TABLE OF CONTENTS

1............ INTRODUCTION........................................................................................................................ 1-1

1.1.......... Project Background................................................................................................................... 1-1

1.2.......... Designated Projects under EIAO................................................................................................ 1-1

1.3.......... Purpose of the EIA Study.......................................................................................................... 1-2

1.4.......... Objectives of this EIA Study...................................................................................................... 1-2

1.5.......... Structure of the EIA Report........................................................................................................ 1-4

 

2............ PROJECT DESCRIPTION.......................................................................................................... 2-1

2.1.......... Introduction............................................................................................................................... 2-1

2.2.......... Project Objectives..................................................................................................................... 2-1

2.3.......... The Need for the Project............................................................................................................ 2-1

2.3.1....... Need for the Development......................................................................................................... 2-1

2.3.2....... Scenario without the Project....................................................................................................... 2-1

2.3.3....... Scenario with the Project............................................................................................................ 2-1

2.4.......... Project Location and Site History................................................................................................ 2-2

2.5.......... Scope of the Project.................................................................................................................. 2-2

2.6.......... Continuous Public Involvement................................................................................................... 2-4

2.7.......... Consideration of Alternative Options........................................................................................... 2-6

2.7.1....... General..................................................................................................................................... 2-6

2.7.2....... Criteria for Options Development................................................................................................ 2-6

2.7.3....... Review of Alternative Options..................................................................................................... 2-7

2.7.4....... Consideration of Alternative Site Locations................................................................................. 2-7

2.7.5....... Consideration of Supporting Facilities Locations......................................................................... 2-9

2.7.6....... Consideration of Ventilation Shafts Location............................................................................. 2-10

2.7.7....... Consideration of Alternative Emergency Outfall Options............................................................ 2-10

2.7.8....... Consideration of Alternative Treatment Level............................................................................. 2-12

2.7.9....... Consideration of Alternative Treatment Processes..................................................................... 2-13

2.7.10..... Consideration of Alternative Sludge Treatment Process............................................................. 2-14

2.7.11..... Consideration for Alternative / Phased Installation in relation to Flow Projections......................... 2-15

2.7.12..... Consideration to Minimise Emergency Discharges..................................................................... 2-15

2.8.......... Construction Methodologies..................................................................................................... 2-16

2.8.1....... Introduction............................................................................................................................. 2-16

2.8.2....... Construction Methods for Tunnels and Caverns......................................................................... 2-16

2.8.3....... Consideration of Alternative Temporary Explosive Magazine Arrangements................................. 2-17

2.8.4....... Construction Methods for THEES Connection Work................................................................... 2-18

2.8.5....... Construction of Administration, Ventilation and Ancillary Buildings............................................. 2-18

2.8.6....... Construction of Slopes and Retaining Walls.............................................................................. 2-19

2.8.7....... Decommissioning of the Existing STSTW................................................................................. 2-19

2.8.8....... Consideration of Demolition Methods....................................................................................... 2-20

2.9.......... Construction Programme.......................................................................................................... 2-21

2.10........ Concurrent Projects.................................................................................................................. 2-21

2.11........ Summary................................................................................................................................. 2-23

 

3............ AIR QUALITY IMPACT.............................................................................................................. 3-1

3.1.......... Introduction............................................................................................................................... 3-1

3.2.......... Environmental Legislations, Standards and Guidelines................................................................. 3-1

3.2.2....... Air Quality Objectives & Technical Memorandum on EIA Process................................................. 3-1

3.2.3....... Air Pollution Control (Construction Dust) Regulation.................................................................... 3-1

3.3.......... Description of Environment........................................................................................................ 3-2

3.4.......... Identification of Air Sensitive Receivers...................................................................................... 3-2

3.5.......... Identification of Pollutant Sources.............................................................................................. 3-6

3.5.1....... Construction Phase.................................................................................................................... 3-6

3.5.2....... Operation Phase........................................................................................................................ 3-7

3.6.......... Assessment Methodology.......................................................................................................... 3-8

3.6.1....... Construction Phase.................................................................................................................... 3-8

3.6.2....... Operation Phase ¡V Odour Impact Assessment........................................................................... 3-14

3.7.......... Prediction and Evaluation of Environmental Impacts.................................................................. 3-22

3.7.1....... Construction Phase.................................................................................................................. 3-22

3.7.2....... Operation Phase...................................................................................................................... 3-28

3.8.......... Mitigation of Adverse Environmental Impacts............................................................................ 3-33

3.8.1....... Construction Phase.................................................................................................................. 3-33

3.8.2....... Operational Odour Impact......................................................................................................... 3-44

3.9.......... Evaluation of Residual Impacts................................................................................................. 3-44

3.9.1....... Construction Phase.................................................................................................................. 3-44

3.9.2....... Operation Phase...................................................................................................................... 3-44

3.10........ Environmental Monitoring and Audit.......................................................................................... 3-44

3.10.1..... Construction Phase.................................................................................................................. 3-44

3.10.2..... Operation Phase...................................................................................................................... 3-44

3.11........ Conclusion.............................................................................................................................. 3-45

3.11.1..... Construction Phase.................................................................................................................. 3-45

3.11.2..... Operation Phase...................................................................................................................... 3-45

 

4............ NOISE IMPACT......................................................................................................................... 4-1

4.1.......... Introduction............................................................................................................................... 4-1

4.2.......... Environmental Legislation, Standards and Criteria........................................................................ 4-1

4.2.1....... General..................................................................................................................................... 4-1

4.2.2....... Construction Noise ¡V General Construction.................................................................................. 4-2

4.2.3....... Construction Noise ¡V Ground-borne Noise................................................................................... 4-3

4.2.4....... Construction Noise ¡V Blasting..................................................................................................... 4-3

4.2.5....... Road Traffic Noise..................................................................................................................... 4-3

4.2.6....... Operational Phase Fixed Plant Noise.......................................................................................... 4-4

4.3.......... Description of Environment........................................................................................................ 4-5

4.4.......... Noise Sensitive Receivers.......................................................................................................... 4-5

4.5.......... Identification of Pollutant Sources.............................................................................................. 4-8

4.5.1....... Construction Phase of Relocated STSTW................................................................................... 4-8

4.5.2....... Operation Phase of Relocated STSTW........................................................................................ 4-9

4.5.3....... Decommissioning and Demolition of the Existing STSTW and the Temporary Explosives Magazine 4-9

4.5.4....... Concurrent Projects.................................................................................................................. 4-10

4.6.......... Assessment Methodology........................................................................................................ 4-10

4.6.1....... Construction Phase and Decommissioning of the Existing STSTW............................................. 4-10

4.6.2....... Operation Phase...................................................................................................................... 4-14

4.7.......... Prediction and Evaluation of Environmental Impacts.................................................................. 4-14

4.7.1....... Construction Noise - Airborne Noise.......................................................................................... 4-14

4.7.2....... Construction Noise - Ground-borne Noise.................................................................................. 4-15

4.7.3....... Traffic Noise due to Relocation of the Existing Noise Barrier during Construction Phase.............. 4-16

4.7.4....... Operational Fixed Plant Noise................................................................................................... 4-16

4.8.......... Mitigation of Adverse Environmental Impacts............................................................................ 4-17

4.8.1....... Construction Noise - Airborne Noise.......................................................................................... 4-17

4.8.2....... Construction Noise ¡V Ground-borne Noise................................................................................. 4-19

4.8.3....... Operational Fixed Plant Noise................................................................................................... 4-19

4.9.......... Evaluation of Residual Impacts................................................................................................. 4-19

4.9.1....... Construction Noise................................................................................................................... 4-19

4.9.2....... Operational Fixed Plant Noise................................................................................................... 4-21

4.10........ Environmental Monitoring and Audit.......................................................................................... 4-21

4.11........ Conclusion.............................................................................................................................. 4-22

4.11.1..... Construction Noise................................................................................................................... 4-22

4.11.2..... Operational Fixed Plant Noise................................................................................................... 4-22

 

5............ WATER QUALITY IMPACT........................................................................................................ 5-1

5.1.......... Introduction............................................................................................................................... 5-1

5.2.......... Environmental Legislation, Standards and Criteria........................................................................ 5-1

