Table of Content

 

Volume I - Environmental Impact Assessment Report

 

1.     INTRODUCTION

Project Background

Requirements of the Environmental Impact Assessment Ordinance       

Objectives of the EIA Study    

The Approach 

Report Structure     

 

2.     DESCRIPTION OF THE PROJECT    

Ocean Park Corporation 

Project Scope 

Previous Submissions     

Project Location     

Site History     

Need for and Benefits of the Project       

Ocean Park’s Redevelopment Strategy  

Project Design & Consideration of Alternatives      

“Without the Project” Scenario      

The EIA Assessment area       

Works Programme and Implementation 

Concurrent Projects Having Potential for Cumulative Effects 

Traffic Forecasts     

 

3.     NOISE IMPACT

Introduction    

Environmental Legislation, Standards and Guidelines   

Noise Sensitive Receivers      

Description of the Environment      

Assessment Methodology and Uncertainties   

Identification of Environmental Impact   

Evaluation of Impacts     

Mitigation of Adverse Environmental Impacts

Evaluation of Residual Impacts      

Environmental Monitoring and Audit      

Conclusion      

 

4.     LANDSCAPE AND VISUAL IMPACT ASSESSMENT  

Introduction    

Project Description 

Review of Planning and Development Control Framework    

Environmental Legislation and Standards      

Methodology of Assessment of Landscape Impacts

Methodology of Assessment of Visual Impacts       

Baseline Study       

Landscape Impact Assessment       

Visual Impact Assessment      

Recommended Landscape and Visual Mitigation Measures  

Residual impacts    

Conclusion      

 

5.     ECOLOGY       

Introduction    

Environmental Legislation, Standards and Guidelines   

Assessment Methodology       

Ecological Value     

Environmental Impact Identification, Prediction and Evaluation    

Mitigation of Adverse Environmental Impacts

Evaluation of Residual Impacts      

Environmental Monitoring and Audit      

Conclusion      

References     

 

6.     WASTE MANAGEMENT IMPLICATIONS   

Introduction    

Environmental Legislation, Policies, Plans, Standards and Criteria       

Assessment Methodology       

Identification and Evaluation of Environmental Impacts

Operation Phase     

Mitigation of Adverse Environmental Impacts

Evaluation of Residual Impacts      

Environmental Monitoring and Audit      

Conclusion      

 

7.     LAND CONTAMINATION   

Introduction    

Environmental Legislation, Policies, Plans, Standards and Criteria       

Assessment Methodology       

Description of the Environment      

Identification of Potential Environmental Impacts  

Identification of Sensitive Receivers      

Land Contamination Assessment    

Prediction and Evaluation of Environmental Impacts     

Preliminary Programmes for Site Investigation and Remediation (Alternative Scenarios for HKSM site)      

Mitigation Measures for Land Contamination 

Residual Environmental Impact      

Environmental Monitoring and Audit Requirements       

Conclusions    

 

8.     AIR QUALITY IMPACT     

Introduction    

Environmental Legislation, Standards and Guidelines   

Description of the Environment      

Air Sensitive Receivers   

Identification of Pollutant Sources 

Assessment Methodology       

Evaluation of Impacts     

Mitigation of Adverse Environmental Impacts

Evaluation of Residual Impacts      

Environmental Monitoring and Audit      

Conclusion      

 

9.     WATER QUALITY     

Introduction    

Environmental Legislation and Standards      

Baseline Conditions

Water Sensitive Receivers      

Assessment Methodology       

Identification and Evaluation of Environmental Impacts

Mitigation Measures       

Residual Environmental Impacts    

Conclusion      

 

10.    SEWERAGE AND SEWAGE TREATMENT  

Introduction    

Background    

Sewerage Catchment Area    

Design assumptions and criteria     

Development and Flow Projections

Existing & Committed Sewerage Infrastructure      

Sewerage Impact Assessment

Conclusion      

 

