means of the depth-averaged results except for
E. coli and faecal coliforms which are annual geometric means.
[3] Data in brackets
indicate the ranges.
[4] Values at
or below laboratory reporting limits are presented as laboratory reporting
limits.
[5] The
sampling period was conducted over 2 weeks, with 3 sampling days for each week,
hence, there are a total of 6 sampling days for each season.
5.2.4.7 To summarise, with reference to the WQOs of North Western and Western Buffer WCZs stated in Section 5.1.3, the Stream at So Kwun Wat Village (R1) attained a WQO compliance rate of 57%, with parameters pH, E. coli, and NH3-N exceeded the WQOs. Whereas Stream at Siu Lam (R2) and Tai Lam Chung River (R3) both attained a WQO compliance rate of 86%, with pH levels and NH3-N exceeded the WQOs for R2 and R3 respectively. The exceedances of E. coli and NH3-N could be an indication of biomass growth due to high organic loading of the inland waters, which may be attributed to nearby unsewered village houses.
5.2.5.1 Beaches in both Tuen Mun and Tusen Wan Districts are at the vicinity of the assessment area. Summaries of EPD’s routine beach water quality monitoring data for the past decade (i.e. Years 2012 to 2022) are presented in Table 5.13 and Table 5.14.
5.2.5.2 As for the beach water quality monitored in Year 2022, for Tuen Mun District, 2 beaches (i.e. Golden Beach and Cafeteria New Beach) ranked “Good” and 4 beaches (i.e. Cafeteria Old Beach, Kadoorie Beach, Castle Peak Beach and Butterfly Beach) ranked “Fair”. As for Tsuen Wan District, all 8 beaches attained a “Fair” ranking. The water quality monitored at these beaches has seen a gradual improvement over the last decade, currently stable water quality suitable for bathing is observed at these beaches. This can be attributed to the completion of sewerage works in the beach hinterland, and the commissioning of the disinfection facilities of the Harbour Area Treatment Scheme.
Table
5.13 Annual geometric mean E. coli levels for Beaches of
Tuen Mun District (Years 2012 to 2022)
E.
coli counts per 100mL |
|||||||||||
2012 |
2013 |
2014 |
2015 |
2016 |
2017 |
2018 |
2019 |
2020 |
2021 |
2022 |
|
Butterfly |
42 |
71 |
38 |
98 |
131 |
81 |
39 |
91 |
129 |
57 |
50 |
Cafeteria New |
47 |
50 |
31 |
30 |
38 |
31 |
18 |
40 |
37 |
17 |
20 |
Cafeteria Old |
48 |
39 |
45 |
41 |
70 |
50 |
30 |
64 |
53 |
23 |
34 |
Castle Peak |
48 |
78 |
91 |
71 |
106 |
65 |
70 |
128 |
112 |
103 |
162 |
Golden |
62 |
45 |
39 |
31 |
45 |
37 |
22 |
41 |
45 |
19 |
24 |
Kadoorie |
40 |
52 |
37 |
29 |
48 |
31 |
28 |
52 |
55 |
19 |
31 |
Table
5.14 Annual
geometric mean E. coli levels for Beaches of Tsuen Wan District (Years
2012 to 2022)
E.
coli counts per 100mL |
|||||||||||
2012 |
2013 |
2014 |
2015 |
2016 |
2017 |
2018 |
2019 |
2020 |
2021 |
2022 |
|
Anglers' |
69* |
133 |
130 |
77 |
76 |
45 |
143 |
88 |
105 |
135 |
142 |
Approach |
83 |
106 |
121 |
143 |
78 |
114 |
92 |
97 |
133 |
71 |
84 |
Casam |
50 |
71 |
63 |
52 |
42 |
43 |
94 |
79 |
84 |
74 |
109 |
Gemini |
40* |
135* |
110* |
56* |
40* |
39* |
120* |
79* |
101* |
127* |
139* |
Hoi
Mei Wan |
51 |
86 |
58 |
90 |
65 |
63 |
92 |
112 |
84 |
76 |
75 |
Lido |
32 |
53 |
57 |
52 |
39 |
34 |
76 |
65 |
66 |
98 |
111 |
Ma
Wan Tung Wan |
24 |
41 |
31 |
20 |
32 |
29 |
74 |
46 |
84 |
93 |
54 |
Ting
Kau |
88* |
107* |
89 |
151 |
140 |
75 |
101 |
102 |
93 |
85 |
96 |
Note
[1] “*” denotes
Beach not open for swimming that year
5.3 Representative Water Sensitive Receivers
5.3.1.1 The assessment area for the water quality impact assessment shall include areas within 500m from the Project boundary, and shall cover the North Western WCZ and other affected WCZs as stipulated in Clause 3.4.6.2 of EIA Study Brief (ESB-352/2022). The assessment area was extended beyond the 500m assessment area to cover other locations including beaches, water pumping stations, and cooling water intakes, etc., to identify other WSRs that may also be affected by the Project and may have a bearing on the environmental acceptability of the Project. The WSRs are listed in Table 5.15 and shown in Figure 5.1, with the major WSR groupings summarised below:
· Gazetted beaches;
· Corals;
· Horseshoe crabs;
· Mangroves;
· Seagrass beds;
· Cooling water intakes;
· WSD flushing water intakes;
· Typhoon shelters / marinas;
· Marine Park;
· Country Parks;
· Rivers;
· Fish Culture Zone and Fisheries Habitat; and
· Water gathering ground and reservoirs.
Table 5.15 Summary of Identified Representative WSRs
ID |
WSR |
Beaches |
|
B1 |
Castle
Peak Beach |
B2 |
Kadoorie
Beach |
B3 |
Cafeteria
Old Beach |
B4 |
Cafeteria
New Beach |
B5 |
Golden
Beach |
B6 |
Anglers’
Beach |
B7 |
Gemini
Beaches |
B8 |
Hoi
Mei Wan Beach |
B9 |
Casam
Beach |
B10 |
Lido
Beach |
B11 |
Ting Kau Beach |
B12 |
Approach Beach |
B13 |
Ma Wan Tung Wan Beach |
Corals |
|
CR1 |
Corals
at To Kau Wan |
CR2 |
Corals
at Sunny Bay |
Horseshoe
Crabs |
|
H1 |
Horseshoe Crabs Area at Yam
O |
Mangroves |
|
MG1 |
Mangrove near Ma Wan |
MG2 |
Mangrove near Yam O |
Seagrass
Beds |
|
SG2 |
Seagrass Beds near Yam O |
Water
Pumping Stations/Cooling Water Intakes |
|
C1 |
Seawater Intake for Future Sunny
Bay Development |
C2 |
ASD Tuen Mun Hospital |
C3 |
EMSD Sam Shing Estate |
WSD1 |
Tuen Mun Salt Water Pumping Station |
WSD2 |
Salt Water Pumping Station near
Hong Kong Garden |
WSD3 |
Sunny Bay Salt Water Pumping
Station |
WSD4 |
Salt Water Pumping Station
near Lok On Pai |
Typhoon Shelters/Sheltered Anchorages/Marinas |
|
SA1 |
Ting Kau
Sheltered Anchorages |
TS1 |
Tuen Mun Typhoon Shelter |
M1 |
Gold Coast Marina and Country
Club |
Marine Park |
|
MP1 |
The Brothers Marine Park
Indicator Point 1 |
MP2 |
The Brothers Marine Park
Indicator Point 2 |
MP3 |
The Brothers Marine Park
Indicator Point 3 |
MP4 |
The Brothers Marine Park
Indicator Point 4 |
Country Park |
|
CP1 |
Tai Lam Country Park |
Rivers |
|
RIV1 |
Tuen Mun River |
RIV2 |
Tai Lam Chung River |
Fish Culture
Zone and Fisheries Habitat |
|
F1 |
Ma Wan Fish Culture Zone |
F2 |
Spawning ground of commercial
fisheries resources in North Lantau Water |
Water
Gathering Ground and Reservoirs |
|
RSV1 |
Lam Tei Irrigation Reservoir |
RSV2 |
Hung Shui Hang Irrigation
Reservoir |
RSV3
|
Tai Lam Chung Reservoir |
WG1 |
Water Gathering Ground |
5.4 Approaches to Avoid and Minimise Hydrodynamic and Water Quality Impacts
5.4.1.1 As discussed in Section 2, the Project has been proactively designed, and duly examined to reduce both the hydrodynamic and water quality impacts induced by the marine and land based works associated with the Project. A summary of the approaches adopted to avoid and minimise water quality impacts are summarised below.
5.4.2 Avoidance of Aboveground Works within Tai Lam Country Park and Water Gathering Ground
5.4.2.1 As the Project alignment would inevitably go through Tai Lam Country Park (the Country Park), to minimise disturbances towards the Country Park, the latest design proposes to adopt tunnel design at the section of Project alignment crossing the Country Park, which would be constructed using drill-and-blast and drill-and-break methods (D&B). Hence, there would be no aboveground works within the Country Park. By adopting this tunnel design and suitable engineering design during tunnel construction, it would avoid any adverse impacts on the water gathering ground inside and in the vicinity of the Country Park, in addition to minimizing impacts caused to the Country Park.
5.4.3 Avoidance of High Ecological Value Natural Watercourses
5.4.3.1 While the alignment sections within the Country Park would take a tunnel form, there would be at-grade roads and viaducts to connect the tunnel sections that daylight outside the Country Park. The ecological impact assessment conducted has identified few natural watercourses with higher ecological value. These watercourses include those near the Tai Lam Chung Reservoir, it should however be noted that works on natural watercourses within the Country Park would be totally avoided. According to the current design, the alignment sections across these watercourses would be in a viaduct form above or in tunnel from underneath. To avoid any direct impacts on these watercourses, the design of these viaduct sections would ensure that the supports and the associated works areas would totally avoid these watercourses. Nevertheless, suitable mitigation measures would also be provided to ensure that indirect impacts such as surface runoff during construction period would not adversely affect these watercourses.
5.4.4 Avoidance of Reclamation near To Kau Wan at North Lantau
5.4.4.1 The latest alignment of the Project has been designed to reduce both hydrodynamic and water quality impacts by completely avoiding reclamation works at To Kau Wan, North Lantau. When comparing with the preliminary alignment presented in the Project Profile, the latest design adjusted the design of Tsing Lung Bridge so that the southern bridge tower can be setback from offshore to the land, thereby eliminating the need for reclamation works at North Lantau. This decision will further improve the hydrodynamic and water quality conditions of the area. However, reclamation works for the northern anchor at TLT would be inevitable due to site constraints (i.e. Tuen Mun Road and existing buildings, etc.).
5.4.5 Conduct Filling Works Within the Seawall
5.4.5.1 As reclamation is unavoidable at TLT, non-dredged reclamation methods such as deep cement mixing (DCM) has been explored to minimise water quality impacts. However, upon considering all aspects including engineering feasibilities, geological conditions, environmental implications, etc., the presence of a thin marine sediment layer at the reclamation area may inevitably require to be dredged. Besides, according to the current design, filling works will only commence upon the full completion of the perimeter seawall and will only be conducted within the seawall to prevent any fill materials and fine suspended solids from being discharged to the open sea. Nonetheless, the dredging works would inevitably generate suspended solids from the disturbed sediment. Hence, quantitative water quality modelling would be conducted to assess the associated impacts.
5.4.6 Minimisation of Reclamation Area in Tsing Lung Tau
5.4.6.1 In addition to considering different reclamation methods, the design of the northern anchor has also been meticulously considered. The preliminary design presented in the Project Profile stated that the reclamation area above sea level would be approximately 2.7ha. However after scrutinising multiple aspects including engineering and environmental technicalities, the latest proposed design has reduced the reclamation extent by approximately 0.5ha (i.e. from 2.7ha to 2.2ha). This reduction has reduced the total amount of dredged sediments, hence reducing the associated water quality impacts during the construction phase. This would also reduce the extent of narrowing the Ha Pang Fairway, thereby reducing the change in hydrodynamic regime during the operational phase.
5.5 Identification and Evaluation of Water Quality Impacts for Construction Phase – Land Based Works
5.5.1.1 The assessment for evaluating the water quality impacts induced by land-based construction works were conducted according to the assessment methodologies specified in Annexes 6 and 14 of EIAO-TM, and Appendix D of the EIA Study Brief, which includes:
· Identification of impact causing factors; and
· Recommendation of mitigation measures (see Section 5.11).