5.2.1....... Environmental Impact Assessment Ordinance............................................................................. 5-1

5.2.2....... Water Quality Objectives............................................................................................................ 5-1

5.2.3....... Hong Kong Planning Standards and Guidelines........................................................................... 5-5

5.2.4....... Water Supplies Department Water Quality Criteria........................................................................ 5-5

5.2.5....... Cooling Water Intake Suspended Solids Criterion........................................................................ 5-5

5.2.6....... Technical Memorandum on Effluent Discharge Standard.............................................................. 5-6

5.2.7....... Practice Notes........................................................................................................................... 5-6

5.2.8....... Sediment Deposition Criterion (Applicable to Ecological Subtidal Habitats Only).......................... 5-6

5.3.......... Description of Environment........................................................................................................ 5-7

5.3.1....... Study Area................................................................................................................................ 5-7

5.3.2....... Marine Water............................................................................................................................. 5-7

5.3.3....... Inland Water............................................................................................................................. 5-11

5.4.......... Water Sensitive Receivers........................................................................................................ 5-15

5.4.1....... Introduction............................................................................................................................. 5-15

5.4.2....... Victoria Harbour Water Control Zone......................................................................................... 5-15

5.4.3....... Tolo Harbour and Channel Water Control Zone........................................................................... 5-16

5.5.......... Identification of Potential Impacts............................................................................................. 5-17

5.5.1....... Construction Impacts............................................................................................................... 5-17

5.5.2....... Operational Impacts................................................................................................................. 5-20

5.5.3....... Wastewater from Sludge Treatment........................................................................................... 5-22

5.5.4....... Non-point Source Storm Pollution............................................................................................. 5-23

5.6.......... Assessment Methodology........................................................................................................ 5-23

5.6.1....... Land-based Construction Works............................................................................................... 5-23

5.6.2....... Operational Effluent Discharges............................................................................................... 5-23

5.7.......... Land-based Construction.......................................................................................................... 5-45

5.7.1....... Prediction and Evaluation of Potential Impacts.......................................................................... 5-45

5.7.2....... Mitigation of Adverse Impacts.................................................................................................. 5-47

5.7.3....... Environmental Monitoring and Audit.......................................................................................... 5-51

5.7.4....... Residual Impacts..................................................................................................................... 5-52

5.8.......... Operational Effluent Discharges to Victoria Harbour ¡V Normal THEES Operation......................... 5-52

5.8.1....... Prediction and Evaluation of Potential Impacts.......................................................................... 5-52

5.8.2....... Mitigation of Adverse Impacts.................................................................................................. 5-60

5.8.3....... Environmental Monitoring and Audit.......................................................................................... 5-61

5.8.4....... Residual Impacts..................................................................................................................... 5-61

5.9.......... Operational Effluent Discharges to Tolo Harbour ¡V Normal Plant / THEES Operation................... 5-61

5.9.1....... Prediction and Evaluation of Potential Impacts.......................................................................... 5-61

5.9.2....... Mitigation of Adverse Impacts.................................................................................................. 5-64

5.9.3....... Environmental Monitoring and Audit.......................................................................................... 5-64

5.9.4....... Residual Impacts..................................................................................................................... 5-64

5.10........ THEES Maintenance Discharge from TPSTW and CSTW to Tolo Harbour.................................... 5-65

5.10.1..... Prediction and Evaluation of Potential Impacts.......................................................................... 5-65

5.10.2..... Mitigation of Adverse Impacts.................................................................................................. 5-71

5.10.3..... Environmental Monitoring and Audit.......................................................................................... 5-71

5.10.4..... Residual Impacts..................................................................................................................... 5-72

5.11........ Emergency Discharge from STSTW to Tolo Harbour.................................................................. 5-72

5.11.1..... Evaluation and Prediction of Potential Impacts.......................................................................... 5-72

5.11.2..... Mitigation of Adverse Impacts.................................................................................................. 5-74

5.11.3..... Environmental Monitoring and Audit.......................................................................................... 5-75

5.11.4..... Residual Impacts..................................................................................................................... 5-75

5.12........ Operational Impact - Wastewater from Sludge Treatment............................................................ 5-75

5.12.1..... Evaluation and Prediction of Potential Impacts.......................................................................... 5-75

5.12.2..... Mitigation of Adverse Impacts.................................................................................................. 5-76

5.12.3..... Environmental Monitoring and Audit.......................................................................................... 5-76

5.12.4..... Residual Impacts..................................................................................................................... 5-76

5.13........ Operational Impact - Non-point Source Storm Pollution.............................................................. 5-76

5.13.1..... Evaluation and Prediction of Potential Impacts.......................................................................... 5-76

5.13.2..... Mitigation of Adverse Impacts.................................................................................................. 5-76

5.13.3..... Environmental Monitoring and Audit.......................................................................................... 5-77

5.13.4..... Residual Impacts..................................................................................................................... 5-77

5.14........ Conclusion.............................................................................................................................. 5-77

5.14.1..... Construction Phase.................................................................................................................. 5-77

5.14.2..... Operational Phase.................................................................................................................... 5-78

 

6............ LAND CONTAMINATION............................................................................................................ 6-1

6.1.......... Introduction............................................................................................................................... 6-1

6.2.......... Environmental Legislation, Standards and Criteria........................................................................ 6-1

6.3.......... Assessment Methodology.......................................................................................................... 6-1

6.4.......... Description of the Project Area................................................................................................... 6-2

6.5.......... Identification of Potential Land Contamination Concern................................................................ 6-3

6.5.2....... Existing STSTW......................................................................................................................... 6-3

6.5.3....... Existing Vehicle Detention Centre (VDC) and its Surrounding Areas.............................................. 6-3

6.5.4....... Nui Po Shan North..................................................................................................................... 6-4

6.6.......... Prediction and Evaluation of Environmental Impacts.................................................................. 6-10

6.6.2....... Future Land Uses..................................................................................................................... 6-11

6.6.3....... Possible Remediation Measures............................................................................................... 6-11

6.7.......... Mitigation of Adverse Environmental Impacts............................................................................ 6-12

6.7.1....... Recommended Further Works................................................................................................... 6-12

6.7.2....... Mitigation Measures for Remediation Works.............................................................................. 6-12

6.8.......... Evaluation of Residual Impacts................................................................................................. 6-13

6.9.......... Conclusion.............................................................................................................................. 6-13

 

7............ HAZARD TO LIFE...................................................................................................................... 7-1

7.1.......... Introduction............................................................................................................................... 7-1

7.1.1....... Background............................................................................................................................... 7-1

7.2.......... Legislative Requirements and Evaluation Criteria......................................................................... 7-2

7.2.2....... EIAO Technical Memorandum (EIAO-TM)..................................................................................... 7-2

7.2.3....... Hong Kong Government Risk Guidelines (HKRG), EIAO-TM Annex 4............................................ 7-2

7.3.......... Study Objectives and Methodology............................................................................................ 7-3

7.4.......... Facility Details........................................................................................................................... 7-5

7.4.1....... Project Overview........................................................................................................................ 7-5

7.4.2....... Statutory / Licensing Requirements............................................................................................. 7-6

7.4.3....... Temporary Storage Magazine Details.......................................................................................... 7-7

7.4.4....... Transport Route Details.............................................................................................................. 7-7

7.4.5....... Use of Explosives Details.......................................................................................................... 7-9

7.4.6....... Base Case and Worst Case for Quantitative Risk Assessment..................................................... 7-9

7.5.......... Population Data....................................................................................................................... 7-12

7.6.......... Hazard Identification................................................................................................................. 7-12

7.6.1....... General.................................................................................................................................... 7-12

7.6.2....... Hazards of Explosives............................................................................................................. 7-12

7.6.3....... Review of Incidents.................................................................................................................. 7-13

7.6.4....... Scenarios for Hazard Assessment............................................................................................ 7-13

7.7.......... Frequency Analysis.................................................................................................................. 7-13

7.7.1....... Introduction............................................................................................................................. 7-13

7.7.2....... Frequency Analysis for Storage of Explosives.......................................................................... 7-14