11.    CULTURAL HERITAGE IMPACT ASSESSMENT 

Introduction    

Project Location     

Proposed Works     

Environmental Legislation and Standards      

Archaeology   

Identification and Evaluation of Potential Impacts 

Mitigation Measures       

Built Heritage 

Baseline Conditions

Identification and Evaluation of Potential Impacts 

Mitigation Measures       

Conclusion      

EM&A      

References     

 

12.    HAZARD TO LIFE     

Introduction    

Environmental Legislations, Policies, Plans, Standards and Criteria     

Assessment Approach and Methodology

Assessment Result  

Conclusions and Recommendations       

 

13.    ENVIRONMENTAL MONITORING AND AUDIT   

Introduction    

Noise Impact   

Landscape and Visual Impact

Ecological Impact   

Waste Management Implications   

Land Contamination       

Air Quality Impact   

Water Quality Impact      

Sewerage and Sewage Treatment Implication      

Impact on Cultural Heritage   

Hazard to Life 

 

14.    CONCLUSIONS & SUMMARY OF ENVIRONMENTAL OUTCOMES     

Introduction    

Noise Impact   

Landscape and Visual Impact

Ecological Impact   

Waste Management Implications   

Land Contamination       

Air Quality Impact   

Water Quality Impact      

Sewerage and Sewage Treatment Implications     

Impact on Cultural Heritage   

Hazard to Life 

Overall Conclusion 

 

15.    IMPLEMENTATION SCHEDULE AND RECOMMENDED MITIGATION MEASURES       

 

List of Tables

 

Table 2.1   Summary of Construction Period for the Development   

Table 3.1   Acceptable Noise Level for Fixed Plant Noise      

Table 3.2   Representative Noise Sensitive Receivers    

Table 3.3   Key Noise Sources to the existing NSRs    

Table 3.3a Noise Measurement Locations   

Table 3.3b Measured Noise Levels      

Table 3.4   Prevailing Background Noise Levels at Representative NSRs

Table 3.5   Traffic Scenarios Assessed

Table 3.6   Peak-hour Traffic at Key Road Links for the “With Redevelopment” and “Without Redevelopment” Scenario       

Table 3.7   Unmitigated Construction Noise Levels During Normal Daytime Working Hours      

Table 3.8   Predicted Traffic Noise Levels for the “With Redevelopment” and “Without Redevelopment” Scenarios - Weekday      

Table 3.9   Predicted Traffic Noise Levels for the “With Redevelopment” and “Without Redevelopment” Scenarios – Weekend / Public Holiday    

Table 3.10 Predicted Fixed Plant Noise Levels     

Table 3.11  Predicted Entertainment Noise Levels – Scenarios A and B  

Table 3.12 Cumulative Impact of Fixed Noise Sources – Scenario IIA     

Table 3.13 Cumulative Impact of Fixed Noise Sources – Scenario IIB     

Table 3.14 Summary of Mitigated Construction Noise Levels During Non-restricted Hours

Table 3.15 Construction Works to be avoided during the Examination Hour of the Police Training School  

Table 4.1   Matrix for Impact Significance Threshold Before Mitigation: Relationship between Sensitivity to Change and Magnitude of Change for LVIA

Table 4.2   Significance of Landscape Resource Impacts in Construction and Operational Phases BEFORE Mitigation      

Table 4.3   Significance of Landscape Character Impacts in Construction and Operational Phases BEFORE Mitigation      

Table 4.4   Example Matrix for Assessment of Glare – Noon 

Table 4.5   Example Matrix for Assessment of Glare – Morning or Dusk 

Table 4.6   Extent of View and Relative Altitudes of VSRs Compared with Ocean Park    

Table 4.7   Significance of Visual Impacts in Construction and Operational Phases Before Mitigation

Table 4.8   Recommended Landscape and Visual Mitigation Measures in Construction and Operational Phases

Table 4.9   Recommended Mitigation Measures and Residual Impact AFTER Mitigation for LR

Table 4.10 Recommended Mitigation Measures and Residual Impact AFTER Mitigation for LCA       

Table 4.11  Recommended Mitigation Measures and Residual Impact AFTER Mitigation for VSR      

