TABLE OF CONTENTS
14. landscape and visual
impact
14.2 Scope
and Content of Assessment Approach
14.3 Environmental
Legislations, Standards and Guidelines
14.5 Review
of Planning and Development Control Framework
14.7 Landscape
Impact Assessment
14.9 Landscape
and Visual Mitigation Measures
14.11 Cumulative
Impacts from concurrent Projects
14.12 Monitoring
and Audit Requirement
List of Tables
Table 14.1 Relationship between
Sensitivity and Magnitude of Change in Defining Impact Significance
Table 14.3 Summary of review of Planning
Framework
Table 14.4.1 Baseline Landscape
Resources
Table 14.4.2 Landscape Character
Area
Table 14.5 Broad Estimated Number of
Trees within each LR
Table 14.6 Visually
sensitive receivers (VSRs) and their sensitivity.
Table 14.7 Magnitude of Landscape Impact during Construction and
Operation
Table 14.8 Magnitude of Visual Impact
during Construction and Operation Phases
Table 14.9 Proposed Design Measures incorporated in the Project
Table 14.13 Significance of Landscape
Impact during Construction and Operational Phases.
Table 14.14 Significance of Visual
Impacts during Construction and Operation Phases.
List of Figures
Project Location Plan |
|
Existing Outline Zoning Plan |
|
Revised RODP |
|
Landscape Resources |
|
Landscape Character Area |
|
Photo of Landscape Resources (1) |
|
Photo of Landscape Resources (2) |
|
Photo of Landscape Resources (3) |
|
Aerial Photo of the
Project |
|
Photo of Landscape Character Area (1) |
|
Photo of Landscape Character Area (2) |
|
Visual Envelope, Visual Sensitive
Receivers and Location of Viewpoints |
|
Location of Designated Projects and
Viewpoints |
|
Landscape Resource Impact Plan and Blow-Up
Plan |
|
Landscape Character Area Impact Plan |
|
Landscape Master Plan |
|
Landscape and Visual Mitigation Plan
(Overall) |
|
Landscape and Visual Mitigation Part
Plans (1-8) |
|
Figure 14.15-16 |
Not used |
Landscape and Visual Mitigation Measure for Schedule 2 DPs |
|
Figure 14.17.17 |
Not used |
Landscape and Visual Mitigation Measure for Schedule 2 DPs |
|
Figure 14.18-21 |
Not used |
Photomontage VP1 |
|
Photomontage VP2 |
|
Photomontage VP3 |
|
Photomontage VP4 |
|
Photomontage VP5 |
|
Photomontage VP6 |
|
Photomontage VP7 |
|
Photomontage VP8 |
|
Photomontage VP9 |
|
Photomontage VP10 |
|
Photomontage VP11 |
|
Photomontage VP12 |
|
Photomontage VP13 |
|
Photomontage VP14 |
|
Photomontage VP15 |
|
Photomontage VP16 |
|
Photomontage VP17 |
|
Photomontage VP18 |
List of Appendices
Broad-brush tree survey |
|
Planning, urban design, blue-green framework and building height concept |
|
Typical section for noise barriers |
|
Perspective view of designated projects |
·
DP1 1 – Construction and operation of new primary distributor road P1,
district distributor road D1, D2, D3, D4, D5 and D6.
·
DP2 1– Construction and operation of a new effluent polishing plant
·
DP3 1 –Construction and operation of a new water reclamation plant
·
DP4 2 – Construction and operation of a refuse transfer
station (RTS)
·
DP5 2 – Construction and operation of two 400kV electricity
substations
·
DP7 1 – Construction and operation of recreational development for proposed
Sites O.1.1, O.1.2, and O.1.3 (as open space) encroach into Deep Bay Buffer
Zone 2
Note:
2
Subject to separate EIA Study, as required.
3
The future zoning of the concerned ‘Conservation
Area’ as shown on Figure 1.2 are subject to
change due to the land use proposals as reflected in the Revised RODP.
i.
Identification and plotting of visual envelope of the proposed Project
within the assessment area.
ii.
Identification of the key groups of sensitive receivers within the
visual envelope and their views at both ground level and elevated vantage
points.
iii.
Description of the visual compatibility of the Project with the
surrounding and the planned setting, and its obstruction and interference with
the key views of the adjacent areas.
iv.
Description of the severity of visual impact in terms of distance, nature,
and number of sensitive receivers. The
visual impact of the Project with and without mitigation measures are included
so as to demonstrate the effectiveness of the proposed mitigation measures.
v.
Clear evaluations and explanation with supportive arguments of all
relevant factors considered in arriving at the significant thresholds of visual
impact.
·
Environmental Impact Assessment Ordinance (Cap.499) and the Technical
Memorandum on EIA Process (EIAO-TM), particularly Annexes 3, 10, 11, 18, 20 and
21;
·
Hong Kong Planning Standards and Guidelines (HKPSG);
·
Town Planning Ordinance (Cap 131);
·
TPB PG-NO.12C - Town Planning Board Guidelines for Application for Developments
within Deep Bay Area Under Section 16 of the Town Planning Ordinance;
·
TPB PG-NO. 41- Town Planning Board Guidelines on Submission of Visual
Impact Assessment for Planning Applications to the Town Planning Board;
·
Approved Kwu Tung South OZP No. S/NE-KTS/18;
· Approved Kwu Tung North OZP No. S/KTN/4;
·
Approved San Tin Outline Zoning Plan No.
S/YL-ST/8;
·
Approved Mai Po and Fairview Park OZP No. S/YL-MP6;
·
Approved Ngau Tam Mei Outline Zoning Plan No. S/YL-NTM/12;
·
Approved Lok Ma Chau Loop Outline Zoning Plan No. S/LMCL/2;
·
Forests and Countryside Ordinance (Cap. 96) and its subsidiary
legislation the Forestry Regulations;
·
Pesticides Ordinance (Cap. 133) and its
subsidiary legislation and the Pesticides Regulations;
·
Plant (Importation and Pest Control) Ordinance
(Cap. 207);
·
Country Parks Ordinance (Cap 208);
·
Marine Parks Ordinance (Cap 476) and associated subsidiary legislation;
·
Protection of Endangered Species of Animals and Plants Ordinance, Cap.
586;
·
SILTech Publication (1991) – Tree Planting and Maintenance in Hong Kong
(Standing Interdepartmental Landscape Technical Group) [11-23];
·
GEO Publication No. 1/2011 – Technical Guidelines on Landscape Treatment
for Slopes;
·
Land Administration Office Instruction (LAOI) Section D-12 – Tree
Preservation;
·
EIAO Guidance Note No. 8/2010;
·
DEVB TCW No. 2/2012 on Allocation of Space for Quality Greening on
Roads;
·
DEVB TC(W) No. 5/2017 - Community Involvement in Planting Works;
·
DEVB TCW No. 6/2015 – Maintenance of Vegetation and Hard Landscape
Features;
·
DEVB TC(W) No. 5/2020- Registration and Preservation of Old and Valuable
Trees;
·
DEVB TCW No. 3/2012 on Site Coverage of Greenery for Government Building
Projects;
·
DEVB TCW No. 1/2018 on Soft Landscape Provisions for Highway Structures;
·
DEVB TCW No. 4/2020 – Tree Preservation;
·
DEVB Publication 2012 – Guidelines on Greening of Noise Barriers;
·
ETWB TCW No. 24/2004 – Specification Facilitating the Use of Concrete
Paving Units Made of Recycled Aggregates;
·
ETWB TCW No. 36/2004 – The Advisory Committee on the Appearance of
Bridges and Associated Structures (ACABAS);
·
ETWB TCW No. 5/2005 – Protection of Natural Streams/Rivers from adverse
Impacts Arising from construction Works;
·
WBTC No. 25/93 – Control of Visual Impact of Slopes;
·
WBTC No. 17/2000 – Improvement to the Appearance of slopes in connection
with WBTC 25/93;
·
Hong Kong 2030 Planning Vision and Strategy Final Report;
·
Landscape Value Mapping of Hong Kong;
·
LAO PN no. 2/2020A on Tree Preservation and Removal Proposal for
Building Development in Private Projects Compliance of Tree Preservation Clause
under Lease;
·
Committee Paper NCSC 9/06 “Advisory Council on the Environment Nature
Conservation Subcommittee – Fung Shui Woods in Hong Kong”;
·
GEO Information Note 01/2021 - Surface Protection and
Appearance of Slopes; and
·
Government General Regulation 740 – restrictions on the
preservation and felling of trees in Hong Kong;
·
Guidelines on Soil Volume for Urban Trees;
·
Guidelines on Soil Improvement;
·
Street Tree Selection Guide; and
·
Wild Animal Protection Ordinance (Cap. 170).
·
Identification and
description of the baseline landscape resources (LRs) and landscape characters
area (LCAs) found within the assessment area. The assessment area includes all
areas within 500 m of the Project area. This is achieved by site visits and
desktop study of topographical maps, information databases and photographs. In this report, buildings, roads, and
pavement are not considered as landscape resources and have therefore not been
included in the mapping of resources. However, it is inevitable that during the
process of identification for broad areas of landscape resources, some
buildings, roads, hard paving, or other features may be included – or
conversely some trees or other resource may be left out. This report attempts
to formalise boundaries between distinct areas of landscape resources for the
purpose of impact assessment and should not be construed as reflecting every
single variable on the ground.
·
Assessment of the degree of
sensitivity of the landscape resources (LRs) and landscape character areas
(LCAs). This is
influenced by a number of factors including whether the resource/character is
common or rare, whether it is considered to be of local, regional, national or
global importance, whether there are any statutory or regulatory
limitations/requirements relating to the resource, the quality of the
resource/character, the maturity of the resource and the ability of the
resource/character to accommodate change.
The
sensitivity of each LR and LCA is classified as follows:
High: |
Important landscape resources and
landscape character of particularly distinctive in character or high
importance, sensitive to relatively small change. |
Medium: |
Landscape resources and landscape
character of moderately valued landscape characteristics reasonably tolerant
to change. |
Low: |
Landscape resources and landscape
character, the nature of which is largely tolerant to change. |
·
Identification of potential
sources of landscape changes. These are the various elements of the
construction works and operation procedures that would generate landscape
impacts.
Assessment
of the potential magnitude of landscape changes. Factors considered include:
-
the compatibility with the surrounding landscape;
-
the duration of the impact under construction and operation phase;
-
scale of development; and
-
reversibility of change.
The
magnitude of landscape changes is classified as follows:
Large: |
The landscape resources and landscape
character would incur a major change. |
Intermediate: |
The landscape resources and landscape
character would incur a moderate change. |
Small: |
The landscape resources and landscape
character would incur slight or barely perceptible change. |
Negligible: |
The landscape resources and landscape
character would incur no discernible change. |
·
Identification of potential
landscape mitigation measures. These may take the form of adopting basic
engineering design to prevent and/or minimise adverse landscape impacts before
adopting other mitigation or compensatory measures to alleviate the
impacts. Potential mitigation measures
should also include the preservation of vegetation and natural landscape resources,
transplanting trees with good condition and high amenity value, enhancement of
existing landscape quality by providing of planting with screening, shading and
ornamental value, re-vegetation of disturbed lands, compensatory planting,
aesthetic design of aboveground structures including provision of finishes,
colour scheme, texture of materials used and any measures to mitigate the
impact on the existing and planned land use and VSRs. A programme for the mitigation measures will be provided. The agencies responsible for
the funding, implementation, management, and maintenance of the mitigation
measures will be identified.
·
Prediction of the
significance of impacts before and after the implementation of the mitigation
measures. Potential mitigation measures suggested would
alleviate the landscape impact and enhance the landscape quality by reinstating
the disturbed lands and improve the compatibility with the surrounding. By
synthesising the magnitude of the change and the sensitivity of the various LRs
and LCAs, it is possible to categorise impacts in a logical, well-reasoned and
consistent fashion. Table 14.1 shows the rationale for dividing the degree of
significance into four thresholds, namely insubstantial, slight, moderate, and
substantial, depending on the combination of a
negligible-small-intermediate-large magnitude of change and a low-medium-high
degree of sensitivity of landscape resource and character.
Table 14.1 Relationship between Sensitivity and
Magnitude of Change in Defining Impact Significance
Magnitude of Change |
Large |
Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
Sensitivity of
Landscape Resource and Landscape Character Area |
Note: All impacts are adverse unless otherwise
noted with beneficial. |
The significance of landscape impacts is categorised as follows:
Substantial: |
Adverse / beneficial impact where the
proposal would cause significant deterioration or improvement in existing
landscape quality. |
Moderate: |
Adverse / beneficial impact where the
proposal would cause a noticeable deterioration or improvement in existing
landscape quality. |
Slight: |
Adverse / beneficial impact where the
proposal would cause a barely perceptible deterioration or improvement in
existing landscape quality. |
Insubstantial: |
No discernible change in the existing
landscape quality. |
·
Prediction of Acceptability
of Impacts. An
overall assessment of the acceptability, or otherwise, of the impacts according
to the five criteria set out in Annex 10 of the EIAO-TM.
·
Where practical, trees in
close proximity are grouped together in the same tree groups. The locations of
these tree groups are drawn on the tree survey plan with the boundaries
corresponding to the collective crown spread of the included trees. Where trees are scattered and/or access to
them are limited, trees are conveniently grouped together in the same tree
groups by visible physical boundaries on site, such as hoarding, fences, paths,
and roads etc. The locations of these tree groups are drawn on the Broad-Brush
Tree Survey Plan with the boundaries corresponding to the physical boundaries
to define these zones. Where practical, all trees in the tree groups are
surveyed at certain reasonable distances where tree species are identifiable.
The amount of each tree species in the same tree groups are counted as far as possible
or estimated for inaccessible trees. The following information is recorded and
provided in ranges for each tree group:
·
species in the tree groups:
- height;
- crown spread;
- trunk diameter (measured 1.3 m from the
ground);
- assessment of tree form (good / fair / poor);
- assessment of tree health (good / fair /
poor);
- assessment of tree amenity value (high /
medium / low); and
-
assessment of tree survival rate after transplanting (high / medium / low).
·
Where applicable, the following
information is provided as remarks for each tree groups, if:
- there is tree included in the Register of Old
and Valuable Trees (OVT) promulgated under DEVB TC(W) No. 5/2020 – Registration
and Preservation of Old and Valuable Trees;
- there is tree potentially registrable in
accordance with the criteria as set out in DEVB TC(W) No. 5/2020 – Registration
and Preservation of Old and Valuable Tree;
- there is tree belonging to species which is
protected under local legislations, including the Forests and Countryside
Ordinance (Cap. 96) and the Protection of Endangered Species of Animals and
Plants Ordinance (Cap. 586);
- there is tree belonging to species which is
included in the latest edition of the publication ‘Rare and Precious Plants of
Hong Kong’ issued by AFCD; and
- there is tree which has special importance
due to special attributes such as protected status; rarity; age over 100 years,
outstanding size or form; and cultural or historical significance etc.
·
Photographic records are taken on site to show the
general overall view of the tree groups.
·
Identification of the visual
envelope during the construction and operation phases of the Project. This is achieved by site visit
and desktop study of topographic maps, photographs, and preparation of
cross-sections to determine visibility of the Project from various
locations.
·
Identification of the visually
sensitive receivers (VSRs) within the Visual Envelope (VE) at construction and
operation phases. These are the people who would reside within,
work within, play within, or travel through, the Visual Envelope.
· Assessment of the degree of sensitivity of the VSRs
The factors considered include:
- the type of VSRs, which is
classified according to whether the person is at home, at work, at play, or
travelling. Those who view the change
from their homes are considered to be highly sensitive as the attractiveness or
otherwise of the outlook from their home will have a substantial effect on
their perception of the quality and acceptability of their home environment and
their general quality of life. Those who
view the impact from their workplace are considered to be only moderately
sensitive as the attractiveness or otherwise of the outlook will have a less
important, although still material, effect on their perception of their quality
of life. The degree to which this
applies depends on whether the workplace is industrial, retail, or
commercial. Those who view the impact
whilst taking part in an outdoor leisure activity may display varying
sensitivity depending on the type of leisure activity. Those who view the impact whilst travelling
on a public thoroughfare will also display varying sensitivity depending on the
speed of travel.