7.7.3....... Frequency Analysis for Transport of Explosives........................................................................ 7-14

7.7.4....... Frequency Analysis for Use of Explosives................................................................................ 7-14

7.8.......... Consequence analysis for Storage and Transport of Explosives................................................ 7-15

7.9.......... Consequence analysis for Use of Explosives............................................................................ 7-15

7.10........ Risk Summation....................................................................................................................... 7-16

7.10.1..... Overview................................................................................................................................. 7-16

7.10.2..... Individual Risk Results............................................................................................................. 7-16

7.10.3..... Societal Risk Results............................................................................................................... 7-19

7.10.4..... ALARP Assessment................................................................................................................. 7-22

7.11........ Hazard Assessment for High Pressure Underground Town Gas Transmission Pipeline................. 7-24

7.11.1..... Introduction............................................................................................................................. 7-24

7.11.2..... The Gas Facilities..................................................................................................................... 7-26

7.11.3..... Surrounding Population............................................................................................................ 7-26

7.11.4..... Time Modes............................................................................................................................. 7-27

7.11.5..... Meteorological Conditions........................................................................................................ 7-27

7.11.6..... Hazard Identification................................................................................................................. 7-27

7.11.7..... Frequency Analysis.................................................................................................................. 7-27

7.11.8..... Consequence Analysis............................................................................................................. 7-28

7.11.9..... Risk Evaluation........................................................................................................................ 7-28

7.11.10... Conclusions and Recommendations......................................................................................... 7-33

7.12........ Cumulative Risk Assessment.................................................................................................... 7-34

7.13........ Conclusions............................................................................................................................. 7-36

7.14........ Recommendations................................................................................................................... 7-36

7.14.1..... Recommendations for Meeting the ALARP Requirements........................................................... 7-36

7.14.2..... Recommendations for Explosives Storage in Magazine............................................................. 7-36

7.14.3..... Recommendations for Explosives Transport............................................................................. 7-37

7.14.4..... Recommendations for Explosives Use...................................................................................... 7-37

7.15........ Reference................................................................................................................................ 7-38

 

8............ ECOLOGICAL IMPACT (TERRESTRIAL AND MARINE).............................................................. 8-1

8.1.......... Introduction............................................................................................................................... 8-1

8.2.......... Environmental Legislation, Standards and Criteria........................................................................ 8-1

8.3.......... Assessment Methodology.......................................................................................................... 8-3

8.3.1....... Assessment Area....................................................................................................................... 8-3

8.3.2....... Literature Review........................................................................................................................ 8-4

8.3.3....... Ecological Survey Methodology................................................................................................. 8-5

8.3.4....... Assessment Approach............................................................................................................... 8-9

8.4.......... Description of the Environment................................................................................................. 8-10

8.4.1....... Sites of Conservation Importance............................................................................................. 8-10

8.4.2....... Literature Review...................................................................................................................... 8-11

8.5.......... Survey Findings....................................................................................................................... 8-17

8.5.1....... Habitat and Vegetation............................................................................................................. 8-17

8.5.2....... Terrestrial Fauna....................................................................................................................... 8-19

8.5.3....... Marine Ecological Resources.................................................................................................... 8-24

8.6.......... Ecological Value...................................................................................................................... 8-26

8.7.......... Impact Identification and Evaluation.......................................................................................... 8-36

8.7.1....... Construction Phase.................................................................................................................. 8-36

8.7.2....... Operational Phase.................................................................................................................... 8-43

8.7.3....... Evaluation of Ecological Impact............................................................................................... 8-46

8.8.......... Mitigation of Adverse Ecological Impacts................................................................................. 8-53

8.8.2....... Avoidance............................................................................................................................... 8-53

8.8.3....... Minimization............................................................................................................................. 8-54

8.8.4....... Compensation......................................................................................................................... 8-57

8.9.......... Evaluation of Residual Ecological Impacts................................................................................ 8-58

8.10........ Environmental Monitoring and Audit.......................................................................................... 8-59

8.11........ Environmental Benefits............................................................................................................. 8-60

8.12........ Conclusion.............................................................................................................................. 8-61

8.13........ References.............................................................................................................................. 8-62

 

9............ FISHERIES IMPACT.................................................................................................................. 9-1

9.1.......... Introduction............................................................................................................................... 9-1

9.2.......... Environmental Legislation, Standards and Criteria........................................................................ 9-1

9.3.......... Assessment Methodology.......................................................................................................... 9-1

9.3.1....... Assessment Area....................................................................................................................... 9-1

9.3.2....... Assessment Approach and Methodology.................................................................................... 9-1

9.4.......... Description of Baseline Condition............................................................................................... 9-2

9.4.2....... Sites of Fisheries Importance..................................................................................................... 9-2

9.4.3....... Capture Fisheries....................................................................................................................... 9-3

9.4.4....... Culture Fisheries........................................................................................................................ 9-5

9.5.......... Identification, Prediction and Evaluation of Environmental Impacts............................................... 9-6

9.5.1....... Construction Phase.................................................................................................................... 9-6

9.5.2....... Operation Phase........................................................................................................................ 9-8

9.6.......... Mitigation of Adverse Environmental Impacts............................................................................ 9-13

9.7.......... Evaluation of Residual Impacts................................................................................................. 9-14

9.8.......... Environmental Monitoring and Audit (EM&A)............................................................................. 9-14

9.9.......... Environmental Benefits............................................................................................................. 9-15

9.10........ Conclusion.............................................................................................................................. 9-15

9.11........ References.............................................................................................................................. 9-16

 

10........... LANDSCAPE AND VISUAL IMPACT......................................................................................... 10-1

10.1........ Introduction............................................................................................................................. 10-1

10.2........ Environmental Legislation, Standards and Criteria...................................................................... 10-1

10.3........ Assessment Methodology........................................................................................................ 10-2

10.3.1..... Landscape Impact Assessment Methodology............................................................................ 10-2

10.3.2..... Visual Impact Assessment Methodology................................................................................... 10-4

10.4........ Review of Planning and Development Control Framework.......................................................... 10-6

10.5........ Baseline Study......................................................................................................................... 10-7

10.5.1..... Landscape Resources.............................................................................................................. 10-7

10.5.2..... Landscape Character Areas (LCAs)......................................................................................... 10-10

10.5.3..... Broad Brush Tree Survey........................................................................................................ 10-13

10.5.4..... Visual Envelope..................................................................................................................... 10-13

10.5.5..... Visually Sensitive Receivers (VSRs)........................................................................................ 10-13

10.6........ Landscape Impact Assessment............................................................................................... 10-18

10.6.1..... Sources of Landscape Impacts............................................................................................... 10-18

10.6.2..... Magnitude of Landscape Impacts........................................................................................... 10-18

10.6.3..... Significance of Unmitigated Landscape Impacts...................................................................... 10-23

10.7........ Visual Impact Assessment...................................................................................................... 10-23

10.7.1..... Sources of Visual Impacts...................................................................................................... 10-23

10.7.2..... Magnitude of Visual Impacts................................................................................................... 10-24

10.7.3..... Significance of Unmitigated Visual Impacts............................................................................. 10-28

10.7.4..... Recommended Photomontage Viewpoints.............................................................................. 10-28

10.8........ Landscape and Visual Mitigation Measures.............................................................................. 10-28

10.9........ Residual Impact..................................................................................................................... 10-31

10.9.1..... Significance of Residual Landscape Impacts........................................................................... 10-31

10.9.2..... Significance of Residual Visual Impacts.................................................................................. 10-38

10.10...... Environmental Monitoring and Audit........................................................................................ 10-46

10.11...... Conclusion............................................................................................................................. 10-46

 

11........... CULTURAL HERITAGE IMPACT.............................................................................................. 11-1

11.1........ Introduction............................................................................................................................. 11-1

11.2........ Environmental Legislation, Standards and Criteria...................................................................... 11-1

11.2.1..... General.................................................................................................................................... 11-1

11.2.2..... Environmental Impact Assessment Ordinance EIAO (Cap.499) and Technical Memorandum on Environmental Impact Assessment Process (EIAO-TM).............................................................. 11-1