5.5.2 Summary of Key Construction Activities
5.5.2.1 A review has been conducted on the construction methodologies given in Section 2. A summary of the construction methodologies for various alignment sections are given under Table 5.16 and Table 5.17 below. According to the latest design, D&B tunnelling would be adopted for all tunnel sections.
Table 5.16 Summary of Construction Methods for Different Alignment Sections
Alignment Section |
Construction Method |
·
Lam Tei Quarry Interchange ·
So Kwun Wat Interchange ·
North Lantau Interchange ·
Tsing Lung Tau Interchange ·
So Kwun Wat – Siu Lam Open Road Section |
·
At-grade works |
·
Tai Lam Chung River Viaduct |
·
At-grade works without viaduct piers at the river |
·
Lam Tei Tunnel ·
So Kwun Wat Link Road ·
Tai Lam Chung Tunnel (North Section) ·
Tai Lam Chung Tunnel (South Section) |
·
Drill-and-blast tunnelling ·
Drill-and-break tunnelling |
·
Tsing Lung Bridge |
·
Cross-channel suspension bridge with one anchor
each on the northern and southern shore |
5.5.2.2 Other than construction methods, other construction elements are also associated with the construction phase of the Project:
Table 5.17 Construction Elements Required for Construction Works
Construction Elements |
Location |
Magazine sites for the storage of
explosives (for shared use with the Tuen Mun Bypass
(TMB) project) |
1 no. at Lam Tei 1 no. at Siu Lam 1 no. at Pillar Point |
Barging point |
1 no. at TLT 2 nos. at North Lantau |
Temporary works areas |
5 nos. at So Kwun Wat 1 no. at Tai Lam Chung 1 no. at TLT 2 nos. at North Lantau |
5.5.2.3 The potential water pollution sources associated with the construction of the Project are identified and summarised below:
· Construction run-off and general construction activities;
· Tunnelling and underground works;
· Construction for ventilation buildings and administration buildings;
· Sewage due to construction workforce;
· Construction works in close proximity of inland water;
· Diversion of watercourses;
· Groundwater from contaminated areas and contaminated site run-off;
· Operation of barging point; and
· Accidental spillage of chemicals.
5.5.3 Construction Run-off and General Construction Activities
5.5.3.1 Construction site run-off will be generated from construction activities conducted at work sites and has the potential to cause adverse water quality impacts. The potential water pollution sources from construction site run-offs and construction activities may include:
· Run-off and erosion from site surfaces, earth working areas and stockpiles;
· Accidental release of any concrete washing and other grouting materials associated with construction run-off, stormwater or groundwater dewatering process;
· Wash water from concrete washing, dust suppression sprays, equipment and wheel washing facilities;
· General site cleaning and polishing; and
· Chemical spillage such as fuel, oil, solvents and lubricants from the maintenance of construction machinery and equipment.
5.5.3.2 In addition, during rainstorm events, site run-off would wash away soil particles on unpaved lands and areas with exposed topsoil. Which generally contains high concentrations of SS, meaning the discharge of uncontrolled site run-off would increase the SS levels and turbidity at the nearby water bodies. Uncontrolled site run-off may also contain concrete and cement-derived materials which may increase the turbidity, discoloration and pH levels of nearby waterbodies. The increased turbidity of water bodies decreases the amount of sunlight penetration, hence reducing the rate of faecal bacteria decay and the rate of photosynthesis. However, the adverse impacts could be minimised with the implementation of good construction site practices as described in Section 5.11.
5.5.4 Tunnelling and Underground Works
5.5.4.1 As discussed in Section 5.5.1, the tunnel sections of the Project would be constructed by D&B methods. Section 2 has stated that the majority of the tunnel section would go underneath Tai Lam Country Park, where the underground stratum comprised mainly of granite. The depth of this tunnel section would vary between 43 to 465m below local ground. After considering the latest geological information, D&B tunnelling is considered the most suitable construction methodology for the tunnel sections underneath Tai Lam Country Park.
5.5.4.2 The proposed D&B tunnelling works may result in groundwater infiltration which may increase construction site run-off and lead to potential groundwater table drawdown. Any potential drawdown could result in different degrees of ground settlement and dewatering of surface waterbodies (i.e. Lam Tei Irrigation Reservoir, Hung Shui Hang Irrigation Reservoir, Tai Lam Chung Reservoir and nearby streams), and hence groundwater in the vicinity may also be depleted. SS would also be a key concern as infiltrated water could increase the amount of construction site run-off from the site to nearby drainage systems.
5.5.4.3 However, as the D&B tunnel section would be in the granite stratum and with sufficient depth below ground, together with the good practices and mitigation measures as described in Section 5.11, adverse impacts from the change in groundwater level and SS would be insignificant.
5.5.5 Ventilation Buildings and Administration Buildings
5.5.5.1 As discussed in Section 2, there would be a total of 7 ventilation buildings (1 no. at Lam Tei, 2 nos at Pak Shek Hang, 1 no. at So Kwun Wat, 1 no. at Siu Lam, 1 no. at Tai Lam Chung and 1 no. at TLT) and 2 administration buildings (at Lam Tei and North Lantau) along the entire tunnel section, which are also shown in Figure 5.1. The construction of these ventilation buildings and administration buildings would adopt an open cut excavation method and followed by construction of superstructure and utilities.
5.5.5.2 These buildings are located at the vicinity of waterbodies including Lam Tei Irrigation Reservoir, Tai Lam Chung Reservoir, marine waters, and existing drainage systems outside Tai Lam Country Park, etc. Potential impacts may occur during rainfall events whilst the excavation works are ongoing, as silt and sandy materials carried by run-off from the excavation may enter nearby watercourses, increasing their SS content and turbidity. Other pollutants, such as oil and grease, chemicals, and grouting materials, may also be present in the run-off should it flow over storage or maintenance areas, where it may increase discoloration, turbidity, chemical and pH levels of the nearby water bodies. Additionally, the erosion of soil enriched in organic matter may release excess nutrients into adjacent water bodies, potentially leading to eutrophication.
5.5.5.3 These impacts would require the good practices and mitigation measures as described in Section 5.11 to ensure that any residual impacts would be insignificant.
5.5.6 Sewage due to Construction Workforce
5.5.6.1 Sewage will be generated by sanitary facilities (i.e. chemical toilets) provided for the on-site construction workforce. Sewage is characterized by high levels of BOD5, ammonia and E. coli counts. According to Table T-2 of Guidelines for Estimating Sewage Flows for Sewage Infrastructure Planning (GESF) published by EPD, the unit flow factor (UFF) is 0.23 m3/day/employee (0.08 m3/day/employee for commercial employee and 0.15 m³/day/employee for employees of construction activities).
5.5.6.2 According to the current design, during the peak time of construction works, it is anticipated that there will be a workforce of approximately 4,000 people working on site. Hence, it is estimated that during the peak times, a total sewage load of approximately 920 m3/day will be generated.
5.5.6.3 With these mitigation measures in such as providing adequate chemical toilets as described in Section 5.11 in place, no adverse water quality impacts are anticipated.
5.5.7 Construction Works in Close Proximity of Inland Water
5.5.7.1 Construction activities may pollute nearby inland waterbodies near Lam Tei, Siu Lam, Tai Lam Chung, and TLT (i.e. Tai Lam Chung River, Lam Tei Irrigation Reservoir, Hung Shui Hang Irrigation Reservoir, Tai Lam Chung Reservoir, other streams and water gathering ground) through the potential release of construction wastes, which are generally characterised by high concentration of SS and elevated pH. With the implementation of adequate construction site drainage as specified in the ProPECC PN 1/94 , as well as relevant guideline promulgated by WSD for works within water gathering ground stated in Section 5.11, no adverse water quality impacts are anticipated.
5.5.8 Removal or Diversion of Watercourses
5.5.8.1 Due to engineering constraints and geological conditions, it is unavoidable that the Project alignment would encroach, or pass over natural streams at locations including Lam Tei, So Kwun Wat, Siu Lam, Tsing Lung Tau, and North Lantau. The removal or diversion of watercourses would involve excavation and construction works. If not properly controlled, pollutants including excavated materials, chemicals, wastewater or construction materials may be flushed downstream via the watercourse, inducing adverse water quality impacts, in addition flooding may occur in the downstream areas of the diverted or removed watercourses. It should be noted that natural watercourses within the Tai Lam Country Park would be totally avoided. With the implementation of proper mitigation measures stated in Section 5.11, insignificant water quality impacts are anticipated.
5.5.9 Groundwater from Potential Contaminated Areas and Contaminated Site Run-off
5.5.9.1 As discussed in Section 2, the majority of the Project alignment would go underneath Tai Lam Country Park which would have no potential for land contamination.
5.5.9.2 Section 7 has conducted a comprehensive land contamination study for the entire Project. According to the current findings, potential contaminated areas were identified at Lam Tei, Tai Lam Chung, Tsing Lung Tau, and To Kau Wan areas. Proper land contamination remediation and mitigation measures proposed in Section 7 should be followed. If the groundwater that is pumped out or discharged from the dewatering process during excavation works are located within potential contaminated areas, the discharge water could also be contaminated. Any potential contaminated materials which may be disturbed, or any foreign materials which contacts such contaminated material, could be washed by site run-off into the drainage system, thereby discharging contaminated water into the drainage system. Any potential contaminated groundwater or site run-off should be properly treated and disposed in compliance with the requirements of TM-DSS, and mitigation measures described in Section 5.11 should be followed, hence no adverse water quality impacts are anticipated.
5.5.10 Operation of Barging Points
5.5.10.1 As discussed in Section 2, the barging points are located at TLT and North Lantau, which are shown in Figure 2.6. The latest design of the barging point at TLT would be in the form of a temporary barging point located at the proposed reclamation area. Piling at only Tsing Lung Tau would be required for the construction of the barging point, and the barging point will be removed after the construction phase. Construction of the piles will generally involve the use of in-situ bored piles foundations founded on bedrock or seabed. All piling equipment would be set up on a barge, then the pile constructed would be through placing steel pile casing at the pier site in which the seawater trapped would be inside the casing. A funnel would be placed at the top of pile casing during excavation. This construction method of creating a confined environment for excavation could minimize the release of contaminant into the water column and hence reduce the risk of disturbance to the seabed and adjacent marine environment. No open sea dredging of seabed will be involved for the piling works.
5.5.10.2 Considering the relatively small scale of the barging point, the construction of the barging point would have insignificant impacts on water quality, and considering the east-west flow of Urmston Road’s current, it would also have insignificant impacts on the adjacent hydrodynamics. Additionally, given the sufficient water depth, dredging would not be required, this would have avoided any disturbance to the seabed and hence the associated water quality impacts.
5.5.10.3 However, activities conducted at the barging point still have the potential to cause adverse water quality impacts. Uncontrolled surface run-off generated at the barging point may contain high concentrations of SS, oil, grease, and chemicals. Additionally, materials may also be splashed into the surrounding water during the transportation of spoil using the barging point. These activities may increase the turbidity, discoloration, pH level of the nearby marine waters. Barges may also increase the turbidity and SS content of the nearby waters as marine deposits on the seabed may be disturbed through vessel movements and propeller wash.
5.5.10.4 With the implementation of the good practices and mitigation measures recommended in Section 5.11. any residual water quality impacts would be insignificant.
5.5.11 Accidental Spillage of Chemicals
5.5.11.1 The use of chemicals such as engine oil and lubricants, and their storage as waste materials has the potential to cause adverse water quality impacts if spillage occurs and enters the adjacent water bodies. Waste oil may infiltrate the surface soil layer, or discharged into the nearby water environment, increasing hydrocarbon levels. However, adverse impacts can be mitigated by implementing practical mitigation measures and good site practices as described in Section 5.11.
5.6 Identification and Evaluation of Water Quality Impacts for Construction Phase – Marine Based Works
5.6.1.1 According to the latest design, dredging would be required for the reclamation works at TLT. The proposed construction sequence is shown in Appendix 5.3. It can be seen that all the filling works would be constructed within the seawall (i.e. when the seawall reaches above the sea level) and hence there would be no SS released to the marine water. Nonetheless, as the dredging works would be constructed prior to the seawall construction, it would inevitably generate SS when the seabed sediments are disturbed. Hence, a quantitative water quality model was conducted to assess the water quality impacts induced by the reclamation works.
5.6.1.2 Besides reclamation, other potential sources of water quality impacts are identified for the construction phase (marine based works) of the Project:
· Construction of mud pit; and
· Marine works.
Model Parameters
5.6.2.1 The hydrodynamic model for this Project has adopted and refined that of the previously approved Tung Chung New Town Area (TCNTE) EIA (AEIAR-196/2016). The hydrodynamic grids were refined near the reclamation area to simulate the hydrodynamic and water quality impacts for both construction and operational phases of the Project.