- the relative numbers of VSRs
will be expressed in terms of whether there are “many”, “medium” and “few” VSRs
in any one category of VSR
- other factors which are
considered (as required by EIAO GN 8/2010) include the number of VSRs, the
value and quality of existing views, the availability and amenity of
alternative views, the duration or frequency of view, and the degree of
visibility.
The
sensitivity of VSRs is classified as follows:
High: |
The VSR is highly sensitive to any change
in their viewing experience. |
Medium: |
The VSR is moderately sensitive to any
change in their viewing experience. |
Low: |
The VSR is only slightly sensitive to any
change in their viewing experience. |
·
Identification of potential
sources of visual changes. These are the various elements of the
construction works and operation that would generate visual changes.
Assessment of the potential magnitude of visual changes. Factors considered include:
- the compatibility with the
surrounding landscape;
- the duration of the impact;
- the potential blockage of view;
- the reversibility of the
impact;
- the scale of the impact and
distance of the source of impact from the viewer; and
- the degree of visibility of the
impact, and the degree of which the impact dominates the field of vision of the
viewer.
The
magnitude of visual changes is classified as follows:
Large: |
The VSRs would suffer a major change in
their viewing experience. |
Intermediate: |
The VSRs would suffer a moderate change in
their viewing experience. |
Small: |
The VSRs would suffer a small change in
their viewing experience. |
Negligible: |
The VSRs would suffer no discernible
change in their viewing experience. |
·
Identification of potential
visual mitigation measures. These may take the
form of adopting basic engineering design to prevent and/or minimise adverse
visual impacts before adopting other mitigation or compensatory measures to
alleviate the impacts. Potential
mitigation measures should also include the preservation of vegetation and
natural landscape resources, provision of screen planting, re-vegetation of
disturbed lands, compensatory planting. Remedial measures such as colour and
textural treatment of building features; and compensatory measures such as the
implementation of landscape design elements (e.g., tree planting, creation of
new open space, etc.) to compensate for unavoidable adverse impacts and to
attempt to generate potentially beneficial long-term impacts to mitigate the
impact on the existing and planned land use and VSRs. A programme for the mitigation measures will
be provided. The agencies responsible
for the funding, implementation, management, and maintenance of the mitigation
measures will be identified.
·
Prediction of the
significance of visual impacts before and after the implementation of the
mitigation measures. By synthesising the magnitude of the various
visual impacts and the sensitivity of the VSR that are affected, it is possible
to categorise the degree of significance of the impacts in a logical, well-reasoned and
consistent fashion. Table 14.2 shows the rationale for dividing the degree of
significance into four thresholds, namely, insubstantial, slight, moderate, and
substantial, depending on the combination of a
negligible-small-intermediate-large magnitude of change and a low-medium-high
degree of sensitivity of VSRs.
Table 14.2 Relationship between visually sensitive receivers
(VSRs) Sensitivity and Magnitude of Change in Defining Impact Significance
Magnitude of Change |
Large |
Moderate |
Moderate / Substantial |
Substantial |
Intermediate |
Slight / Moderate |
Moderate |
Moderate / Substantial |
|
Small |
Insubstantial / Slight |
Slight / Moderate |
Moderate |
|
Negligible |
Insubstantial |
Insubstantial |
Insubstantial |
|
|
Low |
Medium |
High |
|
Sensitivity of visually
sensitive receivers (VSRs) |
Note: All impacts are adverse unless otherwise
noted with beneficial. |
The significance of visual impacts is categorised as follows:
Substantial: |
Adverse / beneficial impact where the
proposal would cause significant deterioration or improvement in existing
visual quality. |
Moderate: |
Adverse / beneficial impact where the
proposal would cause a noticeable deterioration or improvement in existing
visual quality. |
Slight: |
Adverse / beneficial impact where the
proposal would cause a barely perceptible deterioration or improvement in
existing visual quality. |
Insubstantial: |
No discernible change in the existing
visual quality. |
·
Prediction of Acceptability
of Impacts. An
overall assessment of the acceptability, or otherwise, of the impacts according
to the five criteria set out in Annex 10 of the EIAO-TM.
·
Approved Kwu Tung South OZP No. S/NE-KTS/18;
· Approved Kwu Tung North OZP No. S/KTN/4;
·
Approved Mai Po and Fairview Park OZP No. S/YL-MP/6;
·
Approved Ngau Tam Mei Outline Zoning Plan No.
S/YL-NTM/12;
·
Approved San Tin Outline Zoning Plan No. S/YL-ST/8;
and
·
Approved Lok Ma Chau Loop Outline Zoning Plan No. S/LMCL/2;
Table 14.3 Summary of review of Planning Framework
OZP
Plan Title and No. |
Land Use Zoning |
Potential Change to the OZP and the
Anticipated Future Outlook of the Area due to the Project |
Approved
Kwu Tung South OZP No. S/NE-KTS/18 |
“AGR” |
The existing “AGR” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
“GB” |
The existing “GB” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
|
Approved Kwu Tung North OZP No. S/KTN/4 |
“GB” |
The existing “GB” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
“OU” |
The existing “OU(railway
associated facilities)” and “OU(plant for district cooling system)” will not be affected by
the proposed development. There will be no potential change to this zoning. |
|
“OU (Amenity Area)” |
The existing “OU (Amenity Area)” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
|
“G/IC” |
The existing “G/IC” zoning will not be affected by the proposed development. There will
be no potential change to this zoning. |
|
“Road” |
The existing “Road” area will be partially permanently converted to
“OU” for Refuse Transfer Station and Resource Recovery Facilities |
|
Approved
Mai Po and Fairview Park OZP No. S/YL-MP6; |
“CA” |
The existing Conservation Area zoning will not be affected by the
proposed development. There will be no potential change to this
zoning. |
“OU |
The existing “OU” zoning will not be affected by the proposed development. There will
be no potential change to this zoning. |
|
“V” |
The existing “V” zoning will not be affected by the proposed development. There will
be no potential change to this zoning.
|
|
SSSI |
A tiny portion of the existing “SSSI” zoning will be affected
by the proposed development and proposed
for Other Specified Uses (Innovation & Technology) “OU(I&T)” use. |
|
Approved
San Tin Outline Zoning Plan No. S/YL-ST/8 |
“R(D)” |
The existing “R(D)” besides Castle Peak Road- San Tin Section will be
potentially affected and converted to “OU(I&T)” and Open Space (“O”). |
“V” |
The existing “V” zoning will not be affected by the projects.
Therefore, there will be no potential change to this zone. |
|
“G/IC” |
Some of the existing “G/IC” zoning will be affected due to the proposed
Road. Some part of “G/IC” zoning will be converted into “OU(I&T)” use. |
|
“OU” |
The “OU” zoning San Tin Tsuen Road and Castle Peak Road San Tin Section
will be proposed as “OU(I&T)”). The Other
Specified Use (Service Station) will be permanently converted into Other
Specified Use (Mixed Use). |
|
“GB” |
Part of the existing “GB” zoning near Lok Ma Chau Road and Chau Tau
Village will potentially be affected and converted into “OU(I&T)” and infrastructural
facilities. |
|
“CA” |
Small portion of the “CA” around LMC BCP will be permanently affected
by the Project for the “G/IC”, “A”, “OU(I&T)”. This will include part of the Ha Wan Tsuen, agricultural land and
fishponds. |
|
“U” |
The “U” east of San Sham Road is for the LMC Spur Line and proposed
Northern Link Railway system. This zoning will potentially permanently be
affected for the proposed “OU(I&T)”, “G/IC” and “A”. |
|
Approved
Ngau Tam Mei outline zoning plan no. S/YL-NTM/12. |
“CDA” |
The “CDA” zoning near Shek Wu Wai San Tsuen will be affected for the
construction and operation of proposed public and private housing site, mixed
use development and open space. |
“R(C)” |
The "R(C)” zoning north-east of Maple Garden will be potentially affected for
the construction and operation of proposed public housing site and G/IC
facilities. |
|
“V” |
The “V” zoning Shek Wu Wai will not be affected by the proposed
development. There will be no potential change to this zone. |
|
“OS” |
Majority of the “OS” zoning will be potentially affected for the
construction and operation of residential development, open space, “G/IC” facilities and “OU(I&T)” use. |
|
“REC” |
Only a small portion of “REC” zoning is located within the 500m
assessment area. It will not be affected by the proposed development and
therefore no potential change to this zoning. |
|
“OU” |
This “OU(Electricity Sub-station)” refers to the site between San Tin
Highway and San Tam Road and is intended for the provision of an electric
sub-station. The zoning will be changed from “OU” to “G/IC” use where the
existing Mai Po ESS remains. |
|
“GB” |
The Existing “GB” near the Shek Wu Wai San Tsuen, Siu Hum Tsuen, Pang
Loon Tei and Ngau Tam Mei Water Treatment Works will be permanently affected by
the proposed development for the construction of future schools, Residential
Development, “G/IC” uses, Mixed Use Development and Other Specified Use. |
|
“CA” |
The existing “CA” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
|
Approved
Lok Ma Chau Loop Outline Zoning Plan No. S/LMCL/2 |
“O” |
The existing “O” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
“G/IC” |
The existing “G/IC” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
|
“OU” |
The existing “OU” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
|
“CA” |
The existing “CA” zoning will not be affected by the proposed
development. There will be no potential change to this zoning. |
In
general, most of the affected areas within the Approved Ngau Tam Mei outline zoning plan no. S/YL-NTM/12. Include
the “OS”, “GB”. As for the Approved San
Tin outline zoning plan no. SYL-ST/8, the major affected areas include the “OU” and “U” zoning.
· Proposed mixed use development – High-rise development clusters shall be considered at railway stations to form landmarks that provide a sense of orientation and vistas to help identify key transport nodes.
· Gateways & Focal Points - Building heights shall be proposed to signify and improve the legibility of critical pedestrian and vehicular entry ways.
· Village / Existing Developments - Building heights should harmonise with existing low-rise developments and establishments.
· Green and Natural Elements - Building heights shall respond to adjacent open spaces and green corridors by descending to foster a more human-scale environment along these edges.
· View Corridors and Skyline - Building heights shall be proposed to frame view corridors and to create an undulating skyline that emphasises key landmarks and visual points. Stagnant building heights shall be avoided, and a stepped height profile shall be adopted for smooth transitions and to avoid appearing monotonous.
· Bird Flight Paths – Low-rise profiles shall be adopted along ecologically sensitive areas. A stepdown approach shall be used along important bird flight paths.
·
Planned Development of the
Loop – Reference shall be made to the Loop
situated to the north-eastern of the Project. According to the Approved Lok Ma Chau Loop
OZP No. S/LMCL/2, the proposed building heights with graduated building
profiles that transition from low-rise developments along the northern
waterfront area into inner medium-rise developments and gradually lower again
to low-rise developments along the planned ecological area (the Meander). This planned building profile shall be
considered in conjunction with the nearby proposed building heights, including
interface with the ecologically sensitive areas such as the bird flight
path. Cohesive massing should also be
considered to form a unified image of the Project together with the Loop.
· The proposed building heights and development intensities for the Project give due regard to the physical form and settings of the existing and retained land uses to ensure a better integration with the surrounding area, while it frames key destinations as vantage points creating a sensible skyline that represents the Project.
· The overall development intensity and building height descend towards the northern periphery by designating low and medium-rise developments along the proposed SPS WCP and the important bird flight paths corridor adjacent to LMC station. The I&T developments to the north of the San Tin Highway comprises low to medium density building clusters with stepping building height.
· The proposed building heights and development intensity profiles are also configured to prioritize major development nodes and enhance points of the congregation within the Project. High-rise development clusters are concentrated at the proposed station near Chau Tau, and the proposed San Tin station and neighbouring areas to reflect their visual prominence.
· To create a gateway / landmark feature, the maximum building height for the mixed-use development at the proposed station near Chau Tau is proposed at +200 mPD for the landmark building. The developments within the proposed Station near Chau Tau would create a stepped building height profile echoing the residential developments in the existing villages (On Lung Tsuen, Wing Ping Tsuen, Fan Tin Tsuen and San Lung Tsuen) to the southwest.
· High-density residential and mixed-use development are proposed in the San Tin Station mixed use. The building height profile should reinforce the mixed-use land use, while harmonising with the undulating mountain ridgeline in the backdrop. The mixed-use development sites will adopt the highest building height of +200 mPD to setup the focal point and establish the landmark image of mixed-use development, while surrounding developments would have lower building height restriction (BHR) to create a descending building height profile.
· Greening provision on podium, green roof and vertical greening for the building facades where technically feasible to provide a third dimension of greening framework to the Project;
· In terms of the building finishes natural tones should be considered for the colour palette and non-reflective finishes shall be incorporated for the outward facing building facades to reduce the glare effect and to minimise impact on birds. Light earthy tone colours such as shades of green, grey, brown, and off-white should also be considered to reduce the visibility of the development components. At appropriate area, glass finishes, metal façade cladding of timber colour shall be proposed to increase transparency and integration with context;
· The massing of the podium structure housing the Transport Interchange Hub (TIH), railway station, and retail, dining, and entertainment type (RDE) mall is proposed are encouraged to be in undulating form, providing a series of green spaces at multiple levels corresponding to surrounding uses; and
· To further break down the massing visually, each building when feasible shall be visually sheared at the façade as if they are two buildings, to creates a less lengthy façade and more human-scale.
· A view corridor proposed along San Sham Road would correlate with the mixed-use development at the proposed station near Chau Tau to create a gateway into the I&T Park and emphasize the visual connection to Shenzhen City skyline to the north.
· Another two view corridors running north to south along the mixed-use area. One of the view corridors utilises the proposed green corridors and road alignments from the Shek Wu Wai Interchange (main access points) towards the vibrant core area of San Tin Town Centre (proposed San Tin Station / mixed use development). Building developments along this view corridor would frame the mountain ridgeline of Ngau Tam Shan. The second North-South view corridor provides a visual connection and orientation from the existing village of Shek Wu Wai through the Living Avenue and towards the Ngau Tam Shan’s natural backdrop.
· STEMDC (South of San Tin Highway) – To create a pleasant “Riverside Park”, it is proposed to revitalise the existing water channel to better integrate with the open space design, forming a more resilient blue-green feature facilitating drainage function and a more scenic recreation destination.
· STEMDC (North of San Tin Highway) – The downstream portion of the STEMDC is proposed to be retrained to (i) better integrate with the adjoining reed beds and wetlands; (ii) serve as a transition area between the built development and the wetland in terms of ecological value and recreation function; (iii) incur no adverse impacts, or better yet, some degree of improvement, to the existing drainage performance.
·
STWMDC (Living Avenue;
Cultural & Recreational Complex) – Strategic landscape and technical improvements are proposed to
provide opportunities for better drainage and more sensible blue-green
experiences through naturalise water edge treatment and integrated ponds / tanks
to increase flood retention capabilities and promote water friendly environment.
· Ensuring that the retained key ecological capital is not cut off or engulfed by urban components;
· Maximising areas for potential greenery with an aim to create diverse habitats within the landscape network;
· Ensuring the network connects with adjacent woodlands, wetlands, and essential habitats to support wildlife movements;
· Synergy with adjacent land usage to lay foundation for future landscape design;
· Relating future leisure and recreational provisions to the overall urban design; and
· Promoting walkability within the Project area through open space.