11.2.3..... Guidance Note on Assessment of Impact on Sites of Cultural Heritage in Environmental Impact Assessment Studies................................................................................................................ 11-1

11.2.4..... Antiquities and Monuments Ordinance (A&MO) (Cap.53)............................................................ 11-1

11.2.5..... Hong Kong Planning Standards and Guidelines (HKPSG).......................................................... 11-2

11.2.6..... Guidelines for Cultural Heritage Impact Assessment (GCHIA)...................................................... 11-2

11.3........ Assessment Methodology........................................................................................................ 11-2

11.3.1..... General.................................................................................................................................... 11-2

11.3.2..... Archaeology............................................................................................................................ 11-2

11.3.3..... Built Heritage........................................................................................................................... 11-3

11.4........ Background of Study Area....................................................................................................... 11-4

11.4.1..... Physical Geographical Background........................................................................................... 11-4

11.4.2..... Historical Background.............................................................................................................. 11-5

11.4.3..... Terrestrial Archaeological Resources......................................................................................... 11-5

11.4.4..... Marine Archaeological Resources............................................................................................. 11-5

11.4.5..... Built Heritage Resources.......................................................................................................... 11-5

11.5........ Impact Assessments and Mitigation of Adverse Impacts............................................................ 11-6

11.5.2..... Construction Phase.................................................................................................................. 11-6

11.5.3..... Operation Phase...................................................................................................................... 11-6

11.6........ Environmental Monitoring and Audit.......................................................................................... 11-6

11.6.1..... Construction Phase.................................................................................................................. 11-6

11.6.2..... Operation Phase...................................................................................................................... 11-6

11.7........ Conclusion.............................................................................................................................. 11-6

 

12........... WASTE MANAGEMENT IMPLICATIONS.................................................................................. 12-1

12.1........ Introduction............................................................................................................................. 12-1

12.2........ Environmental Legislation, Standards and Criteria...................................................................... 12-1

12.2.2..... Waste Disposal Ordinance (Cap. 354)....................................................................................... 12-1

12.2.3..... Waste Disposal (Chemical Waste) (General) Regulation (Cap. 354C)........................................... 12-1

12.2.4..... Waste Disposal (Charges for Disposal of Construction Waste) Regulation (Cap. 354N)............... 12-1

12.2.5..... Land (Miscellaneous Provisions) Ordinance (Cap. 28)................................................................ 12-2

12.2.6..... Public Health and Municipal Services Ordinance (Cap. 132)........................................................ 12-2

12.2.7..... Construction and Demolition (C&D) Material Management.......................................................... 12-2

12.2.8..... Other Relevant Guidelines......................................................................................................... 12-2

12.3........ Assessment Methodology........................................................................................................ 12-3

12.4........ Identification of Potential Waste Sources.................................................................................. 12-3

12.5........ Prediction & Evaluation of Environmental Impacts..................................................................... 12-4

12.5.1..... Construction Phase and Demolition of the Existing STSTW and Temporary Explosives Magazine 12-4

12.5.2..... Operation Phase...................................................................................................................... 12-9

12.6........ Mitigation of Adverse Environmental Impacts.......................................................................... 12-10

12.6.1..... Waste Management Hierarchy................................................................................................. 12-10

12.6.2..... Good Site Practices............................................................................................................... 12-11

12.6.3..... Waste Reduction Measures..................................................................................................... 12-11

12.6.4..... Storage, Collection and Transportation of Waste..................................................................... 12-12

12.6.5..... Construction and Demolition Material...................................................................................... 12-14

12.6.6..... Sludge................................................................................................................................... 12-14

12.6.7..... Chemical Waste..................................................................................................................... 12-15

12.6.8..... General Refuse...................................................................................................................... 12-15

12.7........ Evaluation of Residual Impacts............................................................................................... 12-18

12.8........ Environmental Monitoring and Audit........................................................................................ 12-18

12.9........ Conclusion............................................................................................................................. 12-18

 

13........... HEALTH IMPACT.................................................................................................................... 13-1

13.1........ Introduction............................................................................................................................. 13-1

13.2........ Literature Review for Environmental Legislation, Standards and Guidelines................................. 13-1

13.2.1..... United Kingdom (UK) and European Union (EU) Guidance.......................................................... 13-1

13.2.2..... USEPA Guidance..................................................................................................................... 13-3

13.2.3..... Approach Determination........................................................................................................... 13-3

13.3........ Development of Conceptual Model........................................................................................... 13-4

13.4........ Hazard Identification................................................................................................................. 13-4

13.4.1..... General.................................................................................................................................... 13-4

13.4.2..... Sewage Treatment Process and Potential TAPs......................................................................... 13-4

13.4.3..... Literature Review for Chemicals of Potential Concern (COPC)..................................................... 13-5

13.4.4..... Literature Review for Toxicity Values......................................................................................... 13-7

13.4.5..... TAP Sampling and Laboratory Analysis................................................................................... 13-12

13.4.6..... Screening of TAPs for Non-carcinogenic Effect....................................................................... 13-13

13.4.7..... Screening of TAPs for Carcinogenic Effect............................................................................. 13-16

13.5........ Exposure Assessment............................................................................................................ 13-17

13.5.1..... Identification of HRs............................................................................................................... 13-17

13.5.2..... Emission Inventory................................................................................................................. 13-19

13.5.3..... Dispersion Model................................................................................................................... 13-22

13.5.4..... Receptor Concentration Levels................................................................................................ 13-23

13.6........ Exposure Response Relationship............................................................................................ 13-23

13.6.1..... General.................................................................................................................................. 13-23

13.6.2..... Exposure Scenarios............................................................................................................... 13-24

13.7........ Risk Characterization.............................................................................................................. 13-24

13.7.2..... Background Concentration of Criteria Pollutants...................................................................... 13-24

13.7.3..... Risk Due to Chronic Exposure to Criteria Pollutants................................................................. 13-25

13.7.4..... Risk Due to Acute Exposure to Criteria Pollutants.................................................................... 13-26

13.7.5..... Background Contribution of other TAPs.................................................................................. 13-26

13.7.6..... Risk Due to Chronic Exposure to other TAPs........................................................................... 13-27

13.7.7..... Risk Due to Acute Exposure to other TAPs............................................................................. 13-28

13.7.8..... Calculation of Carcinogenic Health Risk................................................................................... 13-28

13.8........ Reuse of Effluent Water......................................................................................................... 13-30

13.9........ Radon................................................................................................................................... 13-31

13.10...... Uncertainty Analysis............................................................................................................... 13-32

13.10.2... Hazard Identification............................................................................................................... 13-32

13.10.3... Exposure Assessment............................................................................................................ 13-32

13.11...... Risk Control and Management................................................................................................ 13-33

13.12...... Conclusion............................................................................................................................. 13-34

13.13...... References............................................................................................................................ 13-35

13.13.1... Literature for STW-related TAPs.............................................................................................. 13-35

13.13.2... Reference for Emission Inventory............................................................................................ 13-36

13.13.3... Reference for Methodology.................................................................................................... 13-37

13.13.4... Health Risk Assessment Guidance.......................................................................................... 13-38

13.13.5... Radon Assessment................................................................................................................ 13-40

 

14........... ENVIRONMENTAL MONITORING AND AUDIT (EM&A) REQUIREMENTS.................................. 14-1

14.1........ Introduction............................................................................................................................. 14-1

14.2........ Air Quality Impact..................................................................................................................... 14-1

14.2.1..... Construction Phase.................................................................................................................. 14-1

14.2.2..... Operation Phase...................................................................................................................... 14-1

14.3........ Noise Impact........................................................................................................................... 14-1

14.3.1..... Construction Phase.................................................................................................................. 14-1

14.3.2..... Operation Phase...................................................................................................................... 14-2

14.4........ Water Quality Impact................................................................................................................ 14-2

14.4.1..... Land-based Construction.......................................................................................................... 14-2

14.4.2..... Effluent Discharge under Normal THEES Operation, After Commissioning of this Project............ 14-2

14.4.3..... THEES Maintenance Discharge from CSTW and TPSTW to Tolo Harbour.................................... 14-2

14.4.4..... Emergency Discharge from CSTW to Tolo Harbour.................................................................... 14-3