Table 5.1   Summary of Rapid Ecological Assessment dive survey results      

Table 5.2   Summary Information on Coral Species recorded 

Table 5.3   Summary of Ocean Park Dive Survey compared to the five best transects of the HKUWS

Table 5.4a Ecological Value of Low Shrubland and Tall Shrubland in the Assessment Area      

Table 5.4b Ecological Value of Plantation & Parkland and Developed Areas in the Assessment Area

Table 5.4c Ecological Value of Freshwater Habitats & Rocky Shore in the Assessment Area   

Table 5.4d Ecological Value of Sandy Shore and Artificial Seawall in the Assessment Area      

Table 5.4e Ecological Value of Subtidal Habitats in the Assessment Area      

Table 5.5a Evaluation of Floral Species of Conservation Interest Recorded Within the Assessment Area    

Table 5.5b Evaluation of Faunal Species of Conservation Interest Recorded Within Assessment Area

Table 5.6   Direct Habitat Loss Resulting From Proposed Works   

Table 5.7a Overall Impact Evaluation of Low Shrubland and Tall Shrubland      

Table 5.7b Overall Impact Evaluation of Plantation & Parkland & Developed Areas   

Table 5.7c Overall Impact Evaluation of Freshwater Habitats 

Table 5.8   Overall Impacts to Species of Conservation Interest      

Table 5.7d Overall Impact Evaluation of Rocky Shore and Sandy Habitats      

Table 5.7e Overall Impact Evaluation of Artificial Seawall and Subtidal Habitats       

Table 6.1   Summary of C&D Material Volumes    

Table 6.2   Estimated Timing of C&D Material and C&D Waste Generation     

Table 6.3   Summary of Waste Materials Produced During Park Operation     

Table 6.4   Summary of Waste Handling Procedures and Disposal Routes     

Table 7.1   Aerial Photographs Reviewed     

Table 7.2   Records of Current and Past Registration of Storage of Dangerous Goods      

Table 7.3   Potential Contaminative Areas/Activities in the Hong Kong School of Motoring

Table 7.4   Potential Contaminative Areas/Activities in the Citybus Depot       

Table 7.5   Potential Contaminative Areas/Activities in the Existing Ocean Park      

Table 7.6a Summary of Elevated Levels of Heavy Metal in Soil Samples at CBD Site      

Table 7.6b Estimated Volume of Heavy Metals Contaminated Soil for CS/S Treatment    

Table 7.7   Estimated Volume of Contaminated Soil at Identified Hotspots in HKSM

Table 7.8   Possible Remediation Options and Preliminary Remediation Programme For HKSM Site

Table 7.9   Comparison between Tai Shue Wan and Open Space near the Rest Garden for Biopile Treatment    

Table 8.1   Hong Kong Air Quality Objectives       

Table 8.2   Background Air Pollutant Concentration for the Study Area    

Table 8.3   Summary of Representative Air Sensitive Receivers      

Table 8.4   Details of Aberdeen Tunnel and Ventilation Shafts

Table 8.5   Predicted Air Pollutant Concentrations at Representative ASRs for the Future Scenario (Year 2026, Redeveloped Park)       

Table 8.6   Predicted Air Pollutant Concentrations at Representative ASRs for the Future Scenario (Year 2026, Park without Development)    

Table 8.7   Predicted SO2 concentrations at Representative ASRs for Future Scenario    

Table 9.1   Summary of Water Quality Objectives for Marine Waters of Southern Water Control Zone

Table 9.2   Summary of Water Quality Objectives for Marine Waters of Western Buffer Water Control Zone       

Table 9.3   Summary Statistics of Marine Water Quality in the Southern WCZ at Station SM2  

Table 10.1 Assumptions on Unit Flow Factors     

Table 10.2 Recommended Unit Flow Factors       

Table 10.3 ADWF in Year 2016 for the Aberdeen Catchment 

Table 10.4 Recommended Peaking Factors for Sewers

Table 10.5 Estimated sewage flow from Ocean Park after redevelopment       

Table 10.6 Existing Facilities of the Aberdeen PTW*    

Table 10.7 Summary of Surcharged Sewers at Peak Flow under SIA Condition       

Table 10.8 Summary of Recommended Sewerage Upgrading Works      

Table 11.1  Recommended Mitigation Measures for the Proposed Project       

Table 11.2  Adverse Impacts to Historical Buildings during the Construction Phase  