The major planned interface projects within the Project include:
· Development of The Loop – Main Works Package 1
· Advance Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Areas
· Remaining Phase of Site Formation and Engineering Infrastructure Works at Kwu Tung North and Fanling North New Development Area – Detailed Design and Site Investigation
· Strategic Feasibility Study on The Development of Wetland Conservation Parks System
· Northern Link (NOL) Main Line
· Ngau Tam Mei New Development Area
· Strategic Study on Major Roads beyond 2030 - Feasibility Study
Table 14.4.1 Baseline Landscape Resources
ID
No. |
Landscape
Resources |
Descriptions |
Sensitivity (Low, Medium, High) |
Baseline area (ha.) |
LR1.0 |
Marsh/ Reed |
Marsh/Reed This LR refers to
the freshwater marsh/ reed areas within the 500m assessment area. The LR is
generally located in the artificial wetland of The Loop, Ha Wan Tsuen and
between ponds and developed areas in Lin Barn Tsuen and abandoned
agricultural land near Shek Wu Wai San Tsuen and Yau Tam Mei Tsuen. The
former is located within the WCA and WBA.
The quality and rarity of these LR are regard as medium. Since it is characterised
by the lush Herbaceous vegetation and common reed grass around some areas of
seasonal open water area. Due to most vegetation are common in Hong Kong or likely
to be evolved from nature succession with human disturbance such as traffic
and agricultural activities in proximity. The rarity and landscape value,
quality and are regard as medium. They are mostly within the Conservation Area
(“CA”) or Green Belt (“GB”). However, its nature is of low ability to
accommodate changes. Hence, the overall sensitivity is considered as
“High”. The dominant tree
species include Macaranga tanarius var. tomentosa and Melia
azedarach. |
High |
14 |
LR2.0 |
Compensatory Wetland |
This LR refers to the mitigation wetlands proposed under other various
designated projects within the assessment area. These are wetland habitat
established and managed primarily for the purpose to provide high ecological
value. These include: (i) STEMDC wetland
which is within and/or in close proximity of the Project boundary. It refers
to the constructed wetland in the form of a flood storage
pond adjacent to San Tin Tsuen Road, Tsing Lung Tsuen drainage channel,
constructed wetland along STEMDC, tidal channel and grasscrete-lined bottom
of STEMDC. They are largely referring to aquatic and riparian vegetation; (ii)
San Tin Constructed Wetland (Lotus Pond) located next to traffic road, hence
receiving higher human disturbance. They are largely comprising of open water
with aquatic plants, emergent vegetation, Phragmites sp, while other
common tree and shrub species were also observed along the riparian zone; (iii)
the Loop’s Ecological Area, which refers to the 12.8 ha reedbed within the
southern edge of The Loop. Due to the on-going construction activities, it
receives frequent human disturbance; (iv) Lok Ma Chau Ecological Enhancement
Area (LMC EEA) which refers to the 34 ha managed freshwater
wetland habitats which is of limited human disturbance. Overall, the mitigation wetlands have medium to
high quality, maturity, and amenity value. It has medium to high rarity and
local importance. As a result of its relative low ability to accommodate
changes, the overall sensitivity of the LR is considered ‘High’. (For further
details, please refer to section 10.6.2 of the EIA
report) The dominant tree
species include Leucaena leucocephala and Melia azedarach. |
High |
22.7 |
LR3.0 |
Pond |
Total area: 228.2 ha. |
||
LR3.1 |
Ponds near San Tin and Sam Po Shue1 |
This LR refers to
the freshwater ponds located within the WCA and WBA which form part of a more
extensive area from San Tin to Mai Po. It is enclosed by bunds with tree
planting and shrubs. Those ponds are found in San Tin area near LMC BCP, Sam
Po Shue and Ha Wan Tsuen. For ponds around San
Tin, they are ponds largely active with overgrown vegetation. They are in
close proximity to open storage and brownfield operation (i.e., LR17)
hindering their landscape amenity value. For the ponds near San Tin Tsuen
Road and Tam Kon Chau Road, more human disturbance such as traffic are found.
The ponds around
Lok Ma Chau (LMC) meander and Ha Wan Tsuen are largely in relation with the
village settlement. These ponds mainly consist common vegetation. For ponds near LMC BCP, they are mainly
active fishpond for fisheries activities consist mainly herbaceous species
along the pond bund. The LR has good
quality and some aesthetic landscape value. Owning to this is an important
landscape features contributing to the landscape character, its qualities and
unique setting, it is relatively intolerant to any changes. This LR has high quality,
maturity, and amenity value. It has high rarity and regional importance. As a
result of its relative low ability to accommodate changes, the overall
sensitivity of the LR is considered ‘High’. The dominant tree
species include Dimocarpus longan and Leucaena leucocephala. |
High |
222.5 |
LR3.2 |
Ponds near Siu Hum Tsuen and Shek Wu Wai San Tsuen 1
|
This LR refers to
the vegetation around the freshwater ponds associated with the agricultural
activities and village type development. These ponds are found in area near
Luk Mei Tsuen, Shek Wu Wai, Shek Wu Wai San Tsuen, Siu Hum Tsuen and
scattered in area in Ki Lun Tsuen, Pang Loon Tei, and Cheung Lek. They are
active or abandoned fishponds supporting limited vegetation. The vegetation
mainly consists of grasses and shrubs along pond bunds. The LR are of average
quality and some aesthetic landscape value. This LR has medium quality, maturity,
and amenity value. It has medium rarity and local importance. As a result of
its relative medium to low ability to accommodate changes, the overall
sensitivity of the LR is considered ‘medium’. The dominant tree species
include Leucaena leucocephala, Macaranga tanarius var. tomentosa and
Melia azedarach. |
Medium |
3.7 |
LR3.3 |
Ponds near Ngau Tam Mei 1 |
This LR refers to
the vegetation around the freshwater ponds associated with
adjacent village/orchard, marsh/reed, and grassland areas. Majority of the
ponds were identified around the settlements in Yau Tam Mei Tsuen and near
the Ngau Tam Mei Water Treatment Works. The identified ponds were found to be
largely inactive or abandoned fishponds and the bunds were not managed and
overgrown. It is also observed that the ponds were mostly interspersed with
village areas and inaccessible. This LR
has medium quality, maturity, and amenity value. It has medium rarity and
local importance. As a result of its relative medium to low ability to accommodate
changes, the overall sensitivity of the LR is considered ‘medium’. The dominant tree
species include, Dimocarpus longan and Macaranga tanarius var.
tomentosa |
Medium |
2 |
LR4.0 |
Natural Watercourse |
Vegetation along
Natural watercourse This LR refers to
the LMC Meander and several small scale and fragmented natural streams within
assessment area of the Project area. They are found in Ha Wan Tsuen, Lok Ma
Chau Tsuen, and Pang Loon Tei. This LR is characterised
by a combination of coarse grassland punctuated by small areas of shrubs. It
is a mix of riparian vegetation with wetland herbs and shrubs. This LR has
medium to high quality, maturity, and amenity value. It has medium rarity and
local importance. As a result of its relative low ability to accommodate
changes, the overall sensitivity of the LR is considered ‘High’. The dominant tree
species include Ficus hispida, Ficus macrocarpa and Macaranga
tanarius var. tomentosa. |
High |
5.95 |
LR5.0 |
Modified water course |
Vegetation along
Modified Water course This LR refers to
the channelised or man-made watercourses. This includes the Shenzhen River
that has been widened or modified in phases since the 1990 and engineered
channel within the Project area. This
also includes the major drainage channel of STEMDC and STWMDC. It is mainly
located along Ki Lun Tsuen to Pang Loon Tei, Shek Wu Wai and Chau Tau. Other
modified watercourses recorded were generally narrow and highly concretised
drainage channels which shared similar features, conditions and were situated
within developed area i.e., adjacent to Maple Garden and Chau Tau Tsuen. The watercourses
are modified with grasscrete banks and tree planting is found along some of
their banks. It is considered that the modified watercourse is commonly found
in Hong Kong and the ability to accommodate changes is high. This LR has
medium to low quality, maturity and amenity value. It has low rarity and
local importance. As a result of its relative high ability to accommodate
changes, the overall sensitivity of the LR is considered ‘Low’. The dominant tree
species include Ficus macrocarpa, Leucaena leucocephala and
Melaleuca cajuputi subsp. Cumingiana. |
Low |
24.29 |
LR6.0 |
Semi-Natural Watercourse |
Vegetation around Semi-natural watercourse This LR refers to the small scale semi-natural water
courses. It is characterised with a combination of concretised or channelised
banks and natural bank. This LR includes vegetation associated with the water
course, both within the streams, along the banks and those vegetation in the
immediate vicinity. The vegetation
mainly consists of grasses, shrubs and cluster of trees in some areas. They are mostly found in the lower stream
area near the Sam Po Shue Wetland running between ponds (LR3) and adjacent to
the Lok Ma Chau Road. This LR supported a medium diversity flora and fauna
given its linkage and location as ecological and hydrological linkage between
ponds. This LR has medium quality, maturity and amenity value. It has medium
rarity and local importance. As a result of its relative medium ability to accommodate
changes, the overall sensitivity of the LR is considered ‘Medium’. The dominant tree species
include Leucaena leucocephala, Macaranga tanarius var. tomentosa and
Melia azedarach. |
Medium |
11 |
LR7.0 |
Seasonal Wet Grassland |
Seasonal Wet Grassland This LR refers to
poorly drained fallow fields and abandoned ponds. A small area of seasonal
wet grassland has been identified with in Project area near the Mai Po San
Tsuen and Siu Hum Tsuen. It is characterised by the herbaceous vegetation
coverage and limited wetland species. This LR has medium quality, maturity
and amenity value. It has medium rarity and local importance. As a result of
its relative medium ability to accommodate changes, the overall sensitivity
of the LR is considered ‘Medium’. |
Medium |
0.2 |
LR8.0 |
Wet Agricultural Land |
Vegetation in Wet
Agricultural Land This LR refers to
the wet agricultural land holdings within the assessment area of the Project area.
They are actively farmed land maintained with very shallow standing water.
Scattered parts of the LR are identified in Shek Wu Wai. The LR is well kept
with mainly herbaceous vegetation, while tree cover within the plots is very
limited. This LR is of good quality and form an integral element of the local
cultural resource. None the less, this LR is of man-made nature and is relatively
less important to the landscape setting. This LR has medium quality, maturity,
and amenity value. It has medium rarity and local importance. As a result of
its relative medium ability to accommodate changes, the overall sensitivity
of the LR is considered ‘Medium’. The dominant tree
species include Dimocarpus longan and Litchi chinensis. |
Medium |
0.2 |
LR9.0 |
Dry Agricultural Land |
Vegetation in Dry Agricultural Land This LR refers to
the agricultural land holdings within the assessment area of the Project area.
Several parts of the LR are identified in Shek Wu Wai, Pang Loon Tei and Chau
Tau Tsuen. They are mainly dry agricultural land, and most lands are active.
The LR is well kept and organized while tree cover within the plots is very
limited. This LR is of good quality. As a result, it has medium quality, maturity,
and amenity value. It has medium rarity and local importance. As a result of
its relative medium ability to accommodate changes, the overall sensitivity
of the LR is considered ‘Medium’. The dominant tree
species include Artocarpus heterophyllus, Clausena lansium and
Dimocarpus longan. |
Medium |
13.7 |
LR10.0 |
Woodland |
Woodland This LR refers to woodland patches within the
assessment area of the Project area. The LR is mainly located in Ha Wan
Fisherman San Tsuen, Ki Lun Shan, area near San Tin Barracks, Mai Po San
Tsuen and along border of the natural hillsides. The trees are either
semi-mature to mature and is generally in fair to good condition. An area of
the woodland is designated within the Mai Po Village SSSI, located to the south
of a junction between Tam Kon Chau Road and Castle Peak Road (Mai Po
Section). The trees are utilised by the community of nesting and breeding of
the Mai Po Village Egretry. (For further details please refer to Section 10 of EIA Report) This LR is of high landscape amenity and quality and possess strong natural
characteristic. It has
medium to high quality, maturity, and amenity value. It has medium rarity and
local importance. As a result of its relative low ability to accommodate
changes, the overall sensitivity of the LR is considered ‘High’. The
dominant tree species include Bridelia tomentosa, Cinnamomum camphora,
Ficus hispida, Ficus variegate, Schefflera heptaphylla and Microcos
nervosa. One flora species of conservation
importance, Incense Tree* (Aquilaria sinensis), was recorded in
several locations at the woodland north-west of Chau Tau Tsuen and in the
woodland south of Pang Loon Tei which both are outside of the Project area. |
High |
31.8 |
LR11.0 |
Mixed Woodland |
Mixed Woodland This
LR refers to the mixed woodland area that are largely scattered throughout
the Project area that are spatially defined by the patterns of surrounding
human developments. This results in
segregated, areas of land that may have various stages and types of
vegetation of variable size and quality.
The vegetation is characterised by a mix of natural, self-seeded, and
plantation-style woodland. Species may
include mature or semi-mature trees forming an interlocking canopy and dense
understory. Area closer to urban
development such Castle Peak Road - San Tin are more dominated by shrubs and
with varying qualities. Others mixed woodland scatters around Shek Wu Wai San Tsuen, Siu Hum Tsuen, and Mai Po Lung Tsuen. Due to the unique natural nature and high quality, the mixed woodlands
which are thought to be of regional significant is of low ability to accommodate
changes. The overall
sensitivity is ‘High’. The
dominant tree species include exotic trees e.g. Acacia confuse, Dimocarpus
long and Acacia confusa, and native trees e.g. Bridelia
tomentosa, Macaranga tanarius var. tomentosa and Microcos nervosa.
One flora species of conservation
importance, Incense Tree (Aquilaria sinensis)*, was recorded in
several locations at the woodland east of Kam Kwai Leng and west of Tam Mei
Hill (Refer to Figure 10.3D). 2 nos. of potential Tree of Particular Interest (TPI) are identified
within this LR i.e. T18 (Ficus
virens) and T19 (Ficus virens).(Refer to Figure 14.10). |
High |
97.4 |
LR12.0 |
Plantation |
Total Area: 64.5 |
||
LR12.1 |
Plantation |
Plantation This LR is
predominantly composed of native tree species growing naturally with some
understory vegetation and plantation-style forests. The trees vary in height
and maturity and provide a continuous greening on the slopes. The LR can be
found on man-made slope, natural hillside, and urban parks. This includes the
San Tin Highway, San Sham Road, Mai Po Lung Tsuen, Maple Garden, Southern
hillside of Ngau Tam Shan, Fan Tin Tsuen and San Tin Park. The trees are mainly
in good condition and semi-mature. This LR has medium quality, maturity, and
amenity value. It has medium rarity and local importance. As a result of its
relative medium ability to accommodate changes, the overall sensitivity of
the LR is considered ‘Medium’. The dominant tree
species include Acacia confuse, Celtis sinensis and Eucalyptus spp.
Whereas one flora species of
conservation importance, Incense Tree* (Aquilaria sinensis) was identified on Kam Kwai Leng within the Project
boundary. |
Medium |
40.1 |
LR12.2 |
Plantation along San Tin- Fanling Highway |
Plantation along San Tin- Fanling Highway This LR refers to
medium-sized and clusters of trees planted by man within the assessment area
of the Project area. It is referring
to the roadside planting along San Tin-Fanling Highway, Kwu Tung Road and San
Tam Road. The trees are mainly in good
condition and semi-mature. This LR has medium quality, maturity and amenity
value. It has medium low rarity and local importance. As a result of its
relative high ability to accommodate changes, the overall sensitivity of the
LR is considered ‘Low’. The dominant tree
species include Acacia confuse, Celtis sinensis and Eucalyptus spp.
Whereas Incense Tree* was identified on North of Kam Kwai Leng within the
Project boundary. 1 nos. of TPI are identified within this LR i.e. T5 (Ficus
virens) (Refer to Figure 14.10). |
Low |
24.3 |
LR13.0 |
Shrubland |
Shrubland This LR refers to
the large patch of shrubs and herbaceous grasses with scattered trees within
the assessment area of the Project area. It is largely referring to the
hillside area bordering the assessment area. It is mainly located in the northern,
eastern, and southwestern side of Project area. The vegetation varies in
height and provides a continuous greening on the slopes. This LR has a strong natural
characteristic, fair to good quality of landscape amenity and small extent of
human disturbance such as the present of small extent of burial ground/ human
settlement. As such, this LR has medium quality, maturity, and amenity value.