14.5........ Land Contamination................................................................................................................. 14-3

14.6........ Hazard to Life.......................................................................................................................... 14-3

14.7........ Ecological Impact (Terrestrial and Marine).................................................................................. 14-4

14.7.1..... Terrestrial Ecology................................................................................................................... 14-4

14.7.2..... Marine Ecology........................................................................................................................ 14-4

14.8........ Fisheries Impact....................................................................................................................... 14-5

14.9........ Landscape and Visual Impact................................................................................................... 14-6

14.9.1..... Mitigation Measures................................................................................................................. 14-6

14.9.2..... Baseline Review....................................................................................................................... 14-7

14.9.3..... Audit Requirements.................................................................................................................. 14-7

14.10...... Cultural Heritage Impact............................................................................................................ 14-7

14.11...... Waste Management Implications............................................................................................... 14-7

14.12...... Health Impact........................................................................................................................... 14-8

 

15........... CONCLUSIONS....................................................................................................................... 15-1

15.1........ Impact Summary...................................................................................................................... 15-1

15.2........ Benefits of the Project............................................................................................................. 15-1

15.3........ Air Quality Impact..................................................................................................................... 15-2

15.4........ Noise Impact........................................................................................................................... 15-2

15.5........ Water Quality Impact................................................................................................................ 15-3

15.6........ Land Contamination................................................................................................................. 15-5

15.7........ Hazard to Life.......................................................................................................................... 15-5

15.8........ Ecological Impact.................................................................................................................... 15-6

15.9........ Fisheries Impact....................................................................................................................... 15-7

15.10...... Landscape and Visual Impact................................................................................................... 15-8

15.11...... Cultural Heritage Impact............................................................................................................ 15-9

15.12...... Waste Management Implications............................................................................................... 15-9

15.13...... Health Impact........................................................................................................................... 15-9

15.14...... Environmental Outcomes........................................................................................................ 15-10

15.15...... Overall Conclusion................................................................................................................. 15-16

 

16........... IMPLEMENTATION SCHEDULE OF RECOMMENDED MITIGATION MEASURES...................... 16-1

16.1........ Implementation Schedule of Recommended Mitigation Measures............................................... 16-1

 

 

 

 

 

 


 

LIST OF TABLES

Table 2.1

Design Treatment Capacity and Effluent Standards

Table 2.2a

Summary of Public Consultation/Engagement Activities

Table 2.2b

Summary of Public Consultation/Engagement Activities

Table 2.3

Evaluation Criteria and Associated Key Issues and Constraints

Table 2.4

Comparison on the Five Alternatives Sites

Table 2.5

Overall Comparison between Compact-type Technologies and CAS

Table 2.6

Existing and Planned Concurrent Projects

Table 3.1

Hong Kong Air Quality Objectives

Table 3.2

Average Concentrations of Pollutant in the Recent Five Years (Year 2010 ¡V 2014) at

Sha Tin EPD Air Quality Monitoring Station

Table 3.3

Representative Air Sensitive Receivers affected by Construction of Relocated STSTW and Demolition of Existing STSTW

Table 3.4

Representative Air Sensitive Receivers in the vicinity of Relocated STSTW for Operational Odour Impact Assessment

Table 3.5

Rock Crushing Operation with Dust Control Measures

Table 3.6

Emission Factor for Dust Emitting Construction Activity

Table 3.7

Particle Size Distribution of Various Processes

Table 3.8

Summary of Measured Odour Emission Rate in Existing STSTW

Table 3.9

Odour Emission Rates for the Relocated STSTW

Table 3.10

Summary of Required Odour Removal Efficiency for Deodorization System

Table 3.11

Design Parameter of the Ventilation Shaft

Table 3.12

Conversion Factors to 5-second Mean Concentration for Point Source

Table 3.13

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Unmitigated Scenario)

Table 3.14

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Unmitigated Scenario)

Table 3.15

Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Interim Stage)

Table 3.16

Predicted Operational Odour Impact on Representative Air Sensitive Receivers (Ultimate Stage)

Table 3.17

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 1, Mitigated Scenario)

Table 3.18

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 1, Mitigated Scenario)

Table 3.19

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2a, Mitigated Scenario)

Table 3.20

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Construction of Relocated STSTW) (Tier 2b, Mitigated Scenario)

Table 3.21

Predicted Cumulative Air Pollutant Concentrations at Representative Air Sensitive Receivers (Demolition of Existing STSTW) (Tier 2, Mitigated Scenario)

Table 4.1

Area Sensitivity Ratings (ASRs)

Table 4.2

Basic Noise Levels (BNLs)

Table 4.3

Ground-borne Noise Criteria (ANL, Leq, 5min dB(A))

Table 4.4

Acceptable Noise Level for Fixed Plant Noise

Table 4.5

Background Noise Measurement Results

Table 4.6

Representative Noise Sensitive Receivers affected by Relocated STSTW to Cavern during Construction and Operation Phases

Table 4.7

Acceptable Noise Levels of the Representative Noise Sensitive Receivers

Table 4.8

Fixed Plant Noise Criteria of Representative Noise Sensitive Receivers

Table 4.9

Representative Noise Sensitive Receivers for Assessment of Ground-borne Noise Impacts Due to Construction Works

Table 4.10

Representative Noise Sensitive Receivers affected by Decommissioning/Demolition of the Existing STSTW

Table 4.11

Summary of Reference Vibration Level of PMEs

Table 4.12

Wave Propagation Properties of Soil

Table 4.13

Loss factor for Coupling into Building Foundation

Table 4.14

Unmitigated Construction Noise Levels due to the Project at Representative NSRs During Normal Daytime Working Hours

Table 4.15

Predicted Construction Ground-borne Noise Impact Associated with the PME Use at

Open Works Areas

Table 4.16

Maximum Sound Power Levels for Fixed Plant Noise Sources

Table 4.17

Predicted Fixed Plant Noise Levels at Representative Noise Sensitive Receivers

Table 4.18

Mitigated Construction Noise Levels due to the Project at Representative NSRs During Normal Daytime Working Hours (Using Quiet PME)

Table 4.19

Mitigated Construction Noise Levels due to the Project at Representative NSRs During Normal Daytime Working Hours (with further Mitigation Measures)

Table 4.20

Evaluation of Residual Noise Impacts during Construction Phase

Table 5.1

Summary of Key Water Quality Objectives for Tolo Harbour and Channel WCZ

Table 5.2

Summary of Key Water Quality Objectives for Victoria Harbour (Phases One, Two and Three) WCZ

Table 5.3

WSD¡¦s Target Seawater Quality Objectives at Flushing Water Intakes

Table 5.4

Baseline Water Quality Condition for Victoria Harbour WCZ in 2014

Table 5.5

Baseline Water Quality Condition for Tolo Harbour and Channel WCZ in 2014

Table 5.6

Baseline Water Quality Condition for Shing Mun River and its Tributary in 2014

Table 5.7

Baseline Water Quality Condition for Major Inland Water Bodies in 2015 (Dry Season)

Table 5.8

Baseline Water Quality Condition for Major Inland Water Bodies in 2015 (Wet Season)

Table 5.9

Design Standards of the Existing STSTW, Proposed CSTW and Existing TPSTW

Table 5.10

Projects Incorporated in Modelling

Table 5.11

Pollution  Loading  from  Stonecutters  Island  Sewage  Treatment  Works  under  HATS Stage 2A

Table 5.12

Dry Weather Diurnal Flow Pattern of STSTW

Table 5.13

Projected Dry Weather Diurnal Flow Pattern of TPSTW

Table 5.14

Summary of Water Quality Modelling Scenarios

Table 5.15

Monthly Flow Rates of the Co-used and Not Co-used Options

Table 5.16

Monthly Flow Rates of the Proposed IP Scheme Under Co-used Option for Model Input

Table 5.17

Annual Volumes of  Secondarily Treated and Disinfected Effluent Overflow to Tolo Harbour under ¡§Without Project¡¨ Scenario

Table 5.18

Annual Volume of Secondarily Treated and Disinfected Effluent Overflow to Tolo Harbour under ¡§With Project¡¨ Scenario