5.6.2.2 Delft3D-FLOW module was used for hydrodynamic simulations with the grid layout shown in Appendix 5.5. The model has also been verified against the approved TCNTE EIA model to ensure the grid refinement did not adversely affect the model’s performance. Validation methodologies and results are shown in Appendix 5.5. Detailed information regarding hydrodynamic modelling methodology and parameters can also be referred to Appendix 5.4.
5.6.2.3 The Delft3D-WAQ module was adopted for construction phase water quality modelling. Outputs from the hydrodynamic model conducted using the Delft3D-FLOW module were coupled into the water quality model for water quality simulation, including parameters such as averaged fresh water flow, wind, initial conditions and boundary conditions, etc. Methodology and modelling parameters for the water quality models are presented in Appendix 5.6.
Consideration of Concurrent Projects
5.6.2.4 Based on the latest information, as part of the construction of Road P1 (Tai Ho - Sunny Bay Section), dredging may be required at Sham Shui Kok, which may overlap with the construction programme of Route 11, hence the dredging works for Road P1 is also included in the construction phase water quality model of this Project to simulate the cumulative impacts of both construction works. Details can also be referred to in Appendix 5.6.
Modelled Scenarios
5.6.2.5 As discussed in Section 2, dredging would be required due to the thin layer of marine sediments at the reclamation area, and filling will only be conducted within the completed seawall (i.e. when the seawall reaches above the sea level). Therefore, only water modelling scenarios associated with the dredging works were conducted, as no adverse water quality impacts are anticipated from filling works.
5.6.2.6 A total of 4 scenarios were modelled to simulate the water quality impacts induced from the reclamation works, including:
· WQ01a “Base Case 1”: Reclamation works next to shoreline without silt curtain;
· WQ01b “Base Case 2”: Reclamation works away from shoreline without silt curtain;
· WQ02a “Enhanced Case 1”: Reclamation works next to shoreline with silt curtain deployed; and
· WQ02b “Enhanced Case 2”: Reclamation works away from shoreline with silt curtain deployed.
5.6.2.7 For all modelling scenarios, a conservative assumption of a total dredged sediment volume of 30,000m3 over 10 working days were adopted. Dredging for Road P1 (Tai Ho - Sunny Bay Section) at Sham Shui Kok is included for all 4 scenarios.
Water Quality Model Observation
Points
5.6.2.8 Observation points were selected from the list of Representative WSRs presented under Section 5.3, and included in the water quality model outputs to evaluate the construction phase water quality impacts. The selected observation points are listed below in Table 5.18 and shown in Figure 5.1.
Table 5.18 Water Quality Model Observation Points
ID |
Observation Points |
Geodesic
Distance from Reclamation Area (km) |
B6 |
Anglers’
Beach |
1.8 |
B13 |
Ma Wan Tung Wan Beach |
2.4 |
C1 |
Seawater Intake
for Future Sunny Bay Development |
2.2 |
WSD2 |
Salt Water
Pumping Station near Hong Kong Garden |
0.7 |
WSD4 |
Salt
Water Pumping Station near Lok On Pai |
4.3 |
CR1 |
Corals
at To Kau Wan |
1.1 |
CR2 |
Corals
at Sunny Bay |
2.3 |
F1 |
Ma Wan Fish Culture Zone |
1.6 |
MG1 |
Mangrove near Ma Wan |
2.0 |
MP1 |
The Brothers Marine Park
Indicator Point 1 |
6.1 |
MP2 |
The Brothers Marine Park
Indicator Point 2 |
4.6 |
5.6.3 Criteria for Construction Phase Water Quality Modelling
Criteria for Suspended Solids
5.6.3.1 According to the WQOs for marine water, the SS criterion states that “Waste discharges / human activities shall not cause the natural ambient level to be to be raised by 30% nor give rise to accumulation of suspended solids which may adversely affect aquatic communities”. Hence for the water quality model, the SS criteria is defined as 30% of the 90th percentile of the SS data measured at the monitoring stations. The ambient SS concentrations (i.e. 90th percentile value) of the closest EPD monitoring stations NM1, NM2, and WM4 in North Western and Western Buffer WCZs were analysed.
5.6.3.2 The 90th percentile of marine suspended solid concentrations measured at surface, middle, and bottom layers are presented in Table 5.19. Monthly sampling data from years 1986 to 2021 were taken from April to September and October to March for wet season and dry season respectively.
Table 5.19 Ambient SS levels from EPD Monitoring Station (1986-2021)
Station |
90th Percentile
Suspended Solids Concentrations (mg/L) |
||||||||
Surface |
Middle |
Bottom |
Depth Averaged |
||||||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Annual |
|
NM1 |
14.7 |
9.7 |
20.0 |
15.0 |
23.7 |
26.4 |
17.8 |
16.3 |
17.3 |
NM2 |
13.0 |
9.6 |
15.0 |
11.1 |
23.3 |
17.6 |
15.4 |
11.6 |
12.6 |
WM4 |
13.0 |
9.1 |
20.2 |
13.0 |
25.2 |
20.1 |
20.9 |
16.7 |
13.2 |
5.6.3.3 The SS criteria (i.e. the allowed elevation of SS), is then derived from the 90th percentile SS concentration measurements of EPD’s monitoring stations, and the observation points adopted the criteria are summarised under Table 5.20.
Table 5.20 Observation Points and Adopted Suspended Solids Criteria
Station/ Observation Points |
Suspended Solids Criteria
(mg/L) |
||||||||
Surface |
Middle |
Bottom |
Depth Averaged |
||||||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Annual |
|
NM1 |
4.4 |
2.9 |
6.0 |
4.5 |
7.1 |
7.9 |
5.3 |
4.9 |
5.2 |
NM2 |
3.9 |
2.9 |
4.5 |
3.3 |
7.0 |
5.3 |
4.6 |
3.5 |
3.8 |
WM4 |
3.9 |
2.7 |
6.1 |
3.9 |
7.6 |
6.0 |
6.3 |
5.0 |
4.0 |
Criterion
for Sedimentation Rate
5.6.3.4 Corals were discovered in the vicinity of the reclamation area, the dredging/filling activities may adversely impact the coral communities if there are any significant amount of sediment deposition. Hence, sedimentation rate of SS is also considered in the water quality model. Studies conducted by Hawker & Connell (1992) and Pastorok & Bilyard (1985) suggested that a sedimentation rate higher than 100 g/m2/day would introduce moderate to severe impact upon corals. This value is therefore adopted as the criterion for sedimentation rate assessment.
Criteria for Dissolved Oxygen
Depletion
5.6.3.5 Dissolved oxygen (DO) depletion induced by dredging/filling associated with the construction phase of the Project was assessed based on the requirements of the WQO, and hence were adopted as the assessment criterion for DO depletion.
5.6.3.6 DO data from EPD’s routine water quality monitoring programme from years 1986 to 2021 were analysed to determine the allowable change in DO levels from each EPD monitoring station. The allowable change is calculated as the ambient DO level minus the DO requirements of the WQO (i.e. 4mg/L for depth averaged, surface and middle layers, 2mg/L for bottom layer, and 5mg/L for FCZs), whereas the WSD DO criterion (i.e. > 2 mg/L) was adopted for WSD salt water pumping stations. The ambient level is calculated as the 10th percentile value of the DO data measured by EPD monitoring stations.
5.6.3.7 The ambient levels of the concerned EPD monitoring stations, and the DO Depletion criteria are summarised in Table 5.21 and Table 5.22 respectively.
Table 5.21 Ambient DO Levels from EPD Monitoring Stations (1986-2021)
Station |
Ambient DO (mg/L) |
|||||||
Surface |
Middle |
Bottom |
Depth Averaged |
|||||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
|
NM1 |
5.3 |
4.5 |
5.7 |
3.3 |
5.6 |
2.7 |
5.6 |
3.8 |
NM2 |
5.6 |
4.6 |
5.8 |
4.2 |
5.8 |
3.6 |
5.7 |
4.6 |
WM4 |
5.1 |
4.4 |
5.6 |
3.4 |
5.6 |
4.4 |
5.5 |
3.9 |
Table 5.22 Criteria for DO Depletion
Location |
DO Depletion Criteria
(mg/L) |
|||||||
Surface |
Middle |
Bottom |
Depth Averaged |
|||||
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
Dry Season |
Wet Season |
|
NM1 |
1.3 |
0.5 |
1.7 |
0.0 |
3.6 |
0.7 |
1.6 |
0.0 |
NM2 |
1.6 |
0.6 |
1.8 |
0.2 |
3.8 |
1.6 |
1.7 |
0.6 |
WM4 |
1.1 |
0.4 |
1.6 |
0.0 |
3.6 |
2.4 |
1.5 |
0.0 |
FCZs |
0.1 |
0.0 |
0.6 |
0.0 |
0.6 |
0.0 |
0.5 |
0.0 |
5.6.4 Water Quality Modelling Results for Construction Phase
5.6.4.1 As discussed in Section 5.6.2, modelling scenarios (i.e. WQ01a and b and WQ02a and b) were conducted to simulate the water quality impacts induced upon nearby observation points during the construction phase. The modelling results for the key water quality parameters are summarised below with detailed results given in Appendix 5.7.
Suspended Solids
5.6.4.2
The modelled maximum SS
concentrations at all the observation points are summarised in Table 5.24
to Table 5.27, with the SS criteria presented in which is presented in Table
5.23. According to the modelling results, the predicted SS elevations due
to construction under Base Cases (WQ01a
and b) at all observation points are well within their respective criteria. The
Enhanced Cases (WQ02a and b) showed the further improvement in water quality
after the implementation of a silt curtain, and the SS criteria are compiled
for all observation points. Hence, adverse water quality impact due to the
release of SS is not anticipated even before the implementation of silt
curtain. Nonetheless as a water quality enhancement measure, the deployment of
silt curtain is still recommended. It should be noted that for both WQ01a-b and
WQ02a-b, the observation points nearest to the dredging site of the Project
(i.e. Tsing Lung Tau) including B6, WSD2, CR1, and F1 have all complied with
their respective SS criteria. This indicates that the overall water quality
impact of the Project’s construction phase is insignificant.
Table 5.23 SS Criteria for Observation Points
Obs Pts[2] |
SS Criteria (mg/L)[1] |
|||||||
Dry Season |
Wet Season |
|||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
|
B6 |
3.9 |
2.8 |
6.2 |
3.9 |
7.7 |
6.2 |
6.3 |
4.0 |
B13 |
3.9 |
2.8 |
6.2 |
3.9 |
7.7 |
6.2 |
6.3 |
4.0 |
C1 |
4.5 |
2.9 |
6.0 |
4.6 |
7.2 |
8.2 |
5.4 |
5.0 |
WSD2 |
3.9 |
2.8 |
6.2 |
3.9 |
7.7 |
6.2 |
6.3 |
4.0 |
WSD4 |
3.9 |
2.9 |
4.5 |
3.3 |
7.1 |
5.6 |
4.5 |
3.5 |
CR1 |
4.5 |
2.9 |
6.0 |
4.6 |
7.2 |
8.2 |
5.4 |
5.0 |
CR2 |
4.5 |
2.9 |
6.0 |
4.6 |
7.2 |
8.2 |
5.4 |
5.0 |
F1 |
3.9 |
2.8 |
6.2 |
3.9 |
7.7 |
6.2 |
6.3 |
4.0 |
MG1 |
3.9 |
2.8 |
6.2 |
3.9 |
7.7 |
6.2 |
6.3 |
4.0 |
MP1 |
4.5 |
2.9 |
6.0 |
4.6 |
7.2 |
8.2 |
5.4 |
5.0 |
MP2 |
4.5 |
2.9 |
6.0 |
4.6 |
7.2 |
8.2 |
5.4 |
5.0 |
Notes:
[1] S =
surface layer, M = middle layer, B = bottom layer, and DA = depth averaged.
[2] Obs Pts =
observation points.