It has low rarity and low local importance. As a result of its relative
medium ability to accommodate changes, the overall sensitivity of the LR is
considered ‘Medium’. |
Medium |
109.4 |
LR14.0 |
Grassland |
Grassland This LR refers to
the large patch grassland with scattered trees within the assessment area of
the Project area. It is largely referring to the hillside area bordering the
assessment area. It is mainly located to the east and southwest
side of Project. It is common on the hillside of
Tit Hang Shan, Ki Lun Shan, most of the top of Ngau Tam Shan and the small
hill adjacent to the Vineyard. The grassland provides a continuous greening
on the slopes. This LR has a natural characteristic, fair to good quality of
landscape amenity and small extent of human disturbance. As such, this LR has
medium quality, maturity and amenity value. It has low rarity and local
importance. As a result of its relative medium ability to accommodate changes,
the overall sensitivity of the LR is considered ‘Medium’. |
Medium |
207 |
LR15.0 |
Village/ Orchard |
Vegetation in Village Type Development This LR refers to traditional villages and modern
villages within the assessment area of the Project area. This includes areas
in Ki Lun Tsuen, Luk Mei Tsuen, Pang Loon Tei, Siu Hum Tsuen, Shek Wu Wai,
Shek Wu Wai San Tsuen, Mai Po Lung Tsuen, San Tin, Lin Barn Tsuen, Ha Wan
Tsuen, Lok Ma Chau Tsuen, Pak Shek Au, and Chau Tau Tsuen. The vegetation is
arranged by human following the domestic structures and the interwoven roads
and paths. It also refers to the small patches of orchards identified in east
Shek Wu Wai agricultural land and Pang Loon Tei village area. The LR contains common fruit tree species
and is often managed by human. These Vegetation is highly disturbed and
dominated by exotic and ornamental species. This LR has medium quality, maturity,
and amenity value. It has low rarity and low local importance. As a result of
its relative high ability to accommodate changes, the overall sensitivity of
the LR is considered ‘Low’. The dominant tree species include Ficus
macrocarpa, Leucaena leucocephala and Macaranga tanarius var.
tomentosa. 3 nos. of TPI are identified within this LR i.e. T1 (Ficus macrocarpa), T21 (Ficus
virens), T28 (Ficus virens). (Refer to Figure
14.10). |
Low |
78.7 |
LR16.0 |
Developed Area/ (Including residential area and man-made structure) |
Vegetation in
developed area (Including residential area and man-made structure) This LR refers to urbanised areas within the
assessment area of the Project area, which are heavily developed with mainly
hard paved surfaces and limited vegetated landscape areas. The major area includes Maple Garden, Royal Palm,
Tam Mei Barracks, Gurka cemetery, San Tin Barrack, Mai Po San Tsuen, Hop
Shing Wai San Tin Highway - Fanling Highway, the San Tin Interchange, MTR LMC
Station, the Loop area, and sport ground in front of Ha Wan Tsuen. The Vegetation in this LR is mainly man-made
landscape planting. This LR has medium quality, maturity and low to medium
amenity value. It has low rarity and low local importance. As a result of its
relative high ability to accommodate changes, the overall sensitivity of the
LR is considered ‘Low’. The dominant tree species include Ficus
macrocarpa, Leucaena leucocephala and Macaranga tanarius var.
tomentosa. One flora species of
conservation importance, Incense Tree* (Aquilaria sinensis), was
recorded in wasteland along Lok Ma Chau Road, which was an abandoned
wasteland, and subject to current construction activities along Ha Wan Tsuen
East Road. 9 nos. TPI are identified within this LR i.e. T3 (Melaleuca cajuputi subsp. Cumingiana), T4 (Ficus virens), T6
(Ficus virens), T8 (Ficus virens), T9
(Ficus virens),T12 (Ficus
macrocarpa), T13 (Ficus macrocarpa), T16 (Ficus macrocarpa), T17 (Eucalytuts spp.) and T27 (Melaleuca cajuputi subsp.
Cumingiana) (Refer to Figure 14.10). |
Low |
453.7 |
LR17.0 |
Wasteland/ Open storage/ Temporary Area |
Vegetation in
wasteland/open storage/ temporary area This LR refers to
areas that are heavily adapted for human industrial use such as open areas
for storage, parking, or other associated activities such as factory
facilities, waste processing and other industrial workshop. They are characterised by small internal roads with very little
existing vegetation. In which most are self-seeded trees and shrubs scattered
around the areas. Generally,
vegetation is found along the periphery of the boundary lot lines that trees
and understory form rows of vegetation. The Vegetation in this LR is mainly self-seedling
trees with understory and shrub planting of low amenity value. This LR has
medium quality, maturity and low to medium amenity value. It has low rarity
and low local importance. As a result of its relative high ability to accommodate
changes, the overall sensitivity of the LR is considered ‘Low’. The dominant tree
species include Ficus macrocarpa,Leucaena
leucocephala and Macaranga tanarius var. tomentosa. one no. of TPI are
identified within this LR i.e. T24 (Ficus macrocarpa).(Refer
to Figure 14.10) |
Low |
127.3 |
* In accordance with DEVB TCW No. 4/2020, “trees” refers to a plant with
trunk diameter larger than 95mm (300mm girth) measured 1300mm above ground
level. The identified Incense
Tree* (Aquilaria sinensis) are not considered as tree due to their DBH
smaller than 95mm. Detailed are discussed under the Ecological Section of
this EIA Report. 1
Refer to the subject and its adjacent associated vegetation |
Table 14.4.2 Landscape Character Area
ID. No |
LCA |
Descriptions
|
Sensitivity
|
LCA1 |
Settled Valley Landscape |
LCA1 refers to the valley
areas located in the north-west of Tam Mei Barracks, Yau Tam Mei Tsuen, and
the east of Ki Lun Tsuen. This LCA is dominated by scattered settlements,
tracks, large sized hillside woodland and grassland. While most of the human
settlement and development do not detract the character of the mountain
backdrop, in addition to its relative natural characteristics, the overall
landscape quality and value is considered as high. The LCA has a low capacity
to accept changes. As a result, the overall sensitivity is considered “High”. |
High |
LCA2 |
Upland And Hillside Landscape |
LCA 2 refers to large
undeveloped hillside areas in the Lam Tsuen Country Park, Ki Lun Shan, Ngau
Tam Shan and Lok Ma Chau area. This LCA comprises some large sized strips of
woodland, grassland and shrubland. Due to its strong natural characteristics,
the ability to accommodate changes is low. As a result, the overall
sensitivity is considered to be “High”. |
High |
LCA3 |
Rural Coastal Plain Landscape |
LCA3 refers to the flat and expansive areas in Mai
Po, San Tin, Lin Barn Tsuen, and area adjoining Sam Po Shue Wetland near LMC
BCP. It is dominated by large sized fishponds and small agricultural plots.
This LCA include part of the WCA and WBA.
Regarding its significant local character with man-made landscaping,
the landscape value and quality is considered as high, it has a low capacity
to accept changes. The overall sensitivity is considered “High”. |
High |
LCA4 |
Rural Inland Plain Landscape |
LCA 4 refers to the flat and expansive lowland areas
in Shek Wu Wai San Tsuen, Shek Wu Wai Tsuen, Luk Mei Tsuen, Mai Po Lung
Tsuen, Siu Hum Tsuen, and Ki Lun Tsuen, which are lying between the low hills
and wooded knolls. This LCA consists of village houses in rural areas
separated by narrow footpaths or lanes, mature trees and peripheral woodland
scattered along the abandoned fields. Given the previously developed nature
of the character area, the ability to accommodate changes is considered as
medium. The overall sensitivity is considered as “Medium”. |
Medium |
LCA5 |
Urban Peripheral Village Landscape |
LCA 5 refers to village
areas on the fringes of urban developments, which is in Fan Tin Tsuen, Tsing
Lung Tsuen, and Tung Chan Wai. The LCA is dominated by the small-scale
village settlements, mainly with low-rise houses in a dense cluster. As a
result of human disturbance, the landscape value and quality are considered
as medium, and it has a medium capacity to accept changes. The overall sensitivity is considered
“Medium”. |
Medium |
LCA6 |
Miscellaneous Rural Fringe Landscape |
LCA 6 refers to rural
areas which located in Chau Tau Village, Lok Ma Chau, and Mai Po San Tsuen.
This LCA consists of agricultural fields, patch of tree cluster and scattered
villages as well as open storage and parking areas which have been converted
from abandoned agricultural fields. Given the previously developed nature of
the LCA, the landscape value and quality are considered as medium. The
overall sensitivity is considered “Medium”. |
Medium |
LCA7 |
Comprehensive Residential Development |
This LCA 7 refers to the
areas composed of comprehensive residential development near Fairview Park
and Palm Springs. The LCA has limited natural vegetation and mainly comprised
of artificial landscaping. As a result of the man-made nature, the landscape
value and quality are considered as low. The overall sensitivity is considered
“Low”. |
Low |
LCA8 |
Institutional Landscape |
LCA 8 refers to urban areas of the San Tin Barracks,
water treatment work and Tam Mei Barracks. This LCA is dominated by small or
medium sized barracks, open areas, and car parks. The LCA also has some
patches of vegetation clusters well as vegetation associated with the
barracks and open areas. As a result of the built nature and special
characteristic of this LCA, the landscape value and quality are considered as medium. This LCA has a medium capacity to accept
changes. The overall sensitivity is considered “Medium”. |
Medium |
LCA9 |
Transportation Corridor Landscape |
This LCA 9 refers to the
major areas of San Tin Highway, Fanling Highway, Kwu Tung Road, and San Tin
Interchange. Vegetation cover is restricted to a narrow strip with grass and
some roadside planting. Given the man-made nature of this LCA, the landscape
quality and value are considered as low, and has a high capacity to accept
changes. As a result, the overall sensitivity is considered “Low”. |
Low |
LCA10 |
Miscellaneous Urban Fringe Landscape |
LCA 10 refers to the mix used areas in the LMC BCP
and adjoining areas including the Loop future development. This LCA is
dominated by administration building, utility facilities, scattered
associated open storages, vacant land, channelised watercourses and traffic
roads. It also contains some plantation along the control point. As this
landscape has been heavily developed, due to its man-made nature, it is
considered to have a high capacity to accept changes. The overall sensitivity
is considered “Low”. |
Low |
Broad-brush Tree Survey
Table 14.5 Broad Estimated Number of Trees within
each LR
ID |
Landscape Resources |
Area within Project area (ha) |
Estimated Number of Trees within the
LR |
LR1.0 |
Marsh/ Reed |
8.0 |
738 |
LR2.0 |
Compensatory
Wetland |
4.9 |
740 |
LR3.1 |
Ponds near San
Tin and Sam Po Shue |
92 |
4165 |
LR3.2 |
Ponds near
Siu Hum Tsuen and Shek Wu Wai San Tsuen |
3.1 |
371 |
LR3.3 |
Ponds near
Ngau Tam Mei |
N/A |
N/A |
LR4 |
Natural
Watercourse |
0.2 |
34 |
LR5 |
Modified
water course |
9.4 |
529 |
LR6 |
Semi-Natural
Watercourse |
6.5 |
397 |
LR7 |
Seasonal Wet
Grassland |
0.1 |
9 |
LR8 |
Wet
Agricultural Land |
0.2 |
18 |
LR9 |
Dry
Agricultural Land |
10.3 |
1044 |
LR10 |
Woodland |
5.2 |
929 |
LR11 |
Mixed
Woodland |
29.7 |
4945 |
LR12.1 |
Plantation on slope |
12.0 |
4105 |
LR12.2 |
Plantation along roadside |
14.1 |
2645 |
LR13 |
Shrubland |
16.2 |
3080 |
LR14 |
Grassland |
17.6 |
2818 |
LR15 |
Village/ Orchard |
34.7 |
4094 |
LR16.0 |
Vegetation in developed area (Including residential area and man-made
structure) |
228 |
21935 |
LR17 |
Vegetation in Waste land/open storage/ temporary area |
117 |
11894 |
Visual Baseline
· The visual envelope may extend to the whole of the area from which the development site and the proposed scheme is visible. That area from which any part of the proposed development would be visible is extensive on account of the scale of the proposed development and the fact it is situated at lowland and wetland area which will be visually prominent. However, it should be noted that for the purposes of this assessment, a nominal approximate 6.5km Project area has been taken around the proposed development as it is considered that the visual impact generated by the proposed development would be insignificant beyond this distance.
· Baseline review of Visual Sensitive Receivers (VSRs) within the visual envelope are described, together with their sensitivity to change and ability to accommodate changes in the following section.