Table 11.3  Adverse Impacts to Historical Graves during the Construction Phase     

Table 11.4  Adverse Impacts to Historical Buildings during the Operation Phase      

Table 11.5  Adverse impacts to the Historical Graves during the Operational Phase 

Table 14.1 Summary of Key Environmental Outcomes / Benefits   

Table 15.1 Project Implementation Schedule       

 

Volume II – Drawings

 

List of Figures

Figure 1.1          Location of the Project Site

Figure 2.1          Master Plan –The Waterfront

Figure 2.2          Master Plan –The Summit

Figure 2.3          Diagrammatic Section Through the Site

Figure 2.4          The Location of Expanded Area (The Waterfront)

Figure 2.5          The Location of Expanded Area (The Summit)

Figure 3.1a        Measurement Locations for Existing Noise Levels

Figure 3.1          Locations of Representative Noise Sensitive Receivers-Construction Noise

Figure 3.2          Locations of Representative Noise Sensitive Receivers-Project Inducted Traffic Noise

Figure 3.3          Locations of Representative Noise Sensitive Receivers-Fixed Plant and Entertainment Noise

Figure 3.4          Indicative Barging Point and Conveyor Belt System Locations

Figure 3.5          Typical Section of Conveyor Belt System

Figure 3.6          Glory Hole Method for Excavation at Headland Typical Section

Figure 4.1.1       Location Plan for the Project

Figure 4.1.2       Existing Aerial View of Ocean Park

Figure 4.1.3       The Proposed Development – Master Layout Plan

Figure 4.1.4       The Proposed Development – Image for “The Waterfront”

Figure 4.1.5       The Proposed Development – Image for “The Summit”

Figure 4.1.6       Planning & Development Framework (OZP)

Figure 4.1.7       Envisaged Phasing Plan

Figure 4.1.8       Not used

Figure 4.1.9       Not used

Figure 4.1.10     Photo of Physical Model – “The Waterfront”

Figure 4.1.11     Photo of Physical Model –“The Summit”

Figure 4.2.1       Landscape Resources

Figure 4.2.2       Photo of Landscape Resources (LR1 - 4) – Sheet 1 of 4

Figure 4.2.3       Photo of Landscape Resources (LR5 - 8) – Sheet 2 of 4

Figure 4.2.4       Photo of Landscape Resources (LR9 - 10) – Sheet 3 of 4

Figure 4.2.5       Photo of Landscape Resources (LR11 - 14) – Sheet 4 of 4

Figure 4.3.1       Landscape Character Area

Figure 4.3.2       Photo of Landscape Character Area (LCA1 - 5) – Sheet 1 of 5

Figure 4.3.3       Photo of Landscape Character Area (LCA6 - 9) – Sheet 2 of 5

Figure 4.3.4       Photo of Landscape Character Area (LCA10 - 12) – Sheet 3 of 5

Figure 4.3.5       Photo of Landscape Character Area (LCA13 - 15) – Sheet 4 of 5

Figure 4.3.6       Photo of Landscape Character Area (LCA15 - 16) – Sheet 5 of 5

Figure 4.4.1       Visibility Contour Plan – “The Waterfront”

Figure 4.4.2       Visibility Contour Plan – “The Summit”

Figure 4.4.3       Visibility Contour Plan – Funicular Train

Figure 4.4.4       Zone of Visual Influence for Visual Sensitive Receivers

Figure 4.4.5       Photo of Visual Sensitive Receivers Group (VSR1 - 3) – Sheet 1 of 7

Figure 4.4.6       Photo of Visual Sensitive Receivers Group (VSR4 - 7) – Sheet 2 of 7

Figure 4.4.7       Photo of Visual Sensitive Receivers Group (VSR8 - 10) – Sheet 3 of 7