Table 5.19

Predicted Water Quality at Selected WSD Flushing Water Intakes

Table 5.20

Predicted Water Quality at Kai Tak DCS Cooling Water Intake

Table 5.21

Predicted Water Quality at KTTS / Potential Water Sports Area

Table 6.1

Summary of Hotspots within STSTW

Table 7.1

Drill and Blast ¡V Explosives Requirements (Summary)

Table 7.2

Drill and Blast ¡V Typical Project Profiles

Table 7.3

Drill and Blast ¡V Initiating Systems

Table 7.4

Summary of Explosives Deliveries and Transport Quantities

Table 7.5

Scenarios Considered in the QRA Study

Table 7.6

Overall Frequency for Failure Scenarios Leading to Higher than Expected Vibration (Scenario U01 in Table 7.5)

Table 7.7

Frequency of Accidental Explosion due to Detonation of Full Load of Explosives during Delivery to Blast Site (Scenarios U02 to U04 in Table 7.5)

Table 7.8

Potential Loss of Life for Base Case

Table 7.9

Potential Loss of Life for Worst Case

Table 7.10

Potential Loss of Life for Base Case and Sensitivity Case

Table 7.11

Estimated Occurrence Frequencies of Significant Town Gas Releases at the

HP Underground Town Gas Transmission Pipelines

Table 7.12

Ignition Probabilities from Cox, Lees and Ang Model

Table 8.1

Baseline Information of Ecological Resources in the Assessment Area

Table 8.2

Ecological Survey Schedule

Table 8.3

Flora Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.4

Avifauna Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.5

Butterfly Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.6

Amphibian Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.7

Mammal Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.8

Fish Species of Conservation Importance Previously Recorded within the Assessment Area

Table 8.9

Habitats Recorded within the Assessment Area

Table 8.10

Avifauna Species of Conservation Importance Recorded within the Assessment Area from Recent Survey

Table 8.11

Number of Nests Recorded at Penfold Park Egretry in 2015

Table 8.12

Flight Heights of Ardeids that took off from Penfold Park Egretry

Table 8.13

Relative Percentage of Ardeid Usage in each Flight Line

Table 8.14

Mammal Species of Conservation Importance Recorded within the Assessment Area from Recent Survey

Table 8.15

Herpetofauna Species of Conservation Importance Recorded within the Assessment Area from Recent Survey

Table 8.16

Odonate Species of Conservation Importance Recorded within the Assessment Area from Recent Survey

Table 8.17

Freshwater Species of Conservation Importance Recorded within the Assessment Area from Recent Survey

Table 8.18

Species, Coverage and Size of Corals Found at the Spot-check Dive Sites

Table 8.19

Total Abundance and Biomass of Each Faunal Group

Table 8.20

Total Abundance and Biomass Recorded from Each Sampling Sites

Table 8.21

Intertidal Species Recorded during the Walk-through Survey

Table 8.22

Ecological Evaluation of Woodland within the Assessment Area

Table 8.23

Ecological Evaluation of Fung Shui Wood within the Assessment Area

Table 8.24

Ecological Evaluation of Plantation within the Assessment Area

Table 8.25

Ecological Evaluation of Shrubland within the Assessment Area

Table 8.26

Ecological Evaluation of Cultivated Land within the Assessment Area

Table 8.27

Ecological Evaluation of Developed Area within the Assessment Area

Table 8.28

Ecological Evaluation of the Streams S1 to S3 within the Assessment Area

Table 8.29

Ecological Evaluation of the Other Permanent and Seasonal Streams within the Assessment Area

Table 8.30

Ecological Evaluation of the Subtidal Hard Substrate, Soft Bottom and Intertidal Habitats within the Assessment Area

Table 8.31

Species of Conservation Importance Recorded within the Assessment Area during Recent Surveys and Previous Study

Table 8.32

Loss of Terrestrial Habitats

Table 8.33

Evaluation of Ecological Impacts to Woodland within the Assessment Area

Table 8.34

Evaluation of Ecological Impacts to Fung Shui Wood within the Assessment Area

Table 8.35

Evaluation of Ecological Impacts to Plantation within the Assessment Area

Table 8.36

Evaluation of Ecological Impacts to Shrubland within the Assessment Area

Table 8.37

Evaluation of Ecological Impacts to Cultivated Land within the Assessment Area

Table 8.38

Evaluation of Ecological Impacts to Developed Area within the Assessment Area

Table 8.39

Evaluation of Ecological Impacts to Stream within the Assessment Area

Table 8.40

Evaluation of Ecological Impacts to Other Permanent and Seasonal Streams within the Assessment Area

Table 8.41

Evaluation of Ecological Impacts to Subtidal Hard Substrate, Soft Bottom and Intertidal Habitats within the Assessment Area

Table 8.42

Compensatory Planting Proposed under the Project

Table 8.43

Flora Species to be Considered for Compensatory Planting

Table 9.1

Baseline Information of Fisheries Resources in the Assessment Area

Table 9.2

Recent Figures of Hong Kong Capture Fisheries Industry

Table 9.3

Summary of Capture Fisheries Data in the Assessment Area

Table 9.4

Fisheries Production (kg/ha) of the Top Ten Families in the Assessment Area

Table 9.5

Recent Figures of Hong Kong Culture Fisheries Industry

Table 9.6

Summary of Potential Fisheries Impact during Construction Phase

Table 9.7

Summary of Potential Fisheries Impact during Operation Phase

Table 10.1

Relationship between Landscape Sensitivity and Magnitude of Change in Defining

Impact Significance

Table 10.2

Relationship between Visually Sensitive Receivers (VSRs) Sensitivity and

Magnitude of Change in Defining Impact Significance

Table 10.3

Summary of the Review of Planning and Development Control Framework

Table 10.4

Baseline Landscape Resources (LRs) and their Sensitivity

Table 10.5

Baseline Landscape Character Areas (LCAs) and their Sensitivity

Table 10.6

Baseline Visually Sensitive Receivers (VSRs) and their Sensitivity

Table 10.7

Magnitude of Landscape Impacts during Construction and Operation

Table 10.8

 

Locations and Development Details of Permanent Aboveground Structures

Table 10.9

Magnitude of Visual Impacts during Construction and Operation

Table 10.10

Landscape and Visual Mitigation Measures for Construction Phase

Table 10.11

Landscape and Visual Mitigation Measures for Operation Phase

Table 10.12

Significance of Landscape Impacts during Construction and Operation Phases

Table 10.13

Significance of Visual Impacts during Construction and Operation Phases

Table 12.1

Summary of Inert and Non-Inert C&D Material Volumes Generated from Work Areas

Table 12.2

Anticipated Timing of Wastes Arising / Generation from Construction Activities and Disposal

Table 12.3

Summary on Disposal and Reuse of Inert C&D Materials Generated

Table 12.4

Tentative Transportation Routings for Waste Disposal

Table 12.5

Summary of Waste Arising, Waste Handling Procedures and Disposal Routes

Table 13.1

TAPs from Criteria Air Pollutants of HKAQOs

Table 13.2

TAP Considered in Various STW-related Literature and Guidelines

Table 13.3

Basis of the Toxicity Values from Various Standards / Guidelines           

Table 13.4

Toxicity Criteria of the Non-carcinogenic Risk Assessment of the Identified TAPs

Table 13.5

Toxicity Criteria of Carcinogenic Risks of the Identified TAPs

Table 13.6

List of Detectable TAPs

Table 13.7

List of Non-detectable TAPs

Table 13.8

Summary of short-listed TAPs for Non-Carcinogenic Risk Assessment

Table 13.9

Summary of short-listed TAPs for Carcinogenic Risk Assessment

Table 13.10

Representative Human Receptors in the vicinity of Relocated STSTW for Operational Health Impact Assessment

Table 13.11

Summary of Concentration Levels of Detectable TAPs at Emission Sources

Table 13.12

Removal Efficiency of Deodourizer for Different TAPs

Table 13.13

Summary of Maximum Incremental Concentration of TAPs with Non-carcinogenic Risk Level  