Table 14.6 Visually
sensitive receivers (VSRs) and their sensitivity |
|||||||||
VSR ID. |
Visually Sensitive Receiver (VSR) |
Type
of VSRs |
Number
of Individuals (Many/ Medium/ Few) |
Quality
of Existing View (Good/Fair/
Poor) |
Availability of Alternative Views (Yes/No) |
Degree
of Visibility (Full/
Partial/ Glimpse) |
Duration
of View (Long/ Medium/ Short) |
Frequency
of View (Frequent/ Occasional/ Rare) |
Sensitivity (Low, Medium, High) |
R1 |
Low-rise residents of Maple Garden, Palm Springs, and Royal Palm |
Residential |
Many |
Fair |
Yes |
Full |
Long |
Frequent |
Medium |
R2 |
Residents of Mai Po San Tsuen, Mai Po Lo Wai |
Residential |
Medium |
Fair |
Yes |
Partial |
Long |
Frequent |
Medium |
R3 |
Residents of San Tsing Lung Tsuen, Yan Sau Wai, On Lung Tsuen, Wing
Ping Tsuen, Fan Tin (San Yi Cho and Ming Tak Tong), San Lung Tsuen, Tung Chan
Wai |
Residential |
Medium |
Fair |
Yes |
Partial |
Long |
Frequent |
High |
R4 |
Residents of Long Ha Tsuen, Man Yuen Tsuen, and Pok Wai Village |
Residential |
Medium |
Fair |
Yes |
Partial |
Long |
Frequent |
Medium |
R5 |
Residents of the Vineyard and low-rise residential area along Tam Mei
Road |
Residential |
Medium |
Fair |
Yes |
Partial |
Long |
Frequent |
Medium |
R6 |
Residents of Chau Tau Village, Poon Uk Tsuen |
Residential |
Few |
Fair |
Yes |
Full |
Long |
Frequent |
High |
R7 |
Residents of Fair View Park |
Residential |
Many |
Fair |
Yes |
Glimpse |
Long |
Frequent |
Medium |
R8 |
Residents of Proposed Kwu Tung North New Development Area and Ma Tso
Lung area. |
Residential |
Medium |
Fair |
Yes |
Partial |
Long |
Frequent |
Medium |
R9 |
Future residents of the Loop development |
Residential |
Medium |
Fair |
Yes |
Full |
Long |
Frequent |
High |
R10 |
Residents of Shek Wu Wai, recreational users of Shek Wu Wai Playground |
Residential/Recreational |
Few |
Fair |
Yes |
Full |
Long |
Frequent |
High |
R11 |
Residents of Ha Wan Fisherman San Tsuen |
Residential |
Few |
Fair |
Yes |
Full |
Long |
Frequent |
High |
REC 1 |
Hikers along Ngau Tam Shan Hiking Trail |
Recreational |
Medium |
Good |
Yes |
Partial |
Medium |
Occasional |
Medium |
REC 2 |
Visitors of Mai Po Marsh Wetland reserve |
Recreational |
Few |
Good |
Yes |
Full |
Medium |
Rare |
Medium |
REC 3 |
Hiker of Ki Lun Shan |
Recreational |
Few |
Good |
Yes |
Full |
Medium |
Rare |
Medium |
REC 4 |
Park visitors of San Tin Park and Man Tin Cheung Park |
Recreational |
Many |
Fair |
Yes |
Glimpse |
Medium |
Occasional |
Medium |
REC 5 |
Hikers of Lam Tsuen Country Park |
Recreational |
Medium |
Good |
Yes |
Full |
Medium |
Occasional |
High |
REC 6 |
Future users of Sam Po Shue Wetland
Conservation Park |
Recreational |
Medium |
Good |
Yes |
Full |
Medium |
Occasional |
High |
T1 |
Travellers of San Tin Highway |
Travelling |
Many |
Poor |
Yes |
Glimpse |
Short |
Rare |
Low |
T2 |
Users of MTR Lok Ma Chau Station |
Travelling |
Many |
Fair |
Yes |
Glimpse |
Short |
Rare |
Low |
T3 |
Traveller of Fan Ling Highway |
Travelling |
Many |
Fair |
Yes |
Glimpse |
Short |
Rare |
Low |
O1 |
Workers of Open Storage/ Industrial usage of Ngau Tam Mei |
Occupational |
Medium |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
O2 |
Workers around Castle peak road (Mai Po section) |
Occupational |
Medium |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
O3 |
Farmer in Agricultural land near LMC BCP |
Occupational |
Medium |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
O4 |
Industrial and potential tertiary users of Kwu Tung and Pak Shek Au |
Occupational |
Medium |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
O5 |
Workers in open storage |
Occupational |
Few |
Fair |
Yes |
Full |
Short |
Occasional |
Low |
O6 |
Future workers of the Loop development |
Occupational |
Medium |
Fair |
Yes |
Full |
Medium |
Occasional |
Medium |
GIC1 |
Lok Ma Chau Operation Base |
Institutional |
Medium |
Fair |
Yes |
Partial |
Medium |
Occasional |
Medium |
GIC2 |
Users of Gurkha Cemetery |
Institutional |
Few |
Fair |
Yes |
Full |
Medium |
Occasional |
Medium |
GIC3 |
Users of San Tin Barracks |
Institutional |
Few |
Fair |
Yes |
Glimpse |
Medium |
Occasional |
Medium |
GIC4 |
Users of Tam Mei Barracks |
Institutional |
Few |
Fair |
Yes |
Glimpse |
Medium |
Occasional |
Low |
Note: R = Residential; Rec = Recreational;
T=Transport Related/ Traveller; I=Institutional, GIC=Government/Community, O=
Occupational,
Direct Impact:
·
Construction of the development within building lot
of the Project (Schedule 3 DP)
·
Site clearance works involving the removal of the
existing storage containers and recreational facilities, as well as the removal
of existing trees, shrub planting, fishpond and wetland;
·
Site formation works including cutting and filling;
·
Construction of the viaduct and finishing works;
·
Excavation works and haulage off-site of excavated
materials;
·
Storage of existing topsoil for reinstatement
works;
·
Importation and storage of construction equipment
and plant;
·
Materials
stockpiling;
·
Construction of site access;
·
Temporary traffic management activities;
·
Removal of existing roads
·
Construction of local road and associated internal
site roads and bridges;
·
Construction of proposed San Tin Station and proposed
station near Chau Tau, as well as proposed residential, mixed use, I&T,
logistic, storage and workshop uses (LSW) and
Other Specified Use development;
·
Construction of proposed tracks and stations
platforms;
·
Re-alignment of roads;
·
Re-alignment and upgrading of drainage channel and
watercourse;
·
Laying down utilities including water, drainage, power,
and waste;
·
Construction of the temporary parking areas,
on-site accommodation offices and structures and working areas, importation and
storage of equipment and materials;
·
Indirect Impact;
·
Construction traffic;
·
The laying down of utilities, including water,
drainage and power;
·
Temporary site access areas, site cabins and heavy
machinery;
·
After dark lighting and welding; and
·
Dust and construction debris.
·
Operation of individual development within the
building lot of the Project;
·
Operation
of proposed San Tin Station and proposed station near Chau Tau, proposed
residential, mixed use, I&T, LSW and Other Specified Use development;
·
Operation of proposed
Open Space;
·
Provision of Noise
mitigation structures;
·
Residual
impacts of permanent removal of existing trees and other vegetation; and
·
Changes
of landscape character permanently due to the Project.
Table 14.7 Magnitude of Landscape Impact during Construction and Operation |
|||||
ID
No. |
Landscape
resources/ Landscape character areas |
Description of works |
Description of Impacts (Area loss (ha) / Total Area of LR (ha)/ Type of loss) |
Magnitude of change (Large/
Intermediate/ Small/ Negligible) |
|
Construction |
Operation |
||||
Landscape resources (LRs) |
|||||
LR1.0 |
Marsh/ Reed |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D1, Road P1 (DP1) and Road D2 (DP1) - Site
clearance work for “OU(I&T)”, “G/IC”, “OU(MU), “Rsc”, “O” and associated
internal development. - Run-off
from site clearance works and construction of the temporary structures and
working areas |
- Disturbance
to existing landscape resource by construction activities. - Permanent
loss of approx. 63% of this LR -
Baseline area coverage is approx.14 ha. Permanent
loss 9 ha. of LR 1.0 -
A total of approx. 738 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Intermediate |
Intermediate |
LR2.0 |
Compensatory wetland |
- The
Project (Schedule 3 DP) - Run-off
from construction of the temporary structures and working areas. |
- Disturbance
to existing landscape resource by construction activities. - Permanent
loss of approx. 4.96 ha (22%) of mitigation wetland of STEMDC - Baseline
area coverage is approx. 22.7 ha. - A
total of approx. 75 nos. of trees will be either transplanted or felled,
subject to detailed design. - The
compensatory wetland abutting STEMDC will be disturbed during construction
phase. Affected compensatory wetland will be reinstated as part of the
revitalisation of STEMDC. |
Intermediate |
Intermediate |
LR3.0 – Ponds |
|||||
LR3.1 |
Ponds near San Tin and Sam Po
Shue |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D3 (DP1) - Construction
and operation of O.1.1, O.1.2 (DP7) - “OU(I&T)”,
“G/IC” and internal connection road - Construction
of temporary structures and working areas - Run-off
from site clearance works. - Run-off
from construction of the temporary structures and working areas. - Permanent
operation of “OU(I&T)”, “G/IC” |
- Permanent
loss of partial extent of existing vegetation around ponds. - Approx. 41% of this area will be permanently
loss due to the works especially the existing vegetation around the ponds. -
Baseline area coverage is approx. 222.5 ha.
Permanent loss of 92 ha. -
A total of approx. 4,146 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Large |
Large |
LR3.2 |
Ponds near Siu Hum Tsuen and Shek Wu Wai San Tsuen |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D1 (DP1) - Site
clearance work for “O”, “Rsc”, “OU(MU)”, “G/IC” and associated internal roads. - Run-off
from site clearance works. - Run-off
from construction of the temporary structures and working areas. - Permanent
operation of “O”, “Rsc”, “OU(MU)” and “G/IC” |
- Permanent
loss of partial extent of existing vegetation around pond. - Approx.83%
of this LR will be affected. -
Baseline area coverage is approx. 3.74 ha. - Permanent
loss of 3.1 ha. - A
total of approx. 877 nos. of trees will be either transplanted or felled,
subject to detailed design. |
Large |
Large |
LR 3.3 |
Ponds near Ngau Tam Mei |
- No
permanent work is proposed. |
- Baseline
area coverage is approx. 2 ha. - No
tree will be felled or transplanted. |
Negligible |
Negligible |
LR4.0 |
Natural Watercourse |
- No
permanent work is proposed. |
- Baseline
area coverage is approx. 5.95 ha. - No
tree will be felled or transplanted. |
Negligible |
Negligible |
LR5.0 |
Modified watercourse |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D1 (DP1) -
Revitalisation of San Tin Eastern &
Western Main Drainage Channel (DP6) - Construction
of “R”, “Rsc”, “OU”, and “O” developments and associated internal roads. - Channel
enhancement measures, including development of associated infrastructure
along channel will be implemented. - Diverting
of channel alignment due to conflict with proposed development OU(I&T) - Boxing
and culverting of a portion of existing channel - Construction
of associated internal site roads. - Permanent
Operation of “R”, “Rsc”, “OU”, and “O” developments |
- Approx.
16% of this LR will be permanently loss due to the works, including the
existing vegetation around the ponds. -
Baseline area coverage is approx. 24.29
ha. Permanent loss of 3.8 ha - A
total of approx. 441 nos. of trees will be either transplanted or felled,
subject to detailed design. |
Small |
Small |
LR6.0 |
Semi-Natural
Watercourse |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D1 (DP1) - Site
clearance for proposed “OU(I&T)”,
“G/IC” and “O” developments and associated internal roads. - Channel
enhancement measures, including development of associated infrastructure
along channel will be implemented. - Boxing
and culverting of a portion of existing channel - Construction
of associated internal site roads. |
- Temporary
disturbance to existing landscape by construction activities and channel revitalisation
along proposed open space. - Approx.
1.1 ha. (6%) will be temporary disturbed during construction phase. These are
found in the proposed “A” and “O” in Pang Loon Tei, Chau Tau Tsuen and around
San Tin. - Approx.
55% of this LR will be permanently loss. -
Baseline area is approx.11 ha. Permanent
loss of 6.1 ha -
A total of approx. 551 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Intermediate |
Intermediate |
LR7.0 |
Seasonal Wet Grassland |
- The
Project (Schedule 3 DP) - Construction
of Road D5 (DP1) - Run-off
from site clearance works. - Run-off
from construction of the temporary structures and working areas. - Permanent
demolition of existing seasonal wet grassland along Castle Peak Road. |
- Permanent
loss of entire 0.1 ha of LR due to works. -
Approx. 43% loss. Baseline area is approx.
0.23 ha. -
A total of approx.9 nos. of trees will be
either transplanted or felled, subject to detailed design. |
Intermediate |
Intermediate |
LR8.0 |
Wet Agricultural Land |
- The
Project (Schedule 3 DP) - Construction
and operation of Road D1 (DP1) - Site
clearance for “O”,” “Rsc”,” G/IC” and associated internal roads. - Run-off
from site clearance works. - Run-off
from construction of the temporary structures and working areas. - Demolition
of existing seasonal wet grassland along caste peak road for” O”, “G/IC”,” R”
and “OU(RAF)” |
- Permanent
loss of all 0.2 ha of LR due to works. -
Baseline area is approx. 0.20 ha. A total of
approx. 18 nos. of trees will be either transplanted or felled, subject to
detailed design. |
Large |
Large |
LR9.0 |
Dry Agricultural Land |
- The Project (Schedule 3 DP) - Site
clearance for Open space “O”, “G/IC”, “Rsc” and “R”, and “E” development. - Construction
of temporary structures and working areas - Construction
of access roads and associated internal roads. - Permanent
demolition of LR9 |
- Approx.
76% of this LR will be permanently loss due to the works, including the
existing vegetation around the dry agricultural land. -
Baseline area is approx. 13.7ha. -
Permanent loss of 10.36 ha -
A total of approx. 1,558 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Large |
Large |
LR10.0 |
Woodland |
- The
Project (Schedule 3 DP) -
Site clearance for “OU(I&T)” - Construction
of temporary structures and working areas - Construction
of access roads and associated internal roads. -
Permanent demolition of LR10 abutting San
Tin Highway |
- Temporary
disturbance to existing landscape resource by construction activities - Approx.
5.3% of this LR will be affected permanently. - Baseline
area coverage is approx. 31.8ha. Permanent loss of 1.7 ha of this LR - A
total of approx. 267 nos. of trees will be either transplanted or felled,
subject to detailed design. |
Small |
Small |
LR11.0 |
Mixed Woodland |
- The
Project (Schedule 3 DP) - Construction
and operation of DP2, DP4 and DP7 - Site
clearance for “G/IC”, “OU(MU)”, “Rsc” and “O” and “A” - Construction
of access roads and associated internal roads. - Construction
of temporary structures and working areas -
Partial permanent loss of LR 11 near Mai
Po Lung, Tsuen, and Shek Wu Wai San Tsuen
|
- Temporary
disturbance to existing landscape by construction activities - Approx.
17% of this LR will be affected. - Affected
Mixed woodland is located near Mai Po Lung Tsuen and Shek Wu Wai San Tsuen. -
Baseline area is approx. 97.43 ha.
Permanent loss of 16.3 ha. mixed
woodland. - A
total of approx. 4,793 nos. of trees will be either transplanted or felled,
subject to detailed design. |
Intermediate |
Intermediate |
LR12.0 Plantation |
|||||
LR12.1 |
Plantation on slope |
- Proposed
Project (Schedule 3 DP) - Site
clearance for “G/IC” - Construction
of access roads and associated internal roads. - Construction
of temporary structures and working areas - Permanent
loss of partial plantation -
Operation of new development |
- Approx.
9% of this LR will be affected permanently. -
Baseline vegetation coverage is approx. 40.1
ha. Permanent loss of 3.8 Ha. mixed
woodland. - A
total of approx. 3,114 nos. of trees will be either transplanted or felled,
subject to detailed design. |
Small |
Small |
LR12.2 |
Plantation along roadside |
- Proposed Project (Schedule 3 DP) - Operation
of new development - Site
clearance for “G/IC”, “OU(MU)”, “Rsc”, “O” and “A” - Construction
of access roads and associated internal roads. (Including Road L5, L10) - Construction
of temporary structures and working areas - Permanent
loss of partial plantation |
- Approx.58%
of this LR will be affected permanently. -
Baseline vegetation coverage is
approx.24.35 ha. Permanent loss of
plantation of approx. 14. ha -
A total of approx. 2,541 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Intermediate |
Intermediate |
LR13.0 |
Shrubland |
- Proposed
Project (Schedule 3 DP) -
Operation of new development and Road D1,
D2 (DP1) - Site
clearance works for “G/IC”, “E” and “Rsc”. - Construction
of the Temporary structures and working areas - Construction
of associated internal roads. - Temporary
disturbance to existing landscape by construction activities as most of LR13
is planned as Green Belt area or outside the development boundary. - Permanent
loss of partial plantation -
Operation of new development. |
- Permanent
loss of shrubland approx. 11% of this LR - Baseline
vegetation coverage is approx. 109 ha. Permanent loss of 11.8 ha. -
A total of approx. 2,859 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Small |
Small |
LR14.0 |
Grassland |
- Proposed
Project (Schedule 3 DP) - Operation
of new development and Road D1 (DP1). - Site
clearance works for “OU(I&T)”, “OU(MU)”, “O”, “GIC”, “Rsc”. - Construction
and operation of Road D1 (DP1) - Construction
of the temporary structures and working areas - Construction
of associated internal roads. -
Permanent loss of grassland located within
development boundary near Pang Loon Tei, Chau Tau Tsuen, Lin Barn Tsuen, and
adjoining of San Tin Tsuen Road. |
- Permanent
loss of plantation of approx. of 6%. -
Baseline vegetation coverage is approx.20
ha. Permanent loss of plantation of approx. 16.9 ha -
A total of approx. 2,804 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Small |
Small |
LR15.0 |
Village/ Orchard |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of DP2. - Site
clearance works for “G/IC”, “Rsc”. “OU(MU)”, “O” and “E” - Construction
of temporary structures and working areas. - Construction
of access roads and associated internal roads. - Permanently
demolition of existing Orchard near Pang Loon Tei, LMC BCP, Siu Hum Tsuen. - Partial
extent of orchard is demolition near Mai Po Lung Tsuen Pang Loon Tei, Shek Wu
Wai/ Shek Wu Wai San Tsuen, Chau Tau Tsuen - Operation
of new development. |
- Permanent
loss of plantation of approx. 44%. -
Baseline vegetation coverage is approx. 78.73ha.