Figure 4.4.8       Photo of Visual Sensitive Receivers Group (VSR11 – 15) – Sheet 4 of 7

Figure 4.4.9       Photo of Visual Sensitive Receivers Group (VSR16 – 19) – Sheet 5 of 7

Figure 4.4.10     Photo of Visual Sensitive Receivers Group (VSR20 - 23) – Sheet 6 of 7

Figure 4.4.11     Photo of Visual Sensitive Receivers Group (VSR24 – 27) – Sheet 7 of 7

Figure 4.5.1       Views for Visual Sensitive Receivers (VSR1 – 4) – Sheet 1 of 8

Figure 4.5.2       Views for Visual Sensitive Receivers (VSR5 – 8) – Sheet 2 of 8

Figure 4.5.3       Views for Visual Sensitive Receivers (VSR9 – 10) – Sheet 3 of 8

Figure 4.5.4       Views for Visual Sensitive Receivers (VSR11 – 15) – Sheet 4 of 8

Figure 4.5.5       Views for Visual Sensitive Receivers (VSR15 – 16) – Sheet 5 of 8

Figure 4.5.6       Views for Visual Sensitive Receivers (VSR17 – 19) – Sheet 6 of 8

Figure 4.5.7       Views for Visual Sensitive Receivers (VSR20 – 23) – Sheet 7 of 8

Figure 4.5.8       Views for Visual Sensitive Receivers (VSR24 – 27) – Sheet 8 of 8

Figure 4.5.9       Existing Night View for Ocean Park and Surrounding Area – Sheet 1 of 3

Figure 4.5.10     Existing Night View for Ocean Park and Surrounding Area – Sheet 2 of 3

Figure 4.5.11     Existing Night View for Ocean Park and Surrounding Area – Sheet 3 of 3

Figure 4.5.12     Existing Special Events Night View for Ocean Park

Figure 4.6.1       Mitigation measures – Operation Phase

Figure 4.6.2       Photomontage – Residual Visual Impact for VSR2 (Ocean Park Cable Car) – Sheet 1 of 16

Figure 4.6.3       Photomontage – Residual Visual Impact for VSR2 (Ocean Park Cable Car) – Sheet 2 of 16

Figure 4.6.4       Photomontage – Residual Visual Impact for VSR7 (Southwest Nam Fung Road) – Sheet 3 of 16

Figure 4.6.5       Photomontage – Residual Visual Impact for VSR7  (Southwest Nam Fung Road) – Sheet 4 of 16

Figure 4.6.6       Photomontage – Residual Visual Impact for VSR11 (Ap Lei Chau) – Sheet 5 of 16

Figure 4.6.7       Photomontage – Residual Visual Impact for VSR11 (Ap Lei Chau) – Sheet 6 of 16

Figure 4.6.8       Photomontage – Residual Visual Impact for VSR14 (Shouson Hill) – Sheet 7 of 16

Figure 4.6.9       Photomontage – Residual Visual Impact for VSR14 (Shouson Hill) – Sheet 8 of 16

Figure 4.6.10     Photomontage – Residual Visual Impact for VSR15 (Deep Water Bay) – Sheet 9 of 16

Figure 4.6.11     Photomontage – Residual Visual Impact for VSR15  (Deep Water Bay) – Sheet 10 of 16

Figure 4.6.12     Photomontage – Residual Visual Impact for VSR17 (Chung Hom Kok) – Sheet 11 of 16

Figure 4.6.13     Photomontage – Residual Visual Impact for VSR17 (Chung Hom Kok) – Sheet 12 of 16

Figure 4.6.14     Photomontage – Residual Visual Impact for VSR22 (Wong Nai Chung Gap) – Sheet 13 of 16

Figure 4.6.15     Photomontage – Residual Visual Impact for VSR22 (Wong Nai Chung Gap) – Sheet 14 of 16

Figure 4.6.16     Photomontage – Residual Visual Impact for VSR28 (Manly Villa) – Sheet 15 of 16

Figure 4.6.17     Photomontage – Residual Visual Impact for VSR28 (Manly Villa) – Sheet 16 of 16