Table 5.24 Maximum SS Elevation for Scenario WQ01a
Obs Pts[2] |
Modelled SS
Elevation (mg/L)[1] |
Compliance of
Criteria |
|||||||
Dry Season |
Wet Season |
||||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
||
B6 |
0.9 |
1.0 |
1.2 |
1.0 |
0.8 |
0.8 |
0.8 |
0.8 |
✔ |
B13 |
0.1 |
0.1 |
0.1 |
0.1 |
0.0 |
0.0 |
0.1 |
0.0 |
✔ |
C1 |
0.2 |
0.2 |
0.3 |
0.2 |
0.1 |
0.2 |
0.3 |
0.1 |
✔ |
WSD2 |
1.3 |
1.8 |
2.1 |
1.7 |
1.6 |
2.0 |
2.6 |
2.0 |
✔ |
WSD4 |
0.4 |
0.5 |
0.6 |
0.5 |
0.2 |
0.3 |
0.5 |
0.4 |
✔ |
CR1 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
CR2 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
F1 |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
MG1 |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
MP1 |
0.2 |
0.3 |
0.5 |
0.3 |
0.2 |
0.3 |
0.4 |
0.3 |
✔ |
MP2 |
0.4 |
0.5 |
0.6 |
0.5 |
0.4 |
0.5 |
0.4 |
0.4 |
✔ |
[1] S = surface layer, M = middle layer, B =
bottom layer, and DA = depth averaged.
[2] Obs Pts = observation points.
Table 5.25 Maximum SS Elevation for Scenario WQ01b
Obs Pts[2] |
Modelled SS
Elevation (mg/L)[1] |
Compliance of
Criteria |
|||||||
Dry Season |
Wet Season |
||||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
||
B6 |
0.6 |
0.7 |
0.9 |
0.7 |
0.6 |
0.6 |
0.5 |
0.6 |
✔ |
B13 |
0.1 |
0.1 |
0.1 |
0.1 |
0.0 |
0.1 |
0.1 |
0.1 |
✔ |
C1 |
0.2 |
0.2 |
0.3 |
0.2 |
0.1 |
0.2 |
0.3 |
0.2 |
✔ |
WSD2 |
0.6 |
0.9 |
1.0 |
0.9 |
0.8 |
0.9 |
1.2 |
1.0 |
✔ |
WSD4 |
0.3 |
0.4 |
0.5 |
0.4 |
0.2 |
0.3 |
0.4 |
0.3 |
✔ |
CR1 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.2 |
0.2 |
0.2 |
✔ |
CR2 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
F1 |
0.2 |
0.2 |
0.2 |
0.2 |
0.1 |
0.2 |
0.2 |
0.1 |
✔ |
MG1 |
0.1 |
0.1 |
0.2 |
0.2 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
MP1 |
0.2 |
0.3 |
0.5 |
0.3 |
0.2 |
0.3 |
0.5 |
0.3 |
✔ |
MP2 |
0.4 |
0.5 |
0.6 |
0.5 |
0.4 |
0.5 |
0.4 |
0.4 |
✔ |
[1] S = surface layer, M = middle layer, B =
bottom layer, and DA = depth averaged.
[2] Obs Pts = observation points.
Table 5.26 Maximum SS Elevation for Scenario WQ02a
Obs Pts[2] |
Modelled SS
Elevation (mg/L)[1] |
Compliance of
Criteria |
|||||||
Dry Season |
Wet Season |
||||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
||
B6 |
0.5 |
0.5 |
0.7 |
0.6 |
0.5 |
0.4 |
0.4 |
0.4 |
✔ |
B13 |
0.0 |
0.1 |
0.1 |
0.1 |
0.0 |
0.0 |
0.0 |
0.0 |
✔ |
C1 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
WSD2 |
0.7 |
1.0 |
1.2 |
0.9 |
0.9 |
1.1 |
1.4 |
1.1 |
✔ |
WSD4 |
0.2 |
0.3 |
0.3 |
0.3 |
0.1 |
0.2 |
0.3 |
0.2 |
✔ |
CR1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
CR2 |
0.1 |
0.1 |
0.2 |
0.1 |
0.0 |
0.1 |
0.1 |
0.1 |
✔ |
F1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
MG1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
MP1 |
0.1 |
0.2 |
0.4 |
0.2 |
0.1 |
0.2 |
0.3 |
0.2 |
✔ |
MP2 |
0.2 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
✔ |
[1] S =
surface layer, M = middle layer, B = bottom layer, and DA = depth averaged.
[2] Obs Pts =
observation points.
Table 5.27 Maximum SS Elevation for Scenario WQ02b
Obs Pts[2] |
Modelled SS
Elevation (mg/L)[1] |
Compliance of
Criteria |
|||||||
Dry Season |
Wet Season |
||||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
||
B6 |
0.3 |
0.4 |
0.5 |
0.4 |
0.3 |
0.3 |
0.3 |
0.3 |
✔ |
B13 |
0.0 |
0.1 |
0.1 |
0.1 |
0.0 |
0.0 |
0.0 |
0.0 |
✔ |
C1 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
WSD2 |
0.3 |
0.5 |
0.6 |
0.5 |
0.5 |
0.5 |
0.7 |
0.5 |
✔ |
WSD4 |
0.2 |
0.2 |
0.3 |
0.2 |
0.1 |
0.2 |
0.2 |
0.2 |
✔ |
CR1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
CR2 |
0.1 |
0.1 |
0.2 |
0.1 |
0.1 |
0.1 |
0.2 |
0.1 |
✔ |
F1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
MG1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
0.1 |
✔ |
MP1 |
0.1 |
0.2 |
0.4 |
0.2 |
0.1 |
0.2 |
0.3 |
0.2 |
✔ |
MP2 |
0.2 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
0.3 |
✔ |
Notes:
[1] S =
surface layer, M = middle layer, B = bottom layer, and DA = depth averaged.
[2] Obs Pts =
observation points.
Sedimentation Rate
5.6.4.3 The modelled maximum daily sedimentation rates at coral habitats are summarised in Table 5.28. According to the modelling results, the predicted daily sedimentation rates due to construction under Base Cases (WQ01a and b), at coral habitats are well within the criterion of 100 g/m2/day, with Enhanced Cases (WQ02a and b) demonstrating further optimisation of water quality with the deployment of a silt curtain. Hence, adverse water quality impact due to sedimentation is not anticipated.
Table 5.28 Sedimentation Rate at Coral Habitats (g/m2/day)
Obs Pts[2] |
Modelled
Sedimentation Rate |
Criteria |
Compliance of
Criteria |
|||||||
Dry Season |
Wet Season |
|||||||||
WQ 01A |
WQ 01B |
WQ 02A |
WQ 02B |
WQ 01A |
WQ 01B |
WQ 02A |
WQ 02B |
|||
CR1 |
4.5 |
4.4 |
2.6 |
2.8 |
5.7 |
6.5 |
3.3 |
3.7 |
100 |
✔ |
CR2 |
9.1 |
9.2 |
6.6 |
6.7 |
4.0 |
4.5 |
2.5 |
2.9 |
100 |
✔ |
Dissolved Oxygen Depletion
5.6.4.4
The DO depletion calculated
from the maximum SS elevation is presented from Table 5.29 to Table
5.32. The calculation
methodology is presented in Appendix 5.6. Modelling results revealed that the
oxygen depletion at all observation points for the Base Cases (WQ01a and b)
will be less than the detection limit of 0.1mg/L even without the deployment of
silt curtains. Hence, it is anticipated that the DO depletion arising from the
reclamation works will be insignificant. The results from Enhanced Cases (WQ02a
and b) demonstrated that the deployment of silt curtains will further reduce
the water quality impacts. However, it is still advisable to deploy silt
curtain as a good practice which would further reduce the water quality
impacts.
Table 5.29 Maximum DO
Depletion for Scenario WQ01a
Obs Pts[2] |
Maximum DO
Depletion (mg/L)[1] |
|||||||
Dry Season |
Wet Season |
|||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
|
B6 |
1.2E-02 |
1.3E-02 |
1.6E-02 |
1.4E-02 |
1.1E-02 |
1.0E-02 |
1.1E-02 |
1.1E-02 |
B13 |
1.1E-03 |
1.2E-03 |
1.4E-03 |
1.2E-03 |
5.4E-04 |
6.2E-04 |
7.1E-04 |
6.3E-04 |
C1 |
2.1E-03 |
2.6E-03 |
3.8E-03 |
3.0E-03 |
1.6E-03 |
2.1E-03 |
3.3E-03 |
1.9E-03 |
WSD2 |
1.6E-02 |
2.3E-02 |
2.8E-02 |
2.2E-02 |
2.0E-02 |
2.7E-02 |
3.4E-02 |
2.6E-02 |
WSD4 |
5.4E-03 |
6.7E-03 |
8.1E-03 |
6.7E-03 |
3.2E-03 |
4.5E-03 |
6.1E-03 |
4.6E-03 |
CR1 |
1.7E-03 |
1.9E-03 |
2.7E-03 |
1.9E-03 |
1.3E-03 |
1.9E-03 |
2.9E-03 |
1.9E-03 |
CR2 |
1.3E-03 |
1.7E-03 |
2.8E-03 |
1.7E-03 |
7.5E-04 |
1.0E-03 |
1.6E-03 |
1.1E-03 |
F1 |
2.1E-03 |
2.4E-03 |
2.9E-03 |
2.3E-03 |
1.8E-03 |
1.9E-03 |
2.3E-03 |
1.8E-03 |
MG1 |
2.0E-03 |
2.1E-03 |
2.3E-03 |
2.1E-03 |
1.4E-03 |
1.7E-03 |
2.1E-03 |
1.7E-03 |
MP1 |
2.6E-03 |
3.8E-03 |
7.0E-03 |
4.0E-03 |
2.2E-03 |
3.8E-03 |
5.8E-03 |
3.3E-03 |
MP2 |
4.8E-03 |
6.0E-03 |
7.3E-03 |
6.1E-03 |
5.4E-03 |
6.2E-03 |
5.6E-03 |
5.6E-03 |
[1] S = surface layer, M = middle layer, B =
bottom layer, and DA = depth averaged.
[2] Obs Pts = observation points.
Table 5.30 Maximum DO Depletion for Scenario WQ01b
Obs Pts[2] |
Maximum DO
Depletion (mg/L)[1] |
|||||||
Dry Season |
Wet Season |
|||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
|
B6 |
7.3E-03 |
8.8E-03 |
1.2E-02 |
9.5E-03 |
8.0E-03 |
7.8E-03 |
6.7E-03 |
7.4E-03 |
B13 |
1.1E-03 |
1.2E-03 |
1.4E-03 |
1.2E-03 |
5.7E-04 |
6.5E-04 |
7.5E-04 |
6.6E-04 |
C1 |
2.1E-03 |
2.8E-03 |
3.9E-03 |
3.0E-03 |
1.7E-03 |
2.3E-03 |
3.6E-03 |
2.1E-03 |
WSD2 |
8.2E-03 |
1.2E-02 |
1.3E-02 |
1.1E-02 |
1.1E-02 |
1.2E-02 |
1.6E-02 |
1.3E-02 |
WSD4 |
4.1E-03 |
5.5E-03 |
6.7E-03 |
5.5E-03 |
2.9E-03 |
4.2E-03 |
5.5E-03 |
4.3E-03 |
CR1 |
1.5E-03 |
1.8E-03 |
2.7E-03 |
1.8E-03 |
1.2E-03 |
2.1E-03 |
3.1E-03 |
2.1E-03 |
CR2 |
1.3E-03 |
1.7E-03 |
2.8E-03 |
1.7E-03 |
8.4E-04 |
1.2E-03 |
1.8E-03 |
1.2E-03 |
F1 |
2.0E-03 |
2.4E-03 |
2.7E-03 |
2.1E-03 |
1.6E-03 |
2.0E-03 |
2.5E-03 |
1.9E-03 |
MG1 |
1.8E-03 |
1.9E-03 |
2.1E-03 |
2.0E-03 |
1.5E-03 |
1.7E-03 |
2.2E-03 |
1.7E-03 |
MP1 |
2.6E-03 |
3.9E-03 |
7.1E-03 |
4.1E-03 |
2.3E-03 |
3.9E-03 |
5.9E-03 |
3.5E-03 |
MP2 |
4.9E-03 |
5.9E-03 |
7.4E-03 |
6.1E-03 |
5.3E-03 |
6.3E-03 |
5.7E-03 |
5.5E-03 |
[1] S = surface layer, M = middle layer, B = bottom
layer, and DA = depth averaged.
[2] Obs Pts = observation points.