Table 13.14

Background Concentration of Criteria Pollutants from PATH Model

Table 13.15

Background TAPs Concentrations

Table 13.16

Maximum Predicted Cumulative Annual Average Concentrations of TAPs

Table 13.17

Maximum Predicted Cumulative Hourly Average Concentrations of TAPs

Table 13.18

Cancer Risk Guidance

Table 13.19

Total Incremental Cancer Risk due to Identified TAPs

Table 13.20

Indoor Air Quality Objectives for Office and Public Places

Table 13.21

Potential Accidental Events and Preventive Measures

Table 15.1

Summary of Key Environmental Outcomes / Benefits

Table 16.1

Implementation Schedule of Recommended Mitigation Measures


 

LIST OF DIAGRAMS

Diagram 2.01

Trenchless Pipe-laying Method

Diagram 2.02

Sewage Treatment Process Schematic Flow Diagram

Diagram 5.01

Water Bodies Potentially Affected by the THEES Effluent

Diagram 5.02

Generalized THEES Effluent Flow to Victoria Harbour Considered Under Scenarios 1, 2a, 2b, 3a and 3b

Diagram 5.03

Proposed Intake and Discharge Points of IP System

Diagram 5.04

Generalized Effluent Flow to Tolo Harbour Considered Under Scenario 4

Diagram 5.05

Generalized Effluent Flow to Tolo Harbour Considered Under Scenario 5

Diagram 5.06

Generalized Effluent Flow to Tolo Harbour Considered Under Scenarios 6a and 6b

Diagram 5.07

Generalized Effluent Flow to Tolo Harbour Considered Under Scenario 7

Diagram 7.01

Hong Kong Government Risk Guidelines

Diagram 7.02

Schematic Diagram of QRA Process

Diagram 7.03

Proposed Magazine Location and Explosives Transport Route

Diagram 7.04

Maximum Individual Risk Contours for Delivery Route (Outdoor Population)

Diagram 7.05

Maximum Individual Risk Contours for Delivery Route (Indoor Population)

Diagram 7.06

Individual Risk Contours for Magazine (Outdoor Population)

Diagram 7.07

Individual Risk Contours for Magazine (Indoor Population)

Diagram 7.08

F-N Curves for Storage, Transport and Use of Explosives

Diagram 7.09

F-N Curves Breakdown by Storage, Transport and Use of Explosives

Diagram 7.10

Framework for the Tolerability of Individual Risk in IGEM

Diagram 7.11

IGEM F-N Criterion Envelope

Diagram 7.12

Individual Risk Contours for the HP Underground Town Gas Transmission Pipeline

Diagram 7.13

Societal Risk Curve for Construction Stage

Diagram 7.14

Societal Risk Curve for Operational Stage

Diagram 7.15

Societal Risk Curve with IGEM F-N Criterion Envelope for Construction Stage

Diagram 7.16

Societal Risk Curve with IGEM F-N Criterion Envelope for Operational Stage

Diagram 7.17

Cumulative Individual Risk Contours

Diagram 7.18

FN Curves of Cumulative Risks

Diagram 8.01

Indicative Section of Access Road at Nui Po Shan

Diagram 13.01

Detailed UK Format for Health Risk Assessment Conceptual Process

Diagram 13.02

Schematic Flow of Treatment Process for Relocated STSTW

 


 

ABBREVIATIONS

3RS

Expansion of Hong Kong International Airport into a Three-Runway System

A&MO

AAB

Antiquities and Monuments Ordinance

Antiquities Advisory Board

AADT

Annual Average Daily Traffic

ACM

Asbestos Containing Materials

ADWF

Average Dry Weather Flow

AFCD

Agriculture, Fisheries and Conservation Department

AGI

Above Ground Installation

AGS

Aerobic Granular Sludge

AHM

Artificial Hard Materials

ALARP

AL Levels

As Low As is Reasonably Practicable

Action and Limit Levels

AMO

Antiquities and Monuments Office

ANL

Acceptable Noise Level

APCO

APHA

Air Pollution Control Ordinance

American Public Health Association

AQMS

Air Quality Monitoring System

AQO

Air Quality Objective

ASR

Air Sensitive Receiver

Area Sensitivity Rating (referred in Chapter 4 only)

ATC

Annual Traffic  Census

ATSDR

Agency for Toxic Substances and Disease Registry

BAF

Biological Aerated Filter

BC

Barrier Correction

BCF

Hong Kong Boundary Crossing Facilities

BDTM

Base District Traffic Model

BE

Bulk Explosives

BMP

Best Management Practice

BNL

Basic Noise Level

BOD

Biochemical Oxygen Demand

BOD5

5-day Biochemical Oxygen Demand

BSAP

Biodiversity Strategy and Action Plan

C&D

Construction and Demolition

C&DMMP

C&ED

Construction and Demolition Material Management Plan

Customs and Excise Department

CA

Conservation Area

Cal/EPA

California Environmental Protection Agency

CALINE4

California Line Source Dispersion Model, version 4

CAP

Contaminated Assessment Plan

CAR

Contamination Assessment Report

CAS

Conventional Activated Sludge

CBD

Convention on Biological Diversity

CBL

Cross Bay Link

CCTV

CDB

Closed-Circuit Television

Code of Practice for Demolition of Buildings

CE

Cartridged Emulsion

CEDD

Civil Engineering and Development Department

CEPT

Chemically Enhanced Primary Treatment

CFR

Code of Federal Regulations

CHIA

Cultural Heritage Impact Assessment

CIC

Construction Industry Council

CKR

Central Kowloon Route

CLP

CNP

CLP Power Hong Kong Ltd.

Construction Noise Permit

CNS

Central Nervous System

CO

Carbon Monoxide

CO2

Carbon Dioxide

COC

Chemicals of Concern

COD

Chemical Oxygen Demand

COPC

Chemical of Potential Concern

CRTN

Calculation of Road Traffic Noise

Csat

Soil Saturation

CSM

Conceptual Site Model

CSTW

Cavern Sewage Treatment Works

CT10

CUHK

Container Terminal 10 Development at Southwest Tsing Yi

Chinese University of Hong Kong

CWB

Central-Wan Chai Bypass

CWTC

Chemical Waste Treatment Centre

DA

Depth-Averaged

DA-TM

DAF

Technical Memorandum on Noise from Construction Work in Designated Areas

Dissolved Air Flotation

DBH

Diameter at Breast Height

DC

Distance Attenuation

DCDB

The Code of Practice for Demolition of Buildings

DCS

District Cooling System

DEFRA

Department of Environment, Food, and Rural Affairs

DETR

Department of Environment Transport and Regions

DEVB

DGPS

DG

Development Bureau

Differential Global Positioning System

Dangerous Goods

DNRA

Dissimilatory Nitrate Reduction to Ammonia

DO

Dissolved Oxygen

DOCEP

Department of Consumer and Employment Protection

DP

Designated Project

DSD

Drainage Services Department

E&M

Electrical and Mechanical

EIA

Environmental Impact Assessment

EIAO

Environmental Impact Assessment Ordinance

EIAO-TM

Technical Memorandum on Environmental Impact Assessment Process

EIDAS

Explosives Incidents Database Advisory Service

EM&A

Environmental Monitoring and Audit

EMFAC-HK

Emission Factors Hong Kong Model

EMP

Environmental Management Plan

EMSD

Electrical and Mechanical Services Department

EP

Environmental Permit

EPD

ER

ES

Environmental Protection Department

Engineer¡¦s Representative

Executive Summary

ESB

EIA Study Brief

ESTC

Explosives Storage and Transport Committee

ETWB

ET

Environment, Transport and Works Bureau

Environmental Team

EUGRIS

European Groundwater and Contaminated Land Remediation Information System

FC

Façade Correction

FCZ

Fish Culture Zone

FDM

Fugitive Dust Model

FPA

Fisheries Protection Area

FSD

Fire Services Department

FSP

Fine Suspended Particulates

FTA

Fault Tree Analysis

GB

GBNSR

Green Belt

Ground Borne Noise Sensitive Receiver

GCHIA

Guidelines for Cultural Heritage Impact Assessment

GEO

Geotechnical Engineering Office

GIC

Government, Institution or Community

GIS

Geographic Information System

GLTM

Greening, Landscape and Tree Management

GPS

Global Positioning System

GW-TM

Technical Memorandum on Noise from Construction Work other than Percussive Piling