Permanent loss of plantation of approx. 34.7. ha. -
A total of approx. 4,031 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Intermediate |
Intermediate |
LR16.0 |
Vegetation in developed area (Including residential area and man-made
structure) |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of DP1, DP2, DP3, DP4, DP5, DP7. - Demolition
of some of the existing structures/road and associated structures. - Construction
of access roads and associated internal roads. - Operation
of new roads network and development. |
- Permanent
loss of approx. 50% of this LR. -
Baseline coverage is approx. 453.7ha. Permanent loss of approx. 227 ha. -
A total of approx. 21,715 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Large |
Large |
LR17.0 |
Vegetation in Waste land/open storage/ temporary area |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of DP1, DP2, DP3, DP4, DP5, DP7. - Demolition
of existing Open storage/waste ground and associated structures. - Construction
of access roads and associated internal roads. - Site
clearance work for Schedule 3 DP development. - Operation
of new roads network and development. |
- Permanent
loss of approx. 98% of this LR. -
Baseline coverage is approx. 127.3 ha Permanent
loss of approx.117.2ha. -
A total of approx. 11656 nos. of trees will
be either transplanted or felled, subject to detailed design. |
Large |
Large |
Landscape character area (LCAs) |
|||||
LCA1 |
Settled Valley Landscape |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of Road D5 (DP1). - Construction
of the I&T development and associated “O”, “GIC” and associated roads. - Site
clearance works. - Presence
of construction equipment. - Construction
of the temporary structures and working areas. - New
buildings and road network replacing existing development and vegetation. |
-
Proposed works
alters the perception of landscape and visual amenity of LCA1, especially
area within the Pang Loon Tei. -
A portion of
LCA1 will permanently be affected while the nature of works is differ from
existing elements. -
Magnitude of
change would be intermediate. |
Intermediate |
Intermediate |
LCA2 |
Upland And Hillside Landscape |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of Road D5 (DP1). - Construction
of the I&T development and associated “O”, “G/IC” and associated roads. - Site
clearance works. - Presence
of construction equipment - Construction
of the temporary structures and working areas. -
New buildings and road network replacing
existing development and vegetation. |
-
Proposed works
within the Pang Loon Tei alters the perception of landscape and visual
amenity of LCA2. -
The impact is
at the peripheral area and relatively small. -
Magnitude of
change would be small. |
Small |
Small |
LCA3 |
Rural Coastal Plain Landscape |
- Proposed
Project (Schedule 3 DP) - Construction
of the “OU(I&T)” development and associated “O”, “G/IC” and associated roads.
- DP1,
DP6, DP7 and associated internal roads. - Site
clearance works. - Presence
of construction equipment. - Construction
of the temporary structures and working areas - Construction
of the “OU(I&T)” and associated internal roads. - Construction
of residential developments. |
- Proposed
work would alter perception of landscape quality of the visual amenity of LCA. - Considered
the different nature of and scale of the development. - The
magnitude of change to this LCA is Large. |
Large |
Large |
LCA4 |
Rural Inland Plain Landscape |
- Proposed
Project (Schedule 3 DP). - Site
clearance works for “OU(I&T)” development, “O”, “GIC”, residential use,
“OU(MU)” Presence of construction equipment. - Construction
of the temporary structures and working areas. - Construction
of the “R”, “Rsc”, “OU(MU)”, “G/IC” and “OU(I&T)”
developments. - DP1-DP7
and associated internal roads. - New
proposed road networks and proposed development replacing the existing
generally open characters. |
- Proposed
work would change the landscape quality. - During
operation phases, majority of this LCA will be impacted. The nature of the
new development is largely different from current character. Permanent loss
of existing vegetation due to the replacement with infrastructure and/ or
buildings. - The
magnitude of change is considered as large. |
Large |
Large |
LCA5 |
Urban Peripheral Village
Landscape |
- Proposed
Project (Schedule 3 DP) - Site
clearance works for “OU(I&T)” and “A”. - Presence
of the construction of the temporary structures and working areas. - Construction
and operation of the residential and amenity green. |
- Proposed
work would change the landscape quality. - Consider
the nature of the current and proposed development character are of similar
nature, the scale of work is localised. - The
magnitude of change is considered as small. |
Small |
Small |
LCA6 |
Miscellaneous Rural Fringe
Landscape |
- Proposed
Project (Schedule 3 DP). - Site clearance works for “OU(I&T)” and “A”. - Presence
of the construction of the temporary structures and working areas. - Associated
internal roads. - Construction
and operation of “G/IC”, “OU(I&T)” and “A”. |
- Proposed
work and construction within LCA6 alter perception of landscape quality and
visual amenity of LCA6. - Presence
of the projects alters perception of landscape quality and visual amenity of
LCA6. - Consider
the nature of the current and proposed development character are of similar
nature, the scale of work is localised. - The
magnitude of change is considered as small.
|
Small |
Small |
LCA7 |
Comprehensive Residential Development |
- Proposed
Project (Schedule 3 DP). - Site
clearance works. - Presence
of the construction of the temporary structures and working areas. - Associated
internal roads. - Construction
of the “G/IC” and “A”. |
- Construction
within LCA6 alters perception of landscape quality and visual amenity of LCA6. -
Consider the nature of the current and
proposed Project are of similar nature, it is compatible to surrounding
landscape character. -
Hence the magnitude of change is considered
as small. |
Small |
Small |
LCA8 |
Institutional Landscape |
Nil |
Nil |
Negligible |
Negligible |
LCA9 |
Transportation Corridor
Landscape |
- Proposed
Project (Schedule 3 DP) - Associated
internal roads. - Construction
of Iconic bridge, viaduct, and associated transportation infrastructure. - Construction
and operation of DP 1. |
- Construction
within LCA9 alters perception of landscape quality and visual amenity of LCA9. - During
Operation phases, the nature of the proposed development will be of similar
nature to current LCA. - Consider
the localised impact, the magnitude of change for both phase is small. |
Small |
Small |
LCA10 |
Miscellaneous Urban Fringe
Landscape |
- Proposed
Project (Schedule 3 DP). - Construction
and operation of OU(I&T) and associated infrastructure works and internal
roads. - Site
clearance works. - Presence
of the construction of the temporary structures and working areas. - Construction
and operation of DP1 and DP6. |
- During
construction phase, the temporary works area for the construction of the “OU(I&T)”,
connecting roads to the Loop and upgrading of San Sham Road. - During
operation phases, the majority of the LCA will be altered with viaduct
structures, Science Park type development and associated internal roads. - Consider
the localised impact and nature of the proposed development of similar nature
of current character. The magnitude of change is considered as intermediate. |
Intermediate |
Intermediate |
Insubstantial: LR4.0, LR3.3
Slight: LR2.0, LR5.0, LR12.1, LR13.0, LR14.0
Moderate: LR1.0, LR6.0, LR7.0, LR10.0, LR11.0, LR12.2, LR15.0, LR16.0
and LR17.0
Substantial: LR3.1, LR3.2, LR8.0, LR9.0
·
Construction of development within the building
lots of the Project (Schedule 3 DP);
·
Construction of landscape deck and elevated walkway;
·
Site clearance and potential tree removal/
transplanting;
·
Modification, retrofitting and/ or demolition of
existing structures;
·
Construction of the viaduct and finishing works;
·
Temporary access path, site offices, haul road,
storage of construction materials, heavy machinery, equipment and plants,
hoarding, construction traffic;
·
Loss of other vegetation due to the construction
works;
·
Dust and construction debris, and
·
Potential night-time glare arising from the
lighting of construction activities.
·
The laying down of utilities, including water,
drainage and power;
·
After dark welding, and
·
Dust during dry weather.
·
Operation of proposed above ground structures, including the proposed
mitigation measures such as noise barriers;
·
Permanent removal of existing trees, vegetation and
other natural or rural features such as wetland, fishponds, farmland, orchard,
settlements, etc; and
·
Changes of visual environment and landscape
character permanently due to the Project.
·
DP1 – Construction and operation of new primary distributor road P1,
district distributor road D1, D2, D3, D4, D5 and D6
·
major public viewpoint
which covers the proposed development to represents key VSRs or VSR groups who
would be potentially affected by the proposed permanent structures; and
·
the viewpoints
should be able to represent the worst-case scenarios and demonstrate the compatibility of the proposed development to the adjacent visual
context and illustrate the visual effect during Day 1 without mitigation
measures, Day 1 with mitigation measures and Year 10 with mitigation measures.
Table 14.8 Magnitude of Visual Impact
during Construction and Operation Phases
Visually sensitive receiver (VSR) |
Type of VSR |
Source of visual impact |
Approx. viewing distance (m) |
Compatibility of the project with the surrounding landscape (High/ Medium/ Low) |
Duration of impacts (Long/ Medium/ Short) |
Scale of development (Large/ Medium/ Small) |
Reversibility of change (Yes/ No) |
Potential blockage of view (Full/ Partial/ Nil) |
Magnitude of change (Large/ Intermediate/ Small/ Negligible) |
|||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
|||||
R1 |
Low-rise
residents of Maple Garden, Palm Springs and Royal Palm |
Residential |
The Project, DP3 |
300-1000m |
Medium |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
R2 |
Residents of
Mai Po San Tsuen, Mai Po Lo Wai |
Residential |
The Project, DP
2, DP3 |
50-100m |
Medium |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
R3 |
Residents of
San Tsing Lung Tsuen, Yan Sau Wai, On Lung Tsuen, Wing Ping Tsuen, Fan Tin
(San Yi Cho and Ming Tak Tong), San Lung Tsuen, Tung Chan Wai |
Residential |
The Project, DP2,
DP3 |
150-200m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Large |
Large |
R4 |
Residents of
Long Ha Tsuen, Man Yuen Tsuen, and Pok Wai Village |
Residential |
The Project |
1600-2500m |
Medium |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Nil |
Nil |
Negligible |
Negligible |
R5 |
Residents of
Vineyard and low-rise residential area along Tam Mei Road |
Residential |
The Project |
750m |
Medium |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Partial |
Partial |
Small |
Small |
R6 |
Residents of
Chau Tau Village, Poon Uk Tsuen |
Residential |
The Project,
DP1 |
50-150m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
R7 |
Residents of
Fair View Park |
Residential |
The Project |
1000-2400m |
Medium |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Partial |
Partial |
Negligible |
Negligible |
R8 |
Residents of
Proposed Kwu Tung New Town Development and Ma Tso Lung area. |
Residential |
The Project |
2000-3000m |
Medium |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Partial |
Partial |
Negligible |
Negligible |
R9 |
Future
residents of the Loop. |
Residential |
The Project,
DP1 |
350m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
R10 |
Residents of
Shek Wu Wai, recreational users of Shek Wu Wai Playground |
Residential |
The Project |
200m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Full |
Full |
intermediate |
intermediate |
R11 |
Residents of
Fisherman San Tsuen |
Residential |
The Project |
10m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
REC 1 |
Hikers along
Ngau Tam Shan Hiking Trail |
Recreational |
The Project, DP5 |
400m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Large |
Large |
REC 2 |
Visitors of Mai
Po Marsh Wetland reserve |
Recreational |
The Project |
570m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
REC 3 |
Hiker of Ki Lun
Shan |
Recreational |
The Project |
300m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Large |
Large |
REC 4 |
Park visitors
of San Tin Park and Man Tin Cheung Park |
Recreational |
The Project |
100-250m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
REC 5 |
Hikers of Lam
Tsuen Country Park |
Recreational |
The Project |
2300m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
REC 6 |
Future users of Sam Po Shue wetland
conservation park |
Recreational |
The Project, DP7 |
570m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
T1 |
Travellers of
San Tin Highway |
Travelling |
The Project, DP1,
DP2, DP2, DP4, DP5 |
Transient, 0m |
Medium |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
T2 |
Users of MTR
Lok Ma Chau Station |
Travelling |
The Project |
Transient, 350m |
Medium |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
T3 |
Traveller of
Fan Ling Highway |
Travelling |
The Project, DP4 |
Transient, 0m |
Medium |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Small |
Small |
O1 |
Workers of Open
Storage/ Industrial usage of Ngau Tam Mei |
Occupational |
The Project |
1100m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Partial |
Partial |
Small |
Small |
O2 |
Workers around
Castle peak road (Mai Po section) |
Occupational |
The Project, |
950- 1500m |
Low |
Medium |
Medium |
Long |
Medium |
Medium |
Yes |
No |
Nil |
Nil |
Negligible |
Negligible |
O3 |
Farmer in
Agricultural land near LMC BCP |
Occupational |
The Project, DP5 |
10-50m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
O4 |
Industrial and
potential tertiary users of Kwu Tung and Pak Shek Au |
Occupational |
The Project |
270-300m |
Low |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Small |
Small |
Small |
Small |
O5 |
Workers in open
storage |
Occupational |
The Project |
0m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
O6 |
Future workers
of the Loop development |
Occupational |
The Project,
DP1, DP9 |
350m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
GIC1 |
Lok Ma Chau Operation
Base |
Institutional |
The Project,
DP1 |
1900m |
Low |
Medium |
Medium |
Long |
Small |
Small |
Yes |
No |
Partial |
Partial |
Small |
Small |
GIC2 |
Users of Gurkha
Cemetery |
Institutional |
The Project, DP5
|
150m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Full |
Full |
Large |
Large |
GIC3 |
Users of San
Tin Barracks |
Institutional |
The Project, DP5 |
250 |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Full |
Full |
Large |
Large |
GIC4 |
Users of Tam
Mei Barracks |
Institutional |
The Project |
350-700m |
Low |
Medium |
Medium |
Long |
Large |
Large |
Yes |
No |
Partial |
Partial |
Intermediate |
Intermediate |
Note: The Project= Schedule 3 project, VSR= Visually sensitive
receivers, R = Residential; Rec = Recreational; T=Transport Related/ Traveller;
I=Institutional, GIC=Government/Community, O= Occupational,1= will be removed
during operation phases.
Residential
Occupational
Residential
Travelling
Occupation/ G/IC
Residential
Recreational
Travelling
Occupation/
G/IC
Residential
Recreational
Landscape
and Aesthetic
External Design Measures in the Proposed Scheme
Avoidance of potential impacts
·
The boundary of the Project area has been optimised
to avoid impact on a patch of moderate to high ecological value mature woodland
and a section of natural watercourse behind San Tin Barracks at Pang Loon Tei.
·
High value
natural landscape should be well protected and preserved. Important features of higher ecological value and egretries are areas of
conservation importance within the assessment area. An “Open Space” was proposed under the Revised
RODP, where the loss of the roosting substratum at the MPLV Egretry would be
avoided and minimised. Construction
activities near the MPLV Egretry should only be conducted outside the breeding
season (September to February in the following year) in order to minimise the
potential disturbance impact on the egretry.
Enhancement measures (e.g., water features and planting of mature trees)
were also proposed at the “Open Space” located adjacent to the MPLV Egretry to
promote ardeid usage. While the loss of
San Tin Open Storage Area Night Roost and Ha Wan Tsuen Night Roost would be
unavoidable, roosting area would be re-provided in the open space along the
bank of the diverted channel and adjacent to the proposed fisheries research
centre respectively, under the Revised RODP.
The re-provided night roost would comprise water features and mature
native tree species that are currently used as a roosting substratum. These features should be established prior to
the dry season prior to the arrival of overwintering birds in order to provide
suitable roosting opportunities.
·
Under the Revised RODP, 37.35 ha of the Project are excluded from
development, and would be zoned, and preserved as Green Belt. It has preserved 3.54 ha of woodland falling
within the Project area and 12.18 ha of mixed woodland. For further detail, refer to Section 10
of the EIA Report.