Table 5.31 Maximum DO Depletion for Scenario WQ02a
Obs Pts[2] |
Maximum DO
Depletion (mg/L)[1] |
|||||||
Dry Season |
Wet Season |
|||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
|
B6 |
6.6E-03 |
7.1E-03 |
8.9E-03 |
7.5E-03 |
5.9E-03 |
5.7E-03 |
5.8E-03 |
5.8E-03 |
B13 |
6.1E-04 |
7.0E-04 |
8.2E-04 |
7.2E-04 |
3.5E-04 |
4.0E-04 |
4.6E-04 |
4.0E-04 |
C1 |
1.2E-03 |
1.5E-03 |
2.4E-03 |
1.7E-03 |
9.3E-04 |
1.3E-03 |
2.1E-03 |
1.2E-03 |
WSD2 |
9.0E-03 |
1.3E-02 |
1.5E-02 |
1.2E-02 |
1.1E-02 |
1.5E-02 |
1.9E-02 |
1.4E-02 |
WSD4 |
3.0E-03 |
3.7E-03 |
4.5E-03 |
3.7E-03 |
1.8E-03 |
2.5E-03 |
3.4E-03 |
2.6E-03 |
CR1 |
9.9E-04 |
1.1E-03 |
1.7E-03 |
1.1E-03 |
7.4E-04 |
1.2E-03 |
1.9E-03 |
1.2E-03 |
CR2 |
8.4E-04 |
1.0E-03 |
2.0E-03 |
1.1E-03 |
4.5E-04 |
6.6E-04 |
1.0E-03 |
6.9E-04 |
F1 |
1.2E-03 |
1.4E-03 |
1.7E-03 |
1.3E-03 |
1.0E-03 |
1.2E-03 |
1.5E-03 |
1.1E-03 |
MG1 |
1.1E-03 |
1.2E-03 |
1.3E-03 |
1.2E-03 |
8.7E-04 |
1.1E-03 |
1.4E-03 |
1.1E-03 |
MP1 |
1.4E-03 |
2.3E-03 |
4.6E-03 |
2.5E-03 |
1.4E-03 |
2.5E-03 |
4.0E-03 |
2.2E-03 |
MP2 |
2.8E-03 |
3.5E-03 |
4.4E-03 |
3.7E-03 |
3.3E-03 |
4.0E-03 |
3.7E-03 |
3.5E-03 |
[1] S =
surface layer, M = middle layer, B = bottom layer, and DA = depth averaged.
[2] Obs Pts =
observation points.
Table 5.32 Maximum DO
Depletion for Scenario WQ02b
Obs Pts[2] |
Maximum DO
Depletion (mg/L)[1] |
|||||||
Dry Season |
Wet Season |
|||||||
S |
M |
B |
DA |
S |
M |
B |
DA |
|
B6 |
4.0E-03 |
4.8E-03 |
6.5E-03 |
5.2E-03 |
4.4E-03 |
4.3E-03 |
3.7E-03 |
4.1E-03 |
B13 |
6.0E-04 |
6.9E-04 |
8.1E-04 |
7.1E-04 |
3.7E-04 |
4.3E-04 |
4.9E-04 |
4.3E-04 |
C1 |
1.2E-03 |
1.6E-03 |
2.5E-03 |
1.7E-03 |
1.0E-03 |
1.5E-03 |
2.3E-03 |
1.3E-03 |
WSD2 |
4.5E-03 |
6.3E-03 |
7.4E-03 |
6.2E-03 |
5.9E-03 |
6.8E-03 |
8.6E-03 |
6.9E-03 |
WSD4 |
2.3E-03 |
3.0E-03 |
3.7E-03 |
3.0E-03 |
1.6E-03 |
2.4E-03 |
3.2E-03 |
2.5E-03 |
CR1 |
9.0E-04 |
1.0E-03 |
1.7E-03 |
1.1E-03 |
7.7E-04 |
1.3E-03 |
2.0E-03 |
1.4E-03 |
CR2 |
8.4E-04 |
1.0E-03 |
2.0E-03 |
1.1E-03 |
7.7E-04 |
1.3E-03 |
2.0E-03 |
1.4E-03 |
F1 |
1.1E-03 |
1.3E-03 |
1.6E-03 |
1.2E-03 |
9.9E-04 |
1.3E-03 |
1.6E-03 |
1.2E-03 |
MG1 |
1.1E-03 |
1.1E-03 |
1.3E-03 |
1.1E-03 |
9.0E-04 |
1.2E-03 |
1.5E-03 |
1.1E-03 |
MP1 |
1.5E-03 |
2.4E-03 |
4.6E-03 |
2.6E-03 |
1.5E-03 |
2.6E-03 |
4.1E-03 |
2.3E-03 |
MP2 |
2.9E-03 |
3.6E-03 |
4.4E-03 |
3.7E-03 |
3.4E-03 |
4.2E-03 |
3.7E-03 |
3.5E-03 |
Notes:
[1] S =
surface layer, M = middle layer, B = bottom layer, and DA = depth averaged.
[2] Obs Pts =
observation points.
Contaminant Release from Disturbed
Sediment
5.6.4.5
Contaminant releases from
disturbed sediment is anticipated during dredging works. The pore water and
elutriate test results in Table 5.8 indicated that parameters including arsenic, zinc, TIN, UIA, total
PAHs, PCBs, and TBT would require further assessment to determine whether the
criteria would be complied with at the key observation points (see detailed
calculations and methods shown in Appendix 5.6). The calculations presented in Table 5.33 and Table
5.34 for concentrations
derived from elutriate tests, and Table
5.35 and Table 5.36 for concentrations derived from pore water tests. It can be seen that
there are full compliances of criteria at ecological and recreational
observation points for both elutriate and pore water tests calculations. Hence,
adverse water quality impact from contaminants released from disturbed
sediments are not anticipated.
Table 5.33 Estimated
Contaminant Concentration at Observation Points in Western Buffer WCZ from
Elutriate Tests
Parameter |
As |
Zn |
TIN[1] |
UIA[1] |
PAHs |
PCBs |
TBT |
|
Criteria |
13 |
8 |
0.40 |
0.021 |
0.2 |
0.03 |
0.006 |
|
Baseline Conditions |
- |
- |
0.35 |
0.004 |
- |
- |
- |
|
Obs Pts |
Dilution Factor |
(µg/L) |
(µg/L) |
(mg/L) |
(mg/L) |
(µg/L) |
(µg/L) |
(µg/L) |
B6 |
176 |
8.5E-02 |
7.4E-01 |
3.6E-01 |
4.4E-03 |
5.1E-02 |
1.0E-03 |
8.5E-05 |
B13 |
240 |
6.3E-02 |
5.5E-01 |
3.6E-01 |
4.3E-03 |
3.8E-02 |
7.5E-04 |
6.3E-05 |
F1 |
157 |
9.6E-02 |
8.3E-01 |
3.6E-01 |
4.4E-03 |
5.7E-02 |
1.1E-03 |
9.6E-05 |
MG1 |
200 |
7.5E-02 |
6.6E-01 |
3.6E-01 |
4.3E-03 |
4.5E-02 |
9.0E-04 |
7.5E-05 |
Compliance |
✔ |
✔ |
✔ |
✔ |
✔ |
✔ |
✔ |
Note:
[1] A factor (i.e.
10/365) is applied converting the assumed working days to the WQO annual
criteria.
Table 5.34 Estimated
Contaminant Concentration at Observation Points in North Western WCZ from
Elutriate Tests
Parameter |
As |
Zn |
TIN[1] |
UIA[1] |
PAHs |
PCBs |
TBT |
|
Criteria |
13 |
8 |
0.5 |
0.021 |
0.2 |
0.03 |
0.006 |
|
Baseline Conditions |
- |
- |
0.5 |
0.003 |
- |
- |
- |
|
Obs Pts |
Dilution Factor |
(µg/L) |
(µg/L) |
(mg/L) |
(mg/L) |
(µg/L) |
(µg/L) |
(µg/L) |
CR1 |
113 |
1.3E-01 |
1.2E+00 |
5.0E-01 |
3.6E-03 |
8.0E-02 |
1.6E-03 |
1.3E-04 |
CR2 |
229 |
6.6E-02 |
5.7E-01 |
5.0E-01 |
3.3E-03 |
3.9E-02 |
7.9E-04 |
6.6E-05 |
Compliance |
✔ |
✔ |
✔ |
✔ |
✔ |
✔ |
✔ |
[1] A factor (i.e. 10/365) is applied converting
the assumed working days to the WQO annual criteria.
Table 5.35 Estimated
Contaminant Concentration at Observation Points in Western Buffer WCZ from Pore
Water Tests
Parameter |
TIN[1] |
UIA[1] |
PAHs |
PCBs |
TBT |
|
Criteria |
0.40 |
0.021 |
0.2 |
0.03 |
0.006 |
|
Baseline Conditions |
0.35 |
0.004 |
- |
- |
- |
|
Obs Pts |
Dilution Factor |
(mg/L) |
(mg/L) |
(µg/L) |
(µg/L) |
(µg/L) |
B6 |
176 |
3.5E-01 |
7.2E-03 |
5.1E-02 |
1.0E-03 |
8.5E-05 |
B13 |
240 |
3.5E-01 |
6.3E-03 |
3.8E-02 |
7.5E-04 |
6.3E-05 |
F1 |
157 |
3.5E-01 |
7.5E-03 |
5.7E-02 |
1.1E-03 |
9.6E-05 |
MG1 |
200 |
3.5E-01 |
6.8E-03 |
4.5E-02 |
9.0E-04 |
7.5E-05 |
Compliance |
✔ |
✔ |
✔ |
✔ |
✔ |
[1] A factor (i.e. 10/365) is applied converting
the assumed working days to the WQO annual criteria.
Table 5.36 Estimated
Contaminant Concentration at Observation Points in North Western WCZ from Pore
Water Tests
Parameter |
TIN[1] |
UIA[1] |
PAHs |
PCBs |
TBT |
|
Criteria |
0.50 |
0.021 |
0.2 |
0.03 |
0.006 |
|
Baseline Conditions |
0.50 |
0.003 |
- |
- |
- |
|
Obs Pts |
Dilution Factor |
(mg/L) |
(mg/L) |
(µg/L) |
(µg/L) |
(µg/L) |
CR1 |
113 |
5.0E-01 |
7.9E-03 |
8.0E-02 |
1.6E-03 |
1.3E-04 |
CR2 |
229 |
5.0E-01 |
5.4E-03 |
3.9E-02 |
7.9E-04 |
6.6E-05 |
Compliance |
✔ |
✔ |
✔ |
✔ |
✔ |
Note:
[1] A factor
(i.e. 10/365) is applied converting the assumed working days to the WQO annual
criteria.
5.6.4.6 As seen through the water quality modelling results, the water quality at the key observation points have achieved full compliance of the criteria. Nonetheless, “Enhanced Case” (i.e. simulation with one silt curtain deployed) was also simulated to determine the effectiveness of the enhancement measures. Results indicate that the water quality would experience further improvements. Hence, it is recommended as a good practice to deploy a silt curtain during dredging works to further optimise the water quality.
5.6.5.1 As mentioned in Section 2.9, marine deposit will be dredged during the construction of seawall. The dredged marine deposit will be backfilled to a mud pit formed within the reclamation area. The mud pit will be formed by sheet piling with the silt curtain in place. The mud pit will be completely sealed, such that the backfilled marine deposit will not leak to surrounding waterbodies. Given the nature of sheet piling works, minimal amount of suspended solids will be generated. With deployment of silt curtain, adverse water quality impact is not anticipated.
5.6.6.1 During construction phase, marine traffic for the transportation of construction materials for reclamation is anticipated to increase. The induced number of marine vessels during construction phase may impact the marine water quality. The potential water quality impacts include sewage generated by the construction workforce and accidental spillage of chemicals / chemicals waste into the marine environment. The potential impact associated with sewage generated by the workforce can be readily controlled by the provision of adequate sanitary facilities such as portable chemical toilets on the marine vessels. The storage and disposal of chemical waste should follow the guidelines stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. Water quality impacts due to the increase in marine traffic is not anticipated. Besides, overflow of filling materials in the barges or hoppers can cause water pollution during loading or transportation. Good management practice such as limiting the capacity of a barge to avoid overflow of filling material can minimise the potential water quality impact.
5.7 Identification and Evaluation of Water Quality Impacts for Operational Phase
5.7.1.1 According to the latest design, the reclaimed northern anchor at TLT may affect the hydrodynamic regime of the area through narrowing the Ha Pang Fairway between TLT and To Kau Wan. Hence, a quantitative hydrodynamic assessment was conducted to assess the overall hydrodynamic impacts.
5.7.1.2 Other potential sources of water quality impacts are identified for the operational phase of the Project:
· Road run-off discharged from paved roads and developments proposed under the Project;
· Tunnel run-off and drainage;
· Sewage generated by ventilation buildings and administration buildings; and
· Wastewater generated from washing and maintenance operations.