H2S

Hydrogen Sulphide

HAB

Harmful Algal Bloom

HAP

Hazardous Air Pollutant

HATS

Harbour Area Treatment Scheme

HD

Housing Department

HEC

Health and Environmental Committee

HHRA

Human Health Risk Assessment

HIA

Health Impact Assessment

HKCG

Hong Kong and China Gas Company

HKPSG

Hong Kong Planning Standards and Guidelines

HKRG

Hong Kong Government Risk Guidelines

HKSAR

Hong Kong Special Administrative Region

HP

High Pressure

HPCL

Health Protection Concentration Level

HR

Human Receptor

HSC

HTML

Health and Safety Commission

Hyper Text Markup Language

HyD

Highways Department

HZMB

Hong Kong - Zhuhai - Macao Bridge

IAQ

Indoor Air Quality

IARC

International Agency for Research on Cancer

ICOMOS

IEC

International Council on Monuments and Sites

Independent Environmental Checker

IF

Influencing Factor

IFAS

Integrated Fixed Film Activated Sludge System

IGEM

Institution of Gas Engineers and Managers

IND-TM

Technical Memorandum on Noise from Places other than Domestic Premises, Public Places or Construction Sites

IP

Interception and Pumping

IR

Individual Risk

IRIS

Integrated Risk Information System

ISCST3

Industrial Sources Complex Short Term 3

ISEPS

Intermediate Sewage and Effluent Pumping Station

IUCN

International Union for Conservation of Nature

IUR

Inhalation Unit Risk

IWMF

Integrated Waste Management Facilities

KCRC

Kowloon-Canton Railway Corporation

KED

Kowloon Explosives Depot

KTAC

Kai Tak Approach Channel

KTD

Kai Tak Development

KTN

Kai Tak Nullah

KTTS

Kwun Tong Typhoon Shelter

MRL

Minimum Risk Level

LandsD

LC

Lands Department

Local Concern

LCA

Landscape Character Area

LCSD

Leisure and Cultural Services Department

LR

Landscape Resource

LTT

Lam Tin Tunnel

mAG

Meters above Ground

MBBR

Moving Bed Biofilm Reactor

MBR

MD

Membrane Bioreactor

Mines Division

MHSA

Mine Safety and Health Administration

MIC

MLE

MLSS

Maximum Instantaneous Charge

Modified Ludzack-Ettinger

Mixed Liquor Suspended Solids

MM5

Mesoscale Model 5

MTRC

MTR Corporation Limited

NaOCl

Sodium Hypochlorite

NAPL

Non-Aqueous Phase Liquid

NCO

Noise Control Ordinance

NEDA

Non Explosive Demolition Agents

NENT

North East New Territories

NH3

Ammonia

NH3-N

Ammonia Nitrogen

NIMBY

Not-In-My-Backyard

NO2

Nitrogen Dioxide

NO2-N

Nitrite Nitrogen

NO3-N

Nitrate Nitrogen

NSR

Noise Sensitive Receiver

NTU

Turbidity

O3

Ozone

OEHHA

Office of Environmental Health Hazard Assessment

OVT

Old and Valuable Tree

OU

Other Specified Uses (referred in Chapter 10 only)

OU

Odour Unit

OZP

Outline Zoning Plan

PAH

Poly-aromatic Hydrocarbons / Polycyclic Aromatic Hydrocarbons

PATH

Pollutants in the Atmosphere and their Transport over Hong Kong model

PCB

Polychlorinated Biphenyls

PCR

Petroleum Carbon Ranges

PCRAMMET

PCRAMMET Meteorological Program

PCW

PDF

Prescribed Construction Work

Portable Document Format

PER

Preliminary Environmental Review

PFA

Pulverized Fuel Ash

PFC

Public Fill Committee

PFRF

PGC

PRC

Public Fill Reception Facilities

Potential Global Concern

Potential Regional Concern

PlanD

Planning Department

PLL

Potential Loss of Life

PME

PM10

 

PM2.5

Powered Mechanical Equipment

Suspended particulates in air with a nominal aerodynamic diameter of 10µm or smaller

Suspended particulates in air with a nominal aerodynamic diameter of 2.5µm or smaller

PN

Practice Note

PO4

Orthophosphate Phosphorus

PP-TM

Technical Memorandum on Noise from Percussive Piling

PPRTV

Provisional Peer-Reviewed Toxicity Value

PPV

Peak Particle Velocity

ProPECC

Professional Persons Environmental Consultative Committee

PRS

Potential Reclamation Site

PTW

PVC

PVS

QA

QC

Preliminary Treatment Work

Polyvinyl Chloride

Planning Vision and Strategy

Quality Assurance

Quality Control

QPME

Quality Powered Mechanical Equipment

QRA

Quantitative Risk Assessment

RAGS

Risk Assessment Guidance for Superfund

RAP

Remediation Action Plan

RBRG

Risk-Based Remediation Goal

RC

Reinforced Concrete

RCL

Receptor Concentration Level

REL

Reference Exposure Level

REA

Rapid Ecological Assessment

RfC

Reference Concentrations

Rn

Radon

RO

Regional Office

RR

Remediation Report

RSP

Respirable Suspended Particulates

RT

Reverberation Time

SANI

SAS

Sulphate Reduction Autotrophic Denitrification and Nitrification Integrated

Surplus Activated Sludge

SCISTW

Stonecutters Island Sewage Treatment Works

SCL

Shatin to Central Link

SI

Site Investigation

SiO2

Silica

SKSTW

Sai Kung Sewage Treatment Works

SO2

Sulphur Dioxide

SPL

Sound Pressure Level

SPME

Specified Powered Mechanical Equipment

SRB

Sulphate-Reducing Bacteria

SS

Suspended Solids

SSSI

Sites of Special Scientific Interest

STDC

Sha Tin District Council

STDO

Sha Tin District Office

STEPS

Sha Tin Effluent Pumping Station

STF

Sludge Treatment Facilities

STSTW

Sha Tin Sewage Treatment Works

STW

Sewage Treatment Works

STWTW

Sha Tin Water Treatment Works

SVOC

Semi-Volatile Organic Compound

SWL

Sound Power Level

TAP

Toxic Air Pollutant

TBM

Tunnel Boring Machine

TCNTE

Tung Chung New Town Extension

TC(W)

Technical Circular (Works)

TD

Transport Department

TH

Tolo Harbour

THEES

Tolo Harbour Effluent Export Scheme

THMB

Tolo Harbour and Mirs Bay

TIN

Total Inorganic Nitrogen

TKN

Total Kjeldahl Nitrogen

TKO

TM

Tseung Kwan O

Technical Memorandum

TM-CLKL

Tuen Mun - Chek Lap Kok Link

TM-DSS

Technical Memorandum on Standards for Effluents Discharged into Drainage and Sewerage Systems, Inland and Coastal Waters

TN

Total Nitrogen

TNT

Trinitrotoluene

TP

Total Phosphorus

TPEDM

Territorial Population and Employment Data Matrices

TPEPS

Tai Po Effluent Pumping Station

TPL

Total Pollution Load

TPSTW

Tai Po Sewage Treatment Works

TSP

Total Suspended Particulates

UDS

Ultimate Design Scenario

UIA

Unionized Ammonia

UK HSE

UNESCO

UK Health and Safety Executive

United Nations Educational Scientific and Cultural Organization

USEPA

US Environmental Protection Agency

UV

Ultraviolet

VCE

Vapour Cloud Explosion

VDC

Vehicle Detention Centre

VKT

Vehicle-Kilometer-Travelled

VOC

Volatile Organic Compound

VPF

Value of Preventing a Fatality

VSR

WBTC

Visually Sensitive Receiver

Works Bureau Technical Circular

WCZ

Water Control Zone

WDII

Wan Chai Development Phase II

WDO

Waste Disposal Ordinance

WENT

West New Territories

WHO

World Health Organization

WIL

West Island Line

WMP

Waste Management Plan

WPCO

Water Pollution Control Ordinance

WQO

Water Quality Objective

WSD

Water Supplies Department

WSR

Water Sensitive Receiver