TABLE OF CONTENTS

EXECUTIVE SUMMARY

1.     INTRODUCTION

Background

Summary of Construction Works

2      ENVIRONMENTAL MONITORING AND AUDIT REQUIREMENTS

Monitoring Parameters

Monitoring Methodology and Calibration Details

Environmental Quality Performance Limits (Action and Limit Levels)

Environmental Mitigation Measures

3      MONITORING RESULTS

Air Quality

Noise

Water Quality

4      INSPECTION RESULTS

Implementation Status of Environmental Mitigation Measures

Status of Environmental Licensing and Permitting

Advice on Solid and Liquid Waste Management Status

5      NON-COMPLIANCE (EXCEEDANCE) OF THE ENVIRONMENTAL QUALITY PERFORMANCE LIMITS (ACTION AND LIMIT LEVELS)

Summary of Exceedances

Review of the Reasons for and the Implications of Non-compliance

Summary of Actions Taken

6      ENVIRONMENTAL COMPLAINTS

Complaint Log

Complaint Response Procedure

7      NOTIFICATION OF SUMMONS AND SUCCESSFUL PROSECUTIONS

8      COMMENTS, CONCLUSIONS AND RECOMMENDATIONS

 

List of Table

Table 1.1       Contact Information of Key Personnel

Table 1.2       Summary of Works Undertaken in the Reporting Quarter

Table 3.1       Comparison of Baseline and Averaged Impact Monitoring Results of 1-hr TSP Concentration

Table 3.2       Comparison of Baseline and Averaged Impact Monitoring Results of 24-hr TSP Concentration

Table 3.3       Comparison of Baseline and Impact Monitoring Results of Noise (Day-time) Monitoring

Table 3.4       Total Number of Water Quality Exceedances and Percentage Differences of Number of Water Quality Exceedances in the Quarter

Table 3.5       Summary of Statistical Analysis of SS Results

Table 4.1      Waste Disposal in the Reporting Quarter

 

List of Figures

 

Figure 1.1       Project Site Location

Figure 2.1       Air Quality and Noise Environmental Monitoring Stations (1 of 3)

Figure 2.2       Air Quality and Noise Environmental Monitoring Stations (2 of 3)

Figure 2.3       Air Quality and Noise Environmental Monitoring Stations (3 of 3)

Figure 2.4       Water Quality Monitoring Stations (1 of 2)

Figure 2.5       Water Quality Monitoring Stations (2 of 2)

Figure 6.1       Complaint Response Procedures

 

Appendices

Appendix A     Project Organisation Chart and Contact Details of the Project Organisation

Appendix B     Construction Programme

Appendix C     Details of Monitoring Requirements

Appendix D     Copy of Equipment Calibration Certificates

Appendix E     Environmental Quality Performance (Action/Limit) Levels

Appendix F     Implementation Status of Environmental Mitigation Measures (EMIS)

Appendix G    Graphical Presentation of Air Quality Monitoring Results

Appendix H     Graphical Presentation of Noise Monitoring Results

Appendix I      Summary Status of Environmental Licences and Permits

Appendix J     Graphical Presentation of Water Monitoring Results (DOSM, DOB, TUR & SS)

Appendix K     Summary of Environmental Complaints

Appendix L     Statistical Analysis of the Trend of Suspended Solids in the Reporting Quarter

Appendix M    Landscape and Visual Audit and Monitoring (Operational Phase) Bi-monthly Inspection Report No.01 (December 2006)