Figure 4.6.18     Photomontage – Residual Visual Impact for VSR14 (Shouson Hill) – Sheet 1 of 4

Figure 4.6.19     Photomontage – Residual Visual Impact for VSR14 (Shouson Hill) – Sheet 2 of 4

Figure 4.6.20     Photomontage – Residual Visual Impact for VSR15 (Deep Water Bay) – Sheet 3 of 4

Figure 4.6.21     Photomontage – Residual Visual Impact for VSR15 – Sheet 4 of 4

Figure 4.7.1       Photo Illustrations of Typical Mitigation Measures

Figure 5.1          Habitat Map

Figure 5.2          General Walk Transect of Avifaunal and Location of Macroinvertebrate Survey

Figure 5.3          Locations of Marine Survey Area

Figure 5.4          Proposed Location of Compensatory Planting

Figure 7.1          Potential Contaminated Areas Inspected in the Hong Kong School of Motoring

Figure 7.2          Potential Contaminated Areas Inspected in the Citybus Depot

Figure 7.3a        Potential Contaminated Areas Inspected in the Existing Ocean Park - Lowland

Figure 7.3b        Potential Contaminated Areas Inspected in the Existing Ocean Park - Headland

Figure 7.4          Proposed Sampling Locations for Hong Kong School of Motoring and City Bus Depot

Figure 7.5a        Proposed Area for On-Site Biopile Treatment at Tai Shue Wan

Figure 7.5b        Proposed Area for On-Site Biopile Treatment Near Nam Long Shan Road Rest Garden

Figure 7.6          Interface of HKSM & CBD Sites and Proposed Development Area

Figure 8.1          The Study Area for Air Quality Impact Assessment

Figure 8.2          Locations of Representative Air Sensitive Receivers

Figure 8.3          Contours of Hourly Average Nitrogen Dioxide Concentrations in mg/m3 at 1.5m above Ground Level

Figure 8.4          Contours of 24-Hour Average Nitrogen Dioxide Concentrations in mg/m3 at 1.5m above Ground Level

Figure 8.5          Contours of 24-Hour Average Respirable Suspended Particulate Concentrations in mg/m3 at 1.5m above Ground Level

Figure 8.6          Contours of Hourly Average Sulphur Dioxide Concentrations in mg/m3 at 70m above Ground Level

Figure 9.1          Location of EPD Water Quality Monitoring Station

Figure 9.2          Location of Water Sensitive Receivers

Figure 10.1        PVS Zone Boundaries in Aberdeen Sewerage Catchment

Figure 10.2        Existing Sewerage Infrastructure in Aberdeen Sewerage Catchment

Figure 10.3        Existing Sewerage Infrastructure in Study Area

Figure 10.4a-c   Existing Sewerage Network

Figure 10.5a-c   Surcharged Sewers in Baseline Condition

Figure 10.6a-c   Surcharged Sewers in Additional Flow Condition

Figure 10.7a-c   Upgrading Works

Figure 11.1        Photo of Model Showing Future Development at Lowland and to the Right the Country Club Facilities

Figure 11.2       Location of School of Motoring

Figure 11.3        Aerial Photograph Taken in 1924 of the Wong Chuk Hang Area

Figure 11.4       Photo Showing the General Area of the Wong Chuk Hang Rockcarving

Figure 11.5       Wong Chuk Hang Rockcarving - Photo of Most Western Carving

Figure 11.6       Wong Chuk Hang Rockcarving - Photo of Most Eastern Carving

Figure 11.7        Wong Chuk Hang Rockcarving - Photo of Centre Carving

Figure 11.8        Previous Testing Near Wong Chuk Hang San Wai

Figure 11.9        Revised Collinson Map Drawn in 1895

Figure 11.10     Map Drawn in 1945 within the Study Area

Figure 11.11      1957 Map within the Study Area

Figure 11.12      1971 Map of Wong Chuk Hang

Figure 11.13      Map of 1975 Showing Large River in the SoM Area

Figure 11.14      Map of 1978 Showing the Ocean Park Lowland and SoM Areas

Figure 11.15      Aerial Photograph Taken in 1978 of the Wong Chuk Hang Area

Figure 11.16      Map of 1957 Showing the Headland and its Impacts

Figure 11.17      Map Showing the Headland area in 1975

Figure 11.18      Photo Taken of the Site Formation at Headland

Figure 11.19      Area Proposed for Archaeological Survey

Figure 11.20      The Study Area as seen on the Collinson Ordnance Map of Hong Kong (1845)