5.7.2 Reclaimed Northern Anchor
Modelling Parameters
5.7.2.1 Hydrodynamic modelling using the Delf3D-FLOW module was used to simulate the hydrodynamic regime change due to the reclaimed northern anchor. The details of hydrodynamic modelling methodology and parameters are presented in Appendix 5.4.
Modelled Scenarios
5.7.2.2 To simulate the hydrodynamic changes induced by the reclaimed northern anchor at TLT, the modelling scenarios summarised below were conducted, details on the scenarios can be referred to in Appendix 5.4:
· Scenario H01 “Base Case”; and
· Scenario H02 “Operational Case”.
5.7.3 Hydrodynamic Modelling Results
5.7.3.1 Hydrodynamic modelling was conducted to simulate that hydrodynamic regime changes as a result of the narrowed Ha Pang Fairway between TLT and To Kau Wan due to the northern anchor reclamation.
5.7.3.2 The instantaneous discharge, cumulative discharge, and depth averaged velocity at five major channels around the study site, i.e. 1) Siu Lam, 2) Kap Shui Mun, 3) Ma Wan Channel, 4) Rambler Channel, and 5) Victoria harbour for both Scenarios H01 and H02 are summarised under Table 5.37 to Table 5.40 respectively, with detailed results shown in Appendix 5.8.
5.7.3.3 As shown in Table 5.37, the changes in instantaneous discharge for Scenario H02 are insignificant for both dry and wet seasons for all 5 channels. The comparison of ebb/flood tidal flow volume for the 5 channels are shown in Table 5.38. For the cross section at Siu Lam and Vitoria Harbour, which are further away from the proposed reclamation, the changes in ebb/flood tidal flow volume are insignificant (<1%) for both wet and dry seasons. For cross sections that are closer to the proposed reclamation, it is observed that there was a slight increase in tidal flow volume at Kap Shui Mun, and a slight decrease in tidal flow volume at Ma Wan Channel during both dry and wet seasons. The highest percentage change was observed at Kap Shui Mun during flood tide of the wet season, at approximately 3.7%. The cumulative flux (i.e. the residual of the combined flow volume from ebb tide flow volume and flood tide flow volume change for a typical wet/dry season) is compared in Table 5.39, which indicates that the net change in cumulative flow is much less than the daily tidal flow volume. Hence the overall hydrodynamic impacts are considered insignificant.
5.7.3.4 The changes in depth averaged velocities for Scenario H02 are also insignificant as shown in Table 5.40, overall the changes of depth averaged velocities are between 0.0m/s to 0.2m/s. During the dry season, it was observed that the percentage changes are from -1.2% to 2.8% and for wet season, the percentage changes are from -0.9% to 1.9%.
Table
5.37 Comparison
of Instantaneous Discharge Results at Concerned Channels
Channels |
Seasons |
Instantaneous
Discharge (m3/s)[1] |
|
Scenario
H01 |
Scenario
H02 |
||
Siu
Lam |
Dry |
-5.4E+04 - 6.3E+04 |
-5.4E+04 - 6.2E+04 |
Wet |
-5.1E+04 - 6.4E+04 |
-5.1E+04 - 6.4E+04 |
|
Kap
Shui Mun |
Dry |
-1.8E+04 - 1.6E+04 |
-1.7E+04 - 1.6E+04 |
Wet |
-1.8E+04 - 1.4E+04 |
-1.8E+04 - 1.4E+04 |
|
Ma Wan Channel |
Dry |
-4.5E+04 - 3.8E+04 |
-4.5E+04 - 3.8E+04 |
Wet |
-4.4E+04 - 3.8E+04 |
-4.4E+04 - 3.7E+04 |
|
Rambler Channel |
Dry |
-2.4E+03 - 4.6E+03 |
-2.5E+03 - 4.6E+03 |
Wet |
-1.9E+03 - 5.1E+03 |
-2.0E+03 - 5.2E+03 |
|
Victoria Harbour |
Dry |
-1.1E+04 - 1.1E+04 |
-1.1E+04 - 1.1E+04 |
Wet |
-1.4E+04 - 8.5E+03 |
-1.4E+04 - 8.3E+03 |
[1] Please
refer to Appendix 5.8 for the current flow direction of
different cross sections.
Table 5.38 Comparison of Ebb/Flood Tidal Flow Volume at
Concerned Channels
Channels |
Ebb Tidal Flow (m3) |
Flood Tidal Flow (m3) |
||||||
Scenario
H01 |
Scenario
H02 |
Difference |
Scenario
H01 |
Scenario
H02 |
Difference |
|||
Dry Season |
||||||||
Siu Lam |
1.5E+10 |
1.5E+10 |
-8.1E+07 |
-0.5% |
-1.8E+10 |
-1.8E+10 |
6.9E+07 |
-0.4% |
Kap Shui Mun |
4.3E+09 |
4.3E+09 |
4.1E+07 |
1.0% |
-5.1E+09 |
-5.2E+09 |
-8.7E+07 |
1.7% |
Ma Wan |
1.0E+10 |
1.0E+10 |
-1.0E+08 |
-1.0% |
-1.3E+10 |
-1.3E+10 |
1.5E+08 |
-1.2% |
Rambler |
1.3E+09 |
1.3E+09 |
-1.7E+07 |
-1.3% |
-6.1E+08 |
-6.0E+08 |
1.6E+06 |
-0.3% |
Victoria |
2.3E+09 |
2.3E+09 |
-7.8E+06 |
-0.3% |
-4.0E+09 |
-3.9E+09 |
7.3E+06 |
-0.2% |
Wet Season |
||||||||
Siu Lam |
1.5E+10 |
1.5E+10 |
-1.2E+08 |
-0.8% |
-1.6E+10 |
-1.6E+10 |
-6.2E+07 |
0.4% |
Kap Shui Mun |
4.6E+09 |
4.7E+09 |
3.5E+07 |
0.7% |
-3.6E+09 |
-3.8E+09 |
-1.4E+08 |
3.8% |
Ma Wan |
9.7E+09 |
9.6E+09 |
-1.4E+08 |
-1.5% |
-1.3E+10 |
-1.2E+10 |
9.3E+07 |
-0.7% |
Rambler |
1.5E+09 |
1.5E+09 |
-1.6E+07 |
-1.1% |
-2.8E+08 |
-2.9E+08 |
-1.0E+07 |
3.7% |
Victoria |
3.8E+09 |
3.8E+09 |
-1.1E+07 |
-0.3% |
-2.4E+09 |
-2.4E+09 |
-6.0E+06 |
0.3% |
[1] Please refer to Appendix 5.8 for the current
flow direction of different cross sections.
[2] The presented values are the cumulative tidal
flow volume within a 15-day spring-neap cycle.
Table
5.39 Comparison of Cumulative Discharge Results at
Concerned Channels
Channels |
Scenario H01 (m3) |
Scenario H02 (m3) |
Cumulative Change (m3) |
Daily Maximum Tidal Flow of
Scenario H01 (m3) |
Change to Tidal Flow (%) |
||
15days |
Daily
Averaged |
||||||
|
A |
B |
C |
D |
E |
F |
|
Dry Season |
|||||||
Siu Lam |
-2.9E+09 |
-2.9E+09 |
-1.2E+07 |
-8.1E+05 |
1.40E+09 |
-0.1 |
|
Kap Shui Mun |
-8.5E+08 |
-9.0E+08 |
-4.6E+07 |
-3.0E+06 |
4.10E+08 |
-0.7 |
|
Ma Wan |
-2.8E+09 |
-2.7E+09 |
4.9E+07 |
3.3E+06 |
1.01E+09 |
0.3 |
|
Rambler |
7.0E+08 |
6.8E+08 |
-1.5E+07 |
-1.0E+06 |
1.18E+08 |
-0.9 |
|
Victoria |
-1.6E+09 |
-1.6E+09 |
-4.6E+05 |
-3.0E+04 |
2.99E+08 |
0.0 |
|
Wet Season |
|||||||
Siu Lam |
-6.2E+08 |
-8.0E+08 |
-1.8E+08 |
-1.2E+07 |
1.40E+09 |
-0.8 |
|
Kap Shui Mun |
1.0E+09 |
9.1E+08 |
-1.0E+08 |
-6.9E+06 |
4.24E+08 |
-1.6 |
|
Ma Wan |
-2.9E+09 |
-2.9E+09 |
-4.8E+07 |
-3.2E+06 |
9.85E+08 |
-0.3 |
|
Rambler |
1.2E+09 |
1.2E+09 |
-2.7E+07 |
-1.8E+06 |
1.33E+08 |
-1.3 |
|
Victoria |
1.4E+09 |
1.4E+09 |
-1.7E+07 |
-1.1E+06 |
3.09E+08 |
-0.4 |
|
Notes:
[1] A 15-day spring-neap
cycle in a typical wet/dry season is considered. The daily average cumulative
change (D) = C/ 15days.
[2] The daily
tidal flow range is the highest ebb/flood tide volume within the typical
season.
[3] F = D / E
[4] Please
refer to Appendix
5.8 for the current flow direction of different cross sections.
Table
5.40 Comparison
of Depth Averaged Velocity at Concerned Channels
Channels |
Seasons |
Seasonal
Average of Depth Averaged Velocities (m/s) |
Difference
(m/s) |
Difference
(%) |
||
Scenario
H01 |
Scenario
H02 |
|||||
Siu Lam |
Dry |
0.46 |
0.47 |
0.01 |
2.8 |
|
Wet |
0.40 |
0.41 |
0.01 |
1.9 |
||
Kap Shui Mun |
Dry |
0.99 |
1.00 |
0.01 |
1.1 |
|
Wet |
0.89 |
0.90 |
0.02 |
1.8 |
||
Ma Wan Channel |
Dry |
0.53 |
0.52 |
-0.01 |
-1.2 |
|
Wet |
0.55 |
0.54 |
-0.01 |
-0.9 |
||
Rambler Channel |
Dry |
0.27 |
0.27 |
0.00 |
-0.9 |
|
Wet |
0.25 |
0.25 |
0.00 |
0.0 |
||
Victoria Harbour |
Dry |
0.30 |
0.30 |
0.00 |
-0.3 |
|
Wet |
0.30 |
0.30 |
0.00 |
-0.1 |
||
5.7.3.5 Considering that the overall hydrodynamic impacts on the marine waters due to the reclamation is insignificant and considering that there are no additional pollution sources induced by the project, the predicted water quality impact on marine waters due to the operational phase of the Project is minimal.
5.7.4 Surface Run-off from Paved Areas of the Project
5.7.4.1 Surface run-offs would typically contain pollutants that are deposited onto paved surfaces including roads, bridges, administration buildings and ventilation buildings which are then discharged to existing waterways during rainfall and storms via drainage systems, and are considered as a non-point source. The key pollutants in concern include sediments, oil and grease, heavy metals, debris, rubber, and fertilizers.
5.7.4.2 Pollutants such as rubber, debris, oil and grease and sediments are mostly generated by road users (i.e. vehicles), and are accumulated on the roads during dry periods, most of the accumulation is found in slightly depressed and at-grade road sections where sediment and silt will be carried and deposited. Pollutants deposited on the road surface will be washed away from the roads by run-off generated during rainfall and storms events, where a large proportion of the rainfall landing on road hard surfaces will reach the surface water drainage systems.
5.7.4.3 Factors including climatic conditions and intensity of precipitation, topography, and the degree of urbanisation has a significant influence on the characteristics of road run off. Following high intensity precipitation, the road surface may be scoured, resulting in an initial run-off that is referred to as the “first-flush”, which typically contains a high amount of pollutants, and may include significant water quality impacts on the water bodies. Subsequent run-offs may contain lower levels of pollutants. Overall, with the application of adequate mitigation measures such as providing adequate silt traps and oil interceptors as necessary at road drainages described in Section 5.11, any water quality impacts can be reduced to an acceptable level.
5.7.5 Drainage of Road Surface and Tunnel Runoff
5.7.5.1 During or after rainstorm events, rainwater fell on the at-grade roads and viaducts may flow into the drainage system, and seepage of groundwater into the tunnel may generate tunnel run-off. In addition, the regular cleansing of the tunnel will also generate tunnel run-off. These run-off may contain limited amount of SS, oil and grease. Directly discharge of tunnel run-off into nearby waterbodies may induce adverse water quality impact and should be avoided. No adverse water quality impacts are anticipated with the proper implementation of recommended mitigation measures such as the installation of silt traps and oil/grit interceptors as necessary as described in Section 5.12.