Enhancement in Landscape and Visual Aspect
Table 14.9 Proposed Design Measures incorporated in
the Project
Design Measures |
|
DM1 |
Provision
of Wildlife corridor where appropriate and applicable -
Opportunity for ecological linkage is proposed at below location. -
1) Between STEMDC, Ha Wan Tsuen and Lok Ma Chau should be provided
for target mammal species via culvert / constructed wetland in order to
prevent roadkill and guiding wildlife into the underpasses. -
2) Provide ecological linkage between the various “GB” under the Revised
RODP, targeting mammal species of conservation importance -
Details of the proposed wildlife corridor shall be formulated in
detailed design in later stages and shall be agreed with relevant authorities
(e.g., AFCD and EPD) prior to commencement of construction works. It is expected that, provision of wildlife
corridor can maximise the ecological function of preserved “GB” and mitigate
the habitat fragmentation impact. -
To enhance visual and air permeability -
For further details, refer to Section 10.11.10 of the EIA
Report. |
(i)
Summary of proposed generic landscape and visual measures for the
overall proposed Project
(ii)
Summary of proposed landscape and visual mitigation measures for
specific Schedule 2 DPs
Table 14.10 Generic Proposed
Landscape and Visual Mitigation Measures for Construction Phase including Schedule 2
DPs
ID
No. |
Landscape
and Visual Mitigation Measures |
Funding Agency |
Implementation Agency |
CM1 |
Preservation of Existing Vegetation - All the existing vegetation and trees to be
retained and not to be affected by the Projects shall be carefully protected
during construction by means of fencing during construction stage to prevent
damage to tree canopies and root zones from vehicles and storage of
materials. - The tree preservation and tree treatment shall be
subject to the detailed design stage and in accordance with DEVB TC(W) No.
4/2020 - Tree Preservation and the latest guidelines on Tree Preservation
during Development issued by GLTMS of DEVB. - A detailed tree survey will be carried out for
the Tree Preservation and Removal proposal (TPRP) process which will be
carried out at the later detailed design stage of the Project. The detailed
tree survey will propose which trees should be retained, transplanted, or
removed and will include details of tree protection measures for those trees
to be retained. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM2 |
Transplantation of Existing Trees - Trees unavoidably affected by the works should be
transplanted as far as possible in accordance with DEVB TC(W) No. 4/2020- Tree preservation
and the latest Guidelines on Tree Preservation during Development issued by
GLTMS of DEVB. - Sufficient time should be reserved for the
advanced tree transplanting preparation works to enhance the survival rate of
the transplanted trees. - The transplanting proposals are subject to review
at the detailed design stage and to agreement-in-principle with the relevant
management and maintenance agents and/or Government departments. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM3 |
Reinstatement of Temporarily Disturbed Landscape
Areas -
All hard
and soft landscape areas disturbed temporarily during construction should be
reinstated on like-to-like basis, to the satisfaction of the relevant
Government departments. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM4 |
Minimise Disturbance on Watercourses -
The design
shall minimise disturbance on watercourses, particularly for natural
watercourse. Good site practices as described in ETWB TCW No. 5/2005
“Protection of natural streams/rivers from adverse impacts arising from
construction works” shall also be adopted to avoid any pollution entering the
watercourses nearby where applicable. Should temporarily or indirect disturbance
on watercourse is unavoidable, it shall be reinstated to the satisfaction of
relevant Government departments. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM5 |
Minimise Topographical Changes - The proposed site formation works should be
optimised to reduce topographical/ landform changes, as well as reduce land
take and interference with natural terrain. - Where there is a need to significantly cut into
the existing landform, retaining walls and cut slopes should be considered to
minimise landform changes and land resumption. - Earthworks and engineered slopes should be
designed to be a visually interesting landform, compatible with the
surrounding landscape and maximise greening opportunities. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Applicable
to Visual Impact |
|||
CM6 |
Management of Construction Activities and Facilities -
Management
of facilities on work sites which give control on the height and
disposition/arrangement of all facilities on the works site to minimise
visual impact to adjacent VSRs. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM7 |
Control on night- time lighting -
Control of
night-time lighting glare to prevent light overspill to the nearby VSRs and
into the sky. Relevant best practices
as suggested in the "Charter on External Lighting" and “Guidelines on Industry Best Practices
for External Lighting Installations” promulgated by The Environment Bureau (ENB)
shall be adopted. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM8 |
Construction of decorative hoarding around
construction works -
Erection
of decorative screen hoarding or hoarding compatible with the surrounding
setting. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM9 |
Advance planting of screen planting -
Advance
screen planting of fast-growing tree and shrub species to proposed
development |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
CM10 |
Creating interface between Ponds, Wetland and the
proposed Project - The 20m "landscape buffer” between
STEMDC and OU(I&T) and the 35m "landscape buffer” are being
proposed to create buffer between the existing and/or the development and
wetland. - Native tree species, shrub mix, and riparian
vegetation should be incorporated in the "landscape buffer”. - Phasing of pond filling works in San Tin – Sam Po
Shue area should be adopted. The pond
filling works should be started from urbanised area towards the wetland
area (i.e. from the southeast near STEMDC or San Tin Highway, towards the north-west),
and construction activities should be minimised at any one time, so as to
allow gradual displacement of wildlife. It shall be conducted during wet
season as far as practicable. For
details of the wetland enhancement areas, please refer to Section 2 -
Project description and Section 10 -Ecological Impact Assessment |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Table 14.11 Proposed Landscape and Visual
Mitigation Measures for Operation Phase including Schedule 2 DPs
ID No. |
Landscape and
Visual Mitigation Measures |
Funding
Agency |
Implementation
Agency |
Maintenance/
Management Agency* |
|
||||
Sensitive and
aesthetically pleasing design of aboveground structures -
Aesthetically pleasing design as regard to the
form, material and façade finishes should be incorporated to the proposed
above ground structures for both Schedule 2 and Schedule 3 DPs above ground
structures. Implementation of lighter colour tone, natural materials on
façade design should be implemented where appropriate. -
The planning of the Revised RODP has considered
reducing potential visual impacts, enhancing visual amenity, and keeping
visual corridors. The proposed development will ensure the building massing
is compatible with its surroundings. |
Government/ Private Sector |
Contractors of the Government/
Private Sector |
Contractors of the Government/ Private Sector/
Building proponents |
|
OM2 |
Landscape integration of build development -
Buffer tree planting and vertical greening shall
also be maximised for ventilation building, engineering structures and
associated facilities as far as appropriate to provide a source of green
visual relief, minimise any potential adverse landscape and visual impacts
through greening effect (e.g., provision of tree / shrub / climber planting),
and to blend in the structures to the adjacent landscape and visual
context. -
Integration of biophilic/ resilient/sustainable
landscape design, smart landscape infrastructure and edible planting are
encouraged where practicable subject to detail design stage. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Contractors of
the Government/ Private Sector/ Building proponents |
OM3 |
Provision of roadside planting/ amenity planting /
peripheral screening or planting -
Roadside soft landscape should be incorporated to
the proposed vehicular roads, station, and associated engineering facilities.
Ornamental and native species suited for roadside planting should be proposed
to soften the road corridors. Shade tolerant plants with tall to medium
height should be planted to under the viaduct to soften the hard edges and
provide screening. -
When technically feasible, application of
blue-green infrastructure and sustainable drainage system shall be
incorporated in roadside planters. |
Government |
Contractors of
the Government |
HyD/ LCSD |
OM4 |
Provision of new tree planting -
Compensatory tree planting should be provided in
accordance with DEVB TC(W) 4/2020 – Tree Preservation to compensate for
felled trees. -
Compensatory shrub planting should be provided to
compensate for the loss of shrub planting in amenity areas. -
As far as practicable, tree compensation within
the proposed Project will be provided at a 1:1 ratio when appropriate and
applicable. -
Trees affected by DPs will be compensated within
their respective DP areas. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/ Private Sector |
OM5 |
Incorporation of green roof -
Roof greening should be proposed to the roof area
of the proposed structures as far as practical to enhance the landscape
quality of the structures and mitigate any potential visual impact on
adjacent VSRs. Roof greening shall comply with the site coverage of greenery requirements
shall be in accordance with DEVB TC(W) No. 3/2012 – Site Coverage of Greenery
for Government Building Projects. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/ Private Sector |
OM6 |
Sensitive design of noise barriers -
The proposed noise barriers & enclosures
shall be design in an elegant manner that includes suitable combination of transparent
and sound absorbent materials, appropriate colour selection of panels and
supporting structures, or provision of at-grade planting of trees, shrubs
and/or climbers. |
Government |
Contractors
of the Government |
HyD |
OM7 |
Control of night-time
lighting glare -
All the night-time lighting shall be avoided
except for safety purpose. No light glare shall illuminate directly outside
the Project. Relevant best practices as suggested in the “Charter on External
Lighting” and “Guidelines on Industry Best Practices for External Lighting
Installations” promulgated by ENB shall be adopted. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
n/a |
OM8 |
Revitalisation
and naturalisation of river to create a Blue green network -
The major drainage channel/ man-made watercourse
channels within the Project area will be affected by the works. -
It presents an opportunity to better integrate
integrated blue-green infrastructure into the urban and landscape design. As
such, forming a more resilient blue-green feature facilitating drainage
function and a more scenic recreation destination. -
Where technically feasible, soft banks allowing
reed planting, tree planting shall be encouraged. - Ponds and water
features should be incorporated where appropriate |
Government |
Contractors
of the Government/DSD |
DSD |
OM9 |
Maximise greening on engineering structures and surfaces -
Where technically feasible and appropriate (i.e.,
where suitable depth of planting medium, maintenance access and enough light
penetration to ground level available) climber should be proposed at vertical
surfaces such as greening facade of building blocks, viaduct piers or noise
barriers to break up the appearance of uniform engineered structures and
surfaces. -
Tree planting integrate with wider streetscape
elements such as hardscape paving, outdoor furniture and lighting poles
should be considered to create a pedestrian-friendly network. -
At-grade road planting should be considered along
central median planters and on the road island with reference to DEVB TC(W)
No. 2/2012, DEVB TC(W) No. 1/2018, DEVB TC(W) No. 6/2015. - For greening of
highways specifically, refer to HQ/GN/15 – “Guidelines for Greening Works
along Highways”. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/ Private Sector |
OM10 |
Landscape treatment on slope -
To minimise adverse impacts in relation to LRs,
LCAs and VSRs site formation should be reduced as far as possible to avoid
substantial slope cutting. When condition does not allow, slope landscaping
shall be explored wherever possible. -
Hydroseeding of modified slopes should be done as
soon as grading works are completed to prevent erosion and subsequent loss of
landscape resources and character. -
Tree seedlings and/ or shrubs should be planted
where the slope gradient and site conditions allow. Greening shall be planted
on retaining structures associated with modified slopes, where technically
feasible. -
All slope landscaping works should comply with
GEO Publication No. 1/2011- “Technical Guidelines on landscape Treatment for
Slopes.” |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/Private Sector |
OM11 |
Sensitive design of landscape areas / provision
of Open Space -
The principles adopted in the Revised RODP ensure
that urban design and landscape framework are incorporated which will also
improve the landscape visual amenity. -
Elegant, sensitive design and generous planting
of the associated landscape areas. -
Provision of wetland/freshwater habitat/water
pond at appropriate location for habitat creation. -
All requirements for Open Space areas stated in
the EIA Report should be adhered to. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/Private Sector |
OM12 |
Off-site
woodland compensation -
Woodland compensation is proposed for woodland
that are unavoidably affected. The proposed location and detailed design are
subject to further agreement. -
Woodland compensation would be provided based on
“no net loss” and “like for like” basis or by providing a compensation area
with equivalent or higher ecological function. However, in light of a paucity
of suitable area for on-site compensation within the Project area, off-site
woodland compensation is considered instead. -
Plant species should be selected to include a mix
of species with pioneering characteristics (fast-growing/ light-tolerant/
drought-tolerant/ wind-tolerant, etc.) and native species and complementary
species to the local area. - For further
detailed for the proposed location and list of recommended species, refer to Section
10.13. |
Government |
Contractors
of the Government |
AFCD |
OM13 |
Creation
of landscape buffer -
An NBA namely “landscape buffer” area was
proposed along the northwestern boundary of the Revised ROPD, between the
proposed Project area in San Tin and Sam Po Shue Wetland, and also at the
existing LMC BCP, between the land use “OU(I&T).1.1.1” and STEMDC. -
The “landscape buffer” would minimise disturbance
from Project Area by providing a buffer area between the development and the
adjacent wetland and by incorporating gentle slope interface with the ponds
and planting of trees and native/ suitable vegetation. -
For further details, refer to Section 10.11.12. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/Private Sector |
OM14 |
Stepped building
height profile. -
The building height profile shall refer to the
recommended Building Height Concept (Appendix 14.2.4) down from the
south to the north to respond to the SPS WCP and the important bird flight
paths adjacent to the LMC station in order to minimise negative impacts on
the sensitive area. The pinnacles and building profiles of each character
zone shall also respect the peak and ridge line in the backdrop. -
As a broad general principle, the maximum
development height permitted will be reduced as they approach villages, low
rise developments and open space. While high-rise development shall be
considered at mixed use development and critical pedestrian and vehicular
entry. -
Low rise
profiles shall be adopted along ecologically sensitive areas. A stepdown
approach shall be used along important bird flight paths. For
further detail, refer to Section 14.5.17-14.5.19 and Appendix 14.2.4. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
Initiating
Government department (development user department)/Private Sector |
OM15 |
Provision of breezeway/ airpaths -
Provision of Breezeway/ Airpaths to ensure
effective air ventilation going through the Project and to improve the
micro-climate of its proposed urban environments in accordance with the HKPSG
Ch11- Urban Design Guidelines. - Major ones
include 1) along San Tin Highway and Fanling Highway towards Kwu Tung North New Development Area
to the east; 2) along proposed open space to the southeast of
the proposed San Tin Station, namely Town Park. 3) along the proposed major road of
Road D1 parallel to Town Park across the San Tin Town Centre (East) through the
proposed open space along STEMDC, namely Riverside Park towards the low-rise
education uses and Ki Lun Shan. -
Other breezeways are generally following the
revitalised river channels – STEMDC and STWMDC, major walkways and public
open space. -
To enhance visual and air permeability -
For further details, refer to Section
14.5.23-25. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
- |
OM16 |
Provision
of view corridor -
View Corridor are proposed to maximise and
aligned principally along major breezeways and visual connection to local
landmarks and visual resources. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
- |
*Management
and Maintenance Agencies are identified as per DEVB TCW No. 6/2015.
Agreement from individual agent shall be sought at the detailed design stage
before commencement of the contract. Note: The
Contractor shall be responsible for the maintenance of the soft landscape
works during the establishment period at operation phases. The project
proponent shall then be responsible for the management and maintenance of the
soft landscape work until such time those are successfully handed over to the
designated agent/department. |
·
Topsoil, where
identified, shall be stripped, and stored for re-use in the construction of the
soft landscape works.
·
Existing trees to
be retained on site shall be carefully protected during construction.
Table 14.12 Proposed Landscape and Visual Mitigation
Measures for Operational and Construction Phase for schedule 2 DPs
ID No. |
Landscape and
Visual Mitigation Measures |
Funding
Agency |
Implementation
Agency |
Maintenance/
Management Agency* |
Mitigation measures for
drainage related infrastructure DP- DP2,3 |
||||
Operation |
||||
OM17 |
Sensitive layout design of
above-ground structures -
All above-ground structures, including STLMC effluent
polishing plant (DP2) and STLMC Water Reclamation Plant (DP3), etc. shall be
sensitively designed in a manner that responds to the existing and planned
urban context. The height, form and layout shall be optimised to minimise
potential visual impact. -
The footprint layout and massing of development
components and the works area should also be kept to a practical minimum and
the detailed design of development components for construction phase should
follow the Sustainable Building Design Guidelines. -
The form, textures, finishes and colours of the
proposed development components should aim to be compatible with the existing
surroundings. |
Government |
Contractors
of the Government |
Initiating
Government department (development user department) |
Mitigation measures for
drainage related infrastructure DP- DP6,7 |
||||
Operation |
||||
OM18 |
Watercourse impact mitigation within WCA For channelised watercourses, if these are
modified, the DSD PN No. 3/2021- Guidelines on Design for Revitalisation of
River Channel, should be considered. Appropriate
mitigation measures should be proposed to ensure the new watercourses match
the existing as far as possible. Measures
can include enhancement planting to upgrade the channels as appropriate,
including consideration of wetland planting along embankments where
appropriate; as well as consideration of the best materials for the channel
lining (e.g., gabion). All measures
must also ensure any necessary maintenance work can be carried out and that
the channel meets all its requirements for water flow. |
Government/
Private Sector |
Contractors
of the Government/ Private Sector |
n/a |
*Management
and Maintenance Agencies are identified as per DEVB TCW No. 6/2015.