Figure 11.21      The Study Area as seen on the revised Collinson Ordnance Map of Hong Kong (1895)

Figure 11.22      Map Showing the Recorded Heritage Resources in Wong Chuk Hang San Wai (AAHB-900 to 916)

Figure 11.23      Map Showing the Recorded Heritage Resources on Nam Long Shan Road (AAHB-917 to 920)

Figure 11.24      Location of the Historical Grave

 

Volume III – Appendices

 

List of Appendices

Appendix 2.1     The Original Scheme Presented in the Project Profile

Appendix 2.2     Preliminary Construction Programme

Appendix 2.3     Traffic Forecast for Years 2005 and 2026

Appendix 3.1     Assumed Area Sensitivity Ratings of the Representative NSRs

Appendix 3.2     Photographs of the Representative NSRs

Appendix 3.3     Construction Noise Impact Assessment (Unmitigated Scenario)

Appendix 3.4     Fixed Plant Noise Impact Assessment

Appendix 3.5     Entertainment Noise Impact Assessment

Appendix 3.6     Construction Noise Impact Assessment (Mitigated Scenario)

Appendix 4.1     Broad Tree Survey Report for “The Waterfront” & “The Summit”

Appendix 4.2     Tree Survey Report for Expansion of Arrival Area and Transport Facilities – Application for Rezoning

Appendix 5.1     Representative Photographs of Habitats

Appendix 5.2     Plant Species of Conservation Interest

Appendix 5.3     Plant Species Recorded On or Adjacent to Features

Appendix 5.4     Fauna Recorded Within the Assessment Area

Appendix 5.5     Composition and Abundance (No. of Individuals/percentage cover per 0.25m2) of Rocky Shore, Sandy Shore and Artificial Seawall Biota at the Assessment Area –Batch 2

Appendix 5.6     Coral Species and Abundance recorded during Rapid Ecological Assessment (REA)

Appendix 5.7     Representative photographs of Coral Species

Appendix 5.8     Five Community Types defined in the Underwater Survey in Coastal Waters of Hong Kong (HKUWS) (Oceanway, 2002)

Appendix 7.1a   Contamination Assessment Plan – Hong Kong School of Motoring

Appendix 7.1b   Contamination Assessment Plan – City Bus Depot

Appendix 7.2     Contamination Assessment Report – City Bus Depot

Appendix 7.3     Remediation Action Plan – City Bus Depot

Appendix 8.1     Sensitivity Test for Emission Rates

Appendix 8.2     Details for the Calculations of the Composite Emission Factors for each Road Link

Appendix 8.3     Details for the Calculations of Portal Emission

Appendix 8.4     Details for the Calculation of Chimney Emission Factor

Appendix 10.1   Breakdown of Population in Aberdeen Sewerage Catchment and Flow Build-up

Appendix 10.2   Breakdown of Estimated Sewage Flow from Ocean Park after Redevelopment

Appendix 10.3   Capacity Performance of Existing Trunk Sewers in 2016 and Proposed Upgrading Works

Appendix 10.4   Estimated Sewage Flow to Aberdeen Preliminary Treatment Works

Appendix 11.1   Location of Ground Investigation undertaken at the Lowland

Appendix 11.2   Map Showing the Recorded Heritage Resources in Wong Chuk Hang San Wai and Nam Long Shan Road

Appendix 11.3   Built Heritage Catalogue

Appendix 11.4   Built Heritage Plates

 

Volume IV – Appendices

 

Appendix 12.1   Detailed QRA Assessment for Explosives Related Activities