5.7.6 Sewage Effluent from the Proposed Buildings
5.7.6.1 During the operational phase, the sewage generated at administration buildings proposed at Lam Tei and Ng Kwu Leng would be a pollution source. Staff and workers stationed at the administration buildings will generate sewage through toilet and sanitary facilities. To avoid adverse water quality impacts, the sewage should not be discharged to waterbodies, and instead discharged through sewers that are connected to public sewerage systems which are located at the vicinity of the buildings.
5.7.6.2 No toiletry facilities are proposed for all ventilation buildings. It is therefore considered that no sewage will be generated at the ventilation buildings. Adverse impacts are therefore not anticipated.
5.7.7 Wastewater Generated from Washing and Maintenance Operations
5.7.7.1 Wastewater will be generated from washing and maintenance operations associated with work vehicles and the maintenance activities for the tunnel ventilation system. Direct discharge of the generated wastewater to the nearby drainage system and waterbodies will induce adverse water quality impacts and should be avoided, the wastewater should instead be discharged to the sewerage system.
5.7.7.2 The estimated amount of wastewater generated by washing and maintenance operations associated with the tunnel system would be approximately 300 m3/day, which includes water used for general cleansing (using water and vacuuming cleaning only) of the tunnel surface and the ventilation system. The wastewater generated from general cleansing of ventilation system may include dusts and undissolved oils.
5.7.7.3 The estimated amount of wastewater generated by washing and maintenance activities of work vehicles is approximately 3.0 m3/day. Wastewater from washing and maintenance operations associated work vehicles usually contains hydrocarbon pollutants such as petroleum and diesel.
5.7.7.4 No adverse water quality impact is anticipated with the proper implementation of recommended mitigation measures such as discharging wastewater to the public sewerage system properly, as described in Section 5.12.
5.8 Cumulative Impacts from Concurrent Projects
5.8.1.1 The construction of the Project may potentially overlap with the construction phase of Road P1 (Tai Ho - Sunny Bay Section), based on the latest information. Hence, the proposed dredging at Sham Shui Kok is included within the construction phase water quality model. No unacceptable cumulative water quality impacts have been anticipated given that proper mitigation measures (i.e. deployment of silt curtains) are implemented.
5.8.1.2 The construction of the Project may potentially overlap with the construction periods of other nearby concurrent projects as identified in Section 2. The identified concurrent projects within the 500m Assessment Area of the Project may induce cumulative water quality impacts, which are evaluated and discussed in Appendix 5.9. No cumulative water quality impacts have been anticipated for concurrent projects.
5.8.1.3 Appendix 5.9 also tabulates and evaluates those concurrent projects that are beyond the 500m Assessment Area of the Project. Given the large separation distances, the cumulative impacts from these concurrent projects beyond 500m would not be significant.
5.9 Recommended Mitigation Measures – Construction Phase (Marine Based Works)
5.9.1.1 The potential impact associated with sewage generated by the workforce shall be controlled by the provision of adequate sanitary facilities such as portable chemical toilets on the marine vessels. The storage and disposal of chemical waste shall follow the guidelines stipulated in the Waste Disposal (Chemical Waste) (General) Regulations. Besides, overflow of filling materials in the barges or hoppers can cause water pollution during loading or transportation. Good management practice such as limiting the capacity of a barge to avoid overflow of filling material can minimise the potential water quality impact.
5.10 Recommended Enhancement Measures – Construction Phase (Marine Works)
5.10.1.1 The deployment of a silt curtain can reduce the sediment dispersing away from the reclamation site, with the aim of localising the sediment plume because of the dredging activities. The feasibility of deploying a double silt curtain (adopted in the approved EIA Report of Hong Kong International Airport 3rd Runway System (AEIAR-185/2014)) has been carefully considered to further enhance the water quality. However, considering that the current flow velocity at the vicinity of TLT exceeds 1.0m/s, the effectiveness of a double layer silt curtain would be significantly reduced. Hence, the deployment of a single layer silt curtain is recommended as a water quality enhancement measure throughout the reclamation works at TLT.
5.10.1.2 The quantitative water quality modelling results (i.e. Scenario WQ01a and b) have shown that dredging even without the use of any enhancement measures (i.e. deployment of silt curtain), full compliance of the assessment criteria have been met at the concerned key observation points. Nonetheless, scenarios with the implementation of the enhancement measure (i.e. Scenario WQ02a and b) have shown that the deployment of a silt-curtain would further reduce water quality impacts due to dredging works, whilst continuing to ensure the full compliance of assessment criteria at all key observation points.
5.10.2 Construction of Mud Pit
5.10.2.1 The deployment of silt curtain is also recommended as a water quality enhancement measure during the formation of mud pit. The mud pit should be completely sealed to prevent any leakage of backfilled sediments to the surrounding marine waters.
5.11 Recommended Mitigation Measures – Construction Phase (Land Based Works)
5.11.1 Construction Run-off and General Construction Activities
5.11.1.1 Best Management Practices (BMPs) of mitigation measures in controlling water pollution and good site management, as specified in ProPECC PN 1/94, should be followed as applicable to prevent run-off with a high level of SS from entering the surrounding waters. Additionally, all effluent discharged from the construction site should comply with the standards stipulated in the TM-DSS. The following mitigation measures are recommended to protect the water quality of the nearby waterbodies, and should provide sufficient and adequate control to site discharges to minimise adverse water quality impacts when properly implemented.
5.11.1.2 All effluent discharged from the construction site should comply with the standards stipulated in the TM-DSS. The following measures are recommended to protect the water quality of the nearby water, and when properly implemented should be sufficient to adequately control site discharges to avoid water quality impacts:
· At the start of site establishment, perimeter cut-off drains to direct off-site water around the site should be constructed with internal drainage works and erosion and sedimentation control facilities implemented. Drains (both temporary and permanent drainage pipes and culverts), earth bunds or sand bag barriers should be provided on site to direct stormwater to silt removal facilities. The design of the temporary on-site drainage system will be undertaken by the contractor prior to the commencement of construction;
· The dikes or embankments for flood protection should be implemented around the boundaries of earthwork areas. Temporary ditches should be provided to facilitate the run-off activities discharge into an appropriate watercourse, through a silt/sediment trap. The silt/sediment traps should be incorporated in the permanent drainage channels to enhance deposition rates;
· The design of efficient silt removal facilities should be based on the guidelines in Appendix A1 of ProPECC PN 1/94. The detailed design of the sand/silt traps should be undertaken by the Contractor prior to the commencement of construction;
· Measures should be taken to minimise the ingress of site drainage into excavations. If the excavation of trenches in rainy seasons are necessary, it should be excavated and backfilled in short sections wherever practicable. Water pumped from trenches or foundation excavations should be discharged into storm drains installed with silt removal facilities;
· All open stockpiles of construction materials (i.e. aggregates, sand and fill material, etc.) should be covered with tarpaulin or similar fabric during rainstorms. Measures should be taken to prevent the washing away of construction materials, soil, silt or debris into any drainage system;
· Manholes (including newly constructed ones) should always be adequately covered and temporarily sealed to prevent silt, construction materials or debris from being washed into the drainage system and storm run-off being directed into foul sewers;
· Precautions should be taken during rainy seasons, and actions as summarised in Appendix A2 of ProPECC PN 1/94 should be taken when a rainstorm is forecasted or imminent. Particular attention should be paid to the control of silty surface run-off during storm events;
· All vehicles and plants should be cleaned before leaving construction sites to minimise the deposition of earth, mud, debris and other potentially polluting particles on roads. An adequately designed and sited wheel washing facilities should be provided at every construction site exit where practicable. Wash water should have sand and silt settled out and removed at least on a weekly basis to ensure the continued efficiency of the process. The section of access road leading to, and exiting from, the wheel-wash bay to the public road should be paved with sufficient back fall towards the wheel-wash bay to prevent vehicles from tracking of soil and silty water to public roads and drains;
· Oil interceptors should be provided in the drainage system downstream of any oil/fuel pollution sources. The oil interceptors should be emptied and cleaned regularly to prevent the release of oil and grease into the stormwater drainage system after accidental spillage. A bypass should be provided for the oil interceptors to prevent flushing during heavy rain;
· Construction solid waste, debris and rubbish on site should be collected, handled, and disposed of properly to minimise adverse water quality impacts;
· Water used for tests to check for leakages in structures and pipes should be reused for other purposes as far as practicable. Surplus unpolluted water could be discharged into stormwater drainage;
· Earthworks final surfaces should be compacted, and the subsequent permanent work or surface protection should be carried out immediately after the final surfaces are formed to prevent erosion of earth caused by rainstorms. Appropriate drainage with intercepting channels should be provided where necessary;
· Extracted groundwater from activities such as water pumped from basement or foundation construction, and groundwater seepage pumped from tunnel or cavern constructions should be discharged into stormwater drainage after the removal of silt through silt removal facilities; and
· Water used in ground boring and drilling for site investigation or rock/soil anchoring should as far as practicable be recirculated after sedimentation. When there is a need for final disposal, the wastewater should be discharged into stormwater drainage through silt removal facilities.
5.11.1.3 As recommended in DSD Technical Circular No. 1/2017 “Temporary Flow Diversions and Temporary Works Affecting Capacity in Stormwater Drainage System” and DSD’s Practice Notes No. 1/2017 “Design rainfall and profile for temporary works within the Dry Season”, the temporary drainage system during the construction phase should cope with a design return period of 1 in 10 years rainfall for dry season. For the design of temporary works and temporary flow diversion in the wet season, the design rainfall depths and profiles as stated in DSD Stormwater Drainage Manual (SDM) should be adopted. This is because rainfall intensity in the dry season is usually less than that encountered in the wet season.
5.11.1.4 Good site practices should be adopted to remove rubbish and litter from construction sites so as to prevent the rubbish and litter from spreading from thes site area. It is recommended to clean the construction sites on a regular basis.
5.11.1.5 Requirements to be incorporated in the contract document of the Project should be established based on the water quality mitigation measures as mentioned above.
5.11.2 Tunnelling and Underground Works
5.11.2.1 Whilst conducting tunnelling works, the Contractor should adopt suitable water control strategies as far as practicable, including:
· Probing ahead: The Contractor should undertake rigorous probing of the ground ahead of tunnel excavation works to identify zones of potential significant water inflow. The probe drilling results should be evaluated to determine where grouting is required in line with the tunnel ahead. In zones where significant water inflow could occur due to discrete, permeable features, grouting should be applied to reduce overall inflow of gsroundwater;
· Pre-grouting: Where water inflow quantities are excessive, pre-grouting will be required to reduce the water inflow into the tunnel, which will be achieved via a systematic and carefully specified protocol; and
· In principle, the grout pre-treatment would be designed based on probe hole drilling ahead of the tunnel face.
5.11.2.2 In the event of where there is still excessive drawdown of the groundwater table, even after the implementation of water control strategies, post-grouting should be applied as far as practicable, which is described below:
· Post-grouting: Groundwater drawdown will most likely be caused by inflows of water into the tunnel that have not been sufficiently controlled by pre-grouting measures. Should there be groundwater drawdown, post-grouting should be undertaken before the lining is cast. Whilst post-grouting is unlikely required, it should still be considered as a contingency measure to further reduce the permeability of the tunnel to limit groundwater inflow to acceptable levels.
5.11.3 Ventilation Buildings and Administration Buildings
5.11.3.1 For underground excavations for the proposed ventilation buildings and administration buildings which will require temporary dewatering during their construction, the following mitigation measures are recommended to minimise the potential adverse effects to the groundwater table during the works:
· Toe grouting should be applied beneath the toe level of the temporary/permanent cofferdam walls as necessary to lengthen the effective flow path of groundwater from outside and thus control the amount of water inflow to the excavation; and
· Recharge wells should be installed as necessary outside the excavation areas. Water pumped from the excavation areas should be recharge back onto the ground.
5.11.4 Sewage due to Construction Workforce
5.11.4.1 No sewage discharge to the drainage system, watercourses, and marine water will be allowed. Adequate and sufficient portable chemical toilets should be provided in the works areas to handle sewage generated by the construction workforce. Should there be any on-site kitchens or canteens, a temporary storage tank should be provided to collect wastewater. A registered collector should be employed to clean and maintain the chemical toilets on a regular basis.
5.11.4.2 Notices should be posted at conspicuous locations to remind the construction workforce not to discharge any sewage or wastewater into the surrounding environment. Regular environmental audit of the construction site should be conducted to provide an effective control of any malpractices and to achieve continual improvement of environmental performances on site.