Agreement from individual agent shall be sought at the detailed design stage
before commencement of the contract. Note: The
Contractor shall be responsible for the maintenance of the soft landscape
works during the establishment period at operation phases. The project
proponent shall then be responsible for the management and maintenance of the
soft landscape work until such time those are successfully handed over to the
designated agent/department. |
Programme of Implementation of Landscape and Visual Mitigation Measures
Landscape
Resources
Landscape
Character area
Visual Impact
Photomontage
·
Existing Baseline Conditions – This photo illustrates the ‘before scenario’ – the
existing landscape conditions before construction of the Project
for the
purpose to assess the magnitude of visual change.
·
Day 1 without mitigation measures (Operation Phase) – This photomontage
illustrates the proposed the Project development at Day 1
without mitigation. This photomontage is
used to assess the effectiveness of implementing mitigation measures in
reducing the landscape and visual impacts.
·
Day 1 with mitigation measures (Operation Phase) – This photomontage
illustrates the proposed the Project development at Day 1 with
mitigation. The implementation of
mitigation measures at Day 1 will reduce the landscape and visual impacts
imposed by the proposed the Project at Day 1.
·
Year 10 with mitigation measures (Operation Phase) – This
photomontage illustrates the Project at Year 10 with
mitigation. The implementation of mitigation measures will have matured at
Year 10 further reducing the landscape and visual impacts imposed by the
proposed development.
Photomontage Viewpoint 1 – View from Community Sports
Photomontage Viewpoint 2 – View from Pak Shek Au cycle way
Photomontage Viewpoint 3 - View from Ki Lun Shan hiking trail
Photomontage Viewpoint 4 - View from Kai Kung Leng hiking
trail
Photomontage Viewpoint 5 - View from pedestrian footbridge of San
Tin Highway
Photomontage
Viewpoint 6 - View from pedestrian footbridge of
NT Circular Road
Photomontage Viewpoint 7 - View from Tam Kon Chau
Road near Mai Po Nature Reserve
Photomontage Viewpoint 8 - View from Lok Ma Chau MTR station
Photomontage
Viewpoint 9 - View from Yan Sau Wai
Photomontage
Viewpoint 10 - View from Man Tin Cheung Park
Photomontage Viewpoint 11- View from the Loop
Photomontage
Viewpoint 12 - View from hiking trail of Ngau
Tam Shan
Photomontage Viewpoint 13 – View from San Tam
Road/ Mai Po San Tsuen
Photomontage Viewpoint 14 - View from San Tin Highway Cycleway
(Castle Peak Rd - San Tin)
Photomontage Viewpoint 15 - View from San
Tin Highway footbridge
Photomontage
Viewpoint 16 – View
from Kwu Tung Road
Photomontage
Viewpoint 17 – View from Shek Wu Wai playground
Photomontage
Viewpoint 18 – View from Yau Pok
Road Near Tai Seng Wai
Table 14.13 Significance
of Landscape Impact during Construction and Operational Phases
Landscape Resource / Landscape Character Areas |
Sensitivity (Low,
Medium, High) |
Magnitude of Change (Negligible, Small,
Intermediate, Large) |
Impact Significance before Mitigation
(Insubstantial, Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Significance of Residual Impact after Mitigation (Insubstantial, Slight, Moderate, Substantial) |
||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
||||
Day 1 |
Year 10 |
||||||||||
Landscape Resources (LRs) |
|||||||||||
LR1.0 |
Marsh/ Reedbed |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM8, OM9, OM13, OM18 |
Moderate |
Slight |
Insubstantial |
LR2.0 |
Compensatory wetland |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6, CM10 &OM1-OM5, OM8-OM9, OM13, OM18 |
Moderate |
Slight |
Insubstantial |
LR3.1 |
Ponds near San Tin and Sam Po Shue |
High |
High |
Large |
Large |
Substantial |
Substantial |
DM1, CM1-CM6, CM10
&OM1-OM5, OM8-OM9, OM13, OM18 |
Substantial |
Substantial |
Moderate |
LR3.2 |
Ponds near Siu Hum Tsuen and Shek Wu Wai San Tsuen |
Medium |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1-CM6, CM10
&OM1-OM5, OM9, OM18 |
Substantial |
Moderate |
Slight |
LR3.3 |
Ponds near Ngau Tam Mei |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
insubstantial |
LR4.0 |
Natural Watercourse |
High |
High |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
LR5.0 |
Modified watercourse |
Low |
Low |
Small |
Small |
Slight |
Slight |
CM1-CM6,
CM10 &OM1-OM5, OM8-OM9, OM13, OM18 |
Slight |
Insubstantial |
Insubstantial |
LR6.0 |
Semi-Natural Watercourse |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6, CM10 &OM1-OM5, OM9, OM8, OM18 |
Moderate |
Slight |
Insubstantial |
LR7.0 |
Seasonal Wet Grassland |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 & OM1-OM5, OM8, OM9 |
Moderate |
Slight |
Insubstantial |
LR8.0 |
Wet Agricultural Land |
Medium |
Medium |
Large |
Large |
substantial |
substantial |
CM1-CM6
& OM1-OM5, OM9 |
substantial |
Moderate |
Slight |
LR9.0 |
Dry Agricultural Land |
Medium |
Medium |
Large |
Large |
substantial |
substantial |
CM1-CM6 &
OM1-OM5, OM9 |
substantial |
Moderate |
Slight |
LR10.0 |
Woodland |
High |
High |
Small |
Small |
Moderate |
Moderate |
CM1-CM6 & OM1-OM5, OM9, OM12 |
Moderate |
Slight |
Insubstantial |
LR11.0 |
Mixed Woodland |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9, OM10 |
Moderate |
Slight |
Insubstantial |
LR12.1 |
Plantation on slope |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM6 &
OM1-OM5, OM9, OM10 |
Slight |
Insubstantial |
Insubstantial |
LR12.2 |
Plantation along roadside |
Low |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9 |
Moderate |
Slight |
Insubstantial |
LR13.0 |
Shrubland |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM6 & OM1-OM5, OM9 |
Slight |
Insubstantial |
Insubstantial |
LR14.0 |
Grassland |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1, CM3-CM6 & OM1-OM3, OM5, OM9-OM10 |
Slight |
Insubstantial |
Insubstantial |
LR15.0 |
Village/ Orchard |
Low |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9 |
Moderate |
Slight |
Insubstantial |
LR16.0 |
Vegetation in developed area (Including residential
area and man-made structure) |
Low |
Low |
Large |
Large |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9-OM11 |
Moderate |
Slight |
Insubstantial |
LR 17.0 |
Vegetation in Waste land/open storage/ temporary
area |
Low |
Low |
Large |
Large |
Moderate |
Moderate |
CM1-CM6 & OM1-OM5, OM9-OM11, OM13 |
Moderate |
Slight |
Insubstantial |
Landscape Character Area (LCA) |
|||||||||||
LCA1 |
Settled Valley Landscape |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9 |
Moderate |
Slight |
Insubstantial |
LCA2 |
Upland And Hillside Landscape |
High |
High |
Small |
Small |
Moderate |
Moderate |
CM1-CM6 &
OM1-OM5, OM9 |
Moderate |
Slight |
Insubstantial |
LCA3 |
Rural Coastal Plain Landscape |
High |
High |
Large |
Large |
Substantial |
Substantial |
CM1-CM6 &
OM1-OM5, OM8, OM9, OM13 |
Substantial |
Moderate |
Slight |
LCA4 |
Rural Inland Plain Landscape |
Medium |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1-CM6, CM10
&OM1-OM5, OM9, OM18 |
Substantial |
Moderate |
Slight |
LCA5 |
Urban Peripheral Village Landscape |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM6, CM10
&OM1-OM5, OM9, OM18 |
Slight |
Insubstantial |
Insubstantial |
LCA6 |
Miscellaneous Rural Fringe Landscape |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM6 &
OM1-OM5, OM9 |
Slight |
Insubstantial |
Insubstantial |
LCA7 |
Comprehensive Residential Development |
Low |
Low |
Small |
Small |
Slight |
Slight |
CM1-CM6, CM10
&OM1-OM5, OM9, OM18 |
Slight |
Insubstantial |
Insubstantial |
LCA8 |
Institutional Landscape |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
LCA9 |
Transportation Corridor Landscape |
low |
low |
Small |
Small |
Slight |
Slight |
CM1-CM6 &
OM1-OM5, OM9 |
Slight |
Insubstantial |
Insubstantial |
LCA10 |
Miscellaneous Urban Fringe Landscape |
low |
low |
Intermediate |
Intermediate |
Slight |
Slight |
CM1-CM6, CM10
&OM1-OM5, OM9, OM13, OM18 |
Slight |
Insubstantial |
Insubstantial |
Table 14.14 Significance
of Visual Impacts during Construction and Operation Phases
No. |
Key VSRs |
Representing VP |
Receptor Sensitivity (Low,
Medium, High) |
Magnitude
of Change (Negligible,
Small, Intermediate, Large) |
Impact
Significance Threshold BEFORE Mitigation (Insubstantial,
Slight, Moderate, Substantial) |
Recommended Mitigation Measures |
Residual
Impact Significance Threshold AFTER
Mitigation (Insubstantial, Slight, Moderate,
Substantial) |
|||||
Construction |
Operation |
|||||||||||
Construction |
Operation |
Construction |
Operation |
Construction |
Operation |
Day 1 |
Year 10 |
|||||
R1 |
Low-rise
residents of Maple Garden, Palm Springs and Royal Palm |
VP6, VP18 |
High |
High |
Small |
Small |
Moderate |
Moderate |
CM1-CM10;
OM1-OM17 |
Moderate |
Moderate |
Slight |
R2 |
Residents of
Mai Po San Tsuen, Mai Po Lo Wai |
VP6, VP7. VP13 |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10;
OM1-OM17 |
Moderate |
Moderate |
Moderate |
R3 |
Residents of
San Tsing Lung Tsuen, Yan Sau Wai, On Lung Tsuen, Wing Ping Tsuen, Fan Tin
(San Yi Cho and Ming Tak Tong), San Lung Tsuen, Tung Chan Wai |
VP9, VP10. VP14, VP16 |
Medium |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1-CM10;
OM1-OM17 |
Substantial |
Substantial |
Substantial |
R4 |
Residents of
Long Ha Tsuen, Man Yuen Tsuen and Pok Wai Village |
VP6, VP18 |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
R5 |
Residents of
Vineyard and low-rise residential area along Tam Mei Road |
VP6 |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM9; OM1-OM7 |
Slight |
Slight |
Slight |
R6 |
Residents of
Chau Tau Village, Poon Uk Tsuen |
VP1, VP2 |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9;
OM1-OM7 |
Moderate |
Moderate |
Slight |
R7 |
Residents of
Fair View Park |
VP5, VP18 |
Medium |
Medium |
Small |
Small |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
R8 |
Residents of
Proposed Kwu Tung New Town Development and Ma Tso Lung area. |
VP1 |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial |
Insubstantial |
Insubstantial |
R9 |
Future
residents of the proposed Loop development. |
VP11 |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10; OM1-OM18 |
Moderate |
Moderate |
Moderate |
R10 |
Residents of
Shek Wu Wai, recreational users of Shek Wu Wai Playground |
VP15, VP17 |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9;
OM1-OM7 |
Moderate |
Moderate |
Moderate |
R11 |
Residents of
Fisherman San Tsuen |
VP11 |
High |
High |
Large |
Large |
Moderate |
Moderate |
CM1-CM9; OM1-OM7 |
Moderate |
Moderate |
Moderate |
REC 1 |
Hikers along
Ngau Tam Shan Hiking Trail |
VP3, VP12 |
Medium |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1-CM9;
OM1-OM17 |
Substantial |
Substantial |
Substantial |
REC 2 |
Visitors of
Mai Po Marsh Wetland reserve |
VP7, VP18 |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10;
OM1-OM18 |
Moderate |
Moderate |
Slight |
REC 3 |
Hiker of Ki
Lun Shan |
VP3 |
Medium |
Medium |
Large |
Large |
Substantial |
Substantial |
CM1-CM10; OM1-OM18 |
Substantial |
Substantial |
Substantial |
REC 4 |
Park
visitors of San Tin Park and Man Tin Cheung Park |
VP9. VP10, VP16 |
Medium |
Medium |
Large |
Large |
Moderate |
Moderate |
CM1-CM9; OM1-OM17 |
Moderate |
Moderate |
Slight |
REC 5 |
Hikers of
Lam Tsuen Country Park |
VP4 |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10; OM1-OM18 |
Moderate |
Moderate |
Moderate |
REC 6 |
Future users
of Sam Po Shue wetland conservation park |
VP8 |
High |
High |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10;
OM1-OM18 |
Moderate |
Moderate |
Moderate |
T1 |
Travelers of
San Tin Highway |
VP6, P13, VP14, VP 15, VP16 |
Low |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9;
OM1-OM17 |
Moderate |
Moderate |
Moderate |
T2 |
Users of MTR
Lok Ma Chau Station |
VP8 |
Low |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9; OM1-OM17 |
Moderate |
Moderate |
Moderate |
T3 |
Traveller of
Fan Ling Highway |
VP2, VP14, VP15 |
Low |
Low |
Intermediate |
Intermediate |
Slight |
Slight |
CM1-CM9; OM1-OM17 |
Slight |
Slight |
Insubstantial |
O1 |
Workers of
Open Storage/ Industrial usage of Ngau Tam Mei |
VP5 |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM9;
OM1-OM17 |
Slight |
Slight |
Insubstantial |
O2 |
Workers
around Castle peak road (Mai Po Section) |
VP5 |
Medium |
Medium |
Negligible |
Negligible |
Insubstantial |
Insubstantial |
- |
Insubstantial
|
Insubstantial
|
Insubstantial |
O3 |
Farmer in
Agricultural land near LMC BCP |
VP11 |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9;
OM1-OM7 |
Moderate |
Moderate |
Moderate |
O4 |
Industrial
and potential tertiary users of Kwu Tung and Pak Shek Au |
VP2 |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM9; OM1-OM7 |
Slight |
Slight |
Insubstantial |
O5 |
Workers in
open storage |
VP6, VP7, VP13 |
Low |
Low |
Intermediate |
Intermediate |
Slight |
Slight |
CM1-CM9; OM1-OM17 |
Slight |
Slight |
Insubstantial |
O6 |
Future
workers of the Loop development |
VP11 |
Medium |
Medium |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM10;
OM1-OM18 |
Moderate |
Moderate |
Moderate |
GIC1 |
Lok Ma Chau
Operation Base |
VP8 |
Medium |
Medium |
Small |
Small |
Slight |
Slight |
CM1-CM9; OM1-OM7 |
Slight |
Slight |
Insubstantial |
GIC2 |
Users of
Gurkha Cemetery |
VP4, VP12 |
Medium |
Medium |
Large |
Large |
Moderate |
Moderate |
CM1-CM9; OM1-OM7 |
Moderate |
Moderate |
Moderate |
GIC3 |
Users of San
Tin Barracks |
VP 12 |
Medium |
Medium |
Large |
Large |
Moderate |
Moderate |
CM1-CM9; OM1-OM7 |
Moderate |
Moderate |
Moderate |
GIC4 |
Users of Tam
Mei Barracks |
VP 4 |
Low |
Low |
Intermediate |
Intermediate |
Moderate |
Moderate |
CM1-CM9;
OM1-OM7 |
Moderate |
Moderate |
Slight |
Operation
phases