5.11.5 Construction Works in Close Proximity of Inland Water
5.11.5.1 The practices outlined in ETWB TC (Works) No. 5/2005 “Protection of natural streams/rivers from adverse impacts arising from construction works” should also be adopted where applicable to minimise the water quality impacts. Relevant mitigation measures from the ETWB TC (Works) No. 5/2005 are listed below:
· Construction works close to the inland waters should be carried out in dry season as far as practicable where the flow in the surface channel or stream is low;
· Trenches should be dug and backfilled in short sections. Measures should be taken to minimize the ingress of rainwater into trenches;
· The use of less or smaller construction plants may be specified in areas close to the water courses to reduce the disturbance to the surface water;
· Temporary storage of materials (e.g. equipment, chemicals and fuel) and temporary stockpile of construction materials should be located well away from any watercourses during carrying out of the construction works;
· Stockpiling of construction materials and dusty materials should be covered and located away from any watercourses. Construction debris and spoil should be covered up and / or disposed of as soon as possible to avoid being washed into the nearby water receivers; and
· Proper shoring may need to be erected in order to prevent soil or mud from slipping into the watercourses.
5.11.5.2 In addition, WSD’s Conditions for Working within Water Gathering Grounds shall also be complied with. The conditions are provided in Appendix 5.10.
5.11.6 Removal or Diversion of Watercourses
5.11.6.1
During removal or diversion of
watercourses, precaution measures should be implemented to prevent adverse
water quality impact to the surrounding environment and downstream areas.
Removal or diversion of natural watercourses within the Tai Lam Country Park
would be totally avoided. Good site practices as described in ETWB TC(Works)
No. 5/2005 “Protection of natural streams/rivers from adverse impacts
arising from construction works” and ProPECC PN1/94 “Construction
Site Drainage” should be implemented. The following major measures
include:
· Cofferdams or impermeable structures should be installed as appropriate to isolate the water flow from the construction works area;
· Dewatering or flow diversion shall be conducted prior to the construction works to prevent water overflow to the surrounding area;
· Watercourse removal and flow diversion should be conducted in dry season as far as practicable when the water flow is low;
· Water drained from the watercourse shall be diverted to new/temporary drainage for watercourse diversion; and
· Any excavated land-based sediment from the diversion of watercourse shall be properly stored at bunded areas away from any watercourses and covered with tarpaulin before transporting out of the site.
5.11.7 Groundwater from Contaminated Areas and Contaminated Site Run-off
5.11.7.1 The remediation of contaminated land should be properly conducted following the recommendations proposed under Section 7.
5.11.7.2 Any excavated contaminated material and exposed contaminated surface should be properly housed and covered to avoid generation of contaminated run-off, the open stockpiling of contaminated materials should not be allowed. Any contaminated run-off generated under the construction process should be properly collected and treated as necessary before disposal.
5.11.7.3 The direct discharge of groundwater from contaminated areas is not allowed. Prior to any excavation works within potentially contaminated areas, the baseline groundwater quality in these areas should be reviewed based on the past relevant site investigation data and any additional groundwater quality measurements to be performed with reference to Guidance Note for Contaminated Land Assessment and Remediation, the review results should be submitted to EPD for approval. If the review results indicated that the groundwater generated from the excavation works would be contaminated, the contaminated groundwater should be either properly treated or properly recharged into the ground in compliance with the requirements of the TM-DSS.
5.11.7.4 If a water treatment facility is deployed on-site to treat the contaminated groundwater, it should be equipped with suitable instruments (e.g. oil interceptor, activated carbon, etc.) to reduce the pollution level to an acceptable standard and remove to any prohibited substances (such as total petroleum hydrocarbon) to an undetectable range. All treated effluent from the wastewater treatment plant shall meet the requirements as stipulated in the TM-DSS and should be either discharged into the foul sewers or tankered away for proper disposal.
5.11.7.5 If the deployment of a treatment facility to treat the contaminated groundwater is not feasible, groundwater recharging wells should be installed as appropriate to recharge the contaminated groundwater back onto the ground. The recharging wells should be selected at places where the groundwater quality will not be affected by the recharge operation as stipulated in TM-DSS. The baseline groundwater quality should be determined before selecting the recharge wells and a working plan should be submitted to EPD for agreement. Pollution levels of the recharged groundwater shall not be higher than pollutant levels of ambient groundwater at the recharge well. Groundwater monitoring wells should be installed near the recharge points to monitor the effectiveness of the recharge wells, and to ensure that no there is no increase of groundwater level and the transfer of pollutants beyond the site boundary. Prior to the recharge, oil and grease, if any, should be removed as necessary by installing an oil interceptor. The Contractor should apply for a discharge licence under the WPCO through the Regional Office of EPD for groundwater recharge operation or the discharge of treated groundwater.
5.11.7.6 All exposed earth areas should be completed and vegetated as soon as possible after earthworks have been completed. If excavation of soil cannot be avoided during the rainy season, or at any time of year when rainstorms are likely, exposed slope surfaces should be covered by tarpaulin or other means. All drainage facilities and erosion and sediment control structures should be regularly inspected and maintained to ensure proper and efficient operation at all times and particularly following rainstorms. Deposited silt and grit should be removed regularly and disposed of by spreading evenly over stable, vegetated areas. For works area that is close to watercourses, excavation works shall avoid the rainy season as far as possible, and excavation works shall be proceeded section by section.
5.11.8 Operation of Barging Points
5.11.8.1 To minimise the adverse water quality impacts of the surface run-off generated by the operation of the barging point, the mitigation measures recommended under Section 5.11.1 should be followed. To minimise the potential adverse water quality impact due to the transportation of spoil using the barging point, the following good site practices should be strictly followed:
· Loading of barges and hoppers should be controlled to prevent the splashing of material into the surrounding water. Barges or hoppers should not be filled to a level that will cause the overflow of materials or polluted water during loading or transportation; and
· All vessels should be sized so that adequate clearance is maintained between vessels and the seabed in all tide conditions, to minimise that undue turbidity is not generated by turbulence from vessel movement or propeller wash.
5.11.9 Accidental Spillage of Chemicals
5.11.9.1 The Contractor must be registered as a chemical waste producer if chemical wastes are produced from the construction activities. The Waste Disposal Ordinance (Cap. 354) and its subsidiary regulations, in particular the Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C), should be observed and complied with for the control of chemical wastes. The Contractor is also recommended to develop management procedures for the chemicals used and prepare an emergency spillage handling procedure to deal with chemical spillage in case of an accident occurs, a contingency plan for any accidental spillage and heavy rainfall event should also be devised.
5.11.9.2 Any services and maintenance facilities should be located on hard standings within a bunded area, sumps and oil interceptors should be provided. Activities with the potential for accidental leakage and spillage of chemicals, including the maintenance of vehicles and equipment should only be undertaken within areas that are appropriately equipped to control the discharges from these potential accidents. The service and maintenance, and any chemical storage areas should not be positioned near watercourses as a safeguard measure.
5.11.9.3 Disposal of chemical wastes should be carried out in compliance with the Waste Disposal Ordinance. The Code of Practice on the Packaging, Labelling, and Storage of Chemical Wastes published under the Waste Disposal Ordinance details the requirements to deal with chemical wastes. General requirements are given as follows:
· Suitable containers should be used to hold the chemical wastes to avoid leakage or spillage during storage, handling, and transport;
· Chemical waste containers should be suitably labelled, to notify and warn the personnel who are handling the wastes, to avoid accidents; and
· Storage area should be selected at a safe location on-site and adequate space should be allocated to the storage area.
5.11.10 Adoption of Marine Based Construction Method
5.11.10.1 To minimise the water quality impacts induced by the reclamation works, all filling works should be conducted within the completed leading seawall, so that reclamation filling materials would not be discharged into the open sea.
5.12 Recommended Mitigation Measures – Operational Phase
5.12.1 Reclaimed Northern Anchor
5.12.1.1 As discussed in Section 5.7, the hydrodynamic modelling results have indicated that the overall change in hydrodynamic regime due to the reclaimed northern anchor at Tsing Lung Tau are insignificant. Hence it is also expected that the operational phase water quality impacts would be minimal. Hence no mitigation measures are considered necessary.
5.12.2 Surface Run-off from Paved Areas of the Project
5.12.2.1 Surface run-off is identified as a source of water pollution. The paved and developed areas, especially the new roads and tunnels will increase the quantity of surface run-off. The presence of oil, grease and grit on the paved surfaces could be washed into the nearby drainage systems, or nearby watercourses during rainfall.
5.12.2.2 To minimise the adverse water quality impacts, the road drainages should be equipped with adequate silt traps and oil interceptors as necessary. Regular washing of the roads and paved areas are also recommended to prevent the accumulation of pollutants. To maintain the equipment’s efficiency, contents collected in silt traps and oil interceptors should be cleared regularly, and transferred to an appropriate disposal facility, or to be collected for reuse if possible. Considering the recommended mitigation measure, the adverse water quality impact generated by surface run-off is kept to a minimum.
5.12.3 Drainage of Road Surface and Tunnel Runoff
5.12.3.1 Tunnel run-off is also identified as a non-point water pollution sources. To minimise the adverse water quality impacts, the discharge of road drainage channels should pass through treatment facilities (i.e. silt traps and oil/grit interceptors) as necessary to remove oil, grease and sediment content before the run-off is discharged to the public stormwater drainage system. The treatment facilities including silt traps and oil interceptors should be cleaned and maintained regularly to ensure their continued effectiveness. Oily contents of the oil interceptors should be transferred to an appropriate facility, or where possible, reused. With the proper implementation of the recommended mitigation measures, no adverse water quality impacts are anticipated.
5.12.4 Sewage Effluent from the Proposed Buildings
5.12.4.1 Sewage effluent generated should be discharged to the existing sewerage networks identified at the vicinity of the proposed administration buildings, the sewerage system at these buildings should be connected properly whilst ensuring that the public networks have a sufficient capacity to handle the sewage load generated. Toilets and other sanitary facilities should be cleaned and maintained on a regular basis.
5.12.5 Wastewater Generated from Washing and Maintenance Operation
5.12.5.1 Wastewater generated by washing and maintenance activities of ventilation systems should be collected and treated via an active carbon filter before being discharged to public stormwater drainage system, whereas wastewater generated by washing and maintenance activities associate with work vehicles should be collected and treated by petrol interceptors before being discharged. A Licensed Chemical Contractor should be employed to collect and dispose of spent lubrication oil generated from vehicle maintenance activities in compliance with the Waste Disposal Ordinance. No direct discharge of these wastewaters into the inland water will be allowed, and instead should be discharged to the public sewerage system properly.
5.13.1.1 With the full implementation of the recommended mitigation measures for the construction phase of the proposed Project, no unacceptable residual impacts on water quality are anticipated. It is recommended that regular audit of the implementation of the recommended mitigation measures be carried out during the construction phase.
5.13.1.2 With the full implementation of the recommended mitigation measures for the operational phase of the proposed Project, no unacceptable residual impacts on water quality are anticipated.
5.14 Environmental Monitoring and Audit (EM&A)
5.14.1.1 With the proper implementation of the recommended mitigation measures, no unacceptable water quality impacts are expected during the construction phase of the Project. Nevertheless, inland water quality monitoring is still recommended. Details of the monitoring and auditing requirements are provided in the stand-alone EM&A Manual for the Project.
5.14.1.2 Marine water quality monitoring is recommended during dredging/filling associated with the reclamation works at TLT, the sampling locations are recommended at the key concerned WSRs. Details of the monitoring and auditing requirements are provided in the stand-alone EM&A Manual for the Project.
5.14.1.3 As no adverse water quality impact is anticipated for the operational phase of the Project, no EM&A activities are required.
5.15.1.1 The key water quality impact associated with the Project which could impact the nearby waterbodies and water sensitive receivers are mainly associated with the construction phase of the Project, which includes general construction activities, construction site run-off, tunnelling and underground works, sewage due to construction workforce, construction works in close proximity of inland water, groundwater from contaminated areas and contaminated site run-off, the accidental spillage of chemicals, and dredging and filling works for the reclamation. With the proper implementation of recommended mitigation measures, no adverse water quality impacts would be anticipated during the construction phase of the Project.
5.15.1.2 During the operational phase of the Project, the major sources of potential adverse water quality impact include road run-off discharged from paved roads and developments proposed under the Project, the sewage generated by the proposed ventilation and administration buildings, and the change in hydrodynamic regime due to the reclamation. However, with proper implementation of the recommended mitigation measures, no adverse water quality impacts would be anticipated during the operational phase of the Project.